PERHITUNGAN KELILING BIDANG TANAH

BID 1 BID 2 BID 3 BID 4 BID 5 BID 6 BID 7 BID 8


15.11 2.87 6.26 2.42 6.31 1.13 23.11 15.77
4.24 55.02 7.66 22.14 15.49 12.42 12.93 8.18
24.76 56.72 25.27 12.62 8.11 8.88 23.58
12.73 8.34 8.34 4.29
17.01 6.52 4.81 16.76
3.75 8.8 8.52 18.56
14.76 6.11 7.58 2.9
12.29 11.36 13.53 2.9
6.11 8.8
13.38 13.38
28.83 39.91
27.5 3.13
9.13

104.65 114.61 39.19 24.56 160.5 129.66 44.92 92.94


711.03
PERHITUNGAN PEKERJAAN PONDASI
TENAGA KERJA/METER JUMLAH KOEF HARGA SATUAN JUMLAH
PEKERJA 1.12155 Rp 100,000 Rp 112,155
TUKANG 0.26745 Rp 150,000 Rp 40,118
KEPALA TUKANG 0.026745 Rp 170,000 Rp 4,547
MANDOR 0.05341 Rp 170,000 Rp 9,080
TOTAL UPAH TENAGA KERJA/METER Rp 165,899

BAHAN MATERIAL/METER JUMLAH KOEF HARGA SATUAN JUMLAH


PASIR URUG 0.03456 Rp 135,000 Rp 4,666
BATU BELAH/KALI 0.474 Rp 270,000 Rp 127,980
SEMEN PC 51.345 Rp 1,800 Rp 92,421
PASIR PASANG 0.13608 Rp 190,000 Rp 25,855
TOTAL BAHAN MATERIAL/METER Rp 250,922

TOTAL PEKERJAAN PONDASI/ METER Rp 416,821


TOTAL JUMLAH PEKERJAAN PONDASI 711.03 Rp 416,821 Rp 296,371,987
PERHITUNGAN KELILING BIDANG TANAH

BID 1 BID 2 BID 3 BID 4 BID 5 BID 6 BID 7 BID 8


16.71 22.24 6.26 11.87 9.95 1.13 23.11 15.77
16.87 7.89 7.66 21.36 14.35 12.42 12.93 8.18
23.82 19.3 25.27 2.78 9.56 8.11 8.88 23.58
6.16 6.71 25.12 1.42 39.14 8.34 28.65 4.29
9.61 2.87 11.28 22.14 9.29 4.81 6.83 16.76
5.2 55.02 19.78 6.31 8.52 18.56
8.35 56.72 9.59 5.49 7.58 2.9
49.59 9.18 8.62 13.53 2.9
4.24 5.65 8.34 8.8
24.76 31.97 6.52 13.38
12.73 8.8 39.91
17.01 6.11
3.75 11.36
14.76 6.11
12.29 11.11
3.79
22.49
13.38
28.83
27.5
9.13

225.85 170.75 151.76 59.57 266.18 126.53 80.4 92.94


1173.98