Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PEMBANGUNAN SALURAN BARU UDITCH

NO ITEM PEKERJAAN SATUAN VOLUME HARGA SATUAN

1 PEKERJAAN PERSIAPAN
A. pembersihan Lahan ls 1.00 5,000,000
B. mobilisasi demobilisasi ls 1.00 4,000,000

2 PEKERJAAN GALIAN
A. galian tanah m3 144.00 150,000
B. lantai kerja dudukan U Ditch m3 14.40 1,500,000
C. Timbunan Tanah kembali m3 72.00 120,000

3 PEKERJAAN UDITCH
A. U Ditch 300x300 + tutup m 36.00 576,000
A. U Ditch 400x400 + tutup m 30.00 726,000
A. U Ditch 500x500 + tutup m 30.00 1,140,000

4 BAK KONTROL
A. BAK KONTROL 100 x 100 TITIK 11.00 3,500,000
B. TUTUP BAK KONTROL TITIK 11.00 1,500,000
TOTAL HARGA

5,000,000
4,000,000

21,600,000
21,600,000
8,640,000

20,736,000
21,780,000
34,200,000

38,500,000
16,500,000

192,556,000