RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : REHABILITASI TAHAP 1

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Rompi, helm K3, terpal pengaman kerja 1.00 Ls - 1,250,000.00 1,250,000.00
2 Bongkaran Plafon PVC 18.00 m2 Taksir.11 73,750.00 1,327,500.00
SUB TOTAL I 1,250,000.00
II GEDUNG OGAN
RUANG RAWAT-1
A PEKERJAAN SERVICE DUCTING AD DAN DUCTING MESIN HEPA FILTER
1 Perubahan Tambah titik grill supply 1.00 Bh - 1,500,000.00 1,500,000.00
2 Dop Jalur ducting AC Existing 1.00 Titik - 250,000.00 250,000.00
3 Pemindahan Ducting Ac Return 4.80 m2 - 250,000.00 1,200,000.00
4 Pemasangan Grill Return 4.80 m2 - 1,500,000.00 7,200,000.00
5 Geser Mesin Hefa Filter 1.00 Ls - 1,000,000.00 1,000,000.00
6 Repair ducting mesin Hepa Filter 5.40 m2 - 250,000.00 1,350,000.00
7 Dudukan/gantungan ducting 3.00 Titik - 400,000.00 1,200,000.00
8 PergantianHefa Filter 2.00 bh - 6,000,000.00 12,000,000.00
9 Pergantian Prefilter 2.00 bh - 1,500,000.00 3,000,000.00
10 Pergantian carbon filter 2.00 m2 - 500,000.00 1,000,000.00
11 Pemindahan titik Remote AC 1.00 Titik - 500,000.00 500,000.00
SUB TOTAL A 30,200,000.00
B PEKERJAAN FINISHING
1 Pemasangan Rangka Plafond PVC 18.00 m2 DHSP 4.2.1.21 148,725.50 2,677,059.00
2 Pasang Plafond PVC Existing 18.00 m Taksir.11 73,750.00 1,327,500.00
3 Pasang List Plafond PVC 18.00 m - 45,000.00 810,000.00
4 Pasang Tutup Ventilasi Jendela gibsum 9mm 2.50 m2 - 60,115.00 150,287.50
5 Pengecatan dinding dalam 60.70 m2 DHSP Pek. Lain-lain 11 45,438.25 2,758,101.78
6 Jasa pasang Pintu Aluminium Kaca 1.00 Unit - 1,000,000.00 1,000,000.00
7 Peninggian Elevasi Pintu exiaitng 2.00 bh - 1,000,000.00 2,000,000.00
8 Pekerjaan Vinil Anti Bakteri 19.20 m2 - 850,000.00 16,320,000.00
SUB TOTAL B 27,042,948.28
III GEDUNG SDM
RUANG RAPAT
1 Bongkaran dinding Partisi 1.00 Ls - 750,000.00 750,000.00
2 Pasangan Dinding partisi 2 muka 4.00 m2 - 329,012.05 1,316,048.21
3 Pengecatan dinding 20.00 m2 DHSP Pek. Lain-lain 11 45,438.25 908,765.00
SUB TOTAL 2,974,813.21
IV GEDUNG INSTALASI FARMASI
GUDANG OBAT DAN RUANG ADMINISTRASI
1 Mengerok Cat dinding 20.00 m2 - 25,000.00 500,000.00
2 Pengecatan dinding 20.00 m2 DHSP Pek. Lain-lain 11 45,438.25 908,765.00
SUB TOTAL 1,408,765.00
V GEDUNG RAMBANG
TPO OBAT
1 Mengerok Cat dinding 5.00 m2 - 25,000.00 125,000.00
2 Pengecatan dinding plafond 20.00 m2 DHSP Pek. Lain-lain 11 45,438.25 908,765.00
BAYI TABUNG
3 Bongkaran keramik lantai KM 1.00 Ls - 500,000.00 500,000.00
4 Bongkaran keramik dinding KM 1.00 Ls - 750,000.00 750,000.00
5 Pasangan keramik Lantai KM 20x20 3.00 m2 - 270,627.50 811,882.50
6 Pasangan keramik Dinding KM 20x25 20.00 m2 DHSP Pek. Lain-lain 11 291,542.90 5,830,858.00
7 Pasangan Floor drain 1.00 bh 5.1.1.14 323,262.50 323,262.50
TPO KEMOTERAPI - T.PELAYANAN OBAT
8 Mengerok Cat dinding 20.00 m2 - 25,000.00 500,000.00
9 Cat dinding 43.50 m2 - 45,438.25 1,976,563.88
TITIK BOCOR
10 Perbaikan 3 titik bocor 3.00 Titik - 1,000,000.00 3,000,000.00
SUB TOTAL 14,726,331.88
VI LAKITAN
1 Bongkaran keramik lantai KM 1.00 Ls - 500,000.00 500,000.00
2 Bongkaran keramik dinding KM 1.00 Ls - 750,000.00 750,000.00
3 Pasangan keramik Lantai KM 20x20 3.00 m2 - 270,627.50 811,882.50
4 Pasangan keramik Dinding KM 20x25 20.00 m2 DHSP Pek. Lain-lain 11 291,542.90 5,830,858.00
5 Bongkar pasang klosed duduk existing 1.00 Ls - 500,000.00 500,000.00
6 Pasangan Floor drain 20.00 m2 5.1.1.14 323,262.50 6,465,250.00
SUB TOTAL 14,857,990.50
VII RAMBANG KEMOTERAPI
1 Vinil lantai Lanjutan 45.28 m2 - 850,000.00 38,483,750.00
SUB TOTAL 38,483,750.00
VIII GEDUNG LAKITAN 1.3
GEDUNG D
1 Pembersihan dak beton 1.00 Ls - 500,000.00 500,000.00
2 Bongkaran keramik dinding KM 1.00 Ls - 750,000.00 750,000.00
3 Pasangan keramik Lantai KM 20x20 3.00 m2 DHSP Pek. Lain-lain 11 291,542.90 874,628.70
4 Pasangan keramik Dinding KM 20x25 20.00 m2 5.1.1.14 323,262.50 6,465,250.00
SUB TOTAL 8,589,878.70
IX KELINGI 1.2
LANTAI 1
1 Pasang partisi dan P2 Aluminium + Kaca 1.00 Unit - 13,500,000.00 13,500,000.00
2 Pasangan Door Closer pintu existing 4.00 bh 4.6.2.4 285,895.50 1,143,582.00
3 Bongkar tralis Jendela (1 unit) + pembuatan dudukan jemur 1.00 Ls - 1,000,000.00 1,000,000.00
LANTAI 2
4 Pengecatan kusen kayu dengan cat minyak 309.20 m2 4.7.1.5 66,544.50 20,575,399.69
SUB TOTAL 36,218,981.69
X WISMA RSMH
LANTAI 2
1 Bongkar Keramik Lantai 2.00 m2 - 500,000.00 1,000,000.00
2 Water Profing lantai 2.00 m2 - 250,000.00 500,000.00
LANTAI 3
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
1 Bongkar Keramik Lantai 2.00 m2 - 500,000.00 1,000,000.00
2 Water Profing lantai 2.00 m2 - 250,000.00 500,000.00
3 Perbaikan Pipa pvc 4 inci bocor 4.00 m 5.1.1.32 165,852.50 663,410.00
LANTAI 1
1 Bongkar plafond bocor 4.00 m2 - 15,000.00 60,000.00
2 Pasang Plafond ex bocor 4.00 m2 4.5.1.7 60,115.00 240,460.00
3 Pengecatan plafond 10.00 m2 4.7.1.10 29,202.25 292,022.50
SUB TOTAL 4,255,892.50
XI PEKERJAAN AKHIR
1 Testing dan comisioning 1.00 Ls - 4,500,000.00 4,500,000.00
2 Pekerjaan Finishing dan pembersihan akhir 1.00 Ls - 1,000,000.00 1,000,000.00
SUB TOTAL IV 5,500,000.00
TOTAL 185,509,351.76
PPN 11% 20,406,028.69
TOTAL+PPN11% 205,915,380.45
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : REHABILITASI RUANG OK

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 5,000,000.00 5,000,000.00
2 Pembersihan Lokasi dan Pergeseran Perabot 1.00 Ls - 1,500,000.00 1,500,000.00
SUB TOTAL I 5,000,000.00
II RUANG POLIKLINIK DIAGNOSTIK THT
A PEKERJAAN SCREDD LANTAI
1 Pembersihan permukaan Beton 787.68 m2 2.2.1.9 23,375.00 18,412,020.00
2 Lapis Sika Permukaan Lantai 787.68 m2 16 118,360.00 93,229,804.80
3 Screed Lantai 1:4 787.68 m2 - 250,000.00 196,920,000.00
4 Acian lantai 787.68 m2 4.4.2.27 51,007.00 40,177,193.76
5 Waterprofing lantai 787.68 m2 - 350,000.00 275,688,000.00
SUB TOTAL II 624,427,018.56
B PEKERJAAN VINIL LANTAI
1 Bongkaran vinil lantai (anti bakteri) 313.00 m2 - 45,000.00 14,085,000.00
2 Pasangan Finil lantai anti bakteri 313.00 m2 60 658,548.00 206,125,524.00
SUB TOTAL III 220,210,524.00
IV PEKERJAAN AKHIR
1 Pembersihan akhir 1.00 Ls - 1,000,000.00 1,000,000.00
SUB TOTAL IV 1,000,000.00
TOTAL 850,637,542.56
PPN 11% 93,570,129.68
TOTAL+PPN11% 944,207,672.24
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : REHABILITASI RUANG OK DAN ENDOSSCOPY

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 5,000,000.00 5,000,000.00
2 Pembersihan Lokasi dan Pergeseran Perabot 1.00 Ls - 1,500,000.00 1,500,000.00
SUB TOTAL I 5,000,000.00
II RUANG POLIKLINIK DIAGNOSTIK THT
A PEKERJAAN SCREDD LANTAI
1 Pekerjaan dinding pengaman dari triplek 1.00 Ls - 1,500,000.00 1,500,000.00
2 Pembersihan permukaan Beton 87.68 m2 2.2.1.9 23,375.00 2,049,520.00
3 Ciping permukaan beton existing 87.68 m2 - 55,000.00 4,822,400.00
4 Lapis Sika Permukaan Lantai 87.68 m2 16 118,360.00 10,377,804.80
5 Screed Lantai 1:4 87.68 m2 - 250,000.00 21,920,000.00
6 Acian lantai 87.68 m2 4.4.2.27 51,007.00 4,472,293.76
7 Waterprofing lantai 87.68 m2 - 350,000.00 30,688,000.00
SUB TOTAL II 75,830,018.56
III RUANG ENDOSCOPY
A PEKERJAAN VINIL LANTAI
1 Bongkaran vinil lantai (anti bakteri) 117.06 m2 - 55,000.00 6,438,080.00
2 Pekerjaan Nat Ulang Keramik existing 117.06 m2 - 95,000.00 11,120,320.00
3 Pasangan Finil lantai anti bakteri 117.06 m2 60 658,548.00 77,086,994.69
SUB TOTAL III 94,645,394.69
IV PEKERJAAN AKHIR
1 Pembersihan akhir 1.00 Ls - 1,500,000.00 1,500,000.00
SUB TOTAL IV 1,500,000.00
TOTAL 176,975,413.25
PPN 11% 19,467,295.46
TOTAL+PPN11% 196,442,708.71
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : MAINTENANCE GEDUNG OK , GEDUNG KELINGI DAN GEDUNG PERALATAN

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 2,000,000.00 2,000,000.00
2 Biaya langsir Bahan material dan bahan Bongkaran 1.00 Ls - 3,500,000.00 3,500,000.00
3 Terpal Sekat pengaman 1.00 Ls - 1,750,000.00 1,750,000.00
SUB TOTAL I 7,250,000.00
II RUANG OKA LANTAI 2
PEKERJAAN KAMAR 20.01
1 Cuci + Bongkaran vinil lantai (anti bakteri) 49.14 m2 - 75,000.00 3,685,500.00
2 Pekerjaan Nat Ulang Keramik existing 49.14 m2 - 95,000.00 4,668,300.00
3 Pasangan Vinil lantai Khusus (anti bakteri) 49.14 m2 - 1,317,096.00 64,722,097.44
PEKERJAAN KAMAR 20.04
1 Cuci + Bongkaran vinil lantai (anti bakteri) 33.99 m2 - 75,000.00 2,549,250.00
2 Pekerjaan Nat Ulang Keramik existing 33.99 m2 - 95,000.00 3,229,050.00
3 Pasangan Vinil lantai Khusus (anti bakteri) 33.99 m2 - 1,317,096.00 44,768,093.04
SUB TOTAL II 123,622,290.48
III GEDUNG KELINGI LANTAI 1
REHAB RUANG SPOELHOEK
1 Bongkaran Keramik Lantai kamar mandi dan beton selasar jalur pipa 1.00 Ls - 1,000,000.00 1,000,000.00
Taksir
2 Bongkaran Spoelhoex Existing 1.00 Unit Sarana 592,350.00 592,350.00
1190
3 Pengadaan karung Untuk material bongkaran 20.00 bh - 10,000.00 200,000.00
4 Galian Tanah Pipa PVC 4 dan 2 Inci 0.96 m3 2.3.1.1 104,087.50 99,924.00
5 Urugan kembali galian tanah galian pipa 0.32 m3 2.3.1.9 76,175.00 24,376.00
6 Pekerjaan penanaman Pipa PVC 4 Inci Spoelhoek dalam tanah 16.00 m2 5.1.1.32 165,852.50 2,653,640.00
7 Pekerjaan Penanaman Pipa PVC 2 Inci Floor drain dalam tanah 16.00 m2 5.1.1.29 62,508.19 1,000,131.00
8 Pekerjaan bobok jalur pipa ke Dinding beton bak Kontrol (pipa 4Inci) 1.00 Ls - 135,000.00 135,000.00
9 Pergantian Floor drain stainlees baru 1.00 bh 5.1.1.23 339,624.57 339,624.57
10 Pekerjaan Rolagh bata Pasangan 1 batu ad 1:2 0.28 0.3 4.4.1.1 272,481.00 76,294.68
11 Pekerjaan Keramik Lantai 20x20 1.96 m 4.4.3.36 290,882.90 570,130.48
Taksir
12 Pasang Ulang Spoelhoex Existing 1.00 Unit Sarana 592,350.00 592,350.00
1190
13 Cor Ulang Beton selasar ex bobokan tanam pipa PVC 4 dan 2 Inci 0.20 m3 4.1.1.5 1,298,203.50 259,640.70
SUB TOTAL III 7,543,461.43
IV GEDUNG PERLENGKAPAN (SAMPING KANTOR POS SATPAM TENGAH)
REHAB KAMAR MANDI DEPAN
1 Bongkaran Keramik Lantai kamar mandi 0.30 m3 - 1,895,619.00 568,685.70
2 Pengadaan karung Untuk material bongkaran 50.00 bh - 10,000.00 500,000.00
3 Pemasangan keramik lantai KM 30x30 unpolish 6.00 m2 4.4.3.35 349,112.50 2,094,675.00
4 Pergantian Floor drain stainlees baru 1.00 bh 5.1.1.14 323,262.50 323,262.50
5 Perbaikan Pipa PVC 2 Inci Floor drain 2.00 m 5.1.1.29 62,508.19 125,016.38
6 MengeroK cat dinding lama dan cat dak expose lama 18.50 m2 - 25,000.00 462,500.00
7 Pengecatan Dinding dan dak expose 18.50 m2 - 45,438.25 840,607.63
SUB TOTAL IV 4,914,747.20
V PEKERJAAN AKHIR
1 Pekerjaan Finishing dan pembersihan akhir 1.00 Ls - 1,500,000.00 1,500,000.00
SUB TOTAL IV 1,500,000.00
TOTAL 144,830,499.11
PPN 11% 15,931,354.90
TOTAL+PPN11% 160,761,854.01
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : REHABILITASI TAHAP 2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 750,000.00 750,000.00
2 Biaya langsir Bahan material dan bahan Bongkaran 1.00 Ls - 750,000.00 750,000.00
SUB TOTAL I 1,500,000.00
II RAMBANG KEMOTRAPI
1 Pasangan Vinil lantai Khusus (anti bakteri) 207.96 m2 - 850,000.00 176,768,125.00
SUB TOTAL II 176,768,125.00
TOTAL 178,268,125.00
PPN 11% 19,609,493.75
TOTAL+PPN11% 197,877,618.75
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : REHABILITASI TAHAP 3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 750,000.00 750,000.00
2 Biaya langsir Bahan material dan bahan Bongkaran 1.00 Ls - 750,000.00 750,000.00
SUB TOTAL I 1,500,000.00
II LAKITAN 1.3 GEDUNG D
1 Pembersihan dak beton permukaan Lantai 6.00 m2 - 23,375.00 140,250.00
2 Pekerjaan Bobokan 1.00 Ls - 1,000,000.00 1,000,000.00
2 Pekerjaan Acian dak lantai 6.00 m2 4.4.2.27 51,007.00 306,042.00
3 Waterprofing sika beton dak lantai 6.00 m2 - 350,000.00 2,100,000.00
4 Penggantian pipa PVC 1 Inci 4.00 m 5.1.1.27 33,671.00 134,684.00
5 Penggantian pipa PVC 4 Inci 12.00 m 5.1.1.32 165,852.50 1,990,230.00
6 Pemasangan Klem Pipa PVC 4 Inci 1.00 Ls - 500,000.00 500,000.00
SUB TOTAL II 6,171,206.00
III RAMBANG 1.2 LANTAI 2
1 Bongkaran keramik lantai KM 1.00 Ls - 500,000.00 500,000.00
2 Bongkaran dinding partisi kitchen zink 1.00 Ls - 250,000.00 250,000.00
3 Pekerjaan Pipa PVC 2 inci 4.00 m 5.1.1.29 62,508.19 250,032.75
4 Pekerjaan Keramik lantai 20x20 2.00 m2 4.4.3.36 290,882.90 581,765.80
5 Pergantian floor drain stainless 1.00 bh 5.1.1.14 323,262.50 323,262.50
6 Slang flexibel 1 inci buangan kitchen zink 2.00 m 5.1.1.29 62,508.19 125,016.38
7 Pasangan partisi gibsum dibelakang kitchen zink (tanpa rangka) 2.88 m2 4.4.3.36 29,202.25 84,102.48
8 Pengecatan dinding 5.61 m2 DHSP Pek. L 45,438.25 254,908.58
SUB TOTAL III 2,369,088.49
IV GEDUNG KELINGI
LANTAI 1
REHAB RUANG SPOELHOEK
1 Bongkaran Keramik Lantai kamar mandi dan beton selasar jalur pipa 1.00 Ls - 1,000,000.00 1,000,000.00
Taksir
2 Bongkaran Spoelhoex Existing 1.00 Unit Sarana 592,350.00 592,350.00
1190
3 Pengadaan karung Untuk material bongkaran 20.00 bh - 10,000.00 200,000.00
4 Galian Tanah Pipa PVC 4 dan 2 Inci 0.96 m3 2.3.1.1 104,087.50 99,924.00
5 Urugan kembali galian tanah galian pipa 0.32 m3 2.3.1.9 76,175.00 24,376.00
6 Pekerjaan penanaman Pipa PVC 4 Inci Spoelhoek dalam tanah 16.00 m2 5.1.1.32 165,852.50 2,653,640.00
7 Pekerjaan Penanaman Pipa PVC 2 Inci Floor drain dalam tanah 16.00 m2 5.1.1.29 62,508.19 1,000,131.00
8 Pekerjaan bobok jalur pipa ke Dinding beton bak Kontrol (pipa 4Inci) 1.00 Ls - 135,000.00 135,000.00
9 Pergantian Floor drain stainlees baru 1.00 bh 5.1.1.23 339,624.57 339,624.57
10 Pekerjaan Rolagh bata Pasangan 1 batu ad 1:2 0.28 0.3 4.4.1.1 272,481.00 76,294.68
11 Pekerjaan Keramik Lantai 20x20 1.96 m 4.4.3.36
Taksir 290,882.90 570,130.48
12 Pasang Ulang Spoelhoex Existing 1.00 Unit Sarana 592,350.00 592,350.00
13 Cor Ulang Beton selasar ex bobokan tanam pipa PVC 4 dan 2 Inci 0.20 m3 1190
4.1.1.5 1,298,203.50 259,640.70
KANOPI
14 Bongkar Atap dan rangka kanopi lama + buang 1.00 Ls - 3,000,000.00 3,000,000.00
15 Pasang Rangka Atap Kanopi Zink Alum 37.26 m2 - 297,895.13 11,099,572.36
16 Pasang Rangka Atap Kanopi Polycarbonat 37.26 m2 - 500,000.00 18,630,000.00
17 Pengecatan Tiang Besi 3.00 m2 - 45,743.50 137,230.50
KAMAR MANDI KAMAR 2
18 Perbaikan Kuci Pintu Km kamar 2 1.00 Ls - 500,000.00 500,000.00
KAMAR MANDI PERAWAT
19 Bongkar Klosed existing 1.00 Ls - 500,000.00 500,000.00
20 Pasang Klosed Duduk 1.00 unit - 3,655,201.00 3,655,201.00
LANTAI 2
KAMAR MANDI UMUM PASIEN
1 Bongkaran Pintu KM 1.00 Ls - 750,000.00 750,000.00
1 Pergantian Pintu KM PVC 3.00 bh - 938,591.50 2,815,774.50
2 Pasangan kusen Aluminium KM 14.70 m 4.2.1.11 199,596.10 2,934,062.67
PANTRI
1 Bongkar pintu Pantri existing 1.00 Ls - 500,000.00 500,000.00
2 Pasang Pintu Aluminium + Kaca 8mm 1.00 unit - 4,342,200.64 4,342,200.64
KAMAR MANDI PETUGAS
1 Bongkaran Pintu KM 2.00 Ls - 500,000.00 1,000,000.00
2 Pergantian Pintu KM PVC 2.00 bh - 938,591.50 1,877,183.00
3 Pasangan kusen Aluminium KM 9.80 m 4.2.1.11 199,596.10 1,956,041.78
SUB TOTAL IV 61,240,727.88
V GEDUNG PERLENGKAPAN (SAMPING KANTOR POS SATPAM TENGAH)
REHAB KAMAR MANDI DEPAN
1 Bongkaran Keramik Lantai kamar mandi 0.30 m3 - 1,895,619.00 568,685.70
2 Pengadaan karung Untuk material bongkaran 50.00 bh - 10,000.00 500,000.00
3 Pemasangan keramik lantai KM 30x30 unpolish 6.00 m2 4.4.3.35 349,112.50 2,094,675.00
4 Pergantian Floor drain stainlees baru 1.00 bh 5.1.1.14 323,262.50 323,262.50
5 Perbaikan Pipa PVC 2 Inci Floor drain 2.00 m 5.1.1.29 62,508.19 125,016.38
6 MengeroK cat dinding lama dan cat dak expose lama 18.50 m2 - 25,000.00 462,500.00
7 Pengecatan Dinding dan dak expose 18.50 m2 - 45,438.25 840,607.63
SUB TOTAL V 4,914,747.20
VI RUANG GRAHA LAMA LANTAI 2
PEKERJAAN VINIL RUANG ENDOSCOPY
1 Pekerjaan Nat Ulang Keramik existing 117.06 m2 - 50,000.00 5,852,800.00
2 Pasangan Vinil lantai Khusus (anti bakteri) 117.06 m2 - 850,000.00 99,497,600.00
SUB TOTAL II 105,350,400.00
VII PEKERJAAN AKHIR
1 Pekerjaan Finishing dan pembersihan akhir 1.00 Ls - 2,000,000.00 2,000,000.00
SUB TOTAL VI 2,000,000.00
TOTAL 183,546,169.56
PPN 11% 20,190,078.65
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
TOTAL+PPN11% 203,736,248.22
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : REHABILITASI RUANG I B S

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME ANALISA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pekerjaan SMKK3 dan K3 1.00 Ls - 5,000,000.00 5,000,000.00
2 Biaya langsir Bahan material dan bahan Bongkaran 1.00 Ls - 3,500,000.00 3,500,000.00
SUB TOTAL I 8,500,000.00
II SELASAR LANTAI 2 GEDUNG I B S
II.1 PEKERJAAN KUSEN DAN WASTAFEL
II.1.1 KUSEN DAN PINTU ALUMINIUM
1 Pekerjaan Kusen Aluminium Pintu geser Ruang Pantri Uk 212x99 1.00 Set - 10,500,000.00 10,500,000.00
2 Pekerjaan Kusen Aluminium Pintu Swing Selasar ke wastafel Uk 270x73 1.00 Set - 13,500,000.00 13,500,000.00
Pekerjaan Kusen Aluminium Tutup akses pintu lama disebelah wastafel Uk
3 1.00 Set - 8,950,000.00 8,950,000.00
250x82
II.1.2 WASTAFEL DINDING TEMPAT CUCI PIRING
1 Pemasangan wastafel dinding 1.00 unit Pek.Lain 87 2,927,826.00 2,927,826.00
2 Pemasangan Kran wastafel dinding 1.00 unit Pek.Lain 105 385,233.75 385,233.75
3 Pekerjaan Pipa 1 Inci 4.00 m1 5.1.1.27 33,671.00 134,684.00
4 Pekerjaan Pipa 1/2 Inci outbow 8.00 m2 5.1.1.25 25,669.88 205,359.00
II.1.3 EXHAUSTFAN PLAFOND RUANG MAKAN
II.1.3.1 BONGKARAN
1 Sewa Scafolding 4.00 Set - 250,000.00 1,000,000.00
2 Bongkaran Plafond Gibsum 12.00 m2 Pek.lain 21 11,275.00 135,300.00
3 Pengadaan karung Untuk material bongkaran 50.00 bh - 10,000.00 500,000.00
II.1.3.2 DUCTING EXHAUSTFAN PLAFOND
4 Support/Gantungan Ducting 1.00 Ls - 1,500,000.00 1,500,000.00
5 Pemasangan flexible ducting exhaustfan 7.00 m1 - 250,000.00 1,750,000.00

6 Bobok dinding + Pemasangan Grill exhaustfan dinding ukuran 25" x 10" 1.00 Unit - 1,500,000.00 1,500,000.00

7 Pemasangan Rangka Plafond hollo 4x4 ex bongkaran flexible exhaust 12.00 m2 4.2.1.21 148,725.50 1,784,706.00
8 Pemasangan Exhaustfan Plafond 12 Inci 1.00 Unit 4.2.1.22 693,000.00 693,000.00
II.1.3.3 INSTALASI SAKLAR EXHAUSTFAN
9 Pemasangan Instalasi Saklar exhaustfan 1.00 Titik Taksir 2 314,366.25 314,366.25
10 Pemasangan Saklar Exhaustfan Plafond 1.00 bh Taksir 6 57,097.70 57,097.70
11 Pemasangan Gibsum 9mm ex bongkaran flexible exhaust 6.00 m2 4.5.1.7 60,115.00 360,690.00
12 Pengecatan Plafond Gibsum 6.00 m2 4.7.1.10 29,202.25 175,213.50
13 Pengecatan Dinding 50.00 m2 Pek.lain 11 45,438.25 2,271,912.50
II.1.4 LEMARI GANTUNG 60X60X40CM
Pengadaan dan Pemasangan Interior lemari gantung peralatan makan P=60
1 1.00 Set - 2,500,000.00 2,500,000.00
L=60 T=40 Triplek Lapis HPL
SUB TOTAL II 51,145,388.70
III RUANG CHILLER LANTAI 3 GEDUNG IBS
III.1 PEKERJAAN LANTAI
1 Pekerjaan dinding pengaman dari triplek 1.00 Ls - 1,500,000.00 1,500,000.00
2 Pembersihan permukaan Beton 75.92 m2 - 23,375.00 1,774,513.13
3 Ciping permukaan beton existing 75.92 m2 - 55,000.00 4,175,325.00
4 Lapis Sika Permukaan Lantai 2 kali 75.92 m2 - 236,720.00 17,970,598.80
5 Acian lantai 75.92 m2 4.4.2.27 51,007.00 3,872,196.41
6 Waterprofing lantai 75.92 m2 - 350,000.00 26,570,250.00
III.2 BOCOR HVAC DAN DUCTING EXISTING
1 Support / Gantungan Ducting 1.00 Ls - 3,000,000.00 3,000,000.00
Pekerjaan Bungkus pipa dan Ducting AC dan Return existing dengan Ducting
2 99.00 m2 - 650,000.00 64,350,000.00
bahan Polyisocyanurate Foam
3 Pekerjaan Pipa PVC drain 1 inci buangan dari ducting talang 36.00 m1 5.1.1.27 33,671.00 1,212,156.00
SUB TOTAL II 124,425,039.33
VI PEKERJAAN AKHIR
1 Pekerjaan Finishing dan pembersihan akhir 1.00 Ls - 1,500,000.00 1,500,000.00
SUB TOTAL VI 1,500,000.00
TOTAL 185,570,428.03
PPN 11% 20,412,747.08
TOTAL+PPN11% 205,983,175.11
PEKERJAAN VINIL
GRAHA LANTAI 2 RUANG DIAGNOSTIK DAN TINDAKAN PENYAKIT DALAM
1 RUANG ENDOSCOPY 1 Luas 37.465 m2
36.23

2 RUANG ENDOSCOPY 2 Luas 37.465 m2


36.17

3 RUANG FLuorosCopy/ Rontgen Luas 42.126 m2


rontgen 39.18

TOTAL 189.456 M2
4 Ruang 1

Luas 17.015 m2

4 Ruang 2

Luas 13.53 m2

5 Ruang Bronnscopy 1

Luas 25.7964 m2

6 Ruang Bronnscopy 2

Luas 25.7964 m2
7 Ruang Tindakan Paru

Luas 20.1875 m2

TOTAL LUAS VINIL 520.4173 M2


RUANG OKA

1 KAMAR 20.01
Luas 49.14 m2

2 KAMAR 20.04
Luas 33.99 m2

3 SELASAR
Luas 235 m2

TOTAL LUAS VINIL 83.13 M2


RAMBANG KEMOTRAPI

57.4175
30.035
87.96
3
30.225
24.85

TOTAL LUAS VINIL 233.4875


RAMBANG KEMOTRAPI

57.4175
30.035
87.96
3
28.815
24.85
17.425
3.735

TOTAL LUAS VINIL 253.2375


kemo anak 119.9
ruang depan kemo 22.4
rkemo wanita 82.5
TOTAL 224.8

207.9625
45.275
Taksir. 1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.1
JENIS PEKERJAAN : Pemasangan Titik Nyala Stop Kontak
SATUAN PEMBAYARAN : Ttk
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1350 150,000 20,250.00
3 Kepala Tukang L.03 0.0135 175,000 2,362.50
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 23,537.50
B. BAHAN
1 Kabel NYM 3 x 2,5 mm2 M' 15.00 15,000 225,000.00
2 Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750 33,000.00
3 T-Dus PVC HI "EGA" Dia. 20mm Bh 1 4,250 4,250.00
JUMLAH HARGA BAHAN 262,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 285,787.50
E. OVERHEAD & PROFIT 10,0 % x D 28,578.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 314,366.25

Taksir. 2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.2
JENIS PEKERJAAN : Pemasangan Titik Nyala Saklar
SATUAN PEMBAYARAN : Ttk
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1350 150,000 20,250.00
3 Kepala Tukang L.03 0.0135 175,000 2,362.50
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 23,537.50
B. BAHAN
1 Kabel NYM 3 x 2,5 mm2 M' 15.00 15,000 225,000.00
2 Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750 33,000.00
3 T-Dus PVC HI "EGA" Dia. 20mm Bh 1 4,250 4,250.00
JUMLAH HARGA BAHAN 262,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 285,787.50
E. OVERHEAD & PROFIT 10,0 % x D 28,578.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 314,366.25
Taksir. 3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.3
JENIS PEKERJAAN : Pemasangan Titik Nyala Lampu
SATUAN PEMBAYARAN : Ttk
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1350 150,000 20,250.00
3 Kepala Tukang L.03 0.0135 175,000 2,362.50
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 23,537.50
B. BAHAN
1 Kabel NYM 2 x 2,5 mm2 M' 15.00 13,000 195,000.00
2 Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750 33,000.00
3 T-Dus PVC HI "EGA" Dia. 20mm Bh 1 4,250 4,250.00
JUMLAH HARGA BAHAN 232,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 255,787.50
E. OVERHEAD & PROFIT 10,0 % x D 25,578.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 281,366.25

Taksir.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir .4
JENIS PEKERJAAN : Pemasangan 1 Buah Stop Kontak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1000 150,000 15,000.00
3 Kepala Tukang L.03 0.0100 175,000 1,750.00
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 17,675.00
B. BAHAN
1 Stop Kontak Bh 1.00 26,000 26,000.00
2 Inbow dus Bh 1.00 5,000 5,000.00
3 Semen Portland Kg 0.20 1,160 232.00
JUMLAH HARGA BAHAN 31,232.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 48,907.00
E. OVERHEAD & PROFIT 10,0 % x D 4,890.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 53,797.70
Taksir. 5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir. 5
JENIS PEKERJAAN : Pemasangan 1 Buah Saklar Tunggal
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1000 150,000 15,000.00
3 Kepala Tukang L.03 0.0100 175,000 1,750.00
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 17,675.00
B. BAHAN
1 Saklar Tunggal Bh 1.00 19,000 19,000.00
2 Inbow dus Bh 1.00 5,000 5,000.00
2 Semen Portland Kg 0.20 1,160 232.00
JUMLAH HARGA BAHAN 24,232.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 41,907.00
E. OVERHEAD & PROFIT 10,0 % x D 4,190.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 46,097.70

Taksir.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir.6
JENIS PEKERJAAN : Pemasangan 1 buah saklar ganda
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1000 150,000 15,000.00
3 Kepala Tukang L.03 0.0100 175,000 1,750.00
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 17,675.00
B. BAHAN
1 Saklar Ganda Bh 1.00 29,000 29,000.00
2 Inbow dus Bh 1.00 5,000 5,000.00
3 Semen Portland Kg 0.20 1,160 232.00
JUMLAH HARGA BAHAN 34,232.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 51,907.00
E. OVERHEAD & PROFIT 10,0 % x D 5,190.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,097.70
Taksir.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir.7
JENIS PEKERJAAN : Pemasangan 1 buah exhaust fan
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 0.1000 150,000 15,000.00
3 Kepala Tukang L.03 0.0100 175,000 1,750.00
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 17,675.00
B. BAHAN
1 Exhaust fan Bh 1.00 400,000 400,000.00
JUMLAH HARGA BAHAN 400,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 417,675.00
E. OVERHEAD & PROFIT 10,0 % x D 41,767.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 459,442.50

Taksir.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.8
JENIS PEKERJAAN : Pemasangan 1 buah pintu KM/WC bahan PVC
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.050 120,000 6,000.00
2 Tukang L.02 0.500 150,000 75,000.00
3 Kepala Tukang L.03 0.050 175,000 8,750.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Pintu KM/WC PVC bh 1.000 750,000 750,000.00
2 Sealent tube 0.432 30,000 12,960.00
JUMLAH HARGA BAHAN 762,960.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 853,265.00
E. OVERHEAD & PROFIT 10,0 % x D 85,326.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 938,591.50
Taksir.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.9
JENIS PEKERJAAN : Pemasangan 1 bh pintu aluminium warna lengkap (kusen, kunci engsel setara dekson) - ice glass
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.050 120,000 6,000.00
2 Tukang L.02 0.500 150,000 75,000.00
3 Kepala Tukang L.03 0.050 175,000 8,750.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Pintu aluminium warna lengkap bh 1.000 3,500,000 3,500,000.00
2 Sealent tube 0.432 30,000 12,960.00
JUMLAH HARGA BAHAN 3,512,960.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 3,603,265.00
E. OVERHEAD & PROFIT 10,0 % x D 360,326.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,963,591.50

Taksir.10
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.10
JENIS PEKERJAAN : Pemasangan 1 m2 aluminium composite panel (ACP) + rangka besi hollow galvanis, modul 60 x 60 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.390 120,000 46,800.00
2 Tukang L.02 0.700 150,000 105,000.00
3 Kepala Tukang L.03 0.070 175,000 12,250.00
4 Mandor L.04 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 165,345.00
B. BAHAN
1 Hollow besi galvanis 40.40.4 mm btg 0.800 37,500 30,000.00
2 Aluminium composite panel (ACP) m² 1.100 425,000 467,500.00
3 Braket siku/plat siku alumunium 25.25.3 mm btg 0.267 58,000 15,486.00
4 Paku beton kg 0.080 22,000 1,760.00
5 Paku sekrup kg 0.110 55,000 6,050.00
6 Sealant tube 0.250 30,000 7,500.00
JUMLAH HARGA BAHAN 528,296.00
C. PERALATAN
Peralatan 10% 0.10 528,296.00 52,829.60
JUMLAH HARGA PERALATAN 52,829.60

D. JUMLAH ( A + B + C ) 746,470.60
E. OVERHEAD & PROFIT 10,0 % x D 74,647.06
F. HARGA SATUAN PEKERJAAN ( D + E ) 821,117.66
Taksir.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.11
JENIS PEKERJAAN : Pemasangan 1 m2 plafond PVC
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.150 120,000 18,000.00
2 Tukang L.02 0.250 150,000 37,500.00
3 Kepala Tukang L.03 0.025 175,000 4,375.00
4 Mandor L.04 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 73,750.00
B. BAHAN
1 Plafond PVC m² 1.100 85,000 93,500.00
2 Screw bh 18.000 175 3,150.00
JUMLAH HARGA BAHAN 96,650.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 170,400.00
E. OVERHEAD & PROFIT 10,0 % x D 17,040.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 187,440.00

Taksir.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.12
JENIS PEKERJAAN : Pemasangan 1 m' list plafond PVC
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.050 120,000 6,000.00
2 Tukang L.02 0.050 150,000 7,500.00
3 Kepala Tukang L.03 0.005 175,000 875.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 14,930.00
B. BAHAN
1 List plafond PVC m² 1.050 20,000 21,000.00
2 Screw bh 18.000 175 3,150.00
JUMLAH HARGA BAHAN 24,150.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 39,080.00
E. OVERHEAD & PROFIT 10,0 % x D 3,908.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,988.00
Taksir.13
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.13
JENIS PEKERJAAN : Pemasangan 1 m² atap bitumen bergelombang monolayer 3 mm (uk. 200x95x0,3cm) kemiringan
atap min 15°, jarak rangka gording maksimal 45 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.140 120,000 16,800.00
2 Tukang L.02 0.070 150,000 10,500.00
3 Kepala Tukang L.03 0.007 175,000 1,225.00
4 Mandor L.04 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Atap bitumen gelombang monolayer 3 mm lbr 0.747 168,000 125,496.00
2 Sekrup bh 9.097 1,200 10,916.40
JUMLAH HARGA BAHAN 136,412.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 166,232.40
E. OVERHEAD & PROFIT 10,0 % x D 16,623.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 182,855.64

Taksir.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.14
JENIS PEKERJAAN : Pemasangan 1 m² genteng bitumen bergelombang monolayer 3 mm (uk. 200x97x0,3cm) kemiringan
atap > 10°, jarak rangka gording maksimal 45 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.140 120,000 16,800.00
2 Tukang L.02 0.070 150,000 10,500.00
3 Kepala Tukang L.03 0.007 175,000 1,225.00
4 Mandor L.04 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Genteng bitumen gelombang monolayer 3 mm lbr 0.723 165,000 119,295.00
2 Sekrup bh 11.465 1,200 13,758.00
JUMLAH HARGA BAHAN 133,053.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 162,873.00
E. OVERHEAD & PROFIT 10,0 % x D 16,287.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 179,160.30
Taksir.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.15
JENIS PEKERJAAN : Pemasangan 1 m² genteng bitumen bergelombang monolayer 3 mm (uk. 106x40x0,3 cm),
kemiringan atap > 15º jarak gording maksimal 32 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.200 120,000 24,000.00
2 Tukang L.02 0.100 150,000 15,000.00
3 Kepala Tukang L.03 0.010 175,000 1,750.00
4 Mandor L.04 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 42,600.00
B. BAHAN
1 Genteng bitumen gelombang monolayer 3 mm lbr 3.710 54,000 200,340.00
2 Sekrup bh 16.129 1,200 19,354.80
JUMLAH HARGA BAHAN 219,694.80
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 262,294.80
E. OVERHEAD & PROFIT 10,0 % x D 26,229.48
F. HARGA SATUAN PEKERJAAN ( D + E ) 288,524.28

Taksir.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.16
JENIS PEKERJAAN : Pemasangan 1 m' nok bitumen
SATUAN PEMBAYARAN : M'
NO. KOMPONEN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja L.01 0.084 120,000 10,080.00


2 Tukang L.02 0.125 150,000 18,750.00
3 Kepala Tukang L.03 0.013 175,000 2,275.00
4 Mandor L.04 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Nok bitumen lbr 1.438 80,000 115,040.00
2 Sekrup bh 10.000 1,200 12,000.00
JUMLAH HARGA BAHAN 127,040.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 158,885.00
E. OVERHEAD & PROFIT 10,0 % x D 15,888.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 174,773.50
Taksir.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.17
JENIS PEKERJAAN : Pemasangan 1 m² cat pelapis anti bocor
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.020 120,000 2,400.00
2 Tukang L.02 0.063 150,000 9,450.00
3 Kepala Tukang L.03 0.006 175,000 1,050.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 13,455.00
B. BAHAN 0.00
1 Cat pelapis anti bocor Kg 0.500 51,000 25,500.00
JUMLAH HARGA BAHAN 25,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 38,955.00
E. OVERHEAD & PROFIT 10,0 % x D 3,895.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,850.50

Taksir.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.18
JENIS PEKERJAAN : Pemasangan 1 m² membran bitumen pelapis anti bocor sistem bakar
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.250 120,000 30,000.00
2 Tukang L.02 0.500 150,000 75,000.00
3 Kepala Tukang L.03 0.0500 175,000 8,750.00
4 Mandor L.04 0.0125 185,000 2,312.50
JUMLAH HARGA TENAGA 116,062.50
B. BAHAN
1 Lapisan coating primer kg 0.300 42,000 12,600.00
2 Membran bitumen pelapis anti bocor m² 1.050 75,000 78,750.00
JUMLAH HARGA BAHAN 91,350.00
C. PERALATAN
1
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 207,412.50
E. OVERHEAD & PROFIT 10,0 % x D 20,741.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 228,153.75
Taksir. 19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir. 19
JENIS PEKERJAAN : Pemasangan 1 m2 plastik untuk cor jalan beton
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.008 120,000 960.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 175,000
4 Mandor L.04 0.001 185,000 185.00
JUMLAH HARGA TENAGA 1,145.00
B. BAHAN
1 Plastik m² 1.05 3,250 3,412.50
JUMLAH HARGA BAHAN 3,412.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 4,557.50
E. OVERHEAD & PROFIT 10,0 % x D 455.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,013.25

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir. 20
JENIS PEKERJAAN : Pemasangan 100 m2 karung goni basah untuk curing beton
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.800 120,000 96,000.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 175,000
4 Mandor L.04 0.080 185,000 14,800.00
JUMLAH HARGA TENAGA 110,800.00
B. BAHAN
1 Karung goni buah 102.00 10,000 1,020,000.00
2 Air liter 5,000.00 36 180,000.00
JUMLAH HARGA BAHAN 1,200,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,310,800.00
E. OVERHEAD & PROFIT 10,0 % x D 131,080.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,441,880.00
Taksir. 21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir. 21
JENIS PEKERJAAN : Menyirami 100 m2 karung goni dengan air selama 4 hari
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 2.000 120,000 240,000.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 175,000
4 Mandor L.04 0.100 185,000 18,500.00
JUMLAH HARGA TENAGA 258,500.00
B. BAHAN
1 Air liter 20,000.00 36 720,000.00
JUMLAH HARGA BAHAN 720,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 978,500.00
E. OVERHEAD & PROFIT 10,0 % x D 97,850.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,076,350.00

Taksir. 22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir 22
JENIS PEKERJAAN : Pemasangan 1 m2 geotekstil untuk timbunan
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.100 120,000 12,000.00
2 Tukang L.02 0.020 150,000 3,000.00
3 Kepala Tukang L.03 175,000
4 Mandor L.04 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 16,850.00
B. BAHAN
1 Geotekstil m² 1.05 22,000 23,100.00
JUMLAH HARGA BAHAN 23,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 39,950.00
E. OVERHEAD & PROFIT 10,0 % x D 3,995.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 43,945.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir .23
JENIS PEKERJAAN : Pemasangan 1 m² cerucup gelam untuk pondasi (p. 1,5m - 20 cm)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.300 120,000 36,000.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 0.030 175,000 5,250.00
4 Mandor L.04 185,000
JUMLAH HARGA TENAGA 41,250.00
B. BAHAN
1 Gelam dia.6-8 btg 6.00 15,000 90,000.00
JUMLAH HARGA BAHAN 90,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 131,250.00
E. OVERHEAD & PROFIT 10,0 % x D 13,125.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 144,375.00

Pembuatan 1 Unit Septic Tank


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. SEPTIC TANK
Galian Tanah m3 4.500 127,957.50 575,808.75
Pas. Batu bata ad. 1 : 2 m2 12.750 132,414.70 1,688,287.43
Lantai Kerja m3 0.300 1,080,409.00 324,122.70
Plasteran ad 1:4 m2 12.750 108,791.32 1,387,089.33
Plat Beton Bertulang t. 12 cm m3 0.3600 5,895,735.00 2,122,464.60
Pipa Hawa Bh 1.0000 21,700.00 21,700.00
JUMLAH TENAGA KERJA 6,119,472.81
B RESAPAN
Galian Tanah m3 1.200 127,957.50 153,549.00
Koral m3 0.500 450,000.00 225,000.00
Ijuk Kg 25.000 36,000.00 900,000.00
Pipa Dia. 4" m 2.000 165,852.50 331,705.00
JUMLAH TENAGA BAHAN 1,610,254.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 7,729,726.81


DAFTAR HARGA SATUAN
PEKERJAAN 10%
KOTA PALEMBANG TAHUN 2021

No. Mata Pembayaran Harga Satuan Pekerjaan (Rp)


DIVISI No. Mata Pembayaran Uraian Satuan

a b b c d e
2.2.1 PEKERJAAN PERSIAPAN PEKERJAAN PERSIAPAN

2.2.1.1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter m² 256,146.00


2.2.1.1 Pek pagar sementara dari kayu

2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 m² 408,826.00


2.2.1.2 Pek pagar sementara dari seng gelombang meter
2.2.1.3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 m² 356,873.00
2.2.1.3 Pek pagar sementara dari kawat duri meter
2.2.1.4 Pek Bouwplank 2.2.1.4 Pengukuran dan pemasangan 1 m' Bouwplank m' 66,566.50
2.2.1.5 Pek kantor sementara 2.2.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran m² 1,412,521.00
2.2.1.6 Pek rumah jaga 2.2.1.6 Pembuatan 1 m2 rumah jaga (konstruksi kayu) m² 1,139,050.00
2.2.1.7 Pek gudang semen 2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan m² 1,150,413.00
2.2.1.8 Pek bedeng pekerja 2.2.1.8 Pembuatan 1 m bedeng pekerja
2
m² 1,189,518.00
2.2.1.9 Pembersihan dan perataan lapangan 2.2.1.9 Pembersihan 1 m2 lapangan dan perataan m² 23,375.00
2.2.1.10 Pek steger / perancah 2.2.1.10 Pembuatan 1 m2 steger / perancah dari bambu m² 94,006.00
2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40cm x50cm x25cm bh 200,211.00
2.2.1.11 Pek kotak adukan ukuran 40cm x50cm

2.2.1.12 Seme jalan sementara 2.2.1.12 Pembuatan 1 m2 jalan sementara m² 245,162.50


2.2.1.13 Pembongkaran beton bertulang 2.2.1.13 Pembongkaran 1 m3 beton bertulang m³ #VALUE!
2.2.1.14 Pembongkaran dinding tembok bata 2.2.1.14 Pembongkaran 1 m³ dinding tembok bata m3 947,809.50
2.2.1.15 Pemasangan 1 m2 kawat jaring galvanis panjang 240 cm m² 67,978.90
2.2.1.15 Pek kawat jaring galvanis

2.2.1.16 Pemasangan 1 m2 panel beton pracetak 5x50x240 cm untuk m² 558,398.50


2.2.1.16 Pek panel beton pracetak 5x50x240 cm pagar
2.2.1.16.a Pemasangan 1 m2 panel beton pracetak 5x40x240 cm untuk m² 553,465.00
2.2.1.16.a Pek panel beton pracetak 5x40x240 cm pagar

2.3.1 PEKERJAAN TANAH PEKERJAAN TANAH


2.3.1.1 Galian tanah per 1m 2.3.1.1 Penggalian tanah biasa sedalam 1 m m³ 104,087.50
2.3.1.2 Galian tanah per 2m 2.3.1.2 Penggalian tanah biasa sedalam 2 m m³ 127,957.50
2.3.1.3 Galian tanah per 3m 2.3.1.3 Penggalian tanah biasa sedalam 3 m m³ 152,234.50
2.3.1.4 Galian tanah keras 2.3.1.4 Penggalian tanah keras sedalam 1 m m³ 138,512.00
2.3.1.5 Galian tanah cadas 2.3.1.5 Penggalian tanah cadas sedalam 1 m m³ 210,210.00
2.3.1.6 Galian tanah lumpur 2.3.1.6 Penggalian tanah lumpur sedalam 1 m m³ 167,557.50
2.3.1.7 Stripping tanah 2.3.1.7 Pengerjaan stripping setinggi 1 m m² 7,617.50
2.3.1.8 Pembuangan tanah sejauh 30 m 2.3.1.8 Pembuangan 1 m³ tanah sejauh 30 m m³ 45,595.00
2.3.1.9 Pek urugan kembali galian tanah 2.3.1.9 Pengurugan kembali 1 m³ galian tanah m³ 76,175.00
2.3.1.10 Pemadatan per 20 cm 2.3.1.10 Pemadatan tanah 1 m³ per 20 cm m³ 76,175.00
2.3.1.11 Pek urugan dengan pasir urug 2.3.1.11 Pengurugan 1 m³ dengan pasir urug m³ 167,035.00
2.3.1.12 Pek lapisan pudel 2.3.1.12 Pemasangan 1 m³ lapisan pudel 1:3:7 m³ 574,651.00
2.3.1.13 Pekerjaan lapisan ijuk 2.3.1.13 Pemasangan 1 m² lapisan ijuk m² 319,852.50
2.3.1.14 Pengurugan dengan sirtu padat 2.3.1.14 Pengurugan 1 m³ dengan sirtu padat m³ 143,687.50
2.3.1.15 Pek Urugan dengan tanah timbunan 2.3.1.15 Pengurugan 1 m³ dengan tanah timbunan m³ 130,487.50

3.2.1 PEKERJAAN PONDASI PEKERJAAN PONDASI


3.2.1.1 Pek pondasi batu kali 1pc:3pp 3.2.1.1 Pemasangan 1 m³ pondasi batu Kali 1PC:3PP m³ 1,224,954.50
3.2.1.1.a Pemasangan 1 m³ pondasi batu bata (8x8x16) cm campuran m³ 1,127,951.57
3.2.1.1.a Pek pondasi batu bata 1pc:3pp
1PC:3PP
3.2.1.2 Pek pondasi batu kali 1pc:4pp 3.2.1.2 Pemasangan 1 m³ pondasi batu Kali 1PC:4PP m³ 1,179,618.00
3.2.1.2.a Pemasangan 1 m³ pondasi batu bata (8x8x16) cm campuran m³ 1,087,077.95
3.2.1.2.a Pek pondasi batu bata 1pc:4pp
1PC:4PP
3.2.1.3 Pek pondasi batu kali 1pc:5pp 3.2.1.3 Pemasangan 1 m³ pondasi batu Kali 1PC:5PP m³ 1,148,202.00
3.2.1.4 Pek pondasi batu kali 1pc:6pp 3.2.1.4 Pemasangan 1 m³ pondasi batu Kali 1PC:6PP m³ 1,126,108.50
3.2.1.5 Pek pondasi batu kali 1pc:8pp 3.2.1.5 Pemasangan 1 m³ pondasi batu Kali 1PC:8PP m³ 1,095,842.00
3.2.1.6 Pek pondasi batu kali 1kp:1sm:2 pp 3.2.1.6 Pemasangan 1 m³ pondasi batu Kali 1KP:1SM:2 PP m³ 1,276,326.92

3.2.1.7 Pek pondasi batu kali 1pc:3kp:10 pp 3.2.1.7 Pemasangan 1 m³ pondasi batu Kali 1PC:3KP:10 PP m³ 1,328,899.00
3.2.1.8 Pek pondasi batu kali 1/4pc:1kp:4 pp 3.2.1.8 Pemasangan 1 m³ pondasi batu Kali 1/4PC:1KP:4 PP m³ 1,276,500.50
3.2.1.9 Pek batu kosong (aanstamping) 3.2.1.9 Pemasangan 1 m³ batu kosong (aanstamping) m³ 782,298.00
3.2.1.10 Pek pondasi siklop 60% beton 3.2.1.10 Pemasangan 1 m³ pondasi siklop 60% beton m³ 3,337,999.50
3.2.1.11 Pek pondasi sumuran ø 100cm 3.2.1.11 Pemasangan 1 m³ pondasi sumuran Ø 100cm m³ 1,206,408.50
4.1.1 PEKERJAAN BETON PEKERJAAN BETON
4.1.1.1 Pek beton mutu K100 4.1.1.1 Pembuatan 1 m3 beton mutu f'c 7,4 MPa (K100) m³ 1,043,240.00
4.1.1.2 Pek beton mutu K125 4.1.1.2 Pembuatan 1 m3 beton mutu f'c 9,8 MPa (K125) m³ 1,080,409.00
4.1.1.3 Pek beton mutu K150 4.1.1.3 Pembuatan 1 m3 beton mutu f'c 12,2 MPa (K150) m³ 1,108,173.00
4.1.1.4 Pek lantai kerja mutu K100 4.1.1.4 Pembuatan 1 m3 lantai kerja beton mutu f'c 7,4 MPa (K100) m³ 955,185.00
4.1.1.5 Pek beton mutu K175 4.1.1.5 Pembuatan 1 m3 beton mutu f'c 14,5 MPa (K175) m³ 1,298,203.50
4.1.1.6 Pek beton mutu K200 4.1.1.6 Pembuatan 1 m3 beton mutu f'c 16,9 MPa (K200) m³ 1,173,606.50
4.1.1.7 Pek beton mutu K225 4.1.1.7 Pembuatan 1 m3 beton mutu f'c 19,3 MPa (K225) m³ 1,199,979.00
4.1.1.8 Pek beton mutu K250 4.1.1.8 Pembuatan 1 m beton mutu f'c 21,7 MPa (K250)
3
m³ 1,213,052.50
4.1.1.9 Pek beton mutu K275 4.1.1.9 Pembuatan 1 m beton mutu f'c 24 MPa (K275)
3
m³ 1,235,762.00
4.1.1.10 Pek beton mutu K300 4.1.1.10 Pembuatan 1 m3 beton mutu f'c 26,4 MPa (K300) m³ 1,242,400.50
4.1.1.11 Pek beton mutu K325 4.1.1.11 Pembuatan 1 m3 beton mutu f'c 28,8 MPa (K325) m³ 1,347,054.50
4.1.1.12 Pek beton mutu K350 4.1.1.12 Pembuatan 1 m3 beton mutu f'c 31,2 MPa (K350) m³ 1,356,245.00
4.1.1.13 Pembuatan 1 m3 beton kedap air dengan strorox 100 m³ 1,439,735.00
4.1.1.13 Pek beton kedap air dengan storox

4.1.1.14 Pek PVC waterstop 150mm 4.1.1.14 Pemasangan 1 m' PVC Waterstop lebar 150mm m' 89,133.00
4.1.1.15 Pek PVC waterstop 200mm 4.1.1.15 Pemasangan 1 m' PVC Waterstop lebar 200mm m' 121,159.50
a b b c d e
4.1.1.16 Pemasangan 1 m' PVC Waterstop lebar 230-320mm m' 191,994.00
4.1.1.16 Pek PVC waterstop 230-320mm
4.1.1.17 Pek besi polos atau ulir 4.1.1.17 Pembesian 1 kg dengan besi polos atau ulir kg 19,026.15
4.1.1.18 Pemasangan 1 kg kabel presstressed polos/strands kg 18,263.30
4.1.1.18 Pek kabel presstressed polos/strands
4.1.1.19 Pek jaring kawat baja (wiremesh) 4.1.1.19 Pemasangan 1 kg jaring kawat baja (wiremesh) kg 15,379.10
4.1.1.20 Pek bekisting untuk pondasi 4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi m² 213,906.00
4.1.1.21 Pek bekisting untuk sloof 4.1.1.21 Pemasangan 1 m bekisting untuk sloof
2
m² 224,356.00
4.1.1.22 Pek bekisting untuk kolom 4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom m² 365,563.00
4.1.1.23 Pek bekisting untuk balok 4.1.1.23 Pemasangan 1 m2 bekisting untuk balok m² 370,843.00
4.1.1.24 Pek bekisting untuk lantai 4.1.1.24 Pemasangan 1 m bekisting untuk lantai
2
m² 431,563.00
4.1.1.25 Pek bekisting untuk dinding 4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding m² 437,063.00
4.1.1.26 Pek bekisting untuk tangga 4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga m² 367,158.00
4.1.1.27 Pemasangan 1 m jembatan untuk pengecoran beton
2
m² 108,586.50
4.1.1.27 Pek jembatan untuk pengecoran beton

4.1.1.35 Pembuatan 1 m' kolom praktis beton bertulang (11x11) cm m' 106,991.50
4.1.1.35 Pek kolom praktis beton bertulang
4.1.1.36 Pembuatan 1 m' ring balok beton bertulang (10x15) cm m' 138,699.00
4.1.1.36 Pek ring balok beton bertulang

4.1.2 PEKERJAAN BETON PRACETAK


PEKERJAAN BETON PRACETAK

4.1.2.1 Pembuatan 1 m2 lahan produksi tebal 8 cm beton f’c 14,5 Mpa m² 91,390.20
4.1.2.1 Pek lahan produksi tebal 8 cm

4.1.2.2 Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 MPa m² 114,322.45
4.1.2.2 Pek lahan produksi tebal 10 cm

4.1.2.3 Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 Mpa m² 127,894.80
4.1.2.3 Pek lahan produksi tebal 12 cm

4.1.2.4 Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 MPa m² 171,484.50
4.1.2.4 Pek lahan produksi tebal 15 cm

4.1.2.5 Pembuatan 1 m2 bekisting untuk pelat beton pracetak (5 kali m² 254,774.55


4.1.2.5 Pek bekisting untuk pelat beton pracetak (5 kali pakai) pakai)
4.1.2.6 Pembuatan 1 m2 bekisting untuk balok beton pracetak (10 - 12 m² 46,538.25
4.1.2.6 Pek bekisting untuk pelat beton pracetak (10 - 12 kali pakai) kali pakai)
4.1.2.7 Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10 - 12 m² 44,915.75
4.1.2.7 Pek bekisting untuk pelat beton pracetak (10 - 12 kali pakai) kali pakai)
Pek pemasangan dan membuka bekisting komponen pelat beton 4.1.2.8 Pemasangan dan membuka bekisting 1 m3 komponen pelat m³ 10,983.50
4.1.2.8
pracetak beton pracetak
Bak pemasangan dan membuka bekisting komponen pelat beton 4.1.2.9 Pemasangan dan membuka bekisting 1 buah komponen balok buah 17,715.50
4.1.2.9
pracetak beton pracetak
Kok pemasangan dan membuka bekisting komponen pelat beton 4.1.2.10 Pemasangan dan membuka bekisting 1 buah komponen kolom buah 14,349.50
4.1.2.10
pracetak beton pracetak
4.1.2.11 Penuangan/menebar beton untuk 1 m³ plat beton pracetak m³ 91,228.50
4.1.2.11 Pek penuangan/menebar beton plat beton pracetak
4.1.2.12 Penuangan/menebar beton untuk 1 m³ balok beton pracetak m³ 93,786.00
4.1.2.12 Pek penuangan/menebar beton balok beton pracetak
4.1.2.13 Penuangan/menebar beton untuk 1 m³ kolom beton bercetak m³ 84,535.00
4.1.2.13 Pek penuangan/menebar beton kolom beton bercetak
4.1.2.14 Ereksi 1 buah komponen untuk pelat beton pracetak buah 204,250.84
4.1.2.14 Pek ereksi komponen pelat beton pracetak
4.1.2.15 Ereksi 1 buah komponen untuk balok beton pracetak buah 187,659.23
4.1.2.15 Pek ereksi komponen balok beton pracetak
4.1.2.16 Ereksi 1 buah komponen untuk kolom beton pracetak buah 253,495.45
4.1.2.16 Pek ereksi komponen kolom beton pracetak
4.1.2.17 Langsir 1 buah komponen untuk pelat pracetak ( ± 20 m) buah 47,158.77
4.1.2.17 Pek Langsir komponen pelat pracetak
4.1.2.18 Langsir 1 buah komponen untuk balok pracetak ( ± 20 m) buah 47,159.20
4.1.2.18 Pek Langsir komponen balok pracetak
4.1.2.19 Langsir 1 buah komponen untuk kolom pracetak ( ± 20 m) buah 47,158.77
4.1.2.19 Pek Langsir komponen kolom pracetak

4.1.2.20 Pek grout campuran 4.1.2.20 Bahan 1 m3 grout campuran m³ 1,604,405.00


4.1.2.21 Pek grout ( tidak campuran ) 4.1.2.21 Bahan 1 m3 grout ( tidak campuran) m³ 2,376,440.00
4.1.2.22 Upah grouting pada join pracetak 4.1.2.22 Upah melakukan grouting 1 titk pada join pracetak titik 86,773.50
4.1.2.23 Pek bekisting joint pracetak 4.1.2.23 Pemasangan 1 titk bekisting joint pracetak titik 100,246.30
4.1.2.24 Upah join dengan sling 4.1.2.24 Upah 1 titik join dengan sling titik 71,208.50

4.2.1 PEKERJAAN BESI & PEKERJAAN BESI & ALUMUNIUM


ALUMUNIUM
4.2.1.1 Pek 1 kg baja profil 4.2.1.1 Pemasangan 1 kg baja profil kg 37,295.50
4.2.1.2 Pek rangka kuda-kuda baja IWF 4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF kg 37,295.50
4.2.1.2a Pemasangan 1 m2 rangka kuda-kuda + reng atap baja ringan m² 241,046.04
4.2.1.2a Pek rangka kuda-kuda + reng atap baja ringan

4.2.1.3 Pek perakitan 100 kg baja 4.2.1.3 Pengerjaan perakitan 100 kg baja kg 52,503.00
4.2.1.4 Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka m² 870,369.50
4.2.1.4 Pek pintu besi rangkap baja siku
4.2.1.5 Pek pengelasan 10 cm dengan las listrik 4.2.1.5 Pengerjaan pengelasan 10 cm dengan las listrik cm 36,199.90
4.2.1.6 Pek rangka jendela squaretube 4.2.1.6 Pembuatan 1 m² rangka jendela squaretube 25x5 m² 439,840.50
4.2.1.7 Pek pintu rolling door besi 4.2.1.7 Pemasangan 1 m² pintu rolling door besi m² 1,024,221.00
4.2.1.8 Pemasangan 1 m² pintu folding door bahan plastik / PVC m² 748,627.00
4.2.1.8 Pek pintu folding door plastik / PVC
4.2.1.9 Pek sunscreen alumunium 4.2.1.9 Pemasangan 1 m² sunscreen aluminium m² 626,274.00
4.2.1.10 Pek rolling door allumunium 4.2.1.10 Pemasangan 1 m2 rolling door alluminium m² 1,079,925.00
4.2.1.11 Pek kusen pintu alumunium 4.2.1.11 Pemasangan 1 m kusen pintu alluminium m' 199,596.10
4.2.1.12 Pek pintu alumunium strip 8 cm 4.2.1.12 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m² 1,372,045.95
4.2.1.13 Pek pintu kaca rangka allumunium 4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alluminium m² 1,042,030.00
4.2.1.14 Pemasangan 1 m2 venetions blinds dan vertical blinds m² 156,150.50
4.2.1.14 Pek venetions blinds dan vertical blinds

4.2.1.15 Pek trali besi strip 4.2.1.15 Pemasangan 1 m2 terali besi strip (2 x 3) mm m² 606,180.30
4.2.1.16 Pek kawat nyamuk 4.2.1.16 Pemasangan 1 m2 kawat nyamuk m² 79,880.90
4.2.1.17 Pek jendela nako dan tralis 4.2.1.17 Pemasangan 1 m2 jendela nako dan tralis m² 466,108.50
4.2.1.18 Pemasangan 1 m' talang datar / jurai seng bjls 28 lebar 90 cm m' 175,906.50
4.2.1.18 Pek talang datar / jurai seng
4.2.1.19 Pemasangan 1 m' talang ½ lingkaran D-15 cm, seng plat bjls 30 m' 154,660.00
4.2.1.19 Pek talang ½ lingkaran
lebar 45 cm
4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul m² 112,645.50
4.2.1.20 Pek rangka besi hollow untuk partisi 60x120, untuk partisi
4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul m² 148,725.50
4.2.1.21 Pek rangka besi hollow untuk plafon 60x120, untuk plafon
4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin m² 297,895.13
4.2.1.22 Pek atap pelana rangka profil C75 profil C75
4.2.1.23 Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil m² 324,665.55
4.2.1.23 Pek atap jurai rangka profil C75 C75
No. Mata Pembayaran Harga Satuan Pekerjaan (Rp)
DIVISI No. Mata Pembayaran Uraian Satuan

a b b c d e
4.4.1 PEKERJAAN DINDING PEKERJAAN DINDING PASANGAN
PASANGAN
4.4.1.1 Pemasangan 1 m² dinding bata merah 1 batu camp. 1PC:2PP m² 272,481.00
4.4.1.1 Pek dinding bata merah 1 batu 1PC:2PP
4.4.1.2 Pemasangan 1 m² dinding bata merah 1 batu camp. 1PC:3PP m² 260,410.70
4.4.1.2 Pek dinding bata merah 1 batu 1PC:3PP
4.4.1.3 Pemasangan 1 m² dinding bata merah 1 batu camp. 1PC:4PP m² 252,497.30
4.4.1.3 Pek dinding bata merah 1 batu 1PC:4PP
4.4.1.4 Pemasangan 1 m² dinding bata merah 1 batu camp. 1PC:5PP m² 248,085.20
4.4.1.4 Pek dinding bata merah 1 batu 1PC:5PP
4.4.1.5 Pemasangan 1 m² dinding bata merah 1 batu camp. 1PC:6PP m² 245,894.00
4.4.1.5 Pek dinding bata merah 1 batu 1PC:6PP
4.4.1.6 Pemasangan 1 m² dinding bata merah 1 batu 1PC:3KP:10PP m² 284,355.83
4.4.1.6 Pek dinding bata merah 1 batu 1PC:3KP:10PP
4.4.1.7 Pemasangan 1 m² dinding bata merah 1/2 batu camp. 1PC:2PP m² 132,414.70
4.4.1.7 Pek dinding bata merah 1/2 batu 1PC:2PP
4.4.1.8 Pemasangan 1 m² dinding bata merah 1/2 batu camp. 1PC:3PP m² 126,823.62
4.4.1.8 Pek dinding bata merah 1/2 batu 1PC:3PP
4.4.1.9 Pemasangan 1 m² dinding bata merah 1/2 batu camp. 1PC:4PP m² 123,541.00
4.4.1.9 Pek dinding bata merah 1/2 batu 1PC:4PP
4.4.1.10 Pemasangan 1 m² dinding bata merah 1/2 batu camp. 1PC:5PP m² 121,471.68
4.4.1.10 Pek dinding bata merah 1/2 batu 1PC:5PP
4.4.1.11 Pemasangan 1 m² dinding bata merah 1/2 batu camp. 1PC:6PP m² 120,242.32
4.4.1.11 Pek dinding bata merah 1/2 batu 1PC:6PP
4.4.1.12 Pemasangan 1 m² dinding bata merah 1/2 batu 1PC:8PP m² 118,046.50
4.4.1.12
4.4.1.13 Pemasangan 1 m² dinding bata merah 1/2 batu 1PC:3KP:10PP m² 144,369.50
4.4.1.13 Pek dinding bata merah 1/2 batu 1PC:3KP:10PP
4.4.1.14 Pemasangan 1 m² dinding bata merah 1/2 batu 1KP:1SM:1PP m² 141,839.50
4.4.1.14 Pek dinding bata merah 1/2 batu 1KP:1SM:1PP
4.4.1.15 Pemasangan 1 m² dinding bata merah 1/2 batu 1KP:1SM:2PP m² 135,074.50
4.4.1.15 Pek dinding bata merah 1/2 batu 1KP:1SM:2PP
4.4.1.16 Pek dinding HB20 1PC:3PP 4.4.1.16 Pemasangan 1 m² dinding HB20 camp. 1PC:3PP m² 383,851.82
4.4.1.17 Pek dinding HB20 1PC:4PP 4.4.1.17 Pemasangan 1 m² dinding HB20 camp. 1PC:4PP m² 381,685.26
4.4.1.18 Pek dinding HB15 1PC:3PP 4.4.1.18 Pemasangan 1 m² dinding HB15 camp. 1PC:3PP m² 341,768.24
4.4.1.19 Pek dinding HB15 1PC:4PP 4.4.1.19 Pemasangan 1 m² dinding HB15 camp. 1PC:4PP m² 340,023.20
4.4.1.20 Pek dinding HB10 1PC:3PP 4.4.1.20 Pemasangan 1 m² dinding HB10 camp. 1PC:3PP m² 302,038.66
4.4.1.21 Pek dinding HB10 1PC:4PP 4.4.1.21 Pemasangan 1 m² dinding HB10 camp. 1PC:4PP m² 301,208.38
4.4.1.22 Pemasangan 1 m² dinding terawang (rooster bata) 12x11x24 m² 190,091.00
4.4.1.22 Pek dinding terawang (rooster bata) 1SP:3PP
campuran 1SP:3PP
4.4.1.23 Pemasangan 1m² dinding terawang (rooster beton) 20x20 m² 291,291.00
4.4.1.23 Pek dinding terawang (rooster ) 1PC:4PP
camp. 1PC:4PP
4.4.1.23.a Pemasangan 1 m² dinding terawang (rooster keramik) 20x20 m² 79,541.00
4.4.1.23.a Pek dinding terawang (rooster keramik) 1PC:4PP
camp. 1PC:4PP
4.4.1.23.b Pemasangan 1 m² dinding glass block 20x20 camp. 1PC:4PP m² 739,541.00
4.4.1.23.b Pek dinding glass block 20x20 1PC:4PP
4.4.1.24 Pemasangan 1 m² dinding bata berongga camp. 1PC:3PP m² 350,152.00
4.4.1.24 Pek dinding bata berongga 1PC:3PP
4.4.1.25 Pek dinding bata ringan tebal 7,5 cm 4.4.1.25 Pemasangan 1 m² dinding bata ringan tebal 7,5 cm m² 454,071.37
4.4.1.26 Pek dinding bata ringan tebal 10 cm 4.4.1.26 Pemasangan 1 m² dinding bata ringan tebal 10 cm m² 493,640.94

4.4.2 PEKERJAAN PLESTERAN


PEKERJAAN PLESTERAN

4.4.2.1 Pemasangan 1 m² plesteran 1PC:1PP tebal 15 mm m² 93,456.00


4.4.2.1 Pek plesteran 1 PC:1PP tebal 15 mm
4.4.2.2 Pemasangan 1 m² plesteran 1PC:2PP tebal 15 mm m² 85,865.82
4.4.2.2 Pek plesteran 1PC:2PP tebal 15 mm
4.4.2.3 Pemasangan 1 m² plesteran 1PC:3PP tebal 15 mm m² 83,121.68
4.4.2.3 Pek Plesteran 1PC:3PP tebal 15 mm
4.4.2.4 Pemasangan 1 m² plesteran 1PC:4PP tebal 15 mm m² 81,288.24
4.4.2.4 Pek plesteran 1PC:4PP tebal 15 mm
4.4.2.5 Pemasangan 1 m² plesteran 1PC:5PP tebal 15 mm m² 80,193.78
4.4.2.5 Pek plesteran 1PC:5PP tebal 15 mm
4.4.2.6 Pemasangan 1 m² plesteran 1PC:6PP tebal 15 mm m² 79,340.32
4.4.2.6 Pek plesteran 1PC:6PP tebal 15 mm
4.4.2.7 Pemasangan 1 m² plesteran 1PC:7PP tebal 15 mm m² 78,854.34
4.4.2.7 Pek plesteran 1PC:7PP tebal 15 mm
4.4.2.8 Pemasangan 1 m² plesteran 1PC:8PP tebal 15 mm m² 78,368.36
4.4.2.8 Pek plesteran 1PC:8PP tebal 15 mm
4.4.2.9 Pemasangan 1 m² plesteran 1PC:1/2KP:3PP tebal 15mm m² 83,673.26
4.4.2.9 Pek plesteran 1PC:1/2KP:3PP tebal 15 mm
4.4.2.10 Pemasangan 1 m² plesteran 1PC:2KP:8PP tebal 15mm m² 81,961.00
4.4.2.10 Pek plesteran 1PC:2KP:8PP tebal 15 mm
4.4.2.11 Pemasangan 1 m² plesteran 1SM:1KP:1PP tebal 15mm m² 92,499.00
4.4.2.11 Pek plesteran 1SM:1KP:1PP tebal 15 mm
4.4.2.12 Pemasangan 1 m² plesteran 1SM:1KP:2PP tebal 15mm m² 89,243.00
4.4.2.12 Pek plesteran 1SM:1KP:2PP tebal 15 mm
4.4.2.13 Pemasangan 1 m² plesteran 1PC:2PP tebal 20 mm m² 114,936.93
4.4.2.13 Pek plesteran 1PC:2PP tebal 20 mm
4.4.2.14 Pemasangan 1 m² plesteran 1PC:3PP tebal 20 mm m² 90,966.57
4.4.2.14 Pek plesteran 1PC:3PP tebal 20 mm
4.4.2.15 Pemasangan 1 m² plesteran 1PC:4PP tebal 20 mm m² 108,791.32
4.4.2.15 Pek plesteran 1PC:4PP tebal 20 mm
4.4.2.16 Pemasangan 1 m² plesteran 1PC:5PP tebal 20 mm m² 107,374.21
4.4.2.16 Pek plesteran 1PC:5PP tebal 20 mm
4.4.2.17 Pemasangan 1 m² plesteran 1PC:6PP tebal 20 mm m² 106,194.09
4.4.2.17 Pek plesteran 1PC:6PP tebal 20 mm
4.4.2.18 Pemasangan 1 m² plesteran 1SM:1KP:2PP tebal 20 mm m² 123,436.50
4.4.2.18 Pek plesteran 1SM:1KP:2PP tebal 20 mm
4.4.2.19 Pek berapen 1PC:5PP tebal 15 mm 4.4.2.19 Pemasangan 1 m² berapen 1PC:5PP tebal 15 mm m² 45,246.78
4.4.2.20 Pemasangan 1 m² plesteran skoning 1PC:2PP lebar 10 cm m 87,356.50
4.4.2.20 Pek plesteran skoning 1PC:2PP lebar 10 cm
4.4.2.21 Pemasangan 1 m² plesteran granit 1PC:2 Granit tebal 10 mm m² 237,193.00
4.4.2.21 Pek plesteran granit 1PC:2 Granit tebal 10 mm
4.4.2.22 Pemasangan 1 m² plesteran teraso 1PC:2 Teraso tebal 10 mm m² 233,893.00
4.4.2.22 Pek plesteran teraso 1PC:2 Teraso tebal 10 mm
4.4.2.23 Pek plesteran ciprat 1PC:2PP 4.4.2.23 Pemasangan 1 m² plesteran ciprat 1PC:2PP m² 67,348.82
4.4.2.24 Pek finishing siar pasangan bata 4.4.2.24 Pemasangan 1 m² finishing siar pasangan bata m² 39,308.81
4.4.2.25 Pek finishing siar pas. conblock 4.4.2.25 Pemasangan 1 m² finishing siar pas. conblock m² 18,640.60
4.4.2.26 Pek finishing siar pas. batu belah 4.4.2.26 Pemasangan 1 m² finishing siar pas. batu belah m² 79,897.84
4.4.2.27 Pek acian 4.4.2.27 Pemasangan 1 m² acian m² 51,007.00
No. Mata Pembayaran Harga Satuan Pekerjaan (Rp)
DIVISI No. Mata Pembayaran Uraian Satuan

a b b c d e
4.4.3 PEKERJAAN PENUTUP LANTAI &
PEKERJAAN PENUTUP LANTAI PENUTUP DINDING
& PENUTUP DINDING

4.4.3.1 Pek ubin PC abu-abu 40x40 4.4.3.1 Pemasangan 1 m2 lantai ubin PC abu-abu 40x40 m² 123,645.50
4.4.3.2 Pek ubin PC abu-abu 30x30 4.4.3.2 Pemasangan 1 m2 lantai ubin PC abu-abu 30x30 m² 139,899.10
4.4.3.3 Pek ubin PC abu-abu 20x20 4.4.3.3 Pemasangan 1 m2 lantai ubin PC abu-abu 20x20 m² 321,451.90
4.4.3.4 Pek ubin warna 40x40 4.4.3.4 Pemasangan 1 m2 lantai ubin warna 40x40 m² 126,599.00
4.4.3.5 Pek ubin warna 30x30 4.4.3.5 Pemasangan 1 m lantai ubin warna 30x30
2
m² 148,644.10
4.4.3.6 Pek ubin warna 20x20 4.4.3.6 Pemasangan 1 m2 lantai ubin warna 20x20 m² 192,531.90
4.4.3.7 Pek ubin teraso 40x40 4.4.3.7 Pemasangan 1 m2 lantai ubin teraso 40x40 m² 151,802.20
4.4.3.8 Pek ubin teraso 30x30 4.4.3.8 Pemasangan 1 m lantai ubin teraso 30x30
2
m² 174,212.50
4.4.3.9 Pek ubin granit 40x40 4.4.3.9 Pemasangan 1 m2 lantai ubin granit 40x40 m² 525,203.80
4.4.3.9.a Pek granit 60x60 4.4.3.9.a Pemasangan 1 m2 lantai ubin granit 60x60 m² 355,058.44
4.4.3.10 Pek ubin granit 30x30 4.4.3.10 Pemasangan 1 m lantai ubin granit 30x30
2
m² 415,767.00
4.4.3.11 Pek lantai ubin teralux 40x40 4.4.3.11 Pemasangan 1 m2 lantai ubin teralux 40x40 m² 166,023.55
4.4.3.12 Pek ubin teralux 30x30 4.4.3.12 Pemasangan 1 m2 lantai ubin teralux 30x30 m² 255,818.75
4.4.3.13 Pemasangan 1 m lantai ubin teralux marmer 60x60
2
m² 509,954.50
4.4.3.13 Pek ubin teralux marmer 60x60

4.4.3.14 Pemasangan 1 m2 lantai ubin teralux marmer 40x40 m² 515,597.50


4.4.3.14 Pek ubin teralux marmer 40x40

4.4.3.15 Pemasangan 1 m2 lantai ubin teralux marmer 30x30 m² 500,637.50


4.4.3.15 Pek ubin teralux marmer 30x30

4.4.3.16 Pek plint ubin PC abu-abu 15x20 4.4.3.16 Pemasangan 1 m' Plint ubin PC abu-abu 15x20 m' 38,854.20
4.4.3.17 Pek plint ubin PC abu-abu 15x20 4.4.3.17 Pemasangan 1 m' Plint ubin PC abu-abu 10x30 m' 36,877.94
4.4.3.18 Pek plint ubin PC abu-abu 10x40 4.4.3.18 Pemasangan 1 m' plint ubin PC abu-abu 10x40 m' 36,105.74
4.4.3.19 Pek plint ubin warna 10x20 4.4.3.19 Pemasangan 1 m' plint ubin warna 10x20 m' 40,251.64
4.4.3.20 Pek plint ubin warna 10x30 4.4.3.20 Pemasangan 1 m' plint ubin warna 10x30 m' 67,361.14
4.4.3.21 Pek plint ubin warna 10x40 4.4.3.21 Pemasangan 1 m' plint ubin warna 10x40 m' 42,616.64
4.4.3.22 Pek plint ubin teraso 10x30 4.4.3.22 Pemasangan 1 m' plint ubin teraso 10x30 m' 45,228.04
4.4.3.23 Pek plint ubin teraso 10x40 4.4.3.23 Pemasangan 1 m' plint ubin teraso 10x40 m' 42,033.64
4.4.3.24 Pek plint ubin granit 10x40 4.4.3.24 Pemasangan 1 m' plint ubin granit 10x40 m' 75,556.14
4.4.3.24.a Pek plint ubin granit 10x60 4.4.3.24.a Pemasangan 1 m' plint ubin granit 10x60 m' 62,427.64
4.4.3.25 Pek plint ubin granit 10x30 4.4.3.25 Pemasangan 1 m' plint ubin granit 10x30 m' 64,254.74
4.4.3.26 Pek plint ubin teralux kerang 10x40 4.4.3.26 Pemasangan 1 m' plint ubin teralux kerang 10x40 m' 42,539.64
4.4.3.27 Pek plint ubin teralux kerang 10x30 4.4.3.27 Pemasangan 1 m' plint ubin teralux kerang 10x30 m' 45,033.89
4.4.3.28 Pek plint ubin teralux marmer 10x60 4.4.3.28 Pemasangan 1 m' plint ubin teralux marmer 10x60 m' 135,264.14
4.4.3.29 Pek plint ubin teralux marmer 10x40 4.4.3.29 Pemasangan 1 m' plint ubin teralux marmer 10x40 m' 137,354.14
4.4.3.30 Pek plint ubin teralux marmer 10x30 4.4.3.30 Pemasangan 1 m' plint ubin teralux marmer 10x30 m' 133,372.14
4.4.3.31 Pemasangan 1 m2 lantai teraso cor ditempat tebal 3 cm m² 540,848.00
4.4.3.31 Pek lantai teraso cor ditempat

4.4.3.32 Pek lantai keramik artistik 10x20 4.4.3.32 Pemasangan 1 m2 lantai keramik artistik 10x20 m² 675,166.25
4.4.3.33 Pemasangan 1 m2 lantai keramik artistik 10x20 atau 5x20 m² 710,902.94
4.4.3.33 Pek artistik 10x20 atau 5x20

4.4.3.34 Pek lantai keramik 33x33 4.4.3.34 Pemasangan 1 m2 lantai keramik 33x33 m² 298,842.94
4.4.3.34.a Pek keramik 40x40 4.4.3.34.a Pemasangan 1 m2 lantai keramik 40x40 m² 280,362.94
4.4.3.35 Pek keramik 30x30 4.4.3.35 Pemasangan 1 m2 lantai keramik 30x30 m² 349,112.50
4.4.3.36 Pek keramik 20x20 4.4.3.36 Pemasangan 1 m lantai keramik 20x20
2
m² 290,882.90
4.4.3.37 Pemasangan 1 m2 lantai keramik 10x33 variasi/border m² 450,420.30
4.4.3.37 Pek lantai keramik 10x33 variasi/border

4.4.3.38 Pek lantai keramik mozaik 30x30 4.4.3.38 Pemasangan 1 m2 lantai keramik mozaik 30x30 m² 363,071.50
4.4.3.39 Pek plint keramik 10x20 4.4.3.39 Pemasangan 1 m' plint keramik 10x20 m' 57,582.14
4.4.3.39.a Pek plint keramik 10x40 4.4.3.39.a Pemasangan 1 m' plint keramik 10x40 m' 51,735.64
4.4.3.39.b Pek plint keramik 10x30 4.4.3.39.b Pemasangan 1 m' plint keramik 10x30 m' 52,012.84
4.4.3.40 Pek plint keramik 10x10 4.4.3.40 Pemasangan 1 m' plint keramik 10x10 m' 57,857.14
4.4.3.41 Pek plint keramik 5x20 4.4.3.41 Pemasangan 1 m' plint keramik 5x20 m' 63,237.57
4.4.3.42 Pek plint internal cove artistik 4.4.3.42 Pemasangan 1 m' plint internal cove artistik 5x5x20 m' 301,490.64
4.4.3.43 Pek marmer 100x100 4.4.3.43 Pemasangan 1 m2 lantai marmer 100x100 m² 2,105,526.94
4.4.3.44 Pek lantai karpet 4.4.3.44 Pemasangan 1 m2 lantai karpet m² 188,034.00
4.4.3.45 Pemasangan 1 m2 underlayer (lapisan bawah karpet) m² 164,681.00
4.4.3.45 Pek underlayer (lapisan bawah karpet)

4.4.3.46 Pek lantai parquet 4.4.3.46 Pemasangan 1 m2 lantai parquet m² 611,655.00


4.4.3.47 Pek lantai kayu gymfloor 4.4.3.47 Pemasangan 1 m2 lantai kayu gymfloor m² 570,735.00
4.4.3.48 Pek dinding porslen 11x11 4.4.3.48 Pemasangan 1 m dinding porslen 11x11
2
m² 704,833.80
4.4.3.49 Pek dinding porslen 10x20 4.4.3.49 Pemasangan 1 m2 dinding porslen 10x20 m² 797,453.80
4.4.3.50 Pek dinding porslen 20x20 4.4.3.50 Pemasangan 1 m2 dinding porslen 20x20 m² 778,313.80
4.4.3.51 Pek dinding keramik artistik 10x20 4.4.3.51 Pemasangan 1 m dinding keramik artistik 10x20
2
m² 733,323.80
4.4.3.52 Pek dinding keramik artistik 5x20 4.4.3.52 Pemasangan 1 m2 dinding keramik artistik 5x20 m² 1,213,033.80
4.4.3.53 Pek dinding keramik 10x20 4.4.3.53 Pemasangan 1 m2 dinding keramik 10x20 m² 351,458.80
4.4.3.54 Pek dinding keramik 20x20 4.4.3.54 Pemasangan 1 m2 dinding keramik 20x20 m² 344,006.30
4.4.3.55 Pek dinding marmer 100x100 4.4.3.55 Pemasangan 1 m2 dinding marmer 100x100 m² 2,321,335.94
4.4.3.56 Pek dinding bata pelapis 3x7x24 4.4.3.56 Pemasangan 1 m2 dinding bata pelapis 3x7x24 m² 505,345.94
4.4.3.57 Pek dinding batu paras 4.4.3.57 Pemasangan 1 m2 dinding batu paras m² 395,180.50
4.4.3.58 Pek dinding batu tempel hitam 4.4.3.58 Pemasangan 1 m2 dinding batu tempel hitam m² 334,680.50
4.4.3.59 Pek lantai vinyl 30x30 4.4.3.59 Pemasangan 1 m2 lantai vinyl 30x30 m² 426,211.50
4.4.3.60 Pek wallpaper lebar 50 cm 4.4.3.60 Pemasangan 1 m wallpaper lebar 50 cm
2
m² 244,414.50
4.4.3.61 Pek Floor harderner 4.4.3.61 Pemasangan 1 m2 Floor harderner m² 79,046.00
4.4.3.62 Pek plint vinyl karet 15x30 4.4.3.62 Pemasangan 1 m' plint vinyl karet 15x30 m' 55,858.00
4.4.3.63 Pek plint kayu 2x10 4.4.3.63 Pemasangan 1 m' plint kayu 2x10 m' 56,386.00
4.4.3.64 Pek paving block natural tebal 6 cm 4.4.3.64 Pemasangan 1 m2 paving block natural tebal 6 cm m² 233,769.25
4.4.3.65 Pek paving block natural tebal 8 cm 4.4.3.65 Pemasangan 1 m2 paving block natural tebal 8 cm m² 309,254.55
4.4.3.66 Pemasangan 1 m2 paving block berwarna tebal 6 cm m² 243,546.05
4.4.3.66 Pek paving block berwarna tebal 6 cm

4.4.3.67 Pemasangan 1 m2 paving block berwarna tebal 8 cm m² 310,365.55


4.4.3.67 Pek paving block berwarna tebal 8 cm
a b b c d e
4.5.1 PEKERJAAN PLAFOND PEKERJAAN PLAFOND
4.5.1.1 Pemasangan 1 m² langit-langit asbes semen 4,5,6 mm m² 44,533.50
4.5.1.1 Pek asbes semen 4,5,6 mm
4.5.1.2 Pek akustik 30x30 4.5.1.2 Pemasangan 1 m² langit-langit akustik 30x30 m² 172,381.00
4.5.1.3 Pek m² akustik 30x60 4.5.1.3 Pemasangan 1 m² langit-langit akustik 30x60 m² 129,701.00
4.5.1.4 Pek akustik 60x120 4.5.1.4 Pemasangan 1 m² langit-langit akustik 60x120 m² 136,152.50
4.5.1.5 Pek tripleks tebal. 4 mm 4.5.1.5 Pemasangan 1 m² langit-langit tripleks tebal. 4 mm m² 62,243.50
4.5.1.6 Pek lambrisering kayu 4.5.1.6 Pemasangan 1 m² langit-langit lambrisering kayu m² 332,332.00
4.5.1.7 Pemasangan 1 m² langit-langit gypsum board tebal 9 mm m² 60,115.00
4.5.1.7 Pek gypsum board tebal 9 mm
4.5.1.7.a Pemasangan 1 m² langit-langit kalsi board tebal 3,5 mm m² 52,107.00
4.5.1.7.a Pek kalsi board tebal 3,5 mm
4.5.1.8 Pemasangan 1 m² langit-langit akustik berikut rangka m² 808,225.00
4.5.1.8 Pek akustik berikut rangka alumunium
alumunium
4.5.1.9 Pek list kayu profil 4.5.1.9 Pemasangan m' list langit-langit kayu profil m' 42,075.00
4.5.1.9.a Pek list gypsum profil 4.5.1.9.a Pemasangan m' list langit-langit gypsum profil m' 37,988.50

4.5.2 PEKERJAAN PENUTUP ATAP


PEKERJAAN PENUTUP ATAP

4.5.2.1 Pek atap genteng palentong kecil 4.5.2.1 Pemasangan 1 m2 atap genteng palentong kecil m² 123,246.75
4.5.2.2 Pek atap genteng kodok glazur 4.5.2.2 Pemasangan 1 m2 atap genteng kodok glazuur m² 188,012.00
4.5.2.3 Pemasangan 1 m2 atap genteng palentong besar/super m² 102,872.00
4.5.2.3 Pek atap genteng palentong besar/super

4.5.2.4 Pek bubung genteng palentong kecil 4.5.2.4 Pemasangan 1 m2 bubung genteng palentong kecil m² 173,063.00
4.5.2.5 Pek bubung genteng kodok glazur 4.5.2.5 Pemasangan 1 m2 bubung genteng kodok glazuur m² 148,313.00
4.5.2.6 Pemasangan 1 m2 bubung genteng palentong besar m² 163,713.00
4.5.2.6 Pek bubung genteng palentong besar

4.5.2.7 Pek rooflight fiberglass 4.5.2.7 Pemasangan 1 m rooflight fiberglass 90x180


2
m² 119,317.00
4.5.2.8 Pemasangan 1 m2 atap asbes gelombang 92x250 tebal 5 mm m² 98,263.00
4.5.2.8 Pek atap asbes gelombang 92x250

4.5.2.9 Pemasangan 1 m2 atap asbes gelombang 92x225 tebal 5 mm m² 109,263.00


4.5.2.9 Pek atap asbes gelombang 92x225

4.5.2.10 Pemasangan 1 m2 atap asbes gelombang 92x200 tebal 5 mm m² 102,102.00


4.5.2.10 Pek atap asbes gelombang 92x200

4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 92x180 tebal 5 mm m² 116,292.00


4.5.2.11 Pek atap asbes gelombang 92x180

4.5.2.12 Pemasangan 1 m2 atap asbes gelombang 105x300 tebal 5 mm m² 70,862.00


4.5.2.12 Pek atap asbes gelombang 105x300

4.5.2.13 Pemasangan 1 m2 atap asbes gelombang 105x270 tebal 5 mm m² 74,712.00


4.5.2.13 Pek atap asbes gelombang 105x270

4.5.2.14 Pemasangan 1 m2 atap asbes gelombang 105x240 tebal 5 mm m² 73,194.00


4.5.2.14 Pek atap asbes gelombang 105x240

4.5.2.15 Pemasangan 1 m atap asbes gelombang 105x210 tebal 5 mm


2
m² 72,468.00
4.5.2.15 Pek atap asbes gelombang 105x210

4.5.2.16 Pemasangan 1 m2 atap asbes gelombang 105x150 tebal 5 mm m² 81,202.00


4.5.2.16 Pek atap asbes gelombang 105x150

4.5.2.17 Pemasangan 1 m2 atap asbes gelombang 108x300 tebal 6 mm m² 80,212.00


4.5.2.17 Pek atap asbes gelombang 108x300

4.5.2.18 Pemasangan 1 m2 atap asbes gelombang 108x270 tebal 6 mm m² 79,750.00


4.5.2.18 Pek atap asbes gelombang 108x270

4.5.2.19 Pemasangan 1 m2 atap asbes gelombang 108x240 tebal 6 mm m² 85,030.00


4.5.2.19 Pek atap asbes gelombang 108x240

4.5.2.20 Pemasangan 1 m2 atap asbes gelombang 108x210 tebal 6 mm m² 83,952.00


4.5.2.20 Pek atap asbes gelombang 108x210

4.5.2.21 Pemasangan 1 m2 atap asbes gelombang 108x180 tebal 6 mm m² 91,872.00


4.5.2.21 Pek atap asbes gelombang 108x180

4.5.2.22 Pek bubung stel gelombang 92 cm 4.5.2.22 Pemasangan 1 m’ bubung stel gelombang 92 cm m' 153,389.50
4.5.2.23 Pek bubung stel gelombang 105 cm 4.5.2.23 Pemasangan 1 m' bubung stel gelombang 105 cm m' 123,029.50
4.5.2.24 Pek bubung stel gelombang 108 cm 4.5.2.24 Pemasangan 1 m' bubung stel gelombang 108 cm m' 136,834.50
4.5.2.25 Pek nok paten 92 cm 4.5.2.25 Pemasangan 1 m' nok paten 92 cm m' 57,689.50
4.5.2.26 Pek nok paten 105 cm 4.5.2.26 Pemasangan 1 m' nok paten 105 cm m' 62,969.50
4.5.2.27 Pek nok paten 108 cm 4.5.2.27 Pemasangan 1 m' nok paten 108 cm m' 67,589.50
4.5.2.28 Pek nok stel rata 92 cm 4.5.2.28 Pemasangan 1 m' nok stel rata 92 cm m' 77,566.50
4.5.2.29 Pek nok stel rata 105 cm 4.5.2.29 Pemasangan 1 m' nok stel rata 105 cm m' 88,269.50
4.5.2.30 Pek atap genteng beton 4.5.2.30 Pemasangan 1 m2 atap genteng beton m² 135,311.00
4.5.2.31 Pek atap genteng aspal 4.5.2.31 Pemasangan 1 m2 atap genteng aspal m² 346,153.50
4.5.2.32 Pemasangan 1 m2 genteng metal polos atap pelana m² 191,438.50
4.5.2.32 Pek genteng metal polos atap pelana

4.5.2.32.a Pemasangan 1 m2 genteng metal berpasir atap pelana m² 207,168.50


4.5.2.32.a Pek genteng metal berpasir atap pelana

4.5.2.33 Pek genteng metal polos atap jurai 4.5.2.33 Pemasangan 1 m2 genteng metal polos atap jurai m² 267,668.50
4.5.2.33.a Pemasangan 1 m2 genteng metal berpasir atap jurai m² 291,868.50
4.5.2.33.a Pek genteng metal berpasir atap jurai

4.5.2.34 Pek atap sirap kayu 4.5.2.34 Pemasangan 1 m2 atap sirap kayu m² 262,542.50
4.5.2.35 Pek nok genteng beton 4.5.2.35 Pemasangan 1 m' nok genteng beton m' 183,433.80
4.5.2.36 Pek nok genteng aspal 4.5.2.36 Pemasangan 1 m' nok genteng aspal m' 95,353.50
4.5.2.37 Pek nok genteng metal 4.5.2.37 Pemasangan 1 m' nok genteng metal m' 97,163.00
4.5.2.37.a Pek nok genteng metal berpasir 4.5.2.37.a Pemasangan 1 m' nok genteng metal berpasir m' 118,943.00
4.5.2.38 Pek nok atap sirap 4.5.2.38 Pemasangan 1 m' nok atap sirap m' 105,803.50
4.5.2.39 Pek atap seng gelombang 4.5.2.39 Pemasangan 1 m' atap seng gelombang m' 101,750.00
4.5.2.40 Pek nok atap seng 4.5.2.40 Pemasangan 1 m' nok atap seng m' 64,586.50
4.5.2.41 Pek alumunium gelombang 4.5.2.41 Pemasangan 1 m2 atap alumunium gelombang m² 164,736.00
4.5.2.42 Pek nok atap alumunium gelombang 4.5.2.42 Pemasangan 1 m' nok atap alumunium gelombang m' 98,945.00
4.5.2.43 Pek lapisan Alumunium Foil 4.5.2.43 Pemasangan 1 m2 lapisan Alumunium Foil m² 43,152.62
4.6.1 PEKERJAAN KAYU PEKERJAAN KAYU
4.6.1.1 Pembuatan & pemasangan 1 m³ kusen kayu kelas II m³ 10,119,725.00
4.6.1.1 Pek kusen kayu kelas II
4.6.1.2 Pembuatan & pemasangan 1 m³ kusen kayu kelas III m³ 7,653,800.00
4.6.1.2 Pek kusen kayu kelas III
4.6.1.3 Pembuatan & pemasangan 1 m² pintu kayu klam kayu kelas II m² 433,735.50
4.6.1.3 Pek pintu kayu klam kayu kelas II
4.6.1.4 Pembuatan & pemasangan 1 m² pintu klam kayu kelas III m² 358,935.50
4.6.1.4 Pek pintu klam kayu kelas III
4.6.1.5 Pembuatan & pemasangan 1 m² pintu panel kayu kelas II m² 895,125.00
4.6.1.5 Pek pintu panel kayu kelas II
4.6.1.6 Pembuatan & pemasangan 1 m² pintu/jendela kaca kayu kelas II m² 676,060.00
4.6.1.6 Pek pintu/jendela kaca kayu kelas II
4.6.1.7 Pembuatan & pemasangan 1 m² pintu/jendela jalusi kayu kelas m² 1,008,645.00
4.6.1.7 Pek pintu jendela jalusi kayu kelas II
II
4.6.1.8 Pembuatan & pemasangan 1 m² pintu plywood rangkap m² 665,923.50
4.6.1.8 Pek pintu plywood rangkap
4.6.1.9 Pembuatan & pemasangan 1 m² pintu plywood rangka ekspose m² 738,254.00
4.6.1.9 Pek pintu plywood rangka ekspose kayu kelas II
kayu kelas II
4.6.1.10 Pembuatan & pemasangan 1 m² jalusi kusen kayu kelas II m² 812,542.50
4.6.1.10 Pek jalusi kusen kayu kelas II
4.6.1.11 Pembuatan & pemasangan 1 m² pintu teakwood rangka m² 731,016.00
4.6.1.11 Pek pintu teakwood rangka ekspose kayu kelas II
ekspose kayu kelas II
4.6.1.12 Pembuatan & pemasangan 1 m² pintu lapis formika rangka m² 859,364.00
4.6.1.12 Pek pintu lapis formika rangka ekspose kayu kelas II
ekspose kayu kelas II
4.6.1.13 Pemasangan 1 m³ kuda-kuda konvensional kayu kelas II m³ 8,481,000.00
4.6.1.13 Pek kuda-kuda konvensional kayu kelas II
4.6.1.14 Pek kuda-kuda ekspose kayu kelas II 4.6.1.14 Pemasangan 1 m³ kuda-kuda ekspose kayu kelas II m³ 10,603,697.50
4.6.1.15 Pek kontruksi gordeng kayu kelas II 4.6.1.15 Pemasangan 1 m³ kontruksi gordeng kayu kelas II m³ 10,073,497.50
Pek rangka atap genteng keramik kayu kelas II 4.6.1.16 Pemasangan 1 m² rangka atap genteng keramik kayu kelas II m² 275,192.50
4.6.1.16
Pek rangka atap genteng beton kayu kelas II 4.6.1.17 Pemasangan 1 m² rangka atap genteng beton kayu kelas II m² 374,522.50
4.6.1.17
4.6.1.18 Pek rangka atap sirap kayu kelas II 4.6.1.18 Pemasangan 1 m² rangka atap sirap kayu kelas II m² 106,770.40
Pek rangka langit-langit 50x100 kayu kelas III 4.6.1.19 Pemasangan 1 m² rangka langit-langit 50x100 kayu kelas III m² 139,221.50
4.6.1.19
Pek rangka langit-langit 60x60 kayu kelas III 4.6.1.20 Pemasangan 1 m² rangka langit-langit 60x60 kayu kelas III m² 136,378.00
4.6.1.20
4.6.1.21 Pek listplank 3x20 kayu kelas IV 4.6.1.21 Pemasangan 1 m' listplank 3x20 kayu kelas IV m' 72,495.50
4.6.1.21.a Pek listplank bahan kalsiplank 4.6.1.21.a Pemasangan 1 m' listplank bahan kalsiplank m' 71,582.50
4.6.1.22 Pek listplank 3/30 kayu kelas II 4.6.1.22 Pemasangan 1 m' listplank 3/30 kayu kelas II m' 103,361.50
Pek rangka dinding pemisah kayu kelas III 4.6.1.23 Pemasangan 1 m² rangka dinding pemisah kayu kelas III m² 188,050.50
4.6.1.23

Pek dinding pemisah teakwood double kayu kelas II 4.6.1.24 Pemasangan 1 m² dinding pemisah teakwood double kayu m² 295,300.50
4.6.1.24
kelas II
Pek dinding pemisah plywood rangkap kayu kelas II 4.6.1.25 Pemasangan 1 m² dinding pemisah plywood rangkap kayu m² 353,595.00
4.6.1.25
kelas II
Pek dinding lambrisering kayu kelas II 4.6.1.26 Pemasangan 1 m² dinding lambrisering kayu kelas II m² 461,560.00
4.6.1.26

Pek dinding lambrisering dari plywood 4.6.1.27 Pemasangan 1 m² dinding lambrisering dari plywood m² 82,428.50
4.6.1.27
Pek dinding bilik rangka kayu kelas III 4.6.1.28 Pemasangan 1 m² dinding bilik rangka kayu kelas III m² 120,465.95
4.6.1.28

4.6.2 PEKERJAAN KUNCI & KACA


PEKERJAAN KUNCI & KACA
4.6.2.1 Pek kunci tanam antik 4.6.2.1 Pemasangan 1 buah kunci tanam antik buah 317,080.50
4.6.2.2 Pek kunci tanam biasa 4.6.2.2 Pemasangan 1 buah kunci tanam biasa buah 264,962.50
4.6.2.2.a Pek kunci tanam stainless 4.6.2.2.a Pemasangan 1 buah kunci tanam stainless buah 548,762.50
4.6.2.2.b Pek kunci+handle 4.6.2.2.b Pemasangan 1 buah kunci+handle buah 407,962.50
4.6.2.3 Pek kunci tanam kamar mandi 4.6.2.3 Pemasangan 1 buah kunci tanam kamar mandi buah 241,895.50
4.6.2.4 Pek kunci tanam silinder 4.6.2.4 Pemasangan 1 buah kunci tanam silinder buah 285,895.50
4.6.2.5 Pek engsel pintu 4.6.2.5 Pemasangan 1 buah engsel pintu buah 69,745.50
4.6.2.6 Pek engsel jendela kupu-kupu 4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu buah 48,446.75
4.6.2.7 Pek engsel angin 4.6.2.7 Pemasangan 1 buah engsel angin buah 73,251.75
4.6.2.8 Pek spring knip 4.6.2.8 Pemasangan 1 buah spring knip buah 59,845.50
4.6.2.9 Pek kait angin 4.6.2.9 Pemasangan 1 buah kait angin buah 58,745.50
4.6.2.10 Pek door closer 4.6.2.10 Pemasangan 1 buah door closer buah 649,335.50
4.6.2.11 Pek slot 4.6.2.11 Pemasangan 1 buah slot buah 96,893.50
4.6.2.12 Pek door holder 4.6.2.12 Pemasangan 1 buah door holder buah 225,835.50
4.6.2.13 Pek door stop 4.6.2.13 Pemasangan 1 buah door stop buah 163,762.50
4.6.2.13.a Pek door handle 4.6.2.13.a Pemasangan 1 buah door handle buah 566,835.50
4.6.2.14 Pek rel pintu dorong 4.6.2.14 Pemasangan 1 buah rel pintu dorong buah 834,080.50
4.6.2.15 Pek kunci lemari 4.6.2.15 Pemasangan 1 buah kunci lemari buah 67,227.05
4.6.2.16 Pek kaca polos tebal 3 mm 4.6.2.16 Pemasangan 1 m2 kaca polos tebal 3 mm m² 167,555.30
4.6.2.17 Pek kaca polos tebal 5 mm 4.6.2.17 Pemasangan 1 m2 kaca polos tebal 5 mm m² 215,955.30
4.6.2.18 Pek kaca polos tebal 8 mm 4.6.2.18 Pemasangan 1 m2 kaca polos tebal 8 mm m² 463,794.65
4.6.2.19 Pek kaca polos tebal 12 mm 4.6.2.19 Pemasangan 1 m kaca polos tebal 12 mm
2
m² 691,422.05
4.6.2.19.a Pek kaca buram tebal 12 mm 4.6.2.19.a Pemasangan 1 m2 kaca buram tebal 12 mm m² 1,508,172.05
4.6.2.20 Pek kaca cermin tebal 5 mm 4.6.2.20 Pemasangan 1 m2 kaca cermin tebal 5 mm m² 297,445.50
4.6.2.21 Pek kaca cermin tebal 8 mm 4.6.2.21 Pemasangan 1 m2 kaca cermin tebal 8 mm m² 1,148,598.00
Pek kaca “Wiremesh glass ” tebal 5 mm 4.6.2.22 Pemasangan 1 m2 kaca “Wiremesh glass ” tebal 5 mm m² 242,995.50
4.6.2.22

4.6.2.23 Pek kaca patri tebal 5 mm 4.6.2.23 Pemasangan 1 m2 kaca patri tebal 5 mm m² 2,278,501.50
4.7.1 PEKERJAAN PENGECATAN
PEKERJAAN PENGECATAN

4.7.1.1 m² 22,610.50
4.7.1.1
Pengikisan/pengerokan permukaan cat tembok lama Pengikisan/pengerokan 1 m2 permukaan cat tembok lama
4.7.1.2 Pencucianpermukaan dinding lama 4.7.1.2 Pencucian 1 m2 permukaan dinding lama m² 21,400.50
Pengerokan karat atau cat lama permukaan baja 4.7.1.3 Pengerokan 1 m2 karat atau cat lama permukaan baja m² 22,418.00
4.7.1.3

Pengecatan bidang kayu baru 1 lapis cat dasar 2 lapis penutup 4.7.1.4 Pengecatan 1 m² bidang kayu baru 1 lapis cat dasar 2 lapis m² 45,743.50
4.7.1.4
penutup
Pengecatan bidang kayu baru, 1 lapis cat dasar, 3 lapis penutup 4.7.1.5 Pengecatan 1 m² bidang kayu baru, 1 lapis cat dasar, 3 lapis m² 66,544.50
4.7.1.5
penutup
4.7.1.6 Pelaburan bidang kayu dgn teak oil 4.7.1.6 Pelaburan 1 m² bidang kayu dgn teak oil m² 50,193.00
4.7.1.7 Pelaburan bidang kayu dengan politur 4.7.1.7 Pelaburan 1 m2 bidang kayu dengan politur m² 69,430.90
4.7.1.8 Pelaburan bidang kayu dengan residu atau ter 4.7.1.8 Pelaburan 1 m bidang kayu dengan residu atau ter
2
m² 16,346.00
4.7.1.9 Pelaburan dengan vernis 4.7.1.9 Pelaburan 1 m2 bidang kayu dengan vernis m² 57,920.50
4.7.1.10 Pengecatan plafond 4.7.1.10 Pengecatan 1 m plafond
2
m² 29,202.25
4.7.1.10.a Pengecatan tembok baru ( Interior ) 4.7.1.10.a Pengecatan 1 m tembok baru ( Interior )
2
m² 30,346.25
4.7.1.10.b Pengecatan 1 m2 tembok baru ( Eksterior ) 4.7.1.10.b Pengecatan 1 m2 tembok baru ( Eksterior ) m² 48,650.25
4.7.1.11 Pengecatan tembok lama 4.7.1.11 Pengecatan 1 m tembok lama
2
m² 23,265.00
4.7.1.12 Pelaburan tembok dengan kalkarium 4.7.1.12 Pelaburan 1 m tembok dengan kalkarium
2
m² 13,310.00
4.7.1.13 Pelaburan tembok baru dengan kapur 4.7.1.13 Pelaburan 1 m2 tembok baru dengan kapur m² 24,013.00
4.7.1.14 Pelaburan tembok lama dengan kapur 4.7.1.14 Pelaburan 1 m tembok lama dengan kapur
2
m² 12,100.00
4.7.1.15 Pemasangan wallpaper 4.7.1.15 Pemasangan 1 m² wallpaper m² 168,038.75
Pengecatan permukaan baja dengan menie besi 4.7.1.16 Pengecatan 1 m2 permukaan baja dengan menie besi m² 43,848.75
4.7.1.16

Pengecatan permukaan baja dengan menie besi dengan perancah 4.7.1.17 Pengecatan 1 m2 permukaan baja dengan menie besi dengan m² 83,660.50
4.7.1.17 perancah
Pengecatan permukaan baja galvanis cara manual 4 lapis 4.7.1.18 Pengecatan 1 m2 permukaan baja galvanis cara manual 4 lapis m² 92,505.05
4.7.1.18

Pengecatan permukaan baja galvanis cara manual 1 lapis cat 4.7.1.19 Pengecatan 1 m2 permukaan baja galvanis cara manual 1 lapis m² 40,958.50
4.7.1.19 mutakhir cat mutakhir
Pengecatan permukaan baja galvanis cara manual 3 lapis 4.7.1.20 Pengecatan 1 m2 permukaan baja galvanis cara manual 3 lapis m² 227,920.00
4.7.1.20

Pengecatan permukaan baja galvanis cara semprot 3 lapis cat 4.7.1.21 Pengecatan 1 m2 permukaan baja galvanis cara semprot 3 lapis m² 205,953.00
4.7.1.21 mutakhir cat mutakhir
4.7.1.22 Plituran 10 m2 dengan plitur melamic 4.7.1.22 Plituran 10 m2 dengan plitur melamic m² 3,009,930.00
No. Mata Pembayaran Harga Satuan Pekerjaan (Rp)
DIVISI No. Mata Pembayaran Uraian Satuan

a b b c d e

5.1.1 PEKERJAAN SANITASI GEDUNG


PEKERJAAN SANITASI GEDUNG
5.1.1.1 Pek closet duduk/monoblock 5.1.1.1 Pemasangan 1 buah closet duduk/monoblock buah 3,158,485.00
5.1.1.2 Pek closet jongkok porslen 5.1.1.2 Pemasangan 1 buah closet jongkok porslen buah 713,856.00
5.1.1.3 Pek closet jongkok teraso 5.1.1.3 Pemasangan 1 buah closet jongkok teraso buah 559,515.00
5.1.1.4 Pek urinoir 5.1.1.4 Pemasangan 1 buah urinoir buah 3,266,846.00
5.1.1.5 Pek wastafel 5.1.1.5 Pemasangan 1 buah wastafel buah 1,536,656.00
5.1.1.6 Pek batchcuip porselen 5.1.1.6 Pemasangan 1 buah batchcuip porselen buah 6,748,698.00
Pek bak mandi fiberglass vol 0,30 m3 5.1.1.7 Pemasangan 1 buah bak mandi fiberglass vol 0,30 m3 buah 2,138,235.00
5.1.1.7

Pek bak mandi pas. batu bata vol 0,30 m3 5.1.1.8 Pemasangan 1 buah bak mandi pas. batu bata vol 0,30 m3 buah 3,538,425.00
5.1.1.8

5.1.1.9 Pek bak mandi teraso vol 0,30 m 3


5.1.1.9 Pemasangan 1 buah bak mandi teraso vol 0,30 m3 buah 2,138,235.00
Pek bak/penampung air fiberglass vol 1 m3 5.1.1.10 Pemasangan 1 buah bak/penampung air fiberglass vol 1 m3 buah 1,751,805.00
5.1.1.10

5.1.1.11 Pek bak air beton vol 1 m3 5.1.1.11 Pemasangan 1 buah bak air beton vol 1 m3 buah 9,138,102.60
5.1.1.12 Pek bak cuci piring stainles steel 5.1.1.12 Pemasangan 1 buah bak cuci piring stainles steel buah 722,287.50
5.1.1.13 Pek bak cuci piring teraso 5.1.1.13 Pemasangan 1 buah bak cuci piring teraso buah 795,657.50
5.1.1.14 Pek floor drain stainless steel 5.1.1.14 Pemasangan 1 buah floor drain stainless steel buah 323,262.50
5.1.1.14.a Pek floor drain plastik 5.1.1.14.a Pemasangan 1 buah floor drain plastik buah 59,262.50
Pek bak kontrol pasangan bata 30x30 5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 buah 581,377.50
5.1.1.15
Pek bak kontrol pasangan bata 45x45 5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45x45 buah 845,245.50
5.1.1.16
Pek bak kontrol pasangan bata 60x60 5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60x60 buah 981,854.50
5.1.1.17
5.1.1.18 Pek pipa galvanis Ø 1/2" 5.1.1.18 Pemasangan 1 m pipa galvanis Ø 1/2" m' 74,059.31
5.1.1.19 Pek kran Ø 3/4" atau 1/2" 5.1.1.19 Pemasangan 1 buah kran Ø 3/4" atau 1/2" buah 125,633.75
5.1.1.20 Pek pipa galvanis Ø 3/4" 5.1.1.20 Pemasangan 1 m pipa galvanis Ø 3/4" m' 83,758.13
5.1.1.21 Pek pipa galvanis Ø 1" 5.1.1.21 Pemasangan 1 m pipa galvanis Ø 1" m' 111,641.14
5.1.1.22 Pek pipa galvanis Ø 11/2" 5.1.1.22 Pemasangan 1 m pipa galvanis Ø 11/2" m' 175,729.13
5.1.1.23 Pek pipa galvanis Ø 3" 5.1.1.23 Pemasangan 1 m pipa galvanis Ø 3" m' 339,624.57
5.1.1.24 Pek pipa galvanis Ø 4" 5.1.1.24 Pemasangan 1 m pipa galvanis Ø 4" m' 466,915.02
5.1.1.25 Pek pipa PVC tipe AW Ø 1/2" 5.1.1.25 Pemasangan 1 m pipa PVC tipe AW Ø 1/2" m' 25,669.88
5.1.1.26 Pek pipa PVC tipe AW Ø 3/4" 5.1.1.26 Pemasangan 1 m pipa PVC tipe AW Ø 3/4" m' 28,943.06
5.1.1.27 Pek pipa PVC tipe AW Ø 1" 5.1.1.27 Pemasangan 1 m pipa PVC tipe AW Ø 1" m' 33,671.00
5.1.1.28 Pek pipa PVC tipe AW Ø 11/2" 5.1.1.28 Pemasangan 1 m pipa PVC tipe AW Ø 11/2" m' 50,506.50
5.1.1.29 Pek pipa PVC tipe AW Ø 2" 5.1.1.29 Pemasangan 1 m pipa PVC tipe AW Ø 2" m' 62,508.19
5.1.1.30 Pek pipa PVC tipe AW Ø 21/2" 5.1.1.30 Pemasangan 1 m pipa PVC tipe AW Ø 21/2" m' 85,477.56
5.1.1.31 Pek pipa PVC tipe AW Ø 3" 5.1.1.31 Pemasangan 1 m pipa PVC tipe AW Ø 3" m' 114,572.56
5.1.1.32 Pek pipa PVC tipe AW Ø 4" 5.1.1.32 Pemasangan 1 m pipa PVC tipe AW Ø 4" m' 165,852.50
Pek pipa tanah Ø 20cm untuk air limbah 5.1.1.33 Pemasangan 1 m pipa tanah Ø 20cm untuk air limbah m' 381,971.92
5.1.1.33
Pek pipa tanah Ø 15cm untuk air limbah 5.1.1.34 Pemasangan 1 m pipa tanah Ø 15cm untuk air limbah m' 223,053.60
5.1.1.34
5.1.1.35 Pek pipa beton Ø 15-20cm 5.1.1.35 Pemasangan 1 m pipa beton Ø 15-20cm m' 359,548.42
5.1.1.36 Pek pipa beton Ø 30-100cm 5.1.1.36 Pemasangan 1 m pipa beton Ø 30-100cm m' 719,078.80

Taksir PEKERJAAN LAIN - LAIN


PEKERJAAN LAIN - LAIN
Taksir 1 titik nyala stop kontak Taksir 1 Pemasangan titik nyala stop kontak titik 314,366.25
Taksir 2 titik nyala saklar Taksir 2 Pemasangan titik nyala saklar titik 314,366.25
Taksir 3 titik nyala lampu Taksir 3 Pemasangan titik nyala lampu titik 281,366.25
Taksir 4 Pek stop kontak Taksir 4 Pemasangan 1 buah stop kontak buah 53,797.70
Taksir 5 Pek saklar tunggal Taksir 5 Pemasangan 1 buah saklar tunggal buah 46,097.70
Taksir 6 Pek saklar ganda Taksir 6 Pemasangan 1 buah saklar ganda buah 57,097.70
Taksir 7 Pek exhaust fan Taksir 7 Pemasangan 1 buah exhaust fan buah 459,442.50
Taksir 8 Pek pintu KM/WC Taksir 8 Pemasangan 1 buah pintu KM/WC PVC buah 938,591.50
Pek pintu KM/WC aluminium warna lengkap - ice glass Taksir 9 Pemasangan 1 bh pintu KM/WC aluminium warna lengkap buah 3,963,591.50
Taksir 9 (kusen, kunci engsel setara dekson) - ice glass

Pek aluminium composite panel (ACP) + rangka besi hollow Taksir 10 Pemasangan 1 m² aluminium composite panel (ACP) + rangka m² 821,117.66
Taksir 10 galvanis modul 60 x 60 cm besi hollow galvanis modul 60 x 60 cm

Taksir 11 Pek plafond PVC Taksir 11 Pemasangan 1 m² plafond PVC m² 187,440.00


Taksir 12 Pek list plafond PVC Taksir 12 Pemasangan 1 m' list plafond PVC m' 42,988.00
Pek atap bitumen bergelombang monolayer 3 mm (uk. Taksir 13 Pemasangan 1 m² atap bitumen bergelombang monolayer 3 mm m² 182,855.64
200x95x0,3cm) kemiringan atap min 15°, (uk. 200x95x0,3cm) kemiringan atap min 15°,
Taksir 13 jarak rangka gording maksimal 45 cm jarak rangka gording maksimal 45 cm

Pek genteng bitumen bergelombang monolayer 3 mm (uk. Taksir 14 Pemasangan 1 m² genteng bitumen bergelombang monolayer 3 m² 179,160.30
Taksir 14 200x97x0,3cm) kemiringan atap > 10°, jarak rangka gording mm (uk. 200x97x0,3cm) kemiringan atap > 10°, jarak rangka
maksimal 45 cm gording maksimal 45 cm
Pek genteng bitumen bergelombang monolayer 3 mm (uk. Taksir 15 Pemasangan 1 m² genteng bitumen bergelombang monolayer 3 m² 288,524.28
106x40x0,3 cm), kemiringan atap > 15º mm (uk. 106x40x0,3 cm), kemiringan atap > 15º
Taksir 15 jarak gording maksimal 32 cm jarak gording maksimal 32 cm

Taksir 16 Pek nok bitumen Taksir 16 Pemasangan 1 m' nok bitumen m' 174,773.50
Taksir 17 Pegecatan cat pelapis anti bocor Taksir 17 Pegecatan 1 m² cat pelapis anti bocor m² 42,850.50
Pek membran bitumen pelapis anti bocor sistem bakar Taksir 18 Pemasangan 1 m² membran bitumen pelapis anti bocor sistem m² 228,153.75
Taksir 18
bakar
Taksir 19 Pek plastik untuk cor jalan beton Taksir 19 Pemasangan 1 m² plastik untuk cor jalan beton m² 5,013.25
Pemasangan 100 m² karung goni basah untuk curing beton Taksir 20 Pemasangan 100 m² karung goni basah untuk curing beton m² 1,441,880.00
Taksir 20
Menyirami 100 m² karung goni dengan air selama 4 hari Taksir 21 Menyirami 100 m² karung goni dengan air selama 4 hari m² 1,076,350.00
Taksir 21
Taksir 22 Pek geotekstil untuk timbunan Taksir 22 Pemasangan 1 m² geotekstil untuk timbunan m² 43,945.00
Pek cerucup gelam untuk pondasi (p. 1,5m - 20 cm) Taksir 23 Pemasangan 1 m² cerucup gelam untuk pondasi (p. 1,5m - 20 m² 144,375.00
Taksir 23
cm)
Taksir PEKERJAAN LAIN - PEKERJAAN LAIN - LAIN
LAIN
1 Pemasangan scafolding (sewa) 1 Pemasangan 1 unit scafolding (sewa) unit 88,335.50
Pek pondasi beton bertulang (150 kg besi + Membuat 1 m3 pondasi beton bertulang (150 kg m³ 5,037,048.50
2 2
bekesting) besi + bekesting)
Pek sloof beton bertulang (200 kg besi + Membuat 1 m3 sloof beton bertulang (200 kg m³ 5,617,590.00
3 3
bekesting) besi + bekesting)
Pek kolom beton bertulang (300 kg besi + Membuat 1 m3 kolom beton bertulang (300 kg m³ 9,307,089.00
4 4
bekesting) besi + bekesting)
Pek balok beton bertulang (200 kg besi + Membuat 1 m3 balok beton bertulang (200 kg m³ 7,398,286.50
5 5
bekesting) besi + bekesting)
Pek kolom beton bertulang (150 kg besi + Membuat 1 m3 kolom beton bertulang (150 kg m³ 5,936,260.00
6 6
bekesting) besi + bekesting)
Pek dinding beton bertulang (150 kg besi + Membuat 1 m3 dinding beton bertulang (150 kg m³ 5,895,735.00
7 7
bekesting) besi + bekesting)
Pek dinding beton bertulang (200 kg besi + Membuat 1 m3 dinding beton bertulang (200 kg m³ 6,523,690.00
8 8
bekesting) besi + bekesting)
9 Bongkaran partisi m2 11,000.00
10 Pemasangan partisi kalsi board+ rangka m2 272,600.90
Pengecatan tembok baru untuk Interior setara m2 45,438.25
11
jotun
Pengecatan tembok baru untuk Exterior setara m2 49,728.25
12
jotun
13 Pengecatan tembok lama setara jotun m2 32,835.00
Pengecatan tembok lama untuk eksterior setara m2 35,805.00
14
jotun
15 Pemasangan keramik 20 x 25 m2 297,250.80
16 Pemasangan Waterproofing Sika m2 118,360.00
17 Bongkar pasang kloset Ls 220,000.00
18 Injeksi titik 100,000.00
19 Bongkaran atap m2 11,000.00
20 Bongkaran atap baja ringan + atap m2 21,300.00
21 Bongkaran plafon m2 11,275.00
22 Pengadaan dan instalasi lampu DL LED titik 341,880.00
23 Instalasi dan pemasangan sakelar tunggal titik 341,021.45
24 Instalasi dan pemasangan sakelar ganda titik 352,021.45
25 Pembongkaran keramik + plesteran m³ 947,809.50
m2 179,294.50
26 Pemasangan 1m' pipa PVC tipe AW diameter 5''
27 Pemasangan trali besi costum fabrikasi m2 541,425.50
Pemasangan 1 buah closed duduk (setara TOTO, bh 4,700,740.00
28
CW421J)
29 Pemasangan keramik 25x25 m2 326,650.50
Unit 4,884,568.17
Pembuatan dan Pemasangan Jendela Kaca
30
Rangka Alumunium uk. 1,6 x 1,4 m + Aksesoris

Unit 2,997,316.48
Pembuatan dan Pemasangan Jendela Kaca
31
Rangka Alumunium uk. 1,4 x 0,8 m + Aksesoris

Pembuatan dan Pemasangan Jendela Kaca Daun Unit 5,517,622.69


32 Rangka Alumunium uk. 1,75 x 1,5 m + Kusen
dan Aksesoris
33 Pemasangan sandblast m2 88,000.00
Pembuatan dan Pemasangan Pintu Unit 6,095,122.69
34 Geser Rangka Alumunium uk. 1,75 x 1,5
m + Aksesoris
35 Bongkar pasang membran lama m2 55,000.00
36 Pemasangan 1 m2 acian mortar m2 71,885.00
37 Plamiran m2 16,007.50
Pemasangan pintu sliding alumunium kaca unit 4,584,704.95
38
+sanblast
39 Pemasangan engsel casement Bh 184,846.75
40 Pemasangan Rambuncis Bh 96,893.50
Pembuatan dan Pemasangan Pintu Kaca 1 Daun unit 5,023,822.07
41 Rangka Alumunium uk. 0,9 x 2,1 m + Kusen +
Sunblast + Aksesoris
Pemasangan 1 m2 rangka dinding partisi + m2 237,162.05
42
Gypsum Board 9 mm (1 Sisi)
m2 329,012.05
Pemasangan 1 m2 rangka Baja Ringan C.75.75
43
dinding partisi + Gypsum Board 9 mm (2 Sisi)

Pemasangan 1m2 partisi rangka baja ringan + m2 329,012.05


43
dinding kalsiboard (2sisi)
Pemasangan 1m2 rangka dinding partisi + m2 237,162.05
41
kalsiboard (1 sisi)
Pemasangan 1 m2 rangka besi hollow m2 326,535.00
44 1x40.40.2mm, modul 60 x 120cm, dinding
partisi + Gypsum Board 9 mm (2 Sisi)
45 waterproofing aquatite m2 211,860.00
46 Pemasangan urinoir setara TOTO Unit 4,993,846.00
47 Pemasangan urinar partition setara TOTO Unit 1,980,000.00
Pembuatan dan Pemasangan Jendela Kaca Daun unit 4,152,112.58
48 Rangka Alumunium uk. 1,2 x 1,5 m + Kusen +
Aksesoris
49 Pemasangan lampu LED 24 Watt bh 165,000.00
Pemasangan Aksesoris SPOEL HOEK / SLOP bh 5,758,005.00
50
SINK
51 Pemasangan tanki air 550 liter dan instalasi bh 1,400,575.00
52 Pemasangan trali besi m2 874,152.40
53 Pemasangan Pintu alumunium wc bh 2,299,335.50
Bh 3,655,201.00
54 Pemasangan 1 buah closet duduk Setara TOTO
Pemasangan 1 buah Eco-Washer (soft closing Bh 1,726,133.75
55
TOTO TCW07S)
56 Pemasangan 1 buah Shower Spray Bh 339,033.75
57 Pemasangan Wastafel TOTO Bh 2,045,835.00
58 Pemasangan 1 buah Tee Stainless Bh 274,133.75
59 Perbaikan dinding retak m2 57,200.00
60 Pemasangan Karpet Vinyl m2 658,548.00
61 Pek Pasang Kusen + Jendela 5,716,100.00
62 Membuat sloof beton bertulang m3 5,030,949.00
63 Pemasangan 1 m2 lantai keramik ukuran 25cm x 25cm m2 270,627.50
64 Pemasangan 1m2 Dinding Keramik Ukuran (25 x 40 cm) m2 316,812.10
65 Pembuatan dan Pemasangan Pintu Kaca Rangka Alumunium 1 Daun uk. 1 x 2,15 m + Kusen + Engsel + Aksesoris unit 4,342,200.64
unit 938,591.50
66 Pemasangan 1 buah pintu KM/WC bahan PVC
67 Pengadaan dan Instalasi pintu koboi unit 3,780,323.21
68 Membuat 1 m3 plat beton bertulang m3 5,343,508.50
unit 3,705,328.00
69 Pemasangan grill stainless steel tutup saluran
70 Pengadaan dan Instalasi Pintu ACP uk. 1.2 x 2.75 (P1) unit 5,801,131.93
71 Pengadaan dan Instalasi Pintu ACP uk. 1.5 x 2.75 (P3) unit 7,217,470.91
72 Pengadaan dan Instalasi Pintu ACP uk. 1.75 x 2.75 (P2) unit 7,741,854.55
73 Pengadaan dan Instalasi Pintu ACP uk. 0.95 x 2.75 (P4) unit 5,276,748.28
74 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.8 x 1.5 (J1) unit 2,237,589.42
75 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 1.5 (J3) unit 3,918,291.22
76 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 0.75 (J2) unit 3,109,467.53
77 Pengadaan dan Instalasi Bouven uk. 0.85 x 0.75 (J5) unit 768,185.73
78 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.9 x 1.5 (J4) unit 2,333,829.00
79 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.9 x 0.75 (J6) unit 1,662,737.74
80 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.8 x 0.75 (J7) unit 1,574,949.09
Pemasangan 1 bh pintu aluminium warna bh 3,083,591.50
81
lengkap - ice glass
82 Pemasangan 1 bh pintu Alumunium ACP bh 3,083,591.50
83 Pemasangan 1 buah exhaust fan 16'' bh 1,100,000.00
84 Pemasangan 1 buah exhaust fan 12'' bh 693,000.00
85 Pemasangan 1 buah exhaust fan 10'' bh 665,500.00
86 Pintu Aluminium Kaca Double unit 7,188,306.11
87 Pemasangan 1 buah wastafel TOTO Bh 2,927,826.00
88 Pemasangan keramik dinding 30 x60 m2 337,260.00
89 Pengecatan dengan cat minyak m2 43,848.75
90 Pemasangan urinoir unit 2,506,966.00
91 Pembuatan 1 m2 Partisi Kaca Alumunium m2 851,925.14
92 Pemasangan 1 roll pipa flexible 4" roll 756,800.00
93 Pengadaan dan instalasi pintu kaca alumunium uk. 0,8 x 2,15 (p1) Unit 4,051,173.50
94 Pengadaan dan instalasi pintu kaca alumunium uk. 0,9 x 2,15 (P1) Unit 4,333,522.88
95 Pengadaan dan Instalasi Sakelar Ganda titik 229,440.20
96 Pemasangan 1 buah Spoelhoek Unit 9,746,385.00
97 Pemasangan 1m2 Keramik Ukuran (25 x 40 cm) m2 308,892.10
98 Pemasangan 1 m² rooster keramik 20x40 m2 972,274.60
99 Pengadaan dan Instalasi Sakelar Tunggal titik 217,271.45
100 Pengadaan dan Instalasi Stop Kontak titik 226,016.45
101 Membuat 1 m3 plat beton bertulang (150 kg besi + bekesting) m3 5,343,508.50
102 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 2 x 2.7 (P3) Unit 10,225,140.31
103 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 1.00 x 2.15 (P4) Unit 4,342,200.64
104 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 0.8 x 2.15 (P1) Unit 4,064,123.21
105 Pemasangan kran diameter dan shower unit 385,233.75
106 Pemasangan 1 m2 dinding keramik ukuran 25cm x 20cm m2 291,542.90
Pembuatan dan Pemasangan Pintu ACP 2 Unit 7,003,720.28
107
Daun
108 Pengadaan dan Instalasi Pintu ACP uk. 1.5 x 2.75 Unit 7,217,470.91
109 Pengadaan Dan Instalasi Pintu ACP uk. 1,75 x 2,10 Unit 7,555,729.95
110 Pengadaan Dan Instalasi Pintu ACP uk. 1,40 x 2,35 Unit 6,564,987.32
111 Pengadaan Dan Instalasi Pintu ACP uk. 1,30 x 2,35 Unit 6,255,403.28
112 Pengadaan Dan Instalasi Jendela Kaca Alumunium uk. 0,80 x 0,75 unit 1,586,202.09
113 Pengadaan Dan Instalasi Jendela Kaca Alumunium uk. 0,90 x 0,75 unit 1,674,716.74
114 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 0.75 (J2) unit 3,130,884.53
115 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 1.5 (J3) unit 3,945,153.22
116 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.8 x 1.5 (J1) unit 2,254,287.42
117 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.9 x 1.5 (J4) unit 2,351,253.00
118 Pengadaan dan Instalasi Bouven uk. 0.85 x 0.75 (J5) unit 779,801.73
119 Pemasangan 1 m2 lantai granit kasar ukuran 60 x 60 m2 395,318.44
120 Pekerjaan membran bakar m2 200,000.00
121 Pengadaan dan Instalasi Pintu uk. 1.5 x 2.15 (P1) Unit 7,881,294.07
122 Pengadaan dan Instalasi Pintu uk. 1.35 x 2.15 (P1) Unit 7,543,252.24
123 Pengadaan dan Instalasi Pintu uk. 0.8 x 2.15 (P1) Unit 4,052,441.21
124 pemasangan bouven Unit 437,321.71
125 Pengadaan dan instalasi lampu TL +Aksesoris titik 505,711.25
126 Pemasangan Shower Spray bh 235,633.75
127 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 1.1 x 2 unit 4,342,200.64
128 Pembuatan dan Pemasangan Pintu alumunium kaca 1,9 x 0,77 unit 4,625,720.00
129 Pembuatan dan Pemasangan Jendela Kaca 0,9 x 1,23 Unit 2,128,603.40
130 Pembuatan dan Pemasangan Jendela Kaca 1,23 x 1,48 Unit 3,476,990.00
131 Pembuatan dan Pemasangan Jendela Kaca 1,23 x 2,38 Unit 4,440,810.00
132 Pembuatan dan Pemasangan Jendela Kaca 1 x 0,55 Unit 1,555,994.00
133 Pemasangan plat stainless m2 763,495.00
134 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 0.7 x 2.1 (P1) unit 3,802,838.83
135 Pengadaan dan Instalasi Pintu ACP Uk. 0.7 x 2.1 + rel unit 4,390,133.86
136 Pengadaan Dan Instalasi Pintu ACP uk. 1,6 x 2,1 unit 6,564,987.32
137 Pemasangan kran sensor Bh 2,627,966.00
138 Pemasangan 1 m’ pipa PPR 1/2 Inch m 161,689.00
139 Pemasangan 1 m’ pipa PPR 3/4 Inch m 234,426.50
140 Pasangan cermin m2 275,000.00
141 Pemasangan 1 m2 terali besi m2 747,956.57
142 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium Uk 1 x 1.2 m2 2,917,926.00
143 Pemasangan kawat Harmonika m2 64,614.00
144 Pemasangan 1 m2 ragka kanopi baja ringan m2 168,715.50
145 Pemasangan 1 m2 atap PVC Fiberglass m2 118,260.00
146 Pemesangan BV Uk 2 x 0,3 Unit 1,173,172.99
147 Pemesangan BV Uk 0,7 x 0,3 Unit 495,949.80
148 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,2 x 1,5 m + Kusen + Engsel + Aksesoris unit 3,658,347.00
149 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0,6 x 1,2 m + Engsel + Aksesoris unit 1,939,663.00
150 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium Geser Daun uk. 0,7 x 0,7 m + Kusen + Aksesoris unit 2,144,793.41
151 Pembuatan 1 m2 Partisi Kaca 5mm + Sunblast m2 1,101,020.14
152 Pemasangan keramik ukuran 10cm x 20cm m2 141,094.14
1. Pemasangan 1 unit scafolding (sewa)

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.250 120,000 30,000.00
2 Tukang Batu (L.02) OH 0.017 150,000 2,550.00
3 Kepala Tukang (L.03) OH 0.0020 175,000 350.00
4 Mandor (L.04) OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 35,305.00
B. BAHAN
1 Pipa PVC 4” unit 1.00 45,000 45,000.00

JUMLAH HARGA BAHAN 45,000.00


C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 80,305.00


E. OVERHEAD & PROFIT 10,0 % x D 8,030.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 88,335.50

2 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekesting)


NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 5.3 120,000 636,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.3 150,000 195,000.00
4 Tukang Besi L.02 OH 1.05 150,000 157,500.00
5 Kepala Tukang L.03 OH 0.262 175,000 45,850.00
6 Mandor L.04 OH 0.265 185,000 49,025.00
JUMLAH HARGA TENAGA 1,124,625.00
B. BAHAN
1 Kayu m3 0.2 1,900,000 380,000.00
2 Paku 5-12 cm kg 1.5 22,000 33,000.00
3 Minyak bekesting Liter 0.4 11,000 4,400.00
4 Besi beton polos kg 157.5 13,900 2,189,250.00
5 Kawat beton kg 2.25 20,000 45,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
JUMLAH HARGA BAHAN 3,454,510.00
C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 4,579,135.00
E. OVERHEAD & PROFIT 10,0 % x D 457,913.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,037,048.50

3 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekesting)

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 5.65 120,000 678,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.56 150,000 234,000.00
4 Tukang Besi L.02 OH 1.4 150,000 210,000.00
5 Kepala Tukang L.03 OH 0.323 175,000 56,525.00
6 Mandor L.04 OH 0.283 185,000 52,355.00
JUMLAH HARGA TENAGA 1,272,130.00
B. BAHAN
1 Kayu m3 0.27 1,900,000 513,000.00
2 Paku 5-12 cm kg 2 22,000 44,000.00
3 Minyak bekesting Liter 0.6 11,000 6,600.00
4 Besi beton polos kg 210 13,900 2,919,000.00
5 Kawat beton kg 3 20,000 60,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
JUMLAH HARGA BAHAN 4,345,460.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,617,590.00


E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,617,590.00
4 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekesting)

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 5.65 120,000 678,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.56 150,000 234,000.00
4 Tukang Besi L.02 OH 1.4 150,000 210,000.00
5 Kepala Tukang L.03 OH 0.323 175,000 56,525.00
6 Mandor L.04 OH 0.283 185,000 52,355.00
JUMLAH HARGA TENAGA 1,272,130.00
B. BAHAN
1 Kayu m3 0.4 1,900,000 760,000.00
2 Paku 5-12 cm kg 4 22,000 88,000.00
3 Minyak bekesting Liter 2 11,000 22,000.00
4 Besi beton polos kg 315 13,900 4,378,500.00
5 Kawat beton kg 4.5 20,000 90,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
9 balok kayu m3 0.15 1,600,000 240,000.00
10 Plywood 9 mm Lbr 3.5 145000 507,500.00
11 Dolken Kayu Ø8-10cm p.4m Batang 20 15000 300,000.00
JUMLAH HARGA BAHAN 7,188,860.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 8,460,990.00


E. OVERHEAD & PROFIT 10,0 % x D 846,099.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 9,307,089.00

5 Membuat 1 m3 balok beton bertulang (200 kg besi + bekesting)

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 6.35 120,000 762,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.65 150,000 247,500.00
4 Tukang Besi L.02 OH 1.4 150,000 210,000.00
5 Kepala Tukang L.03 OH 0.333 175,000 58,275.00
6 Mandor L.04 OH 0.318 185,000 58,830.00
JUMLAH HARGA TENAGA 1,377,855.00

B. BAHAN
1 Kayu m3 0.32 1,900,000 608,000.00
2 Paku 5-12 cm kg 3.2 22,000 70,400.00
3 Minyak bekesting Liter 1.6 11,000 17,600.00
4 Besi beton polos kg 210 13,900 2,919,000.00
5 Kawat beton kg 3 20,000 60,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
9 balok kayu m3 0.14 1,600,000 224,000.00
10 Plywood 9 mm Lbr 2.8 145000 406,000.00
11 Dolken Kayu Ø8-10cm p.4m Batang 16 15000 240,000.00
JUMLAH HARGA BAHAN 5,347,860.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 6,725,715.00


E. OVERHEAD & PROFIT 10,0 % x D 672,571.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 7,398,286.50

6 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekesting)

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 5.3 120,000 636,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.3 150,000 195,000.00
4 Tukang Besi L.02 OH 1.05 150,000 157,500.00
5 Kepala Tukang L.03 OH 0.265 175,000 46,375.00
6 Mandor L.04 OH 0.265 185,000 49,025.00
JUMLAH HARGA TENAGA 1,125,150.00
B. BAHAN
1 Kayu m3 0.32 1,900,000 608,000.00
2 Paku 5-12 cm kg 3.2 22,000 70,400.00
3 Minyak bekesting Liter 1.6 11,000 17,600.00
4 Besi beton polos kg 157.5 13,900 2,189,250.00
5 Kawat beton kg 2.25 20,000 45,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
9 balok kayu m3 0.12 1,600,000 192,000.00
10 Plywood 9 mm Lbr 2.8 145,000 406,000.00
11 Dolken Kayu Ø8-10cm p.4m Batang 32 15,000 480,000.00
JUMLAH HARGA BAHAN 4,811,110.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,936,260.00


E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,936,260.00
7 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekesting)
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 5.3 120,000 636,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.3 150,000 195,000.00
4 Tukang Besi L.02 OH 1.05 150,000 157,500.00
5 Kepala Tukang L.03 OH 0.262 175,000 45,850.00
6 Mandor L.04 OH 0.265 185,000 49,025.00
JUMLAH HARGA TENAGA 1,124,625.00
B. BAHAN
1 Kayu m3 0.24 2,600,000 624,000.00
2 Paku 5-12 cm kg 3.2 22,000 70,400.00
3 Minyak bekesting Liter 1.6 11,000 17,600.00
4 Besi beton polos kg 157.5 13,900 2,189,250.00
5 Kawat beton kg 2.25 20,000 45,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
9 balok kayu m3 0.16 1,600,000 256,000.00
10 Plywood 9 mm Lbr 2.8 145,000 406,000.00
11 Dolken Kayu Ø8-10cm p.4m Batang 24 15,000 360,000.00
JUMLAH HARGA BAHAN 4,771,110.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,895,735.00


E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,895,735.00

8 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekesting)

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
w
A. TENAGA
1 Pekerja L.01 OH 5.65 120,000 678,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Tukang Kayu L.02 OH 1.56 150,000 234,000.00
4 Tukang Besi L.02 OH 1.4 150,000 210,000.00
5 Kepala Tukang L.03 OH 0.323 175,000 56,525.00
6 Mandor L.04 OH 0.283 185,000 52,355.00
JUMLAH HARGA TENAGA 1,272,130.00

B. BAHAN
1 Kayu m3 0.25 2,600,000 650,000.00
2 Paku 5-12 cm kg 3 22,000 66,000.00
3 Minyak bekesting Liter 1.2 11,000 13,200.00
4 Besi beton polos kg 210 13,900 2,919,000.00
5 Kawat beton kg 3 20,000 60,000.00
6 Sement Portland kg 336 1,160 389,760.00
7 Pasir Beton m3 0.54 135,000 72,900.00
8 Kerikil m3 0.81 420,000 340,200.00
9 balok kayu m3 0.105 1,600,000 168,000.00
10 Plywood 9 mm Lbr 2.5 145,000 362,500.00
11 Dolken Kayu Ø8-10cm p.4m Batang 14 15,000 210,000.00
JUMLAH HARGA BAHAN 5,251,560.00

C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 6,523,690.00


E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 6,523,690.00
Pemasangan partisi kalsi board+
10 rangka m2 Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.45 120,000 54,000
Tukang Kayu L.02 OH 0.35 150,000 52,500
Kepala Tukang L.03 OH 0.035 175,000 6,125
Mandor L.04 OH 0.023 185,000 4,255
JUMLAH TENAGA KERJA 116,880
B BAHAN
1 Rangka baja C75.75 kg 3 16333 48,999
2 baut (screw driver) bh 4 175 700
3 Dynabolt bh 1.6 1500 2,400
4 kalsi board lbr 0.728 55000 40,040
5 Compound kg 1 15500 15,500
6 Kain kasa roll 1.6 7000 11,200
7 Sekrup kg 0.22 55000 12,100

JUMLAH TENAGA BAHAN 130,939


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 247,819


E. Overhead & Profit 10% X D 24,782
F. Harga Satuan Pekerjaan (D+E) 272,601
Pengecatan tembok baru untuk Interior
11 setara jotun m2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.02 120,000 2,400
Tukang cat L.02 OH 0.063 150,000 9,450
Kepala Tukang L.03 OH 0.0063 175,000 1,103
Mandor L.04 OH 0.003 185,000 555
JUMLAH TENAGA KERJA 13,508
B BAHAN
Plamir L 0.1 25,000 2,500
Cat Dasar Kg 0.1 45,000 4,500

Cat Penutup (cat tembok interior ex= Jotun) L 0.26 80,000 20,800

JUMLAH TENAGA BAHAN 27,800


C. PERALATAN
-
JUMLAH TENAGA ALAT

D. Jumlah (A+B+C) 41,308


E. Overhead & Profit 10% X D 4,131
F. Harga Satuan Pekerjaan (D+E) 45,438.25

Pengecatan tembok baru untuk Exterior


12 setara jotun m2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.02 120,000 2,400
Tukang cat L.02 OH 0.063 150,000 9,450
Kepala Tukang L.03 OH 0.0063 175,000 1,103
Mandor L.04 OH 0.003 185,000 555
JUMLAH TENAGA KERJA 13,508
B BAHAN
Plamir L 0.1 25,000 2,500
Cat Dasar Kg 0.1 45,000 4,500

Cat Penutup (cat tembok Exterior ex= Jotun) L 0.26 95,000 24,700

JUMLAH TENAGA BAHAN 31,700


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 45,208


E. Overhead & Profit 10% X D 4,521
F. Harga Satuan Pekerjaan (D+E) 49,728.25

13 Pengecatan tembok lama setara jotun m2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 120,000 3,360
Tukang cat L.02 OH 0.042 150,000 6,300
Kepala Tukang L.03 OH 0.0042 175,000 735
Mandor L.04 OH 0.003 185,000 555
JUMLAH TENAGA KERJA 10,950
B BAHAN
Cat Dasar Kg 0.1 45,000 4,500

Cat Penutup (cat tembok interior ex= Jotun) L 0.18 80,000 14,400

JUMLAH TENAGA BAHAN 18,900


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 29,850


E. Overhead & Profit 10% X D 2,985
F. Harga Satuan Pekerjaan (D+E) 32,835.00

Pengecatan tembok lama untuk eksterior


14 setara jotun m2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 120,000 3,360
Tukang cat L.02 OH 0.042 150,000 6,300
Kepala Tukang L.03 OH 0.0042 175,000 735
Mandor L.04 OH 0.003 185,000 555
JUMLAH TENAGA KERJA 10,950
B BAHAN
Cat Dasar Kg 0.1 45,000 4,500

Cat Penutup (cat tembok interior ex= Jotun) L 0.18 95,000 17,100

JUMLAH TENAGA BAHAN 21,600


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 32,550


E. Overhead & Profit 10% X D 3,255
F. Harga Satuan Pekerjaan (D+E) 35,805.00
15 Pemasangan keramik 20 x 25 m2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.9 120,000 108,000
Tukang Besi L.02 OH 0.45 150,000 67,500
Kepala Tukang L.03 OH 0.045 175,000 7,875
Mandor L.04 OH 0.045 185,000 8,325
JUMLAH TENAGA KERJA 191,700
B BAHAN
keramik 20 x 25 doos 1 55,000 55,000
semen portland kg 9.3 1,160 10,788
pasir pasang m3 0.018 115,000 2,070
semen warna 1 kg 1.94 5,500 10,670

JUMLAH TENAGA BAHAN 78,528


C. PERALATAN
JUMLAH TENAGA ALAT

D. Jumlah (A+B+C) 270,228


E. Overhead & Profit 10% X D 27,023
F. Harga Satuan Pekerjaan (D+E) 297,250.80

16 Pemasangan Waterproofing Sika m2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.2 120,000 24,000
Tukang Batu L.02 OH 0.1 150,000 15,000
Kepala Tukang L.03 OH 0.01 175,000 1,750
Mandor L.04 OH 0.01 185,000 1,850

JUMLAH TENAGA KERJA 42,600


B BAHAN
Semen SIKA kg 3.25 20,000 65,000

JUMLAH TENAGA BAHAN 65,000


C. PERALATAN
-

JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 107,600


E. Overhead & Profit 10% X D 10,760
F. Harga Satuan Pekerjaan (D+E) 118,360

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir .23
20 JENIS PEKERJAAN Bongkaran atap baja ringan + atap
SATUAN PEMBAYARAN m2
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 0.1420 120,000 17,040.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 175,000 0.00
4 Mandor L.04 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 19,445.00
B. BAHAN
1 0.00
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 19,445.00
OVERHEAD & PROFIT 10,0 % x D 1,944.50
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 21,389.50
21,300.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir .23
21 JENIS PEKERJAAN Bongkaran plafon
SATUAN PEMBAYARAN m2
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 0.0700 120,000 8,400.00
2 Tukang L.02 150,000
3 Kepala Tukang L.03 175,000 0.00
4 Mandor L.04 0.01 185,000 1,850.00
JUMLAH HARGA TENAGA 10,250.00
B. BAHAN
1 0.00
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 10,250.00
OVERHEAD & PROFIT 10,0 % x D 1,025.00
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 11,275.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP) 0.005
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir .23
22 JENIS PEKERJAAN Pengadaan dan instalasi lampu DL LED
SATUAN PEMBAYARAN titik
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 120,000 0.00
2 Tukang L.02 0.14 150,000 21,000.00
3 Kepala Tukang L.03 0.0100 175,000 1,750.00
4 Mandor L.04 0.0100 185,000 1,850.00
JUMLAH HARGA TENAGA 24,600.00
B. BAHAN
1 Kabel NYM 2X2,5 mm2 m 7.5 13000 97,500.00
Pipa konduit PVC HI EGA DIA 20 MM m 12 2850 34,200.00
2
3 T-Dus PVC HI EGA Dia 20 mm bh 1 4500 4,500.00
Lampu DL LED 24 WATT PHILIPS DN020B bh 1.00 150,000 150,000.00
4
JUMLAH HARGA BAHAN 286,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 310,800.00
OVERHEAD & PROFIT 10,0 % x D 31,080.00
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 341,880.00

Taksir. 2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir
23 JENIS PEKERJAAN Instalasi dan pemasangan sakelar tunggal
SATUAN PEMBAYARAN titik
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 120,000
2 Tukang Listrik L.02 0.1350 150,000 20,250.00
3 Kepala Tukang L.03 0.0135 175,000 2,362.50
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 23,537.50
B. BAHAN
1 Kabel NYM 3 x 2,5 mm2 M' 15.00 15,000 225,000.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750 33,000.00
2
3 T-Dus PVC HI "EGA" Dia. 20mm Bh 1 4,250 4,250.00
4 Saklar Tunggal Bh 1.00 19,000 19,000.00
5 Inbow dus Bh 1.00 5,000 5,000.00
6 Semen Portland Kg 0.20 1,160 232.00
JUMLAH HARGA BAHAN 286,482.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 310,019.50
OVERHEAD & PROFIT 10,0 % x D 31,001.95
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 341,021.45

Taksir. 2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir
24 JENIS PEKERJAAN Instalasi dan pemasangan sakelar ganda
SATUAN PEMBAYARAN titik
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 120,000
2 Tukang Listrik L.02 0.1350 150,000 20,250.00
3 Kepala Tukang L.03 0.0135 175,000 2,362.50
4 Mandor L.04 0.0050 185,000 925.00
JUMLAH HARGA TENAGA 23,537.50
B. BAHAN
1 Kabel NYM 3 x 2,5 mm2 M' 15.00 15,000 225,000.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750 33,000.00
2
3 T-Dus PVC HI "EGA" Dia. 20mm Bh 1 4,250 4,250.00
4 Saklar ganda Bh 1.00 29,000 29,000.00
5 Inbow dus Bh 1.00 5,000 5,000.00
6 Semen Portland Kg 0.20 1,160 232.00
JUMLAH HARGA BAHAN 296,482.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 320,019.50
OVERHEAD & PROFIT 10,0 % x D 32,001.95
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 352,021.45
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.14
25 JENIS PEKERJAAN Pembongkaran keramik + plesteran
SATUAN PEMBAYARAN m³

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 6.667 120000.000 800040
2 Mandor L.04 OH 0.333 185000.000 61605
JUMLAH HARGA TENAGA 861645
B. BAHAN
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 861645
E. OVERHEAD & PROFIT (15%) 10 % x D 86164.5
F. HARGA SATUAN PEKERJAAN ( D + E ) 947809.5

PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum

Pemasangan 1m' pipa PVC tipe AW


26 diameter 5'' m2 Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.081 120,000 9,720
Tukang Kayu L.02 OH 0.135 150,000 20,250
Kepala Tukang L.03 OH 0.0135 175,000 2,363
Mandor L.04 OH 0.004 185,000 740
JUMLAH TENAGA KERJA 33,073
B BAHAN
1 Pipa pvc 5'' m 1.2 100000 120,000
2 perlengkapan % 0.35 28350 9,923
JUMLAH TENAGA BAHAN 129,923
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 162,995


E. Overhead & Profit 10% X D 16,300
F. Harga Satuan Pekerjaan (D+E) 179,295

Pemasangan trali besi costum fabrikasi


27 m2 Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.2 120,000 24,000
Tukang Kayu L.02 OH 0.2 150,000 30,000
Kepala Tukang L.03 OH 0.02 175,000 3,500
Mandor L.04 OH 0.001 185,000 185
JUMLAH TENAGA KERJA 57,685
B BAHAN
Besi 25 12,000 300,000
Pengelasan 40 3,363 134,520
JUMLAH TENAGA BAHAN 434,520
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 492,205


E. Overhead & Profit 10% X D 49,221
F. Harga Satuan Pekerjaan (D+E) 541,425.50

Pemasangan 1 buah closed duduk (setara


bh
28 TOTO, CW421J)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 3.3 120,000 396,000
Tukang batu L.02 OH 1.1 150,000 165,000
Kepala Tukang L.03 OH 0.01 175,000 1,750
Mandor L.04 OH 0.16 185,000 29,600

JUMLAH TENAGA KERJA 669,400


B BAHAN
Closed duduk ex. TOTO unit 1 3,400,000 3,400,000
Perlengkapan Ls 6%xclosed 204,000 204,000

JUMLAH TENAGA BAHAN 3,604,000


C. PERALATAN
-

JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,273,400


E. Overhead & Profit 10% X D 427,340
F. Harga Satuan Pekerjaan (D+E) 4,700,740

29 Pemasangan keramik 25x25 m2 Analisa TK2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.7 120,000 84,000
Tukang Kayu L.02 OH 0.35 150,000 52,500
Kepala Tukang L.03 OH 0.035 175,000 6,125
Mandor L.04 OH 0.035 185,000 6,475
JUMLAH TENAGA KERJA 149,100
B BAHAN
keramik 25x25 doos 1.05 116,000 121,800
semen pc kg 10.2 1,160 11,832
pasir pasang m3 0.045 115,000 5,175
semen warna kg 1.56 5,800 9,048
JUMLAH TENAGA BAHAN 147,855
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 296,955


E. Overhead & Profit 10% X D 29,696
F. Harga Satuan Pekerjaan (D+E) 326,651

Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,4 x 0,8 m + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.112 120,000 13,440.00
2 Tukang Khusus Aluminium L.02 OH 0.263 150,000 39,480.00
3 Kepala Tukang L.03 OH 0.027 175,000 4,704.00
4 Mandor L.04 OH 0.006 185,000 1,201.76
-
-
JUMLAH TENAGA KERJA 58,825.76
B BAHAN
2 Pintu Alluminium m 4.928 200,000.00 985,600.00
3 Profil Kaca m 5.040 7,500.00 37,800.00
4 Sealant Tube 0.302 30,000.00 9,072.00
5 Kaca tebal 5 mm m2 1.120 150,000.00 168,000.00
6 Engsel Casement unit 2.000 161,900.00 323,800.00
7 Rambuncis Bh 2.000 48,575.00 97,150.00
9 Sunblast m2 1.120 200,000.00 224,000.00
-
-
-
JUMLAH TENAGA BAHAN 1,845,422.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,904,247.76


E. Overhead & Profit 0% X D 190,424.78
F. Harga Satuan Pekerjaan (D+E) 2,094,672.54

Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,6 x 1,4 m + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.224 120,000 26,880.00
2 Tukang Khusus Aluminium L.02 OH 0.526 150,000 78,960.00
3 Kepala Tukang L.03 OH 0.054 175,000 9,408.00
4 Mandor L.04 OH 0.013 185,000 2,403.52
-
-
JUMLAH TENAGA KERJA 117,651.52
B BAHAN
2 Pintu Alluminium m 9.856 200,000.00 1,971,200.00
3 Profil Kaca m 10.080 7,500.00 75,600.00
4 Sealant Tube 0.605 30,000.00 18,144.00
5 Kaca tebal 5 mm m2 2.240 150,000.00 336,000.00
6 Engsel Casement unit 2.000 161,900.00 323,800.00
7 Rambuncis Bh 2.000 48,575.00 97,150.00
9 Sunblast m2 2.240 200,000.00 448,000.00
-
-
-
JUMLAH TENAGA BAHAN 3,269,894.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,387,545.52


E. Overhead & Profit 0% X D 338,754.55
F. Harga Satuan Pekerjaan (D+E) 3,726,300.07

32 Pembuatan dan Pemasangan Jendela Kaca Daun Rangka Alumunium uk. 1,75 x 1,5 m + Kusen dan Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 3.058 120,000 366,900.00
2 Tukang Khusus Aluminium L.02 OH 3.412 150,000 511,781.25
3 Kepala Tukang L.03 OH 0.091 175,000 15,916.25
4 Mandor L.04 OH 0.029 185,000 5,341.88
-
-
JUMLAH TENAGA KERJA 899,939.38
B BAHAN
1 Kusen Aluminium m 6.500 150,000.00 975,000.00
2 Pintu Alluminium m 11.550 200,000.00 2,310,000.00
3 Profil Kaca m 11.813 7,500.00 88,593.75
4 Sealant Tube 4.609 30,000.00 138,262.50
5 Kaca tebal 5 mm m2 2.625 150,000.00 393,750.00
6 Engsel Casement unit 1.000 161,900.00 161,900.00
7 Rambuncis Bh 1.000 48,575.00 48,575.00
-
-
-
JUMLAH TENAGA BAHAN 4,116,081.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,016,020.63


E. Overhead & Profit 0% X D 501,602.06
F. Harga Satuan Pekerjaan (D+E) 5,517,622.69
34 Pembuatan dan Pemasangan Pintu Geser Rangka Alumunium uk. 1,75 x 1,5 m + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 3.058 120,000 366,900.00
2 Tukang Khusus Aluminium L.02 OH 3.412 150,000 511,781.25
3 Kepala Tukang L.03 OH 0.091 175,000 15,916.25
4 Mandor L.04 OH 0.029 185,000 5,341.88
-
-
JUMLAH TENAGA KERJA 899,939.38
B BAHAN
1 Kusen Aluminium m 6.500 150,000.00 975,000.00
2 Rangka Jendela Alumunium m 11.550 200,000.00 2,310,000.00
3 Profil Kaca m 11.813 7,500.00 88,593.75
4 Sealant Tube 4.609 30,000.00 138,262.50
5 Kaca tebal 5 mm m2 2.625 150,000.00 393,750.00
6 Engsel Casement unit 1.000 161,900.00 161,900.00
7 Rambuncis Bh 1.000 48,575.00 48,575.00
9 Sunblast m2 2.625 200,000.00 525,000.00

-
-
JUMLAH TENAGA BAHAN 4,641,081.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,541,020.63


E. Overhead & Profit 0% X D 554,102.06
F. Harga Satuan Pekerjaan (D+E) 6,095,122.69

30 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,6 x 1,4 m + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.804 120,000 336,480.00
2 Tukang Khusus Aluminium L.02 OH 3.106 150,000 465,960.00
3 Kepala Tukang L.03 OH 0.080 175,000 13,923.00
4 Mandor L.04 OH 0.026 185,000 4,734.52
-
-
JUMLAH TENAGA KERJA 821,097.52
B BAHAN
1 Kusen Aluminium m 6.000 150,000.00 900,000.00
2 Rangka Jendela Alumunium m 9.856 200,000.00 1,971,200.00
3 Profil Kaca m 10.080 7,500.00 75,600.00
4 Sealant Tube 4.205 30,000.00 126,144.00
5 Kaca tebal 5 mm m2 2.240 150,000.00 336,000.00
6 Engsel Casement unit 1.000 161,900.00 161,900.00
7 Rambuncis Bh 1.000 48,575.00 48,575.00
-
-
JUMLAH TENAGA BAHAN 3,619,419.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,440,516.52


E. Overhead & Profit 0% X D 444,051.65
F. Harga Satuan Pekerjaan (D+E) 4,884,568.17

31 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,4 x 0,8 m + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.004 120,000 240,480.00
2 Tukang Khusus Aluminium L.02 OH 2.155 150,000 323,280.00
3 Kepala Tukang L.03 OH 0.046 175,000 8,015.00
4 Mandor L.04 OH 0.016 185,000 2,911.16
-
-
JUMLAH TENAGA KERJA 574,686.16
B BAHAN
1 Kusen Aluminium m 4.400 150,000.00 660,000.00
2 Rangka Jendela Alumunium m 4.928 200,000.00 985,600.00
3 Profil Kaca m 5.040 7,500.00 37,800.00
4 Sealant Tube 2.942 30,000.00 88,272.00
5 Kaca tebal 5 mm m2 1.120 150,000.00 168,000.00
6 Engsel Casement unit 1.000 161,900.00 161,900.00
7 Rambuncis Bh 1.000 48,575.00 48,575.00

-
-
JUMLAH TENAGA BAHAN 2,150,147.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,724,833.16


E. Overhead & Profit 0% X D 272,483.32
F. Harga Satuan Pekerjaan (D+E) 2,997,316.48
DIVISI 4 / 4.4.2.27

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.27
36 JENIS PEKERJAAN Pemasangan 1 m2 acian mortar
SATUAN PEMBAYARAN m2

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang Batu L.03 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 42,600.00
B. BAHAN 0.00
1 Semen portland Kg 3.250 7,000 22,750.00
JUMLAH HARGA BAHAN 22,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 65,350.00
E. OVERHEAD & PROFIT 10,0 % x D 6,535.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 71,885.00

37 Plamiran m2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.02 120,000 2,400
Tukang cat L.02 OH 0.063 150,000 9,450
Kepala Tukang L.03 OH 0.0063 175,000 1,103
Mandor L.04 OH 0.003 185,000 555
JUMLAH TENAGA KERJA 13,508
B BAHAN
Plamir L 0.1 25,000 2,500

JUMLAH TENAGA BAHAN 2,500


C. PERALATAN
-
JUMLAH TENAGA ALAT

D. Jumlah (A+B+C) 16,008


E. Overhead & Profit 10% X D 0
F. Harga Satuan Pekerjaan (D+E) 16,007.50

Pemasangan pintu sliding alumunium kaca


38 +sanblast
Pintu Sliding Aluminium Kaca
Pintu aluminium kaca 2.7 m2 1044884.5 2821188.15
Kunci tanam stainless 1 bh 584457.5 584457.5
Rel pintu sliding 1 bh 842330.5 842330.5
Handle 2 bh 50000 100000
sanblast 2.6901 m2 88000 236728.8
Rp4,584,704.95

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.6
39 JENIS PEKERJAAN Pemasangan engsel casement
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Kayu (L.02) OH 0.10 150,000 15,000.00
3 Kepala tukang (L.03) OH 0.010 175,000 1,750.00
4 Mandor (L.04) OH 0.0005 185,000 92.50
JUMLAH HARGA TENAGA 18,042.50
B. BAHAN
1 Engsel Kupu-kupu Bh 1.00 26,000 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 168,042.50
E. OVERHEAD & PROFIT 10,0 % x D 16,804.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 184,846.75
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.11
40 JENIS PEKERJAAN Pemasangan Rambuncis
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Kayu (L.02) 0.2 150,000 30,000.00
3 Kepala tukang (L.03) 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 36,085.00
B. BAHAN
1 Rambuncis Bh 1.00 52,000 52,000.00
JUMLAH HARGA BAHAN 52,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 88,085.00
E. OVERHEAD & PROFIT 10,0 % x D 8,808.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 96,893.50

Pemasangan pintu alumunium kaca 2,1 x 0,9


Pintu Aluminium Kaca
Kusen Aluminium 5.2 m' Rp201,038.75 Rp 1,045,401.50
Pintu Kaca 1.935 m2 ### Rp 2,021,851.51
engsel 3 bh Rp 75,658.00 Rp 226,974.00
Kunci 1 bh Rp584,457.50 Rp 584,457.50
handle 2 bh Rp573,710.50 Rp 1,147,421.00
Door closer 1 bh Rp656,210.50 Rp 656,210.50
sanblast 1.935 m2 Rp 88,000.00 Rp 170,280.00
Rp 5,852,596.01
41 Pembuatan dan Pemasangan Pintu Kaca 1 Daun Rangka Alumunium uk. 0,9 x 2,1 m + Kusen + Sunblast + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.769 120,000 332,280.00
2 Tukang Khusus Aluminium L.02 OH 3.024 150,000 453,622.50
3 Kepala Tukang L.03 OH 0.071 175,000 12,453.00
4 Mandor L.04 OH 0.024 185,000 4,358.97
-
-
JUMLAH TENAGA KERJA 802,714.47
B BAHAN
1 Kusen Aluminium m 6.000 150,000.00 900,000.00
2 Pintu Alluminium m 8.316 200,000.00 1,663,200.00
3 Profil Kaca m 8.505 7,500.00 63,787.50
5 Kaca tebal 5 mm m2 1.890 150,000.00 283,500.00
6 Sunblast m2 1.890 80,000.00 151,200.00
7 Engsel Pintu Set 1.000 75,000.00 75,000.00
8 Kunci Set Set 1.000 350,000.00 350,000.00
sandblast 1.930 80,000.00 154,400.00
4 Sealant Tube 4.110 30,000.00 123,309.00
-
JUMLAH TENAGA BAHAN 3,764,396.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,567,110.97


E. Overhead & Profit 0% X D 456,711.10
F. Harga Satuan Pekerjaan (D+E) 5,023,822.07
42 Pemasangan 1 m2 rangka dinding partisi + Gypsum Board 9 mm (1 Sisi)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.350 120,000 42,000.00
2 Tukang Khusus Aluminium L.02 OH 0.300 150,000 45,000.00
3 Kepala Tukang L.03 OH 0.030 175,000 5,250.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
-
-
JUMLAH TENAGA KERJA 95,580.00
B BAHAN
Rangka Baja C 75 . 75 kg 3.267 17,647.00 57,646.87
Baut (screw driver) bh 0.400 175.00 175.00
Gypsum Board 9 mm Lbr 0.364 75,000.00 27,300.00
Compound kg 1.500 15,500.00 23,250.00
Kain kasa roll 0.800 7,000.00 5,600.00
Sekrup gypsum kg 0.110 55,000.00 6,050.00
-
-
-
-
JUMLAH TENAGA BAHAN 120,021.87
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 215,601.87


E. Overhead & Profit 0% X D 21,560.19
F. Harga Satuan Pekerjaan (D+E) 237,162.05

43 Pemasangan 1 m2 rangka Baja Ringan C.75.75 dinding partisi + Gypsum Board 9 mm (2 Sisi)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.450 120,000 54,000.00
2 Tukang Khusus Aluminium L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.023 185,000 4,255.00
-
-
JUMLAH TENAGA KERJA 116,880.00
B BAHAN
Rangka Baja C 75 . 75 kg 3.267 17,647.00 57,646.87
Baut (screw driver) bh 0.400 175.00 175.00
Gypsum Board 12 mm Lbr 0.728 75,000.00 54,600.00
Compound kg 3.000 15,500.00 46,500.00
Kain kasa roll 1.600 7,000.00 11,200.00
Sekrup gypsum kg 0.220 55,000.00 12,100.00
-
-
-
-
JUMLAH TENAGA BAHAN 182,221.87
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 299,101.87


E. Overhead & Profit 0% X D 29,910.19
F. Harga Satuan Pekerjaan (D+E) 329,012.05

44 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120cm, dinding partisi + Gypsum Board 9 mm (2 Sisi)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.450 120,000 54,000.00
2 Tukang Khusus Aluminium L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.023 185,000 4,255.00
-
-
JUMLAH TENAGA KERJA 116,880.00
B BAHAN
Baut (screw driver) bh 0.400 175.00 70.00
Dynabolt bh 1.600 13,500.00 13,500.00
Gypsum Board 12 mm Lbr 0.728 75,000.00 54,600.00
Compound kg 3.000 15,500.00 46,500.00
Kain kasa roll 1.600 7,000.00 11,200.00
Sekrup gypsum kg 0.220 55,000.00 12,100.00
Rangka Metal Hollow 40.40.2 mm M1 3.500 12,000.00 42,000.00
-
-
-
JUMLAH TENAGA BAHAN 179,970.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 296,850.00


E. Overhead & Profit 0% X D 29,685.00
F. Harga Satuan Pekerjaan (D+E) 326,535.00

DIVISI 4 / 4.4.2.27

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.27
45 JENIS PEKERJAAN waterproofing aquatite
SATUAN PEMBAYARAN m2

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang Batu L.03 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 42,600.00
B. BAHAN 0.00
1 Aquatite 1.000 150,000 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 192,600.00
E. OVERHEAD & PROFIT 10,0 % x D 19,260.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 211,860.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.4
46 JENIS PEKERJAAN Pemasangan urinoir setara TOTO
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.00 150,000 150,000.00
3 Kepala Tukang (L.03) OH 0.10 175,000 17,500.00
4 Mandor (L.04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 296,750.00
B. BAHAN
1 Urinoir Unit 1.00 3,620,000 3,620,000.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Perlengkapan 30 % 0.30 2,050,000 615,000.00
JUMLAH HARGA BAHAN 4,243,110.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 4,539,860.00
E. OVERHEAD & PROFIT 10,0 % x D 453,986.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 4,993,846.00

48 Pembuatan dan Pemasangan Jendela Kaca Daun Rangka Alumunium uk. 1,2 x 1,5 m + Kusen + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.502 120,000 300,240.00
2 Tukang Khusus Aluminium L.02 OH 2.745 150,000 411,750.00
3 Kepala Tukang L.03 OH 0.066 175,000 11,623.50
4 Mandor L.04 OH 0.022 185,000 4,029.30
-
-
JUMLAH TENAGA KERJA 727,642.80
B BAHAN
1 Kusen Aluminium m 5.400 150,000.00 810,000.00
2 Pintu Alluminium m 7.920 200,000.00 1,584,000.00
3 Profil Kaca m 8.100 7,500.00 60,750.00
4 Sealant Tube 3.726 30,000.00 111,780.00
5 Kaca tebal 5 mm m2 1.800 150,000.00 270,000.00
6 Engsel Casement unit 1.000 161,900.00 161,900.00
7 Rambuncis Bh 1.000 48,575.00 48,575.00
-
-
-
JUMLAH TENAGA BAHAN 3,047,005.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,774,647.80


E. Overhead & Profit 0% X D 377,464.78
F. Harga Satuan Pekerjaan (D+E) 4,152,112.58
ANALISA HARGA SATUAN PEKERJAAN
(AHSP) 0.005
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir .23
49 JENIS PEKERJAAN Pemasangan lampu LED 24 Watt
SATUAN PEMBAYARAN titik
HARGA JUMLAH HARGA (Rp.)
KOMPONEN SATUAN KOEFISIEN SATUAN
NO. (Rp.)
A. TENAGA
1 Pekerja L.01 120,000
2 Tukang L.02 0.135 150,000
3 Kepala Tukang L.03 0.0135 175,000
4 Mandor L.04 0.0050 185,000
JUMLAH HARGA TENAGA
B. BAHAN
1 Kabel NYM 2X2,5 mm2 m 15 13000

2 Pipa konduit PVC HI EGA DIA 20 MM m 12 2750


3 T-Dus PVC HI EGA Dia 20 mm bh 1 4250
Lampu DL LED 24 WATT PHILIPS DN020B bh 1.00 150,000 150,000.00
4
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 150,000.00
OVERHEAD & PROFIT 10,0 % x D 15,000.00
E.
F. HARGA SATUAN PEKERJAAN ( D + E ) 165,000.00

Pemasangan Aksesoris SPOEL HOEK /


50 SLOP SINK bh Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 3.3 120,000 396,000
Tukang Kayu L.02 OH 1.1 150,000 165,000
Kepala Tukang L.03 OH 0.01 175,000 1,750
Mandor L.04 OH 0.16 185,000 29,600
JUMLAH TENAGA KERJA 592,350
B BAHAN
SLOP SINK TOTO UNIT 1 4,200,000 4,200,000

Perlengkapan LS 6% X CLOSET 442,200 442,200


-
-
JUMLAH TENAGA BAHAN 4,642,200
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,234,550


E. Overhead & Profit 10% X D 523,455
F. Harga Satuan Pekerjaan (D+E) 5,758,005

Pemasangan tanki air 550 liter dan


51 instalasi bh Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.2 120,000 24,000
Tukang Kayu L.02 OH 0.15 150,000 22,500
Kepala Tukang L.03 OH 0.1 175,000 17,500
Mandor L.04 OH 0.05 185,000 9,250
JUMLAH TENAGA KERJA 73,250
B BAHAN
TEDMOD 1200 LITER bh 1 1,200,000 1,200,000
JUMLAH TENAGA BAHAN 1,200,000
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,273,250


E. Overhead & Profit 10% X D 127,325
F. Harga Satuan Pekerjaan (D+E) 1,400,575.00
52 Pemasangan trali besi Analisa TK2
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.4 120,000 168,000
Tukang Kayu L.02 OH 1.4 150,000 210,000
Kepala Tukang L.03 OH 0.144 175,000 25,200
Mandor L.04 OH 0.072 185,000 13,320
JUMLAH TENAGA KERJA 416,520
B BAHAN
Besi 20 14,200 284,000
Pengelasan 28 3,363 94,164
-
JUMLAH TENAGA BAHAN 378,164
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 794,684


E. Overhead & Profit 10% X D 79,468
F. Harga Satuan Pekerjaan (D+E) 874,152.40

52 Pemasangan trali besi m2 Analisa TK2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.4 120,000 168,000
Tukang Kayu L.02 OH 1.4 150,000 210,000
Kepala Tukang L.03 OH 0.144 175,000 25,200
Mandor L.04 OH 0.072 185,000 13,320
JUMLAH TENAGA KERJA 416,520
B BAHAN
Besi 20 14,200 284,000
Pengelasan 28 3,363 94,164
-
JUMLAH TENAGA BAHAN 378,164
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 794,684


E. Overhead & Profit 10% X D 79,468
F. Harga Satuan Pekerjaan (D+E) 874,152.40

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.9
53 JENIS PEKERJAAN Pemasangan Pintu alumunium wc
SATUAN PEMBAYARAN bh

KOMPONEN SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)


NO.
A. TENAGA
1 Pekerja L.01 0.050 120,000 6,000.00
2 Tukang L.02 0.500 150,000 75,000.00
3 Kepala Tukang L.03 0.050 175,000 8,750.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Pintu aluminium warna lengkap bh 1.000 2,000,000 2,000,000.00
JUMLAH HARGA BAHAN 2,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,090,305.00
OVERHEAD & PROFIT 10,0 % x D 209,030.50
E.
HARGA SATUAN PEKERJAAN ( D + E ) 2,299,335.50
F.

DIVISI 5 / 5.1.1.1.

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.1
54 JENIS PEKERJAAN Pemasangan 1 buah closet duduk Setara TOTO
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 3.30 120,000 396,000.00
2 Tukang Batu (L.02) OH 1.10 150,000 165,000.00
3 Kepala Tukang (L.03) OH 0.01 175,000 1,750.00
4 Mandor (L.04) OH 0.16 185,000 29,600.00
JUMLAH HARGA TENAGA 592,350.00
B. BAHAN
1 Closet duduk Unit 1.00 2,576,000 2,576,000.00
2 Perlengkapan 6% x closet Ls 1.00 154,560 154,560.00
JUMLAH HARGA BAHAN 2,730,560.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 3,322,910.00
E. OVERHEAD & PROFIT 10,0 % x D 332,291.00
HARGA SATUAN PEKERJAAN ( D + E ) 3,655,201.00
F.
DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
55 JENIS PEKERJAAN Pemasangan 1 buah Eco-Washer (soft closing TOTO TCW07S)
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.4 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.04 175,000 7,000.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 69,125.00
B. BAHAN
1 Eco washer M 1.00 1,500,000 1,500,000.00
2 Sealtape Buah 0.025 3,500 87.50
JUMLAH HARGA BAHAN 1,500,087.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,569,212.50


E. OVERHEAD & PROFIT 10,0 % x D 156,921.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,726,133.75

DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
56 JENIS PEKERJAAN Pemasangan 1 buah Shower Spray
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.4 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.04 175,000 7,000.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 69,125.00
B. BAHAN
1 Shower M 1.00 239,000 239,000.00
2 Sealtape Buah 0.025 3,500 87.50
JUMLAH HARGA BAHAN 239,087.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 308,212.50


E. OVERHEAD & PROFIT 10,0 % x D 30,821.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 339,033.75

DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
58 JENIS PEKERJAAN Pemasangan 1 buah Tee Stainless
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.4 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.04 175,000 7,000.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 69,125.00
B. BAHAN
1 Tee M 1.00 180,000 180,000.00
2 Sealtape Buah 0.025 3,500 87.50
JUMLAH HARGA BAHAN 180,087.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 249,212.50


E. OVERHEAD & PROFIT 10,0 % x D 24,921.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 274,133.75
DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
57 JENIS PEKERJAAN Pemasangan Wastafel TOTO
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 1.2000 120,000 144,000.00
2 Tukang Batu (L.02) OH 1.4500 150,000 217,500.00
3 Kepala Tukang (L.03) OH 0.1500 175,000 26,250.00
4 Mandor (L.04) OH 0.0600 185,000 11,100.00
JUMLAH HARGA TENAGA 398,850.00
B. BAHAN
1 Wastafel Unit 1.20 1,200,000 1,440,000.00
2 Semen Portland kg 6.000 3,500 21,000.00
3 Pasir Pasang m3 0.010
4 Perlengkapan 12 % 0.120
JUMLAH HARGA BAHAN 1,461,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,859,850.00


E. OVERHEAD & PROFIT 10,0 % x D 185,985.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,045,835.00

DIVISI 4 / 4.7.1.10.b
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.10.b
59 JENIS PEKERJAAN Perbaikan dinding retak
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) MLAH ARGA Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.03 140,000 4,200.00
2 Tukang Cat (L.02) OH 0.080 160,000 12,800.00
3 Kepala Tukang (L.03) OH 180,000 0.00
4 Mandor (L.04) OH 185,000 0.00
JUMLAH HARGA TENAGA 17,000.00
B. BAHAN 0.00
1 Semen putih Kg 6,000 6,000.00
2 Damdex liter 55,000 7,000.00
3 LEM FOX Kg 6,000 6,000.00
4 MU 250 Kg 16,000 16,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 52,000.00
E. OVERHEAD & PROFIT 10,0 % x D 5,200.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,200.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.59
60 JENIS PEKERJAAN Pemasangan Karpet Vinyl
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 0.15 140,000 21,000.00
2 Tukang Batu L.02 OH 0.15 160,000 24,000.00
3 Kepala tukang L.03 OH 0.015 180,000 2,700.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 49,180.00
B. BAHAN 0.00
1 Vinyl m2 1.10 490,000 539,000.00
2 Lem Kg 0.35 30,000 10,500.00
JUMLAH HARGA BAHAN 549,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 598,680.00
E. OVERHEAD & PROFIT 10,0 % x D 59,868.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 658,548.00

61 Pek Pasang Kusen + Jendela


1 Unit Jendela Type J1 (3 lbg 60 x 90/50) ukuran dalam
Kusen Alumunium silver 4" M1 11 150000 1650000
Jendela Alumunium M1 13.6 120000 1,632,000.00
Kaca polos clear 5 mm M2 1.82 150000 273,000.00
Karet kaca M1 21 2000 42,000.00
Casement 16" SET 6 60000 360000
Casement 8" SET 6 40000 240000
Rambuncis/grendel jendela SET 6 17500 105000
Dinabolt dia. 12 mm BH 8 2500 20000
Pengisian aduk 3 sisi LS 3 25000 75000
4397000
Upas pasng 30 persen LS 1 1319100 1319100
5716100
62 Membuat sloof beton bertulang
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 5.650 120,000.00 678,000.00
Tukang Batu L.02 OH 0.275 150,000.00 41,250.00
Tukang Kayu L.02 OH 1.560 150,000.00 234,000.00
Tukang Besi L.02 OH 1.400 150,000.00 210,000.00
Kepala Tukang L.03 OH 0.323 175,000.00 56,525.00
Mandor L.04 OH 0.283 185,000.00 52,355.00
JUMLAH TENAGA KERJA 1,272,130.00
B BAHAN
Kayu kelas m3 0.270 1,900,000.00 513,000.00
Paku 5-12 cm kg 2.000 22,000.00 44,000.00
Minyak bekesting Liter 0.600 11,000.00 6,600.00
Besi beton polos kg 157.500 12,000.00 1,890,000.00
Kawat beton kg 2.250 20,000.00 45,000.00
Sement Portland kg 336.000 1,160.00 389,760.00
Pasir Beton m3 0.540 135,000.00 72,900.00
Kerikil kg 0.810 420,000.00 340,200.00

JUMLAH TENAGA BAHAN 3,301,460.00


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,573,590.00


E. Overhead & Profit - 457,359.00
F. Harga Satuan Pekerjaan (D+E) 5,030,949.00

63 Pemasangan 1 m2 lantai keramik ukuran 25cm x 25cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.7 120,000.00 84,000.00
Tukang Batu L.02 OH 0.35 150,000.00 52,500.00
Kepala Tukang L.03 OH 0.035 175,000.00 6,125.00
Mandor L.04 OH 0.035 185,000.00 6,475.00
JUMLAH TENAGA KERJA 149,100.00
B BAHAN
Ubin Keramik uk.25x25 Dos 16 4100 65,600.00
Semen Portland Kg 10 1160 11,600.00
Pasir Pasang Kg 0.045 105000 4,725.00
Semen Warna M3 1.5 10000 15,000.00
JUMLAH TENAGA BAHAN 96,925.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 246,025.00


E. Overhead & Profit - 24,602.50
F. Harga Satuan Pekerjaan (D+E) 270,627.50

64 Pemasangan 1m2 Dinding Keramik Ukuran (25 x 40 cm)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.9 120,000.00 108,000.00
Tukang Batu L.02 OH 0.45 150,000.00 67,500.00
Kepala Tukang L.03 OH 0.045 175,000.00 7,875.00
Mandor L.04 OH 0.045 185,000.00 8,325.00
JUMLAH TENAGA KERJA 191,700.00
B BAHAN
Keramik Uk. 25 x 40 cm Bh 10 6500 65,000.00
Semen Portland Kg 9.6 1160 11,136.00
Pasir Pasang M3 0.045 115000 5,175.00
Semen warna Kg 1.5 10000 15,000.00
JUMLAH TENAGA BAHAN 96,311.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 288,011.00


E. Overhead & Profit - 28,801.10
F. Harga Satuan Pekerjaan (D+E) 316,812.10

65 Pembuatan dan Pemasangan Pintu Kaca Rangka Alumunium 1 Daun uk. 1 x 2,15 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.786 120,000.00 94,308.00
2 Tukang Khusus Aluminium L.02 OH 2.276 150,000.00 341,422.50
3 Kepala Tukang L.03 OH 0.228 175,000.00 39,832.63
4 Mandor L.04 OH 0.041 185,000.00 7,529.50
-
-
JUMLAH TENAGA KERJA 483,092.63
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.930 150,000.00 1,039,500.00
2 Sekrup Fixer buah 12.600 950.00 11,970.00
3 Sealant tube 0.378 30,000.00 11,340.00
II Daun Pintu -
1 Alumunium Profil m 6.930 150,000.00 1,039,500.00
2 Profil Alumunium T m 7.087 7,500.00 53,156.25
3 Sealant tube 0.425 85,000.00 36,146.25
4 Kaca tebal 5 mm m2 2.150 150,000.00 322,500.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 2.150 50,000.00 107,500.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,464,362.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,947,455.13


E. Overhead & Profit - 394,745.51
F. Harga Satuan Pekerjaan (D+E) 4,342,200.64
66 Pemasangan 1 buah pintu KM/WC bahan PVC
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.05 120,000.00 6,000.00
Tukang L.02 OH 0.5 150,000.00 75,000.00
Kepala Tukang L.03 OH 0.05 175,000.00 8,750.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 90,305.00
B BAHAN
Pintu KM/WC PVC bh 1 750000 750,000.00
Sealent tube 0.432 30000 12,960.00
JUMLAH TENAGA BAHAN 762,960.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 853,265.00


E. Overhead & Profit - 85,326.50
F. Harga Satuan Pekerjaan (D+E) 938,591.50

67 Pengadaan dan Instalasi pintu koboi


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.726 120,000.00 87,084.00
2 Tukang Khusus Aluminium L.02 OH 2.158 150,000.00 323,685.00
3 Kepala Tukang L.03 OH 0.216 175,000.00 37,763.25
4 Mandor L.04 OH 0.037 185,000.00 6,912.71
-
-
JUMLAH TENAGA KERJA 455,444.96
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.354 30,000.00 10,620.00
II Daun Pintu -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.638 7,500.00 49,781.25
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 1.720 150,000.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 1.720 50,000.00 86,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 2,981,212.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,436,657.46


E. Overhead & Profit 0% X D 343,665.75
F. Harga Satuan Pekerjaan (D+E) 3,780,323.21

68 Membuat 1 m3 plat beton bertulang


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 5.300 120,000.00 636,000.00
Tukang Batu L.02 OH 0.275 150,000.00 41,250.00
Tukang Kayu L.02 OH 1.300 150,000.00 195,000.00
Tukang Besi L.02 OH 1.050 150,000.00 157,500.00
Kepala Tukang L.03 OH 0.262 175,000.00 45,850.00
Mandor L.04 OH 0.265 185,000.00 49,025.00
JUMLAH TENAGA KERJA 1,124,625.00
B BAHAN
Kayu kelas m3 0.320 1,900,000.00 608,000.00
Paku 5-12 cm kg 3.200 22,000.00 70,400.00
Minyak bekesting Liter 1.600 11,000.00 17,600.00
Besi beton polos kg 157.500 13,900.00 2,189,250.00
Kawat beton kg 2.250 20,000.00 45,000.00
Sement Portland kg 336.000 1,160.00 389,760.00
Pasir Beton m3 0.540 135,000.00 72,900.00
Kerikil kg 0.810 420,000.00 340,200.00
Kayu kelas balok m3 0.120 1,600,000.00
Plywood 9 mm lembar 2.800 145,000.00
Dolken Kayu Ø8-10cm p.4m batang 3.200 15,000.00
JUMLAH TENAGA BAHAN 3,733,110.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,857,735.00


E. Overhead & Profit - 485,773.50
F. Harga Satuan Pekerjaan (D+E) 5,343,508.50

Pemasangan grill stainless steel tutup


69 unit
saluran
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.450 120,000.00 54,000.00
2 Tukang Khusus Aluminium L.02 OH 0.350 150,000.00 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000.00 6,125.00
4 Mandor L.04 OH 0.023 185,000.00 4,255.00
-
-
JUMLAH TENAGA KERJA 116,880.00
B BAHAN
Rangka Metal Hollow 40.40.2 mm M1 73.9 40,000.00 2,956,000.00
Assesoris (perkuatan, las dll) Ls 100%xrangka 40,000.00 295,600.00
-
JUMLAH TENAGA BAHAN 3,251,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,368,480.00


E. Overhead & Profit 10% X D 336,848.00
F. Harga Satuan Pekerjaan (D+E) 3,705,328.00
69 Aspalt buras unit
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.002 120,000.00 240.00
2 Tukang Khusus Aluminium L.02 OH 0.0004 150,000.00 60.00
3 Kepala Tukang L.03 OH 175,000.00 -
4 Mandor L.04 OH 185,000.00 -
-
-
JUMLAH TENAGA KERJA 300.00
B BAHAN
aspalt M1 0.7600 12,500.00 9,500.00
kerosone Ls 0.0700 11,250.00 950.00
pasir halus 0.0500 135,000.00 6,750.00
JUMLAH TENAGA BAHAN 17,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 17,500.00


E. Overhead & Profit 10% X D 1,750.00
F. Harga Satuan Pekerjaan (D+E) 19,250.00

Bongkaran Dinding Glass block


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 38,775.00
B BAHAN
JUMLAH TENAGA BAHAN
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 38,775.00


E. Overhead & Profit - 3,877.50
F. Harga Satuan Pekerjaan (D+E) 42,652.50

Bongkaran Plafon
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 120,000.00 8,400.00
Mandor L.04 OH 0.010 185,000.00 1,850.00
JUMLAH TENAGA KERJA 10,250.00
B BAHAN
JUMLAH TENAGA BAHAN
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 10,250.00


E. Overhead & Profit - 1,025.00
F. Harga Satuan Pekerjaan (D+E) 11,275.00

Pembongkaran 1 m3 dinding tembok bata


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 6.667 120,000.00 800,040.00
Mandor L.04 OH 0.333 185,000.00 61,605.00
JUMLAH TENAGA KERJA 861,645.00
B BAHAN
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 861,645.00


E. Overhead & Profit - 86,164.50
F. Harga Satuan Pekerjaan (D+E) 947,809.50

Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:3PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.3 120,000.00 36,000.00
Tukang Batu L.02 OH 0.1 150,000.00 15,000.00
Kepala Tukang L.03 OH 0.01 175,000.00 1,750.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 55,525.00
B BAHAN
Bata Merah buah 70 550 38,500.00
Semen Portland Kg 14.37 1160 16,669.20
Pasir Pasang m3 0.04 115000 4,600.00
JUMLAH TENAGA BAHAN 59,769.20
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 115,294.20


E. Overhead & Profit - 11,529.42
F. Harga Satuan Pekerjaan (D+E) 126,823.62

Pemasangan 1 m2 plesteran 1SP:3PP tebal 15 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.3 120,000.00 36,000.00
Tukang Batu L.02 OH 0.15 150,000.00 22,500.00
Kepala Tukang L.03 OH 0.015 175,000.00 2,625.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 63,900.00
B BAHAN
Semen Portland Kg 7.776 1160 9,020.16
Pasir Pasang m3 0.023 115000 2,645.00
JUMLAH TENAGA BAHAN 11,665.16
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 75,565.16


E. Overhead & Profit - 7,556.52
F. Harga Satuan Pekerjaan (D+E) 83,121.68

Pemasangan 1 m2 Dinding keramik ukuran 30cm x 30cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.7 120,000.00 84,000.00
Tukang Batu L.02 OH 0.35 150,000.00 52,500.00
Kepala Tukang L.03 OH 0.035 175,000.00 6,125.00
Mandor L.04 OH 0.035 185,000.00 6,475.00
JUMLAH TENAGA KERJA 149,100.00
B BAHAN
Ubin Keramik uk.30x30 Dos 1.05 130000 136,500.00
Semen Portland Kg 10 1160 11,600.00
Pasir Pasang Kg 0.045 115000 5,175.00
Semen Warna M3 1.5 10000 15,000.00
JUMLAH TENAGA BAHAN 168,275.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 317,375.00


E. Overhead & Profit - 31,737.50
F. Harga Satuan Pekerjaan (D+E) 349,112.50

Pemasangan 1 m² langit-langit gypsum board tebal 9 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.1 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.05 150,000.00 7,500.00
Kepala Tukang L.03 OH 0.005 175,000.00 875.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 21,300.00
B BAHAN
gypsum board Lembar 0.364 75000 27,300.00
Paku skrup kg 0.11 55000 6,050.00
JUMLAH TENAGA BAHAN 33,350.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 54,650.00


E. Overhead & Profit - 5,465.00
F. Harga Satuan Pekerjaan (D+E) 60,115.00

Pengecatan 1 m2 tembok baru Interior ( 1 lapis plamuur, 1 lapis cat dasar (sealer), 2 lapis cat penutup ( Spec:
JOTUN)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.02 120,000.00 2,400.00
Tukang Cat L.02 OH 0.063 150,000.00 9,450.00
Kepala Tukang L.03 OH 0.0063 175,000.00 1,102.50
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 13,507.50
B BAHAN
Plamuur Kg 0.1 25000 2,500.00
Cat dasar tembok (sealer) Kg 0.1 43000 4,300.00
Cat penutup (cat tembok) untuk interior
(dalam) Kg 0.26 80000 20,800.00
JUMLAH TENAGA BAHAN 27,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 41,107.50


E. Overhead & Profit - 4,110.75
F. Harga Satuan Pekerjaan (D+E) 45,218.25

Pengecatan 1 m2 Plafond ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.02 120,000.00 2,400.00
Tukang Cat L.02 OH 0.063 150,000.00 9,450.00
Kepala Tukang L.03 OH 0.0063 175,000.00 1,102.50
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 13,507.50
B BAHAN
Plamur Kg 0.1 25000 2,500.00
Cat dasar Kg 0.1 43000 4,300.00
Cat penutup Kg 0.26 24000 6,240.00
JUMLAH TENAGA BAHAN 13,040.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 26,547.50


E. Overhead & Profit - 2,654.75
F. Harga Satuan Pekerjaan (D+E) 29,202.25

70 Pembuatan dan Pemasangan Pintu ACP 1 Daun uk. 1.2 x 2.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.970 120,000.00 116,364.00
2 Tukang Khusus Aluminium L.02 OH 2.615 150,000.00 392,280.00
3 Kepala Tukang L.03 OH 0.262 175,000.00 45,766.00
4 Mandor L.04 OH 0.051 185,000.00 9,385.05
-
-
JUMLAH TENAGA KERJA 563,795.05
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.690 150,000.00 1,303,500.00
2 Sekrup Fixer buah 15.800 950.00 15,010.00
3 Sealant tube 0.474 30,000.00
II Daun Pintu -
1 Alumunium Profil m 7.480 150,000.00 1,122,000.00
2 Profil Alumunium T m 7.650 7,500.00 57,375.00
3 Sealant tube 0.533 85,000.00 45,326.25
4 Kaca tebal 5 mm m2 0.660 150,000.00 99,000.00
5 Aluminium composite panel (ACP) m2 2.640 425,000.00 1,122,000.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 0.660 50,000.00 33,000.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 2.000 25,000.00 50,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 4,709,961.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,273,756.30


E. Overhead & Profit - 527,375.63
F. Harga Satuan Pekerjaan (D+E) 5,801,131.93

71 Pembuatan dan Pemasangan Pintu ACP 2 Daun uk. 1.5 x 2.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.421 120,000.00 170,520.00
2 Tukang Khusus Aluminium L.02 OH 4.378 150,000.00 656,681.25
3 Kepala Tukang L.03 OH 0.438 175,000.00 76,612.81
4 Mandor L.04 OH 0.074 185,000.00 13,666.88
-
-
JUMLAH TENAGA KERJA 917,480.94
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 9.350 150,000.00 1,402,500.00
2 Sekrup Fixer buah 17.000 950.00 16,150.00
3 Sealant tube 0.510 30,000.00
II Daun Pintu -
1 Alumunium Profil m 8.140 150,000.00 1,221,000.00
2 Profil Alumunium T m 8.325 7,500.00 62,437.50
3 Sealant tube 0.574 85,000.00 48,768.75
4 Kaca tebal 5 mm m2 0.825 150,000.00 123,750.00
5 Aluminium composite panel (ACP) m2 3.300 425,000.00 1,402,500.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 0.825 50,000.00 41,250.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 4.000 25,000.00 100,000.00
6 Rambuncis Bh 2.000 20,000.00 40,000.00
-
JUMLAH TENAGA BAHAN 5,643,856.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,561,337.19


E. Overhead & Profit - 656,133.72
F. Harga Satuan Pekerjaan (D+E) 7,217,470.91

72 Pembuatan dan Pemasangan Pintu ACP 2 Daun uk. 1.75 x 2.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.511 120,000.00 181,350.00
2 Tukang Khusus Aluminium L.02 OH 4.561 150,000.00 684,140.63
3 Kepala Tukang L.03 OH 0.456 175,000.00 79,816.41
4 Mandor L.04 OH 0.079 185,000.00 14,598.81
-
-
JUMLAH TENAGA KERJA 959,905.84
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 9.900 150,000.00 1,485,000.00
2 Sekrup Fixer buah 18.000 950.00 17,100.00
3 Sealant tube 0.540 30,000.00
II Daun Pintu -
1 Alumunium Profil m 8.690 150,000.00 1,303,500.00
2 Profil Alumunium T m 8.888 7,500.00 66,656.25
3 Sealant tube 0.608 85,000.00 51,637.50
4 Kaca tebal 5 mm m2 0.963 150,000.00 144,375.00
5 Aluminium composite panel (ACP) m2 3.850 425,000.00 1,636,250.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 0.963 50,000.00 48,125.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 4.000 25,000.00 100,000.00
6 Rambuncis Bh 2.000 20,000.00 40,000.00
-
JUMLAH TENAGA BAHAN 6,078,143.75
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 7,038,049.59


E. Overhead & Profit - 703,804.96
F. Harga Satuan Pekerjaan (D+E) 7,741,854.55

73 Pembuatan dan Pemasangan Pintu ACP 1 Daun uk. 0.95 x 2.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.879 120,000.00 105,534.00
2 Tukang Khusus Aluminium L.02 OH 2.432 150,000.00 364,820.63
3 Kepala Tukang L.03 OH 0.243 175,000.00 42,562.41
4 Mandor L.04 OH 0.046 185,000.00 8,453.11
-
-
JUMLAH TENAGA KERJA 521,370.14
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.140 150,000.00 1,221,000.00
2 Sekrup Fixer buah 14.800 950.00 14,060.00
3 Sealant tube 0.444 30,000.00
II Daun Pintu -
1 Alumunium Profil m 6.930 150,000.00 1,039,500.00
2 Profil Alumunium T m 7.088 7,500.00 53,156.25
3 Sealant tube 0.500 85,000.00 42,457.50
4 Kaca tebal 5 mm m2 0.523 150,000.00 78,375.00
5 Aluminium composite panel (ACP) m2 2.090 425,000.00 888,250.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 0.523 50,000.00 26,125.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 2.000 25,000.00 50,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 4,275,673.75
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,797,043.89


E. Overhead & Profit - 479,704.39
F. Harga Satuan Pekerjaan (D+E) 5,276,748.28

74 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0.8 x 1.5 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.718 120,000.00 86,136.00
2 Tukang Khusus Aluminium L.02 OH 1.280 150,000.00 191,970.00
3 Kepala Tukang L.03 OH 0.128 175,000.00 22,396.50
4 Mandor L.04 OH 0.019 185,000.00 3,444.70
-
-
JUMLAH TENAGA KERJA 303,947.20
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.060 150,000.00 759,000.00
2 Sekrup Fixer buah 9.200 950.00 8,740.00
3 Sealant tube 0.276 30,000.00 8,280.00
II Daun Jendela -
1 Alumunium Profil m 5.060 150,000.00 759,000.00
2 Profil Alumunium T m 5.175 7,500.00 38,812.50
3 Sealant tube 0.311 85,000.00 26,392.50
4 Kaca tebal 5 mm m2 1.200 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 1.200 50,000.00 60,000.00
-
-
JUMLAH TENAGA BAHAN 1,730,225.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,034,172.20


E. Overhead & Profit - 203,417.22
F. Harga Satuan Pekerjaan (D+E) 2,237,589.42

75 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 2 Daun uk. 1.7 x 1.5 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.373 120,000.00 164,784.00
2 Tukang Khusus Aluminium L.02 OH 2.517 150,000.00 377,617.50
3 Kepala Tukang L.03 OH 0.252 175,000.00 44,055.38
4 Mandor L.04 OH 0.034 185,000.00 6,351.05
-
-
JUMLAH TENAGA KERJA 592,807.93
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.140 150,000.00 1,221,000.00
2 Sekrup Fixer buah 14.800 950.00 14,060.00
3 Sealant tube 0.444 30,000.00 13,320.00
II Daun Jendela -
1 Alumunium Profil m 8.140 150,000.00 1,221,000.00
2 Profil Alumunium T m 8.325 7,500.00 62,437.50
3 Sealant tube 0.500 85,000.00 42,457.50
4 Kaca tebal 5 mm m2 5.100 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 5.100 50,000.00 255,000.00
-
-
JUMLAH TENAGA BAHAN 2,969,275.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,562,082.93


E. Overhead & Profit - 356,208.29
F. Harga Satuan Pekerjaan (D+E) 3,918,291.22

76 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 2 Daun uk. 1.7 x 0.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.181 120,000.00 141,744.00
2 Tukang Khusus Aluminium L.02 OH 2.153 150,000.00 322,998.75
3 Kepala Tukang L.03 OH 0.215 175,000.00 37,683.19
4 Mandor L.04 OH 0.024 185,000.00 4,400.23
-
-
JUMLAH TENAGA KERJA 506,826.16
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.354 30,000.00 10,620.00
II Daun Jendela -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.638 7,500.00 49,781.25
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 2.550 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 2.550 50,000.00 127,500.00
-
-
JUMLAH TENAGA BAHAN 2,319,962.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,826,788.66


E. Overhead & Profit - 282,678.87
F. Harga Satuan Pekerjaan (D+E) 3,109,467.53

77 Pembuatan dan Pemasangan Jendela Kaca Mati Rangka Alumunium 1 Lubang uk. 0.85 x 0.75 m + Kusen + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.201 140,000.00 28,189.00
2 Tukang Khusus Aluminium L.02 OH 0.287 160,000.00 45,986.00
3 Kepala Tukang L.03 OH 0.029 180,000.00 5,173.43
4 Mandor L.04 OH 0.010 185,000.00 1,927.24
-
-
JUMLAH TENAGA KERJA 81,275.66
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.520 150,000.00 528,000.00
2 Sekrup Fixer buah 6.400 950.00 6,080.00
3 Sealant tube 0.192 30,000.00 5,760.00
II Profil Kaca -
1 Profil Alumunium T m 3.600 7,500.00 27,000.00
3 Sealant tube 0.216 85,000.00 18,360.00
4 Kaca tebal 5 mm m2 0.638 150,000.00
III Aksesoris -
3 Sunblast m2 0.638 50,000.00 31,875.00
-
-
JUMLAH TENAGA BAHAN 617,075.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 698,350.66


E. Overhead & Profit - 69,835.07
F. Harga Satuan Pekerjaan (D+E) 768,185.73

78 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0.9 x 1.5 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.741 120,000.00 88,968.00
2 Tukang Khusus Aluminium L.02 OH 1.324 150,000.00 198,547.50
3 Kepala Tukang L.03 OH 0.132 175,000.00 23,163.88
4 Mandor L.04 OH 0.020 185,000.00 3,683.35
-
-
JUMLAH TENAGA KERJA 314,362.73
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.280 150,000.00 792,000.00
2 Sekrup Fixer buah 9.600 950.00 9,120.00
3 Sealant tube 0.288 30,000.00 8,640.00
II Daun Jendela -
1 Alumunium Profil m 5.280 150,000.00 792,000.00
2 Profil Alumunium T m 5.400 7,500.00 40,500.00
3 Sealant tube 0.324 85,000.00 27,540.00
4 Kaca tebal 5 mm m2 1.350 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 1.350 50,000.00 67,500.00
-
-
JUMLAH TENAGA BAHAN 1,807,300.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,121,662.73


E. Overhead & Profit - 212,166.27
F. Harga Satuan Pekerjaan (D+E) 2,333,829.00

79 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0.9 x 0.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.609 120,000.00 73,128.00
2 Tukang Khusus Aluminium L.02 OH 1.101 150,000.00 165,078.75
3 Kepala Tukang L.03 OH 0.110 175,000.00 19,259.19
4 Mandor L.04 OH 0.013 185,000.00 2,376.33
-
-
JUMLAH TENAGA KERJA 259,842.26
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.630 150,000.00 544,500.00
2 Sekrup Fixer buah 6.600 950.00 6,270.00
3 Sealant tube 0.198 30,000.00 5,940.00
II Daun Jendela -
1 Alumunium Profil m 3.630 150,000.00 544,500.00
2 Profil Alumunium T m 3.713 7,500.00 27,843.75
3 Sealant tube 0.223 85,000.00 18,933.75
4 Kaca tebal 5 mm m2 0.675 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.675 50,000.00 33,750.00
-
-
JUMLAH TENAGA BAHAN 1,251,737.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,511,579.76


E. Overhead & Profit - 151,157.98
F. Harga Satuan Pekerjaan (D+E) 1,662,737.74

80 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0.8 x 0.75 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.593 120,000.00 71,196.00
2 Tukang Khusus Aluminium L.02 OH 1.074 150,000.00 161,145.00
3 Kepala Tukang L.03 OH 0.107 175,000.00 18,800.25
4 Mandor L.04 OH 0.012 185,000.00 2,218.15
-
-
JUMLAH TENAGA KERJA 253,359.40
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.410 150,000.00 511,500.00
2 Sekrup Fixer buah 6.200 950.00 5,890.00
3 Sealant tube 0.186 30,000.00 5,580.00
II Daun Jendela -
1 Alumunium Profil m 3.410 150,000.00 511,500.00
2 Profil Alumunium T m 3.488 7,500.00 26,156.25
3 Sealant tube 0.209 85,000.00 17,786.25
4 Kaca tebal 5 mm m2 0.600 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.600 50,000.00 30,000.00
-
-
JUMLAH TENAGA BAHAN 1,178,412.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,431,771.90


E. Overhead & Profit - 143,177.19
F. Harga Satuan Pekerjaan (D+E) 1,574,949.09
81 NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : Taksir.9
JENIS PEKERJAAN Pemasangan 1 bh pintu aluminium warna lengkap - ice glass
SATUAN PEMBAYARAN : Bh
HARGA JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN SATUAN
(Rp.)
A. TENAGA
1 Pekerja L.01 0.050 120,000 6,000.00
2 Tukang L.02 0.500 150,000 75,000.00
3 Kepala Tukang L.03 0.050 175,000 8,750.00
4 Mandor L.04 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Pintu aluminium warna lengkap bh 1.000 2,700,000 2,700,000.00
2 Sealent tube 0.432 30,000 12,960.00
JUMLAH HARGA BAHAN 2,712,960.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,803,265.00
E. OVERHEAD & PROFIT 10,0 % x D 280,326.50

F. HARGA SATUAN PEKERJAAN ( D + E ) 3,083,591.50

83 ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir.7
JENIS PEKERJAAN Pemasangan 1 buah exhaust fan 16''
SATUAN PEMBAYARAN : Bh
HARGA JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN SATUAN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 1.0000 150,000 150,000.00
3 Kepala Tukang L.03 175,000 0.00
4 Mandor L.04 185,000 0.00
JUMLAH HARGA TENAGA 150,000.00
B. BAHAN
1 Exhaust fan 16INCH Bh 1.00 850,000 850,000.00
JUMLAH HARGA BAHAN 850,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,000,000.00
E. OVERHEAD & PROFIT 10,0 % x D 100,000.00

F. HARGA SATUAN PEKERJAAN ( D + E ) 1,100,000.00

84 ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir.7
JENIS PEKERJAAN Pemasangan 1 buah exhaust fan 12''
SATUAN PEMBAYARAN : Bh
HARGA JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN SATUAN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 1.0000 150,000 150,000.00
3 Kepala Tukang L.03 175,000 0.00
4 Mandor L.04 185,000 0.00
JUMLAH HARGA TENAGA 150,000.00
B. BAHAN
1 Exhaust fan 16INCH Bh 1.00 480,000 480,000.00
JUMLAH HARGA BAHAN 480,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 630,000.00
E. OVERHEAD & PROFIT 10,0 % x D 63,000.00

F. HARGA SATUAN PEKERJAAN ( D + E ) 693,000.00

85 ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. Taksir.7
JENIS PEKERJAAN Pemasangan 1 buah exhaust fan 10''
SATUAN PEMBAYARAN : Bh
HARGA JUMLAH HARGA (Rp.)
NO. KOMPONEN SATUAN KOEFISIEN SATUAN
(Rp.)
A. TENAGA
1 Pekerja L.01
2 Tukang Listrik L.02 1.0000 150,000 150,000.00
3 Kepala Tukang L.03 175,000 0.00
4 Mandor L.04 185,000 0.00
150,000.00
B. BAHAN
1 Exhaust fan 16INCH Bh 1.00 455,000 455,000.00
JUMLAH HARGA BAHAN 455,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 605,000.00
E. OVERHEAD & PROFIT 10,0 % x D 60,500.00

F. HARGA SATUAN PEKERJAAN ( D + E ) 665,500.00


86 Pembuatan dan Pemasangan Pintu Kaca 2 Daun Rangka Alumunium uk. x m + Kusen + Sunblast + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 3.477 120,000.00 417,180.00
2 Tukang Khusus Aluminium L.02 OH 3.845 150,000.00 576,757.50
3 Kepala Tukang L.03 OH 0.098 175,000.00 17,072.13
4 Mandor L.04 OH 0.031 185,000.00 5,823.62
-
-
JUMLAH TENAGA KERJA 1,016,833.24
B BAHAN
1 Kusen Aluminium m 7.450 150,000.00 1,117,500.00
2 Pintu Alluminium m 12.012 200,000.00 2,402,400.00
3 Profil Kaca m 12.285 7,500.00 92,137.50
4 Sealant Tube 5.207 30,000.00 156,213.00
5 Kaca tebal 5 mm m2 2.730 150,000.00 409,500.00
6 Sunblast m2 2.730 88,000.00 240,240.00
7 Engsel Pintu Set 6.000 75,000.00 450,000.00
8 Kunci Set Set 1.000 350,000.00 350,000.00
9 Grendel Tanam Set 2.000 150,000.00 300,000.00
-
-
JUMLAH TENAGA BAHAN 5,517,990.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,534,823.74


E. Overhead & Profit 0% X D 653,482.37
F. Harga Satuan Pekerjaan (D+E) 7,188,306.11

DIVISI 5 / 5.1.1.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.5
87 JENIS PEKERJAAN Pemasangan 1 buah wastafel TOTO
SATUAN PEMBAYARAN Bh

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 1.20 120,000 144,000.00
2 Tukang Batu (L.02) OH 1.45 150,000 217,500.00
3 Kepala Tukang (L.03) OH 0.15 175,000 26,250.00
4 Mandor (L.04) OH 0.06 185,000 11,100.00
JUMLAH HARGA TENAGA 398,850.00
B. BAHAN
1 Wastafel Unit 1.20 1,804,000 2,164,800.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 105,000 1,050.00
4 Perlengkapan 12.00 % 0.12 750,000 90,000.00
JUMLAH HARGA BAHAN 2,262,810.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,661,660.00
E. OVERHEAD & PROFIT 10,0 % x D 266,166.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,927,826.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.35
88 JENIS PEKERJAAN Pemasangan keramik dinding 30 x60
SATUAN PEMBAYARAN :M2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik kk. 30 x 30 cm Doos 1.05 150,000 157,500.00
JUMLAH HARGA BAHAN 157,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 306,600.00
E. OVERHEAD & PROFIT 10,0 % x D 30,660.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 337,260.00

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.16
89 JENIS PEKERJAAN Pengecatan dengan cat minyak
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.2 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.0025 185,000 462.50
JUMLAH HARGA TENAGA 36,362.50
B. BAHAN
1 CAT MINYAK Kg 0.10 34,000 3,400.00
2 Kuas Bh 0.01 10,000 100.00
JUMLAH HARGA BAHAN 3,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 39,862.50
E. OVERHEAD & PROFIT 10,0 % x D 3,986.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 43,848.75
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.4
90 JENIS PEKERJAAN Pemasangan urinoir
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.00 150,000 150,000.00
3 Kepala Tukang (L.03) OH 0.10 175,000 17,500.00
4 Mandor (L.04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 296,750.00
B. BAHAN
1 Urinoir Unit 1.00 1,800,000 1,800,000.00
2 Semen Portland Kg 1.00 1,160 1,160.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Perlengkapan 30 % 0.10 1,800,000 180,000.00
JUMLAH HARGA BAHAN 1,982,310.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,279,060.00
E. OVERHEAD & PROFIT 10,0 % x D 227,906.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,506,966.00

91 Pembuatan 1 m2 Partisi Kaca Alumunium


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.204 120,000.00 24,504.00
2 Tukang Khusus Aluminium L.02 OH 0.339 150,000.00 50,880.00
3 Kepala Tukang L.03 OH 0.034 175,000.00 5,936.00
4 Mandor L.04 OH 0.010 185,000.00 1,857.40
-
-
JUMLAH TENAGA KERJA 83,177.40
B BAHAN
Profil Alluminium m 3.500 150,000.00 525,000.00
Skrup Fixer buah 8.000 950.00 7,600.00
Sealant tube 0.290 30,000.00 8,700.00
Kaca tebal 5 mm m 1.000 150,000.00 150,000.00
-
-
-
-
-
-
-
JUMLAH TENAGA BAHAN 691,300.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 774,477.40


E. Overhead & Profit 0% X D 77,447.74
F. Harga Satuan Pekerjaan (D+E) 851,925.14

92 Pemasangan 1 roll pipa flexible 4"


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1 120,000.00 120,000.00
Kepala Tukang L.03 OH 1 175,000.00 175,000.00
Mandor L.04 OH 1 185,000.00 185,000.00
JUMLAH TENAGA KERJA 480,000.00
B BAHAN
Pipa Flexible 6" roll 1 160,000.00 160,000.00
Perlatan ls 1 48,000.00 48,000.00
JUMLAH TENAGA BAHAN 208,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 688,000.00


E. Overhead & Profit 10% X D 68,800.00
F. Harga Satuan Pekerjaan (D+E) 756,800.00

93 Pengadaan dan instalasi pintu kaca alumunium uk. 0,8 x 2,15 (p1)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.720 120,000.00 86,400.00
2 Tukang Khusus Aluminium L.02 OH 2.100 150,000.00 315,000.00
3 Kepala Tukang L.03 OH 0.210 175,000.00 36,750.00
4 Mandor L.04 OH 0.030 185,000.00 5,550.00
-
-
JUMLAH TENAGA KERJA 443,700.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.350 30,000.00 10,500.00
II Daun Pintu -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.630 7,500.00 49,725.00
3 Sealant tube 0.400 85,000.00 34,000.00
4 Kaca tebal 5 mm m2 1.720 150,000.00 258,000.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 1.720 50,000.00 86,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,239,185.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,682,885.00


E. Overhead & Profit - 368,288.50
F. Harga Satuan Pekerjaan (D+E) 4,051,173.50

94 Pengadaan dan instalasi pintu kaca alumunium uk. 0,9 x 2,15 (P1)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.780 120,000.00 93,600.00
2 Tukang Khusus Aluminium L.02 OH 2.270 150,000.00 340,500.00
3 Kepala Tukang L.03 OH 0.220 175,000.00 38,500.00
4 Mandor L.04 OH 0.040 185,000.00 7,400.00
-
-
JUMLAH TENAGA KERJA 480,000.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.930 150,000.00 1,039,500.00
2 Sekrup Fixer buah 12.600 950.00 11,970.00
3 Sealant tube 0.370 30,000.00 11,100.00
II Daun Pintu -
1 Alumunium Profil m 6.900 150,000.00 1,035,000.00
2 Profil Alumunium T m 7.080 7,500.00 53,100.00
3 Sealant tube 0.425 85,000.00 36,146.25
4 Kaca tebal 5 mm m2 2.150 150,000.00 322,500.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 2.150 50,000.00 107,500.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,459,566.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,939,566.25


E. Overhead & Profit - 393,956.63
F. Harga Satuan Pekerjaan (D+E) 4,333,522.88

95 Pengadaan dan Instalasi Sakelar Ganda Taksir.2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang Listrik L.02 OH 0.14 150,000.00 21,000.00
Kepala Tukang L.03 OH 0.01 175,000.00 1,750.00
Mandor L.04 OH 0.01 185,000.00 1,850.00
JUMLAH TENAGA KERJA 24,600.00
B BAHAN
Saklar Ganda bh 1.00 29,000.00 29,000.00
Inbow dus bh 1.00 5,000.00 5,000.00
Semen Portland kg 0.20 1,160.00 232.00
Kabel NYM 3 x 2,5 mm2 M' 7.50 15,000.00 112,500.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750.00 33,000.00
T-Dus PVC HI "EGA" Dia. 20mm Bh 1.00 4,250.00 4,250.00
JUMLAH TENAGA BAHAN 183,982.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 208,582.00


E. Overhead & Profit - 20,858.20
F. Harga Satuan Pekerjaan (D+E) 229,440.20

96 Pemasangan 1 buah Spoelhoek


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 3.300 120,000.00 396,000.00
Tukang batu L.02 OH 1.1000 150,000.00 165,000.00
Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.1600 185,000.00 29,600.00
JUMLAH TENAGA KERJA 592,350.00
B BAHAN
Spoelhoek Unit 1 7800000 7,800,000.00
Perlengkapan Ls 6% x closet 468,000.00 468,000.00
JUMLAH TENAGA BAHAN 8,268,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 8,860,350.00


E. Overhead & Profit - 886,035.00
F. Harga Satuan Pekerjaan (D+E) 9,746,385.00

97 Pemasangan 1m2 Keramik Ukuran (25 x 40 cm)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.9 120,000.00 108,000.00
Tukang Batu L.02 OH 0.45 150,000.00 67,500.00
Kepala Tukang L.03 OH 0.045 175,000.00 7,875.00
Mandor L.04 OH 0.045 185,000.00 8,325.00
JUMLAH TENAGA KERJA 191,700.00
B BAHAN
Keramik Uk. 25 x 40 cm Bh 10 6500 65,000.00
Semen Portland Kg 9.6 1160 11,136.00
Pasir Pasang M3 0.045 105000 4,725.00
Semen warna Kg 1.5 5500 8,250.00
JUMLAH TENAGA BAHAN 89,111.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 280,811.00


E. Overhead & Profit - 28,081.10
F. Harga Satuan Pekerjaan (D+E) 308,892.10

98 Pemasangan 1 m² rooster keramik 20x40


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.3 120,000.00 36,000.00
Tukang Batu L.02 OH 0.1 150,000.00 15,000.00
Kepala Tukang L.03 OH 0.01 175,000.00 1,750.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 55,525.00
B BAHAN
Rooster keramik 20x40 Bh 12.5 65000 812,500.00
Semen Portland Kg 9.6 1160 11,136.00
Pasir Pasang M3 0.045 105000 4,725.00
JUMLAH TENAGA BAHAN 828,361.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 883,886.00


E. Overhead & Profit - 88,388.60
F. Harga Satuan Pekerjaan (D+E) 972,274.60

Pengadaan dan Instalasi Sakelar


99
Tunggal
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang Listrik L.02 OH 0.14 150,000.00 20,250.00
Kepala Tukang L.03 OH 0.01 175,000.00 2,362.50
Mandor L.04 OH 0.01 185,000.00 925.00
JUMLAH TENAGA KERJA 23,537.50
B BAHAN
Saklar Tunggal bh 1.00 19,000.00 19,000.00
Inbow dus bh 1.00 5,000.00 5,000.00
Semen Portland kg 0.20 1,160.00 232.00
Kabel NYM 3 x 2,5 mm2 M' 7.50 15,000.00 112,500.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,750.00 33,000.00
T-Dus PVC HI "EGA" Dia. 20mm Bh 1.00 4,250.00 4,250.00
JUMLAH TENAGA BAHAN 173,982.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 197,519.50


E. Overhead & Profit - 19,751.95
F. Harga Satuan Pekerjaan (D+E) 217,271.45

100 Pengadaan dan Instalasi Stop Kontak


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang Listrik L.02 OH 0.14 150,000.00 20,250.00
Kepala Tukang L.03 OH 0.01 175,000.00 2,362.50
Mandor L.04 OH 0.01 185,000.00 925.00
JUMLAH TENAGA KERJA 23,537.50
B BAHAN
Kabel NYM 3 x 2,5 mm2 M' 7.50 14,800.00 111,000.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,850.00 34,200.00
T-Dus PVC HI "EGA" Dia. 20mm Bh 1.00 4,500.00 4,500.00
Stop Kontak bh 1.00 27,000.00 27,000.00
Inbow dus bh 1.00 5,000.00 5,000.00
Semen Portland kg 0.20 1,160.00 232.00
JUMLAH TENAGA BAHAN 181,932.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 205,469.50


E. Overhead & Profit - 20,546.95
F. Harga Satuan Pekerjaan (D+E) 226,016.45

101 Membuat 1 m3 plat beton bertulang (150 kg besi + bekesting)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 5.300 120,000.00 636,000.00
Tukang Batu L.02 OH 0.275 150,000.00 41,250.00
Tukang Kayu L.02 OH 1.300 150,000.00 195,000.00
Tukang Besi L.02 OH 1.050 150,000.00 157,500.00
Kepala Tukang L.03 OH 0.262 175,000.00 45,850.00
Mandor L.04 OH 0.265 185,000.00 49,025.00
JUMLAH TENAGA KERJA 1,124,625.00
B BAHAN
Kayu kelas m3 0.320 1,900,000.00 608,000.00
Paku 5-12 cm kg 3.200 22,000.00 70,400.00
Minyak bekesting Liter 1.600 11,000.00 17,600.00
Besi beton polos kg 157.500 13,900.00 2,189,250.00
Kawat beton kg 2.250 20,000.00 45,000.00
Sement Portland kg 336.000 1,160.00 389,760.00
Pasir Beton m3 0.540 135,000.00 72,900.00
Kerikil kg 0.810 420,000.00 340,200.00

JUMLAH TENAGA BAHAN 3,733,110.00


C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,857,735.00


E. Overhead & Profit - 485,773.50
F. Harga Satuan Pekerjaan (D+E) 5,343,508.50

102 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 2 x 2.7 (P3)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.587 120,000.00 190,464.00
2 Tukang Khusus Aluminium L.02 OH 4.716 150,000.00 707,430.00
3 Kepala Tukang L.03 OH 0.472 175,000.00 82,533.50
4 Mandor L.04 OH 0.083 185,000.00 15,384.60
-
-
JUMLAH TENAGA KERJA 995,812.10
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 10.340 150,000.00 1,551,000.00
2 Sekrup Fixer buah 18.800 950.00 17,860.00
3 Sealant tube 0.564 30,000.00 16,920.00
II Daun Pintu -
1 Alumunium Profil m 20.680 150,000.00 3,102,000.00
2 Profil Alumunium T m 21.150 7,500.00 158,625.00
3 Sealant tube 1.269 85,000.00 107,865.00
4 Kaca tebal 5 mm m2 10.800 150,000.00 1,620,000.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 10.800 50,000.00 540,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 8,299,770.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 9,295,582.10


E. Overhead & Profit - 929,558.21
F. Harga Satuan Pekerjaan (D+E) 10,225,140.31

103 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 1.00 x 2.15 (P4)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.786 120,000.00 94,308.00
2 Tukang Khusus Aluminium L.02 OH 2.276 150,000.00 341,422.50
3 Kepala Tukang L.03 OH 0.228 175,000.00 39,832.63
4 Mandor L.04 OH 0.041 185,000.00 7,529.50
-
-
JUMLAH TENAGA KERJA 483,092.63
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.930 150,000.00 1,039,500.00
2 Sekrup Fixer buah 12.600 950.00 11,970.00
3 Sealant tube 0.378 30,000.00 11,340.00
II Daun Pintu -
1 Alumunium Profil m 6.930 150,000.00 1,039,500.00
2 Profil Alumunium T m 7.087 7,500.00 53,156.25
3 Sealant tube 0.425 85,000.00 36,146.25
4 Kaca tebal 5 mm m2 2.150 150,000.00 322,500.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 2.150 50,000.00 107,500.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,464,362.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,947,455.13


E. Overhead & Profit - 394,745.51
F. Harga Satuan Pekerjaan (D+E) 4,342,200.64

104 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 0.8 x 2.15 (P1)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.726 120,000.00 87,084.00
2 Tukang Khusus Aluminium L.02 OH 2.158 150,000.00 323,685.00
3 Kepala Tukang L.03 OH 0.216 175,000.00 37,763.25
4 Mandor L.04 OH 0.037 185,000.00 6,912.71
-
-
JUMLAH TENAGA KERJA 455,444.96
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.354 30,000.00 10,620.00
II Daun Pintu -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.638 7,500.00 49,781.25
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 1.720 150,000.00 258,000.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 1.720 50,000.00 86,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,239,212.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,694,657.46


E. Overhead & Profit - 369,465.75
F. Harga Satuan Pekerjaan (D+E) 4,064,123.21

105 Pemasangan kran diameter dan shower 5.1.1.19


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.01 120,000.00 1,200.00
Tukang L.02 OH 0.4 150,000.00 60,000.00
Kepala Tukang L.03 OH 0.04 175,000.00 7,000.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 69,125.00
B BAHAN
Kran air + shower M 1 281000 281,000.00
Sealtape Buah 0.025 3500 87.50
JUMLAH TENAGA BAHAN 281,087.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 350,212.50


E. Overhead & Profit 10% X D 35,021.25
F. Harga Satuan Pekerjaan (D+E) 385,233.75

106 Pemasangan 1 m2 dinding keramik ukuran 25cm x 20cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.7 120,000.00 84,000.00
Tukang Batu L.02 OH 0.35 150,000.00 52,500.00
Kepala Tukang L.03 OH 0.035 175,000.00 6,125.00
Mandor L.04 OH 0.035 185,000.00 6,475.00
JUMLAH TENAGA KERJA 149,100.00
B BAHAN
Ubin Keramik uk.25x20 Dos 20 4125 82,500.00
Semen Portland Kg 10.4 1160 12,064.00
Pasir Pasang Kg 0.045 115000 5,175.00
Semen Warna M3 1.62 10000 16,200.00
JUMLAH TENAGA BAHAN 115,939.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 265,039.00


E. Overhead & Profit - 26,503.90
F. Harga Satuan Pekerjaan (D+E) 291,542.90

107 Pembuatan dan Pemasangan Pintu ACP 2 Daun


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.421 120,000.00 170,520.00
2 Tukang Khusus Aluminium L.02 OH 4.378 150,000.00 656,681.25
3 Kepala Tukang L.03 OH 0.438 175,000.00 76,612.81
4 Mandor L.04 OH 0.074 185,000.00 13,666.88
-
-
JUMLAH TENAGA KERJA 917,480.94
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 9.350 150,000.00 1,402,500.00
2 Sekrup Fixer buah 17.000 950.00 16,150.00
II Daun Pintu -
1 Alumunium Profil m 8.140 150,000.00 1,221,000.00
2 Profil Alumunium T m 8.325 7,500.00 62,437.50
3 Sealant tube 0.570 85,000.00 48,450.00
4 Kaca tebal 5 mm m2 0.820 150,000.00 123,000.00
5 Aluminium composite panel (ACP) m2 3.750 425,000.00 1,593,750.00
III Aksesoris -
1 Engsel Pintu set 6.000 38,500.00 231,000.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 0.825 50,000.00 41,250.00
5 Engsel Casement unit 4.000 25,000.00 100,000.00
6 Rambuncis Bh 2.000 20,000.00 40,000.00
-
JUMLAH TENAGA BAHAN 5,449,537.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,367,018.44


E. Overhead & Profit - 636,701.84
F. Harga Satuan Pekerjaan (D+E) 7,003,720.28

108 Pengadaan dan Instalasi Pintu ACP uk. 1.5 x 2.75


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.421 120,000.00 170,520.00
2 Tukang Khusus Aluminium L.02 OH 4.378 150,000.00 656,681.25
3 Kepala Tukang L.03 OH 0.438 175,000.00 76,612.81
4 Mandor L.04 OH 0.074 185,000.00 13,666.88
-
-
JUMLAH TENAGA KERJA 917,480.94
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 9.350 150,000.00 1,402,500.00
2 Sekrup Fixer buah 17.000 950.00 16,150.00
3 Sealant tube 0.510 30,000.00
II Daun Pintu -
1 Alumunium Profil m 8.140 150,000.00 1,221,000.00
2 Profil Alumunium T m 8.325 7,500.00 62,437.50
3 Sealant tube 0.574 85,000.00 48,768.75
4 Kaca tebal 5 mm m2 0.825 150,000.00 123,750.00
5 Aluminium composite panel (ACP) m2 3.300 425,000.00 1,402,500.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 0.825 50,000.00 41,250.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 4.000 25,000.00 100,000.00
6 Rambuncis Bh 2.000 20,000.00 40,000.00
-
JUMLAH TENAGA BAHAN 5,643,856.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,561,337.19


E. Overhead & Profit - 656,133.72
F. Harga Satuan Pekerjaan (D+E) 7,217,470.91

109 Pengadaan Dan Instalasi Pintu ACP uk. 1,75 x 2,10


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.342 120,000.00 160,992.00
2 Tukang Khusus Aluminium L.02 OH 4.238 150,000.00 635,658.75
3 Kepala Tukang L.03 OH 0.424 175,000.00 74,160.19
4 Mandor L.04 OH 0.070 185,000.00 12,873.22
-
-
JUMLAH TENAGA KERJA 883,684.16
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.470 150,000.00 1,270,500.00
2 Sekrup Fixer buah 15.400 950.00 14,630.00
3 Sealant tube 30,000.00
II Daun Pintu -
1 Alumunium Profil m 8.690 150,000.00 1,303,500.00
2 Profil Alumunium T m 8.888 7,500.00 66,656.25
3 Sealant tube 1.000 85,000.00 85,000.00
4 Kaca tebal 5 mm m2 0.963 150,000.00 144,375.00
5 Aluminium composite panel (ACP) m2 4.000 425,000.00 1,700,000.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 1.500 50,000.00 75,000.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 4.000 25,000.00 100,000.00
6 Rambuncis Bh 2.000 20,000.00 40,000.00
-
JUMLAH TENAGA BAHAN 5,985,161.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,868,845.41


E. Overhead & Profit - 686,884.54
F. Harga Satuan Pekerjaan (D+E) 7,555,729.95

110 Pengadaan Dan Instalasi Pintu ACP uk. 1,40 x 2,35


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.952 120,000.00 114,180.00
2 Tukang Khusus Aluminium L.02 OH 2.596 150,000.00 389,347.50
3 Kepala Tukang L.03 OH 0.260 175,000.00 45,423.88
4 Mandor L.04 OH 0.050 185,000.00 9,218.92
-
-
JUMLAH TENAGA KERJA 558,170.30
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.250 150,000.00 1,237,500.00
2 Sekrup Fixer buah 15.000 950.00 14,250.00
3 Sealant tube 0.450 30,000.00
II Daun Pintu -
1 Alumunium Profil m 7.920 150,000.00 1,188,000.00
2 Profil Alumunium T m 8.100 7,500.00 60,750.00
3 Sealant tube 1.000 85,000.00 85,000.00
4 Kaca tebal 5 mm m2 0.770 150,000.00 115,500.00
5 Aluminium composite panel (ACP) m2 4.000 425,000.00 1,700,000.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast 1.5 0.770 50,000.00 38,500.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 2.000 25,000.00 50,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 5,410,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,968,170.30


E. Overhead & Profit - 596,817.03
F. Harga Satuan Pekerjaan (D+E) 6,564,987.32

111 Pengadaan Dan Instalasi Pintu ACP uk. 1,30 x 2,35


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.919 120,000.00 110,328.00
2 Tukang Khusus Aluminium L.02 OH 2.532 150,000.00 379,773.75
3 Kepala Tukang L.03 OH 0.253 175,000.00 44,306.94
4 Mandor L.04 OH 0.048 185,000.00 8,889.07
-
-
JUMLAH TENAGA KERJA 543,297.75
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.030 150,000.00 1,204,500.00
2 Sekrup Fixer buah 14.600 950.00 13,870.00
3 Sealant tube
II Daun Pintu -
1 Alumunium Profil m 7.700 150,000.00 1,155,000.00
2 Profil Alumunium T m 7.875 7,500.00 59,062.50
3 Sealant tube 1.000 85,000.00 85,000.00
4 Kaca tebal 5 mm m2 0.715 150,000.00 107,250.00
5 Aluminium composite panel (ACP) m2 3.500 425,000.00 1,487,500.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 0.715 50,000.00 35,750.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 3.000 25,000.00 75,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 5,143,432.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,686,730.25


E. Overhead & Profit - 568,673.03
F. Harga Satuan Pekerjaan (D+E) 6,255,403.28

112 Pengadaan Dan Instalasi Jendela Kaca Alumunium uk. 0,80 x 0,75
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.593 120,000.00 71,196.00
2 Tukang Khusus Aluminium L.02 OH 1.074 150,000.00 161,145.00
3 Kepala Tukang L.03 OH 0.107 175,000.00 18,800.25
4 Mandor L.04 OH 0.012 185,000.00 2,218.15
-
-
JUMLAH TENAGA KERJA 253,359.40
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.410 150,000.00 511,500.00
2 Sekrup Fixer buah 6.200 950.00 5,890.00
3 Sealant tube 0.186 85,000.00 15,810.00
II Daun Jendela -
1 Alumunium Profil m 3.410 150,000.00 511,500.00
2 Profil Alumunium T m 3.488 7,500.00 26,156.25
3 Sealant tube 0.209 85,000.00 17,786.25
4 Kaca tebal 5 mm m2 0.600 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.600 50,000.00 30,000.00
-
-
JUMLAH TENAGA BAHAN 1,188,642.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,442,001.90


E. Overhead & Profit - 144,200.19
F. Harga Satuan Pekerjaan (D+E) 1,586,202.09

113 Pengadaan Dan Instalasi Jendela Kaca Alumunium uk. 0,90 x 0,75
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.609 120,000.00 73,128.00
2 Tukang Khusus Aluminium L.02 OH 1.101 150,000.00 165,078.75
3 Kepala Tukang L.03 OH 0.110 175,000.00 19,259.19
4 Mandor L.04 OH 0.013 185,000.00 2,376.33
-
-
JUMLAH TENAGA KERJA 259,842.26
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.630 150,000.00 544,500.00
2 Sekrup Fixer buah 6.600 950.00 6,270.00
3 Sealant tube 0.198 85,000.00 16,830.00
II Daun Jendela -
1 Alumunium Profil m 3.630 150,000.00 544,500.00
2 Profil Alumunium T m 3.713 7,500.00 27,843.75
3 Sealant tube 0.223 85,000.00 18,933.75
4 Kaca tebal 5 mm m2 0.675 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.675 50,000.00 33,750.00
-
-
JUMLAH TENAGA BAHAN 1,262,627.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,522,469.76


E. Overhead & Profit - 152,246.98
F. Harga Satuan Pekerjaan (D+E) 1,674,716.74

114 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 0.75 (J2)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.181 120,000.00 141,744.00
2 Tukang Khusus Aluminium L.02 OH 2.153 150,000.00 322,998.75
3 Kepala Tukang L.03 OH 0.215 175,000.00 37,683.19
4 Mandor L.04 OH 0.024 185,000.00 4,400.23
-
-
JUMLAH TENAGA KERJA 506,826.16
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.354 85,000.00 30,090.00
II Daun Jendela -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.638 7,500.00 49,781.25
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 2.550 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 2.550 50,000.00 127,500.00
-
-
JUMLAH TENAGA BAHAN 2,339,432.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,846,258.66


E. Overhead & Profit - 284,625.87
F. Harga Satuan Pekerjaan (D+E) 3,130,884.53

115 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 1.8 x 1.5 (J3)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.373 120,000.00 164,784.00
2 Tukang Khusus Aluminium L.02 OH 2.517 150,000.00 377,617.50
3 Kepala Tukang L.03 OH 0.252 175,000.00 44,055.38
4 Mandor L.04 OH 0.034 185,000.00 6,351.05
-
-
JUMLAH TENAGA KERJA 592,807.93
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.140 150,000.00 1,221,000.00
2 Sekrup Fixer buah 14.800 950.00 14,060.00
3 Sealant tube 0.444 85,000.00 37,740.00
II Daun Jendela -
1 Alumunium Profil m 8.140 150,000.00 1,221,000.00
2 Profil Alumunium T m 8.325 7,500.00 62,437.50
3 Sealant tube 0.500 85,000.00 42,457.50
4 Kaca tebal 5 mm m2 5.100 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 5.100 50,000.00 255,000.00
-
-
JUMLAH TENAGA BAHAN 2,993,695.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,586,502.93


E. Overhead & Profit - 358,650.29
F. Harga Satuan Pekerjaan (D+E) 3,945,153.22

116 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.8 x 1.5 (J1)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.718 120,000.00 86,136.00
2 Tukang Khusus Aluminium L.02 OH 1.280 150,000.00 191,970.00
3 Kepala Tukang L.03 OH 0.128 175,000.00 22,396.50
4 Mandor L.04 OH 0.019 185,000.00 3,444.70
-
-
JUMLAH TENAGA KERJA 303,947.20
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.060 150,000.00 759,000.00
2 Sekrup Fixer buah 9.200 950.00 8,740.00
3 Sealant tube 0.276 85,000.00 23,460.00
II Daun Jendela -
1 Alumunium Profil m 5.060 150,000.00 759,000.00
2 Profil Alumunium T m 5.175 7,500.00 38,812.50
3 Sealant tube 0.311 85,000.00 26,392.50
4 Kaca tebal 5 mm m2 1.200 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 1.200 50,000.00 60,000.00
-
-
JUMLAH TENAGA BAHAN 1,745,405.00
C. PERALATAN

JUMLAH TENAGA ALAT 2,049,352.20


204,935.22
D. Jumlah (A+B+C) 2,254,287.42

117 Pengadaan dan Instalasi Jendela Kaca Alumunium uk. 0.9 x 1.5 (J4)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.741 120,000.00 88,968.00
2 Tukang Khusus Aluminium L.02 OH 1.324 150,000.00 198,547.50
3 Kepala Tukang L.03 OH 0.132 175,000.00 23,163.88
4 Mandor L.04 OH 0.020 185,000.00 3,683.35
-
-
JUMLAH TENAGA KERJA 314,362.73
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.280 150,000.00 792,000.00
2 Sekrup Fixer buah 9.600 950.00 9,120.00
3 Sealant tube 0.288 85,000.00 24,480.00
II Daun Jendela -
1 Alumunium Profil m 5.280 150,000.00 792,000.00
2 Profil Alumunium T m 5.400 7,500.00 40,500.00
3 Sealant tube 0.324 85,000.00 27,540.00
4 Kaca tebal 5 mm m2 1.350 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 1.350 50,000.00 67,500.00
-
-
JUMLAH TENAGA BAHAN 1,823,140.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,137,502.73


E. Overhead & Profit - 213,750.27
F. Harga Satuan Pekerjaan (D+E) 2,351,253.00

118 Pengadaan dan Instalasi Bouven uk. 0.85 x 0.75 (J5)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.201 140,000.00 28,189.00
2 Tukang Khusus Aluminium L.02 OH 0.287 160,000.00 45,986.00
3 Kepala Tukang L.03 OH 0.029 180,000.00 5,173.43
4 Mandor L.04 OH 0.010 185,000.00 1,927.24
-
-
JUMLAH TENAGA KERJA 81,275.66
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.520 150,000.00 528,000.00
2 Sekrup Fixer buah 6.400 950.00 6,080.00
3 Sealant tube 0.192 85,000.00 16,320.00
II Profil Kaca -
1 Profil Alumunium T m 3.600 7,500.00 27,000.00
3 Sealant tube 0.216 85,000.00 18,360.00
4 Kaca tebal 5 mm m2 0.638 150,000.00
III Aksesoris -
3 Sunblast m2 0.638 50,000.00 31,875.00
-
-
JUMLAH TENAGA BAHAN 627,635.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 708,910.66


E. Overhead & Profit - 70,891.07
F. Harga Satuan Pekerjaan (D+E) 779,801.73

ITEM PEMBAYARAN NO. : 4.4.3.9.a


119 JENIS PEKERJAAN Pemasangan 1 m2 lantai granit kasar ukuran 60 x 60
SATUAN PEMBAYARAN :M2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Granit 60/60 Bh 3.05 90,000 274,500.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Semen Warna Kg 1.62 10,000 16,200.00
4 Pasir Pasang M3 0.050 115,000 5,750.00
JUMLAH HARGA BAHAN 305,950.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 359,380.40
E. OVERHEAD & PROFIT 10,0 % x D 35,938.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 395,318.44

121 Pengadaan dan Instalasi Pintu uk. 1.5 x 2.15 (P1)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.279 120,000.00 153,528.00
2 Tukang Khusus Aluminium L.02 OH 4.115 150,000.00 617,216.25
3 Kepala Tukang L.03 OH 0.411 175,000.00 72,008.56
4 Mandor L.04 OH 0.066 185,000.00 12,234.98
-
-
JUMLAH TENAGA KERJA 854,987.79
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.030 150,000.00 1,204,500.00
2 Sekrup Fixer buah 14.600 950.00 13,870.00
3 -
II Daun Pintu -
1 Alumunium Profil m 16.060 150,000.00 2,409,000.00
2 Profil Alumunium T m 16.425 7,500.00 123,187.50
3 Sealant tube 0.986 85,000.00 83,767.50
4 Kaca tebal 5 mm m2 6.450 150,000.00 967,500.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 6.450 50,000.00 322,500.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 6,309,825.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 7,164,812.79


E. Overhead & Profit - 716,481.28
F. Harga Satuan Pekerjaan (D+E) 7,881,294.07

122 Pengadaan dan Instalasi Pintu uk. 1.35 x 2.15 (P1)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.234 120,000.00 148,110.00
2 Tukang Khusus Aluminium L.02 OH 4.026 150,000.00 603,913.13
3 Kepala Tukang L.03 OH 0.403 175,000.00 70,456.53
4 Mandor L.04 OH 0.064 185,000.00 11,772.38
-
-
JUMLAH TENAGA KERJA 834,252.04
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 7.700 150,000.00 1,155,000.00
2 Sekrup Fixer buah 14.000 950.00 13,300.00
3 Sealant -
II Daun Pintu -
1 Alumunium Profil m 15.400 150,000.00 2,310,000.00
2 Profil Alumunium T m 15.750 7,500.00 118,125.00
3 Sealant tube 0.945 85,000.00 80,325.00
4 Kaca tebal 5 mm m2 5.805 150,000.00 870,750.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 2.000 285,000.00 570,000.00
3 Sunblast m2 5.805 50,000.00 290,250.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 6,023,250.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 6,857,502.04


E. Overhead & Profit - 685,750.20
F. Harga Satuan Pekerjaan (D+E) 7,543,252.24

123 Pengadaan dan Instalasi Pintu uk. 0.8 x 2.15 (P1)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.726 120,000.00 87,084.00
2 Tukang Khusus Aluminium L.02 OH 2.158 150,000.00 323,685.00
3 Kepala Tukang L.03 OH 0.216 175,000.00 37,763.25
4 Mandor L.04 OH 0.037 185,000.00 6,912.71
-
-
JUMLAH TENAGA KERJA 455,444.96
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.490 150,000.00 973,500.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant -
II Daun Pintu -
1 Alumunium Profil m 6.490 150,000.00 973,500.00
2 Profil Alumunium T m 6.638 7,500.00 49,781.25
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 1.720 150,000.00 258,000.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 1.720 50,000.00 86,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,228,592.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,684,037.46


E. Overhead & Profit - 368,403.75
F. Harga Satuan Pekerjaan (D+E) 4,052,441.21

124 pemasangan bouven


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.095 120,000.00 11,448.00
2 Tukang Khusus Aluminium L.02 OH 0.120 150,000.00 17,955.00
3 Kepala Tukang L.03 OH 0.012 175,000.00 2,094.75
4 Mandor L.04 OH 0.005 185,000.00 892.44
-
-
JUMLAH TENAGA KERJA 32,390.19
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 1.980 150,000.00 297,000.00
2 Sekrup Fixer buah 3.600 950.00 3,420.00
3 Sealant tube 0.108 30,000.00 3,240.00
II Profil Kaca -
1 Profil Alumunium T m 2.025 7,500.00 15,187.50
3 Sealant tube 0.122 85,000.00 10,327.50
4 Kaca tebal 5 mm m2 0.180 150,000.00 27,000.00
III Aksesoris -
3 Sunblast m2 0.180 50,000.00 9,000.00
-
-
JUMLAH TENAGA BAHAN 365,175.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 397,565.19


E. Overhead & Profit - 39,756.52
F. Harga Satuan Pekerjaan (D+E) 437,321.71

125 Pengadaan dan instalasi lampu TL +Aksesoris Taksir.3


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang L.02 OH 0.14 150,000.00 20,250.00
Kepala Tukang L.03 OH 0.01 175,000.00 2,362.50
Mandor L.04 OH 0.01 185,000.00 925.00
JUMLAH TENAGA KERJA 23,537.50
B BAHAN
Kabel NYM 2 x 2,5 mm2 M' 15.00 13,500.00 202,500.00
Pipa Konduit PVC HI "EGA" Dia. 20mm M' 12.00 2,850.00 34,200.00
T-Dus PVC HI "EGA" Dia. 20mm Bh 1.00 4,500.00 4,500.00
1 set Lampu TL LED 36 Watt + kap bh 1.00 195,000.00 195,000.00
JUMLAH TENAGA BAHAN 436,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 459,737.50


E. Overhead & Profit - 45,973.75
F. Harga Satuan Pekerjaan (D+E) 505,711.25

DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
126 JENIS PEKERJAAN Pemasangan Shower Spray
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.4 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.04 175,000 7,000.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 69,125.00
B. BAHAN
1 Shower M 1.00 145,000 145,000.00
2 Sealtape Buah 0.025 3,500 87.50
JUMLAH HARGA BAHAN 145,087.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 214,212.50


E. OVERHEAD & PROFIT 10,0 % x D 21,421.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 235,633.75

127 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 1.1 x 2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.786 120,000.00 94,308.00
2 Tukang Khusus Aluminium L.02 OH 2.276 150,000.00 341,422.50
3 Kepala Tukang L.03 OH 0.228 175,000.00 39,832.63
4 Mandor L.04 OH 0.041 185,000.00 7,529.50
-
-
JUMLAH TENAGA KERJA 483,092.63
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.930 150,000.00 1,039,500.00
2 Sekrup Fixer buah 12.600 950.00 11,970.00
3 Sealant tube 0.378 30,000.00 11,340.00
II Daun Pintu -
1 Alumunium Profil m 6.930 150,000.00 1,039,500.00
2 Profil Alumunium T m 7.087 7,500.00 53,156.25
3 Sealant tube 0.425 85,000.00 36,146.25
4 Kaca tebal 5 mm m2 2.150 150,000.00 322,500.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 2.150 50,000.00 107,500.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,464,362.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,947,455.13


E. Overhead & Profit - 394,745.51
F. Harga Satuan Pekerjaan (D+E) 4,342,200.64

128 Pembuatan dan Pemasangan Pintu alumunium kaca 1,9 x 0,77


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.380 120,000.00 285,600.00
2 Tukang Khusus Aluminium L.02 OH 2.520 150,000.00 378,000.00
3 Kepala Tukang L.03 OH 0.600 175,000.00 105,000.00
4 Mandor L.04 OH 0.600 185,000.00 111,000.00
-
-
JUMLAH TENAGA KERJA 879,600.00
B BAHAN
I Kusen Jendela
1 KUSEN ALUMUNIUM M 6.000 150,000.00 900,000.00
2 PINTU ALUMUNIUM M 5.914 200,000.00 1,182,800.00
3 PROFIL KACA M 6.040 7,500.00 45,300.00
II -
SEALANT TUBE 3.500 85,000.00 297,500.00
KACA TEBAL 5 MM M2 1.500 150,000.00 225,000.00
SUNBLAST M2 2.000 50,000.00 100,000.00
ENGSEL PINTU SET 3.000 75,000.00 225,000.00
III -
KUNCI SET SET 1.000 350,000.00 350,000.00

-
-
JUMLAH TENAGA BAHAN 3,325,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,205,200.00


E. Overhead & Profit - 420,520.00
F. Harga Satuan Pekerjaan (D+E) 4,625,720.00

129 Pembuatan dan Pemasangan Jendela Kaca 0,9 x 1,23


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.700 120,000.00 84,000.00
2 Tukang Khusus Aluminium L.02 OH 1.230 150,000.00 184,500.00
3 Kepala Tukang L.03 OH 0.120 175,000.00 21,000.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 293,200.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 4.680 150,000.00 702,000.00
2 Sekrup Fixer buah 8.520 950.00 8,094.00
3 Sealant tube 0.250 30,000.00 7,500.00
II Daun Jendela -
1 Alumunium Profil m 4.680 150,000.00 702,000.00
2 Profil Alumunium T m 4.800 7,500.00 36,000.00
3 Sealant tube 0.280 85,000.00 23,800.00
4 Kaca tebal 5 mm m2 1.100 150,000.00
III Aksesoris -
1 Engsel Casement unit 3.000 25,000.00 75,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 1.350 50,000.00 67,500.00
-
-
JUMLAH TENAGA BAHAN 1,641,894.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,935,094.00


E. Overhead & Profit - 193,509.40
F. Harga Satuan Pekerjaan (D+E) 2,128,603.40

130 Pembuatan dan Pemasangan Jendela Kaca 1,23 x 1,48


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.800 120,000.00 216,000.00
2 Tukang Khusus Aluminium L.02 OH 1.600 150,000.00 240,000.00
3 Kepala Tukang L.03 OH 0.850 175,000.00 148,750.00
4 Mandor L.04 OH 0.850 185,000.00 157,250.00
-
-
JUMLAH TENAGA KERJA 762,000.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.000 150,000.00 900,000.00
2 Sekrup Fixer buah 12.000 950.00 11,400.00
3 Sealant tube 1.500 30,000.00 45,000.00
II Daun Jendela -
1 Alumunium Profil m 7.000 150,000.00 1,050,000.00
2 Profil Alumunium T m 7.000 7,500.00 52,500.00
3 Sealant tube 2.000 85,000.00 170,000.00
4 Kaca tebal 5 mm m2 2.000 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 2.000 50,000.00 100,000.00
-
-
JUMLAH TENAGA BAHAN 2,398,900.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,160,900.00


E. Overhead & Profit - 316,090.00
F. Harga Satuan Pekerjaan (D+E) 3,476,990.00

131 Pembuatan dan Pemasangan Jendela Kaca 1,23 x 2,38


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.600 120,000.00 192,000.00
2 Tukang Khusus Aluminium L.02 OH 1.400 150,000.00 210,000.00
3 Kepala Tukang L.03 OH 0.800 175,000.00 140,000.00
4 Mandor L.04 OH 0.800 185,000.00 148,000.00
-
-
JUMLAH TENAGA KERJA 690,000.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.000 150,000.00 1,200,000.00
2 Sekrup Fixer buah 18.000 950.00 17,100.00
3 Sealant tube 1.000 30,000.00 30,000.00
II Daun Jendela -
1 Alumunium Profil m 9.000 150,000.00 1,350,000.00
2 Profil Alumunium T m 8.000 7,500.00 60,000.00
3 Sealant tube 1.000 85,000.00 85,000.00
4 Kaca tebal 5 mm m2 2.900 150,000.00 435,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 2.000 50,000.00 100,000.00
-
-
JUMLAH TENAGA BAHAN 3,347,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 4,037,100.00


E. Overhead & Profit - 403,710.00
F. Harga Satuan Pekerjaan (D+E) 4,440,810.00

132 Pembuatan dan Pemasangan Jendela Kaca 1 x 0,55


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.580 120,000.00 69,600.00
2 Tukang Khusus Aluminium L.02 OH 1.000 150,000.00 150,000.00
3 Kepala Tukang L.03 OH 0.100 175,000.00 17,500.00
4 Mandor L.04 OH 0.030 185,000.00 5,550.00
-
-
JUMLAH TENAGA KERJA 242,650.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.400 150,000.00 510,000.00
2 Sekrup Fixer buah 6.200 950.00 5,890.00
3 Sealant tube 0.180 30,000.00 5,400.00
II Daun Jendela -
1 Alumunium Profil m 3.400 150,000.00 510,000.00
2 Profil Alumunium T m 3.480 7,500.00 26,100.00
3 Sealant tube 0.200 85,000.00 17,000.00
4 Kaca tebal 5 mm m2 0.550 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.550 50,000.00 27,500.00
-
-
JUMLAH TENAGA BAHAN 1,171,890.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,414,540.00


E. Overhead & Profit - 141,454.00
F. Harga Satuan Pekerjaan (D+E) 1,555,994.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.4
133 JENIS PEKERJAAN Pemasangan plat stainless
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 1.050 120,000 126,000.00
2 Tukang Las Biasa L.03 OH 1.050 150,000 157,500.00
3 Kepala Tukang L.03 OH 0.105 175,000 18,375.00
4 Mandor L.04 OH 0.052 185,000 9,620.00
JUMLAH HARGA TENAGA 311,495.00
B. BAHAN
2 Besi Plat Baja m2 1.000 452,000 452,000.00
3 0.00
JUMLAH HARGA BAHAN 452,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 763,495.00


E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 763,495.00

134 Pengadaan dan Instalasi Pintu Kaca Alumunium uk. 0.7 x 2.1 (P1)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.726 120,000.00 87,084.00
2 Tukang Khusus Aluminium L.02 OH 2.158 150,000.00 323,685.00
3 Kepala Tukang L.03 OH 0.216 175,000.00 37,763.25
4 Mandor L.04 OH 0.037 185,000.00 6,912.71
-
-
JUMLAH TENAGA KERJA 455,444.96
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.000 150,000.00 900,000.00
2 Sekrup Fixer buah 11.800 950.00 11,210.00
3 Sealant tube 0.354 30,000.00 10,620.00
II Daun Pintu -
1 Alumunium Profil m 6.000 150,000.00 900,000.00
2 Profil Alumunium T m 6.000 7,500.00 45,000.00
3 Sealant tube 0.398 85,000.00 33,851.25
4 Kaca tebal 5 mm m2 1.260 150,000.00 189,000.00
III Aksesoris -
1 Engsel Pintu set 2.000 38,500.00 77,000.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 1.000 50,000.00 50,000.00
4 Door closer set 1.000 500,000.00 500,000.00
-
JUMLAH TENAGA BAHAN 3,001,681.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,457,126.21


E. Overhead & Profit - 345,712.62
F. Harga Satuan Pekerjaan (D+E) 3,802,838.83

135 Pengadaan dan Instalasi Pintu ACP Uk. 0.7 x 2.1 + rel
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.688 120,000.00 82,536.00
2 Tukang Khusus Aluminium L.02 OH 2.086 150,000.00 312,937.50
3 Kepala Tukang L.03 OH 0.209 175,000.00 36,509.38
4 Mandor L.04 OH 0.035 185,000.00 6,527.91
-
-
JUMLAH TENAGA KERJA 438,510.78
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 6.160 150,000.00 924,000.00
2 Sekrup Fixer buah 11.200 950.00 10,640.00
3 Sealant tube 0.336 30,000.00
II Daun Pintu -
1 Alumunium Profil m 6.160 150,000.00 924,000.00
2 Profil Alumunium T m 6.300 7,500.00 47,250.00
3 Sealant tube 0.378 85,000.00 32,130.00
4 Kaca tebal 5 mm m2 0.385 150,000.00 57,750.00
5 Aluminium composite panel (ACP) m2 1.470 425,000.00 624,750.00
III Aksesoris -
1 Engsel Pintu set 1.500 38,500.00 57,750.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast m2 0.385 50,000.00 19,250.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 2.000 25,000.00 50,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 3,552,520.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,991,030.79


E. Overhead & Profit - 399,103.08
F. Harga Satuan Pekerjaan (D+E) 4,390,133.86

136 Pengadaan Dan Instalasi Pintu ACP uk. 1,6 x 2,1


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.952 120,000.00 114,180.00
2 Tukang Khusus Aluminium L.02 OH 2.596 150,000.00 389,347.50
3 Kepala Tukang L.03 OH 0.260 175,000.00 45,423.88
4 Mandor L.04 OH 0.050 185,000.00 9,218.92
-
-
JUMLAH TENAGA KERJA 558,170.30
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 8.250 150,000.00 1,237,500.00
2 Sekrup Fixer buah 15.000 950.00 14,250.00
3 Sealant tube 0.450 30,000.00
II Daun Pintu -
1 Alumunium Profil m 7.920 150,000.00 1,188,000.00
2 Profil Alumunium T m 8.100 7,500.00 60,750.00
3 Sealant tube 1.000 85,000.00 85,000.00
4 Kaca tebal 5 mm m2 0.770 150,000.00 115,500.00
5 Aluminium composite panel (ACP) m2 4.000 425,000.00 1,700,000.00
III Aksesoris -
1 Engsel Pintu set 3.000 38,500.00 115,500.00
2 Kunci Tanam + Handle Bh 1.000 285,000.00 285,000.00
3 Sunblast 1.5 0.770 50,000.00 38,500.00
4 Door closer set 1.000 500,000.00 500,000.00
5 Engsel Casement unit 2.000 25,000.00 50,000.00
6 Rambuncis Bh 1.000 20,000.00 20,000.00
-
JUMLAH TENAGA BAHAN 5,410,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 5,968,170.30


E. Overhead & Profit - 596,817.03
F. Harga Satuan Pekerjaan (D+E) 6,564,987.32

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.4
137 JENIS PEKERJAAN Pemasangan kran sensor
SATUAN PEMBAYARAN Bh

KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO.
A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.00 150,000 150,000.00
3 Kepala Tukang (L.03) OH 0.10 175,000 17,500.00
4 Mandor (L.04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 296,750.00
B. BAHAN
1 Urinoir Unit 1.00 1,900,000 1,900,000.00
2 Semen Portland Kg 1.00 1,160 1,160.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Perlengkapan 30 % 0.10 1,900,000 190,000.00
JUMLAH HARGA BAHAN 2,092,310.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,389,060.00
E. OVERHEAD & PROFIT 10,0 % x D 238,906.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,627,966.00

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.25
138 JENIS PEKERJAAN Pemasangan 1 m’ pipa PPR 1/2 Inch
SATUAN PEMBAYARAN : M'

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
M
1 Pipa PVC 1/2” % 1.20 100,000 120,000.00
2 Perlengkapan 35 0.35 35,000 12,250.00
JUMLAH HARGA BAHAN 132,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 146,990.00
E. OVERHEAD & PROFIT 10,0 % x D 14,699.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 161,689.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.26
139 JENIS PEKERJAAN Pemasangan 1 m’ pipa PPR 3/4 Inch
SATUAN PEMBAYARAN : M'

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
M
1 Pipa PVC 3/4” % 1.20 150,000 180,000.00
2 Perlengkapan 35 0.35 52,500 18,375.00
JUMLAH HARGA BAHAN 198,375.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 213,115.00
E. OVERHEAD & PROFIT 10,0 % x D 21,311.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 234,426.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.26
140 JENIS PEKERJAAN Pasangan cermin
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.036 0.00
2 Tukang Batu (L.02) OH 0.06 0.00
3 Kepala Tukang (L.03) OH 0.006 0.00
4 Mandor (L.04) OH 0.002 0.00
JUMLAH HARGA TENAGA 0.00
B. BAHAN
M
1 Pipa PVC 3/4” % 1.00 250,000 250,000.00
2 Perlengkapan 35 0.35 0.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 250,000.00
E. OVERHEAD & PROFIT 10,0 % x D 25,000.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 275,000.00

141 Pemasangan 1 m2 terali besi 0


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.67 120,000.00 200,400.00
Tukang Batu L.02 OH 1.67 150,000.00 250,500.00
Kepala Tukang L.03 OH 0.167 175,000.00 29,225.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 495,480.00
B BAHAN
Besi Strip Kg 6.177 14000 86,478.00
Pengelasan cm 27.08 3619 98,002.52
JUMLAH TENAGA BAHAN 184,480.52
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 679,960.52


E. Overhead & Profit - 67,996.05
F. Harga Satuan Pekerjaan (D+E) 747,956.57

142 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium Uk 1 x 1.2 Taksir 32
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.160 120,000.00 139,200.00
2 Tukang Khusus Aluminium L.02 OH 2.110 150,000.00 316,500.00
3 Kepala Tukang L.03 OH 0.210 175,000.00 36,750.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 496,150.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.940 150,000.00 891,000.00
2 Sekrup Fixer buah 10.800 950.00 10,260.00
3 Sealant tube 0.320 85,000.00 27,200.00
II Daun Jendela -
1 Alumunium Profil m 5.940 150,000.00 891,000.00
2 Profil Alumunium T m 6.080 7,500.00 45,600.00
3 Sealant tube 0.370 85,000.00 31,450.00
4 Kaca tebal 5 mm m2 2.400 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 2.400 50,000.00 120,000.00
-
-
JUMLAH TENAGA BAHAN 2,156,510.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,652,660.00


E. Overhead & Profit - 265,266.00
F. Harga Satuan Pekerjaan (D+E) 2,917,926.00

143 JENIS PEKERJAAN Pemasangan kawat Harmonika


SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
1 m2 1.10 40,000 44,000.00
2
JUMLAH HARGA BAHAN 44,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 58,740.00
E. OVERHEAD & PROFIT 10,0 % x D 5,874.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 64,614.00

144 JENIS PEKERJAAN Pemasangan 1 m2 ragka kanopi baja ringan


SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang L.03 OH 0.450 150,000 67,500.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 102,500.00
B. BAHAN
2 Profil C-75. 75 M' 3.500 16,333 57,165.50
4 Screw bh 38.000 175 6,650.00
5 Dynabolt bh 1.600 1,500 2,400.00
JUMLAH HARGA BAHAN 66,215.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 168,715.50
E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 168,715.50
145 JENIS PEKERJAAN Pemasangan 1 m2 atap PVC Fiberglass
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.075 150,000 11,250.00
3 Kepala tukang (L.11) OH 0.08 175,000 14,000.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 44,360.00
B. BAHAN
1 Almn gel tbl 0,55 Lbr 1.05 70,000 73,500.00
2 Paku hak panj 15cm Kg 0.02 20,000 400.00
JUMLAH HARGA BAHAN 73,900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 118,260.00
E. OVERHEAD & PROFIT 10,0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 118,260.00

146 Pemesangan BV Uk 2 x 0,3


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.258 120,000.00 30,936.00
2 Tukang Khusus Aluminium L.02 OH 0.339 150,000.00 50,820.00
3 Kepala Tukang L.03 OH 0.034 175,000.00 5,929.00
4 Mandor L.04 OH 0.013 185,000.00 2,430.90
-
-
JUMLAH TENAGA KERJA 90,115.90
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 5.060 150,000.00 759,000.00
2 Sekrup Fixer buah 9.200 950.00 8,740.00
3 Sealant tube 0.276 85,000.00 23,460.00
II Profil Kaca -
1 Profil Alumunium T m 5.175 7,500.00 38,812.50
3 Sealant tube 0.311 85,000.00 26,392.50
4 Kaca tebal 5 mm m2 0.600 150,000.00 90,000.00
III Aksesoris -
3 Sunblast m2 0.600 50,000.00 30,000.00
-
-
JUMLAH TENAGA BAHAN 976,405.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,066,520.90


E. Overhead & Profit - 106,652.09
F. Harga Satuan Pekerjaan (D+E) 1,173,172.99

147 Pemesangan BV Uk 0,7 x 0,3


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.107 120,000.00 12,840.00
2 Tukang Khusus Aluminium L.02 OH 0.135 150,000.00 20,302.50
3 Kepala Tukang L.03 OH 0.014 175,000.00 2,368.63
4 Mandor L.04 OH 0.005 185,000.00 1,002.33
-
-
JUMLAH TENAGA KERJA 36,513.46
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 2.200 150,000.00 330,000.00
2 Sekrup Fixer buah 4.000 950.00 3,800.00
3 Sealant tube 0.120 85,000.00 10,200.00
II Profil Kaca -
1 Profil Alumunium T m 2.250 7,500.00 16,875.00
3 Sealant tube 0.135 85,000.00 11,475.00
4 Kaca tebal 5 mm m2 0.210 150,000.00 31,500.00
III Aksesoris -
3 Sunblast m2 0.210 50,000.00 10,500.00
-
-
JUMLAH TENAGA BAHAN 414,350.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 450,863.46


E. Overhead & Profit - 45,086.35
F. Harga Satuan Pekerjaan (D+E) 495,949.80

148 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium uk. 1,2 x 1,5 m + Kusen + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000.00 144,000.00
2 Tukang Khusus Aluminium L.02 OH 2.200 150,000.00 330,000.00
3 Kepala Tukang L.03 OH 0.200 175,000.00 35,000.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 512,700.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 7.000 150,000.00 1,050,000.00
2 Sekrup Fixer buah 13.000 950.00 12,350.00
II Daun Jendela
1 Alumunium Profil m 6.000 150,000.00 900,000.00
2 Profil Alumunium T m 7.200 7,500.00 54,000.00
3 Sealant tube 0.432 85,000.00 36,720.00
4 Kaca tebal 5 mm m2 3.600 150,000.00 540,000.00
III Aksesoris
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 3.600 50,000.00 180,000.00
-
-
JUMLAH TENAGA BAHAN 2,813,070.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 3,325,770.00


E. Overhead & Profit - 332,577.00
F. Harga Satuan Pekerjaan (D+E) 3,658,347.00

149 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium 1 Daun uk. 0,6 x 1,2 m + Engsel + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000.00 72,000.00
2 Tukang Khusus Aluminium L.02 OH 1.200 150,000.00 180,000.00
3 Kepala Tukang L.03 OH 0.200 175,000.00 35,000.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 290,700.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 4.000 150,000.00 600,000.00
2 Sekrup Fixer buah 8.000 950.00 7,600.00
II Daun Jendela -
1 Alumunium Profil m 4.000 150,000.00 600,000.00
2 Profil Alumunium T m 4.050 7,500.00 30,375.00
3 Sealant tube 0.243 85,000.00 20,655.00
4 Kaca tebal 5 mm m2 0.720 150,000.00 108,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.720 50,000.00 36,000.00
-
-
JUMLAH TENAGA BAHAN 1,472,630.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,763,330.00


E. Overhead & Profit - 176,333.00
F. Harga Satuan Pekerjaan (D+E) 1,939,663.00

150 Pembuatan dan Pemasangan Jendela Kaca Rangka Alumunium Geser Daun uk. 0,7 x 0,7 m + Kusen + Aksesoris
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.012 120,000.00 121,488.00
2 Tukang Khusus Aluminium L.02 OH 1.879 150,000.00 281,782.50
3 Kepala Tukang L.03 OH 0.188 175,000.00 32,874.63
4 Mandor L.04 OH 0.015 185,000.00 2,742.07
-
-
JUMLAH TENAGA KERJA 438,887.20
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 4.180 150,000.00 627,000.00
2 Sekrup Fixer buah 7.600 950.00 7,220.00
3 Sealant tube 0.228 30,000.00 6,840.00
II Daun Jendela -
1 Alumunium Profil m 4.180 150,000.00 627,000.00
2 Profil Alumunium T m 4.275 7,500.00 32,062.50
3 Sealant tube 0.257 85,000.00 21,802.50
4 Kaca tebal 5 mm m2 0.980 150,000.00
III Aksesoris -
1 Engsel Casement unit 4.000 25,000.00 100,000.00
2 Rambuncis Bh 2.000 20,000.00 40,000.00
3 Sunblast m2 0.980 50,000.00 49,000.00
-
-
JUMLAH TENAGA BAHAN 1,510,925.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,949,812.20


E. Overhead & Profit - 194,981.22
F. Harga Satuan Pekerjaan (D+E) 2,144,793.41

151 Pembuatan 1 m2 Partisi Kaca 5mm + Sunblast


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.204 120,000.00 24,504.00
2 Tukang Khusus Aluminium L.02 OH 0.339 150,000.00 50,880.00
3 Kepala Tukang L.03 OH 0.034 175,000.00 5,936.00
4 Mandor L.04 OH 0.010 185,000.00 1,857.40
-
-
JUMLAH TENAGA KERJA 83,177.40
B BAHAN
Profil Alluminium m 4.400 150,000.00 660,000.00
Skrup Fixer buah 8.000 950.00 7,600.00
Sealant tube 0.290 85,000.00 24,650.00
Kaca tebal 5 mm m 1.100 150,000.00 165,000.00
Sunblast m2 1.210 50,000.00 60,500.00
-
JUMLAH TENAGA BAHAN 917,750.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,000,927.40


E. Overhead & Profit XD 100,092.74
F. Harga Satuan Pekerjaan (D+E) 1,101,020.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

152 NAMA PAKET 0


PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.39
JENIS PEKERJAAN Pemasangan keramik ukuran 10cm x 20cm
SATUAN PEMBAYARAN m2

NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)

A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik uk. 10 x 20 cm m2 1.00 95,000 95,000.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.025 10,000 250.00
JUMLAH HARGA BAHAN 96,917.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 128,267.40
E. OVERHEAD & PROFIT 10,0 % x D 12,826.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 141,094.14

153 Daun Jendela Kaca Alumunium uk. 1,7 x 0,6 Natural


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000.00 144,000.00
2 Tukang Khusus Aluminium L.02 OH 2.200 150,000.00 330,000.00
3 Kepala Tukang L.03 OH 0.200 175,000.00 35,000.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 512,700.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 4.600 150,000.00 690,000.00
2 Sekrup Fixer buah 6.200 950.00 5,890.00
3 Sealant tube 0.186 85,000.00 15,810.00
II Daun Jendela -
1 Alumunium Profil m 4.600 150,000.00 690,000.00
2 Profil Alumunium T m 4.600 7,500.00 34,500.00
3 Sealant tube 0.209 85,000.00 17,786.25
4 Kaca tebal 5 mm m2 0.600 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.600 50,000.00 30,000.00
-
-
JUMLAH TENAGA BAHAN 1,553,986.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,066,686.25


E. Overhead & Profit - -
F. Harga Satuan Pekerjaan (D+E) 2,066,686.25

154 Daun Jendela Kaca Alumunium uk. 0,6 x 1,215 Natural


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000.00 144,000.00
2 Tukang Khusus Aluminium L.02 OH 2.200 150,000.00 330,000.00
3 Kepala Tukang L.03 OH 0.200 175,000.00 35,000.00
4 Mandor L.04 OH 0.020 185,000.00 3,700.00
-
-
JUMLAH TENAGA KERJA 512,700.00
B BAHAN
I Kusen Jendela
1 Profil Alumunium m 3.630 150,000.00 544,500.00
2 Sekrup Fixer buah 6.000 950.00 5,700.00
3 Sealant tube 0.186 85,000.00 15,810.00
II Daun Jendela -
1 Alumunium Profil m 3.630 150,000.00 544,500.00
2 Profil Alumunium T m 3.630 7,500.00 27,225.00
3 Sealant tube 0.209 85,000.00 17,786.25
4 Kaca tebal 5 mm m2 0.729 150,000.00
III Aksesoris -
1 Engsel Casement unit 2.000 25,000.00 50,000.00
2 Rambuncis Bh 1.000 20,000.00 20,000.00
3 Sunblast m2 0.360 50,000.00 18,000.00
-
-
JUMLAH TENAGA BAHAN 1,243,521.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,756,221.25


E. Overhead & Profit - -
F. Harga Satuan Pekerjaan (D+E) 1,756,221.25
DIVISI 2 / 2.2.1.1
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET
KOTA
ITEM PEMBAYARAN 2.2.1.1
JENIS PEKERJAAN Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter
SATUAN PEMBAYARAN M²
KOEFISIE HARGA SATUAN JUMLAH
NO. URAIAN KODE SATUAN
N (Rp.) HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.400 120,000 48,000.00
2 Tukang Kayu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.020 185,000 3,700.00
JUMLAH HARGA 85,200.00
B. BAHAN TENAGA
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.250 15,000 18,750.00
2 Semen Portland Kg 5.000 1,160 5,800.00
3 Pasir Beton m3 0.005 135,000 675.00
4 Koral Beton m 3 0.009 435,000 3,915.00
5 Kayu 5/7 m3 0.072 1,600,000 115,200.00
6 Paku Biasa 2" - 5" Kg 0.060 22,000 1,320.00
7 Residu Liter 0.400 5,000 2,000.00
JUMLAH HARGA BAHAN 147,660.00
C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN
D. JUMLAH ( A + B + C ) 232,860.00
E. OVERHEAD & PROFIT (15 %) 10,0 % x D 23,286.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 256,146.00

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.2
JENIS PEKERJAAN : Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
SATUAN PEMBAYARAN : M²

KOEFISIE HARGA SATUAN JUMLAH


NO. KOMPONEN KODE SATUAN
N (Rp.) HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang Kayu L.02 OH 0.400 150,000 60,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.020 185,000 3,700.00
JUMLAH HARGA 91,200.00
B. BAHAN TENAGA
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.250 15,000 18,750.00
2 Semen Portland Kg 2.50 1,160 2,900.00
3 Seng Gelombang Lbr 1.20 102,000 122,400.00
4 Pasir Beton m3 0.005 135,000 675.00
5 Koral Beton m 3 0.009 435,000 3,915.00
6 Kayu 5/7 m 3 0.072 1,600,000 115,200.00
7 Paku Biasa 2" - 5" Kg 0.060 22,000 1,320.00
8 Meni Besi Liter 0.45 34,000 15,300.00
JUMLAH HARGA BAHAN 280,460.00
C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN
D. JUMLAH ( A + B + C ) 371,660.00
E. OVERHEAD & PROFIT (15%) 10 % x D 37,166.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 408,826.00
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.3
JENIS PEKERJAAN : Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter

SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang Kayu L.02 OH 0.300 150,000 45,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.020 185,000 3,700.00
JUMLAH HARGA TENAGA 76,200.00

B. BAHAN
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.00 15,000 15,000.00
2 Semen Portland Kg 2.000 1,160 2,320.00
3 Kawat Duri m' 25.000 9,000 225,000.00
4 Pasir Beton m3 0.005 135,000 675.00
5 Koral Beton m3 0.009 435,000 3,915.00
6 Paku Biasa 2" - 5" Kg 0.060 22,000 1,320.00
JUMLAH HARGA BAHAN 248,230.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 324,430.00
E. OVERHEAD & PROFIT (15 %) 10 % x D 32,443.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 356,873.00

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.4
JENIS PEKERJAAN : Pengukuran dan pemasangan 1 m' Bouwplank
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.10 120,000 12,000.00
2 Tukang Kayu L.02 OH 0.10 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.01 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00

B. BAHAN
1 Kayu Balok 5/7 m3 0.012 1,600,000 19,200.00
2 Paku 2" - 3" Kg 0.02 22,000 440.00
3 Kayu Papan 3/20 m3 0.007 1,600,000 11,200.00
JUMLAH HARGA BAHAN 30,840.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 60,515.00
E. OVERHEAD & PROFIT (15 %) 10 % x D 6,051.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 66,566.50
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.5
JENIS PEKERJAAN : Pembuatan 1 m2 kantor sementara lantai plesteran
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 2.00 120,000 240,000.00
2 Tukang Kayu L.02 OH 2.00 150,000 300,000.00
3 Tukang Batu L.03 OH 1.00 150,000 150,000.00
4 Kepala Tukang L.04 OH 0.30 175,000 52,500.00
5 Mandor L.05 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 751,750.00

B. BAHAN
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.250 15,000 18,750.00
2 Kayu m3 0.180 1,600,000 288,000.00
3 Paku Biasa Kg 0.080 22,000 1,760.00
4 Besi Strip Kg 1.100 9,000 9,900.00
5 Semen Portland Kg 35.000 1,160 40,600.00
6 Pasir Pasang m3 0.150 115,000 17,250.00
7 Pasir Beton m3 0.100 135,000 13,500.00
8 Koral Beton m3 0.150 435,000 65,250.00
9 Bata Merah Bh 30.000 550 16,500.00
10 Seng Plat Lbr 0.250 90,000 22,500.00
11 Jendela Naco Bh 0.200 10,500 2,100.00
12 Kaca Polos m2 0.080 110,000 8,800.00
13 Kunci Tanam Bh 0.150 155,000 23,250.00
14 Plywood 4mm Lbr 0.060 70,000 4,200.00
JUMLAH HARGA BAHAN 532,360.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,284,110.00
E. OVERHEAD & PROFIT (15 %) 10 % x D 128,411.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,412,521.00

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.6
JENIS PEKERJAAN : Pembuatan 1 m2 rumah jaga (konstruksi kayu)
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 1.00 120,000 120,000.00
2 Tukang Kayu L.02 OH 1.50 150,000 225,000.00
3 Kepala Tukang L.03 OH 0.15 175,000 26,250.00
4 Mandor L.04 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 380,500.00

B. BAHAN
1 Dolken Kayu ɸ 8-10/400 cm Batang 3.00 15,000 45,000.00
2 Kayu m3 0.276 1,600,000 441,600.00
3 Paku Biasa Kg 0.700 22,000 15,400.00
4 Seng Gelombang Lbr 1.500 102,000 153,000.00
JUMLAH HARGA BAHAN 655,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,035,500.00
E. OVERHEAD & PROFIT(CONTOH 15%) 10 % x D 103,550.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,139,050.00
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.7
JENIS PEKERJAAN : Pembuatan 1 m2 gudang semen dan peralatan
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L01) OH 1.00 120,000 120,000.00
2 Tukang Kayu (L02) OH 2.00 150,000 300,000.00
3 Kepala Tukang (L03) OH 0.20 175,000 35,000.00
4 Mandor (L04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 464,250.00

B. BAHAN
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.70 15,000 25,500.00
2 Kayu m3 0.210 1,600,000 336,000.00
3 Paku Biasa Kg 0.300 22,000 6,600.00
4 Semen Portland Kg 10.50 1,160 12,180.00
5 Pasir Beton m3 0.03 135,000 4,050.00
6 Koral Beton m3 0.05 435,000 21,750.00
7 Seng Gelombang Lbr 1.50 102,000 153,000.00
8 Seng Plat Lbr 0.250 90,000 22,500.00
JUMLAH HARGA BAHAN 581,580.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,045,830.00
E. OVERHEAD & PROFIT (15%) 10 % x D 104,583.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,150,413.00

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.8
JENIS PEKERJAAN : Pembuatan 1 m2 bedeng pekerja
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 1.00 120,000 120,000.00
2 Tukang Kayu L.02 OH 2.00 150,000 300,000.00
3 Kepala Tukang L.03 OH 0.20 175,000 35,000.00
4 Mandor L.04 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 464,250.00

B. BAHAN
1 Dolken Kayu ɸ 8-10/400 cm Batang 1.25 15,000 18,750.00
2 Kayu m3 0.186 1,600,000 297,600.00
3 Paku Biasa Kg 0.300 22,000 6,600.00
4 Semen Portland Kg 18.00 1,160 20,880.00
5 Pasir Beton m3 0.03 135,000 4,050.00
6 Koral Beton m3 0.05 435,000 21,750.00
7 Seng Gelombang Lbr 1.50 102,000 153,000.00
8 Plywood 4mm Lbr 1.350 70,000 94,500.00
JUMLAH HARGA BAHAN 617,130.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,081,380.00
E. OVERHEAD & PROFIT (15%) 10 % x D 108,138.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,189,518.00

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.9
JENIS PEKERJAAN : Pembersihan 1 m2 lapangan dan perataan
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.10 120,000 12,000.00
2 Mandor L.02 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 21,250.00

B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 21,250.00
E. OVERHEAD & PROFIT (15 %) 10 % x D 2,125.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 23,375.00
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.10
JENIS PEKERJAAN : Pembuatan 1 m2 steger / perancah dari bambu

SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.25 120,000 30,000.00
2 Tukang Kayu L.02 OH 0.02 150,000 3,000.00
3 Kepala Tukang L.03 OH 0.002 175,000 350.00
4 Mandor L.04 OH 0.01 185,000 1,850.00
JUMLAH HARGA TENAGA 35,200.00
B. BAHAN
1 Bambu dia. 6 - 8 /600 cm Batang 1.25 35000.000 43,750.00
2 Tali Ijuk Kg 0.186 35000.000 6,510.00
JUMLAH HARGA BAHAN 50,260.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0
D. JUMLAH( A + B + C ) 85,460.00
E. OVERHEAD & PROFIT (15%) 10 % x D 8,546.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 94,006.00

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.11
JENIS PEKERJAAN : Pembuatan 1 buah kotak adukan ukuran 40cm x50cm x25cm

SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Tukang kayu L.01 OH 0.3 150000.000 45,000.00
2 Kepala Tukang L.02 OH 0.03 175000.000 5,250.00
JUMLAH HARGA TENAGA 50,250.00
B. BAHAN
1 Kayu Papan Kelas III m3 0.036 2600000 93600.00
2 Kayu Balok 5/7 m3 0.014 2600000 36400.00
3 Paku Biasa Kg 0.08 22000.000 1760.00
JUMLAH HARGA BAHAN 131760
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 182,010.00
E. OVERHEAD & PROFIT (15%) 10 % x D 18201
F. HARGA SATUAN PEKERJAAN ( D + E ) 200,211.00
DIVISI 2 / 2.2.1.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.12
JENIS PEKERJAAN : Pembuatan 1 m2 jalan sementara
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 1 120000.000 120000
2 Mandor L.04 OH 0.005 185000.000 925
JUMLAH HARGA TENAGA 120925
B. BAHAN
1 Batu Belah m3 0.15 420000.000 63000
2 Batu Pecah m3 0.09 420000.000 37800
3 Pasir Pasang m3 0.01 115000.000 1150
JUMLAH HARGA BAHAN 101950
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 222875
E. OVERHEAD & PROFIT (15%) 10 % x D 22287.5
F. HARGA SATUAN PEKERJAAN ( D + E ) 245162.5

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum

DIVISI 2 / 2.2.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.13
JENIS PEKERJAAN : Pembongkaran 1 m3 beton bertulang
SATUAN PEMBAYARAN : M³
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 13 120000.000 1600080
2 Mandor L.04 OH 0.666 185000.000 123210
JUMLAH HARGA TENAGA 1723290
B. BAHAN
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) #VALUE!
E. OVERHEAD & PROFIT (15 %) 10 % x D #VALUE!
F. HARGA SATUAN PEKERJAAN ( D + E ) #VALUE!

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum

DIVISI 2 / 2.2.1.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.14
JENIS PEKERJAAN : Pembongkaran 1 m3 dinding tembok bata
SATUAN PEMBAYARAN : M³
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 6.667 120000.000 800040
2 Mandor L.04 OH 0.333 185000.000 61605
JUMLAH HARGA TENAGA 861645
B. BAHAN
JUMLAH HARGA BAHAN 0,00
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 861645
E. OVERHEAD & PROFIT (15%) 10 % x D 86164.5
F. HARGA SATUAN PEKERJAAN ( D + E ) 947809.5

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum
DIVISI 2/ 2.2.1.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.15
JENIS PEKERJAAN : Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.042 120,000 5040
2 Tukang Besi L.02 OH 0.004 150,000 600
3 Kepala Tukang L.03 OH 0.002 175,000 350
4 Mandor L.04 OH 0.042 185,000 7770
JUMLAH HARGA TENAGA 13760
B. BAHAN
1 Kawat jaring Lbr 0.1434 335000.000 48039
JUMLAH HARGA BAHAN 48039
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 61799
E. OVERHEAD & PROFIT (15%) 10 % x D 6179.9
F. HARGA SATUAN PEKERJAAN ( D + E ) 67978.9

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum

DIVISI 2 /2.2.1.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.16
JENIS PEKERJAAN : Pemasangan 1 m2 panel beton pracetak 5x50x240 cm untuk pagar
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.375 120000.000 45000
2 Tukang Batu L.02 OH 0.125 150000.000 18750
3 Kepala Tukang L.03 OH 0.012 175000.000 2100
4 Mandor L.04 OH 0.019 185000.000 3515
JUMLAH HARGA TENAGA 69365
B. BAHAN
1 Panel Beton Pracetak uk. 240.50.5 Lbr 0.986 120000.000 118320
2 Kolom Beton pracetak Batang 0.525 370000.000 194250
3 Semen PC Kg 45 1160.000 52200
4 Pasir Beton m3 0.074 135000.000 9990
5 Koral m3 0.146 435000.000 63510
JUMLAH HARGA BAHAN 438270
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 507635
E. OVERHEAD & PROFIT (15%) 10 % x D 50763.5
F. HARGA SATUAN PEKERJAAN ( D + E ) 558398.5

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum
DIVISI 2 /2.2.1.16.a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.2.1.16.a
JENIS PEKERJAAN : Pemasangan 1 m2 panel beton pracetak 5x40x240 cm untuk pagar
SATUAN PEMBAYARAN : M²
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.375 120000.000 45000
2 Tukang Batu L.02 OH 0.125 150000.000 18750
3 Kepala Tukang L.03 OH 0.012 175000.000 2100
4 Mandor L.04 OH 0.019 185000.000 3515
JUMLAH HARGA TENAGA 69365
B. BAHAN
1 Panel Beton Pracetak uk. 5x40x240 cm Lbr 1.233 120000.000 147960
2 Kolom Beton pracetak Batang 0.525 305000.000 160125
3 Semen PC Kg 45 1160.000 52200
4 Pasir Beton m3 0.074 135000.000 9990
5 Koral m3 0.146 435000.000 63510
JUMLAH HARGA BAHAN 433785
C. PERALATAN
JUMLAH HARGA PERALATAN 0,00
D. JUMLAH( A + B + C ) 503150
E. OVERHEAD & PROFIT (15%) 10 % x D 50315
F. HARGA SATUAN PEKERJAAN ( D + E ) 553465

Keterangan : Bedasarkan Permen PU No. 28/PRT/M/2016 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.1
JENIS PEKERJAAN : Penggalian 1 m3 tanah biasa sedalam 1 m

SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.750 120,000 90,000.00
2 Mandor L.04 OH 0.025 185,000 4,625.00
JUMLAH HARGA TENAGA 94,625.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 94,625.00
E. OVERHEAD & PROFIT(15 %) 10,0 % x D 9,462.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 104,087.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.2
JENIS PEKERJAAN : Penggalian 1 m3 tanah biasa sedalam 2 m
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.900 120,000 108,000.00
2 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 116,325.00
B. BAHAN

JUMLAH HARGA BAHAN 0.00


C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 116,325.00
E. OVERHEAD & PROFIT(CONTOH 15%) 10,0 % x D 11,632.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 127,957.50

DIVISI 2 / 2.3.1.3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 2.3.1.3
JENIS PEKERJAAN : Menggali 1 m3 tanah biasa sedalam 3 m
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja (L01) OH 1.050 120,000 126,000.00
2 Mandor (L04) OH 0.067 185,000 12,395.00
JUMLAH HARGA TENAGA 138,395.00
B. BAHAN

JUMLAH HARGA BAHAN 0.00


C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 138,395.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 13,839.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 152,234.50
DIVISI 2 / 2.3.1.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.4
JENIS PEKERJAAN : Menggali 1 m3 tanah keras sedalam 1 m
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.000 120,000 120,000.00
2 Mandor L.04 OH 0.032 185,000 5,920.00
JUMLAH HARGA TENAGA 125,920.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 125,920.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 12,592.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 138,512.00

DIVISI 2 / 2.3.1.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.5
JENIS PEKERJAAN : Menggali 1 m3 tanah cadas sedalam 1 m
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.500 120,000 180,000.00
2 Mandor L.04 OH 0.060 185,000 11,100.00
JUMLAH HARGA TENAGA 191,100.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 191,100.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 19,110.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 210,210.00

DIVISI 2 / 2.3.1.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.6
JENIS PEKERJAAN : Menggali 1 m3 tanah lumpur sedalam 1 m
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000 144,000.00
2 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 152,325.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 152,325.00
E. OVERHEAD & PROFIT ( 15%) 10,0 % x D 15,232.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 167,557.50
DIVISI 2 / 2.3.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.7
JENIS PEKERJAAN : Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter
SATUAN PEMBAYARAN : M²
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.050 120,000 6,000.00
2 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 6,925.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 6,925.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 692.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 7,617.50

DIVISI 2 / 2.3.1.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.8
JENIS PEKERJAAN : Pembuangan 1 m3 tanah sejauh 30 meter
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L,01 OH 0.330 120,000 39,600.00
2 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 41,450.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 41,450.00
E. OVERHEAD & PROFIT ( 15%) 10,0 % x D 4,145.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 45,595.00

DIVISI 2 / 2.3.1.9
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.9
JENIS PEKERJAAN : Pengurugan kembali 1 m3 galian tanah
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.500 120,000 60,000.00
2 Mandor L.04 OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 69,250.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 69,250.00
E. OVERHEAD & PROFIT ( 15%) 10,0 % x D 6,925.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 76,175.00
DIVISI 2 / 2.3.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.10
JENIS PEKERJAAN : Pemadatan tanah 1 m3 tanah ( per 20 cm )
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.500 120,000 60,000.00
2 Mandor L.04 OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 69,250.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 69,250.00
E. OVERHEAD & PROFIT (15 %) 10,0 % x D 6,925.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 76,175.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.11
JENIS PEKERJAAN : Pengurungan 1 m³ dengan pasir urug
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 37,850.00
B. BAHAN
1 Pasir Urug M3 1.200 95,000 114,000.000
JUMLAH HARGA BAHAN 114,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 151,850.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 15,185.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 167,035.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.12
JENIS PEKERJAAN : Pemasangan 1 m³ lapisan pudel campuran 1KP:3PP:7TL
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.800 120,000 96,000.00
2 Tukang L.02 OH 0.400 150,000 60,000.00
3 Kepala Tukang L.03 OH 0.040 175,000 7,000.00
4 Mandor L.04 OH 0.080 185,000 14,800.00
JUMLAH HARGA TENAGA 177,800.00
B. BAHAN
1 Kapur Padam m3 0.135 1,750,000 236,250.00
1 Pasir Pasang m3 0.400 105,000 42,000.00
2 Tanah Liat m3 0.948 70,000 66,360.00
JUMLAH HARGA BAHAN 344,610.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 522,410.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 52,241.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 574,651.00
DIVISI 2 / 2.3.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.13
JENIS PEKERJAAN : Pemasangan 1 m² lapisan ijuk tebal 10 cm untuk bidang resapan
SATUAN PEMBAYARAN : M²
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
\
A. TENAGA
1 Pekerja L.01 OH 0.150 120,000 18,000.00
2 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 20,775.00
B. BAHAN
1 Ijuk m3 6.000 45,000 270,000.00
JUMLAH HARGA BAHAN 270,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 290,775.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 29,077.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 319,852.50
DIVISI 2 / 2.3.1.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.14
JENIS PEKERJAAN : Pengurungan 1 m³ sirtu padat
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Mandor L.04 OH 0.025 185,000 4,625.00
JUMLAH HARGA TENAGA 34,625.00
B. BAHAN
1 Sirtu m3 1.200 80,000 96,000.00
JUMLAH HARGA BAHAN 96,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 130,625.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 13,062.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 143,687.50

DIVISI 2 / 2.3.1.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 2.3.1.15
JENIS PEKERJAAN : Pengurungan 1 m³ dengan tanah timbunan
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Mandor L.04 OH 0.025 185,000 4,625.00
JUMLAH HARGA 34,625.00
B. BAHAN TENAGA
1 Tanah Timbunan m3 1.200 70,000 84,000.00
JUMLAH HARGA BAHAN 84,000.00
C. PERALATAN
JUMLAH HARGA 0.00
PERALATAN

D. JUMLAH( A + B + C ) 118,625.00
E. OVERHEAD & PROFIT (15%) 10,0 % x D 11,862.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 130,487.50
DIVISI 3 / 3.2.1.1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.1
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP:3PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 319,500.00
B. BAHAN
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 202.000 1,160 234,320.00
3 Pasir Pasang m3 0.485 115,000 55,775.00
JUMLAH HARGA BAHAN 794,095.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,113,595.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 111,359.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,224,954.50

DIVISI 3 / 3.2.1.1.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.1.a
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu bata (8x8x16) cm campuran 1SP:3PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 2.025 120,000 243,000.00


2 Tukang Batu L.02 OH 0.675 150,000 101,250.00
3 Kepala Tukang L.03 OH 0.068 175,000 11,900.00
4 Mandor L.04 OH 0.101 185,000 18,685.00
JUMLAH HARGA TENAGA 374,835.00
B. BAHAN
1 Batu Bata bh 726.000 550 399,300.00
2 Semen Portland Kg 170.022 1,160 197,225.52
3 Pasir Pasang m3 0.470 115,000 54,050.00
JUMLAH HARGA BAHAN 650,575.52
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,025,410.52
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 102,541.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,127,951.57
DIVISI 3 / 3.2.1.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.2
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP : 4PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 319,500.00
B. BAHAN
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 163.000 1,160 189,080.00
3 Pasir Pasang m3 0.520 115,000 59,800.00
JUMLAH HARGA BAHAN 752,880.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,072,380.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 107,238.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,179,618.00

DIVISI 3 / 3.2.1.2.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.2.a
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu bata (8x8x16) cm campuran 1SP : 4PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 2.025 120,000 243,000.00


2 Tukang Batu L.02 OH 0.675 150,000 101,250.00
3 Kepala Tukang L.03 OH 0.068 175,000 11,900.00
4 Mandor L.04 OH 0.101 185,000 18,685.00
JUMLAH HARGA TENAGA 374,835.00
B. BAHAN
1 Batu Bata bh 726.000 550 399,300.00
2 Semen Portland Kg 136.998 1,160 158,917.68
3 Pasir Pasang m3 0.480 115,000 55,200.00
JUMLAH HARGA BAHAN 613,417.68
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 988,252.68
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 98,825.27
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,087,077.95
DIVISI 3 / 3.2.1.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.3
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP:5PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 319,500.00
B. BAHAN
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 136.000 1,160 157,760.00
3 Pasir Pasang m3 0.544 115,000 62,560.00
JUMLAH HARGA BAHAN 724,320.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,043,820.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 104,382.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,148,202.00

DIVISI 3 / 3.2.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.4
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP:6PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH 319,500.00
B. BAHAN HARGA
TENAGA
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 117.000 1,160 135,720.00
3 Pasir Pasang m3 0.561 115,000 64,515.00
JUMLAH 704,235.00
C. PERALATAN HARGA
BAHAN
JUMLAH 0.00
HARGA
PERALATAN
D. JUMLAH( A + B + C ) 1,023,735.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 102,373.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,126,108.50
DIVISI 3 / 3.2.1.5

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.5
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP:8PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH 319,500.00
B. BAHAN HARGA
TENAGA
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 91.000 1,160 105,560.00
3 Pasir Pasang m3 0.584 115,000 67,160.00
JUMLAH 676,720.00
C. PERALATAN HARGA
BAHAN
JUMLAH 0.00
HARGA
PERALATAN
D. JUMLAH( A + B + C ) 996,220.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 99,622.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,095,842.00

DIVISI 3 / 3.2.1.6

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.6
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu kali campuran 1SP : 1KP : 2PP
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.500 120,000 180,000.00


2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH 319,500.00
B. BAHAN HARGA
TENAGA
1 Batu Kali m3 1.200 420,000 504000.00
2 Kapur m3 0.170 1,750,000 297500.00
3 Semen Portland Kg 0.170 1,160 197.20
4 Pasir Pasang m3 0.340 115,000 39100.00
JUMLAH 840,797.20
C. PERALATAN HARGA
BAHAN
JUMLAH 0.00
HARGA
PERALATAN
D. JUMLAH( A + B + C ) 1,160,297.20
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 116,029.72
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,276,326.92
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.7
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu belah campuran 1SP : 3KP : 10PP
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.500 120,000 180,000.00
2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 319,500.00
B. BAHAN
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 61.000 1,160 70,760.00
3 Kapur m3 0.147 1,750,000 257,250.00
4 Pasir Pasang m3 0.492 115000.000 56,580.00
JUMLAH HARGA BAHAN 888,590.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,208,090.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 120,809.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,328,899.00

DIVISI 3 / 3.2.1.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.8
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi batu belah campuran 1/4SP : 1KP : 4PP
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.500 120,000 180,000.00
2 Tukang Batu L.02 OH 0.750 150,000 112,500.00
3 Kepala Tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 319,500.00
B. BAHAN
1 Batu Kali m3 1.200 420,000 504,000.00
2 Semen Portland Kg 41.000 1,160 47,560.00
3 Kapur m3 0.131 1750000 229,250.00
4 Pasir Pasang m3 0.523 115000.000 60,145.00
JUMLAH HARGA BAHAN 840,955.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,160,455.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 116,045.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,276,500.50
DIVISI 3 / 3.2.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
KOTA 0
ITEM PEMBAYARAN NO. : 3.2.1.9
JENIS PEKERJAAN : Pemasangan 1 m³ batu kosong ( anstamping )
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.780 120,000 93,600.00
2 Tukang Batu L.02 OH 0.390 150,000 58,500.00
3 Kepala Tukang L.03 OH 0.039 175,000 6,825.00
4 Mandor L.04 OH 0.039 185,000 7,215.00
JUMLAH HARGA TENAGA 166,140.00
B. BAHAN
1 Batu Kali m3 1.2 420000.000 504000.00
2 Pasir Urug m3 0.432 95000.000 41040.00
JUMLAH HARGA BAHAN 545,040.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 711,180.00
E. OVERHEAD&PROFIT (15 %) 10,0 % x D 71,118.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 782,298.00

DIVISI 3 / 3.2.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 3.2.1.10
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi siklop, 60% beton campuran 1SP: 2PB:
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 3.400 120,000 408,000.00
2 Tukang Batu L.02 OH 0.850 150,000 127,500.00
3 Kepala Tukang L.03 OH 0.085 175,000 14,875.00
4 Mandor L.04 OH 0.170 185,000 31,450.00
JUMLAH HARGA TENAGA 581,825.00
B. BAHAN
1 Batu Kali m3 0.480 420,000 201,600.00
2 Semen Portland Kg 194.000 1,160 225,040.00
3. Pasir Beton m3 0.312 135,000 42,120.00
4 Kerikil m3 0.468 420,000 196,560.00
5 Besi Beton Kg 126.000 13,900 1,751,400.00
6 Kawat Beton Kg 1.800 20,000 36,000.00
JUMLAH HARGA BAHAN 2,452,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 3,034,545.00
E. OVERHEAD&PROFIT(CONTOH 15%) 10,0 % x D 303,454.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,337,999.50
DIVISI 3 / 3.2.1.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 3.2.1.11
JENIS PEKERJAAN : Pemasangan 1 m³ pondasi sumuran, diameter 100 cm
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 2.400 120,000 288,000.00
2 Tukang Batu L.02 OH 0.800 150,000 120,000.00
3 Kepala Tukang L.03 OH 0.080 175,000 14,000.00
4 Mandor L.04 OH 0.119 185,000 22,015.00
JUMLAH HARGA TENAGA 444,015.00
B. BAHAN
1 Batu Belah m3 0.450 420,000 189,000.00
2 Semen Portland Kg 194.000 1,160 225,040.00
3 Pasir Beton m3 0.312 135000.000 42,120.00
4 Kerikil m3 0.468 420000.000 196,560.00

JUMLAH HARGA BAHAN 652,720.00


C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,096,735.00
E. OVERHEAD&PROFIT(CONTOH 15%) 10,0 % x D 109,673.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,206,408.50
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.1
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K 100), slump(3 - 6) cm, w/c = 0,87
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.650 120,000 198,000.00


2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 247.000 1,160 286,520.00
2 Pasir Beton m3 0.621 135,000 83,835.00
3 Kerikil (Maks 30mm) m3 0.740 420,000 310,800.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 688,895.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH A + B + C ) 948,400.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 94,840.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,043,240.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.2
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K 125), slump(12 ± 2) cm, w/c = 0,78
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.650 120,000 198,000.00


2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 276.000 1,160 320,160.00
2 Pasir Beton m3 0.591 135,000 79,785.00
3 Kerikil (Maks 30mm) m3 0.750 420,000 315,000.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 722,685.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 982,190.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 98,219.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,080,409.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.3
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K 150), slump(12 ± 2) cm, w/c = 0,72
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 299.000 1,160 346,840.00
2 Pasir Beton m3 0.571 135,000 77,085.00
3 Kerikil (Maks 30mm) m3 0.753 420,000 316,260.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 747,925.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,007,430.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 100,743.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,108,173.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.4
JENIS PEKERJAAN : Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa slump (3-6) cm, w/c = 0,87
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000 144,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.060 185,000 11,100.00
JUMLAH HARGA TENAGA 188,600.00
B. BAHAN
1 Semen Portland Kg 230.000 1,160 266,800.00
2 Pasir Beton m3 0.638 135,000 86,130.00
3 Kerikil (Maks 30mm) m3 0.761 420,000 319,620.00
4 Air Liter 200.000 36 7,200.00
JUMLAH HARGA BAHAN 679,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 868,350.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 86,835.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 955,185.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.5
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 175), slump(12 ± 2) cm, w/c = 0,66
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 326.000 1,160 378,160.00
2 Pasir Beton m3 0.760 135,000 102,600.00
3 Kerikil (Maks 30mm) m3 1.029 420,000 432,180.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 920,680.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,180,185.00
E. OVERHEAD&PROFIT (15%) 10,0 % x D 118,018.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,298,203.50
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.1.6

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.6
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K 200), slump(12 ± 2) cm, w/c = 0,61
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 352.000 1,160 408,320.00
2 Pasir Beton m3 0.522 135,000 70,470.00
3 Kerikil (Maks 30mm) m3 0.764 420,000 320,880.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 807,410.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,066,915.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 106,691.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,173,606.50
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.7
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K 225), slump(12 ± 2) cm, w/c = 0,58
SATUAN PEMBAYARAN : M³
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.650 120,000 198,000.00


2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 371.000 1,160 430,360.00
2 Pasir Beton m3 0.499 135,000 67,365.00
3 Kerikil (Maks 30mm) m3 0.776 420,000 325,920.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 831,385.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,090,890.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 109,089.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,199,979.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.1.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.8
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K 250), slump(12 ± 2) cm, w/c = 0,56
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 384.000 1,160 445,440.00
2 Pasir Beton m3 0.494 135,000 66,690.00
3 Kerikil (Maks 30mm) m3 0.770 420,000 323,400.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 843,270.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,102,775.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 110,277.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,213,052.50
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.9
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 24,0 Mpa (K 275), slump(12 ± 2) cm, w/c = 0,53
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 406.000 1,160 470,960.00
2 Pasir Beton m3 0.489 135,000 66,015.00
3 Kerikil (Maks 30mm) m3 0.760 420,000 319,200.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 863,915.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,123,420.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 112,342.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,235,762.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.10
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K 300), slump(12 ± 2) cm, w/c = 0,52
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.650 120,000 198,000.00
2 Tukang Batu L.02 OH 0.275 150,000 41,250.00
3 Kepala Tukang L.03 OH 0.028 175,000 4,900.00
4 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 259,505.00
B. BAHAN
1 Semen Portland Kg 413.000 1,160 479,080.00
2 Pasir Beton m3 0.486 135,000 65,610.00
3 Kerikil (Maks 30mm) m3 0.756 420,000 317,520.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 869,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,129,455.00
E. OVERHEAD&PROFIT(15%) 10,0 % x D 112,945.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,242,400.50
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.11
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 28,8 Mpa (K 325), slump(12 ± 2) cm, w/c = 0,49
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 2.100 120,000 252,000.00
2 Tukang Batu L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.105 185,000 19,425.00
JUMLAH HARGA TENAGA 330,050.00
B. BAHAN
1 Semen Portland Kg 439.000 1,160 509,240.00
2 Pasir Beton Kg 0.479 135,000 64,665.00
3 Kerikil (Maks 30mm) Kg 0.745 420,000 312,900.00
4 Air Liter 215.000 36 7,740.00
JUMLAH HARGA BAHAN 894,545.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,224,595.00
E. OVERHEAD & PROFIT 10,0 % x D 122,459.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,347,054.50
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.1.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.12
JENIS PEKERJAAN : Membuat 1 m3 beton mutu f'c = 31,2 Mpa (K 350), slump(12 ± 2) cm, w/c = 0,48
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 2.100 120,000 252,000.00
2 Tukang Batu L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.105 185,000 19,425.00
JUMLAH HARGA TENAGA 330,050.00
B. BAHAN
1 Semen Portland Kg 448.000 1,160 519,680.00
2 Pasir Beton Kg 0.476 135,000 64,260.00
3 Kerikil (Maks 30mm) Kg 0.741 420,000 311,220.00
4 Air Liter 215 36 7,740.00
JUMLAH HARGA BAHAN 902,900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 1,232,950.00
E. OVERHEAD & PROFIT 10,0 % x D 123,295.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,356,245.00
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.13
JENIS PEKERJAAN : Membuat 1 m3 beton kedap air dengan strorox - 100
SATUAN PEMBAYARAN : M³

HARGA SATUAN JUMLAH HARGA


NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 2.100 120,000 252,000.00
2 Tukang Batu L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.105 185,000 19,425.00
JUMLAH HARGA TENAGA 330,050.00
B. BAHAN
1 Semen Portland Kg 400.000 1,160 464,000.00
2 Pasir Beton m3 0.480 135,000 64,800.00
3 Kerikil (2cm/3cm) m3 0.800 420,000 336,000.00
4 Strorox - 100 Kg 1.200 95,000 114,000.00
JUMLAH HARGA BAHAN 978,800.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,308,850.00
E. OVERHEAD & PROFIT 10,0 % x D 130,885.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,439,735.00

DIVISI 4 / 4.1.1.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.14
JENIS PEKERJAAN : Pemasangan 1 m PVC Waterstop lebar 150 mm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.060 120,000 7,200.00
2 Tukang Batu/Pipa L.02 OH 0.030 150,000 4,500.00
3 Kepala Tukang L.03 OH 0.003 175,000 525.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 12,780.00
B. BAHAN
1 Waterstop lebar 150 mm m 1.050 65,000 68,250.00
JUMLAH HARGA BAHAN 68,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 81,030.00
E. OVERHEAD & PROFIT 10,0 % x D 8,103.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 89,133.00
DIVISI 4 / 4.1.1.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.15
JENIS PEKERJAAN : Pemasangan 1 m PVC Waterstop lebar 200 mm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.070 120,000 8,400.00
2 Tukang Batu/Pipa L.02 OH 0.035 150,000 5,250.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 15,645.00
B. BAHAN
1 Waterstop lebar 200 mm m 1.050 90,000 94,500.00
JUMLAH HARGA BAHAN 94,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 110,145.00
E. OVERHEAD & PROFIT 10,0 % x D 11,014.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 121,159.50

DIVISI 4 / 4.1.1.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.16
JENIS PEKERJAAN : Pemasangan 1 m PVC Waterstop lebar 230 - 320 mm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.080 120,000 9,600.00
2 Tukang Batu L.02 OH 0.040 150,000 6,000.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 17,040.00
B. BAHAN
1 Waterstop lebar 230 - 320 mm m 1.050 150,000 157,500.00
JUMLAH HARGA BAHAN 157,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 174,540.00
E. OVERHEAD & PROFIT 10,0 % x D 17,454.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 191,994.00
DIVISI 4 / 4.1.1.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.17
JENIS PEKERJAAN : Pemasangan 10 kg dengan besi polos atau ulir
SATUAN PEMBAYARAN : Kg
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.070 120,000 8,400.00
2 Tukang Besi L.02 OH 0.070 150,000 10,500.00
3 Kepala Tukang L.03 OH 0.007 175,000 1,225.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 20,865.00
B. BAHAN
1 Besi Beton (polos/ulir) Kg 10.500 14,200 149,100.00
2 Kawat Beton Kg 0.150 20,000 3,000.00
JUMLAH HARGA BAHAN 152,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 172,965.00
E. OVERHEAD & PROFIT 10,0 % x D 17,296.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 190,261.50
1 kg 19,026.15

DIVISI 4 / 4.1.1.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.18
JENIS PEKERJAAN : Pemasangan 10 kg kabel presstressed polos / strands
SATUAN PEMBAYARAN : Kg
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.050 120,000 6,000.00
2 Tukang Besi L.02 OH 0.050 150,000 7,500.00
3 Kepala Tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 14,930.00
B. BAHAN
1 Besi Beton (polos/ulir) Kg 10.500 14,200 149,100.00
2 Kawat Beton Kg 0.100 20,000 2,000.00
JUMLAH HARGA BAHAN 151,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 166,030.00
E. OVERHEAD & PROFIT 10,0 % x D 16,603.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 182,633.00
1 Kg 18,263.30
DIVISI 4 / 4.1.1.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.19
JENIS PEKERJAAN : Pemasangan 10 kg jaring kawat baja ( wiremesh )
SATUAN PEMBAYARAN : Kg
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.025 120,000 3,000.00
2 Tukang Besi L.02 OH 0.025 150,000 3,750.00
3 Kepala Tukang L.03 OH 0.025 175,000 4,375.00
4 Mandor L.04 OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 11,310.00
B. BAHAN
1 Jaring Kawat Baja dilas Kg 10.200 12,500 127,500.00
2 Kawat Beton Kg 0.050 20,000 1,000.00
JUMLAH HARGA BAHAN 128,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 139,810.00
E. OVERHEAD & PROFIT 10,0 % x D 13,981.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 153,791.00
1 Kg 15,379.10

DIVISI 4 / 4.1.1.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.20
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk pondasi
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.520 120,000 62,400.00
2 Tukang Kayu L.02 OH 0.260 150,000 39,000.00
3 Kepala Tukang L.03 OH 0.026 175,000 4,550.00
4 Mandor L.04 OH 0.026 185,000 4,810.00
JUMLAH HARGA TENAGA 110,760.00
B. BAHAN
1 Kayu m3 0.040 1,900,000 76,000.00
2 Paku 5 - 10 cm Kg 0.300 22,000 6,600.00
3 Minyak Bekisting Liter 0.100 11,000 1,100.00
JUMLAH HARGA BAHAN 83,700.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 194,460.00
E. OVERHEAD & PROFIT 10,0 % x D 19,446.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 213,906.00
DEVISI 4 / 4.1.1.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.21
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk sloof
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.520 120,000 62,400.00
2 Tukang Kayu L.02 OH 0.260 150,000 39,000.00
3 Kepala Tukang L.03 OH 0.026 175,000 4,550.00
4 Mandor L.04 OH 0.026 185,000 4,810.00
JUMLAH HARGA TENAGA 110,760.00
B. BAHAN
1 Kayu m3 0.045 1,900,000 85,500.00
2 Paku 5 - 10 cm Kg 0.300 22,000 6,600.00
3 Minyak Bekisting Liter 0.100 11,000 1,100.00
JUMLAH HARGA BAHAN 93,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 203,960.00
E. OVERHEAD & PROFIT 10,0 % x D 20,396.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 224,356.00

DIVISI 4 / 4.1.1.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.22
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk kolom
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.660 120,000 79,200.00
2 Tukang Kayu L.02 OH 0.330 150,000 49,500.00
3 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
4 Mandor L.04 OH 0.033 185,000 6,105.00
JUMLAH HARGA TENAGA 140,580.00
B. BAHAN
1 Kayu m3 0.040 1,900,000 76,000.00
2 Paku 5 - 12 cm Kg 0.400 22,000 8,800.00
3 Minyak Bekisting Liter 0.200 11,000 2,200.00
4 Balok Kayu m3 0.015 1,600,000 24,000.00
5 Plywood tebal 9mm Lbr 0.350 145,000 50,750.00
6 Dolken Kayu ɸ 8-10cm -panj 4m Batang 2.000 15,000 30,000.00
JUMLAH HARGA BAHAN 191,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 332,330.00
E. OVERHEAD & PROFIT 10,0 % x D 33,233.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 365,563.00
DIVISI 4 / 4.1.1.23
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.23
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk balok
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.660 120,000 79,200.00
2 Tukang Kayu L.02 OH 0.330 150,000 49,500.00
3 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
4 Mandor L.04 OH 0.033 185,000 6,105.00
JUMLAH HARGA TENAGA 140,580.00
B. BAHAN
1 Kayu m3 0.040 1,900,000 76,000.00
2 Paku 5 - 12 cm Kg 0.400 22,000 8,800.00
3 Minyak Bekisting Liter 0.200 11,000 2,200.00
4 Balok Kayu m3 0.018 1,600,000 28,800.00
5 Plywood tebal 9mm Lbr 0.350 145,000 50,750.00
6 Dolken Kayu g ɸ 8-10cm -panj 4m Batang 2.000 15,000 30,000.00
JUMLAH HARGA BAHAN 196,550.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) . 337,130.00
E. OVERHEAD & PROFIT 10,0 % x D 33,713.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 370,843.00

DIVISI 4 / 4.1.1.24
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.24
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk lantai
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.660 120,000 79,200.00
2 Tukang Kayu L.02 OH 0.330 150,000 49,500.00
3 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
4 Mandor L.04 OH 0.033 185,000 6,105.00
JUMLAH HARGA TENAGA 140,580.00
B. BAHAN
1 Kayu m3 0.040 1,900,000 76,000.00
2 Paku 5 - 12 cm Kg 0.400 22,000 8,800.00
3 Minyak Bekisting Liter 0.200 11,000 2,200.00
4 Balok Kayu m3 0.015 1,600,000 24,000.00
5 Plywood tebal 9mm Lbr 0.350 145,000 50,750.00
6 Dolken Kayu galam ɸ 8-10cm -panj 4m Batang 6.000 15,000 90,000.00

JUMLAH HARGA BAHAN 251,750.00


C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 392,330.00
E. OVERHEAD & PROFIT 10,0 % x D 39,233.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 431,563.00
DIVISI 4 / 4.1.1.25
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.25
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk dinding
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.660 120,000 79,200.00
2 Tukang Kayu L.02 OH 0.330 150,000 49,500.00
3 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
4 Mandor L.04 OH 0.033 185,000 6,105.00
JUMLAH HARGA TENAGA 140,580.00
B. BAHAN
1 Kayu m3 0.030 2,600,000 78,000.00
2 Paku 5 - 12 cm Kg 0.400 22,000 8,800.00
3 Minyak Bekisting Liter 0.200 11,000 2,200.00
4 Balok Kayu m3 0.020 1,600,000 32,000.00
5 Plywood tebal 9mm Lbr 0.350 145,000 50,750.00
6 Dolken Kayu ɸ 8-10cm -panj 4m Batang 3.000 15,000 45,000.00
7 Penjaga jarak bekisting/spacer Buah 4.000 10,000 40,000.00
JUMLAH HARGA BAHAN 256,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 397,330.00
E. OVERHEAD & PROFIT 10,0 % x D 39,733.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 437,063.00

DIVISI 4 / 4.1.1.26
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.26
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk tangga
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.660 120,000 79,200.00
2 Tukang Kayu L.02 OH 0.330 150,000 49,500.00
3 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
4 Mandor L.04 OH 0.033 185,000 6,105.00
JUMLAH HARGA TENAGA 140,580.00
B. BAHAN
1 Kayu m3 0.030 2,600,000 78,000.00
2 Paku 5 - 12 cm Kg 0.400 22,000 8,800.00
3 Minyak Bekisting Liter 0.150 11,000 1,650.00
4 Balok Kayu m3 0.015 1,600,000 24,000.00
5 Plywood tebal 9mm Lbr 0.350 145,000 50,750.00
6 Dolken Kayu ɸ 8-10cm -panj 4m Batang 2.000 15,000 30,000.00
JUMLAH HARGA BAHAN 193,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 333,780.00
E. OVERHEAD & PROFIT 10,0 % x D 33,378.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 367,158.00
DIVISI 4 / 4.1.1.27

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.27
JENIS PEKERJAAN : Pemasangan 1 m2 jembatan untuk pengecoran beton
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.150 120,000 18,000.00
2 Tukang Kayu L.02 OH 0.050 150,000 7,500.00
3 Kepala Tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 27,855.00
B. BAHAN
1 Kayu m3 0.0264 1,900,000 50,160.00
2 Paku 5 - 12 cm Kg 0.600 22,000 13,200.00
3 Dolken Kayu ɸ 8-10cm -panj 4m Batang 0.500 15,000 7,500.00
JUMLAH HARGA BAHAN 70,860.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 98,715.00
E. OVERHEAD & PROFIT 10,0 % x D 9,871.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 108,586.50

DIVISI 4 / 4.1.1.35
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.35
JENIS PEKERJAAN : Membuat 1 m1 kolom praktis beton bertulang (11 x 11) cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.180 120,000 21,600.00
2 Tukang Batu L.02 OH 0.020 150,000 3,000.00
3 Tukang Kayu L.03 OH 0.020 150,000 3,000.00
4 Tukang Besi L.04 OH 0.020 150,000 3,000.00
5 Kepala Tukang L.05 OH 0.006 175,000 1,050.00
6 Mandor L.06 OH 0.009 185,000 1,665.00
JUMLAH HARGA TENAGA 33,315.00
B. BAHAN
1 Kayu m3 0.002 1,900,000 3,800.00
2 Paku 5 - 12 cm Kg 0.010 22,000 220.00
3 Minyak Bekisting Liter 0.00
4 Besi Beton Polos Kg 3.000 13,900 41,700.00
5 Kawat Beton Kg 0.450 20,000 9,000.00
6 Semen Portland Kg 4.000 1,160 4,640.00
7 Pasir Beton m3 0.006 135000 810.00
8 Kerikil m3 0.009 420000 3,780.00
JUMLAH HARGA BAHAN 63,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 97,265.00
E. OVERHEAD & PROFIT 10,0 % x D 9,726.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 106,991.50
DIVISI 4 / 4.1.1.36

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.1.36
JENIS PEKERJAAN : Membuat 1 m1 ring balok beton bertulang(10 x 15) cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.297 120,000 35,640.00
2 Tukang Batu L.02 OH 0.033 150,000 4,950.00
3 Tukang Kayu L.03 OH 0.033 150,000 4,950.00
4 Tukang Besi L.04 OH 0.033 150,000 4,950.00
5 Kepala Tukang L.05 OH 0.010 175,000 1,750.00
6 Mandor L.06 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,015.00
B. BAHAN
1 Kayu m3 0.003 1,900,000 5,700.00
2 Paku 5 - 12 cm Kg 0.020 22,000 440.00
3 Minyak Bekisting Liter 0.00
4 Besi Beton Polos Kg 3.600 13,900 50,040.00
5 Kawat Beton Kg 0.050 20,000 1,000.00
6 Semen Portland Kg 5.500 1,160 6,380.00
7 Pasir Beton m3 0.009 135000 1,215.00
8 Kerikil m3 0.015 420000 6,300.00
JUMLAH HARGA BAHAN 71,075.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 126,090.00
E. OVERHEAD & PROFIT 10,0 % x D 12,609.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 138,699.00
DIVISI 4 / 4.1.2.1
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.1
JENIS PEKERJAAN : Pembuatan 1 m2 lahan produksi tebal 8cm beton f'c 14,5 Mpa (K 175) slump (12 ± 2)cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.132 120,000 15,840.00
2 Tukang Batu L.02 OH 0.022 150,000 3,300.00
3 Kepala Tukang L.03 OH 0.002 175,000 350.00
4 Mandor L.04 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 20,785.00
B. BAHAN
1 Semen Portland Kg 26.080 1,160 30,252.80
2 Pasir Beton m3 0.043 135,000 5,805.00
3 Kerikil (Maks 30mm) m3 0.061 420,000 25,620.00
4 Air Liter 17.200 36 619.20
JUMLAH HARGA BAHAN 62,297.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 83,082.00
E. OVERHEAD & PROFIT 10,0 % x D 8,308.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 91,390.20
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%

DIVISI 4 / 4.1.2.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.2
JENIS PEKERJAAN : Pembuatan 1 m2 l ahan produksi tebal 10cm beton f'c 14,5 Mpa (K 175) slump (12 ± 2)cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 0.165 120,000 19,800.00


2 Tukang Batu L.02 OH 0.028 150,000 4,200.00
3 Kepala Tukang L.03 OH 0.003 175,000 525.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 26,005.00
B. BAHAN
1 Semen portland Kg 32.600 1,160 37,816.00
2 Pasir Beton m3 0.0543 135,000 7,330.50
3 Kerikil (Maks 30mm) m3 0.0762 420,000 32,004.00
4 Air Liter 21.500 36 774.00
JUMLAH HARGA BAHAN 77,924.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 103,929.50
E. OVERHEAD & PROFIT 10,0 % x D 10,392.95
F. HARGA SATUAN PEKERJAAN ( D + E ) 114,322.45
CATATAN
Bobot isi pasir = 1.400 kg/m3 , Bobot isi Kerikil = 1.350 kg/m3 , Buckling factor pasir = 20%
DIVISI 4 / 4.1.2.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.3
JENIS PEKERJAAN : Pembuatan 1 m2 lahan produksi tebal 12cm beton f'c 14,5 Mpa (K 175) slump (12 ± 2)cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.198 120,000 23,760.00
2 Tukang Batu L.02 OH 0.033 150,000 4,950.00
3 Kepala Tukang L.03 OH 0.003 175,000 525.00
4 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 31,085.00
B. BAHAN
1 Semen PC Kg 32.120 1,160 37,259.20
2 Pasir Beton Kg 0.065 135,000 8,775.00
3 Kerikil (Maks 30mm) Kg 0.091 420,000 38,220.00
4 Air Liter 25.800 36 928.80
JUMLAH HARGA BAHAN 85,183.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 116,268.00
E. OVERHEAD & PROFIT 10,0 % x D 11,626.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 127,894.80

DIVISI 4 / 4.1.2.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.4
JENIS PEKERJAAN : Pembuatan 1 m2 lahan produksi tebal 15 cm beton f'c 14,5 Mpa (K 175) slump (12 ± 2)cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 0.248 120,000 29,760.00


2 Tukang Batu L.02 OH 0.041 150,000 6,150.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 39,015.00
B. BAHAN
1 Semen PC Kg 48.90 1,160 56,724.00
2 Pasir Beton m3 0.0814 135,000 10,989.00
3 Kerikil (Maks 30mm) m3 0.1143 420,000 48,006.00
4 Air Liter 32.25 36 1,161.00
JUMLAH HARGA BAHAN 116,880.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 155,895.00

E. OVERHEAD & PROFIT 10,0 % x D 15,589.50


F. HARGA SATUAN PEKERJAAN ( D + E ) 171,484.50
DIVISI 4 / 4.1.2.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.5
JENIS PEKERJAAN : Pembuatan 1 m2 bekisting untuk plat beton pracetak (5 kali pakai)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.007 120,000 840.00
2 Tukang Kayu L.02 OH 0.076 150,000 11,400.00
3 Kepala Tukang L.03 OH 0.008 175,000 1,400.00
4 Mandor L.04 OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 13,825.00
B. BAHAN
1 Lantai Kerja Tebal 10cm m3 0.008 83,153 665.22
2 Besi Hollow 50.50.3 Kg 9.394 14,000 131,516.00
3 Kayu Kaso 5/7 m3 0.005 2,600,000 13,000.00
4 Phenol Film 12mm Lbr 0.080 225,000 18,000.00
5 Minyak Bekisting L 0.200 11,000 2,200.00
6 Dinabolt dia 12mm (10-15cm) Bh 3.882 13,500 52,407.00
JUMLAH HARGA BAHAN 217,788.22
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 231,613.22
E. OVERHEAD & PROFIT 10,0 % x D 23,161.32
F. HARGA SATUAN PEKERJAAN ( D + E ) 254,774.55

DIVISI 4 / 4.1.2.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.6
JENIS PEKERJAAN : Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.004 120,000 480.00
2 Tukang Kayu L.02 OH 0.038 150,000 5,700.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 7,065.00
B. BAHAN
1 Kayu Kaso 5/7 m3 0.005 2,600,000 13,000.00
2 Phenol Film 12mm Lbr 0.043 225,000 9,675.00
3 Minyak Bekisting L 0.200 11,000 2,200.00
4 Paku 5-7cm Kg 0.046 22,000 1,012.00
5 Dinabolt dia 12mm (10-15cm) Bh 0.693 13,500 9,355.50
JUMLAH HARGA BAHAN 35,242.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 42,307.50
E. OVERHEAD & PROFIT 10,0 % x D 4,230.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 46,538.25
DIVISI 4 / 4.1.2.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.7
JENIS PEKERJAAN : Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.004 120,000 480.00
2 Tukang Kayu L.02 OH 0.038 150,000 5,700.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 7,065.00
B. BAHAN
1 Kayu Kaso 5/7 m3 0.004 2,600,000 10,400.00
2 Phenol Film 12mm Lbr 0.048 225,000 10,800.00
3 Minyak Bekisting L 0.200 11,000 2,200.00
4 Paku 5-7cm Kg 0.046 22,000 1,012.00
5 Dinabolt dia 12mm (10-15cm) Bh 0.693 13,500 9,355.50
JUMLAH HARGA BAHAN 33,767.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 40,832.50
E. OVERHEAD & PROFIT 10,0 % x D 4,083.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 44,915.75

DIVISI 4 / 41.2.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.8
JENIS PEKERJAAN : Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 0.053 120,000 6,360.00


2 Tukang Kayu L.02 OH 0.018 150,000 2,700.00
3 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 9,985.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 9,985.00
E. OVERHEAD & PROFIT 10,0 % x D 998.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 10,983.50
DIVISI 4 / 4.1.2.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.9
JENIS PEKERJAAN : Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.089 120,000 10,680.00
2 Tukang Kayu L.02 OH 0.030 150,000 4,500.00
3 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 16,105.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 16,105.00
E. OVERHEAD & PROFIT 10,0 % x D 1,610.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 17,715.50

DIVISI 4 / 4.1.2.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.10
JENIS PEKERJAAN : Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.071 120,000 8,520.00
2 Tukang Kayu L.02 OH 0.024 150,000 3,600.00
3 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 13,045.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 13,045.00
E. OVERHEAD & PROFIT 10,0 % x D 1,304.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 14,349.50
DIVISI 4 / 4.1.2.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.11
JENIS PEKERJAAN : Penuangan/menebar beton untuk 1 M³ komponen untuk pelat pracetak
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L.01 OH 0.064 120,000 7,680.00


2 Tukang Batu L.02 OH 0.244 150,000 36,600.00
3 Tukang Vibrator L.02 OH 0.128 150,000 19,200.00
4 Kepala Tukang L.03 OH 0.034 175,000 5,950.00
5 Mandor L.04 OH 0.073 185,000 13,505.00
JUMLAH HARGA TENAGA 82,935.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 82,935.00
E. OVERHEAD & PROFIT 10,0 % x D 8,293.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 91,228.50

DIVISI 4 / 4.1.2.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.12
JENIS PEKERJAAN : Penuangan/menebar beton 1 M³ komponen untuk balok pracetak
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.069 120,000 8,280.00
2 Tukang Batu L.02 OH 0.242 150,000 36,300.00
3 Tukang Vibrator L.02 OH 0.138 150,000 20,700.00
4 Kepala Tukang L.03 OH 0.037 175,000 6,475.00
5 Mandor L.04 OH 0.073 185,000 13,505.00
JUMLAH HARGA TENAGA 85,260.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 85,260.00
E. OVERHEAD & PROFIT 10,0 % x D 8,526.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 93,786.00
DIVISI 4.1.2.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.13
JENIS PEKERJAAN : Penuangan/menebar beton untuk 1 M³ komponen kolom pracetak
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.061 120,000 7,320.00
2 Tukang Batu L.02 OH 0.213 150,000 31,950.00
3 Tukang Vibrator L.02 OH 0.122 150,000 18,300.00
4 Kepala Tukang L.03 OH 0.033 175,000 5,775.00
5 Mandor L.04 OH 0.073 185,000 13,505.00
JUMLAH HARGA TENAGA 76,850.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 76,850.00
E. OVERHEAD & PROFIT 10,0 % x D 7,685.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 84,535.00

DIVISI 4 / 4.1.2.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.14
JENIS PEKERJAAN : Ereksi 1 buah komponen untuk pelat beton pracetak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.067 165,000 11,055.00
2 Pembantu Operator Crane L.09 OH 0.067 110,000 7,370.00
3 Pekerja L.01 OH 0.067 120,000 8,040.00
4 Tukang Batu L.02 OH 0.067 150,000 10,050.00
5 Tukang Erection L.02 OH 0.134 150,000 20,100.00
6 Kepala Tukang L.03 OH 0.067 175,000 11,725.00
7 Mandor L.04 OH 0.067 185,000 12,395.00
JUMLAH HARGA TENAGA 80,735.00
B. BAHAN
1 Solar L 6.676 10,130 67,627.88
JUMLAH HARGA BAHAN 67,627.88
C. PERALATAN
1 Sewa Crane unit hari 0.067 550,000 36,850.00
2 Sewa Pipe Support buah hari 1.100 427 469.70
JUMLAH HARGA PERALATAN 37,319.70

D. JUMLAH( A + B + C ) 185,682.58
E. OVERHEAD & PROFIT 10,0 % x D 18,568.26
F. HARGA SATUAN PEKERJAAN ( D + E ) 204,250.84
DIVISI 4 / 4.1.2.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.15
JENIS PEKERJAAN : Ereksi 1 buah komponen untuk balok beton pracetak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.061 165,000 10,065.00
2 Pembantu Operator Crane L.09 OH 0.061 110,000 6,710.00
3 Pekerja L.01 OH 0.061 120,000 7,320.00
4 Tukang Batu L.02 OH 0.061 150,000 9,150.00
5 Tukang Erection L.02 OH 0.122 150,000 18,300.00
6 Kepala Tukang L.03 OH 0.061 175,000 10,675.00
7 Mandor L.04 OH 0.061 185,000 11,285.00
JUMLAH HARGA TENAGA 73,505.00
B. BAHAN
1 Solar L 6.110 10,130 61,894.30
JUMLAH HARGA BAHAN 61,894.30
C. PERALATAN
1 Sewa Crane unit hari 0.061 550,000 33,550.00
2 Sewa Scaffolding unit hari 1.100 1,500 1,650.00
JUMLAH HARGA PERALATAN 35,200.00

D. JUMLAH( A + B + C ) 170,599.30
E. OVERHEAD & PROFIT 10,0 % x D 17,059.93
F. HARGA SATUAN PEKERJAAN ( D + E ) 187,659.23

DIVISI 4 / 4.1.2.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.16
JENIS PEKERJAAN : Ereksi 1 buah komponen untuk kolom beton pracetak
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.083 165,000 13,695.00
2 Pembantu Operator Crane L.09 OH 0.083 110,000 9,130.00
3 Pekerja L.01 OH 0.083 120,000 9,960.00
4 Tukang Batu L.02 OH 0.083 150,000 12,450.00
5 Tukang Erection L.02 OH 0.166 150,000 24,900.00
6 Kepala Tukang L.03 OH 0.083 175,000 14,525.00
7 Mandor L.04 OH 0.083 185,000 15,355.00
JUMLAH HARGA TENAGA 100,015.00
B. BAHAN
1 Solar L 8.277 10,130 83,846.01
JUMLAH HARGA BAHAN 83,846.01
C. PERALATAN
1 Sewa Crane unit hari 0.083 550,000 45,650.00
2 Sewa Pipe Support buah hari 2.200 427 939.40
JUMLAH HARGA PERALATAN 46,589.40
D. JUMLAH ( A + B + C ) 230,450.41
E. OVERHEAD & PROFIT 10,0 % x D 23,045.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 253,495.45
DIVISI 4 / 4.1.2.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.17
JENIS PEKERJAAN : Langsir 1 buah komponen untuk pelat pracetak ( ± 20 m)
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.019 165,000 3,135.00
2 Pembantu Operator Crane L.09 OH 0.019 110,000 2,090.00
3 Pekerja L.01 OH 0.019 120,000 2,280.00
4 Tukang Batu L.02 OH 0.038 150,000 5,700.00
JUMLAH HARGA TENAGA 13,205.00
B. BAHAN
1 Solar L 1.897 10,130 19,216.61
JUMLAH HARGA BAHAN 19,216.61
C. PERALATAN
1 Sewa Crane unit hari 0.019 550,000 10,450.00
JUMLAH HARGA PERALATAN 10,450.00

D. JUMLAH( A + B + C ) 42,871.61
E. OVERHEAD & PROFIT 10,0 % x D 4,287.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 47,158.77

DIVISI 4 / 4.1.2.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.18
JENIS PEKERJAAN : Langsir 1 buah komponen untuk balok pracetak ( ± 20 m)
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.019 165,000 3,135.00
2 Pembantu Operator Crane L.09 OH 0.019 110,000 2,090.00
3 Pekerja L.01 OH 0.019 120,000 2,280.00
4 Tukang Batu L.02 OH 0.038 150,000 5,700.00
JUMLAH HARGA TENAGA 13,205.00
B. BAHAN
1 Solar L 1.897 10,130 19,217.00
JUMLAH HARGA BAHAN 19,217.00
C. PERALATAN
1 Sewa Crane unit hari 0.019 550,000 10,450.00
JUMLAH HARGA PERALATAN 10,450.00

D. JUMLAH( A + B + C ) 42,872.00
E. OVERHEAD & PROFIT 10,0 % x D 4,287.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 47,159.20
DIVISI 4.1.2.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.19
JENIS PEKERJAAN : Langsir 1 buah komponen untuk kolom pracetak ( ± 20 m)
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Operator Crane L.08 OH 0.019 165,000 3,135.00
2 Pembantu Operator Crane L.09 OH 0.019 110,000 2,090.00
3 Pekerja L.01 OH 0.019 120,000 2,280.00
4 Tukang Batu L.02 OH 0.038 150,000 5,700.00
JUMLAH HARGA TENAGA 13,205.00
B. BAHAN
1 Solar L 1.897 10,130 19,216.61
JUMLAH HARGA BAHAN 19,216.61
C. PERALATAN
1 Sewa Crane UH 0.019 550,000 10,450.00
JUMLAH HARGA PERALATAN 10,450.00

D. JUMLAH( A + B + C ) 42,871.61
E. OVERHEAD & PROFIT 10,0 % x D 4,287.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 47,158.77

DIVISI 4 / 4.1.2.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.20
JENIS PEKERJAAN : Bahan 1 m3 grout campuran
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
JUMLAH HARGA TENAGA 0.00
B. BAHAN
1 Semen Grout Kg 1,200.00 1,160 1,392,000.00
2 Screening Kg 650.00 83 53,950.00
3 Air L 350.00 36 12,600.00
JUMLAH HARGA BAHAN 1,458,550.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,458,550.00
E. OVERHEAD & PROFIT 10,0 % x D 145,855.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,604,405.00
DIVISI 4 / 4.1.2.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.21
JENIS PEKERJAAN : Bahan 1 m3 grout (tidak campuran)
SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
JUMLAH HARGA TENAGA 0.00
B. BAHAN
1 Semen Grout Kg 1,850.00 1,160 2,146,000.00
2 Air L 400.00 36 14,400.00
JUMLAH HARGA BAHAN 2,160,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 2,160,400.00
E. OVERHEAD & PROFIT 10,0 % x D 216,040.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,376,440.00

DIVISI 4 / 4.1.2.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.22
JENIS PEKERJAAN : Upah 1 titik pekerjaan grout pada joint beton pracetak
SATUAN PEMBAYARAN : Titik
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Tukang Batu L.02 OH 0.367 160,000 58720.00
2 Kepala Tukang L.03 OH 0.074 180,000 13320.00
3 Mandor L.04 OH 0.037 185,000 6845.00
JUMLAH HARGA TENAGA 78,885.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 78,885.00
E. OVERHEAD & PROFIT 10,0 % x D 7,888.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 86,773.50
DIVISI 4 / 4.1.2.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.23
JENIS PEKERJAAN : Pemasangan 1 titk bekisting joint pracetak
SATUAN PEMBAYARAN : Titik
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.147 140,000 20,580.00
2 Tukang Kayu L.02 OH 0.147 160,000 23,520.00
3 Kepala Tukang L.03 OH 0.015 180,000 2,700.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 47,725.00
B. BAHAN
1 Kayu Kaso 5/7 m3 0.012 3E+06 ###
2 Papan cor m3 0.004 2E+06 ###
3 Paku 5-7cm Kg 0.264 22,000 5,808.00
JUMLAH HARGA BAHAN 43,408.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 91,133.00
E. OVERHEAD & PROFIT 10,0 % x D 9,113.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 100,246.30

DIVISI 4 / 4.1.2.24

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.1.2.24
JENIS PEKERJAAN : Upah 1 titk Join dengan Sling
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja 0.220 120,000 26,400.00
2 Tukang Kayu L.02 OH 0.022 150,000 3,300.00
3 Tukang Besi L.02 OH 0.220 150,000 33,000.00
4 Mandor L.04 OH 0.011 185,000 2,035.00
JUMLAH HARGA TENAGA 64,735.00
B. BAHAN
JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 64,735.00
E. OVERHEAD & PROFIT 10,0 % x D 6,473.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 71,208.50
DIVISI 4 / 4.2.1.1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.1
JENIS PEKERJAAN : Pemasangan 1 kg besi profil
SATUAN PEMBAYARAN : Kg
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.060 120,000 7,200.00
2 Tukang Las Konstruksi L.03 OH 0.060 150,000 9,000.00
3 Kepala Tukang L.03 OH 0.006 175,000 1,050.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 17,805.00
B. BAHAN
1 Besi Baja IWF Kg 1.150 14,000 16,100.00
JUMLAH HARGA BAHAN 16,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 33,905.00
E. OVERHEAD & PROFIT 10,0 % x D 3,390.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 37,295.50

DIVISI 4 / 4.2.1.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.2
JENIS PEKERJAAN : Pemasangan 1 kg rangka kuda-kuda baja IWF
SATUAN PEMBAYARAN : Kg
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 0.060 120,000 7,200.00


2 Tukang Las Konstruksi L.03 OH 0.060 150,000 9,000.00
3 Kepala Tukang L.03 OH 0.006 175,000 1,050.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 17,805.00
B. BAHAN
1 Besi baja IWF Kg 1.150 14,000 16,100.00
JUMLAH HARGA BAHAN 16,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 33,905.00
E. OVERHEAD & PROFIT 10,0 % x D 3,390.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 37,295.50
DIVISI 4 / 4.2.1.2a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.2a
JENIS PEKERJAAN : Pemasangan 1 m2 rangka kuda -kuda + reng atap baja ringan
SATUAN PEMBAYARAN : M²
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang L.03 OH 0.450 150,000 67,500.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 102,500.00
B. BAHAN
1 Profil C-75. 80/81 M' 1.488 18,333 27,279.50
2 Profil C-75. 75 M' 2.232 16,333 36,455.26
3 Reng M' 5.400 7,500 40,500.00
4 Screw bh 38.000 175 6,650.00
5 Dynabolt bh 1.600 1,500 2,400.00
6 Talang Jurai M' 0.124 27,000 3,348.00
JUMLAH HARGA BAHAN 116,632.76
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 219,132.76
E. OVERHEAD & PROFIT 10,0 % x D 21,913.28
F. HARGA SATUAN PEKERJAAN ( D + E ) 241,046.04

DIVISI 4 / 4.2.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.3
JENIS PEKERJAAN : Pengerjaan 100 kg pekerjaan perakitan
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Las Biasa L.03 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.001 175,000 175.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 28,100.00
B. BAHAN
1 Solar Kg 1.000 10,130 10,130.00
2 Minyak Pelumas Kg 0.100 35,000 3,500.00
JUMLAH HARGA BAHAN 13,630.00
C. PERALATAN
Sewa alat las jam 0.8 7500 6,000.00
JUMLAH HARGA PERALATAN 6000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 47,730.00


E. OVERHEAD & PROFIT 10,0 % x D 4,773.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 52,503.00
DIVISI 4 / 4.2.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.4
JENIS PEKERJAAN : Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 1.050 120,000 126,000.00


2 Tukang Las Biasa L.03 OH 1.050 150,000 157,500.00
3 Kepala Tukang L.03 OH 0.105 175,000 18,375.00
4 Mandor L.04 OH 0.052 185,000 9,620.00
JUMLAH HARGA TENAGA 311,495.00
B. BAHAN
1 Besi Siku L 30.30.3 Kg 15.000 10,000 150,000.00
2 Besi Plat Baja Kg 32.800 10,000 328,000.00
3 Kawat Las listrik Kg 0.05 35,000 1,750.00
JUMLAH HARGA BAHAN 479,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 791,245.00


E. OVERHEAD & PROFIT 10,0 % x D 79,124.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 870,369.50

DIVISI 4 / 4.2.1.5

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.5
JENIS PEKERJAAN : Pengerjaan 10 cm pengelasan dengan las listrik
SATUAN PEMBAYARAN : Cm
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A. TENAGA (Rp.) (Rp.)

1 Pekerja L.01 OH 0.040 120,000 4,800.00


2 Tukang Besi Konstruksi L.03 OH 0.020 150,000 3,000.00
3 Kepala Tukang L.03 OH 0.002 175,000 350.00
4 Mandor L.04 OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 8,520.00
B. BAHAN
1 Kawat Las Listrik Kg 0.400 35,000 14,000.00
2 Solar Liter 0.300 10,130 3,039.00
3 Minyak Pelumas Liter 0.040 35,000 1,400.00
JUMLAH HARGA BAHAN 18,439.00
C. PERALATAN
1 Sewa Alat Las Jam 0.170 35,000 5,950.00
JUMLAH HARGA PERALATAN 5,950.00

D. JUMLAH( A + B + C ) 32,909.00
E. OVERHEAD & PROFIT 10,0 % x D 3,290.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 36,199.90
DIVISI 4 / 4.2.1.6

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.6
JENIS PEKERJAAN : Pembuatan 1 m2 rangka jendela besi scuare tube
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja (L01) OH 0.650 120,000 78,000.00
2 Tukang las Biasa (L03) OH 0.650 150,000 97,500.00
3 Kepala Tukang (L03) OH 0.065 175,000 11,375.00
4 Mandor (L04) OH 0.032 185,000 5,920.00
JUMLAH HARGA TENAGA 192,795.00
B. BAHAN
1 Besi Square Tube m 4.760 15,000 71,400.00
1 Besi Lis Kaca (1 x 1) cm m 4.522 30,000 135,660.00
3 Pengelasan cm 20 0.00
JUMLAH HARGA BAHAN 207,060.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 399,855.00


E. OVERHEAD & PROFIT 10,0 % x D 39,985.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 439,840.50

DIVISI 4 / 4.2.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.7
JENIS PEKERJAAN : Pemasangan 1 m2 pintu rolling door besi
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.200 120,000 144,000.00
2 Tukang Las Biasa L.03 OH 1.200 150,000 180,000.00
3 Kepala Tukang L.03 OH 0.120 175,000 21,000.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 346,110.00
B. BAHAN
1 Rolling Door Besi m2 1.000 585,000 585,000.00
JUMLAH HARGA BAHAN 585,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 931,110.00


E. OVERHEAD & PROFIT 10,0 % x D 93,111.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,024,221.00
DIVISI 4 / 4.2.1.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.8
JENIS PEKERJAAN : Pemasangan 1 m2 pintu lipat (folding door) bahan plastik / PVC
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.440 120,000 52,800.00
2 Tukang L.03 OH 0.440 150,000 66,000.00
3 Kepala Tukang L.03 OH 0.044 175,000 7,700.00
4 Mandor L.04 OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 130,570.00
B. BAHAN
1 Pintu Lipat m2 1.000 550,000 550,000.00
JUMLAH HARGA BAHAN 550,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 680,570.00
E. OVERHEAD & PROFIT 10,0 % x D 68,057.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 748,627.00

DIVISI 4 / 4.2.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.9
JENIS PEKERJAAN : Pemasangan 1 m2 sunscreen alluminium
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.080 120,000 9,600.00
2 Tukang L.03 OH 0.800 150,000 120,000.00
3 Kepala Tukang L.03 OH 0.080 175,000 14,000.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 144,340.00
B. BAHAN
1 Sunscreen Alluminium m2 1.000 425,000 425,000.00
JUMLAH HARGA BAHAN 425,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 569,340.00
E. OVERHEAD & PROFIT 10,0 % x D 56,934.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 626,274.00
DIVISI 4 / 4.2.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.10
JENIS PEKERJAAN : Pemasangan 1 m2 rolling door alluminium
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.000 120,000 120,000.00
2 Tukang Khusus Alumunium L.03 OH 1.000 150,000 150,000.00
3 Kepala Tukang L.03 OH 0.100 175,000 17,500.00
4 Mandor L.04 OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 296,750.00
B. BAHAN
1 Rolling door aluminium m2 1.000 685,000 685,000.00
JUMLAH HARGA BAHAN 685,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 981,750.00
E. OVERHEAD & PROFIT 10,0 % x D 98,175.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,079,925.00

DIVISI 4 / 4.2.1.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.11
JENIS PEKERJAAN : Pemasangan 1 m kusen pintu alluminium
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.043 120,000 5,160.00
2 Tukang Khusus Aluminium L.03 OH 0.043 150,000 6,450.00
3 Kepala Tukang L.03 OH 0.0043 175,000 752.50
4 Mandor L.03 OH 0.0021 185,000 388.50
JUMLAH HARGA TENAGA 12,751.00
B. BAHAN
1 Profil Alluminium m 1.100 150,000 165,000.00
2 Skrup Fixer buah 2.000 950 1,900.00
3 Sealant tube 0.060 30,000 1,800.00
JUMLAH HARGA BAHAN 168,700.00

C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA( A + B + C ) 181,451.00


E. OVERHEAD & PROFIT 10,0 % x D 18,145.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 199,596.10
DIVISI 4 / 4.2.1.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.12
JENIS PEKERJAAN : Pemasangan 1 m2 pintu alluminium strip lebar 8 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.085 120,000 10,200.00
2 Tukang Khusus Aluminium L.03 OH 0.085 150,000 12,750.00
3 Kepala Tukang L.03 OH 0.0085 175,000 1,487.50
4 Mandor L.04 OH 0.0042 185,000 777.00
JUMLAH HARGA TENAGA 25,214.50
B. BAHAN
1 Profil Alluminium m 4.400 150,000 660,000.00
2 Alluminium Strip m 14.600 38,500 562,100.00
JUMLAH HARGA BAHAN 1,222,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 1,247,314.50
E. OVERHEAD & PROFIT 10,0 % x D 124,731.45
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,372,045.95

DIVISI 4 / 4.2.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.13
JENIS PEKERJAAN : Pemasangan 1 m2 pintu kaca rangka alluminium
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.085 120,000 10,200.00
2 Tukang Khusus Aluminium/Kaca L.03 OH 0.085 150,000 12,750.00
3 Kepala Tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 25,450.00
B. BAHAN
1 Pintu Alluminium m 4.400 200,000 880,000.00
2 Profil Kaca m 4.500 7,500 33,750.00
3 Sealant Tube 0.270 30,000 8,100.00
JUMLAH HARGA BAHAN 921,850.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 947,300.00
E. OVERHEAD & PROFIT 10,0 % x D 94,730.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,042,030.00
DIVISI 4 / 4.2.1.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.14
JENIS PEKERJAAN : Pemasangan 1 m2 venetions blinds dan vertical blinds
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.350 120,000 42,000.00
2 Tukang L.03 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 103,955.00
B. BAHAN
1 Venetions Blinds dan Vertical Blinds m2 1.000 38,000 38,000.00
(tirai)
JUMLAH HARGA BAHAN 38,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 141,955.00
E. OVERHEAD & PROFIT 10,0 % x D 14,195.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 156,150.50

DIVISI 4 / 4.2.1.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.15
JENIS PEKERJAAN : Pemasangan 1 m2 terali besi strip (2 x 3) mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.670 120,000 200,400.00
2 Tukang Las L.03 OH 1.670 150,000 250,500.00
3 Kepala Tukang L.03 OH 0.167 175,000 29,225.00
4 Mandor L.04 OH 0.083 185,000 15,355.00

JUMLAH HARGA TENAGA 495,480.00


B. BAHAN
1 Besi Strip Kg 6.177 9,000 55,593.00
2 Pengelasan cm 27.080 0 0.00
JUMLAH HARGA BAHAN 55,593.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 551,073.00
E. OVERHEAD & PROFIT 10,0 % x D 55,107.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 606,180.30
DIVISI 4 / 4.2.1.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.16
JENIS PEKERJAAN : Pemasangan 1 m2 kawat nyamuk
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang L.03 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00
B. BAHAN
1 Kawat Nyamuk m2 1.100 25,000 27,500.00
2 Pengelasan cm 11.11 - 0.00
3 Besi Strip Kg 1.716 9,000 15,444.00
JUMLAH HARGA BAHAN 42,944.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 72,619.00
E. OVERHEAD & PROFIT 10,0 % x D 7,261.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,880.90

DIVISI 4 / 4.2.1.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.17
JENIS PEKERJAAN : Pemasangan 1 m2 jendela nako dan tralis
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang L.03 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.001 185,000 185.00

JUMLAH HARGA TENAGA 57,685.00


B. BAHAN
m2 302,500.00
1 Jendela Nako (Rangka + Kaca 5mm) 1.100 275,000

2 Paku Skrup 1cm - 2,5cm buah 10.000 55 550.00


3 Besi Strip m2 7.000 9,000 63,000.00
JUMLAH HARGA BAHAN 366,050.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 423,735.00
E. OVERHEAD & PROFIT 10,0 % x D 42,373.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 466,108.50
DIVISI 4 / 4.2.1.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.18
JENIS PEKERJAAN : Pemasangan 1 m' talang datar / jurai seng bjls 28 lebar 90 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang L.03 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 57,685.00
B. BAHAN
1 Seng Plat m 1.050 50,000 52,500.00
2 Paku 1 cm - 2,5 cm Kg 0.015 22,000 330.00
3 Papan Kayu Kelas II atau III m3 0.019 2,600,000 49,400.00
JUMLAH HARGA BAHAN 102,230.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 159,915.00
E. OVERHEAD & PROFIT 10,0 % x D 15,991.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 175,906.50

DIVISI 4 / 4.2.1.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.19
JENIS PEKERJAAN : Pemasangan 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.150 120,000 18,000.00
2 Tukang L.03 OH 0.300 150,000 45,000.00
3 Kepala Tukang L.03 OH 0.030 175,000 5,250.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 69,730.00
B. BAHAN
1 Seng Plat m 1.050 63,000 66,150.00
2 Paku 1 cm - 2,5 cm Kg 0.010 22,000 220.00
3 Besi Strip Kg 0.500 9,000 4,500.00
JUMLAH HARGA BAHAN 70,870.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 140,600.00
E. OVERHEAD & PROFIT 10,0 % x D 14,060.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 154,660.00
DIVISI 4 / 4.2.1.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.20
JENIS PEKERJAAN : Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120cm, dinding partisi
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Besi L.02 OH 0.250 150,000 37,500.00
3 Kepala Tukang L.03 OH 0.025 175,000 4,375.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 74,280.00
B. BAHAN
1 Rangka Metal Hollow 40.40.2 mm M1 3.500 6,250 21,875.00
2 Assesoris (perkuatan, las dll) Ls 100%xrangka 6,250.00
JUMLAH HARGA BAHAN 28,125.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 102,405.00
E. OVERHEAD & PROFIT 10,0 % x D 10,240.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 112,645.50

DIVISI 4 / 4.2.1.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.21
JENIS PEKERJAAN : Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120cm, untuk plafon
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN SATUAN KOEFISIEN
KODE (Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.350 120,000 42,000.00
2 Tukang Besi L.02 OH 0.350 150,000 52,500.00
3 Kepala Tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 103,955.00
B. BAHAN
1 Rangka Metal Hollow 40.40.2 mm M1 4.000 6,250 25,000.00
2 Assesoris (perkuatan, las dll) 100%xrangka Ls 1 6,250 6,250.00
JUMLAH HARGA BAHAN 31,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 135,205.00
E. OVERHEAD & PROFIT 10,0 % x D 13,520.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 148,725.50
DIVISI 4 / 4.2.1.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.22
JENIS PEKERJAAN : Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.734 120,000 88,080.00
2 Tukang Besi L.02 OH 0.734 150,000 110,100.00
3 Kepala Tukang L.03 OH 0.073 175,000 12,775.00
4 Mandor L.04 OH 0.037 185,000 6,845.00
JUMLAH HARGA TENAGA 217,800.00
B. BAHAN
1 Baja ringan canai dingin C75 kg 3.065 16,750 51,338.75
JUMLAH HARGA BAHAN 51,338.75
C. PERALATAN
Peralatan 10 % 0.1 16,750 1,675.00
JUMLAH HARGA PERALATAN 1,675.00

D. JUMLAH( A + B + C ) 270,813.75
E. OVERHEAD & PROFIT 10,0 % x D 27,081.38
F. HARGA SATUAN PEKERJAAN ( D + E ) 297,895.13

DIVISI 4 / 4.2.1.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.2.1.23
JENIS PEKERJAAN : Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.7604 120,000 91,248.00
2 Tukang Besi L.02 OH 0.7604 150,000 114,060.00
3 Kepala Tukang L.03 OH 0.0760 175,000 13,300.00
4 Mandor L.04 OH 0.0380 185,000 7,030.00
JUMLAH HARGA TENAGA 225,638.00
B. BAHAN
1 Baja ringan canai dingin C75 kg 4.05 16,750 67,837.50
JUMLAH HARGA BAHAN 67,837.50
C. PERALATAN
Peralatan 10 % 0.10 16,750 1,675.00
JUMLAH HARGA PERALATAN 1,675.00

D. JUMLAH( A + B + C ) 295,150.50
E. OVERHEAD & PROFIT 10,0 % x D 29,515.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 324,665.55
DIVISI 4 / 4.4.1.1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.1
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:2PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN 0.00
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 43.5 1,160 50,460.00
3 Pasir Pasang m3 0.08 115,000 9,200.00
JUMLAH HARGA BAHAN 136,660.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 247,710.00
E. OVERHEAD & PROFIT 10,0 % x D 24,771.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 272,481.00

DIVISI 4 / 4.4.1.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.2
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN 0.00
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 32.950 1,160 38,222.00
3 Pasir Pasang m3 0.091 115,000 10,465.00
JUMLAH HARGA BAHAN 125,687.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 236,737.00
E. OVERHEAD & PROFIT 10,0 % x D 23,673.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 260,410.70
DIVISI 4 / 4.4.1.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.3
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN 0.00
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 26.550 1,160 30,798.00
3 Pasir Pasang m3 0.093 115,000 10,695.00
JUMLAH HARGA BAHAN 118,493.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 229,543.00
E. OVERHEAD & PROFIT 10,0 % x D 22,954.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 252,497.30

DIVISI 4 / 4.4.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.4
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:5PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN 0.00
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 22.200 1,160 25,752.00
3 Pasir Pasang m3 0.102 115,000 11,730.00
JUMLAH HARGA BAHAN 114,482.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 225,532.00
E. OVERHEAD & PROFIT 10,0 % x D 22,553.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 248,085.20
DIVISI 4 / 4.4.1.5

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.5
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:6PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN 0.00
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 18.500 1,160 21,460.00
3 Pasir Pasang m3 0.122 115,000 14,030.00
JUMLAH HARGA BAHAN 112,490.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 223,540.00
E. OVERHEAD & PROFIT 10,0 % x D 22,354.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 245,894.00

DIVISI 4 / 4.4.1.6

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.6
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP:3KP:10PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.600 120,000 72,000.00
2 Tukang Batu L.02 OH 0.200 150,000 30,000.00
3 Kepala Tukang L.03 OH 0.020 175,000 3,500.00
4 Mandor L.04 OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 111,050.00
B. BAHAN
1 Bata Merah buah 140.000 550 77,000.00
2 Semen Portland Kg 10.080 1,160 11,692.80
3. Kapur Padam m3 0.0275 1,750,000 48,125.00
4 Pasir Pasang m3 0.0925 115000 10,637.50
JUMLAH HARGA BAHAN 147,455.30
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 258,505.30
E. OVERHEAD & PROFIT 10,0 % x D 25,850.53
F. HARGA SATUAN PEKERJAAN ( D + E ) 284,355.83
DIVISI 4 / 4.4.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.7
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP:2PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 18.950 1,160 21,982.00
3 Pasir Pasang m3 0.038 115,000 4,370.00
JUMLAH HARGA BAHAN 64,852.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 120,377.00
E. OVERHEAD & PROFIT 10,0 % x D 12,037.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 132,414.70

DIVISI 4 / 4.4.1.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.8
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 14.370 1,160 16,669.20
3 Pasir Pasang m3 0.040 115,000 4,600.00
JUMLAH HARGA BAHAN 59,769.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 115,294.20
E. OVERHEAD & PROFIT 10,0 % x D 11,529.42
F. HARGA SATUAN PEKERJAAN ( D + E ) 126,823.62
DIVISI 4 / 4.4.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.9
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 11.500 1,160 13,340.00
3 Pasir Pasang m3 0.043 115,000 4,945.00
JUMLAH HARGA BAHAN 56,785.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 112,310.00
E. OVERHEAD & PROFIT 10,0 % x D 11,231.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 123,541.00

DIVISI 4 / 4.4.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.10
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:5PP
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja L.01 OH 0.300 120,000 36,000.00


2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 9.680 1,160 11,228.80
3 Pasir Pasang m3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 54,903.80
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 110,428.80
E. OVERHEAD & PROFIT 10,0 % x D 11,042.88
F. HARGA SATUAN PEKERJAAN ( D + E ) 121,471.68
DIVISI 4 / 4.4.1.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.11
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:6PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00

3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00


4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 8.320 1,160 9,651.20
3 Pasir Pasang m3 0.049 115,000 5,635.00
JUMLAH HARGA BAHAN 53,786.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 109,311.20
E. OVERHEAD & PROFIT 10,0 % x D 10,931.12
F. HARGA SATUAN PEKERJAAN ( D + E ) 120,242.32

DIVISI 4 / 4.4.1.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.12
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:8PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00

JUMLAH HARGA TENAGA 55,525.00


B. BAHAN 0.00
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 6.500 1,160 7,540.00
3 Pasir Pasang m3 0.050 115,000 5,750.00
JUMLAH HARGA BAHAN 51,790.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 107,315.00
E. OVERHEAD & PROFIT 10,0 % x D 10,731.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 118,046.50
DIVISI 4 / 4.4.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.13
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 /2 batu campuran 1SP:3KP:10PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Portland Kg 4.500 1,160 5,220.00
3 Kapur Padam m3 0.015 1750000 26,250.00
4 Pasir Pasang m3 0.05 115000 5,750.00
JUMLAH HARGA BAHAN 75,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 131,245.00
E. OVERHEAD & PROFIT 10,0 % x D 13,124.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 144,369.50

DIVISI 4 / 4.4.1.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.14
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM:1KP:1PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00

3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00


4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Merah Kg 0.018 75000 1,350.00
3 Kapur Padam M3 0.018 1750000 31,500.00
4 Pasir Pasang M3 0.018 115000 2,070.00
JUMLAH HARGA BAHAN 73,420.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 128,945.00
E. OVERHEAD & PROFIT 10,0 % x D 12,894.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 141,839.50
DIVISI 4 / 4.4.1.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.15
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM:1KP:2PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 Bata Merah buah 70.000 550 38,500.00
2 Semen Merah Kg 0.014 75,000 1,050.00
3 Kapur Padam m3 0.014 1750000 24,500.00
4 Pasir Pasang m3 0.028 115000 3,220.00
JUMLAH HARGA BAHAN 67,270.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 122,795.00
E. OVERHEAD & PROFIT 10,0 % x D 12,279.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 135,074.50

DIVISI 4 / 4.4.1.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.16
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB20 campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.350 120,000 42,000.00
2 Tukang Batu L.02 OH 0.150 150,000 22,500.00
3 Kepala Tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 70,455.00
B. BAHAN
1 HB-20 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 30.320 1,160 35,171.20
2 Pasir Pasang m3 0.7280 115,000 83,720.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 278,501.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 348,956.20
E. OVERHEAD & PROFIT 10,0 % x D 34,895.62
F. HARGA SATUAN PEKERJAAN ( D + E ) 383,851.82
DIVISI 4 / 4.4.1.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.17
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB20 campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.350 120,000 42,000.00
2 Tukang Batu L.02 OH 0.150 150,000 22,500.00
3 Kepala Tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 70,455.00
B. BAHAN
1 HB-20 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 24.260 1,160 28,141.60
2 Pasir Pasang m3 0.772 115,000 88,780.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 276,531.60
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 346,986.60
E. OVERHEAD & PROFIT 10,0 % x D 34,698.66
F. HARGA SATUAN PEKERJAAN ( D + E ) 381,685.26

DIVISI 4 / 4.4.1.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.18
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB15 campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.320 120,000 38,400.00
2 Tukang Batu L.02 OH 0.120 150,000 18,000.00
3 Kepala Tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.016 185,000 2,960.00
JUMLAH HARGA TENAGA 61,460.00
B. BAHAN
1 HB-15 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 22.740 1,160 26,378.40
2 Pasir Pasang m3 0.550 115,000 63,250.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 249,238.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 310,698.40
E. OVERHEAD & PROFIT 10,0 % x D 31,069.84
F. HARGA SATUAN PEKERJAAN ( D + E ) 341,768.24
DIVISI 4 / 4.4.1.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.19
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB15 campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.320 120,000 38,400.00
2 Tukang Batu L.02 OH 0.120 150,000 18,000.00
3 Kepala Tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.016 185,000 2,960.00
JUMLAH HARGA TENAGA 61,460.00
B. BAHAN
1 HB-15 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 18.200 1,160 21,112.00
2 Pasir Pasang m3 0.582 115,000 66,930.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 247,652.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 309,112.00
E. OVERHEAD & PROFIT 10,0 % x D 30,911.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 340,023.20

DIVISI 4 / 4.4.1.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.20
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB10 campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 HB-10 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 15.160 1,160 17,585.60
2 Pasir Pasang m3 0.364 115,000 41,860.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 219,055.60
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 274,580.60
E. OVERHEAD & PROFIT 10,0 % x D 27,458.06
F. HARGA SATUAN PEKERJAAN ( D + E ) 302,038.66
DIVISI 4 / 4.4.1.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.21
JENIS PEKERJAAN : Pemasangan 1 m2 dinding conblock HB10 campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 HB-10 bh 12.500 12,500 156,250.00
1 Semen Portland Kg 12.130 1,160 14,070.80
2 Pasir Pasang m3 0.388 115,000 44,620.00
4 Besi Angker diameter 8 Kg 0.280 12,000 3,360.00
JUMLAH HARGA BAHAN 218,300.80
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 273,825.80
E. OVERHEAD & PROFIT 10,0 % x D 27,382.58
F. HARGA SATUAN PEKERJAAN ( D + E ) 301,208.38

DIVISI 4 / 4.4.1.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.22
JENIS PEKERJAAN : Pemasangan 1 m2 dinding terawang (rooster ) 12x11x24 campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Bata Rooster bh 30.000 3,350 100,500.00
2 Semen Portland Kg 11.000 1,160 12,760.00
3 Pasir Pasang m3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 117,285.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 172,810.00
E. OVERHEAD & PROFIT 10,0 % x D 17,281.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 190,091.00
DIVISI 4 / 4.4.1.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.23
JENIS PEKERJAAN : Pemasangan 1 m2 dinding terawang (rooster beton) 20x20 campuran 1SP:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Rooster beton Semen Portland Pasir Pasang bh 25.000 7,700 192,500.00
2 Kg 11.000 1,160 12,760.00
3 m3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 209,285.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 264,810.00
E. OVERHEAD & PROFIT 10,0 % x D 26,481.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 291,291.00

DIVISI 4 / 4.4.1.23.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.23.a
JENIS PEKERJAAN : Pemasangan 1 m² dinding terawang (rooster keramik) 20x20 camp. 1PC:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Rooster keramik 20x20 bh 25.000 38,000 0.00
2 Semen Portland Kg 11.000 1,160 12,760.00
3 Pasir Pasang m3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 16,785.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 72,310.00
E. OVERHEAD & PROFIT 10,0 % x D 7,231.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,541.00
DIVISI 4 / 4.4.1.23.b

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.23.b
JENIS PEKERJAAN : Pemasangan 1 m² dinding glass block 20x20 camp. 1PC:4PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN 0.00
1 Glass Block 20x20 bh 25.000 24,000 600,000.00
2 Semen Portland Kg 11.000 1,160 12,760.00
3 Pasir Pasang m3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 616,785.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 672,310.00
E. OVERHEAD & PROFIT 10,0 % x D 67,231.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 739,541.00

DIVISI 4 / 4.4.1.24

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.24
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 campuran 1SP:3PP
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.150 150,000 22,500.00
3 Kepala Tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN 0.00
1 Bata Rooster bh 70.000 3,350 234,500.00
2 Semen Portland Kg 14.000 1,160 16,240.00
3 Pasir Pasang m3 0.032 115,000 3,680.00
JUMLAH HARGA BAHAN 254,420.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 318,320.00
E. OVERHEAD & PROFIT 10,0 % x D 31,832.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 350,152.00
DIVISI 4 / 4.4.1.25

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.25
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.67 120,000 80,400.00
2 Tukang Batu L.02 OH 1.300 150,000 195,000.00
3 Kepala Tukang L.03 OH 0.13 175,000 22,750.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 298,705.00
B. BAHAN
1 Bata ringan tebal 7,5 cm bh 8.40 12,150 102,060.00
2 Mortar siap pakai Kg 0.473 3,500 1,655.50
JUMLAH HARGA BAHAN 103,715.50
C. PERALATAN
Peralatan 10 % 0 103,716.52 10,371.65
JUMLAH HARGA PERALATAN 10,371.65

D. JUMLAH ( A + B + C ) 412,792.15
E. OVERHEAD & PROFIT 10,0 % x D 41,279.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 454,071.37

DIVISI 4 / 4.4.1.26

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.1.26
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.671 120,000 80,520.00
2 Tukang Batu L.02 OH 1.300 150,000 195,000.00
3 Kepala Tukang L.03 OH 0.13 175,000 22,750.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 298,825.00
B. BAHAN
1 Bata ringan tebal 10 cm bh 8.40 16,201 136,088.40
2 Mortar siap pakai Kg 0.063 3,500 220.50
JUMLAH HARGA BAHAN 136,308.90
C. PERALATAN
Peralatan 10 % 0.10 136,305.94 13,630.59
JUMLAH HARGA PERALATAN 13,630.59

D. JUMLAH ( A + B + C ) 448,764.49
E. OVERHEAD & PROFIT 10,0 % x D 44,876.45
F. HARGA SATUAN PEKERJAAN ( D + E ) 493,640.94
DIVISI 4 / 4.4.2.1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.1
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:1PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.03 OH 0.150 150,000 22,500.00
3 Kepala Tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 15.504 1,160 19,380.00
2 Pasir Pasang m3 0.016 115,000 1,680.00
JUMLAH HARGA BAHAN 21,060.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 84,960.00
E. OVERHEAD & PROFIT 10,0 % x D 8,496.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 93,456.00

DIVISI 4 / 4.4.2.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.2
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:2PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 10.224 1,160 11,859.84
2 Pasir Pasang m3 0.020 115,000 2,300.00
JUMLAH HARGA BAHAN 14,159.84
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 78,059.84
E. OVERHEAD & PROFIT 10,0 % x D 7,805.98
F. HARGA SATUAN PEKERJAAN ( D + E ) 85,865.82

DIVISI 4 / 4.4.2.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.3
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:3PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 7.776 1,160 9,020.16
2 Pasir Pasang m3 0.023 115,000 2,645.00
JUMLAH HARGA BAHAN 11,665.16
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 75,565.16
E. OVERHEAD & PROFIT 10,0 % x D 7,556.52
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,121.68
DIVISI 4 / 4.4.2.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.4
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:4PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 6.240 1,160 7,238.40
2 Pasir Pasang m3 0.024 115,000 2,760.00
JUMLAH HARGA BAHAN 9,998.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 73,898.40
E. OVERHEAD & PROFIT 10,0 % x D 7,389.84
F. HARGA SATUAN PEKERJAAN ( D + E ) 81,288.24

DIVISI 4 / 4.4.2.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.5
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:5PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 5.184 1,160 6,013.44
2 Pasir Pasang m3 0.026 115,000 2,990.00
JUMLAH HARGA BAHAN 9,003.44
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 72,903.44
E. OVERHEAD & PROFIT 10,0 % x D 7,290.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 80,193.78

DIVISI 4 / 4.4.2.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.6
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:6PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00

B. BAHAN

1 Semen Portland Kg 4.416 1,160 5,122.56


2 Pasir Pasang m3 0.027 115,000 3,105.00
JUMLAH HARGA BAHAN 8,227.56
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 72,127.56
E. OVERHEAD & PROFIT 10,0 % x D 7,212.76
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,340.32
DIVISI 4 / 4.4.2.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.7
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:7PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 3.936 1,160 4,565.76
2 Pasir Pasang m3 0.028 115,000 3,220.00
JUMLAH HARGA BAHAN 7,785.76
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 71,685.76
E. OVERHEAD & PROFIT 10,0 % x D 7,168.58
F. HARGA SATUAN PEKERJAAN ( D + E ) 78,854.34

DIVISI 4 / 4.4.2.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.8
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:8PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.300 120,000 36,000.00
2 Tukang Batu (L.03) OH 0.150 150,000 22,500.00
3 Kepala Tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 3.456 1,160 4,008.96
2 Pasir Pasang m3 0.029 115,000 3,335.00
JUMLAH HARGA BAHAN 7,343.96
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 71,243.96
E. OVERHEAD & PROFIT 10,0 % x D 7,124.40
F. HARGA SATUAN PEKERJAAN ( D + E ) 78,368.36

DIVISI 4 / 4.4.2.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.9
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:1/2KP:3PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.360 120,000 43,200.00
2 Tukang Batu (L.03) OH 0.120 150,000 18,000.00
3 Kepala Tukang (L.03) OH 0.012 175,000 2,100.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 66,630.00
B. BAHAN 0.00
1 Semen Portland Kg 5.760 1,160 6,681.60
2 Koral Bulat m3 0.003 420,000 1,260.00
3 Pasir Pasang m3 0.013 115000 1,495.00
JUMLAH HARGA BAHAN 9,436.60
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH( A + B + C ) 76,066.60
E. OVERHEAD & PROFIT 10,0 % x D 7,606.66
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,673.26
DIVISI 4 / 4.4.2.10
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.10
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:2KP:8PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.360 120,000 43,200.00
2 Tukang Batu (L.03) OH 0.120 150,000 18,000.00
3 Kepala Tukang (L.03) OH 0.012 175,000 2,100.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 66,630.00
B. BAHAN 0.00
1 Semen Portland Kg 3.000 1,160 3,480.00
2 Koral Bulat m3 0.005 420,000 2,100.00
3 Pasir Pasang m3 0.02 115000 2,300.00
JUMLAH HARGA BAHAN 7,880.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 74,510.00
E. OVERHEAD & PROFIT 10,0 % x D 7,451.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 81,961.00

DIVISI 4 /4.4.2.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.11
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SM:1KP:1PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.360 120,000 43,200.00
2 Tukang Batu (L.03) OH 0.120 150,000 18,000.00
3 Kepala Tukang (L.03) OH 0.012 175,000 2,100.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 66,630.00
B. BAHAN 0.00
1 Semen Merah m3 0.009 75000 675.00
2 Kapur Padam m3 0.009 1750000 15,750.00
3 Pasir Pasang m3 0.009 115000 1,035.00
JUMLAH HARGA BAHAN 17,460.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 84,090.00
E. OVERHEAD & PROFIT 10,0 % x D 8,409.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 92,499.00

DIVISI 4 / 4.4.2.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.12
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SM:1KP:2PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.360 120,000 43,200.00
2 Tukang Batu (L.03) OH 0.120 150,000 18,000.00
3 Kepala Tukang (L.03) OH 0.012 175,000 2,100.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 66,630.00
B. BAHAN 0.00
1 Semen Merah m3 0.007 75000 525.00
2 Kapur Padam m3 0.007 1750000 12,250.00
3 Pasir Pasang m3 0.015 115000 1,725.00
JUMLAH HARGA BAHAN 14,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 81,130.00
E. OVERHEAD & PROFIT 10,0 % x D 8,113.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 89,243.00
DIVISI 4 / 4.4.2.13
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.13
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:1PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.400 120,000 48,000.00
2 Tukang Batu (L.03) OH 0.200 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 85,570.00
B. BAHAN
1 Semen portland Kg 13.632 1,160 15,813.12
2 Pasir pasang m3 0.027 115,000 3,105.00
JUMLAH HARGA BAHAN 18,918.12
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 104,488.12
E. OVERHEAD & PROFIT 10,0 % x D 10,448.81
F. HARGA SATUAN PEKERJAAN ( D + E ) 114,936.93

DIVISI 4 /4.4.2.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.14
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:3PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.260 120,000 31,200.00
2 Tukang Batu (L.03) OH 0.200 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 67,105.00
B. BAHAN
1 Semen portland Kg 10.368 1,160 12,026.88
2 Pasir pasang m3 0.031 115,000 3,565.00
JUMLAH HARGA BAHAN 15,591.88
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 82,696.88
E. OVERHEAD & PROFIT 10,0 % x D 8,269.69
F. HARGA SATUAN PEKERJAAN ( D + E ) 90,966.57

DIVISI 4 /4.4.2.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.15
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:4PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.400 120,000 48,000.00

2 Tukang Batu (L.03) OH 0.200 150,000 30,000.00


3 Kepala Tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 85,570.00
B. BAHAN
1 Semen portland Kg 8.320 1,160 9,651.20
2 Pasir pasang m3 0.032 115,000 3,680.00
JUMLAH HARGA BAHAN 13,331.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 98,901.20
E. OVERHEAD & PROFIT 10,0 % x D 9,890.12
F. HARGA SATUAN PEKERJAAN ( D + E ) 108,791.32
DIVISI 4 /4.4.2.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.16
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:5PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.400 120,000 48,000.00
2 Tukang Batu (L.03) OH 0.200 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 85,570.00
B. BAHAN
1 Semen Portland Kg 6.912 1,160 8,017.92
2 Pasir Pasang m3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 12,042.92
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 97,612.92
E. OVERHEAD & PROFIT 10,0 % x D 9,761.29
F. HARGA SATUAN PEKERJAAN ( D + E ) 107,374.21

DIVISI 4/ 4.2.17
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.17
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SP:6PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.400 120,000 48,000.00
2 Tukang Batu (L.03) OH 0.200 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 85,570.00
B. BAHAN
1 Semen Portland Kg 5.888 1,160 6,830.08
2 Pasir Pasang m3 0.036 115,000 4,140.00
JUMLAH HARGA BAHAN 10,970.08
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 96,540.08
E. OVERHEAD & PROFIT 10,0 % x D 9,654.01
F. HARGA SATUAN PEKERJAAN ( D + E ) 106,194.09

DIVISI 4/ 4.4.2.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.18
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran 1SM:1KP:2PP tebal 20 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.440 120,000 52,800.00
2 Tukang Batu (L.03) OH 0.220 150,000 33,000.00
3 Kepala Tukang (L.03) OH 0.022 175,000 3,850.00
4 Mandor (L.04) OH 0.022 185,000 4,070.00
JUMLAH HARGA TENAGA 93,720.00
B. BAHAN 0.00
1 Semen Merah m3 0.009 75000 675.00
2 Kapur Padam m3 0.009 1750000 15,750.00
3 Pasir Pasang m3 0.018 115000 2,070.00
JUMLAH HARGA BAHAN 18,495.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 112,215.00
E. OVERHEAD & PROFIT 10,0 % x D 11,221.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 123,436.50
DIVISI 4 /4.4.2.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.19
JENIS PEKERJAAN : Pemasangan 1 m2 berapen 1SP:5PP tebal 15 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Batu (L.03) OH 0.075 150,000 11,250.00
3 Kepala Tukang (L.03) OH 0.008 175,000 1,400.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 32,130.00
B. BAHAN
1 Semen Portland Kg 5.184 1,160 6,013.44
2 Pasir Pasang m3 0.026 115,000 2,990.00
JUMLAH HARGA BAHAN 9,003.44
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 41,133.44
E. OVERHEAD & PROFIT 10,0 % x D 4,113.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 45,246.78

DIVISI 4 /4.4.2.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.20
JENIS PEKERJAAN : Pemasangan 1 m1 plesteran skoning 1SP:3PP lebar 10 cm
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.080 120,000 9,600.00
2 Tukang Batu (L.03) OH 0.400 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.040 175,000 7,000.00
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 77,340.00
B. BAHAN
1 Semen portland Kg 0.500 1,160 580.00
2 Pasir Pasang m3 0.013 115,000 1,495.00
JUMLAH HARGA BAHAN 2,075.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 79,415.00
E. OVERHEAD & PROFIT 10,0 % x D 7,941.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 87,356.50

DIVISI 4 / 4.4.2.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.21
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran granit 1SP: 2 granit tebal 1cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.450 120,000 54,000.00
2 Tukang Batu (L.03) OH 0.225 150,000 33,750.00
3 Kepala Tukang (L.03) OH 0.023 175,000 4,025.00
4 Mandor (L.04) OH 0.023 185,000 4,255.00
JUMLAH HARGA TENAGA 96,030.00
B. BAHAN
1 Semen Portland Kg 10.000 1,160 11,600.00
2 Batu Granit Kg 15.000 7,200 108,000.00
JUMLAH HARGA BAHAN 119,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 215,630.00
E. OVERHEAD & PROFIT 10,0 % x D 21,563.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 237,193.00
DIVISI 4 / 4.4.2.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.22
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran traso 1SP: 2 traso tebal 1cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.450 120,000 54,000.00
2 Tukang Batu L.03 OH 0.225 150,000 33,750.00
3 Kepala Tukang L.03 OH 0.023 175,000 4,025.00
4 Mandor L.04 OH 0.023 185,000 4,255.00
JUMLAH HARGA TENAGA 96,030.00
B. BAHAN
1 Semen Portland Kg 10.000 1,160 11,600.00
2 Batu traso Kg 15.000 7,000 105,000.00
JUMLAH HARGA BAHAN 116,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 212,630.00
E. OVERHEAD & PROFIT 10,0 % x D 21,263.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 233,893.00

DIVISI 4 / 4.4.2.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.23
JENIS PEKERJAAN : Pemasangan 1 m2 plesteran ciprat 1SP: 2PP
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.02 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 55,525.00
B. BAHAN
1 Semen Portland Kg 4.320 1,160 5,011.20
2 Pasir Pasang Kg 0.006 115,000 690.00
JUMLAH HARGA BAHAN 5,701.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 61,226.20
E. OVERHEAD & PROFIT 10,0 % x D 6,122.62
F. HARGA SATUAN PEKERJAAN ( D + E ) 67,348.82

DIVISI 4 / 4.4.2.24
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.24
JENIS PEKERJAAN : Pemasangan 1 m2 finishing siar pasangan bata merah
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.150 120,000 18,000.00
2 Tukang Batu L.03 OH 0.075 150,000 11,250.00
3 Kepala Tukang L.03 OH 0.008 175,000 1,400.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 32,130.00
B. BAHAN 0.00
1 Semen Portland Kg 3.108 1,160 3,605.28
JUMLAH HARGA BAHAN 3,605.28
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 35,735.28
E. OVERHEAD & PROFIT 10,0 % x D 3,573.53
F. HARGA SATUAN PEKERJAAN ( D + E ) 39,308.81
DIVISI 4 / 4.4.2.25

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.25
JENIS PEKERJAAN : Pemasangan 1 m2 finishing siar pasangan conblock ekspose
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.070 120,000 8,400.00
2 Tukang Batu L.03 OH 0.035 150,000 5,250.00
3 Kepala Tukang L.03 OH 0.004 175,000 700.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 15,090.00
B. BAHAN 0.00
1 Semen Portland Kg 1.600 1,160 1,856.00
JUMLAH HARGA BAHAN 1,856.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 16,946.00
E. OVERHEAD & PROFIT 10,0 % x D 1,694.60
F. HARGA SATUAN PEKERJAAN ( D + E ) 18,640.60

DIVISI 4 / 4.4.2.26

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.26
JENIS PEKERJAAN : Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP:2PP
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.300 120,000 36,000.00
2 Tukang Batu L.03 OH 0.150 150,000 22,500.00
3 Kepala Tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 63,900.00
B. BAHAN
1 Semen Portland Kg 6.340 1,160 7,354.40
2 Pasir Pasang m3 0.012 115,000 1,380.00
JUMLAH HARGA BAHAN 8,734.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 72,634.40
E. OVERHEAD & PROFIT 10,0 % x D 7,263.44
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,897.84

DIVISI 4 / 4.4.2.27

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.2.27
JENIS PEKERJAAN : Pemasangan 1 m2 acian
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.200 120,000 24,000.00
2 Tukang Batu L.03 OH 0.100 150,000 15,000.00
3 Kepala Tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 42,600.00
B. BAHAN 0.00
1 Semen portland Kg 3.250 1,160 3,770.00
JUMLAH HARGA BAHAN 3,770.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 46,370.00
E. OVERHEAD & PROFIT 10,0 % x D 4,637.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 51,007.00
DIVISI 4 / 4.4.3.1
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.1
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Abu-abu 40/40 Bh 6.63 6,400 42,432.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 58,975.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAHA + B + C ) 112,405.00
E. OVERHEAD & PROFIT 10,0 % x D 11,240.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 123,645.50

DIVISI 4 / 4.4.3.2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.2
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Abu-abu 30/30 Bh 11.87 4,800 56,976.00
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 73,751.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 127,181.00
E. OVERHEAD & PROFIT 10,0 % x D 12,718.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 139,899.10

DIVISI 4 / 4.4.3.3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.3
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.270 120,000 32,400.00
2 Tukang Batu L.02 OH 0.135 150,000 20,250.00
3 Kepala Tukang L.03 OH 0.014 175,000 2,450.00
4 Mandor L.04 OH 0.014 185,000 2,590.00
JUMLAH HARGA TENAGA 57,690.00
B. BAHAN
1 Ubin Abu-abu 20/20 Bh 26.50 8,200 217,300.00
2 Semen Portland Kg 10.40 1,160 12,064.00
3 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 234,539.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 292,229.00
E. OVERHEAD & PROFIT 10,0 % x D 29,222.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 321,451.90
DIVISI 4 / 4.4.3.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.4
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin warna ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Warna 40/40 Bh 6.63 5,900 39,117.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Semen Warna Kg 0.60 10,000 6,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 61,660.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 115,090.00
E. OVERHEAD & PROFIT 10,0 % x D 11,509.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 126,599.00

DIVISI 4 / 4.4.3.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.5
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin warna ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.260 120,000 31,200.00
2 Tukang Batu L.02 OH 0.13 150,000 19,500.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 55,380.00
B. BAHAN
1 Ubin Warna 30/30 Bh 11.87 4,800 56,976.00
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Semen Warna Kg 0.60 10,000 6,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 79,751.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 135,131.00
E. OVERHEAD & PROFIT 10,0 % x D 13,513.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 148,644.10

DIVISI 4 / 4.4.3.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.6
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin warna ukuran 20cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)

A. TENAGA

1 Pekerja L.01 OH 0.270 120,000 32,400.00


2 Tukang Batu L.02 OH 0.135 150,000 20,250.00
3 Kepala Tukang L.03 OH 0.014 175,000 2,450.00
4 Mandor L.04 OH 0.014 185,000 2,590.00
JUMLAH HARGA TENAGA 57,690.00
B. BAHAN
1 Ubin Warna 20/20 Bh 26.50 3,400 90,100.00
2 Semen Portland Kg 10.40 1,160 12,064.00
3 Semen Warna Kg 1.00 10,000 10,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 117,339.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 175,029.00
E. OVERHEAD & PROFIT 10,0 % x D 17,502.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 192,531.90
DIVISI 4 / 4.4.3.7
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.7
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teraso ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Teraso Bh 6.63 8,300 55,029.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Semen Warna Kg 1.30 10,000 13,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 84,572.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 138,002.00
E. OVERHEAD & PROFIT 10,0 % x D 13,800.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 151,802.20

DIVISI 4 / 4.4.3.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.8
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teraso ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.260 120,000 31,200.00
2 Tukang Batu L.02 OH 0.130 150,000 19,500.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 55,380.00
B. BAHAN
1 Ubin Teraso Bh 11.87 6,000 71,220.00
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Semen Warna Kg 1.50 10,000 15,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 102,995.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 158,375.00
E. OVERHEAD & PROFIT 10,0 % x D 15,837.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 174,212.50

DIVISI 4 / 4.4.3.9
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.9
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin granit ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Granit 40/40 Bh 6.63 59,500 394,485.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Semen Warna Kg 1.30 10,000 13,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 424,028.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 477,458.00
E. OVERHEAD & PROFIT 10,0 % x D 47,745.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 525,203.80
DIVISI 4 / 4.4.3.9.a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.9.a
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin granit ukuran 60cm x 60cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Granit 60/60 Bh 3.05 78,000 237,900.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Semen Warna Kg 1.62 10,000 16,200.00
4 Pasir Pasang M3 0.050 115,000 5,750.00
JUMLAH HARGA BAHAN 269,350.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 322,780.40
E. OVERHEAD & PROFIT 10,0 % x D 32,278.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 355,058.44

DIVISI 4 / 4.4.3.10
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.10
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin granit ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.260 120,000 31,200.00
2 Tukang Batu L.02 OH 0.13 150,000 19,500.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 55,380.00
B. BAHAN
1 Ubin Granit 30/30 Bh 11.87 24,500 290,815.00
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Semen Warna Kg 1.50 10,000 15,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 322,590.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 377,970.00
E. OVERHEAD & PROFIT 10,0 % x D 37,797.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 415,767.00

DIVISI 4 / 4.4.3.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.11
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.250 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Teralux 40/40 Bh 6.63 10,250 67,957.50
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Semen Warna Kg 1.30 10,000 13,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 97,500.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 150,930.50
E. OVERHEAD & PROFIT 10,0 % x D 15,093.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 166,023.55
DIVISI 4 / 4.4..3.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.12
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teralux ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.260 120,000 31,200.00
2 Tukang Batu L.02 OH 0.13 150,000 19,500.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 55,380.00
B. BAHAN
1 Ubin Teralux 30/30 Bh 11.87 12,250 145,407.50
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Semen Warna Kg 1.50 10,000 15,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 177,182.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 232,562.50
E. OVERHEAD & PROFIT 10,0 % x D 23,256.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 255,818.75

DIVISI 4 / 4.4.3.13
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.13
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teralux marmer ukuran 60cm x 60cm
SATUAN PEMBAYARAN :M2
HARGA JUMLAH
NO. KOMPONEN KODE SATUAN KOEFISIEN SATUAN HARGA (Rp.)
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.24 120,000 28,800.00
2 Tukang Batu L.02 OH 0.12 150,000 18,000.00
3 Kepala Tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.012 185,000 2,220.00
JUMLAH HARGA TENAGA 51,120.00
B. BAHAN
1 Ubin Teralux Marmer 60/60 Bh 3.10 125,000 387,500.00
2 Semen Portland Kg 9.60 1,160 11,136.00
3 Semen Warna Kg 1.50 10,000 15,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 412,475.00

C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 463,595.00
E. OVERHEAD & PROFIT 10,0 % x D 46,359.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 509,954.50

DIVISI 4 / 4.4.3.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.14
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.25 120,000 30,000.00
2 Tukang Batu L.02 OH 0.125 150,000 18,750.00
3 Kepala Tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 53,430.00
B. BAHAN
1 Ubin Teralux Marmer 40/40 Bh 6.63 59,000 391,170.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Semen Warna Kg 1.30 10,000 13,000.00
4 Pasir Pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 415,295.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 468,725.00
E. OVERHEAD & PROFIT 10,0 % x D 46,872.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 515,597.50
DIVISI 4 / 4.4.3.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.15
JENIS PEKERJAAN : Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.26 120,000 31,200.00
2 Tukang Batu L.02 OH 0.13 150,000 19,500.00
3 Kepala tukang L.03 OH 0.013 175,000 2,275.00
4 Mandor L.04 OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 55,380.00
B. BAHAN
1 Ubin teralux marmer 30/30 Bh 11.87 31,000 367,970.00
2 Semen Portland kg 10.00 1,160 11,600.00
3 Semen warna Kg 1.50 10,000 15,000.00
4 Pasir pasang M3 0.045 115,000 5,175.00
JUMLAH HARGA BAHAN 399,745.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 455,125.00
E. OVERHEAD & PROFIT 10,0 % x D 45,512.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 500,637.50

DIVISI 4 / 4.4.3.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.16
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 15cm x 20cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin PC Bh 5.30 1,160 6,148.00
2 Semen Portland kg 1.65 1,160 1,914.00
3 Pasir pasang M3 0.004 115,000 460.00
JUMLAH HARGA BAHAN 8,522.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 35,322.00
E. OVERHEAD & PROFIT 10,0 % x D 3,532.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 38,854.20

DIVISI 4 / 4.4.3.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.17
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin PC Bh 3.53 1,400 4,942.00
2 Semen Portland kg 1.24 1,160 1,438.40
3 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 6,725.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 33,525.40
E. OVERHEAD & PROFIT 10,0 % x D 3,352.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 36,877.94
DIVISI 4 / 4.4.3.18

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.18
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin PC Bh 2.65 1,600 4,240.00
2 Semen Portland kg 1.24 1,160 1,438.40
3 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 6,023.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 32,823.40
E. OVERHEAD & PROFIT 10,0 % x D 3,282.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 36,105.74

DIVISI 4 / 4.4.3.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.19
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin warna ukuran 10cm x 20cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin warna Bh 2.65 2,500 6,625.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.15 10,000 1,500.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 9,792.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 36,592.40
E. OVERHEAD & PROFIT 10,0 % x D 3,659.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 40,251.64

DIVISI 4 / 4.4.3.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.20
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin warna ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin warna Bh 3.53 9,000 31,770.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 34,437.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 61,237.40
E. OVERHEAD & PROFIT 10,0 % x D 6,123.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 67,361.14
DIVISI 4 / 4.4.3.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.21
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin warna ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin warna Bh 2.65 3,500 9,275.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 11,942.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 38,742.40
E. OVERHEAD & PROFIT 10,0 % x D 3,874.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,616.64

DIVISI 4 / 4.4.3.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.22
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teraso ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin teraso Bh 3.53 3,300 11,649.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 14,316.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 41,116.40
E. OVERHEAD & PROFIT 10,0 % x D 4,111.64
F. HARGA SATUAN PEKERJAAN ( D + E ) 45,228.04

DIVISI 4 / 4.4.3.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.23
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teraso ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin teraso Bh 2.65 3,300 8,745.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 11,412.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 38,212.40
E. OVERHEAD & PROFIT 10,0 % x D 3,821.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,033.64
DIVISI 4 / 4.4.3.24

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.24
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin granit ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin granit Bh 2.65 14,800 39,220.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 41,887.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 68,687.40
E. OVERHEAD & PROFIT 10,0 % x D 6,868.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 75,556.14

DIVISI 4 / 4.4.3.24.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.24.a
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin granit ukuran 10cm x 60cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin granit Bh 1.76 13,000 22,880.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.00 10,000 0.00
4 Pasir pasang M3 0.050 115,000 5,750.00
JUMLAH HARGA BAHAN 29,952.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 56,752.40
E. OVERHEAD & PROFIT 10,0 % x D 5,675.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 62,427.64

DIVISI 4 / 4.4.3.25

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.25
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin granit ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint ubin granit Bh 3.53 8,200 28,946.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 31,613.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 58,413.40
E. OVERHEAD & PROFIT 10,0 % x D 5,841.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 64,254.74
DIVISI 4 / 4.4.3.26

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.26
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teralux kerang ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu OH 0.09 150,000 13,500.00
3 Kepala tukang L.02 OH 0.009 175,000 1,575.00
4 Mandor (L04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint teralux kerang Bh 2.63 3,500 9,205.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 11,872.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 38,672.40
E. OVERHEAD & PROFIT 10,0 % x D 3,867.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,539.64

DIVISI 4 / 4.4.3.27

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.27
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teralux kerang ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint teralux kerang Bh 3.53 3,250 11,472.50
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 14,139.90
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 40,939.90
E. OVERHEAD & PROFIT 10,0 % x D 4,093.99
F. HARGA SATUAN PEKERJAAN ( D + E ) 45,033.89

DIVISI 4 / 4.4.3.28

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.28
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teralux marmer ukuran 10cm x 60cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint teralux marmer Bh 1.70 55,000 93,500.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 96,167.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 122,967.40
E. OVERHEAD & PROFIT 10,0 % x D 12,296.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 135,264.14
DIVISI 4 / 4.4.3.29

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.29
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teralux marmer ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja ;L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu ;L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang ;L.03 OH 0.009 175,000 1,575.00
4 Mandor ;L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint teralux marmer Bh 2.65 36,000 95,400.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 98,067.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 124,867.40
E. OVERHEAD & PROFIT 10,0 % x D 12,486.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 137,354.14

DIVISI 4 / 4.4.3.30

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.30
JENIS PEKERJAAN : Pemasangan 1 m’ plint ubin teralux marmer ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.009 175,000 1,575.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 26,800.00
B. BAHAN
1 Plint teralux marmer Bh 3.53 26,000 91,780.00
2 Semen Portland kg 1.14 1,160 1,322.40
3 Semen warna Kg 0.10 10,000 1,000.00
4 Pasir pasang M3 0.003 115,000 345.00
JUMLAH HARGA BAHAN 94,447.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 121,247.40
E. OVERHEAD & PROFIT 10,0 % x D 12,124.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 133,372.14

DIVISI 4 / 4.4.3.31

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.31
JENIS PEKERJAAN : Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.36 120,000 43,200.00
2 Tukang Batu L.02 OH 0.18 150,000 27,000.00
3 Kepala tukang L.03 OH 0.018 175,000 3,150.00
4 Mandor L.04 OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 76,680.00
B. BAHAN 0.00
1 Bahan Teraso cor M3 0.036 11,500,000 414,000.00
2 Semen warna Kg 0.10 10,000 1,000.00
JUMLAH HARGA BAHAN 415,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 491,680.00
E. OVERHEAD & PROFIT 10,0 % x D 49,168.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 540,848.00
DIVISI 4 / 4.4.3.32

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.32
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik artistik 10cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik Bh 53.00 8,200 434,600.00
2 Semen Portland Kg 8.19 1,160 10,237.50
3 Pasir pasang M3 0.045 115,000 4,725.00
4 Semen warna Kg 2.75 10,000 15,125.00
JUMLAH HARGA BAHAN 464,687.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 613,787.50
E. OVERHEAD & PROFIT 10,0 % x D 61,378.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 675,166.25

DIVISI 4 / 4.4.3.33

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.33
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik artistik 10cm x 10cm atau 5cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik Bh 106.00 4,250 450,500.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 3.20 10,000 32,000.00
JUMLAH HARGA BAHAN 497,175.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 10,0 % x D 646,275.40


E. OVERHEAD & PROFIT 64,627.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 710,902.94

DIVISI 4 / 4.4.3.34

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.34
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik ukuran 33 cm x 33 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik uk. 33 cm x 33 cm Dooz 1.05 98,000 102,900.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 0.50 10,000 5,000.00
JUMLAH HARGA BAHAN 122,575.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 271,675.40
E. OVERHEAD & PROFIT 10,0 % x D 27,167.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 298,842.94
DIVISI 4 / 4.4.3.34.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.34.a
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik ukuran 40cm x 40cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik uk. 40x40 cm Dooz 1.05 82,000 86,100.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 0.50 10,000 5,000.00
JUMLAH HARGA BAHAN 105,775.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 254,875.40
E. OVERHEAD & PROFIT 10,0 % x D 25,487.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 280,362.94

DIVISI 4 / 4.4.3.35

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.35
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik kk. 30 x 30 cm Doos 1.05 130,000 136,500.00
2 Semen Portland Kg 10.00 1,160 11,600.00
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 1.50 10,000 15,000.00
JUMLAH HARGA BAHAN 168,275.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 317,375.00
E. OVERHEAD & PROFIT 10,0 % x D 31,737.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 349,112.50

DIVISI 4 / 4.4.3.36

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.36
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik ukuran 20cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik uk. 20 x 20 cm Doos 1.05 78,000 81,900.00
2 Semen Portland Kg 10.40 1,160 12,064.00
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 1.62 10,000 16,200.00
JUMLAH HARGA BAHAN 115,339.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 264,439.00
E. OVERHEAD & PROFIT 10,0 % x D 26,443.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 290,882.90
DIVISI 4 / 4.4.3.37

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.37
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik ukuran 10cm x 33cm untuk variasi/border
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.05 120,000 126,000.00
2 Tukang Batu L.02 OH 0.525 150,000 78,750.00
3 Kepala tukang L.03 OH 0.053 175,000 9,275.00
4 Mandor L.04 OH 0.053 185,000 9,805.00
JUMLAH HARGA TENAGA 223,830.00
B. BAHAN
1 Keramik Uk. 10 x 33 cm Bh 33.00 3,800 125,400.00
2 Semen Portland Kg 9.80 1,160 11,368.00
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 4.37 10,000 43,700.00
JUMLAH HARGA BAHAN 185,643.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 409,473.00
E. OVERHEAD & PROFIT 10,0 % x D 40,947.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 450,420.30

DIVISI 4 / 4.4.3.38

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.38
JENIS PEKERJAAN : Pemasangan 1 m2 lantai keramik mozaik ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Ubin keramik mozaik uk. 30 cm x 30 cm Bh 11.87 11,800 140,066.00
2 Semen Portland Kg 14.15 1,160 16,414.00
3 Pasir pasang M3 0.039 115,000 4,485.00
4 Semen warna Kg 2.00 10,000 20,000.00
JUMLAH HARGA BAHAN 180,965.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 330,065.00
E. OVERHEAD & PROFIT 10,0 % x D 33,006.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 363,071.50

DIVISI 4 / 4.4.3.39

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.39
JENIS PEKERJAAN : Pemasangan 1 m’ plint keramik ukuran 10cm x 20cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik uk. 10 x 20 cm Bh 5.30 3,600 19,080.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.025 10,000 250.00
JUMLAH HARGA BAHAN 20,997.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 52,347.40
E. OVERHEAD & PROFIT 10,0 % x D 5,234.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,582.14
DIVISI 4 / 4.4.3.39.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.39.a
JENIS PEKERJAAN : Pemasangan 1 m’ plint keramik ukuran 10cm x 40cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik uk. 10 x 40 cm Bh 2.65 5,100 13,515.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.050 10,000 500.00
JUMLAH HARGA BAHAN 15,682.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 47,032.40
E. OVERHEAD & PROFIT 10,0 % x D 4,703.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 51,735.64

DIVISI 4 / 4.4.3.39.b

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.39.b
JENIS PEKERJAAN : Pemasangan 1 m’ plint keramik ukuran 10cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik uk. 10 x 30 cm Bh 3.53 3,900 13,767.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.050 10,000 500.00
JUMLAH HARGA BAHAN 15,934.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 47,284.40
E. OVERHEAD & PROFIT 10,0 % x D 4,728.44
F. HARGA SATUAN PEKERJAAN ( D + E ) 52,012.84

DIVISI 4 / 4.4.3.40

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.40
JENIS PEKERJAAN : Pemasangan 1 m’ plint keramik ukuran 10cm x 10cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik uk. 10 x 10 cm Bh 10.60 1,800 19,080.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.05 10,000 500.00
JUMLAH HARGA BAHAN 21,247.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 52,597.40
E. OVERHEAD & PROFIT 10,0 % x D 5,259.74
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,857.14
DIVISI 4 / 4.4.3.41

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.41
JENIS PEKERJAAN : Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.09 120,000 10,800.00
2 Tukang Batu L.02 OH 0.09 150,000 13,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 31,350.00
B. BAHAN
1 Plint keramik Uk. 5 x 20 cm Bh 5.30 4,750 25,175.00
2 Semen Portland Kg 0.57 1,160 661.20
3 Pasir pasang M3 0.0015 115,000 172.50
4 Semen warna Kg 0.013 10,000 130.00
JUMLAH HARGA BAHAN 26,138.70
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 57,488.70
E. OVERHEAD & PROFIT 10,0 % x D 5,748.87
F. HARGA SATUAN PEKERJAAN ( D + E ) 63,237.57

DIVISI 4 / 4.4.3.42

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.42
JENIS PEKERJAAN : Pemasangan 1 m’ plint internal cove artistik 5cm x 5cm x 20cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.75 120,000 90,000.00
2 Tukang Batu L.02 OH 0.75 150,000 112,500.00
3 Kepala tukang L.03 OH 0.075 175,000 13,125.00
4 Mandor L.04 OH 0.038 185,000 7,030.00
JUMLAH HARGA TENAGA 222,655.00
B. BAHAN
1 Internal cove artistik Bh 5.30 9,200 48,760.00
2 Semen Portland Kg 1.14 1,160 1,322.40
3 Pasir pasang M3 0.003 115,000 345.00
4 Semen warna Kg 0.10 10,000 1,000.00
JUMLAH HARGA BAHAN 51,427.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 274,082.40
E. OVERHEAD & PROFIT 10,0 % x D 27,408.24
F. HARGA SATUAN PEKERJAAN ( D + E ) 301,490.64

DIVISI 4 / 4.4.3.43

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.43
JENIS PEKERJAAN : Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Marmer Bh 1.06 1,650,000 1,749,000.00
2 Semen Portland Kg 8.19 1,160 9,500.40
3 Pasir pasang M3 0.045 115,000 5,175.00
4 Semen warna Kg 0.134 10,000 1,340.00
JUMLAH HARGA BAHAN 1,765,015.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,914,115.40
E. OVERHEAD & PROFIT 10,0 % x D 191,411.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,105,526.94
DIVISI 4 / 4.4.3.44

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.44
JENIS PEKERJAAN : Pemasangan 1 m2 lantai karpet
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.17 120,000 20,400.00
2 Tukang Kayu L.02 OH 0.17 150,000 25,500.00
3 Kepala tukang L.03 OH 0.017 175,000 2,975.00
4 Mandor L.04 OH 0.009 185,000 1,665.00
JUMLAH HARGA TENAGA 50,540.00
B. BAHAN 0.00
1 Karpet m2 1.05 84,000 88,200.00
2 Lem Kg 0.35 92,000 32,200.00
JUMLAH HARGA BAHAN 120,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 170,940.00
E. OVERHEAD & PROFIT 10,0 % x D 17,094.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 188,034.00

DIVISI 4 / 4.4.3.45

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.45
JENIS PEKERJAAN : Pemasangan 1 m2 underlayer (pelapis bawah karpet)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.12 120,000 14,400.00
2 Tukang Kayu L.02 OH 0.12 150,000 18,000.00
3 Kepala tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN 0.00
1 Underlayer m2 1.05 78,000 81,900.00
2 Lem Kg 0.35 92,000 32,200.00
JUMLAH HARGA BAHAN 114,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 149,710.00
E. OVERHEAD & PROFIT 10,0 % x D 14,971.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 164,681.00

DIVISI 4 / 4.4.3.46

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.46
JENIS PEKERJAAN : Pemasangan 1 m2 lantai parquet kayu
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN SATUAN HARGA (Rp.)
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Kayu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN 0.00
1 Parquet m2 1.05 335,000 351,750.00
2 Lem Kg 0.60 92,000 55,200.00
JUMLAH HARGA BAHAN 406,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 556,050.00
E. OVERHEAD & PROFIT 10,0 % x D 55,605.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 611,655.00
DIVISI 4 / 4.4.3.47

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.47
JENIS PEKERJAAN : Pemasangan 1 m2 lantai kayu gymfloor
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Kayu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN 0.00
1 Gymfloor m2 1.05 335,000 351,750.00
2 Lem Vinyl Kg 0.60 30,000 18,000.00
JUMLAH HARGA BAHAN 369,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 518,850.00
E. OVERHEAD & PROFIT 10,0 % x D 51,885.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 570,735.00

DIVISI 4 / 4.4.3.48

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.48
JENIS PEKERJAAN : Pemasangan 1 m2 dinding porslen 11cm x 11cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.00 120,000 120,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 213,000.00
B. BAHAN
1 Porselen ( 11 x 11 ) cm Bh 86.00 4,650 399,900.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 1.50 10,000 15,000.00
JUMLAH HARGA BAHAN 427,758.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 640,758.00
E. OVERHEAD & PROFIT 10,0 % x D 64,075.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 704,833.80

DIVISI 4 / 4.4.3.49

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.49
JENIS PEKERJAAN : Pemasangan 1 m2 dinding porslen 10cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Porslen Bh 53.00 9,300 492,900.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 2.75 10,000 27,500.00
JUMLAH HARGA BAHAN 533,258.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 724,958.00
E. OVERHEAD & PROFIT 10,0 % x D 72,495.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 797,453.80
DIVISI 4 / 4.4.3.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.50
JENIS PEKERJAAN : Pemasangan 1 m2 dinding porslen 20cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Porslen Bh 26.00 18,600 483,600.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 1.94 10,000 19,400.00
JUMLAH HARGA BAHAN 515,858.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 707,558.00
E. OVERHEAD & PROFIT 10,0 % x D 70,755.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 778,313.80

DIVISI 4 / 4.4.3.51

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.51
JENIS PEKERJAAN : Pemasangan 1 m2 dinding keramik artistik 10cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Keramik artistik Bh 53.00 8,200 434,600.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir Pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 2.75 10,000 27,500.00
JUMLAH HARGA BAHAN 474,958.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 666,658.00
E. OVERHEAD & PROFIT 10,0 % x D 66,665.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 733,323.80

DIVISI 4 / 4.4.3.52

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.52
JENIS PEKERJAAN : Pemasangan 1 m2 dinding keramik artistik 5cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Keramik artistik Bh 106.00 8,200 869,200.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir Pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 2.90 10,000 29,000.00
JUMLAH HARGA BAHAN 911,058.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,102,758.00
E. OVERHEAD & PROFIT 10,0 % x D 110,275.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,213,033.80
DIVISI 4 / 4.4.3.53

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.53
JENIS PEKERJAAN : Pemasangan 1 m2 dinding keramik 10cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Keramik Uk. 10 x 20 cm Bh 53.00 1,650 87,450.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir Pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 2.75 10,000 27,500.00
JUMLAH HARGA BAHAN 127,808.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 319,508.00
E. OVERHEAD & PROFIT 10,0 % x D 31,950.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 351,458.80

DIVISI 4 / 4.4.3.54

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.54
JENIS PEKERJAAN : Pemasangan 1 m2 dinding keramik 20cm x 20cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.90 120,000 108,000.00
2 Tukang Batu L.02 OH 0.45 150,000 67,500.00
3 Kepala tukang L.03 OH 0.045 175,000 7,875.00
4 Mandor L.04 OH 0.045 185,000 8,325.00
JUMLAH HARGA TENAGA 191,700.00
B. BAHAN
1 Keramik Uk. 20 x 20 cm Bh 26.50 3,350 88,775.00
2 Semen Portland Kg 9.30 1,160 10,788.00
3 Pasir Pasang M3 0.018 115,000 2,070.00
4 Semen warna Kg 1.94 10,000 19,400.00
JUMLAH HARGA BAHAN 121,033.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 312,733.00
E. OVERHEAD & PROFIT 10,0 % x D 31,273.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 344,006.30

DIVISI 4 / 4.4.3.55

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.55
JENIS PEKERJAAN : Pemasangan 1 m2 dinding marmer 100cm x 100cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.30 120,000 156,000.00
2 Tukang Batu L.02 OH 0.65 150,000 97,500.00
3 Kepala tukang L.03 OH 0.065 175,000 11,375.00
4 Mandor L.04 OH 0.065 185,000 12,025.00
JUMLAH HARGA TENAGA 276,900.00
B. BAHAN
1 Marmer Bh 1.06 1,650,000 1,749,000.00
2 Semen Portland Kg 12.44 1,160 14,430.40
3 Pasir Pasang M3 0.025 115,000 2,875.00
4 Semen warna Kg 0.65 10,000 6,500.00
5 Paku 15 cm Kg 3.03 20,000 60,600.00
JUMLAH HARGA BAHAN 1,833,405.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,110,305.40
E. OVERHEAD & PROFIT 10,0 % x D 211,030.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,321,335.94
DIVISI 4 / 4.4.3.56

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.56
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bata pelapis 3cm x 7cm x 24cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 1.00 120,000 120,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 213,000.00
B. BAHAN
1 Bata Pelapis / Bata ekspose Bh 63.00 3,200 201,600.00
2 Semen Portland Kg 12.44 1,160 14,430.40
3 Pasir Pasang M3 0.025 115,000 2,875.00
4 Semen warna Kg 2.75 10,000 27,500.00
JUMLAH HARGA BAHAN 246,405.40
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 459,405.40
E. OVERHEAD & PROFIT 10,0 % x D 45,940.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 505,345.94

DIVISI 4 / 4.4.3.57

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.57
JENIS PEKERJAAN : Pemasangan 1 m2 dinding batu paras
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Batu paras M² 1.10 175,000 192,500.00
2 Semen Portland Kg 11.75 1,160 13,630.00
3 Pasir Pasang M3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 210,155.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 359,255.00
E. OVERHEAD & PROFIT 10,0 % x D 35,925.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 395,180.50

DIVISI 4 / 4.4.3.58

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.58
JENIS PEKERJAAN : Pemasangan 1 m2 dinding batu tempel hitam
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.70 120,000 84,000.00
2 Tukang Batu L.02 OH 0.35 150,000 52,500.00
3 Kepala tukang L.03 OH 0.035 175,000 6,125.00
4 Mandor L.04 OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 149,100.00
B. BAHAN
1 Batu Tempel Hitam M² 1.10 125,000 137,500.00
2 Semen Portland Kg 11.75 1,160 13,630.00
3 Pasir Pasang M3 0.035 115,000 4,025.00
JUMLAH HARGA BAHAN 155,155.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 304,255.00
E. OVERHEAD & PROFIT 10,0 % x D 30,425.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 334,680.50
DIVISI 4 / 4.4.3.59

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.59
JENIS PEKERJAAN : Pemasangan 1 m2 lantai vynil ukuran 30cm x 30cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.15 120,000 18,000.00
2 Tukang Batu L.02 OH 0.15 150,000 22,500.00
3 Kepala tukang L.03 OH 0.015 175,000 2,625.00
4 Mandor L.04 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 44,605.00
B. BAHAN 0.00
1 Vinyl Bh 11.87 28,000 332,360.00
2 Lem Kg 0.35 30,000 10,500.00
JUMLAH HARGA BAHAN 342,860.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 387,465.00
E. OVERHEAD & PROFIT 10,0 % x D 38,746.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 426,211.50

DIVISI 4 / 4.4.3.60

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.60
JENIS PEKERJAAN : Pemasangan 1 m2 wallpaper lebar 50 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.35 120,000 42,000.00
2 Tukang Batu L.02 OH 0.175 150,000 26,250.00
3 Kepala tukang L.03 OH 0.017 175,000 2,975.00
4 Mandor L.04 OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 71,595.00
B. BAHAN 0.00
1 Wallpaper m 2.20 48,000 105,600.00
2 Lem (perekat untuk wallpaper ) Kg 0.25 180,000 45,000.00
JUMLAH HARGA BAHAN 150,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 222,195.00
E. OVERHEAD & PROFIT 10,0 % x D 22,219.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 244,414.50

DIVISI 4 / 4.4.3.61

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.61
JENIS PEKERJAAN : Pemasangan 1 m2 floor harderner
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.12 120,000 14,400.00
2 Tukang Batu L.02 OH 0.12 150,000 18,000.00
3 Kepala tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN
1 Floor Hardener Kg 5.00 7,250 36,250.00
JUMLAH HARGA BAHAN 36,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 71,860.00
E. OVERHEAD & PROFIT 10,0 % x D 7,186.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,046.00
DIVISI 4 / 4.4.3.62

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.62
JENIS PEKERJAAN : Pemasangan 1 m’ plint vynil 15cm x 30cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.08 120,000 9,600.00
2 Tukang Batu L.02 OH 0.08 150,000 12,000.00
3 Kepala tukang L.03 OH 0.008 175,000 1,400.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 23,740.00
B. BAHAN 0.00
1 Vynil Bh 1.76 14,000 24,640.00
2 Lem Kg 0.08 30,000 2,400.00
JUMLAH HARGA BAHAN 27,040.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 50,780.00
E. OVERHEAD & PROFIT 10,0 % x D 5,078.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 55,858.00

DIVISI 4 / 4.4.3.63

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.63
JENIS PEKERJAAN : Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.12 120,000 14,400.00
2 Tukang Batu L.02 OH 0.12 150,000 18,000.00
3 Kepala tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN 0.00
1 Papan kayu kelas II M3 0.003 4,300,000 12,900.00
2 Paku/skrup 5cm Kg 0.05 55,000 2,750.00
JUMLAH HARGA BAHAN 15,650.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 51,260.00
E. OVERHEAD & PROFIT 10,0 % x D 5,126.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 56,386.00

DIVISI 4 / 4.4.3.64

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.64
JENIS PEKERJAAN : Pemasangan 1 m2 paving block natural tebal 6 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.25 120,000 30,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 113,990.50
B. BAHAN 0.00
1 Paving Block 6 cm M² 1.01 82,000 82,820.00
2 Pasir beton M³ 0.05 135,000 6,750.00
JUMLAH HARGA BAHAN 89,570.00
C. PERALATAN
1 Peralatan 10 % 0.10 89,570.00 8,957.00
JUMLAH HARGA PERALATAN 8,957.00

D. JUMLAH ( A + B + C ) 212,517.50
E. OVERHEAD & PROFIT 10,0 % x D 21,251.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 233,769.25
DIVISI 4 / 4.4.3.65

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.65
JENIS PEKERJAAN : Pemasangan 1 m2 paving block natural tebal 8 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.50 120,000 60,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 143,990.50
B. BAHAN 0.00
1 Paving Block 8 cm M² 1.01 115,000 116,150.00
2 Pasir beton M³ 0.07 135,000 9,450.00
JUMLAH HARGA BAHAN 125,600.00
C. PERALATAN
1 Peralatan 10 % 0.10 115,500.00 11,550.00
JUMLAH HARGA PERALATAN 11,550.00

D. JUMLAH ( A + B + C ) 281,140.50
E. OVERHEAD & PROFIT 10,0 % x D 28,114.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 309,254.55

DIVISI 4 / 4.4.3.66

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.66
JENIS PEKERJAAN : Pemasangan 1m2 paving block berwarna tebal 6 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.25 120,000 30,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 113,990.50
B. BAHAN 0.00
1 Paving Block 6 cm berwarna M² 1.01 90,000 90,900.00
2 Pasir beton M³ 0.05 135,000 6,750.00
JUMLAH HARGA BAHAN 97,650.00
C. PERALATAN
1 Peralatan 10 % 0.10 97,650.00 9,765.00
JUMLAH HARGA PERALATAN 9,765.00

D. JUMLAH ( A + B + C ) 221,405.50
E. OVERHEAD & PROFIT 10,0 % x D 22,140.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 243,546.05

DIVISI 4 / 4.4.3.67

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.4.3.67
JENIS PEKERJAAN : Pemasangan 1m2 paving block berwarna tebal 8 cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.50 120,000 60,000.00
2 Tukang Batu L.02 OH 0.50 150,000 75,000.00
3 Kepala tukang L.03 OH 0.05 175,000 8,750.00
4 Mandor L.04 OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 143,990.50
B. BAHAN 0.00
1 Paving Block 8 cm berwarna M² 1.01 115,000 116,150.00
2 Pasir beton M³ 0.07 135,000 9,450.00
JUMLAH HARGA BAHAN 125,600.00
C. PERALATAN
1 Peralatan 10 % 0.10 125,600.00 12,560.00
JUMLAH HARGA PERALATAN 12,560.00

D. JUMLAH ( A + B + C ) 282,150.50
E. OVERHEAD & PROFIT 10,0 % x D 28,215.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 310,365.55
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.1
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.030 120,000 3,600.00
2 Tukang Kayu L.02 OH 0.070 150,000 10,500.00
3 Kepala tukang L.03 OH 0.007 175,000 1,225.00
4 Mandor L.04 OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 16,065.00
B. BAHAN
1 Asbes semen M² 1.100 22,000 24,200.00
2 Paku tripleks kg 0.010 22,000 220.00
JUMLAH HARGA BAHAN 24,420.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 40,485.00
E. OVERHEAD & PROFIT 10,0 % x D 4,048.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 44,533.50

DIVISI 4 / 4.5.1.2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.2
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.120 120,000 14,400.00
2 Tukang Kayu L.02 OH 0.120 150,000 18,000.00
3 Kepala tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN
1 Akustik Uk. 30 x 30 cm Lembar 12.000 10,000 120,000.00
2 Paku tripleks kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 121,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 156,710.00
E. OVERHEAD & PROFIT 10,0 % x D 15,671.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 172,381.00

DIVISI 4 / 4.5.1.3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.3
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L01) OH 0.120 120,000 14,400.00
2 Tukang Kayu (L02) OH 0.120 150,000 18,000.00
3 Kepala tukang (L03) OH 0.012 175,000 2,100.00
4 Mandor (L04) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN
1 Akustik Uk. 30 x 60 cm Lembar 5.800 14,000 81,200.00
2 Paku tripleks kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 82,300.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 117,910.00
E. OVERHEAD & PROFIT 10,0 % x D 11,791.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 129,701.00
DIVISI 4 / 4.5.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.4
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Kayu L.02 OH 0.100 150,000 15,000.00
3 Kepala tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00
B. BAHAN
1 Akustik Uk. 60 x 120 cm Lembar 1.500 62,000 93,000.00
2 Paku tripleks kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 94,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 123,775.00
E. OVERHEAD & PROFIT 10,0 % x D 12,377.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 136,152.50

DIVISI 4 / 4.5.1.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.5
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Kayu L.02 OH 0.100 150,000 15,000.00
3 Kepala tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00
B. BAHAN
1 Tripleks Lembar 0.375 70,000 26,250.00
2 Paku tripleks kg 0.030 22,000 660.00
JUMLAH HARGA BAHAN 26,910.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 56,585.00
E. OVERHEAD & PROFIT 10,0 % x D 5,658.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 62,243.50

DIVISI 4 / 4.5.1.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.6
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.800 120,000 96,000.00
2 Tukang Kayu L.02 OH 0.800 150,000 120,000.00
3 Kepala tukang L.03 OH 0.080 175,000 14,000.00
4 Mandor L.04 OH 0.040 185,000 7,400.00
JUMLAH HARGA TENAGA 237,400.00
B. BAHAN
1 Papan Kayu kelas II m3 0.015 4,300,000 64,500.00
2 Paku kg 0.010 22,000 220.00
JUMLAH HARGA BAHAN 64,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 302,120.00
E. OVERHEAD & PROFIT 10,0 % x D 30,212.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 332,332.00
DIVISI 4 / 4.5.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.7
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Kayu L.02 OH 0.050 150,000 7,500.00
3 Kepala tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 21,300.00
B. BAHAN
1 Gypsum board Lembar 0.364 75,000 27,300.00
2 Paku skrup kg 0.110 55,000 6,050.00
JUMLAH HARGA BAHAN 33,350.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 54,650.00
E. OVERHEAD & PROFIT 10,0 % x D 5,465.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 60,115.00

DIVISI 4 / 4.5.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.7.a
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit kalsi board ukuran (120x240x9) mm, tebal 3,5 mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Kayu L.02 OH 0.050 150,000 7,500.00
3 Kepala tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 21,300.00
B. BAHAN
1 Kalsi board Lembar 0.364 55,000 20,020.00
2 Paku skrup kg 0.110 55,000 6,050.00
JUMLAH HARGA BAHAN 26,070.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 47,370.00
E. OVERHEAD & PROFIT 10,0 % x D 4,737.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 52,107.00

DIVISI 4 / 4.5.1.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.8
JENIS PEKERJAAN : Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L01) OH 0.500 120,000 60,000.00
2 Tukang Besi (L02) OH 0.500 150,000 75,000.00
3 Kepala tukang (L03) OH 0.050 175,000 9,000.00
4 Mandor (L04) OH 0.025 185,000 4,625.00
JUMLAH HARGA TENAGA 148,625.00
B. BAHAN
1 Profil Alluminium "T" m 3.600 135,000 486,000.00
2 Kawat dia 4 mm kg 0.150 16,000 2,400.00
3 Ramset Buah 1.050 4,500 4,725.00
4 Akustik 60 x 120 Lembar 1.500 62,000 93,000.00
JUMLAH HARGA BAHAN 586,125.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 734,750.00
E. OVERHEAD & PROFIT 10,0 % x D 73,475.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 808,225.00
DIVISI 4 / 4.5.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.9
JENIS PEKERJAAN : Pemasangan 1 m’ list langit-langit kayu profil
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.050 120,000 6,000.00
2 Tukang Kayu L.02 OH 0.050 150,000 7,500.00
3 Kepala tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 14,930.00
B. BAHAN
1 List kayu profil m 1.050 22,000 23,100.00
2 Paku kg 0.010 22,000 220.00
JUMLAH HARGA BAHAN 23,320.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 38,250.00
E. OVERHEAD & PROFIT 10,0 % x D 3,825.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 42,075.00

DIVISI 4 / 4.5.1.9.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.1.9.a
JENIS PEKERJAAN : Pemasangan 1 m’ list langit-langit gypsum profil
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.050 120,000 6,000.00
2 Tukang Kayu L.02 OH 0.050 150,000 7,500.00
3 Kepala tukang L.03 OH 0.005 175,000 875.00
4 Mandor L.04 OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 14,930.00
B. BAHAN
1 List gypsum m 1.050 18,000 18,900.00
2 Paku skrup kg 0.010 55,000 550.00
3 Compound Gypsum kg 0.010 15,500 155.00
JUMLAH HARGA BAHAN 19,605.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 34,535.00
E. OVERHEAD & PROFIT 10,0 % x D 3,453.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 37,988.50
DIVISI 4 / 4.5.2.1
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.1
JENIS PEKERJAAN : Pemasangan 1 m2 atap genteng palentong kecil
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.15 120,000 18,000.00
2 Tukang Kayu L.03 OH 0.075 150,000 11,250.00
3 Kepala tukang L.11 OH 0.0075 175,000 1,312.50
4 Mandor L.011 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 32,042.50
B. BAHAN
1 Genteng palentong Bh 25.00 3,200 80,000.00
JUMLAH HARGA BAHAN 80,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 112,042.50
E. OVERHEAD & PROFIT 10,0 % x D 11,204.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 123,246.75

DIVISI 4 / 4.5.2.2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.2
JENIS PEKERJAAN : Pemasangan 1 m2 atap genteng kodok glazuur
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.1 OH 0.15 120,000 18,000.00
2 Tukang Kayu L.3 OH 0.075 150,000 11,250.00
3 Kepala tukang L.11 OH 0.008 175,000 1,400.00
4 Mandor L.15 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 35,920.00
B. BAHAN
1 Genteng kodok glazuur Bh 25.00 5,400 135,000.00
JUMLAH HARGA BAHAN 135,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 170,920.00
E. OVERHEAD & PROFIT 10,0 % x D 17,092.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 188,012.00

DIVISI 4 / 4.5.2.3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.3
JENIS PEKERJAAN : Pemasangan 1 m2 atap genteng palentong besar/super
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.15 120,000 18,000.00
2 Tukang Kayu L.03 OH 0.075 150,000 11,250.00
3 Kepala tukang L.11 OH 0.008 175,000 1,400.00
4 Mandor L.15 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 35,920.00
B. BAHAN
1 Genteng palentong super Bh 12.00 4,800 57,600.00
JUMLAH HARGA BAHAN 57,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 93,520.00
E. OVERHEAD & PROFIT 10,0 % x D 9,352.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 102,872.00
DIVISI 4 / 4.5.2.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.4
JENIS PEKERJAAN : Pemasangan 1 m’ bubung genteng palentong
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L01) OH 0.40 120,000 48,000.00
2 Tukang Kayu (L03) OH 0.20 150,000 30,000.00
3 Kepala tukang (L11) OH 0.02 175,000 3,500.00
4 Mandor (L15) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 81,870.00
B. BAHAN
1 Bubungan genteng palentong Bh 5.00 12,500 62,500.00
2 Semen Portland Kg 8.00 1,160 9,280.00
3 Pasir pasang M3 0.032 115,000 3,680.00
JUMLAH HARGA BAHAN 75,460.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 157,330.00
E. OVERHEAD & PROFIT 10,0 % x D 15,733.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 173,063.00
DIVISI 4 / 4.5.2.5

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.5
JENIS PEKERJAAN : Pemasangan 1 m’ bubung genteng kodok glazuur
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.40 120,000 48,000.00
2 Tukang Kayu L.03 OH 0.20 150,000 30,000.00
3 Kepala tukang L.11 OH 0.02 175,000 3,500.00
4 Mandor L.15 OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 81,870.00
B. BAHAN
1 bubungan genteng kodok glazuur Bh 5.00 8,000 40,000.00
2 Semen Portland Kg 8.00 1,160 9,280.00
3 Pasir pasang M3 0.032 115,000 3,680.00
JUMLAH HARGA BAHAN 52,960.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 134,830.00
E. OVERHEAD & PROFIT 10,0 % x D 13,483.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 148,313.00

DIVISI 4 / 4.5.2.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.6
JENIS PEKERJAAN : Pemasangan 1 m’ bubung genteng palentong besar
SATUAN PEMBAYARAN : M'
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.40 120,000 48,000.00
2 Tukang Kayu L.03 OH 0.20 150,000 30,000.00
3 Kepala tukang L.11 OH 0.02 175,000 3,500.00
4 Mandor L.15 OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 81,870.00
B. BAHAN
1 Genteng bubung palentong besar Bh 4.00 13,500 54,000.00
2 Semen Portland Kg 8.00 1,160 9,280.00
3 Pasir pasang M3 0.032 115,000 3,680.00
JUMLAH HARGA BAHAN 66,960.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 148,830.00
E. OVERHEAD & PROFIT 10,0 % x D 14,883.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 163,713.00
DIVISI 4 / 4.5.2.7
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.7
JENIS PEKERJAAN : Pemasangan 1 m2 roof light fibreglass 90x180
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.067 150,000 10,050.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.15 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,370.00
B. BAHAN
1 Rooflight 90x180 Lbr 0.60 130,000 78,000.00
2 Paku biasa 1/2" - 1 " Kg 0.05 22,000 1,100.00
JUMLAH HARGA BAHAN 79,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 108,470.00
E. OVERHEAD & PROFIT 10,0 % x D 10,847.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 119,317.00

DIVISI 4 / 4.5.2.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.8
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 0,92mx2,5m x 5mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.075 150,000 11,250.00
3 Kepala tukang L.11 OH 0.008 175,000 1,400.00
4 Mandor L.15 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 30,930.00
B. BAHAN
Asbes gelombang 92x250 Paku pancing 6x23
1 Lbr 0.50 112,000 56,000.00
2 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 58,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 89,330.00
E. OVERHEAD & PROFIT 10,0 % x D 8,933.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 98,263.00

DIVISI 4 / 4.5.2.9
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.9
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 0,92mx2,25m x 5mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.075 150,000 11,250.00
3 Kepala tukang L.011 OH 0.008 175,000 1,400.00
4 Mandor L.15 OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 30,930.00
B. BAHAN
1 Asbes gel 92x225 Lbr 0.60 110,000 66,000.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 68,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 99,330.00
E. OVERHEAD & PROFIT 10,0 % x D 9,933.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 109,263.00
DIVISI 4 / 4.5.2.10
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.10
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 0,92mx2,00m x 5mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.070 150,000 10,500.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.15 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 92x200 Lbr 0.60 101,000 60,600.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 63,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 92,820.00
E. OVERHEAD & PROFIT 10,0 % x D 9,282.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 102,102.00

DIVISI 4 / 4.5.2.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.11
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 0,92mx1.80m x 5mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.070 150,000 10,500.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.15 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 92x180 Lbr 0.75 98,000 73,500.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 75,900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 105,720.00


E. OVERHEAD & PROFIT 10,0 % x D 10,572.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 116,292.00

DIVISI 4 / 4.5.2.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.12
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.05mx3.00m x 4mm
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.070 150,000 10,500.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.15 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 105x300 Lbr 0.35 92,000 32,200.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 34,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. JUMLAH( A + B + C ) 64,420.00
E. OVERHEAD & PROFIT 10,0 % x D 6,442.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 70,862.00
DIVISI 4 / 4.5.2.13
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.13
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.05mx2.70m x 4mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.01 OH 0.070 150,000 10,500.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.05 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 105x270 Lbr 0.42 85,000 35,700.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 38,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 67,920.00


E. OVERHEAD & PROFIT 10,0 % x D 6,792.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 74,712.00

DIVISI 4 / 4.5.2.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.14
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.05mx2.40m x 4mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja L.01 OH 0.14 120,000 16,800.00
2 Tukang Kayu L.03 OH 0.070 150,000 10,500.00
3 Kepala tukang L.11 OH 0.007 175,000 1,225.00
4 Mandor L.15 OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 105x240 Lbr 0.44 78,000 34,320.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 36,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 66,540.00
E. OVERHEAD & PROFIT 10,0 % x D 6,654.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 73,194.00

DIVISI 4 / 4.5.2.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.15
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.05mx2.10m x 4mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 105x210 Lbr 0.51 66,000 33,660.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 36,060.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 65,880.00
E. OVERHEAD & PROFIT 10,0 % x D 6,588.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 72,468.00
DIVISI 4 / 4. 5.2.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.16
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.05mx1.50m x 4mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 105x150 Lbr 0.80 52,000 41,600.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 44,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 73,820.00
E. OVERHEAD & PROFIT 10,0 % x D 7,382.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 81,202.00

DIVISI 4 /4.5.2.17
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.17
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.08mx3.00m x 6mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 108x300 Lbr 0.37 110,000 40,700.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 43,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 72,920.00
E. OVERHEAD & PROFIT 10,0 % x D 7,292.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 80,212.00

DIVISI 4 / 4.5.2.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.18
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.08mx2.70m x 6mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 108x270 Lbr 0.38 106,000 40,280.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 42,680.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 72,500.00
E. OVERHEAD & PROFIT 10,0 % x D 7,250.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,750.00
DIVISI 4 / 4.5.2.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.19
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.08mx2.40m x 6mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 108x240 Lbr 0.46 98,000 45,080.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 47,480.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 77,300.00
E. OVERHEAD & PROFIT 10,0 % x D 7,730.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 85,030.00

DIVISI 4 / 4.5.2.20
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.20
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.08mx2.10m x 6mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 108x210 Lbr 0.49 90,000 44,100.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 46,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 76,320.00
E. OVERHEAD & PROFIT 10,0 % x D 7,632.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,952.00

DIVISI 4 / 4.5.2.21
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.21
JENIS PEKERJAAN : Pemasangan 1 m2 atap asbes gelombang 1.08mx1.80m x 6mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Kayu (L.03) OH 0.070 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Asbes gel 108x180 Lbr 0.57 90,000 51,300.00
2 Paku pancing 6x23 Kg 0.12 20,000 2,400.00
JUMLAH HARGA BAHAN 53,700.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 83,520.00
E. OVERHEAD & PROFIT 10,0 % x D 8,352.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 91,872.00
DIVISI 4 / 4.5.2.22
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.22
JENIS PEKERJAAN : Pemasangan 1 m’ bubung stel gelombang 0,92m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Bubung stel gelombang 0,92 m Lbr 2.4 43,000 103,200.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 107,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 139,445.00
E. OVERHEAD & PROFIT 10,0 % x D 13,944.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 153,389.50

DIVISI 4 / 4.5.2.23
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.23
JENIS PEKERJAAN : Pemasangan 1 m’ bubung stel gelombang 1,05m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Bubung stel gelombang 1,05 m Lbr 2.1 36,000 75,600.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 80,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 111,845.00
E. OVERHEAD & PROFIT 10,0 % x D 11,184.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 123,029.50

DIVISI 4 / 4.5.2.24
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.24
JENIS PEKERJAAN : Pemasangan 1 m’ bubung stel gelombang 1,08m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Bubung stel gelombang 1,08 m Lbr 2.05 43,000 88,150.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 92,550.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 124,395.00
E. OVERHEAD & PROFIT 10,0 % x D 12,439.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 136,834.50
DIVISI 4 / 4.5.2.25

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.25
JENIS PEKERJAAN : Pemasangan 1 m’ nok paten 0,92 m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Nok Paten 0,92 m Lbr 1.20 13,500 16,200.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 20,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 52,445.00
E. OVERHEAD & PROFIT 10,0 % x D 5,244.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,689.50

DIVISI 4 / 4.5.2.26
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.26
JENIS PEKERJAAN : Pemasangan 1 m’ nok paten 1,05 m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Nok Paten 1,05 m Lbr 1.20 17,500 21,000.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 25,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 57,245.00
E. OVERHEAD & PROFIT 10,0 % x D 5,724.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 62,969.50

DVISI 4 / 4.5.2.27
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.27
JENIS PEKERJAAN : Pemasangan 1 m’ nok paten 1,08 m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Nok Paten 1,08 m Lbr 1.20 21,000 25,200.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 29,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 61,445.00
E. OVERHEAD & PROFIT 10,0 % x D 6,144.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 67,589.50
DIVISI 4 / 4.5.2.28
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA : 4.5.2.28
ITEM PEMBAYARAN NO. : Pemasangan 1 m’ nok stel rata 0,92m
JENIS PEKERJAAN : M'
SATUAN PEMBAYARAN
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L01) OH 0.10 120,000 12,000.00
2 Tukang Kayu (L03) OH 0.15 150,000 22,500.00
3 Kepala tukang (L11) OH 0.013 175,000 2,275.00
4 Mandor (L15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 37,515.00
B. BAHAN
1 Nok stel rata 0,92 m Lbr 1.10 26,000 28,600.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 33,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 70,515.00


E. OVERHEAD & PROFIT 10,0 % x D 7,051.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 77,566.50

DIVISI 4 / 4.5.2.29
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.29
JENIS PEKERJAAN : Pemasangan 1 m’ nok stel rata 1,05m
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.084 120,000 10,080.00
2 Tukang Kayu (L.03) OH 0.125 150,000 18,750.00
3 Kepala tukang (L.11) OH 0.013 175,000 2,275.00
4 Mandor (L.15) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 31,845.00
B. BAHAN
1 Nok stel rata 1,05 m Lbr 1.10 40,000 44,000.00
2 Paku skrup 3,5” kg 0.08 55,000 4,400.00
JUMLAH HARGA BAHAN 48,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 80,245.00
E. OVERHEAD & PROFIT 10,0 % x D 8,024.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 88,269.50

DIVISI 4 / 4.5.2.30
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.30
JENIS PEKERJAAN : Pemasangan 1 m2 genteng beton
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang Kayu (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.010 175,000 1,750.00
4 Mandor (L.15) OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 42,600.00
B. BAHAN
1 Genteng beton Bh 11.00 7,250 79,750.00
2 Paku biasa 2”-5” Kg 0.03 22,000 660.00
JUMLAH HARGA BAHAN 80,410.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 123,010.00
E. OVERHEAD & PROFIT 10,0 % x D 12,301.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 135,311.00
DIVISI 4 / 4.5.2.31
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.31
JENIS PEKERJAAN : Pemasangan 1 m2 genteng aspal
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang Kayu (L.03) OH 0.300 150,000 45,000.00
3 Kepala tukang (L.11) OH 0.003 175,000 525.00
4 Mandor (L.15) OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 71,375.00
B. BAHAN
1 Genteng aspal Bh 6.90 26,000 179,400.00
2 Plywood 9 mm Lbr 0.35 145,000 50,750.00
3 Paku biasa 1/2”-1” Kg 0.03 22,000 660.00
4 Plastic aerator Bh 0.50 25,000 12,500.00
JUMLAH HARGA BAHAN 243,310.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 314,685.00
E. OVERHEAD & PROFIT 10,0 % x D 31,468.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 346,153.50

DIVISI 4 / 4.5.2.32
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.32
JENIS PEKERJAAN : Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.010 175,000 1,750.00
4 Mandor (L.15) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 40,935.00
B. BAHAN
1 Genteng metal uk. 80 x 100 Bh 1.30 99,000 128,700.00
2 Paku biasa 1/2”-1” Kg 0.20 22,000 4,400.00
JUMLAH HARGA BAHAN 133,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 174,035.00
E. OVERHEAD & PROFIT 10,0 % x D 17,403.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 191,438.50

DIVISI 4 / 4.5.2.32.a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.32.a
JENIS PEKERJAAN : Pemasangan 1 m2 genteng metal berpasir ukuran 80 x 100 atap pelana
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.010 175,000 1,750.00
4 Mandor (L.15) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 40,935.00
B. BAHAN
1 Genteng metal berpasir uk. 80 x 100 Bh 1.30 110,000 143,000.00
2 Paku biasa 1/2”-1” Kg 0.20 22,000 4,400.00
JUMLAH HARGA BAHAN 147,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 188,335.00
E. OVERHEAD & PROFIT 10,0 % x D 18,833.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 207,168.50
DIVISI 4 / 4.5.2.33
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.33
JENIS PEKERJAAN : Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.010 175,000 1,750.00
4 Mandor (L.15) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 40,935.00
B. BAHAN
1 Genteng Metal uk. 80 x 100 Bh 2.00 99,000 198,000.00
2 Paku biasa 1/2”-1” Kg 0.20 22,000 4,400.00
JUMLAH HARGA BAHAN 202,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 243,335.00
E. OVERHEAD & PROFIT 10,0 % x D 24,333.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 267,668.50

DIVISI 4 / 4.5.2.33
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.33
JENIS PEKERJAAN : Pemasangan 1 m2 genteng metal berpasir ukuran 80 x 100 atap jurai
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.010 175,000 1,750.00
4 Mandor (L.15) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 40,935.00
B. BAHAN
1 Genteng Metal Berpasir uk. 80 x 100 Bh 2.00 110,000 220,000.00
2 Paku biasa 1/2”-1” Kg 0.20 22,000 4,400.00
JUMLAH HARGA BAHAN 224,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 265,335.00
E. OVERHEAD & PROFIT 10,0 % x D 26,533.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 291,868.50

DIVISI 4 / 4.5.2.34
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.34
JENIS PEKERJAAN : Pemasangan 1 m2 atap sirap kayu
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.166 120,000 19,920.00
2 Tukang Kayu (L.03) OH 0.250 150,000 37,500.00
3 Kepala tukang (L.11) OH 0.025 175,000 4,375.00
4 Mandor (L.15) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 63,275.00
B. BAHAN
1 Sirap kayu Bh 30.00 5,700 171,000.00
2 Paku biasa 1/2”-1” Kg 0.20 22,000 4,400.00
JUMLAH HARGA BAHAN 175,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 238,675.00
E. OVERHEAD & PROFIT 10,0 % x D 23,867.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 262,542.50
DIVISI 4 / 4.5.2.35
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.35
JENIS PEKERJAAN : Pemasangan 1 m’ nok genteng beton
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.400 120,000 48,000.00
2 Tukang Kayu (L.03) OH 0.200 150,000 30,000.00
3 Kepala tukang (L.11) OH 0.020 175,000 3,500.00
4 Mandor (L.15) OH 0.020 185,000 3,700.00
JUMLAH HARGA TENAGA 85,200.00
B. BAHAN
1 Nok genteng beton Bh 3.50 15,500 54,250.00
2 Paku biasa 1/2”-1” Kg 0.05 22,000 1,100.00
3 Semen PC Kg 10.80 1,160 12,528.00
4 Pasir pasang M3 0.032 115,000 3,680.00
5 Semen warna Kg 1.00 10,000 10,000.00
JUMLAH HARGA BAHAN 81,558.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 166,758.00
E. OVERHEAD & PROFIT 16,675.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 183,433.80

DIVISI 4 / 4.5.2.36
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.36
JENIS PEKERJAAN : Pemasangan 1 m’ nok genteng aspal
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.125 120,000 15,000.00
2 Tukang Kayu (L.03) OH 0.250 150,000 37,500.00
3 Kepala tukang (L.11) OH 0.025 175,000 4,375.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 57,985.00
B. BAHAN
1 Nok genteng aspal Bh 2.00 9,250 18,500.00
2 Paku biasa 1/2”-1” Kg 0.05 22,000 1,100.00
3 Kayu kelas III M3 0.0035 2,600,000 9,100.00
JUMLAH HARGA BAHAN 28,700.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 86,685.00


E. OVERHEAD & PROFIT 10,0 % x D 8,668.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 95,353.50

DIVISI 4 / 4.5 .2.37


ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.37
JENIS PEKERJAAN : Pemasangan 1 m’ nok genteng metal
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.250 120,000 30,000.00
2 Tukang (L.03) OH 0.150 150,000 22,500.00
3 Kepala tukang (L.11) OH 0.015 175,000 2,625.00
4 Mandor (L.15) OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 57,530.00
B. BAHAN
1 Nok genteng metal Bh 1.100 27,000 29,700.00
2 Paku biasa 1/2”-1” Kg 0.05 22,000 1,100.00
JUMLAH HARGA BAHAN 30,800.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 88,330.00
E. OVERHEAD & PROFIT 10,0 % x D 8,833.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 97,163.00
DIVISI 4 / 4.5.2.37.a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.37.a
JENIS PEKERJAAN : Pemasangan 1 m’ nok genteng metal berpasir
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.250 120,000 30,000.00
2 Tukang (L.03) OH 0.150 150,000 22,500.00
3 Kepala tukang (L.11) OH 0.015 175,000 2,625.00
4 Mandor (L.15) OH 0.013 185,000 2,405.00
JUMLAH HARGA TENAGA 57,530.00
B. BAHAN
1 Nok genteng metal berpasir Bh 1.100 45,000 49,500.00
2 Paku biasa 1/2”-1” Kg 0.05 22,000 1,100.00
JUMLAH HARGA BAHAN 50,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 108,130.00
E. OVERHEAD & PROFIT 10,0 % x D 10,813.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 118,943.00

DIVISI 4 / 4.5.2.38
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.38
JENIS PEKERJAAN : Pemasangan 1 m’ nok sirap
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.125 120,000 15,000.00
2 Tukang Kayu (L.03) OH 0.250 150,000 37,500.00
3 Kepala tukang (L.11) OH 0.025 175,000 4,375.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 57,985.00
B. BAHAN
1 Seng plat 3 x 6” Lbr 0.40 90,000 36,000.00
2 Paku biasa 1/2”-1” Kg 0.05 22,000 1,100.00
3 Paku biasa 2”-5” Kg 0.05 22,000 1,100.00
JUMLAH HARGA BAHAN 38,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 96,185.00
E. OVERHEAD & PROFIT 10,0 % x D 9,618.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 105,803.50

DIVISI 4 / 4.5.2.39
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.39
JENIS PEKERJAAN : Pemasangan 1 m2 atap seng gelombang
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.120 120,000 14,400.00
2 Tukang Kayu (L.03) OH 0.06 150,000 9,000.00
3 Kepala tukang (L.11) OH 0.006 175,000 1,050.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 25,560.00
B. BAHAN
1 Seng gelombang 3"-5" Lbr 0.70 95,000 66,500.00
2 Paku biasa 1/2”-1” Kg 0.02 22,000 440.00
JUMLAH HARGA BAHAN 66,940.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 92,500.00


E. OVERHEAD & PROFIT 10,0 % x D 9,250.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 101,750.00
DIVISI 4 / 4.5.2.40

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.40
JENIS PEKERJAAN : Pemasangan 1 m’nok atap seng
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.07 150,000 10,500.00
3 Kepala tukang (L.11) OH 0.007 175,000 1,225.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 30,835.00
B. BAHAN
1 Seng plat 3”x6”bjls28 Lbr 0.30 90,000 27,000.00
2 Paku biasa 1/2”-1” Kg 0.04 22,000 880.00
JUMLAH HARGA BAHAN 27,880.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 58,715.00
E. OVERHEAD & PROFIT 10,0 % x D 5,871.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 64,586.50

DIVISI 4 / 4.5.2.41

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.41
JENIS PEKERJAAN : Pemasangan 1 m2 atap alumunium
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.075 150,000 11,250.00
3 Kepala tukang (L.11) OH 0.08 175,000 14,000.00
4 Mandor (L.15) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 44,360.00
B. BAHAN
1 Almn gel tbl 0,55 Lbr 1.05 100,000 105,000.00
2 Paku hak panj 15cm Kg 0.02 20,000 400.00
JUMLAH HARGA BAHAN 105,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 149,760.00
E. OVERHEAD & PROFIT 10,0 % x D 14,976.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 164,736.00
DIVISI 4 / 4.5.2.42
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.42
JENIS PEKERJAAN : Pemasangan 1 m’ nok alumunium
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.100 120,000 12,000.00
2 Tukang Kayu (L.03) OH 0.100 150,000 15,000.00
3 Kepala tukang (L.11) OH 0.100 175,000 17,500.00
4 Mandor (L.15) OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 53,750.00
B. BAHAN
1 Nok standar 40x18 Bh 1.20 29,500 35,400.00
2 Paku hak panj 15cm Kg 0.04 20,000 800.00
JUMLAH HARGA BAHAN 36,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 89,950.00
E. OVERHEAD & PROFIT 10,0 % x D 8,995.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 98,945.00

DIVISI 4 / 4.5.2.43

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.5.2.43
JENIS PEKERJAAN : Pemasangan 1 m2 alumunium foil / sisalation
SATUAN PEMBAYARAN :M2
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.05 150,000 7,500.00
3 Kepala tukang (L.11) OH 0.005 175,000 875.00
4 Mandor (L.15) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 27,855.00
B. BAHAN
1 Alumunium foil M2 1.05 10,833 11,374.65
JUMLAH HARGA BAHAN 11,374.65
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 39,229.65
E. OVERHEAD & PROFIT 10,0 % x D 3,922.97
F. HARGA SATUAN PEKERJAAN ( D + E ) 43,152.62
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.1
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
SATUAN PEMBAYARAN :M3
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 7.000 120,000 840,000.00
2 Tukang Kayu (L.03) OH 21.000 150,000 3,150,000.00
3 Kepala tukang (L.03) OH 2.100 175,000 367,500.00
4 Mandor (L.04) OH 0.350 185,000 64,750.00
JUMLAH HARGA TENAGA 4,422,250.00
B. BAHAN 0.00
1 Balok kayu m3 1.100 4,300,000 4,730,000.00
2 Paku 10 cm Kg 1.250 22,000 27,500.00
3 Lem kayu Kg 1.000 20,000 20,000.00
JUMLAH HARGA BAHAN 4,777,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 9,199,750.00
E. OVERHEAD & PROFIT 10,0 % x D 919,975.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 10,119,725.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.2
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas III
SATUAN PEMBAYARAN :M3
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 6.000 120,000 720,000.00
2 Tukang Kayu (L.03) OH 18.000 150,000 2,700,000.00
3 Kepala tukang (L.03) OH 1.800 175,000 315,000.00
4 Mandor (L.04) OH 0.300 185,000 55,500.00
JUMLAH HARGA TENAGA 3,790,500.00
B. BAHAN 0.00
1 Balok kayu m3 1.200 2,600,000 3,120,000.00
2 Paku 10 cm Kg 1.250 22,000 27,500.00
3 Lem kayu Kg 1.000 20,000 20,000.00
JUMLAH HARGA BAHAN 3,167,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 6,958,000.00
E. OVERHEAD & PROFIT 10,0 % x D 695,800.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 7,653,800.00

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.3
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.350 120,000 42,000.00
2 Tukang Kayu (L.03) OH 1.050 150,000 157,500.00
3 Kepala tukang (L.03) OH 0.105 175,000 18,375.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 221,205.00
B. BAHAN
1 Papan kayu kelas II m3 0.040 4,300,000 172,000.00
2 Paku 5 – 7 cm Kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 173,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 394,305.00
E. OVERHEAD & PROFIT 10,0 % x D 39,430.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 433,735.50
DIVISI 4 / 4.6.1.4
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.4
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.350 120,000 42,000.00
2 Tukang Kayu (L.03) OH 1.050 150,000 157,500.00
3 Kepala tukang (L.03) OH 0.105 175,000 18,375.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 221,205.00
B. BAHAN
1 Papan kayu m3 0.040 2,600,000 104,000.00
2 Paku 5 – 7 cm Kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 105,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 326,305.00
E. OVERHEAD & PROFIT 10,0 % x D 32,630.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 358,935.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.5
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 1.000 120,000 120,000.00
2 Tukang Kayu (L.03) OH 3.000 150,000 450,000.00
3 Kepala tukang (L.03) OH 0.300 175,000 52,500.00
4 Mandor (L.04) OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 631,750.00
B. BAHAN
1 Papan kayu m3 0.040 4,300,000 172,000.00
2 Lem Kayu Kg 0.500 20,000 10,000.00
JUMLAH HARGA BAHAN 182,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 813,750.00


E. OVERHEAD & PROFIT 10,0 % x D 81,375.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 895,125.00

DIVISI 4 / 4.6.1.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.6
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.800 120,000 96,000.00
2 Tukang Kayu (L.03) OH 2.400 150,000 360,000.00
3 Kepala tukang (L.03) OH 0.240 175,000 42,000.00
4 Mandor (L.04) OH 0.040 185,000 7,400.00
JUMLAH HARGA TENAGA 505,400.00
B. BAHAN
1 Papan kayu m3 0.024 4,300,000 103,200.00
2 Lem Kayu Kg 0.300 20,000 6,000.00
JUMLAH HARGA BAHAN 109,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00
D. JUMLAH ( A + B + C ) 614,600.00
E. OVERHEAD & PROFIT 10,0 % x D 61,460.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 676,060.00
DIVISI 4 / 4.6.1.7
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.7
JENIS PEKERJAAN : Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 1.000 120,000 120,000.00
2 Tukang Kayu (L.03) OH 3.000 150,000 450,000.00
3 Kepala tukang (L.03) OH 0.300 175,000 52,500.00
4 Mandor (L.04) OH 0.050 185,000 9,250.00
JUMLAH HARGA TENAGA 631,750.00
B. BAHAN
1 Papan kayu m3 0.064 4,300,000 275,200.00
2 Lem Kayu Kg 0.500 20,000 10,000.00
JUMLAH HARGA BAHAN 285,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 916,950.00
E. OVERHEAD & PROFIT 10,0 % x D 91,695.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,008,645.00

DIVISI 4 / 4.6.1.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.8
JENIS PEKERJAAN : Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.700 120,000 84,000.00
2 Tukang Kayu (L.03) OH 2.100 150,000 315,000.00
3 Kepala tukang (L.03) OH 0.210 175,000 36,750.00
4 Mandor (L.04) OH 0.035 185,000 6,475.00
JUMLAH HARGA TENAGA 442,225.00
B. BAHAN
1 Papan kayu m3 0.025 4,300,000 107,500.00
2 Paku 1 cm – 2,5 cm kg 0.030 22,000 660.00
3 Lem kayu kg 0.500 20,000 10,000.00
4 Plywood tebal 4 mm Ukuran (90 x 220) cm Lembar 1.000 45,000 45,000.00
JUMLAH HARGA BAHAN 163,160.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 605,385.00
E. OVERHEAD & PROFIT 10,0 % x D 60,538.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 665,923.50

DIVISI 4 / 4.6.1.9
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.9
JENIS PEKERJAAN : Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.800 120,000 96,000.00
2 Tukang Kayu (L.03) OH 2.400 150,000 360,000.00
3 Kepala tukang (L.03) OH 0.240 175,000 42,000.00
4 Mandor (L.04) OH 0.040 185,000 7,400.00
JUMLAH HARGA TENAGA 505,400.00
B. BAHAN
1 Papan kayu m3 0.0256 4,300,000 110,080.00
2 Paku 1 cm – 2,5 cm kg 0.030 22,000 660.00
3 Lem kayu kg 0.500 20,000 10,000.00
4 Plywood tebal 4 mm Ukuran (90 x 220) cm Lembar 1.000 45,000 45,000.00
JUMLAH HARGA BAHAN 165,740.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 671,140.00
E. OVERHEAD & PROFIT 10,0 % x D 67,114.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 738,254.00
DIVISI 4 / 4.6.1.10
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.10
JENIS PEKERJAAN : Pemasangan 1 m2 jalusi kusen, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.670 120,000 80,400.00
2 Tukang Kayu L.03 OH 2.000 150,000 300,000.00
3 Kepala tukang L.03 OH 0.200 175,000 35,000.00
4 Mandor L.04 OH 0.335 185,000 61,975.00
JUMLAH HARGA TENAGA 477,375.00
B. BAHAN
1 Papan kayu m3 0.060 4,300,000 258,000.00
2 Paku 1 cm – 2,5 cm kg 0.150 22,000 3,300.00
JUMLAH HARGA BAHAN 261,300.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 738,675.00
E. OVERHEAD & PROFIT 10,0 % x D 73,867.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 812,542.50

DIVISI 4 / 4.6.1.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.11
JENIS PEKERJAAN : Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.800 120,000 96,000.00
2 Tukang Kayu L.03 OH 2.400 150,000 360,000.00
3 Kepala tukang L.03 OH 0.240 175,000 42,000.00
4 Mandor L.04 OH 0.040 185,000 7,400.00
JUMLAH HARGA TENAGA 505,400.00
B. BAHAN
1 Papan kayu kelas II m3 0.025 4,300,000 107,500.00
2 Paku 1 – 2,5 cm kg 0.030 22,000 660.00
3 Lem kayu kg 0.300 20,000 6,000.00
4 Teakwood 4 mm 90 x 220 cm Lembar 1.000 45,000 45,000.00
JUMLAH HARGA BAHAN 159,160.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 664,560.00
E. OVERHEAD & PROFIT 10,0 % x D 66,456.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 731,016.00

DIVISI 4 / 4.6.1.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.12
JENIS PEKERJAAN : Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.850 120,000 102,000.00
2 Tukang Kayu L.03 OH 2.550 150,000 382,500.00
3 Kepala tukang L.03 OH 0.255 175,000 44,625.00
4 Mandor L.04 OH 0.043 185,000 7,955.00
JUMLAH HARGA TENAGA 537,080.00
B. BAHAN
1 Papan kayu m3 0.025 4,300,000 107,500.00
2 Paku 1 – 2,5 cm kg 0.030 22,000 660.00
3 Lem kayu kg 0.800 20,000 16,000.00
4 Teakwood 4 mm Lembar 1.000 45,000 45,000.00
90 x 220 cm
5 Formika Lembar 0.500 150,000 75,000.00
JUMLAH HARGA BAHAN 244,160.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 781,240.00
E. OVERHEAD & PROFIT 10,0 % x D 78,124.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 859,364.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.13
JENIS PEKERJAAN : Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II
SATUAN PEMBAYARAN :M3
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 4.000 120,000 560,000.00
2 Tukang Kayu L.03 OH 12.000 150,000 1,920,000.00
3 Kepala tukang L.03 OH 1.200 175,000 216,000.00
4 Mandor L.04 OH 0.200 185,000 37,000.00
JUMLAH HARGA TENAGA 2,733,000.00
B. BAHAN
1 m3 1.100 4,300,000 4,730,000.00
2 kg 15.000 9,000 135,000.00
3 kg 5.600 20,000 112,000.00
JUMLAH HARGA BAHAN 4,977,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 7,710,000.00
E. OVERHEAD & PROFIT 10,0 % x D 771,000.00
15,0 % SATUAN
x D
F. HARGA PEKERJAAN ( D + E ) 8,481,000.00

DIVISI 4 / 4.6.1.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.14
JENIS PEKERJAAN : Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II
SATUAN PEMBAYARAN :M3
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 6.700 120,000 804,000.00
2 Tukang Kayu L.03 OH 20.100 150,000 3,015,000.00
3 Kepala tukang L.03 OH 2.010 175,000 351,750.00
4 Mandor L.04 OH 0.335 185,000 61,975.00
JUMLAH HARGA TENAGA 4,232,725.00
B. BAHAN 0.00
Balok kayu
1 m3 1.200 4,300,000 5,160,000.00
Besi strip tebal 5mm Paku 15 cm
2 kg 15.000 9,000 135,000.00
3 kg 5.600 20,000 112,000.00
JUMLAH HARGA BAHAN 5,407,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 9,639,725.00
E. OVERHEAD & PROFIT 10,0 % x D 963,972.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 10,603,697.50

DIVISI 4 / 4.6.1.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.15
JENIS PEKERJAAN : Pemasangan 1 m3 konstruksi gordeng, kayu kelas II
SATUAN PEMBAYARAN :M3
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 6.700 120,000 804,000.00
2 Tukang Kayu L.03 OH 20.100 150,000 3,015,000.00
3 Kepala tukang L.03 OH 2.010 175,000 351,750.00
4 Mandor L.04 OH 0.335 185,000 61,975.00
JUMLAH HARGA TENAGA 4,232,725.00
B. BAHAN 0.00
Balok kayu
1 m3 1.100 4,300,000 4,730,000.00
Besi strip tebal 5mm Paku 12 cm
2 kg 15.000 9,000 135,000.00
3 kg 3.000 20,000 60,000.00
JUMLAH HARGA BAHAN 4,925,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 9,157,725.00
E. OVERHEAD & PROFIT 10,0 % x D 915,772.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 10,073,497.50
DIVISI 4 / 4.6.1.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.16
JENIS PEKERJAAN : Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja L.01 OH 0.100 120,000 12,000.00


2 Tukang Kayu L.03 OH 0.100 150,000 15,000.00
3 Kepala tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00
B. BAHAN 0.00
1 Kaso-kaso 5 x 7cm m3 0.014 4,300,000 60,200.00
2 Reng 2 x 3 cm m3 0.036 4,300,000 154,800.00
3 Paku 5 dan 10 cm kg 0.250 22,000 5,500.00
JUMLAH HARGA BAHAN 220,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 250,175.00
E. OVERHEAD & PROFIT 15,0 % x D 25,017.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 275,192.50

DIVISI 4 / 4.6.1.17
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.17
JENIS PEKERJAAN : Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.100 120,000 12,000.00
2 Tukang Kayu L.03 OH 0.100 150,000 15,000.00
3 Kepala tukang L.03 OH 0.010 175,000 1,750.00
4 Mandor L.04 OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 29,675.00
B. BAHAN 0.00
1 Kaso-kaso 5 x 7cm m3 0.014 4,300,000 60,200.00
2 Reng 3 x 4 cm m3 0.057 4,300,000 245,100.00
3 Paku 5 dan 10 cm kg 0.250 22,000 5,500.00
JUMLAH HARGA BAHAN 310,800.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 340,475.00
E. OVERHEAD & PROFIT 10,0 % x D 34,047.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 374,522.50

DIVISI 4 / 4.6.1.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.18
JENIS PEKERJAAN : Pemasangan 1 m2 rangka atap sirap, kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.120 120,000 14,400.00
2 Tukang Kayu L.03 OH 0.120 150,000 18,000.00
3 Kepala tukang L.03 OH 0.012 175,000 2,100.00
4 Mandor L.04 OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 35,610.00
B. BAHAN
Kayu kelas II Paku 5 - 10 cm
1 m3 0.014 4,300,000 60,200.00
2 kg 0.057 22,000 1,254.00
JUMLAH HARGA BAHAN 61,454.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 97,064.00
E. OVERHEAD & PROFIT 10,0 % x D 9,706.40
F. HARGA SATUAN PEKERJAAN ( D + E ) 106,770.40
DIVISI 4 / 4.6.1.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.19
JENIS PEKERJAAN : Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas III
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja L.01 OH 0.150 120,000 18,000.00
2 Tukang Kayu L.03 OH 0.300 150,000 45,000.00
3 Kepala tukang L.03 OH 0.030 175,000 5,250.00
4 Mandor L.04 OH 0.075 185,000 13,875.00
JUMLAH HARGA TENAGA 82,125.00
B. BAHAN
1 Kaso-kaso 5 x 7cm m3 0.0154 2,600,000 40,040.00
2 Paku 7 cm – 10 cm kg 0.200 22,000 4,400.00
JUMLAH HARGA BAHAN 44,440.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 126,565.00
E. OVERHEAD & PROFIT 10,0 % x D 12,656.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 139,221.50

DIVISI 4 / 4.6.1.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.20
JENIS PEKERJAAN : Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas III
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang Kayu (L.03) OH 0.300 150,000 45,000.00
3 Kepala tukang (L.03) OH 0.030 175,000 5,250.00
4 Mandor (L04) OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 76,100.00
B. BAHAN
1 Kaso-kaso 5 x 7cm m3 0.0163 2,600,000 42,380.00
2 Paku 7 cm – 10 cm kg 0.250 22,000 5,500.00
JUMLAH HARGA BAHAN 47,880.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 123,980.00
E. OVERHEAD & PROFIT 10,0 % x D 12,398.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 136,378.00

DIVISI 4 / 4.6.1.21
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.21
JENIS PEKERJAAN : Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas IV
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.100 120,000 12,000.00
2 Tukang Kayu (L.03) OH 0.200 150,000 30,000.00
3 Kepala tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 46,425.00
B. BAHAN
1 kayu kelas IV m3 0.0108 1,600,000 17,280.00
2 Paku 5 dan 7 cm kg 0.100 22,000 2,200.00
JUMLAH HARGA BAHAN 19,480.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 65,905.00
E. OVERHEAD & PROFIT 10,0 % x D 6,590.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 72,495.50
DIVISI 4 / 4.6.1.21.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.21.a
JENIS PEKERJAAN : Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas IV
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.100 120,000 12,000.00
2 Tukang Kayu (L.03) OH 0.200 150,000 30,000.00
3 Kepala tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 46,425.00
B. BAHAN
1 Kalsiplank btg 0.3500 47,000 16,450.00
2 Paku kg 0.100 22,000 2,200.00
JUMLAH HARGA BAHAN 18,650.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 65,075.00
E. OVERHEAD & PROFIT 10,0 % x D 6,507.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 71,582.50

DIVISI 4 / 4.6.1.22
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.22
JENIS PEKERJAAN : Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas II
SATUAN PEMBAYARAN : M'
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.100 120,000 12,000.00
2 Tukang Kayu (L.03) OH 0.200 150,000 30,000.00
3 Kepala tukang (L.03) OH 0.020 175,000 3,500.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 46,425.00
B. BAHAN
1 kayu kelas II m3 0.01080 4,300,000 46,440.00
2 Paku 5 dan 7 cm kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 47,540.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 93,965.00
E. OVERHEAD & PROFIT 10,0 % x D 9,396.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 103,361.50

DIVISI 4 / 4.6.1.23
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.23
JENIS PEKERJAAN : Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas III
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.450 150,000 67,500.00
3 Kepala tukang (L.03) OH 0.045 175,000 7,875.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 94,855.00
B. BAHAN
1 Kayu kelas III m3 0.028 2,600,000 72,800.00
2 Paku 5 dan 7 cm kg 0.150 22,000 3,300.00
JUMLAH HARGA BAHAN 76,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 170,955.00
E. OVERHEAD & PROFIT 10,0 % x D 17,095.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 188,050.50
DIVISI 4 / 4.6.1.24
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.24
JENIS PEKERJAAN : Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.150 120,000 18,000.00
2 Tukang Kayu (L.03) OH 0.450 150,000 67,500.00
3 Kepala tukang (L.03) OH 0.045 175,000 7,875.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 94,855.00
B. BAHAN
1 Kayu kelas II m3 0.028 4,300,000 120,400.00
2 Paku 5 dan 10 kg 0.150 22,000 3,300.00
3 Teakwood 4 mm Lembar 0.860 45,000 38,700.00
4 Lem kayu kg 0.560 20,000 11,200.00
JUMLAH HARGA BAHAN 173,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 268,455.00
E. OVERHEAD & PROFIT 10,0 % x D 26,845.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 295,300.50

DIVISI 4 / 4.6.1.25
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.25
JENIS PEKERJAAN : Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
SATUAN PEMBAYARAN :M2
KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN
` (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.200 120,000 24,000.00
2 Tukang Kayu (L.03) OH 0.600 150,000 90,000.00
3 Kepala tukang (L.03) OH 0.060 175,000 10,500.00
4 Mandor (L.04) OH 0.010 185,000 1,850.00
JUMLAH HARGA TENAGA 126,350.00
B. BAHAN
1 Kayu kelas II m3 0.028 4,300,000 120,400.00
2 Paku 5 dan 10 kg 0.150 22,000 3,300.00
3 Plywood 4 mm, 120 x 240 Lembar 0.860 70,000 60,200.00
4 Lem kayu kg 0.560 20,000 11,200.00
JUMLAH HARGA BAHAN 195,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 321,450.00
E. OVERHEAD & PROFIT 10,0 % x D 32,145.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 353,595.00

DIVISI 4 / 4.6.1.26
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.26
JENIS PEKERJAAN : Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas II
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.600 120,000 72,000.00
2 Tukang Kayu (L.03) OH 1.800 150,000 270,000.00
3 Kepala tukang (L.03) OH 0.180 175,000 31,500.00
4 Mandor (L.04) OH 0.030 185,000 5,550.00
JUMLAH HARGA TENAGA 379,050.00
B. BAHAN 0.00
1 Papan kayu m3 0.007 4,300,000 30,100.00
2 Paku 5 dan 10 kg 0.100 22,000 2,200.00
3 Paku skrup 10 cm kg 0.150 55,000 8,250.00
JUMLAH HARGA BAHAN 40,550.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 419,600.00
E. OVERHEAD & PROFIT 10,0 % x D 41,960.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 461,560.00
DIVISI 4 / 4.6.1.27
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.27
JENIS PEKERJAAN : Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.025 120,000 3,000.00
2 Tukang Kayu (L.03) OH 0.075 150,000 11,250.00
3 Kepala tukang (L.03) OH 0.008 175,000 1,400.00
4 Mandor (L.04) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 15,835.00
B. BAHAN
1 Plywood 9 mm lembar 0.400 145,000 58,000.00
2 Paku 1 dan 2,5 kg 0.050 22,000 1,100.00
JUMLAH HARGA BAHAN 59,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 74,935.00
E. OVERHEAD & PROFIT 10,0 % x D 7,493.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 82,428.50

DIVISI 4 / 4.6.1.28
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.1.28
JENIS PEKERJAAN : Pemasangan 1 m2 dinding bilik, rangka kayu kelas III
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.100 120,000 12,000.00
2 Tukang Kayu (L.03) OH 0.050 150,000 7,500.00
3 Kepala tukang (L.03) OH 0.005 175,000 875.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 21,300.00
B. BAHAN
1 Bilik Bambu m2 1.500 29,167 43,750.50
2 Kaso-kaso 5 x 7 m3 0.014 2,600,000 36,400.00
3 Paku kg 0.012 22,000 264.00
4 List kayu 2/4 m3 0.003 2,600,000 7,800.00
JUMLAH HARGA BAHAN 88,214.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 109,514.50
E. OVERHEAD & PROFIT 10,0 % x D 10,951.45
F. HARGA SATUAN PEKERJAAN ( D + E ) 120,465.95
DIVISI 4 / 4.6.2.1

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.1
JENIS PEKERJAAN : Pemasangan 1 buah kunci tanam antik
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.06 120,000 7,200.00
2 Tukang Kayu (L.02) OH 0.60 150,000 90,000.00
3 Kepala tukang (L.03) OH 0.06 175,000 10,500.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 108,255.00
B. BAHAN
1 Kunci tanam antik Bh 1.00 180,000 180,000.00
JUMLAH HARGA BAHAN 180,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 288,255.00
E. OVERHEAD & PROFIT 10,0 % x D 28,825.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 317,080.50

DIVISI 4 / 4.6.2.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.2
JENIS PEKERJAAN : Pemasangan 1 buah kunci tanam biasa
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Kayu (L.02) OH 0.50 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 85,875.00
B. BAHAN
1 Kunci tanam Bh 1.00 155,000 155,000.00
JUMLAH HARGA BAHAN 155,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 240,875.00
E. OVERHEAD & PROFIT 10,0 % x D 24,087.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 264,962.50

DIVISI 4 / 4.6.2.2.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.2.a
JENIS PEKERJAAN : Pemasangan 1 buah kunci tanam stainless
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Kayu (L.02) OH 0.50 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 85,875.00
B. BAHAN
1 Handle pintu Bh 1.00 238,000 238,000.00
2 Isi silinder kunci Bh 1.00 175,000 175,000.00
JUMLAH HARGA BAHAN 413,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 498,875.00
E. OVERHEAD & PROFIT 10,0 % x D 49,887.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 548,762.50
DIVISI 4 / 4.6.2.2.b

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.2.b
JENIS PEKERJAAN : Pemasangan 1 buah kunci + handle
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Kayu (L.02) OH 0.50 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 85,875.00
B. BAHAN
1 Kunci tanam + handle Bh 1.00 285,000 285,000.00
JUMLAH HARGA BAHAN 285,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 370,875.00
E. OVERHEAD & PROFIT 10,0 % x D 37,087.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 407,962.50

DIVISI 4 / 4.6.2.3

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.3
JENIS PEKERJAAN : Pemasangan 1 buah kunci kamar mandi
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.005 120,000 600.00


2 Tukang Kayu (L.02) OH 0.50 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 84,905.00
B. BAHAN
1 Kunci tanam KM Bh 1.00 135,000 135,000.00
JUMLAH HARGA BAHAN 135,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 219,905.00
E. OVERHEAD & PROFIT 10,0 % x D 21,990.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 241,895.50

DIVISI 4 / 4.6.2.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.4
JENIS PEKERJAAN : Pemasangan 1 buah kunci silinder
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.005 120,000 600.00
2 Tukang Kayu (L.02) OH 0.50 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 84,905.00
B. BAHAN
1 Kunci Silinder Bh 1.00 175,000 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 259,905.00
E. OVERHEAD & PROFIT 10,0 % x D 25,990.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 285,895.50
DIVISI 4 / 4.6.2.5

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.5
JENIS PEKERJAAN : Pemasangan 1 buah engsel pintu
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 28,405.00
B. BAHAN
1 Engsel Pintu Bh 1.00 35,000 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 63,405.00
E. OVERHEAD & PROFIT 10,0 % x D 6,340.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 69,745.50

DIVISI 4 / 4.6.2.6

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.6
JENIS PEKERJAAN : Pemasangan 1 buah engsel jendela kupu-kupu
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.01 120,000 1,200.00


2 Tukang Kayu (L.02) OH 0.10 150,000 15,000.00
3 Kepala tukang (L.03) OH 0.010 175,000 1,750.00
4 Mandor (L.04) OH 0.0005 185,000 92.50
JUMLAH HARGA TENAGA 18,042.50
B. BAHAN
1 Engsel Kupu-kupu Bh 1.00 26,000 26,000.00
JUMLAH HARGA BAHAN 26,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 44,042.50
E. OVERHEAD & PROFIT 10,0 % x D 4,404.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 48,446.75

DIVISI 4/ 4.6.2.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.7
JENIS PEKERJAAN : Pemasangan 1 buah engsel angin
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.10 120,000 12,000.00
2 Tukang Kayu (L.02) OH 0.20 150,000 30,000.00
3 Kepala tukang (L.03) OH 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.0005 185,000 92.50
JUMLAH HARGA TENAGA 45,592.50
B. BAHAN
1 Engsel Angin Bh 1.00 21,000 21,000.00
JUMLAH HARGA BAHAN 21,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 66,592.50
E. OVERHEAD & PROFIT 10,0 % x D 6,659.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 73,251.75
DIVISI 4 / 4.6.2.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.8
JENIS PEKERJAAN : Pemasangan 1 buah spring knip
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.015 120,000 1,800.00


2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 28,405.00
B. BAHAN
1 Spring Knip Bh 1.00 26,000 26,000.00
JUMLAH HARGA BAHAN 26,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 54,405.00
E. OVERHEAD & PROFIT 10,0 % x D 5,440.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 59,845.50

DIVISI 4 / 4.2.6.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.9
JENIS PEKERJAAN : Pemasangan 1 buah engsel angin
SATUAN PEMBAYARAN : bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 28,405.00
B. BAHAN
1 Kait Angin Bh 1.00 25,000 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 53,405.00
E. OVERHEAD & PROFIT 10,0 % x D 5,340.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 58,745.50

DIVISI 4 / 4.6.2.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.10
JENIS PEKERJAAN : Pemasangan 1 buah door closer
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.05 120,000 6,000.00
2 Tukang Kayu (L.02) OH 0.5 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Door Closer set 1.00 500,000 500,000.00
JUMLAH HARGA BAHAN 500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 590,305.00
E. OVERHEAD & PROFIT 10,0 % x D 59,030.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 649,335.50
DIVISI 4 / 4.6.2.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.11
JENIS PEKERJAAN : Pemasangan 1 buah kunci slot
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Kayu (L.02) 0.2 150,000 30,000.00
3 Kepala tukang (L.03) 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.001 185,000 185.00
JUMLAH HARGA TENAGA 36,085.00
B. BAHAN
1 Kunci Slot Bh 1.00 52,000 52,000.00
JUMLAH HARGA BAHAN 52,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 88,085.00
E. OVERHEAD & PROFIT 10,0 % x D 8,808.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 96,893.50

DIVISI 4 / 4.6.2.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.12
JENIS PEKERJAAN : Pemasangan 1 buah door holder
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.05 120,000 6,000.00
2 Tukang Kayu (L.02) 0.5 150,000 75,000.00
3 Kepala tukang (L.03) 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Door holder Bh 1.00 115,000 115,000.00
JUMLAH HARGA BAHAN 115,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 205,305.00
E. OVERHEAD & PROFIT 10,0 % x D 20,530.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 225,835.50

DIVISI 4 / 4.6.2.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.13
JENIS PEKERJAAN : Pemasangan 1 buah door stop
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Kayu (L.02) OH 0.1 150,000 15,000.00
3 Kepala tukang (L.03) OH 0.01 175,000 1,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 18,875.00
B. BAHAN
1 Door Stop Bh 1.00 130,000 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 148,875.00
E. OVERHEAD & PROFIT 10,0 % x D 14,887.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 163,762.50
DIVISI 4 / 4.6.2.13.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.13.a
JENIS PEKERJAAN : Pemasangan 1 buah door handle
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.05 120,000 6,000.00
2 Tukang Kayu (L.02) OH 0.5 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 Door Handle Bh 1.00 425,000 425,000.00
JUMLAH HARGA BAHAN 425,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 515,305.00
E. OVERHEAD & PROFIT 10,0 % x D 51,530.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 566,835.50

DIVISI 4 / 4.6.2.14

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.14
JENIS PEKERJAAN : Pemasangan 1 buah rel pintu dorong
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.06 120,000 7,200.00


2 Tukang Kayu (L.02) 0.6 150,000 90,000.00
3 Kepala tukang (L.03) 0.06 175,000 10,500.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 108,255.00
B. BAHAN
1 Rel Pintu Dorong Bh 1.00 650,000 650,000.00
JUMLAH HARGA BAHAN 650,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 758,255.00
E. OVERHEAD & PROFIT 10,0 % x D 75,825.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 834,080.50

DIVISI 4 / 4.6.2.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.15
JENIS PEKERJAAN : Pemasangan 1 buah kunci lemari
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.025 120,000 3,000.00
2 Tukang Kayu (L.02) 0.25 150,000 37,500.00
3 Kepala tukang (L.03) 0.025 175,000 4,375.00
4 Mandor (L.04) OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 45,115.50
B. BAHAN
1 Kunci Lemari set 1.00 16,000 16,000.00
JUMLAH HARGA BAHAN 16,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 61,115.50
E. OVERHEAD & PROFIT 10,0 % x D 6,111.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 67,227.05
DIVISI 4 / 4 .6.2.16

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.16
JENIS PEKERJAAN : Pemasangan 1 m2 kaca tebal 3 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.0008 185,000 148.00
JUMLAH HARGA TENAGA 27,073.00
B. BAHAN
1 Kaca tebal 3 mm m2 1.10 110,000 121,000.00
2 Sealant Kg 0.05 85,000 4,250.00
JUMLAH HARGA BAHAN 125,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 152,323.00
E. OVERHEAD & PROFIT 10,0 % x D 15,232.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 167,555.30

DIVISI 4 / 4.6.2.17

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.17
JENIS PEKERJAAN : Pemasangan 1 m2 kaca tebal 5 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.0008 185,000 148.00
JUMLAH HARGA TENAGA 27,073.00
B. BAHAN
1 Kaca tebal 5 mm m2 1.10 150,000 165,000.00
2 Sealant Kg 0.05 85,000 4,250.00
JUMLAH HARGA BAHAN 169,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 196,323.00
E. OVERHEAD & PROFIT 10,0 % x D 19,632.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 215,955.30

DIVISI 4 / 4.6.2.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.18
JENIS PEKERJAAN : Pemasangan 1 m2 kaca tebal 8 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.017 120,000 2,040.00
2 Tukang Kayu (L.02) OH 0.17 150,000 25,500.00
3 Kepala tukang (L.03) OH 0.017 175,000 2,975.00
4 Mandor (L.04) OH 0.0009 185,000 166.50
JUMLAH HARGA TENAGA 30,681.50
B. BAHAN
1 Kaca tebal 8 mm m2 1.10 350,000 385,000.00
2 Sealant Kg 0.07 85,000 5,950.00
JUMLAH HARGA BAHAN 390,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 421,631.50
E. OVERHEAD & PROFIT 10,0 % x D 42,163.15
F. HARGA SATUAN PEKERJAAN ( D + E ) 463,794.65
DIVISI 4 / 4.6.2.19

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.19
JENIS PEKERJAAN : Pemasangan 1 m2 kaca buram tebal 12 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.025 120,000 3,000.00
2 Tukang Kayu (L.02) OH 0.25 150,000 37,500.00
3 Kepala tukang (L.03) OH 0.025 175,000 4,375.00
4 Mandor (L.04) OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 45,115.50
B. BAHAN
1 Kaca tebal 12 mm m2 1.10 525,000 577,500.00
2 Sealant Kg 0.07 85,000 5,950.00
JUMLAH HARGA BAHAN 583,450.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 628,565.50
E. OVERHEAD & PROFIT 10,0 % x D 62,856.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 691,422.05

DIVISI 4 / 4.6.2.19.a

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.19.a
JENIS PEKERJAAN : Pemasangan 1 m2 kaca buram tebal 12 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.025 120,000 3,000.00
2 Tukang Kayu (L.02) OH 0.25 150,000 37,500.00
3 Kepala tukang (L.03) OH 0.025 175,000 4,375.00
4 Mandor (L.04) OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 45,115.50
B. BAHAN
1 Kaca Buram 12 mm m2 1.10 1,200,000 1,320,000.00
2 Sealant Kg 0.07 85,000 5,950.00
JUMLAH HARGA BAHAN 1,325,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,371,065.50
E. OVERHEAD & PROFIT 10,0 % x D 137,106.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,508,172.05

DIVISI 4 / 4.6.2.20

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.20
JENIS PEKERJAAN : Pemasangan 1 m2 kaca cermin tebal 5 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 28,405.00
B. BAHAN
1 Kaca Cermin 5 mm m2 1.10 220,000 242,000.00
JUMLAH HARGA BAHAN 242,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 270,405.00
E. OVERHEAD & PROFIT 10,0 % x D 27,040.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 297,445.50
DIVISI 4 / 4.6.2.21

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.21
JENIS PEKERJAAN : Pemasangan 1 m2 kaca cermin tebal 8 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.017 120,000 2,040.00
2 Tukang Kayu (L.02) OH 0.17 150,000 25,500.00
3 Kepala tukang (L.03) OH 0.017 175,000 2,975.00
4 Mandor (L.04) OH 0.009 185,000 1,665.00
JUMLAH HARGA TENAGA 32,180.00
B. BAHAN
1 Kaca Cermin 8 mm m2 1.10 920,000 1,012,000.00
JUMLAH HARGA BAHAN 1,012,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,044,180.00
E. OVERHEAD & PROFIT 10,0 % x D 104,418.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,148,598.00

DIVISI 4 / 4.6.2.22

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.22
JENIS PEKERJAAN : Pemasangan 1 m2 kaca wireglassed tebal 5 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.015 120,000 1,800.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 28,405.00
B. BAHAN
1 Kaca wireglassed 5 mm m2 1.10 175,000 192,500.00
JUMLAH HARGA BAHAN 192,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 220,905.00
E. OVERHEAD & PROFIT 10,0 % x D 22,090.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 242,995.50
DIVISI 4 / 4.6.2.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.23
JENIS PEKERJAAN : Pemasangan 1 m2 kaca patri tebal 5 mm
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.075 120,000 9,000.00
2 Tukang Kayu (L.02) OH 0.15 150,000 22,500.00
3 Kepala tukang (L.03) OH 0.015 175,000 2,625.00
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 34,865.00
B. BAHAN
1 Kaca patri 5 mm m2 1.10 1,850,000 2,035,000.00
2 Sealant Kg 0.05 30,000 1,500.00
JUMLAH HARGA BAHAN 2,036,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,071,365.00


E. OVERHEAD & PROFIT 10,0 % x D 207,136.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,278,501.50

DIVISI 4 / 4.6.2.24

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.6.2.24
JENIS PEKERJAAN : Pemasangan 1 buah window holder
SATUAN PEMBAYARAN : Bh
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.05 120,000 6,000.00
2 Tukang Kayu (L.02) OH 0.5 150,000 75,000.00
3 Kepala tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 90,305.00
B. BAHAN
1 window holder Bh 1.00 115,000 115,000.00
JUMLAH HARGA BAHAN 115,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 205,305.00
E. OVERHEAD & PROFIT 10,0 % x D 20,530.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 225,835.50
DIVISI 4 / 4.7.1.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.1
JENIS PEKERJAAN : 1 m2 Pengikisan/pengerokan permukaan cat lama
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.15 120,000 18,000.00
2 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 18,555.00
B. BAHAN 0.00
1 Soda Api Kg 0.050 40,000 2,000.00
JUMLAH HARGA BAHAN 2,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 20,555.00
E. OVERHEAD & PROFIT 10,0 % x D 2,055.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 22,610.50

DIVISI 4 / 4.7.1.2

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.2
JENIS PEKERJAAN : 1 m2 Pencucian bidang permukaan tembok yang pernah dicat
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.15 120,000 18,000.00
2 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 18,555.00
B. BAHAN 0.00
1 Sabun Kg 0.050 18,000 900.00
JUMLAH HARGA BAHAN 900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 19,455.00
E. OVERHEAD & PROFIT 10,0 % x D 1,945.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 21,400.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.3
JENIS PEKERJAAN : 1 m2 Pengerokan karat pada permukaan baja cara manual
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.15 120,000 18,000.00


2 Mandor (L.04) OH 0.008 185,000 1,480.00
JUMLAH HARGA TENAGA 19,480.00
B. BAHAN 0.00
1 Sabun Kg 0.050 18,000 900.00
JUMLAH HARGA BAHAN 900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 20,380.00
E. OVERHEAD & PROFIT 10,0 % x D 2,038.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 22,418.00
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.4
JENIS PEKERJAAN : 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.07 120,000 8,400.00
2 Tukang Cat (L.02) OH 0.009 150,000 1,350.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 11,355.00
B. BAHAN
1 Cat menie Kg 0.20 24,000 4,800.00
2 Plamuur Kg 0.15 25,000 3,750.00
3 Cat dasar Kg 0.17 30,000 5,100.00
4 Cat penutup Kg 0.26 54,000 14,040.00
5 Kuas Bh 0.01 10,000 100.00
6 Pengencer Kg 0.03 28,000 840.00
7 Ampelas Lbr 0.2 8,000 1,600.00
JUMLAH HARGA BAHAN 30,230.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 41,585.00
E. OVERHEAD & PROFIT 10,0 % x D 4,158.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 45,743.50

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.5
JENIS PEKERJAAN : Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.07 120,000 8,400.00


2 Tukang Cat (L.02) OH 0.105 150,000 15,750.00
3 Kepala Tukang (L.03) OH 0.004 175,000 700.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 25,405.00
B. BAHAN
1 Cat menie Kg 0.20 24,000 4,800.00
2 Plamuur Kg 0.15 25,000 3,750.00
3 Cat dasar Kg 0.17 30,000 5,100.00
4 Cat penutup Kg 0.35 54,000 18,900.00
5 Kuas Bh 0.01 10,000 100.00
6 Pengencer Kg 0.03 28,000 840.00
7 Ampelas Lbr 0.2 8,000 1,600.00
JUMLAH HARGA BAHAN 35,090.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 60,495.00
E. OVERHEAD & PROFIT 10,0 % x D 6,049.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 66,544.50

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.6
JENIS PEKERJAAN : Pelaburan 1 m2 bidang kayu dengan teak oil
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.04 120,000 4,800.00
2 Tukang Cat (L.02) OH 0.063 150,000 9,450.00
3 Kepala Tukang (L.03) OH 0.063 175,000 11,025.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 25,830.00
B. BAHAN
1 Teak Oil L 0.36 55,000 19,800.00
JUMLAH HARGA BAHAN 19,800.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 45,630.00
E. OVERHEAD & PROFIT 10,0 % x D 4,563.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 50,193.00
DIVISI 4 / 4.7.1.7
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.7
JENIS PEKERJAAN : Pelaburan 1 m2 bidang kayu dengan politur
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.04 120,000 4,800.00


2 Tukang Cat (L.02) OH 0.063 150,000 9,450.00
3 Kepala Tukang (L.03) OH 0.016 175,000 2,800.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 17,605.00
B. BAHAN 0.00
1 Politur L 0.15 43,000 6,450.00
2 Politur jadi L 0.372 62,000 23,064.00
3 Ampelas Lbr 2.00 8,000 16,000.00
JUMLAH HARGA BAHAN 45,514.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 63,119.00
E. OVERHEAD & PROFIT 10,0 % x D 6,311.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 69,430.90

DIVISI 4 / 4.7.1.8

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.8
JENIS PEKERJAAN : Pelaburan 1 m2 bidang kayu dengan cat residu dan ter
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.10 120,000 12,000.00


2 Mandor (L.04) OH 0.006 185,000 1,110.00
JUMLAH HARGA TENAGA 13,110.00
B. BAHAN 0.00
1 Residu atau Ter L 0.35 5,000 1,750.00
JUMLAH HARGA BAHAN 1,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 14,860.00
E. OVERHEAD & PROFIT 10,0 % x D 1,486.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 16,346.00

DIVISI 4 / 4.7.1.9

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.9
JENIS PEKERJAAN : Pelaburan 1 m2 bidang kayu dengan vernis
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.16 120,000 19,200.00
2 Tukang Cat (L.02) OH 0.16 150,000 24,000.00
3 Kepala Tukang (L.03) OH 0.016 175,000 2,800.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 46,555.00
B. BAHAN 0.00
1 Vernis L 0.15 32,000 4,800.00
2 Dempul Kg 0.05 10,000 500.00
3 Ampelas Lbr 0.10 8,000 800.00
JUMLAH HARGA BAHAN 6,100.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 52,655.00
E. OVERHEAD & PROFIT 10,0 % x D 5,265.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 57,920.50
DIVISI 4 / 4.7.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.10
JENIS PEKERJAAN : Pengecatan 1 m2 Plafond ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup (kualitas
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.063 150,000 9,450.00
3 Kepala Tukang (L.03) OH 0.0063 175,000 1,102.50
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 13,507.50
B. BAHAN 0.00
1 Plamur Kg 0.10 25,000 2,500.00
2 Cat dasar Kg 0.10 43,000 4,300.00
3 Cat penutup Kg 0.26 24,000 6,240.00
JUMLAH HARGA BAHAN 13,040.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 26,547.50
E. OVERHEAD & PROFIT 10,0 % x D 2,654.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 29,202.25

DIVISI 4 / 4.7.1.10a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.10.a
JENIS PEKERJAAN : Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar (sealer), 2 lapis cat penutup (Interior/dalam))
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.063 150,000 9,450.00
3 Kepala Tukang (L.03) OH 0.0063 175,000 1,102.50
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 13,507.50
B. BAHAN 0.00
1 Kg 0.10 25,000 2,500.00
2 Kg 0.10 43,000 4,300.00
3 Kg 0.26 28,000 7,280.00
JUMLAH HARGA BAHAN 14,080.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 27,587.50
E. OVERHEAD & PROFIT 10,0 % x D 2,758.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 30,346.25

DIVISI 4 / 4.7.1.10.b
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.10.b
JENIS PEKERJAAN : Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 (Eksterior/luar))
SATUAN PEMBAYARAN :M2
HARGA SATUAN MLAH ARGA Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.063 150,000 9,450.00
3 Kepala Tukang (L.03) OH 0.0063 175,000 1,102.50
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 13,507.50
B. BAHAN 0.00
1 Kg 0.10 25,000 2,500.00
2 Kg 0.10 43,000 4,300.00
3 Kg 0.26 92,000 23,920.00
JUMLAH HARGA BAHAN 30,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 44,227.50
E. OVERHEAD & PROFIT 10,0 % x D 4,422.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 48,650.25
DIVISI 4 / 4.7.1.11

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.11
JENIS PEKERJAAN : Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.028 120,000 3,360.00
2 Tukang Cat (L.02) OH 0.042 150,000 6,300.00
3 Kepala Tukang (L.03) OH 0.0042 175,000 735.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 10,950.00
B. BAHAN
1 Cat dasar Kg 0.12 43,000 5,160.00
2 Cat penutup Kg 0.18 28,000 5,040.00
JUMLAH HARGA BAHAN 10,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH( A + B + C ) 21,150.00
E. OVERHEAD & PROFIT 10,0 % x D 2,115.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 23,265.00

DIVISI 4 / 4.7.1.12

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.12
JENIS PEKERJAAN : Pelaburan 1 m2 tembok dengan kalkarium
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.028 120,000 3,360.00
2 Tukang Cat (L.02) OH 0.042 150,000 6,300.00
3 Kepala Tukang (L.03) OH 0.0042 175,000 735.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 10,950.00
B. BAHAN
1 Kalkarium Kg 0.10 11,500 1,150.00
JUMLAH HARGA BAHAN 1,150.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 12,100.00
E. OVERHEAD & PROFIT 10,0 % x D 1,210.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 13,310.00

DIVSI 4 / 4.7.1.13

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.13
JENIS PEKERJAAN : Pelaburan 1 m2 tembok dengan kapur sirih
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.15 120,000 18,000.00


2 Tukang Cat (L.02) OH 0.001 150,000 150.00
3 Kepala Tukang (L.03) OH 0.0001 175,000 17.50
4 Mandor (L.04) OH 0.0025 185,000 462.50
JUMLAH HARGA TENAGA 18,630.00
B. BAHAN 0.00
1 Kapur sirih Kg 0.15 6,000 900.00
2 Amplas Lbr 0.10 8,000 800.00
3 Alang-alang Ikat 0.25 6,000 1,500.00
JUMLAH HARGA BAHAN 3,200.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 21,830.00
E. OVERHEAD & PROFIT 10,0 % x D 2,183.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 24,013.00
DIVISI 4/ 4.7.1.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.14
JENIS PEKERJAAN : Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.04 120,000 4,800.00
2 Tukang Cat (L.02) OH 0.005 150,000 750.00
3 Kepala Tukang (L.03) OH 0.0005 175,000 87.50
4 Mandor (L.04) OH 0.0025 185,000 462.50
JUMLAH HARGA TENAGA 6,100.00
B. BAHAN 0.00
1 Kapur sirih Kg 0.30 6,000 1,800.00
2 Ampelas Lbr 0.20 8,000 1,600.00
3 Alang-alang Ikat 0.25 6,000 1,500.00
JUMLAH HARGA BAHAN 4,900.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 11,000.00
E. OVERHEAD & PROFIT 10,0 % x D 1,100.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 12,100.00

DIVISI 4 / 4.7.1.15
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.15
JENIS PEKERJAAN : Pemasangan 1 m2 wallpaper
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.2 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.0025 185,000 462.50
JUMLAH HARGA TENAGA 36,362.50
B. BAHAN
1 Wall paper m2 1.20 67,000 80,400.00
2 Lem (perekat untuk wallpaper) Kg 0.20 180,000 36,000.00
JUMLAH HARGA BAHAN 116,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 152,762.50
E. OVERHEAD & PROFIT 10,0 % x D 15,276.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 168,038.75

DIVISI 4 / 4.7.1.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.16
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja dengan menie besi
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.02 120,000 2,400.00
2 Tukang Cat (L.02) OH 0.2 150,000 30,000.00
3 Kepala Tukang (L.03) OH 0.02 175,000 3,500.00
4 Mandor (L.04) OH 0.0025 185,000 462.50
JUMLAH HARGA TENAGA 36,362.50
B. BAHAN
1 Menie besi Kg 0.10 34,000 3,400.00
2 Kuas Bh 0.01 10,000 100.00
JUMLAH HARGA BAHAN 3,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 39,862.50
E. OVERHEAD & PROFIT 10,0 % x D 3,986.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 43,848.75
DIVISI 4 / 4.7.1.17
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.17
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.25 120,000 30,000.00
2 Tukang Cat (L.02) OH 0.225 150,000 33,750.00
3 Kepala Tukang (L.02) OH 0.0225 175,000 3,937.50
4 Mandor (L.04) OH 0.0075 185,000 1,387.50
JUMLAH HARGA TENAGA 69,075.00
B. BAHAN
1 Menie besi Kg 0.10 34,000 3,400.00
2 Pengencer L 0.01 28,000 280.00
3 Kuas Bh 0.01 10,000 100.00
4 Perancah kayu M³ 0.002 1,600,000 3,200.00
JUMLAH HARGA BAHAN 6,980.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 76,055.00
E. OVERHEAD & PROFIT 10,0 % x D 7,605.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,660.50

DIVISI 4 / 4.7.1.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.18
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.25 120,000 30,000.00
2 Tukang Cat (L.02) OH 0.25 150,000 37,500.00
3 Kepala Tukang (L.03) OH 0.025 175,000 4,375.00
4 Mandor (L.04) OH 0.0013 185,000 240.50
JUMLAH HARGA TENAGA 72,115.50
B. BAHAN
1 Menie A Kg 0.10 34,000 3,400.00
2 Menie B Kg 0.10 34,000 3,400.00
3 Cat Kg 0.08 60,000 4,800.00
4 Kuas Bh 0.01 10,000 100.00
5 Pengencer L 0.01 28,000 280.00
JUMLAH HARGA BAHAN 11,980.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 84,095.50
E. OVERHEAD & PROFIT 10,0 % x D 8,409.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 92,505.05

DIVISI 4 / 4.7.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.19
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.06 120,000 7,200.00
2 Tukang Cat (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.012 175,000 2,100.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 18,855.00
B. BAHAN 0.00
1 Cat Kg 0.30 60,000 18,000.00
2 Kuas Bh 0.01 10,000 100.00
3 Pengencer L 0.01 28,000 280.00
JUMLAH HARGA BAHAN 18,380.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 37,235.00
E. OVERHEAD & PROFIT 10,0 % x D 3,723.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 40,958.50
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.20
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.40 120,000 48,000.00
2 Tukang Cat (L.02) OH 0.80 150,000 120,000.00
3 Kepala Tukang (L.03) OH 0.08 175,000 14,000.00
4 Mandor (L.04) OH 0.02 185,000 3,700.00
JUMLAH HARGA TENAGA 185,700.00
B. BAHAN
1 Cat dasar Kg 0.11 60,000 6,600.00
2 Cat antara Kg 0.17 60,000 10,200.00
3 Cat penutup Kg 0.08 54,000 4,320.00
4 Kuas Bh 0.01 10,000 100.00
5 Pengencer L 0.01 28,000 280.00
JUMLAH HARGA BAHAN 21,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 207,200.00
E. OVERHEAD & PROFIT 10,0 % x D 20,720.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 227,920.00

DIVISI 4 / 4.7.1.21
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.21
JENIS PEKERJAAN : Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
SATUAN PEMBAYARAN :M2
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA (Rp.)
A. TENAGA (Rp.)

1 Pekerja (L.01) OH 0.40 120,000 48,000.00


2 Tukang Cat (L.02) OH 0.70 150,000 105,000.00
3 Kepala Tukang (L.03) OH 0.07 175,000 12,250.00
4 Mandor (L.04) OH 0.02 185,000 3,700.00
JUMLAH HARGA TENAGA 168,950.00
B. BAHAN
1 Cat dasar Kg 0.30 60,000 18,000.00
2 Pengencer L 0.01 28,000 280.00
JUMLAH HARGA BAHAN 18,280.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 187,230.00
E. OVERHEAD & PROFIT 10,0 % x D 18,723.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 205,953.00

DIVISI 4 / 4.7.1.22
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 4.7.1.22
JENIS PEKERJAAN : Plituran 10 m2 dengan plitur melamic
SATUAN PEMBAYARAN :M2
HARGA SATUAN JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN
(Rp.)
A. TENAGA
1 Pekerja (L.01) OH 2.00 120,000 240,000.00
2 Tukang Cat (L.02) OH 12.00 150,000 1,800,000.00
3 Kepala Tukang (L.03) OH 1.20 175,000 210,000.00
4 Mandor (L.04) OH 0.10 185,000 18,500.00
JUMLAH HARGA TENAGA 2,268,500.00
B. BAHAN
1 Wood filler kg 1.50 28,000 42,000.00
2 Wood stain kg 1.50 62,000 93,000.00
3 Sanding kg 1.50 68,000 102,000.00
4 Melamic kg 2.40 47,000 112,800.00
5 Thinner L 2.00 35,000 70,000.00
6 Amplas Lbr 6.00 8,000 48,000.00
JUMLAH HARGA BAHAN 467,800.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,736,300.00
E. OVERHEAD & PROFIT 10,0 % x D 273,630.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,009,930.00
DIVISI 5 / 5.1.1.1.

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.1
JENIS PEKERJAAN : Pemasangan 1 buah closet duduk/monoblock
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.30 120,000 396,000.00
2 Tukang Batu (L.02) OH 1.10 150,000 165,000.00
3 Kepala Tukang (L.03) OH 0.01 175,000 1,750.00
4 Mandor (L.04) OH 0.16 185,000 29,600.00
JUMLAH HARGA TENAGA 592,350.00
B. BAHAN
1 Closet duduk Unit 1.00 2,150,000 2,150,000.00
2 Perlengkapan 6% x closet Ls 1.00 129,000 129,000.00
JUMLAH HARGA BAHAN 2,279,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,871,350.00
E. OVERHEAD & PROFIT 10,0 % x D 287,135.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,158,485.00

DIVISI 5 / 5.1.1.2
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.2
JENIS PEKERJAAN : Pemasangan 1 buah closet jongkok porslen
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.50 150,000 225,000.00
3 Kepala Tukang (L.03) OH 0.15 175,000 26,250.00
4 Mandor (L.04) OH 0.16 185,000 29,600.00
JUMLAH HARGA TENAGA 400,850.00
B. BAHAN
1 Closet jongkok Unit 1.00 240,000 240,000.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 115,000 1,150.00
JUMLAH HARGA BAHAN 248,110.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 648,960.00
E. OVERHEAD & PROFIT 10,0 % x D 64,896.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 713,856.00

DIVISI 5 / 5.1.1.3
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.3
JENIS PEKERJAAN : Pemasangan 1 buah closet jongkok teraso
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.50 150,000 225,000.00
3 Kepala Tukang (L.03) OH 0.15 175,000 26,250.00
4 Mandor (L.04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 380,500.00
B. BAHAN
1 Closet jongkok Unit 1.00 115,000 115,000.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Bata merah Bh 7.00 720 5,040.00
JUMLAH HARGA BAHAN 128,150.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 508,650.00
E. OVERHEAD & PROFIT 10,0 % x D 50,865.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 559,515.00
DIVISI 5 / 51.1.4

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.4
JENIS PEKERJAAN : Pemasangan 1 buah urinoir
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 1.00 120,000 120,000.00
2 Tukang Batu (L.02) OH 1.00 150,000 150,000.00
3 Kepala Tukang (L.03) OH 0.10 175,000 17,500.00
4 Mandor (L.04) OH 0.05 185,000 9,250.00
JUMLAH HARGA TENAGA 296,750.00
B. BAHAN
1 Urinoir Unit 1.00 2,050,000 2,050,000.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Perlengkapan 30 % 0.30 2,050,000 615,000.00
JUMLAH HARGA BAHAN 2,673,110.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 2,969,860.00
E. OVERHEAD & PROFIT 10,0 % x D 296,986.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,266,846.00

DIVISI 5 / 5.1.1.5
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.5
JENIS PEKERJAAN : Pemasangan 1 buah wastafel
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 1.20 120,000 144,000.00
2 Tukang Batu (L.02) OH 1.45 150,000 217,500.00
3 Kepala Tukang (L.03) OH 0.15 175,000 26,250.00
4 Mandor (L.04) OH 0.06 185,000 11,100.00
JUMLAH HARGA TENAGA 398,850.00
B. BAHAN
1 Wastafel Unit 1.20 750,000 900,000.00
2 Semen Portland Kg 6.00 1,160 6,960.00
3 Pasir pasang M3 0.01 115,000 1,150.00
4 Perlengkapan 12.00 % 0.12 750,000 90,000.00
JUMLAH HARGA BAHAN 998,110.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,396,960.00
E. OVERHEAD & PROFIT 10,0 % x D 139,696.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,536,656.00

DIVISI 5 / 5.1.1.6
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.6
JENIS PEKERJAAN : Pemasangan 1 buah bathcuip porselen
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.075 120,000 9,000.00
2 Tukang Batu (L.02) OH 0.75 150,000 112,500.00
3 Kepala Tukang (L.03) OH 0.075 175,000 13,125.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 135,180.00
B. BAHAN
1 Bathcuip Unit 1.00 5,000,000 5,000,000.00
2 Perlengkapan 20.00 % 0.2 5,000,000 1,000,000.00
JUMLAH HARGA BAHAN 6,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 6,135,180.00
E. OVERHEAD & PROFIT 10,0 % x D 613,518.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 6,748,698.00
DIVISI 5 / 5.1.1.7

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.7
JENIS PEKERJAAN : Pemasangan 1 buah bak mandi fiberglass vol 0,30 m 3
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.00 120,000 360,000.00
2 Tukang Batu (L.02) OH 4.50 150,000 675,000.00
3 Kepala Tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.90 185,000 166,500.00
JUMLAH HARGA TENAGA 1,210,250.00
B. BAHAN
1 Bak fiberglass Unit 1.00 655,000 655,000.00
2 Perlengkapan 12%xbak Ls 1.00 78,600 78,600.00
JUMLAH HARGA BAHAN 733,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,943,850.00
E. OVERHEAD & PROFIT 10,0 % x D 194,385.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,138,235.00

DIVISI 5 / 5.1.1.8
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.8
JENIS PEKERJAAN : Pemasangan 1 buah bak mandi batu bata vol 0,30 m3
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 6.00 120,000 720,000.00
2 Tukang Batu (L.02) OH 3.00 150,000 450,000.00
3 Kepala Tukang (L.03) OH 0.30 175,000 52,500.00
4 Mandor (L.04) OH 0.03 185,000 5,550.00
JUMLAH HARGA TENAGA 1,228,050.00
B. BAHAN
1 Bata merah bh 150.00 720 108,000.00
2 Semen portland Kg 120.00 1,160 139,200.00
3 Pasir pasang M3 0.30 115,000 34,500.00
4 Porselen 11x11 bh 360.00 4,650 1,674,000.00
5 Semen warna Kg 6.00 5,500 33,000.00
JUMLAH HARGA BAHAN 1,988,700.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 3,216,750.00
E. OVERHEAD & PROFIT 10,0 % x D 321,675.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,538,425.00

DIVISI 5 / 5.1.1.9
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.9
JENIS PEKERJAAN : Pemasangan 1 buah bak mandi teraso vol 0,30 m3
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.00 120,000 360,000.00
2 Tukang Batu (L.02) OH 4.50 150,000 675,000.00
3 Kepala Tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.90 185,000 166,500.00
JUMLAH HARGA TENAGA 1,210,250.00
B. BAHAN
1 Bak fibreglass Unit 1.00 655,000 655,000.00
2 Perlengkapan 12%xbak Ls 0.12 655,000 78,600.00
JUMLAH HARGA BAHAN 733,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,943,850.00
E. OVERHEAD & PROFIT 10,0 % x D 194,385.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,138,235.00
DIVISI 5 / 5.1.1.10

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.10
JENIS PEKERJAAN : Pemasangan 1 buah bak/penampung air fiberglass vol 1 m3
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.3 120,000 36,000.00
2 Tukang Batu (L.02) OH 0.45 150,000 67,500.00
3 Kepala Tukang (L.03) OH 0.045 175,000 7,875.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 114,150.00
B. BAHAN
1 Bak air fiberglass Unit 1.00 1,320,000 1,320,000.00
2 Perlengkapan 12.00 % 0.12 1,320,000 158,400.00
JUMLAH HARGA BAHAN 1,478,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 1,592,550.00
E. OVERHEAD & PROFIT 10,0 % x D 159,255.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,751,805.00

DIVISI 5 / 5.1.1.11
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.11
JENIS PEKERJAAN : Pemasangan 1 buah bak beton volume 1 m3
SATUAN PEMBAYARAN
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.50 120,000 420,000.00
2 Tukang Batu (L.02) OH 4.50 150,000 675,000.00
3 Kepala Tukang (L.03) OH 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.018 185,000 3,330.00
JUMLAH HARGA TENAGA 1,107,080.00
B. BAHAN
1 Beton 1:2:3 M3 0.90 733,286 659,957.40
2 Baja tulangan Kg 180.00 12,000 2,160,000.00
3 Kayu bekisting M2 8.00 247,750 1,982,000.00
4 Ubin porselen Bh 500.00 4,650 2,325,000.00
5 Perlengkapan 10.00 % 0.10 733,286 73,328.60
JUMLAH HARGA BAHAN 7,200,286.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 8,307,366.00


E. OVERHEAD & PROFIT 10,0 % x D 830,736.60
F. HARGA SATUAN PEKERJAAN ( D + E ) 9,138,102.60

DIVISI 5 / 5.1.1.12
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.12
JENIS PEKERJAAN : Pemasangan 1 buah bak cuci piring stainlessteel
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.03 120,000 3,600.00
2 Tukang Batu (L.02) OH 0.30 150,000 45,000.00
3 Kepala Tukang (L.03) OH 0.03 175,000 5,250.00
4 Mandor (L.04) OH 0.015 185,000 2,775.00
JUMLAH HARGA TENAGA 56,625.00
B. BAHAN
1 Bak cuci piring Unit 1.00 335,000 335,000.00
2 Waterdrain Bh 1.00 265,000 265,000.00
JUMLAH HARGA BAHAN 600,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 656,625.00
E. OVERHEAD & PROFIT 10,0 % x D 65,662.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 722,287.50
DIVISI 5 / 5.1.1.13
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.13
JENIS PEKERJAAN : Pemasangan 1 buah bak cuci piring teraso
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.05 120,000 6,000.00
2 Tukang Batu (L.02) 0.50 150,000 75,000.00
3 Kepala Tukang (L.03) 0.05 175,000 8,750.00
4 Mandor (L.04) OH 0.025 185,000 4,625.00
JUMLAH HARGA TENAGA 94,375.00
B. BAHAN
1 Bak cuci piring Unit 1.00 335,000 335,000.00
2 Waterdrain Bh 1.00 265,000 265,000.00
3 Semen Portland Kg 20.00 1,160 23,200.00
4 Pasir Pasang M3 0.05 115,000 5,750.00
JUMLAH HARGA BAHAN 628,950.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 723,325.00
E. OVERHEAD & PROFIT 10,0 % x D 72,332.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 795,657.50

DIVISI 5 / 5.1.1.14
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.14
JENIS PEKERJAAN : Pemasangan 1 buah floor drain stainless steel
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.10 150,000 15,000.00
3 Kepala Tukang (L.03) OH 0.01 175,000 1,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 18,875.00
B. BAHAN
1 Floor drain stainless Unit 1.00 275,000 275,000.00
JUMLAH HARGA BAHAN 275,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 293,875.00


E. OVERHEAD & PROFIT 10,0 % x D 29,387.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 323,262.50

DIVISI 5 / 5.1.1.14.a
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.14.a
JENIS PEKERJAAN : Pemasangan 1 buah floor drain plastik
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.10 150,000 15,000.00
3 Kepala Tukang (L.03) OH 0.01 175,000 1,750.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 18,875.00
B. BAHAN
1 Floor drain plastik Unit 1.00 35,000 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 53,875.00


E. OVERHEAD & PROFIT 10,0 % x D 5,387.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 59,262.50
DIVISI 5 / 5.1.1.15

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.15
JENIS PEKERJAAN : Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm
SATUAN PEMBAYARAN : Bh
NO. KOMPONEN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
A. TENAGA
1 Pekerja (L.01) OH 2.16 120,000 259,200.00
2 Tukang Batu (L.02) OH 0.72 150,000 108,000.00
3 Kepala Tukang (L.03) OH 0.072 175,000 12,600.00
4 Mandor (L.04) OH 0.011 185,000 2,035.00
JUMLAH HARGA TENAGA 381,835.00
B. BAHAN
1 Bata merah bh 40.00 720 28,800.00
2 Semen portland Kg 44.00 1,160 51,040.00
3 Pasir pasang M3 0.07 115,000 8,050.00
4 Pasir beton M3 0.06 135,000 8,100.00
5 Kerikil M3 0.07 450,000 31,500.00
6 Baja tulangan Kg 1.60 12,000 19,200.00
JUMLAH HARGA BAHAN 146,690.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 528,525.00
E. OVERHEAD & PROFIT 10,0 % x D 52,852.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 581,377.50

DIVISI 5 / 5.1.1.16
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.16
JENIS PEKERJAAN : Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.2 120,000 384,000.00
2 Tukang Batu (L.02) OH 1.15 150,000 172,500.00
3 Kepala Tukang (L.03) OH 0.011 175,000 1,925.00
4 Mandor (L.04) OH 0.016 185,000 2,960.00
JUMLAH HARGA TENAGA 561,385.00
B. BAHAN
1 Bata merah bh 70.00 720 50,400.00
2 Semen portland Kg 77.00 1,160 89,320.00
3 Pasir pasang M3 0.13 115,000 14,950.00
4 Pasir beton M3 0.09 135,000 12,150.00
5 Kerikil M3 0.02 450,000 9,000.00
6 Baja tulangan Kg 2.60 12,000 31,200.00
JUMLAH HARGA BAHAN 207,020.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 768,405.00
E. OVERHEAD & PROFIT 10,0 % x D 76,840.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 845,245.50

DIVISI 5 / 5.1.1.17
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.17
JENIS PEKERJAAN : Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 3.2 120,000 384,000.00
2 Tukang Batu (L.02) OH 1.15 150,000 172,500.00
3 Kepala Tukang (L.03) OH 0.011 175,000 1,925.00
4 Mandor (L.04) OH 0.016 185,000 2,960.00
JUMLAH HARGA TENAGA 561,385.00
B. BAHAN
1 Bata merah bh 123.00 720 88,560.00
2 Semen portland Kg 114.00 1,160 132,240.00
3 Pasir pasang M3 0.184 115,000 21,160.00
4 Pasir beton M3 0.12 135,000 16,200.00
5 Kerikil M3 0.033 450,000 14,850.00
6 Baja tulangan Kg 4.85 12,000 58,200.00
JUMLAH HARGA BAHAN 331,210.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 892,595.00
E. OVERHEAD & PROFIT 10,0 % x D 89,259.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 981,854.50
DIVISI 5 / 5.1.1.18
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.18
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 1/2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.054 120,000 6,480.00
2 Tukang Batu (L.02) OH 0.09 150,000 13,500.00
3 Kepala Tukang (L.03) OH 0.009 175,000 1,575.00
4 Mandor (L.04) OH 0.027 185,000 4,995.00
JUMLAH HARGA TENAGA 26,550.00
B. BAHAN
1 Pipa galvanis 1/2” M 1.20 30,833 36,999.60
2 Perlengkapan 35%xpipa Ls 0.35 10,791.55 3,777.04
JUMLAH HARGA BAHAN 40,776.64
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 67,326.64
E. OVERHEAD & PROFIT 10,0 % x D 6,732.66
F. HARGA SATUAN PEKERJAAN ( D + E ) 74,059.31

DIVISI 5 / 5.1.1.19
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.19
JENIS PEKERJAAN : Pemasangan 1 buah kran diameter 1/2” atau 3/4”
SATUAN PEMBAYARAN : Bh
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.01 120,000 1,200.00
2 Tukang Batu (L.02) OH 0.4 150,000 60,000.00
3 Kepala Tukang (L.03) OH 0.04 175,000 7,000.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 69,125.00
B. BAHAN
1 Kran air M 1.00 45,000 45,000.00
2 Sealtape Buah 0.025 3,500 87.50
JUMLAH HARGA BAHAN 45,087.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 114,212.50


E. OVERHEAD & PROFIT 10,0 % x D 11,421.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 125,633.75

DIVISI 5 / 5.1.1.20
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.20
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 3/4”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.054 120,000 6,480.00
2 Tukang Batu (L.02) OH 0.09 150,000 13,500.00
3 Kepala Tukang (L.03) OH 0.009 175,000 1,575.00
4 Mandor (L.04) OH 0.027 185,000 4,995.00
JUMLAH HARGA TENAGA 26,550.00
B. BAHAN
M
1 Pipa galvanis 3/4” 1.20 37,500 45,000.00
%
2 Perlengkapan 35.00 0.35 13,125.00 4,593.75
JUMLAH HARGA BAHAN 49,593.75
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 76,143.75
E. OVERHEAD & PROFIT 10,0 % x D 7,614.38
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,758.13
DIVISI 5 / 5.1.1.21
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.21
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 1”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.054 120,000 6,480.00
2 Tukang Batu (L.02) OH 0.09 150,000 13,500.00
3 Kepala Tukang (L.03) OH 0.009 175,000 1,575.00
4 Mandor (L.04) OH 0.027 185,000 4,995.00
JUMLAH HARGA TENAGA 26,550.00
B. BAHAN
M
1 Pipa galvanis 1” 1.20 56,667 68,000.40
%
2 Perlengkapan 35.00 0.35 19,833 6,941.55
JUMLAH HARGA BAHAN 74,941.95
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 101,491.95
E. OVERHEAD & PROFIT 10,0 % x D 10,149.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 111,641.14

DIVISI 5 / 5.1.1.22
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.22
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 1 1/2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.108 120,000 12,960.00
2 Tukang Batu (L.02) 0.18 150,000 27,000.00
3 Kepala Tukang (L.03) 0.018 175,000 3,150.00
4 Mandor (L.04) OH 0.005 185,000 925.00
JUMLAH HARGA TENAGA 44,035.00
B. BAHAN
M
1 Pipa galvanis 11/2” 1.20 87,500 105,000.00
%
2 Perlengkapan 35 0.35 30,625 10,718.75
JUMLAH HARGA BAHAN 115,718.75
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 159,753.75
E. OVERHEAD & PROFIT 10,0 % x D 15,975.38
F. HARGA SATUAN PEKERJAAN ( D + E ) 175,729.13

DIVISI 5 / 5.1.1.23

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.23
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 3”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.135 120,000 16,200.00
2 Tukang Batu (L.02) OH 0.225 150,000 33,750.00
3 Kepala Tukang (L.03) OH 0.023 175,000 4,025.00
4 Mandor (L.04) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 55,270.00
B. BAHAN
M
1 Pipa galvanis 3” 1.20 191,667 230,000.40
%
2 Perlengkapan 35 0.35 67,083 23,479.21
JUMLAH HARGA BAHAN 253,479.61
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 308,749.61
E. OVERHEAD & PROFIT 10,0 % x D 30,874.96
F. HARGA SATUAN PEKERJAAN ( D + E ) 339,624.57
DIVISI 5 / 5.1.1.24
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.24
JENIS PEKERJAAN : Pemasangan 1 m’ pipa galvanis diameter 4”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.135 120,000 16,200.00
2 Tukang Batu (L.02) OH 0.225 150,000 33,750.00
3 Kepala Tukang (L.03) OH 0.023 175,000 4,025.00
4 Mandor (L.04) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 55,270.00
B. BAHAN
M
1 Pipa galvanis 4” 1.20 279,167 335,000.40
%
2 Perlengkapan 35 0.35 97,708 34,197.80
JUMLAH HARGA BAHAN 369,198.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 424,468.20
E. OVERHEAD & PROFIT 10,0 % x D 42,446.82
F. HARGA SATUAN PEKERJAAN ( D + E ) 466,915.02

DIVISI 5 / 5.1.1.25
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.25
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
M
1 Pipa PVC 1/2” 1.20 6,500 7,800.00
%
2 Perlengkapan 35 0.35 2,275 796.25
JUMLAH HARGA BAHAN 8,596.25
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 23,336.25
E. OVERHEAD & PROFIT 10,0 % x D 2,333.63
F. HARGA SATUAN PEKERJAAN ( D + E ) 25,669.88

DIVISI 5 / 5.1.1.26

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.26
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
M
1 Pipa PVC 3/4” 1.20 8,750 10,500.00
%
2 Perlengkapan 35 0.35 3,063 1,071.88
JUMLAH HARGA BAHAN 11,571.88
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 26,311.88
E. OVERHEAD & PROFIT 10,0 % x D 2,631.19
F. HARGA SATUAN PEKERJAAN ( D + E ) 28,943.06
DIVISI 5 / 5.1.1.27
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.27
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 1”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.036 120,000 4,320.00
2 Tukang Batu (L.02) OH 0.06 150,000 9,000.00
3 Kepala Tukang (L.03) OH 0.006 175,000 1,050.00
4 Mandor (L.04) OH 0.002 185,000 370.00
JUMLAH HARGA TENAGA 14,740.00
B. BAHAN
M
1 Pipa PVC 1” 1.20 12,000 14,400.00
%
2 Perlengkapan 35 0.35 4,200 1,470.00
JUMLAH HARGA BAHAN 15,870.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 30,610.00
E. OVERHEAD & PROFIT 10,0 % x D 3,061.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 33,671.00

DIVISI 5 / 5.1.1.28
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.28
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 11/2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.054 120,000 6,480.00
2 Tukang Batu (L.02) OH 0.09 150,000 13,500.00
3 Kepala Tukang (L.03) OH 0.009 175,000 1,575.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 22,110.00
B. BAHAN
M
1 Pipa PVC 11/2” 1.20 18,000 21,600.00
%
2 Perlengkapan 35 0.35 6,300 2,205.00
JUMLAH HARGA BAHAN 23,805.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 45,915.00


E. OVERHEAD & PROFIT 10,0 % x D 4,591.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 50,506.50

DIVISI 5 / 5.1.1.29
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.29
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.054 120,000 6,480.00
2 Tukang Batu (L.02) OH 0.09 150,000 13,500.00
3 Kepala Tukang (L.03) OH 0.009 175,000 1,575.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 22,110.00
B. BAHAN
M
1 Pipa PVC 2” 1.20 26,250 31,500.00
%
2 Perlengkapan 35 0.35 9,188 3,215.63
JUMLAH HARGA BAHAN 34,715.63
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 56,825.63
E. OVERHEAD & PROFIT 10,0 % x D 5,682.56
F. HARGA SATUAN PEKERJAAN ( D + E ) 62,508.19
DIVISI 5 / 5.1.1.30
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.30
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 21/2”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.081 120,000 9,720.00
2 Tukang Batu (L.02) OH 0.135 150,000 20,250.00
3 Kepala Tukang (L.03) OH 0.0135 175,000 2,362.50
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 33,072.50
B. BAHAN
M
1 Pipa PVC 21/2” 1.20 33,750 40,500.00
%
2 Perlengkapan 35 0.35 11,813 4,134.38
JUMLAH HARGA BAHAN 44,634.38
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 77,706.88
E. OVERHEAD & PROFIT 10,0 % x D 7,770.69
F. HARGA SATUAN PEKERJAAN ( D + E ) 85,477.56

DIVISI 5 / 5.1.1.31
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.31
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 3”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.081 120,000 9,720.00
2 Tukang Batu (L.02) OH 0.135 150,000 20,250.00
3 Kepala Tukang (L.03) OH 0.0135 175,000 2,362.50
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 33,072.50
B. BAHAN
M
1 Pipa PVC 3” 1.20 53,750 64,500.00
%
2 Perlengkapan 35 0.35 18,813 6,584.38
JUMLAH HARGA BAHAN 71,084.38
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 104,156.88
E. OVERHEAD & PROFIT 10,0 % x D 10,415.69
F. HARGA SATUAN PEKERJAAN ( D + E ) 114,572.56

DIVISI 5 / 5.1.1.32

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.32
JENIS PEKERJAAN : Pemasangan 1 m’ pipa PVC tipe AW diameter 4”
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.081 120,000 9,720.00
2 Tukang Batu (L.02) OH 0.135 150,000 20,250.00
3 Kepala Tukang (L.03) OH 0.0135 175,000 2,362.50
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 33,072.50
B. BAHAN
M
1 Pipa PVC 4” 1.20 89,000 106,800.00
%
2 Perlengkapan 35 0.35 31,150 10,902.50
JUMLAH HARGA BAHAN 117,702.50
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 150,775.00


E. OVERHEAD & PROFIT 10,0 % x D 15,077.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 165,852.50
DIVISI 5 / 5.1.1.33
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.33
JENIS PEKERJAAN : Pemasangan 1 m’ pipa air limbah jenis pipa tanah Ǿ 20 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.08 120,000 9,600.00
2 Tukang Batu (L.02) 0.04 150,000 6,000.00
3 Kepala Tukang (L.03) 0.004 175,000 700.00
4 Mandor (L.04) OH 0.004 185,000 740.00
JUMLAH HARGA TENAGA 17,040.00
B. BAHAN
1 Pipa tanah Bh 1.60 179,167 286,667.20
2 Semen portland Kg 35.00 1,160 40,600.00
3 Pasir pasang M3 0.014 115,000 1,610.00
4 Pasir urug M3 0.014 95,000 1,330.00
JUMLAH HARGA BAHAN 330,207.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 347,247.20
E. OVERHEAD & PROFIT 10,0 % x D 34,724.72
F. HARGA SATUAN PEKERJAAN ( D + E ) 381,971.92

DIVISI 5 / 5.1.1.34
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.34
JENIS PEKERJAAN : Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 15 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.06 120,000 7,200.00
2 Tukang Batu (L.02) 0.03 150,000 4,500.00
3 Kepala Tukang (L.03) 0.003 175,000 525.00
4 Mandor (L.04) OH 0.003 185,000 555.00
JUMLAH HARGA TENAGA 12,780.00
B. BAHAN
1 Pipa tanah dia 15 Bh 1.60 116,667 186,667.20
2 Semen portland Kg 0.68 1,160 788.80
3 Pasir pasang M3 0.013 115,000 1,495.00
4 Pasir urug M3 0.011 95,000 1,045.00
JUMLAH HARGA BAHAN 189,996.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 202,776.00
E. OVERHEAD & PROFIT 10,0 % x D 20,277.60
F. HARGA SATUAN PEKERJAAN ( D + E ) 223,053.60
DIVISI 5 / 5.1.1.35

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.35
JENIS PEKERJAAN : Pemasangan 1 m’ pipa beton diameter 15 - 20 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.14 120,000 16,800.00
2 Tukang Batu (L.02) OH 0.07 150,000 10,500.00
3 Kepala Tukang (L.03) OH 0.007 175,000 1,225.00
4 Mandor (L.04) OH 0.007 185,000 1,295.00
JUMLAH HARGA TENAGA 29,820.00
B. BAHAN
1 Pipa beton dia 20 cm Bh 1.10 250,000 275,000.00
2 Bata Merah M3 0.027 325,000 8,775.00
3 Semen portland Kg 3.92 1,160 4,547.20
4 Pasir pasang M3 0.056 115,000 6,440.00
5 Pasir urug M3 0.024 95,000 2,280.00
JUMLAH HARGA BAHAN 297,042.20
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 326,862.20
E. OVERHEAD & PROFIT 10,0 % x D 32,686.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 359,548.42

DIVISI 5 / 5.1.1.36

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)

NAMA PAKET 0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 5.1.1.36
JENIS PEKERJAAN : Pemasangan 1 m’ pipa beton diameter 30 - 100 cm
SATUAN PEMBAYARAN : M'
HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
NO. KOMPONEN KODE SATUAN KOEFISIEN

A. TENAGA
1 Pekerja (L.01) OH 0.38 120,000 45,600.00
2 Tukang Batu (L.02) OH 0.19 150,000 28,500.00
3 Kepala Tukang (L.03) OH 0.019 175,000 3,325.00
4 Mandor (L.04) OH 0.019 185,000 3,515.00
JUMLAH HARGA TENAGA 80,940.00
B. BAHAN
1 Pipa beton dia 30 Bh 1.10 335,000 368,500.00
2 Bata Merah M3 0.55 325,000 178,750.00
3 Semen portland Kg 10.30 1,160 11,948.00
4 Pasir pasang M3 0.061 115,000 7,015.00
5 Pasir urug M3 0.069 95,000 6,555.00
JUMLAH HARGA BAHAN 572,768.00
C. PERALATAN
JUMLAH HARGA PERALATAN 0.00

D. JUMLAH ( A + B + C ) 653,708.00
E. OVERHEAD & PROFIT 10,0 % x D 65,370.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 719,078.80
DAFTAR HADIR

Hari/ Tanggal :
Pukul : 07.30 WIB s/d Selesai
Tempat : Ruang Briefing IPSPRS
Acara : Briefing Pagi

NO NAMA JABATAN TANDA TANGAN

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26
27

28

29

30

Anda mungkin juga menyukai