Anda di halaman 1dari 3

A.

PEKERJAAN ONE TIME EXPENSE VOL SAT HARGA SATUAN HARGA TOTAL
1 mobilisasi dan demobilisasi material 1,0 ls 3.500.000,00 3.500.000
2 pembuangan puing kerja 1,0 ls 450.000,00 450.000
3 sewa scafolding 20,0 set 450.000,00 9.000.000
4 sewa catwalk scafolding 20,0 bh 75.000,00 1.500.000
5 relokasi barang 1,0 ls 5.500.000,00 5.500.000
6 bongkar paving block 100,0 m2 30.000,00 3.000.000
7 bongkar aerodinamis + giant banner 1,0 ls 800.000,00 800.000
8 bongkar dan pasang pintu 1,0 ls 1.500.000,00 1.500.000
9 pembongkaran acp 21,0 m' 40.000,00 840.000
SUB TOTAL ONE TIME EXPENSE 26.090.000
B. PEKERJAAN CEILING + ELEKTRIKAL VOL. SAT HARGA SATUAN HARGA TOTAL
1 Finishing ceilling: Cat mowilex 684,0 m² 55.000,00 37.620.000
2 Kap downlight 5 inch + fitting extention lampu + bohlam Philips LED 18 watt putih 180,0 Ttk 55.000,00 9.900.000
SUB TOTAL PEKERJAAN CEILING DAN ELEKTRIKAL 47.520.000
C. PEKERJAAN RENOVASI VOL. SAT HARGA SATUAN HARGA TOTAL
R. Counter
b. Perbaikan Area Showroom 1 unit
1 Perbaikan dan Upgrade Backdrop Counter 1,0 unit 7.500.000,00 7.500.000
2 Perbaikan Bocor dan Plapon Display, Showroo, R.SA, Admin Service, MPR, R. Kabeng 19,6 m2 800.000,00 15.680.000
3 Led strip philips 15,0 bh 36.000,00 540.000
4 Kabel Supreme 100 meter 0,2 rol 1.500.000,00 240.000
5 saklar 2,0 bh 45.000,00 90.000
6 Partisi Gipsum 14,9 m2 380.000,00 5.643.000
c. Pintu rangka UPVC ruang Nego 1 unit
c. Backdrop musholla
1 Signage Musholla 1,0 ls 1.500.000,00 1.500.000
d. Penggantian Pintu Ruang Musholla 1 unit
1 Ganti Pintu dari Alma ke rangka upvc 1,0 m2 1.700.000,00 1.700.000
R. Toilet Customer
a. instalasi Westafel
1 Plywood finishing HPL ukr 2000 x 600 x 600 2,0 m' 2.700.000,00 5.400.000
2 top table granit 2,0 m' 1.600.000,00 3.200.000
3 kaca cermin bulat D.80cm 1,0 bh 1.200.000,00 1.200.000
4 kran air minimalis sensor 1,0 bh 1.500.000,00 1.500.000
5 istalasi air bersih 5,0 ttk 270.000,00 1.350.000
6 instalasi air kotor 5,0 ttk 180.000,00 900.000
7 Kramik dinding Homogeneouse Tile tipe 5 HY-5 5,4 m2 310.000,00 1.674.000
8 lampu led philips 3,0 m 36.000,00 108.000
9 Stop kontak 5,0 bh 45.000,00 225.000
b. instalasi toilet
1 Pergantian Pintu Toliet dan Jaditor 3,0 bh 2.800.000,00 8.400.000
2 Uriniour 1,0 bh 1.800.000,00 1.800.000
3 Kloset Duduk 2,0 bh 1.900.000,00 3.800.000
4 bongkar lantai wc 9,0 m2 450.000,00 4.050.000
5 bongkar closet jongok lama 2,0 bh 150.000,00 300.000
6 pemasangan lantai kramik 40x40 cm 9,0 m2 310.000,00 2.790.000
7 pemasangan floor drain lantai 4,0 ttk 150.000,00 600.000
8 pemasangan selang siram kloset 2,0 ttk 50.000,00 100.000
9 pemasangan kramik dinding 40x60 35,0 m2 310.000,00 10.850.000
PEKERJAAN LANTAI
1 pek pemasangan paving block 100,0 m2 100.000,00 10.000.000
2 perapian Ram Depan Showroom 40,0 m2 150.000,00 6.000.000
PEK AREA BENGKEL
1 pengikisan permukaan cat bengkel 1508,5 m2 25.000,00 37.712.500
2 plamir dinding 1508,5 m2 30.000,00 45.255.000
3 Pengecatan dinding bengkel 1508,5 m2 50.000,00 75.425.000
4 perbaikan talang Air Bengkel 84,0 m' 60.000,00 5.040.000
5 pengikisan permukaan cat rangka baja 378,0 m2 35.000,00 13.230.000
6 pengecatan meni besi 378,0 m2 25.000,00 9.450.000
PENGECATAN LUAR DAN DALAM GEDUNG SHOWROOM
1 pengikisan / pegerokan permukaan cat 276,0 m2 25.000,00 6.900.000
2 plamir dinding 276,0 m2 30.000,00 8.280.000
3 pengecatan pagar 20,0 m' 120.000,00 2.400.000
4 pengecatan railing tangga interior 46,0 m' 120.000,00 5.520.000
5 pengecatan exterior Dinding mowilex 138,2 m2 50.000,00 6.910.000
6 pengecatan interior dinding mowilex 276,0 m2 45.000,00 12.420.000
SUB TOTAL PEKERJAAN RENOVASI 325.682.500
D. PEKERJAAN PERBAIKAN FASADE DEPAN VOL. SAT HARGA SATUAN HARGA TOTAL

1 kanopi stall community atap alderon kombinasi aklirik 10 mm Besi 50x100 72,0 m2 450.000,00 32.400.000
2 Pemasangan Acp Warna Putih Merk Seven plafon stall community 79,0 m2 250.000,00 19.750.000
SUBTOTAL PEKERJAAN PERBAIKAN FASADE DEPAN 52.150.000
REKAP PEKERJAAN RENOVASI GEDUNG ASTRA DAIHATSU PLAJU
A. PEKERJAAN ONE TIME EXPENSE 26.090.000
B. PEKERJAAN CEILING + ELEKTRIKAL 47.520.000
C. PEKERJAAN RENOVASI 325.682.500
D. PEKERJAAN PERBAIKAN FASADE DEPAN 52.150.000
SUB TOTAL REKAP PEKERJAAN RENOVASI GEDUNG ASTRA 451.442.500,00
PAJAK 11% 49.658.675,00
GRAND TOTAL SESUDAH PAJAK 501.101.175,00