Anda di halaman 1dari 3

REKAPITULASI

RENCANA ANGGARAN BIAYA


Kegiatan :
Pekerjaan :
Lokasi :
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
1 2 3
A PEKERJAAN PENDAHULUAN
A.1. PEKERJAAN PENDAHULUAN -
B PEKERJAAN STRUKTUR
B.1. PEKERJAAN TANAH & PASIR 7.189.153,00
B.2. PEKERJAAN PONDASI & TIANG PANCANG 49.441.702,57
B.3. PEKERJAAN BETON BERTULANG 136.067.757,93
C PEKERJAAN ARSITEKTUR
C.1. PEKERJAAN PASANGAN 127.313.436,86
C.2. PEKERJAAN PELAPIS LANTAI DAN DINDING 41.693.689,08
C.3. PEKERJAAN PLAFOND 36.468.381,22
C.4. PEKERJAAN ATAP 54.565.362,00
C.5. PEKERJAAN KUSEN, PINTU, & JENDELA 17.582.152,00
C.6. PEKERJAAN PENGECATAN 148.598.351,40
D PEKERJAAN MEKANIKAL & PLUMBING
D.1. PEKERJAAN SANITARY 3.350.000,00
D.2. PEKERJAAN MEKANIKAL 43.432.481,00
E PEKERJAAN ELEKTRIKAL
E.1. PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK 33.980.605,00
a. JUMLAH ( A + B + C + D + E ) 699.683.072,06
b. DIBULATKAN 699.684.000,00
TERBILANG :

Sangatta, November 2023


Konsultan Perencana
CV.YUWARAJA KONSULTAN

FAISAL SAGITA, ST
Team Leader
RENCANA ANGGARAN BIAYA
(R.A.B)
Kegiatan :
Pekerjaan :
Lokasi :
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT
( Rp ) ( Rp )
1 2 3 4 5 6

B. PEKERJAAN STRUKTUR
B.1 PEKERJAAN TANAH & PASIR
1 Galian Tanah Pondasi Batu Gunung 30,38 M3 Rp 81.875,00 Rp 2.487.362,50
2 Urugan Tanah Kembali Bekas Galian 26,04 M3 Rp 27.291,00 Rp 710.657,64
3 Urugan Tanah Bawah Lantai & Pemadatan 16,86 M3 Rp 95.150,00 Rp 1.604.157,64
4 Urugan Pasir Bawah Lantai 8,43 M3 Rp 212.750,00 Rp 1.793.402,72
5 Urugan Pasir Bawah Pondasi Batu Gunung 2,17 M3 Rp 212.750,00 Rp 461.667,50
6 Urugan Pasir Bawah Sloof 0,62 M3 Rp 212.750,00 Rp 131.905,00
TOTAL B.1 Rp 7.189.153,00
B.2 PEKERJAAN PONDASI & TIANG PANCANG
1 Cerucuk Ulin 10 / 10 - 200 cm 43,00 Ttk Rp 458.975,00 Rp 19.735.925,00
2 Lantai Kerja Beton Campuran 1 : 3 : 5 6,20 M3 Rp 1.562.596,00 Rp 9.688.095,20
3 Pekerjaan Pondasi Batu Gunung Camp. 1 : 4 13,97 M3 Rp 1.433.418,00 Rp 20.017.682,37
TOTAL B.2 Rp 49.441.702,57
B.3 PEKERJAAN BETON BERTULANG
1 Sloof (S.1) - 20 x 40 cm
a. Beton K-225 4,96 M3 Rp 1.770.737,00 Rp 8.782.855,52
b. Bekisting 49,60 M2 Rp 247.700,00 Rp 12.285.920,00
c. Pembesian 478,50 Kg Rp 28.912,00 Rp 13.834.394,12
2 Sloof (S.2) - 13 x 40 cm
a. Beton K-175 1,14 M3 Rp 1.706.010,00 Rp 1.951.675,44
b. Bekisting 17,60 M2 Rp 247.700,00 Rp 4.359.520,00
c. Pembesian 100,10 Kg Rp 28.912,00 Rp 2.893.948,35
3 Kolom ( K.1 ) - 30 x 30 cm
a. Beton K-225 4,32 M3 Rp 1.770.737,00 Rp 7.649.583,84
b. Bekisting 57,60 M2 Rp 292.708,00 Rp 16.859.980,80
c. Pembesian 317,45 Kg Rp 28.912,00 Rp 9.178.086,87
4 Kolom ( K.2 ) - 30 x 30 cm
a. Beton K - 225 4,32 M3 Rp 1.770.737,00 Rp 7.649.583,84
b. Bekisting 28,80 M2 Rp 292.708,00 Rp 8.429.990,40
c. Pembesian 387,92 Kg Rp 28.912,00 Rp 11.215.566,12
5 Kolom Praktis ( K.P ) - 13 x 13 cm
a. Beton K - 175 1,28 M3 Rp 1.706.010,00 Rp 2.191.199,24
b. Bekisting 19,76 M2 Rp 292.708,00 Rp 5.783.910,08
c. Pembesian 264,16 Kg Rp 28.912,00 Rp 7.637.283,13
10 Ring Balk (RB) - 13 x 40 cm
a. Beton K-175 3,29 M3 Rp 1.706.010,00 Rp 5.607.518,39
b. Bekisting 6,57 M2 Rp 292.708,00 Rp 1.924.215,56
c. Pembesian 270,91 Kg Rp 28.912,00 Rp 7.832.526,23
TOTAL B.3 Rp 136.067.757,93

C. PEKERJAAN ARSITEKTUR
C.1 PEKERJAAN PASANGAN
1 Pasangan Dinding Bata Camp. 1 : 4 248,86 M2 Rp 141.361,00 Rp 35.179.098,46
2 Plesteran Dinding Camp. 1 : 4 248,86 M2 Rp 82.072,00 Rp 20.424.437,92
3 Plesteran Kolom 30 x 30 cm, Camp. 1 : 4 497,72 M2 Rp 82.072,00 Rp 40.848.875,84
4 Acian Dinding 497,72 M2 Rp 51.152,00 Rp 25.459.373,44
5 Acian Kolom 105,60 M2 Rp 51.152,00 Rp 5.401.651,20
TOTAL C.1 Rp 127.313.436,86
C.2 PEKERJAAN PELAPIS LANTAI DAN DINDING
1 Pasangan Granite Lantai Uk. 60 x 60 cm (Polished) 70,02 M2 Rp 297.727,00 Rp 20.846.844,54
2 Pasangan Granite Lantai Uk. 60 x 60 cm ( Unpolished) 70,02 M2 Rp 297.727,00 Rp 20.846.844,54
TOTAL C.2 Rp 41.693.689,08
C.3 PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Hollow Aluminium Uk. 20x40 mm & 40x40 mm 60,90 M2 Rp 410.700,00 Rp 25.011.630,00
2 Pasangan Plafon Gypsum 9 mm 60,90 M2 Rp 71.340,00 Rp 4.344.606,00
4 Pasang List Gypsum 15 cm 99,73 M Rp 71.314,00 Rp 7.112.145,22
TOTAL C.3 Rp 36.468.381,22
C.4 PEKERJAAN ATAP
RENCANA ANGGARAN BIAYA
(R.A.B)
Kegiatan :
Pekerjaan :
Lokasi :
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT
( Rp ) ( Rp )
1 2 3 4 5 6
1 Pasangan Rangka Atap Baja Ringan 99,00 M2 Rp 318.010,00 Rp 31.482.990,00
2 Pasangan Atap Genteng Metal 99,00 M2 Rp 142.750,00 Rp 14.132.250,00
3 Pasangan Listplank GRC 40,00 M Rp 190.518,00 Rp 7.620.720,00
4 Bubungan Atap Genteng Metal 11,00 M Rp 81.582,00 Rp 897.402,00
5 Talang Atap 6,00 M Rp 72.000,00 Rp 432.000,00
TOTAL C.4 Rp 54.565.362,00
C..5 PEKERJAAN KUSEN, PINTU, & JENDELA
1 Pekerjaan Pintu
Pintu Type P.3 4,00 Unit Rp 4.395.538,00 Rp 17.582.152,00

TOTAL C.5 Rp 17.582.152,00


C..6 PEKERJAAN PENGECATAN
1 Pengecatan Dinding Luar ( Eksterior) 560,00 M2 Rp 111.740,00 Rp 62.574.400,00
2 Pengecatan Dinding Dalam ( Interior) 698,11 M2 Rp 109.140,00 Rp 76.191.725,40
3 Pengecatan Plafond 60,90 M2 Rp 109.140,00 Rp 6.646.626,00
4 Pengecatan Lisplank 40,00 M2 Rp 79.640,00 Rp 3.185.600,00
TOTAL C.6 Rp 148.598.351,40

D PEKERJAAN MEKANIKAL & PLUMBING


D.1 PEKERJAAN SANITARY
1 Kitchen Sink Stainless Steel 1,00 Unit Rp 1.500.000,00 Rp 1.500.000,00
2 Meja Beton - dapur 1,00 M Rp 1.850.000,00 Rp 1.850.000,00
SUB TOTAL D.1 Rp 3.350.000,00
D.2 PEKERJAAN MEKANIKAL
Instalasi Air Bersih
1 Pipa Air Bersih 1/2 " Type AW 21,00 m1 Rp 28.125,00 Rp 590.625,00
2 Pipa Air Bersih 1 " Type AW 30,00 m1 Rp 47.160,00 Rp 1.414.800,00
Instalasi Air Bekas
3 Pipa Air Bekas 2 " Type AW 18,00 m1 Rp 138.017,00 Rp 2.484.306,00
4 Saluran Keliling Bangunan 80,00 m1 Rp 399.538,00 Rp 31.963.040,00
5 Bak Kontrol Saluran 6,00 Bh Rp 209.457,00 Rp 1.256.742,00
Instalasi Air Kotor
6 Pipa Air Kotor 4 " Type AW 24,00 m1 Rp 238.457,00 Rp 5.722.968,00
SUB TOTAL D.2 Rp 43.432.481,00

E PEKERJAAN ELEKTRIKAL
E.1 PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK
LANTAI 1
1 Instalasi Titik Lampu 30,00 Titik Rp 426.605,00 Rp 12.798.150,00
2 Instalasi Stop Kontak 10,00 Titik Rp 505.775,00 Rp 5.057.750,00
3 Instalasi Stop Kontak AC 4,00 Titik Rp 505.775,00 Rp 2.023.100,00
4 Lampu Downlight LED 9 Watt 15,00 Bh Rp 433.375,00 Rp 6.500.625,00
5 Lampu Downlight LED 5 Watt 6,00 Bh Rp 402.830,00 Rp 2.416.980,00
6 Stop Kontak 10,00 Bh Rp 147.400,00 Rp 1.474.000,00
7 Stop Kontak AC 4,00 Bh Rp 181.225,00 Rp 724.900,00
8 Stop Kontak Lantai 1,00 Bh Rp 618.900,00 Rp 618.900,00
9 Saklar Tunggal 10,00 Bh Rp 126.900,00 Rp 1.269.000,00
10 Saklar Ganda 8,00 Bh Rp 137.150,00 Rp 1.097.200,00
SUB TOTAL E.1 Rp 33.980.605,00