DEFECT
NO ITEM PEKERJAAN KETERANGAN LAPANGAN
BEFORE AFTER
Project
Owner : BVR GROUP ASIA
Subject : BCC JAKARTA Lansekap
Tahap
Date/ Revision : 2023-09-15
NEW LANDSCAPE
KEMAJUAN PEKERJAAN (%)
No Uraian Pekerjaan NOTE Sat Qty Bobot MINGGU INI S/D MINGGU INI Ket
PRESTASI BOBOT PRESTASI BOBOT
4 PEMBUATAN POS TEMPAT SAMPAH (back area) dinding , finish semen plester polish (epoxy mowilex) M2 27,00 1,077% 80% 0,862%
pintu 3 double swing + 2 pintu single , paint finish unit 5,00 2,393%
Atap Pos Tempat sampah m2 26,00 3,319% 80% 2,655%
5 PEMBUATAN POS GAS (TRALIS) dinding bata finish semen plester polish 1,5 m , M2 10,35 0,436% 100% 0,436%
tralis galvanis h: 2 m , black powder coat M2 14,00 1,340% 100% 1,340%
pintu tralis black powder coat M2 1,76 0,168% 100% 0,168%
Palette flooring M2 30,90 1,381% 100% 1,381%
atap pos gas m2 30,90 1,479% 100% 1,479%
6 FRENCH DRAIN AREA PICKLE BALL FINISH perapihan finishing french drain , grill gutter antikarat m2 14,40 0,919% 50% 0,460%
gravel , geotextile fabric, perapihan grill gutter
7 GUTTER TAMBAHAN AREA SCREEDING LANDSCAPE m2 3,60 0,287%
antikarat
GUTTER TAMBAHAN AREA NEIGHBOOR SAMPING( dekat pos
8 grill gutter metal anti karat m2 4,80 0,460% 100% 0,460%
satpam -front landscape)