MUTUAL CHECK 1

Nama Pekerjaan : NORMALISAI SALURAN AIR KELURAHAN KEPATIHAN


Waktu Pelaksanaan : 30 HARI KALENDER
Kontraktor Pelaksana : CV LUMINTU BERKAH
Konsultan Pengawas : CV UNICON
Tahun Anggaran : 2023

kontrak Pekerjaan Tambah Pekerjaan Kurang CCO


No Uraian Pekerjaan Harga Satuan Jumlah Harga Jumlah Harga Jumlah Harga Jumlah Harga
Volume Sat. PPN (%) Bobot Volume Volume Volume Bobot
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 4 5 6 7 8 9 10 11 10 11 10 11.00 11

I PEKERJAAN PERSIAPAN
I.1 Pengukuran dan Pemasangan Bowplank 1.00 Ls 275,000.00 30,250.00 275,000.00 - - - - 1.00 305,250.00
I.2 Pembongkaran dan Pembersihan 1.00 Ls 260,371.17 28,640.83 260,371.17 - - - - 1.00 289,011.99
I.3 Pasang Papan Nama Pekerjaan 1.00 Unit 350,000.00 38,500.00 350,000.00 - - - - 1.00 388,500.00
I.4 Pembongkaran Beton bertulang 8.10 m3 143,874.09 128,191.81 1,165,380.11 - - - - 8.10 1,293,571.93
I.5 Sewa Direksi Keet/gudang peralatan 1.00 Bln 190,000.00 20,900.00 190,000.00 - - - - 1.00 210,900.00
- - - - -
Alat Pelindung Kerja dan ALAT Pelindung Diri (APD) - - - - -
Topi Pelindung (Safety Helmet) 4.00 Buah 48,600.00 21,384.00 194,400.00 - - - - 4.00 215,784.00
Pelindung Mata (Goggles, Spectacles) 4.00 Buah 24,200.00 10,648.00 96,800.00 - - - - 4.00 107,448.00
Sarung Tangan (Safety Gloves) 4.00 Pasang 9,850.00 4,334.00 39,400.00 - - - - 4.00 43,734.00
Sepatu Keselamatan (Safety Shoes, rubber safety shoes and toe cap 4.00 Pasang 76,300.00 33,572.00 305,200.00 - - - - 4.00 338,772.00
Rompi keselamtan ( safety vest) 4.00 Buah 33,800.00 14,872.00 135,200.00 - - - - 4.00 150,072.00
- - - - -
Rambu - rambu - - - - -
Rambu larangan 1.00 Buah 45,000.00 4,950.00 45,000.00 - - - - 1.00 49,950.00
Rambu peringatan 1.00 Buah 45,000.00 4,950.00 45,000.00 - - - - 1.00 49,950.00
341,192.64 3,101,751.28 - - 3,442,943.92

II PEKERJAAN LAIN LAIN


II.1 Galian Tanah Biasa 52.70 m3 79,375.35 460,138.90 4,183,080.95 22.50 1,982,399.37 (22.50) (1,982,399.37) 75.20 6,625,619.22
II.2 Pembuangan tanah 52.70 m3 34,800.78 201,740.12 1,834,001.11 22.50 869,149.48 (22.50) (869,149.48) 75.20 2,904,890.71
II.3 Pembuatan 1 m3 Beton Mutu f'c=14,5 Mpa (K175) 8.10 m3 1,528,754.19 1,362,119.98 12,382,908.94 (0.83) (1,409,798.77) 0.83 1,409,798.77 7.27 12,335,230.15
II.4 Pembesian dengan besi polos 643.72 kg 16,384.19 1,160,151.39 10,546,830.82 (79.30) (1,442,217.04) 79.30 1,442,217.04 564.42 10,264,765.17
II.5 Pemasangan bekisting 1.62 m2 431,939.96 76,971.70 699,742.74 - - - - 1.62 776,714.44
II.6 Ongkos Pasang Begisting 6.48 m2 90,280.48 64,351.93 585,017.51 - - - - 6.48 649,369.44
3,325,474.03 30,231,582.06 2,851,548.85 2,852,015.80 33,556,589.12
JUMLAH TOTAL 3,666,666.67 33,333,333.33 2,851,548.85 2,852,015.80 36,999,533.04
JUMLAH TOTAL + PPN (DI BULATKAN) 37,000,000.00 37,000,000.00