PROGRESS KESIAPAN

INFRASTRUKTUR KELISTRIKAN
PON XX TAHUN 2021
PT PLN UP3 JAYAPURA
UIW PAPUA DAN PAPUA BARAT
Jayapura, 07 Juni 2021

MANAGER BAGIAN PERENCANAAN


MUSLIM SALAM
INFOGRAFIS VENUE PON WILAYAH KERJA UP3 JAYAPURA

KOTA JAYAPURA (UP3 JAYAPURA) : 28 VENUE


1.
2.
GOR Cenderawasih
Lapangan Baseball/Softball Uncen
: 41 CABOR
3. GOR Voli Indoor Koya Koso
4. GOR Voli Pasir Koya Koso
5. GOR Waringin
6. Teluk Youtefa
7. GOR Koya Timur
8. Pantai Hamadi
9. Lapangan Mahacandra
10. Teluk Yos Sudarso
11. Stadion Mandala
12. GOR Trikora Uncen
13. Arena Sepatu Roda Buper Waena
14.
15.
Lapangan Tenis Walikota Jayapura
Balai Pendidikan dan Pelatihan Penerbangan Jayapura
KABUPATEN JAYAPURA (UP3 JAYAPURA)
1. Lapangan MAF Doyo lama
16. Auditorium Uncen 2. Arena Akuatik Kawasan OR Kampung Harapan
3. Lapangan Baseball/Softball AURI
4. Lapangan Cricket & Hockey Kawasan OR Doyo Baru
5. Lapangan Tembak Kawasan OR Kampung Harapan
6. Lapangan menembak AURI
Progres Pekerjaan 90% 7. Stadion Bas Youwe
8. Istora Papua Bangkit Kawasan OR Kampung Harapan
9. Stadion Papua Bangkit
10. GOR STT GIDI Jayapura
11. GOR Toware
12. Bukit Mc Arthur

www.pln.co.id | 03
01. PROGRESS
01 REALISASIVENUE
KINERJA
RESUME PROGRESS PEMBANGUNAN PON XX UP3 JAYAPURA

No UP3 Venue Persentase No UP3 Venue Persentase


1 Jayapura Stadion Utama Papua Bangkit 100% 15 Jayapura Balai Latihan Kesehatan 100%
2 Jayapura Istora Papua Bangkit 100% 16 Jayapura Balai Latihan Penerbangan 100%
3 Jayapura Lapangan Tembak Kampung Harapan 90% 17 Jayapura Sepatu Roda Buper 70%
4 Jayapura Arena Aquatic 100% 18 Jayapura Teluk Youtefa 100%
5 Jayapura Gor Cendrawasih 100% 19 Jayapura Teluk Yos Sudarso 100%
6 Jayapura Gor Volley Koya 91% 20 Jayapura Pantai Hamadi 100%
7 Jayapura Gor Waringin 28% 21 Jayapura Gor Toware 100%
8 Jayapura Gor Koya Timur 100% 22 Jayapura Gor STT Gidi 100%
9 Jayapura Gor Trikora Uncen 75% 23 Jayapura Lapangan Tembak Auri 100%
10 Jayapura Baseball - Softball Uncen 98% 24 Jayapura Baseball - Softball AURI 100%
11 Jayapura Auditorium Uncen 75% 25 Jayapura Lapangan Cricket - Hockey 100%
12 Jayapura Stadion Mandala 90% 26 Jayapura MAF Doyo Lama 100%
13 Jayapura Lap. Mahacandra Waena 100% 27 Jayapura MAC Arthur Sentani 100%
14 Jayapura Lap. Tenis Kantor Walikota 100% 28 Jayapura Stadion Barnabas Youwe 100%
: 28 VENUE 29   TOTAL PROGRES 90%

: 41 CABANG OLAHRAGA
: Progres 90%

www.pln.co.id | 03
KAWASAN PAPUA BANGKIT

PROGRES
PEKERJAAN
GARDU
LAP. TEMBAK

GARDU
STADION INFRASTRUKTUR
KELISTRIKAN
GH
UTAMA

GARDU
AQUATIC SUDAH 80 %
GI GARDU
SENTANI ISTORA PLTD
WAENA
TARGET SELESAI M4 MARET 2021

TARGET SIMULASI M2 MEI 2021


• ACOS
• GENSET
• UPS

www.pln.co.id | 03
PROGRESS JOINTING SKTM – KAWASAN STADION LUKAS ENEMBE

Jointing GH Kawasan rencana di


kerjakan pada minggu 1 bulan Maret
(menunggu material tiba)

Jointing pertemuan SKTM Vanue


Istora – rencana maret minggu 1 di
eksekusi

Kontruksi sudah siap tinggal dan


sudah siap Connec SKTM akan tetapi
Energize Menunggu Jointing Istora
dan Terminasi L.Tembak selesai di
www.pln.co.id | 03
kerjakan
PROGRESS TERMINASI SKTM – KAWASAN STADION LUKAS ENEMBE

Upaya percepatan pembongkaran


jaringan SUTM dengan teriminasi 8
set untuk memanuver Inter 4 GI
Sentani pada minggu ke 2 Bulan
Maret

Minggu kedua bulan maret Energize

Rencana pindah Jaringan SUTM Inter


4 dan Cempaka menunggu kesiapan
SKTM Inter 4 di GH Kawasan dan L.
Tembak

Kontruksi sudah siap tinggal dan


sudah siap Connec SKTM akan tetapi
Energize Menunggu Jointing Istora
dan Terminasi L.Tembak selesai di
www.pln.co.id | 03
kerjakan
PROGRESS KABEL FIBER OPTIK – KAWASAN STADION LUKAS ENEMBE

BELUM TERPASANG

Panjang : 0.7 kms

SUDAH TERPASANG

Panjang : 1.5 kms

BOX ICON

Terpasang : 1 set

Belum Terpasang : 5 set

www.pln.co.id | 03
KAWASAN OR DOYO BARU

LBS PROGRES
THREE
WAYS
PEKERJAAN
INFRASTRUKTUR
GH GUNUNG
MERAH

GARDU HOCKEY
GARDU
KAWASAN
KELISTRIKAN
INDOOR OR
SUDAH 95 %

TARGET SIMULASI M2 APRIL 2021


• LBS THREE WAYS
• GENSET
GARDU
CRICKET • UPS
OUTDOOR

www.pln.co.id | 03
STADION LUKAS ENEMBE

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Stadion Utama
17 Jayapura 95%
Papua Bangkit
Kabel SKTM selesai di gelar
dan dalam progress
Netar, Kampung Harapan,
a Pembangunan SKTM 6.4 kms penyelesaian Jointing, 100%
Sentani
terminasi dan perakitan
kubikel
Netar, Kampung Harapan,
b Pembangunan GH 1 Pekerjaan Selesai 100%
Sentani
Netar, Kampung Harapan,
c Genset 4x500 kVA 4 Material Telah Tiba 100%
Sentani
Netar, Kampung Harapan,
d UPS 2 x 250 kVA 3 Material Telah Tiba 100%
Sentani
Netar, Kampung Harapan,
e ACO TM 1  Rapat Penjelasan 0% Proses Kontrak
Sentani
Netar, Kampung Harapan,
f UKKB 1 Material Telah Tiba 100%
Sentani

Persiapan Pekerjaan 20% Ren 10 10                               20%


    Real   10 5 5                           20%
Pelaksaanaan Pekerjaan 40% Ren     5 5 5 5 5 5 5 5               40%
    Real         10 10               40%
5 5 5 5
Finishing Pekerjaan 20% Ren               5 5 5 5             20%
    Real                     10 3 2 0       15%
Komisioning 15% Ren                     5 5 5         15%
    Real                                   0%
Tagihan 5% Ren                           5       5%
    Real                                   0%
Total 100% Ren 10% 20% 25% 30% 35% 40% 45% 55% 65% 75% 85% 90% 95% 100%       100%
    Real 0% 10% 15% 20% 25% 30% 35% 40% 50% 60% 70% 73% 75% 75%       75%

Ren Real Series3


www.pln.co.id | 03
ISTORA LUKAS ENEMBE

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

18 Jayapura Istora Papua Bangkit 73%

Kabel SKTM selesai di gelar


dan dalam progress
a Pembangunan SKTM Netar, Kampung Harapan, Sentani 2.1 kms penyelesaian Jointing, 80%
terminasi dan perakitan
kubikel

b Pembangunan GH Netar, Kampung Harapan, Sentani 1 Progress Pekerjaan 100%

c Genset 2x500 kVA Netar, Kampung Harapan, Sentani 2 Material Siap di Gunakan 100%

d UPS 2 x 250 kVA Netar, Kampung Harapan, Sentani 3 Material Siap di Gunakan 100%

e ACO TM Netar, Kampung Harapan, Sentani 1  Rapat Penjelasan 0%

f UKKB Netar, Kampung Harapan, Sentani 1 Material Siap di Gunakan 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren 10 10                               20%
    Real   10 5 5                           20%
Pelaksaanaan Pekerjaan 40% Ren     10 10 10 10                       40%
  Real         5 5 5 5 10 10               40%
Finishing Pekerjaan 20% Ren             10 10                   20%
    Real                     10 4 2 2 2     20%
Komisioning 15% Ren                 10 5               15%
    Real                                   0%
Tagihan 5% Ren                     5             5%
    Real                                   0%
Total 100% Ren 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100% 100%           100%
    Real 0% 10% 15% 20% 25% 30% 35% 40% 50% 60% 70% 74% 76% 78% 80%     80%

Ren Real
www.pln.co.id | 03
LAPANGAN TEMBAK INDOOR

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Lapangan Tembak
19 Jayapura 72%
Kampung Harapan
Kabel SKTM selesai di gelar
dan dalam progress
a Pembangunan SKTM Netar, Kampung Harapan, Sentani 3.96 kms penyelesaian Jointing, 75%
terminasi dan perakitan
kubikel

b Pembangunan GH Netar, Kampung Harapan, Sentani 1 Progress Pekerjaan 100%

c Genset 1x200 kVA Netar, Kampung Harapan, Sentani 1 Material Telah Tiba 100%

d UPS 1 x 100 kVA Netar, Kampung Harapan, Sentani 1 Material Telah Tiba 100%

e ACO TM Netar, Kampung Harapan, Sentani 1  Rapat Penjelasan 0%


GARDU INDUK SENTANI PLTD WAENA

TRF 1
20 MVA
TRF 3
30 MVA
TRF 1
30 MVA
f UKKB Netar, Kampung Harapan, Sentani 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren 10 10                               20%
GARDU
LAP. TEMBAK
GARDU
AQUATIC
    Real   10 5 5                           20%

G U G U
Pelaksaanaan Pekerjaan 40% Ren     5 5 5 5 5 5 5 5               40%
ACOS
400 A
ACOS
400 A
    Real         5 5 5 5 10 10               40%
Finishing Pekerjaan 20% Ren               5 5 5 5             20%

GARDU GARDU
    Real                     10 3 2 0       15%
STADION ISTORA
Komisioning 15% Ren                     5 5 5         15%
G U G U     Real                                   0%
ACOS
400 A
ACOS
400 A
Tagihan 5% Ren                           5       5%

ACO
    Real                                   0%
20 kV Total 100% Ren 10% 20% 25% 30% 35% 40% 45% 55% 65% 75% 85% 90% 95% 100%       100%
    Real 0% 10% 15% 20% 25% 30% 35% 40% 50% 60% 70% 73% 75% 75%       75%
GH UTAMA

Ren Real
www.pln.co.id | 03
AQUATIC

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

20 Jayapura Arena Aquatic 71%

Kabel SKTM selesai di gelar,


Jointing selesai, terminasi
a Pembangunan SKTM Netar, Kampung Harapan, Sentani 2.1 kms selesai dan minus finishing 85%
perakitan kubikel dan suplai
DC

b Genset 1x500 kVA Netar, Kampung Harapan, Sentani 1 Material Telah Tiba 100%

c UPS 1 x 250 kVA Netar, Kampung Harapan, Sentani 2 Material Telah Tiba 100%

GARDU INDUK SENTANI PLTD WAENA d ACO TM Netar, Kampung Harapan, Sentani 1  Rapat Penjelasan 0%
TRF 1 TRF 3 TRF 1
20 MVA 30 MVA 30 MVA

e UKKB Netar, Kampung Harapan, Sentani 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren 10 10                               20%
GARDU
LAP. TEMBAK
GARDU
AQUATIC
    Real   10 5 5                           20%

G U G U
Pelaksaanaan Pekerjaan 40% Ren     10 10 10 10                       40%
ACOS
400 A
ACOS
400 A
    Real         5 5 5 5 10 10               40%
Finishing Pekerjaan 20% Ren             10 10                   20%
    Real                     10 6 4         20%
GARDU
STADION
GARDU
ISTORA Komisioning 15% Ren                 10 5               15%
G U G U
    Real                           5       5%
ACOS ACOS
Tagihan 5% Ren                     5             5%
400 A 400 A
    Real                                   0%
ACO
Total 100% Ren 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100% 100% 100% 100%       100%
20 kV
    Real 0% 10% 15% 20% 25% 30% 35% 40% 50% 60% 70% 76% 80% 85%       85%

GH UTAMA

Ren Real

www.pln.co.id | 03
GOR CENDERAWASIH

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

1 Jayapura Gor Cendrawasih 100%

Selesai dan sudah siap


a Pembangunan SKTM Jalan Koti Depan Mall Jayapura 3 kms 100%
(Energize)
Material Telah Tiba dan Siap di
b Genset 1x500 kVA Jalan Koti Depan Mall Jayapura 1 100%
Gunakan
Material Telah Tiba dan Siap di
c UPS 1 x 250 kVA Jalan Koti Depan Mall Jayapura 1 100%
Gunakan

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren 5 5 5 5                           20%
    Real 5 5 5 5                           20%
Pelaksaanaan Pekerjaan 40% Ren         10 10 5 5 5 5               40%
    Real         5 10 10 10 5                 40%
Finishing Pekerjaan 20% Ren                     10 10           20%
    Real                   5 15             20%
Komisioning 15% Ren                         10 5       15%
    Real                       12 3         15%
Tagihan 5% Ren                             5     5%
    Real                         5         5%
Total 100% Ren 5% 10% 15% 20% 30% 40% 45% 50% 55% 60% 70% 80% 90% 95% 100%     100%
    Real 5% 10% 15% 20% 25% 35% 45% 55% 60% 65% 80% 92% 100%         100%

Ren Real

www.pln.co.id | 03
GOR VOLLEY INDOOR DAN VOLLEY PASIR

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
2 Jayapura Gor Volley Koya 91%
Kompleks Brimob
a Pembangunan SUTM 2,4 kms Pekerjaan Selesai 100%
Koya Kosso
Kompleks Brimob
b Pembangunan SKTM 0,3 kms Pekerjaan Selesai 100%
Koya Kosso
Kompleks Brimob Minus Penggantian CT dan
c Pembangunan KUBIKEL 1 50%
Koya Kosso Suplai DC
Kompleks Brimob
d Genset 1 x 500 kVA 1 Material Telah Tiba 100%
Koya Kosso
Kompleks Brimob
e UPS 2 x 250 kVA 3 Material Telah Tiba 100%
Koya Kosso
Kompleks Brimob
f ACO TM 1 Terpasang 100%
Koya Kosso
Kompleks Brimob
g UKKB 1 Material Telah Tiba 100%
Koya Kosso

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren   10 10                             20%
    Real   10 10                             20%
Pelaksaanaan Pekerjaan 40% Ren       10 10 10 5 5                   40%
    Real         5 5 5 5 5 5 10             40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                     5 5 5 5 0     20%
Komisioning 15% Ren                     5 10           15%
    Real                       5 6 0 0     11%
Tagihan 5% Ren                         5         5%
    Real                                   0%
Total 100% Ren 0% 10% 20% 30% 40% 50% 55% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 10% 20% 20% 25% 30% 35% 40% 45% 50% 65% 75% 86% 91% 91%     91%

Ren Real
www.pln.co.id | 03
GOR WARINGIN

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

3 Jayapura Gor Waringin 34%

a Genset 1x500 kVA Jalan Raya Abepura 1 Material Telah Tiba 100%

b UPS 1 x 100 kVA Jalan Raya Abepura 1 Material Telah Tiba 100%

c LBS Threeway Jalan Raya Abepura 1 0%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren               10 10                 20%
    Real               15 5                 20%
Pelaksaanaan Pekerjaan 40% Ren                   10 10 10 10         40%
    Real                   2 2 4 0 0 0     8%
Finishing Pekerjaan 20% Ren                         10 10       20%
    Real                                   0%
Komisioning 15% Ren                             10 5   15%
    Real                                   0%
Tagihan 5% Ren                                 5 5%
    Real                                   0%
Total 100% Ren 0% 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% 50% 70% 80% 90% 95% 100% 100%
    Real 0% 0% 0% 0% 0% 0% 0% 15% 20% 22% 24% 28% 28%         28%

Ren Real

www.pln.co.id | 03
GOR KOYA TIMUR

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
4 Jayapura Gor Koya Timur 72%
Jalan Raya Koya
a Pembangunan SUTM 0.1 kms Pekerjaan Selesai 100%
Timur
Jalan Raya Koya
b Pembangunan Gardu 1x100 kva Pekerjaan Selesai 100%
Timur
Jalan Raya Koya
c Genset 1x100 kVA 1 Material Telah Tiba 100%
Timur
Jalan Raya Koya
d UPS 1 x 100 kVA 1 Material Telah Tiba 100%
Timur
Jalan Raya Koya
e ACO TR 1  Rapat Penjelasan 0%
Timur

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren   10 10                             20%
    Real   10 10                             20%
Pelaksaanaan Pekerjaan 40% Ren       5 5 5 15 10                   40%
    Real       5 5 5 15 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     10 5           15%
    Real                   15               15%
Tagihan 5% Ren                         5         5%
    Real                     5             5%
Total 100% Ren 0% 10% 20% 25% 30% 35% 50% 60% 70% 80% 90% 95% 100%         100%
    Real 0% 10% 20% 25% 30% 35% 50% 60% 70% 95% 100% 100% 100%         100%

Ren Real
www.pln.co.id | 03
GOR TRIKORA UNCEN

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

5 Jayapura Gor Trikora Uncen 72%

SKTM sudah selesai dalam


Jalan Raya Abepura Samping Lap. tahap terminasi, pemindahan
a Pembangunan SKTM 0.1 75%
Trikora SUTM dan finishing perakitan
kubikel
Jalan Raya Abepura Samping Lap.
b Pembangunan GH 1 Selesai 100%
Trikora
Jalan Raya Abepura Samping Lap.
c Genset 1x100 kVA 1 Material Telah Tiba 100%
Trikora
Jalan Raya Abepura Samping Lap.
d UPS 1 x 100 kVA 1 Material Telah Tiba 100%
Trikora
Jalan Raya Abepura Samping Lap.
e ACO TR 1  Rapat Penjelasan 0%
Trikora
Jalan Raya Abepura Samping Lap.
f UGB 1 Material Telah Tiba 100%
Trikora

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 5 5                       20%
    Real       10 5 5                       20%
Pelaksaanaan Pekerjaan 40% Ren             10 10 10 10               40%
    Real               10 10 10 10             40%
Finishing Pekerjaan 20% Ren                     10 10           20%
    Real                     10 8           18%
Komisioning 15% Ren                         10 5       15%
    Real                                   0%
Tagihan 5% Ren                             5     5%
    Real                                   0%
Total 100% Ren 0% 0% 0% 10% 15% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%     100%
    Real 0% 0% 0% 10% 15% 20% 20% 30% 40% 50% 70% 78% 78%         78%

Ren Real
www.pln.co.id | 03
AUDITORIUM UNCEN

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

7 Jayapura Auditorium Uncen 90%

a Pembangunan Gardu Jalan Raya Abepura 1x200 kva Progress Pekerjaan 78%

b Genset 1x200 kVA Jalan Raya Abepura 1 Material Telah Tiba 100%

c UPS 1 x 250 kVA Jalan Raya Abepura 1 Material Telah Tiba 100%

d UGB Jalan Raya Abepura 1 Material Telah Tiba 100%

Persiapan Pekerjaan 20% Ren       10 5 5                       20%


    Real       10 5 5                       20%
Pelaksaanaan 40% Ren             10 10 10 10               40%
Pekerjaan
    Real               10 10 10 10             40%

Finishing Pekerjaan 20% Ren                     10 10           20%


    Real                     10 8           18%
Komisioning 15% Ren                         10 5       15%
    Real                                   0%
Tagihan 5% Ren                             5     5%
    Real                                   0%
Total 100% Ren 0% 0% 0% 10% 15% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100% 100%   100%
    Real 0% 0% 0% 10% 15% 20% 20% 30% 40% 50% 70% 78% 78%         78%

Ren Real

www.pln.co.id | 03
STADION MANDALA

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

8 Jayapura Stadion Mandala 56%

Menunggu Trafo Stepdown


a Pembangunan SUTM Jalan Raya Abepura 0.36 45%
dari GH GOR Cendrawasih
Jalan Sulawesi
b Genset 1x500 kVA 1 Material Telah Tiba 100%
Jayapura Utara
Jalan Sulawesi
c UPS 1 x 250 kVA 1 Material Telah Tiba 100%
Jayapura Utara
Jalan Sulawesi
d ACO TM 1  Rapat Penjelasan 0%
Jayapura Utara
Jalan Sulawesi
e UGB 1 Material Telah Tiba 100%
Jayapura Utara

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren   5 5 5 5                         20%
    Real   5 5 - - - - 5 5                 20%
Pelaksaanaan Pekerjaan 40% Ren           10 10 5 5 5 5             40%
    Real           - - 5 5 10 10 8           38%
Finishing Pekerjaan 20% Ren                       10 10         20%
    Real                                   0%
Komisioning 15% Ren                           10 5     15%
    Real                                   0%
Tagihan 5% Ren                               5   5%
    Real                                   0%
Total 100% Ren 0% 5% 10% 15% 20% 30% 40% 45% 50% 55% 60% 70% 80% 90% 95% 100%   100%
    Real 0% 5% 10% 10% 10% 10% 10% 20% 30% 40% 50% 58% 58%         58%

Ren Real
www.pln.co.id | 03
BASEBALL / SOFTBALL UNCEN ATAS

Venue dan Jenis


No UP3 Volume Progress Pekerjaan Persentase
Pekerjaan
Baseball - Softball
6 Jayapura 65%
Uncen
Dalam progress
a Pembangunan SUTM 2.00 kms 40%
pekerjaan
Dalam progress
b Pembangunan Gardu 1x250 kva 40%
pekerjaan

c Genset 1x200 kVA 1 Material Telah Tiba 100%

d UGB 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 5 5                      20%
    Real       - 5 5 5 5                   20%
Pelaksaanaan Pekerjaan 40% Ren             10 10 10 10               40%
    Real             - 10 10 10 10             40%
Finishing Pekerjaan 20% Ren                     10 10           20%
    Real                       5           5%
Komisioning 15% Ren                         10 5       15%
    Real                                   0%
Tagihan 5% Ren                             5     5%
    Real                                   0%
Total 100% Ren 0% 0% 0% 10% 15% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%     100%
    Real 0% 0% 0% 0% 5% 10% 15% 30% 40% 50% 60% 65% 65%         65%

Ren Real
www.pln.co.id | 03
LAPANGAN MAHACANDRA

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Lap. Mahacandra
9 Jayapura 69%
Waena
a Pembangunan JTM 0.18 kms Selesai 100%

b Pembangunan Gardu 1 unit Selesai 100%

c Genset 1x100 kVA Belakang Fakultas MIPA Uncen 1 Material Telah Tiba 100%

d ACO TR Belakang Fakultas MIPA Uncen 1  Rapat Penjelasan 0%

e UGB Belakang Fakultas MIPA Uncen 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 10                         20%
    Real       10 10                         20%
Pelaksaanaan Pekerjaan 40% Ren           10 10 10 10                 40%
    Real           10 10 10 10                 40%
Finishing Pekerjaan 20% Ren                   10 10             20%
    Real                   5 15             20%
Komisioning 15% Ren                       10 5         15%
    Real                       15           15%
Tagihan 5% Ren                           5       5%
    Real                       5           5%
Total 100% Ren 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%       100%
    Real 0% 0% 0% 10% 20% 30% 40% 50% 60% 65% 80% 100% 100%         100%

Ren Real
www.pln.co.id | 03
LAP. TENNIS WONDA LAMBU

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Lap. Tenis Kantor
10 Jayapura 72%
Walikota
Selesai dan sudah operasi dan
a Pembangunan SKTM Jalan Kantor Walikota 0.175 kms 100%
sudah menjadi pelanggan PLN

b Genset 1x500 kVA Jalan Kantor Walikota 1 Material Telah Tiba 100%

c UPS 1 x 250 kVA Jalan Kantor Walikota 1 Material Telah Tiba 100%

d LBS Threeway Jalan Kantor Walikota 1 0%

e UGB Jalan Kantor Walikota 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren   10 10                             20%
    Real   10 10                             20%
Pelaksaanaan Pekerjaan 40% Ren       10 10 10 10                     40%
    Real       10 5 5 10 5 5                 40%
Finishing Pekerjaan 20% Ren               10 10                 20%
    Real                 5 15               20%
Komisioning 15% Ren                   5 10             15%
    Real                     5 10           15%
Tagihan 5% Ren                       5           5%
    Real                       5           5%
Total 100% Ren 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%           100%
    Real 0% 10% 20% 30% 35% 40% 50% 55% 65% 80% 85% 100% 100%         100%

Ren Real
www.pln.co.id | 03
BALAI LATIHAN KESEHATAN

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

Balai Latihan
11 Jayapura 58%
Kesehatan

Kompleks Poltekkes
a Genset 1x200 kVA 1 Material Telah Tiba 100%
Padang Bulan

Kompleks Poltekkes
b ACO TR 1  Rapat Penjelasan 0%
Padang Bulan

Kompleks Poltekkes
c UGB 1 Material Telah Tiba 100%
Padang Bulan

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       5 5 5 5                     20%
    Real       5 5 5 5                     20%
Pelaksaanaan Pekerjaan 40% Ren               10 10 10 10             40%
    Real               10 30                 40%
Finishing Pekerjaan 20% Ren                       10 10         20%
    Real                 10 10               20%
Komisioning 15% Ren                           5 10     15%
    Real                   15               15%
Tagihan 5% Ren                               5   5%
    Real                   5               5%
Total 100% Ren 0% 0% 0% 5% 10% 15% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%   100%
    Real 0% 0% 0% 5% 10% 15% 20% 30% 70% 100% 100% 100%           100%

Ren Real
www.pln.co.id | 03
BALAI LATIHAN PENERBANGAN

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

Balai Latihan
12 Jayapura 60%
Penerbangan
Jalan Kayubatu
Proses Pengiriman (Etd
a Genset 1x1000 kVA Deplat, DOK IX, 1 100%
Oktober 2020)
Base-G Jayapura
Jalan Kayubatu
b UPS 1 x 250 kVA Deplat, DOK IX, 1 Material Telah Tiba 100%
Base-G Jayapura
Jalan Kayubatu
c LBS Threeway Deplat, DOK IX, 1  Rapat Penjelasan 0%
Base-G Jayapura
Jalan Kayubatu
d UGB Deplat, DOK IX, 1 Material Telah Tiba 100%
Base-G Jayapura

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       5 5 5 5                     20%
    Real       5 5 5 5                     20%
Pelaksaanaan Pekerjaan 40% Ren               10 10 10 10             40%
    Real               10 10 10 10             40%
Finishing Pekerjaan 20% Ren                       10 10         20%
    Real                     20             20%
Komisioning 15% Ren                           5 10     15%
    Real                     15             15%
Tagihan 5% Ren                               5   5%
    Real                     5             5%
Total 100% Ren 0% 0% 0% 5% 10% 15% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%   100%
    Real 0% 0% 0% 5% 10% 15% 20% 30% 40% 50% 100% 100% 100%         100%

Ren Real

www.pln.co.id | 03
VENUE SEPATU RODA BUPER

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

13 Jayapura Sepatu Roda Buper 56%

SUTM sudah selesai, SKTM on


Pembangunan SUTM,
a 0.5 kms progress, kubikel menunggu 51%
SKTM dan Kubikel
Gardu selesai dibangun

b Genset 1x200 kVA Jalan Masuk IPDN Buper Waena 1 Material Telah Tiba 100%

c ACO TR Jalan Masuk IPDN Buper Waena 1  Rapat Penjelasan 0%

d UGB Jalan Masuk IPDN Buper Waena 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       5 5 5 5                    20%
    Real           5 5 5 5                 20%
Pelaksaanaan Pekerjaan 40% Ren               10 10 10 10             40%
    Real               10 10 3 3             26%
Finishing Pekerjaan 20% Ren                       10 10         20%
    Real                       5           5%
Komisioning 15% Ren                           5 10     15%
    Real                                   0%
Tagihan 5% Ren                               5   5%
    Real                                   0%
Total 100% Ren 0% 0% 0% 5% 10% 15% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%   100%
    Real 0% 0% 0% 0% 0% 5% 10% 25% 40% 43% 46% 51% 51% 51% 51%     51%

Ren Real

www.pln.co.id | 03
TELUK YOUTEFA

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'2 Nov'2 Mar'2


0 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 0 Des'20 Jan'21 Feb'21 1 Apr'21 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%
    Real -   10 10                           20%
Pelaksaanaan
Pekerjaan 40% Ren         10 10 10 10                   40%
    Real         10 10 10 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     5 10           15%
    Real                     15             15%
Tagihan 5% Ren                         5         5%
    Real                       5           5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 95% 100% 100%         100%

Ren Real
www.pln.co.id | 03
TELUK YOS SUDARSO

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%
    Real -   10 10                           20%
Pelaksaanaan Pekerjaan 40% Ren         10 10 10 10                   40%
    Real         10 10 10 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     5 10           15%
    Real                     15             15%
Tagihan 5% Ren                         5         5%
    Real                       5           5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 95% 100% 100%         100%

Ren Real
www.pln.co.id | 03
PANTAI HAMADI

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%
    Real -   10 10                           20%
Pelaksaanaan Pekerjaan 40% Ren         10 10 10 10                   40%
    Real         10 10 10 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     5 10           15%
    Real                     15             15%
Tagihan 5% Ren                         5         5%
    Real                       5           5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 95% 100% 100%         100%

Ren Real
www.pln.co.id | 03
GOR TOWARE

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase Kendala
Pekerjaan

21 Jayapura Gor Toware 64%

Jalan Masuk Pertigaan samping


a Pembangunan Gardu 1x250 kva On Progress 100%
Bukit Teletubbies, Waibu, Sentani
Jalan Masuk Pertigaan samping
b Pembangunan JTR 0.2 kms On Progress 100%
Bukit Teletubbies, Waibu, Sentani
Jalan Masuk Pertigaan samping
c Genset 1x100 kVA 1 Material Telah Tiba 100%
Bukit Teletubbies, Waibu, Sentani
Jalan Masuk Pertigaan samping
d UPS 1 x 100 kVA 1 Material Telah Tiba 100%
Bukit Teletubbies, Waibu, Sentani
Jalan Masuk Pertigaan samping
g UGB 1 Material Telah Tiba 100%
Bukit Teletubbies, Waibu, Sentani

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%
    Real         5 5 5 5                   20%
Pelaksaanaan Pekerjaan 40% Ren         10 10 10 10                   40%
    Real                   10 10 10 5 2 3     40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                           10 10     20%
Komisioning 15% Ren                     10 5           15%
    Real                             10 5   15%
Tagihan 5% Ren                         5         5%
    Real                               5   5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%         100%
    Real 0% 0% 0% 0% 5% 10% 15% 20%
Ren 20% Real
30% 40% 50% 55% 67% 90% 100% 100% 100%

www.pln.co.id | 03
GOR STT GIDI SENTANI

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan

22 Jayapura Gor STT Gidi 82%

a Pembangunan SKTM Jl. Raya Kemiri, Hinekombe, Sentani 0.4 kms Selesai 100%

b Pembangunan Gardu Jl. Raya Kemiri, Hinekombe, Sentani 1x250 kva Selesai 100%

c Pembangunan JTR Jl. Raya Kemiri, Hinekombe, Sentani 0.24 kms Selesai 100%

d Genset 1x200 kVA Jl. Raya Kemiri, Hinekombe, Sentani 1 Selesai 100%

e UPS 1 x 100 kVA Jl. Raya Kemiri, Hinekombe, Sentani 2 Selesai 100%

f ACO TR Jl. Raya Kemiri, Hinekombe, Sentani 1  Rapat Penjelasan 0%

g UGB Jl. Raya Kemiri, Hinekombe, Sentani 1 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren         10 10                       20%
    Real         10 10                       20%
Pelaksaanaan Pekerjaan 40% Ren             10 10 10 10               40%
    Real             10 10 10 10               40%
Finishing Pekerjaan 20% Ren                     10 10           20%
    Real                     10 6 4         20%
Komisioning 15% Ren                         10 5       15%
    Real                         12 3      15%
Tagihan 5% Ren                             5     5%
    Real                             5    5%
Total 100% Ren 0% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%     100%
    Real 0% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 76% 92% 95% 100%     100%

Ren Real

www.pln.co.id | 03
LAPANGAN MENEMBAK AURI SENTANI

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
23 Jayapura Lapangan Tembak Auri 78%
Jalan Raya Sentani - Genyem
a Pembangunan SUTM 0.25 kms Pekerjaan Selesai 100%
Kompleks AURI, Sentani
Jalan Raya Sentani - Genyem
b Pembangunan Gardu 1x200 kva Pekerjaan Selesai 100%
Kompleks AURI, Sentani
Jalan Raya Sentani - Genyem
c Genset 1x200 kVA 1 Material Telah Tiba 100%
Kompleks AURI, Sentani
Jalan Raya Sentani - Genyem
d UPS 1 x 100 kVA 1 Material Telah Tiba 100%
Kompleks AURI, Sentani
Jalan Raya Sentani - Genyem
e ACO TR 1 Pembukaan Sampul 1 0%
Kompleks AURI, Sentani
Jalan Raya Sentani - Genyem
f UGB 1 Material Telah Tiba 100%
Kompleks AURI, Sentani

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 10                         20%
    Real       10 10                         20%
Pelaksaanaan Pekerjaan 40% Ren           10 10 10 10                 40%
    Real           10 10 10 10                 40%
Finishing Pekerjaan 20% Ren                   10 10             20%
    Real                   10 10             20%
Komisioning 15% Ren                       10 5         15%
    Real                     15             15%
Tagihan 5% Ren                           5       5%
    Real                     5             5%
Total 100% Ren 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%       100%
    Real 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 100% 100% 100%         100%

Ren Real
www.pln.co.id | 03
SOFTBALL / BASEBALL AURI

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
24 Jayapura Baseball - Softball AURI 100%

a Pembangunan SUTM Kompleks AURI, Sentani 0.05 kms Selesai 100%

b Pembangunan SKTM Kompleks AURI, Sentani 0.275 kms Selesai 100%

c Pembangunan Gardu Kompleks AURI, Sentani 1x250 kVA Selesai 100%

d Genset 1x200 kVA Kompleks AURI, Sentani 1 Material Telah Tiba 100%

e UPS 1 x 100 kVA Kompleks AURI, Sentani 2 Material Telah Tiba 100%

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 10                         20%
    Real       10 10                         20%
Pelaksaanaan Pekerjaan 40% Ren           10 10 10 10                 40%
    Real           5 5 10 10 10               40%
Finishing Pekerjaan 20% Ren                   10 10             20%
    Real                   10 10             20%
Komisioning 15% Ren                       10 5         15%
    Real                       11 4         15%
Tagihan 5% Ren                           5       5%
    Real                         5         5%
Total 100% Ren 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%       100%
    Real 0% 0% 0% 10% 20% 25% 30% 40% 50% 70% 80% 91% 100%         100%

Ren Real

www.pln.co.id | 03
CRICKET – HOCKEY DOYO BARU

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Lapangan Cricket -
25 Jayapura 98%
Hockey
Genset 2x500 kVA dan Kompleks Sekolah Penerbangan
a 3 Material Telah Tiba 100%
1 x 100 kVA Doyo Baru
Kompleks Sekolah Penerbangan
b UPS 2 x 250 kVA 3 Material Telah Tiba 100%
Doyo Baru
Kompleks Sekolah Penerbangan
c LBS THREE WAYS 1 Material Telah Terpasang 95%
Doyo Baru
Kompleks Sekolah Penerbangan
d UKKB 1 Material Telah Tiba 100%
Doyo Baru
Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren       10 10                         20%
    Real       10 10                         20%
Pelaksaanaan Pekerjaan 40% Ren           10 10 10 10                 40%
    Real           10 5 5 5 5 5 5           40%
Finishing Pekerjaan 20% Ren                   10 10             20%
    Real                     10 10           20%
Komisioning 15% Ren                       10 5         15%
    Real                         12 3       15%
Tagihan 5% Ren                           5       5%
    Real                             5     5%
Total 100% Ren 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%       100%
    Real 0% 0% 0% 10% 20% 30% 35% 40% 45% 50% 65% 80% 92% 95% 100%     100%

Ren Real
www.pln.co.id | 03
MAF DOYO LAMA

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
26 Jayapura MAF Doyo Lama 100%
Kompleks Bandara Adventist
a Genset 1x100 kVA 1 Material Telah Tiba 100%
Aviation Sentani
Kompleks Bandara Adventist
b UKKB 1 Material Telah Tiba 100%
Aviation Sentani

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%

    Real -   10 10                           20%

Pelaksaanaan Pekerjaan 40% Ren         10 10 10 10                   40%


    Real         10 10 10 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     5 10           15%
    Real                     15             15%
Tagihan 5% Ren                         5         5%
    Real                       5           5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 95% 100% 100%         100%

www.pln.co.id | 03
BUKIT MAC ARTHUR

Jan'2 Feb'2 Mar'2 Apr'2 Mei'2 Jun'2 Agst'2 Sep'2 Okt'2 Nov'2 Des'2 Jan'2 Feb'2 Mar'2 Apr'2
Uraian Pekerjaan Bobot   Des'19 0 0 0 0 0 0 Jul'20 0 0 0 0 0 1 1 1 1 Total
Persiapan Pekerjaan 20% Ren     10 10                           20%
    Real -   10 10                           20%
Pelaksaanaan
Pekerjaan
40% Ren       10 10 10 10                   40%
    Real         10 10 10 10                   40%
Finishing Pekerjaan 20% Ren                 10 10               20%
    Real                 10 10               20%
Komisioning 15% Ren                     5 10           15%
    Real                     15             15%
Tagihan 5% Ren                         5         5%
    Real                       5           5%
Total 100% Ren 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 85% 95% 100%         100%
    Real 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 95% 100% 100%         100%

Ren Real
www.pln.co.id | 03
STADION BARNABAS YOUWE

Venue dan Jenis


No UP3 Lokasi Volume Progress Pekerjaan Persentase
Pekerjaan
Stadion Barnabas
28 Jayapura 100%
Youwe
Jalan Masuk Depan Papua Mart,
a Pembangunan SKTM 0.15 kms Penanaman Kabel 100%
Sentani
Jalan Masuk Depan Papua Mart,
b Genset 1x250 kVA 1 Material Telah Tiba 100%
Sentani
Jalan Masuk Depan Papua Mart,
c UPS 1 x 100 kVA 2 Material Telah Tiba 100%
Sentani

Uraian Pekerjaan Bobot   Des'19 Jan'20 Feb'20 Mar'20 Apr'20 Mei'20 Jun'20 Jul'20 Agst'20 Sep'20 Okt'20 Nov'20 Des'20 Jan'21 Feb'21 Mar'21 Apr'21 Total
Persiapan Pekerjaan 20% Ren   10 10                             20%
    Real - 5 5 5 5                         20%
Pelaksaanaan Pekerjaan 40% Ren       10 10 10 10                     40%
    Real           10 15 15                   40%
Finishing Pekerjaan 20% Ren               10 10                 20%
    Real                 15 5               20%
Komisioning 15% Ren                   10 5             15%
    Real                   10 5             15%
Tagihan 5% Ren                       5           5%
    Real                         5         5%
Total 100% Ren 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 95% 100%           100%
    Real 0% 5% 10% 15% 20% 30% 45% 60% 75% 90% 95% 95% 100%         100%

Ren Real
www.pln.co.id | 03
02. TIMELINE SLO
01 REALISASI KINERJA
TIMELINE RENCANA SLO KELISTRIKAN PENDUKUNG PON UP3 JAYAPURA

MARET APRIL MEI JUNI


NO LOKASI JENIS SLO PROGRESS (%) KETERANGAN
M3 M4 M1 M2 M3 M4 M1 M2 M3 M4 M1 M2 M3 M4
1 Stadion Utama Papua Bangkit PHBTM 75
2 Istora Papua Bangkit PHBTM 80
3 Lapangan Tembak Kampung Harapan PHBTM 75
4 Arena Aquatic PHBTM 80
5 Gor Cendrawasih PHBTM 100
6 Gor Volley Koya PHBTM 91
7 Gor Waringin 28
8 Gor Koya Timur PHBTR 100
9 Gor Trikora Uncen PHBTM 75
10 Baseball - Softball Uncen PHBTR 65
11 Auditorium Uncen PHBTR 78
12 Stadion Mandala PHBTM 64
13 Lap. Mahacandra Waena PHBTR 100
14 Lap. Tenis Kantor Walikota PHBTM 100 OK
15 Balai Latihan Kesehatan PHBTR 100
16 Balai Latihan Penerbangan PHBTM 100
17 Sepatu Roda Buper PHBTM 51
18 Teluk Youtefa 100
19 Teluk Yos Sudarso 100
20 Pantai Hamadi 100
21 Gor Toware PHBTR 60
22 Gor STT Gidi PHBTR 100
23 Lapangan Tembak Auri PHBTR 100
24 Baseball - Softball AURI PHBTR 100
25 Lapangan Cricket - Hockey PHBTM 100
26 MAF Doyo Lama 100
27 MAC Arthur Sentani 100
28 Stadion Barnabas Youwe PHBTM 100
29 Command Center POLDA PAPUA PHBTR 100
30 Wisma Atlit Lap. Mandala PHBTM 100 OK (PENDING ITEM)
31 Wisma Atlit Kotaraja Dalam PHBTR 100
32 Wisma Atlit 1 Doyo PHBTR 100
33 Wisma Atlit 1 Koya Brimob PHBTR 100
34 Wisma Atlit 2 Koya Brimob PHBTR 100

www.pln.co.id | 03