Perhitungan Jumlah Jam Kerja

NO TANK DATA INPUT KAPASITAS TANGKI (M3) , DIAMETER/TINGGI (M)

500 1000 1500 2000 2000 2500 2500 5000 5000 7500 10000 10000 15000 15000 20000 20000
I Fabrikasi
1. Cutting, Marking, Grinding &
Bevelling 43 71 89 110 123 134 145 248 286 288 351 327 506 460 597 621
3. Manhole Fabrication 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Total Hari Kerja Fabrikasi 45 75 93 114 127 138 149 252 290 292 355 331 510 464 601 625
Total Hari Kerja Fabrikasi (Tim) 11 19 19 23 25 28 30 32 36 37 44 41 43 39 40 42

II Ereksi Tangki
1. Pemasangan &
Pembongkaran Scafolding 18 37 44 48 47 54 53 80 74 98 110 119 133 140 160 153
2. Penyusunan & Las Pelat Dasar 5 7 10 13 17 17 20 34 39 51 64 57 94 78 103 121
3. Penyusunan & Las Pelat Dinding 30 59 67 76 71 91 73 153 142 231 344 405 455 583 749 645
4. Pemasangan & Las Top Angle 1 1 1 1 2 2 3 5 6 6 7 7 9 8 9 10
5. Pengelasan Dinding ke Dasar 8 10 11 14 15 15 17 31 33 57 64 60 152 139 159 173
6. Pemasangan Struktur Atap 8 9 11 12 15 15 17 26 46 52 58 55 122 101 127 154
7. Pemasangan & Las Pelat atap 2 3 4 5 7 7 8 15 17 19 23 21 34 30 40 42
8. Pemasangan Nozzle/Manhole 11 16 16 16 16 16 16 17 17 18 18 18 18 18 19 19
9. Pemasangan Water/ Product Drain 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4 4
10. Pemasangan Tangga & Handrail 6 6 7 8 8 8 9 11 11 13 14 13 16 15 17 18
Total Hari Kerja Ereksi 91 150 173 195 200 227 218 375 388 548 706 759 1037 1116 1387 1339
Total Hari Kerja Ereksi (Tim) 23 38 35 39 40 45 44 47 49 69 88 95 86 93 92 89

III Uji Tangki


1. Uji Radiografi (RT) 2 2 2 3 3 3 4 10 6 12 10 17 33 31 42 33
2. Uji PT utk nozzle/manhole 6 9 9 9 9 9 9 9 10 10 10 10 10 10 11 11
2. Uji Vacuum Box 1 1 2 2 2 2 3 4 5 5 7 6 10 8 11 12
3. Uji Tekanan/Pressure 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4 4
4. Uji PT utk lasan Dinding-Dasar 2 3 3 3 4 4 4 5 6 6 7 7 8 8 9 9
6. Uji Hidrostatis 4 6 6 6 5 6 5 6 5 7 7 7 8 8 9 8
Total Hari Kerja Uji Tangki 17 23 24 25 25 26 27 37 35 43 45 51 73 69 86 77
Total Hari Kerja Uji Tangki (Tim) 4 6 5 5 5 5 5 5 4 5 6 6 6 6 6 5

IV Pengecetan Tangki
1. Surface Preparation 7 11 14 17 18 20 21 33 37 48 58 56 84 75 94 103
2. Pengecetan Pelat Dinding 5 6 6 7 7 7 7 9 8 10 11 11 12 13 14 13
3. Pengecatan Pelat Atap 4 4 4 4 5 5 5 6 6 7 8 7 10 9 10 12
4. Pengecatan Pelat Dasar 9 10 10 10 10 11 10 12 11 13 14 14 16 15 18 17
5. Pengecatan struktur Atap 6 6 7 7 8 8 9 12 18 20 22 21 43 36 45 53
6. Penegecatan Tangga & Handrail 4 4 4 4 5 5 5 5 5 5 5 5 6 6 6 6
Total Hari Kerja Pengecetan Tangki 35 41 45 49 53 56 57 77 85 103 118 114 171 154 187 204
Total Hari Kerja Pengecetan Tangki (Tim) 9 10 9 10 11 11 11 10 11 13 15 14 14 13 12 14

V Total Hari Kerja (1 team) 379.25 599 683 783.8 827.4 916.2 923.8 1488 1600.125 1979.375 2468.25 2538.625 3546 3589.4166667 4473.26666667 4422.0666667
Total Hari Kerja 95 150 137 157 165 183 185 186 200 247 309 317 296 299 298 295

Note : Tangki 1 - 2 (4 tim), tangki 3 - 7 (5 tim), tangki 8 - 12 (8 tim), tangki 13 - 14 (12 tim), tangki 15 - 16 (15 tim)

Sewa Peralatan

II Fabrikasi Tangki
Mesin Las/Potong (450.000) 5,062,500 8,437,500 8,370,000 10,260,000 11,430,000 12,420,000 13,410,000 14,175,000 16,312,500 16,425,000 19,968,750 18,618,750 19,125,000 17,400,000 18,030,000 18,750,000
Sewa
Mesin Gerinda Mesin Las/Potong per hari: Rp.2,812,500
(250.000) 320.000 4,687,500 4,650,000 5,700,000 6,350,000 6,900,000 7,450,000 7,875,000 9,062,500 9,125,000 11,093,750 10,343,750 10,625,000 9,666,667 10,016,667 10,416,667
Sewa Mesin Gerinda per hari: Rp. 150.000
Mesin Rol (450.000) 2,531,250 4,218,750 4,185,000 5,130,000 5,715,000 6,210,000 6,705,000 7,087,500 8,156,250 8,212,500 9,984,375 9,309,375 9,562,500 8,700,000 9,015,000 9,375,000
TOTAL SEWA ALAT FABRIKASI 10,406,250 17,343,750 17,205,000 21,090,000 23,495,000 25,530,000 27,565,000 29,137,500 33,531,250 33,762,500 41,046,875 38,271,875 39,312,500 35,766,667 37,061,667 38,541,667

II Ereksi Tangki
Crane + Operator (500.000) 11,375,000 18,750,000 17,300,000 19,500,000 20,000,000 22,700,000 21,800,000 23,437,500 24,250,000 34,250,000 44,125,000 47,437,500 43,208,333 46,500,000 46,233,333 44,633,333
Scaffolding (250.000) 5,687,500 9,375,000 8,650,000 9,750,000 10,000,000 11,350,000 10,900,000 11,718,750 12,125,000 17,125,000 22,062,500 23,718,750 21,604,167 23,250,000 23,116,667 22,316,667
Mesin Las (450.000) 10,237,500 16,875,000 15,570,000 17,550,000 18,000,000 20,430,000 19,620,000 21,093,750 21,825,000 30,825,000 39,712,500 42,693,750 38,887,500 41,850,000 41,610,000 40,170,000
Genset (450.000) 10,237,500 16,875,000 15,570,000 17,550,000 18,000,000 20,430,000 19,620,000 21,093,750 21,825,000 30,825,000 39,712,500 42,693,750 38,887,500 41,850,000 41,610,000 40,170,000
Peralatan Lainnya (300.000) 6,825,000 11,250,000 10,380,000 11,700,000 12,000,000 13,620,000 13,080,000 14,062,500 14,550,000 20,550,000 26,475,000 28,462,500 25,925,000 27,900,000 27,740,000 26,780,000
TOTAL SEWA ALAT EREKSI 44,362,500 73,125,000 67,470,000 76,050,000 78,000,000 88,530,000 85,020,000 91,406,250 94,575,000 133,575,000 172,087,500 185,006,250 168,512,500 181,350,000 180,310,000 174,070,000

IV Pengecetan Tangki
Scaffolding (250.000) 2,187,500 2,562,500 2,250,000 2,450,000 2,650,000 2,800,000 2,850,000 2,406,250 2,656,250 3,218,750 3,687,500 3,562,500 3,562,500 3,208,333 3,116,667 3,400,000

V TOTAL 56,956,250 93,031,250 86,925,000 99,590,000 104,145,000 116,860,000 115,435,000 122,950,000 130,762,500 170,556,250 216,821,875 226,840,625 211,387,500 220,325,000 220,488,333 216,011,667

Catatan:
Mesin Roll dipakai 1/2 hari kerja fabrikasi
Perhitungan Jumlah Jam Kerja

NO TANK DATA INPUT KAPASITAS TANGKI (M3) , DIAMETER/TINGGI (M)


500 1000 1500 2000 2000 2500 2500 5000 5000 7500 10000 10000 15000 15000 20000
I Fabrikasi
1. Cutting, Marking, Grinding &
Bevelling 43 71 89 110 123 134 145 248 286 288 351 327 506 460 597
3. Manhole Fabrication 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Total Hari Kerja Fabrikasi 45 75 93 114 127 138 149 252 290 292 355 331 510 464 601

II Ereksi Tangki
1. Pemasangan &
Pembongkaran Scafolding 18 37 44 48 47 54 53 80 74 98 110 119 133 140 160
2. Penyusunan & Las Pelat Dasar 5 7 10 13 17 17 20 34 39 51 64 57 94 78 103
3. Penyusunan & Las Pelat Dinding 30 59 67 76 71 91 73 153 142 231 344 405 455 583 749
4. Pemasangan & Las Top Angle 1 1 1 1 2 2 3 5 6 6 7 7 9 8 9
5. Pengelasan Dinding ke Dasar 8 10 11 14 15 15 17 31 33 57 64 60 152 139 159
6. Pemasangan Struktur Atap 8 9 11 12 15 15 17 26 46 52 58 55 122 101 127
7. Pemasangan & Las Pelat atap 2 3 4 5 7 7 8 15 17 19 23 21 34 30 40
8. Pemasangan Nozzle/Manhole 11 16 16 16 16 16 16 17 17 18 18 18 18 18 19
9. Pemasangan Water/ Product Drain 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4
10. Pemasangan Tangga & Handrail 6 6 7 8 8 8 9 11 11 13 14 13 16 15 17
Total Hari Kerja Ereksi 91 150 173 195 200 227 218 375 388 548 706 759 1037 1116 1387

III Uji Tangki


1. Uji Radiografi (RT) 2 2 2 3 3 3 4 10 6 12 10 17 33 31 42
2. Uji PT utk nozzle/manhole 6 9 9 9 9 9 9 9 10 10 10 10 10 10 11
2. Uji Vacuum Box 1 1 2 2 2 2 3 4 5 5 7 6 10 8 11
3. Uji Tekanan/Pressure 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4
4. Uji PT utk lasan Dinding-Dasar 2 3 3 3 4 4 4 5 6 6 7 7 8 8 9
6. Uji Hidrostatis 4 6 6 6 5 6 5 6 5 7 7 7 8 8 9
Total Hari Kerja Uji Tangki 17 23 24 25 25 26 27 37 35 43 45 51 73 69 86

IV Pengecetan Tangki
1. Surface Preparation 7 11 14 17 18 20 21 33 37 48 58 56 84 75 94
2. Pengecetan Pelat Dinding 5 6 6 7 7 7 7 9 8 10 11 11 12 13 14
3. Pengecatan Pelat Atap 4 4 4 4 5 5 5 6 6 7 8 7 10 9 10
4. Pengecatan Pelat Dasar 9 10 10 10 10 11 10 12 11 13 14 14 16 15 18
5. Pengecatan struktur Atap 6 6 7 7 8 8 9 12 18 20 22 21 43 36 45
6. Penegecatan Tangga & Handrail 4 4 4 4 5 5 5 5 5 5 5 5 6 6 6
Total Hari Kerja Pengecetan Tangki 35 41 45 49 53 56 57 77 85 103 118 114 171 154 187

Total Hari Kerja (1 team) 341 537 625 717 757 838 845 1405 1511 1869 2330 2396 3411 3452 4335
Total Hari Kerja 85 134 125 143 151 168 169 176 189 234 291 300 284 288 289

Note : Tangki 1 - 2 (4 tim), tangki 3 - 7 (5 tim), tangki 8 - 12 (8 tim), tangki 13 - 14 (12 tim), tangki 15 - 16 (15 tim)

Biaya Personel

I Fabrikasi
1 org Mandor (75.000) 3,375,000 5,625,000 6,975,000 8,550,000 9,525,000 10,350,000 11,175,000 18,900,000 21,750,000 21,900,000 26,625,000 24,825,000 38,250,000 34,800,000 45,075,000
1 org Kepala Tukang (50.000) 2,250,000 3,750,000 4,650,000 5,700,000 6,350,000 6,900,000 7,450,000 12,600,000 14,500,000 14,600,000 17,750,000 16,550,000 25,500,000 23,200,000 30,050,000
1 org Tukang Besi 1 (45.000) 2,025,000 3,375,000 4,185,000 5,130,000 5,715,000 6,210,000 6,705,000 11,340,000 13,050,000 13,140,000 15,975,000 14,895,000 22,950,000 20,880,000 27,045,000
1 org Pembantu tukang besi (30.000) 1,350,000 2,250,000 2,790,000 3,420,000 3,810,000 4,140,000 4,470,000 7,560,000 8,700,000 8,760,000 10,650,000 9,930,000 15,300,000 13,920,000 18,030,000
TOTAL FABRIKASI 9,000,000 15,000,000 18,600,000 22,800,000 25,400,000 27,600,000 29,800,000 50,400,000 58,000,000 58,400,000 71,000,000 66,200,000 102,000,000 92,800,000 120,200,000

II Scaffolding
1 org Mandor (65.000) 1,170,000 2,405,000 2,860,000 3,120,000 3,055,000 3,510,000 3,445,000 5,200,000 4,810,000 6,370,000 7,150,000 7,735,000 8,645,000 9,100,000 10,400,000
1 org Tukang besi1 (45.000) 810,000 1,665,000 1,980,000 2,160,000 2,115,000 2,430,000 2,385,000 3,600,000 3,330,000 4,410,000 4,950,000 5,355,000 5,985,000 6,300,000 7,200,000
1 org Pembantu tukang besi (30.000) 540,000 1,110,000 1,320,000 1,440,000 1,410,000 1,620,000 1,590,000 2,400,000 2,220,000 2,940,000 3,300,000 3,570,000 3,990,000 4,200,000 4,800,000
1 org Pekerja (25.000) 450,000 925,000 1,100,000 1,200,000 1,175,000 1,350,000 1,325,000 2,000,000 1,850,000 2,450,000 2,750,000 2,975,000 3,325,000 3,500,000 4,000,000
TOTAL SCAFFOLDING 2,970,000 6,105,000 7,260,000 7,920,000 7,755,000 8,910,000 8,745,000 13,200,000 12,210,000 16,170,000 18,150,000 19,635,000 21,945,000 23,100,000 26,400,000

III Ereksi Tangki


Pekerjaan 2,3,4,5,7
1 org Tukang las I / II (60.000) 2,760,000 4,800,000 5,580,000 6,540,000 6,720,000 7,920,000 7,260,000 14,280,000 14,220,000 21,840,000 30,120,000 33,000,000 44,640,000 50,280,000 63,600,000
1 org Mandor (75.000) 3,450,000 6,000,000 6,975,000 8,175,000 8,400,000 9,900,000 9,075,000 17,850,000 17,775,000 27,300,000 37,650,000 41,250,000 55,800,000 62,850,000 79,500,000
1 org QC (95.000) 4,370,000 7,600,000 8,835,000 10,355,000 10,640,000 12,540,000 11,495,000 22,610,000 22,515,000 34,580,000 47,690,000 52,250,000 70,680,000 79,610,000 100,700,000
1 org Pembantu Tukang Las (35.000) 1,610,000 2,800,000 3,255,000 3,815,000 3,920,000 4,620,000 4,235,000 8,330,000 8,295,000 12,740,000 17,570,000 19,250,000 26,040,000 29,330,000 37,100,000
1 org Crane Oparator (75.000) 3,450,000 6,000,000 6,975,000 8,175,000 8,400,000 9,900,000 9,075,000 17,850,000 17,775,000 27,300,000 37,650,000 41,250,000 55,800,000 62,850,000 79,500,000
TOTAL EREKSI 1 15,640,000 27,200,000 31,620,000 37,060,000 38,080,000 44,880,000 41,140,000 80,920,000 80,580,000 123,760,000 170,680,000 187,000,000 252,960,000 284,920,000 360,400,000

Pekerjaan 6, 10
1 org Tukang las III (40.000) 560,000 600,000 720,000 800,000 920,000 920,000 1,040,000 1,480,000 2,280,000 2,600,000 2,880,000 2,720,000 5,520,000 4,640,000 5,760,000
1 org Mandor (75.000) 1,050,000 1,125,000 1,350,000 1,500,000 1,725,000 1,725,000 1,950,000 2,775,000 4,275,000 4,875,000 5,400,000 5,100,000 10,350,000 8,700,000 10,800,000
1 org QC (95.000) 1,330,000 1,425,000 1,710,000 1,900,000 2,185,000 2,185,000 2,470,000 3,515,000 5,415,000 6,175,000 6,840,000 6,460,000 13,110,000 11,020,000 13,680,000
1 org Pembantu Tukang Las (35.000) 490,000 525,000 630,000 700,000 805,000 805,000 910,000 1,295,000 1,995,000 2,275,000 2,520,000 2,380,000 4,830,000 4,060,000 5,040,000
1 org Crane Oparator (75.000) 1,050,000 1,125,000 1,350,000 1,500,000 1,725,000 1,725,000 1,950,000 2,775,000 4,275,000 4,875,000 5,400,000 5,100,000 10,350,000 8,700,000 10,800,000
TOTAL EREKSI 2 7,840,000 8,400,000 10,080,000 11,200,000 12,880,000 12,880,000 14,560,000 20,720,000 31,920,000 36,400,000 40,320,000 38,080,000 77,280,000 64,960,000 80,640,000

Pekerjaan 8, 9
1 org Tukang las I (60.000) 780,000 1,080,000 1,080,000 1,080,000 1,080,000 1,080,000 1,080,000 1,200,000 1,200,000 1,260,000 1,320,000 1,320,000 1,320,000 1,320,000 1,380,000
1 org Mandor (75.000) 975,000 1,350,000 1,350,000 1,350,000 1,350,000 1,350,000 1,350,000 1,500,000 1,500,000 1,575,000 1,650,000 1,650,000 1,650,000 1,650,000 1,725,000
1 org QC (95.000) 1,235,000 1,710,000 1,710,000 1,710,000 1,710,000 1,710,000 1,710,000 1,900,000 1,900,000 1,995,000 2,090,000 2,090,000 2,090,000 2,090,000 2,185,000
1 org Tukang Pipa (50.000) 650,000 900,000 900,000 900,000 900,000 900,000 900,000 1,000,000 1,000,000 1,050,000 1,100,000 1,100,000 1,100,000 1,100,000 1,150,000
1 org Crane Oparator (75.000) 975,000 1,350,000 1,350,000 1,350,000 1,350,000 1,350,000 1,350,000 1,500,000 1,500,000 1,575,000 1,650,000 1,650,000 1,650,000 1,650,000 1,725,000
TOTAL EREKSI 3 4,615,000 6,390,000 6,390,000 6,390,000 6,390,000 6,390,000 6,390,000 7,100,000 7,100,000 7,455,000 7,810,000 7,810,000 7,810,000 7,810,000 8,165,000

TOTAL TENAGA KERJA EREKSI 31,065,000 48,095,000 55,350,000 62,570,000 65,105,000 73,060,000 70,835,000 121,940,000 131,810,000 183,785,000 236,960,000 252,525,000 359,995,000 380,790,000 475,605,000

V TOTAL BIAYA TENAGA KERJA 40,065,000 63,095,000 73,950,000 85,370,000 90,505,000 100,660,000 100,635,000 172,340,000 189,810,000 242,185,000 307,960,000 318,725,000 461,995,000 473,590,000 595,805,000
-7653322211

9i999999999999999999i
20000

621
4
625

153
121
645
10
173
154
42
19
4
18
1339

33
11
12
4
9
8
77

103
13
12
17
53
6
204

4286
286

46,875,000
31,250,000
28,125,000
18,750,000
125,000,000

9,945,000
6,885,000
4,590,000
3,825,000
25,245,000

59,460,000
74,325,000
94,145,000
34,685,000
74,325,000
336,940,000

6,880,000
12,900,000
16,340,000
6,020,000
12,900,000
96,320,000

1,380,000
1,725,000
2,185,000
1,150,000
1,725,000
8,165,000

466,670,000

591,670,000
Perhitungan Jumlah Jam Kerja

NO TANK DATA INPUT KAPASITAS TANGKI (M3) , DIAMETER/TINGGI (M)


500 1000 1500 2000 2000 2500 2500 5000 5000 7500 10000 10000 15000 15000 20000 20000
I Fabrikasi
1. Cutting, Marking, Grinding &
Bevelling 43 71 89 110 123 134 145 248 286 288 351 327 506 460 597 621
3. Manhole Fabrication 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Total Hari Kerja Fabrikasi 45 75 93 114 127 138 149 252 290 292 355 331 510 464 601 625

II Ereksi Tangki
1. Pemasangan &
Pembongkaran Scafolding 18 37 44 48 47 54 53 80 74 98 110 119 133 140 160 153
2. Penyusunan & Las Pelat Dasar 5 7 10 13 17 17 20 34 39 51 64 57 94 78 103 121
3. Penyusunan & Las Pelat Dinding 30 59 67 76 71 91 73 153 142 231 344 405 455 583 749 645
4. Pemasangan & Las Top Angle 1 1 1 1 2 2 3 5 6 6 7 7 9 8 9 10
5. Pengelasan Dinding ke Dasar 8 10 11 14 15 15 17 31 33 57 64 60 152 139 159 173
6. Pemasangan Struktur Atap 8 9 11 12 15 15 17 26 46 52 58 55 122 101 127 154
7. Pemasangan & Las Pelat atap 2 3 4 5 7 7 8 15 17 19 23 21 34 30 40 42
8. Pemasangan Nozzle/Manhole 11 16 16 16 16 16 16 17 17 18 18 18 18 18 19 19
9. Pemasangan Water/ Product Drain 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4 4
10. Pemasangan Tangga & Handrail 6 6 7 8 8 8 9 11 11 13 14 13 16 15 17 18
Total Hari Kerja Ereksi 91 150 173 195 200 227 218 375 388 548 706 759 1037 1116 1387 1339

III Uji Tangki


1. Uji Radiografi (RT) 2 2 2 3 3 3 4 10 6 12 10 17 33 31 42 33
2. Uji PT utk nozzle/manhole 6 9 9 9 9 9 9 9 10 10 10 10 10 10 11 11
2. Uji Vacuum Box 1 1 2 2 2 2 3 4 5 5 7 6 10 8 11 12
3. Uji Tekanan/Pressure 2 2 2 2 2 2 2 3 3 3 4 4 4 4 4 4
4. Uji PT utk lasan Dinding-Dasar 2 3 3 3 4 4 4 5 6 6 7 7 8 8 9 9
6. Uji Hidrostatis 4 6 6 6 5 6 5 6 5 7 7 7 8 8 9 8
Total Hari Kerja Uji Tangki 17 23 24 25 25 26 27 37 35 43 45 51 73 69 86 77

IV Pengecetan Tangki
1. Surface Preparation 7 11 14 17 18 20 21 33 37 48 58 56 84 75 94 103
2. Pengecetan Pelat Dinding 5 6 6 7 7 7 7 9 8 10 11 11 12 13 14 13
3. Pengecatan Pelat Atap 4 4 4 4 5 5 5 6 6 7 8 7 10 9 10 12
4. Pengecatan Pelat Dasar 9 10 10 10 10 11 10 12 11 13 14 14 16 15 18 17
5. Pengecatan struktur Atap 6 6 7 7 8 8 9 12 18 20 22 21 43 36 45 53
6. Penegecatan Tangga & Handrail 4 4 4 4 5 5 5 5 5 5 5 5 6 6 6 6
Total Hari Kerja Pengecetan Tangki 35 41 45 49 53 56 57 77 85 103 118 114 171 154 187 204

Total Hari Kerja (1 team) 341 537 625 717 757 838 845 1405 1511 1869 2330 2396 3411 3452 4335 4286
Total Hari Kerja 85 134 125 143 151 168 169 176 189 234 291 300 284 288 289 286

Note : Tangki 1 - 2 (4 tim), tangki 3 - 7 (5 tim), tangki 8 - 12 (8 tim), tangki 13 - 14 (12 tim), tangki 15 - 16 (15 tim)

II Ereksi Tangki
Pembuatan Water Sprinkler 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000 7750000
Pembuatan Sump 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000 3500000
Pemasangan Grounding 1000000 1000000 1000000 1000000 1000000 1000000 1000000 1000000 1000000 1500000 1500000 1500000 1500000 1500000 1500000 1500000
TOTAL 12250000 12250000 12250000 12250000 12250000 12250000 12250000 12250000 12250000 12750000 12750000 12750000 12750000 12750000 12750000 12750000

III NDT & Uji Tangki (Alat & Pekerja)


1. Uji Radiografi (Rp. 1.260.000) 2520000 2520000 2520000 3780000 3780000 3780000 5040000 12600000 7560000 15120000 12600000 21420000 41580000 39060000 52920000 41580000
2. Uji Penetran (Rp. 1.035.000) 8280000 12420000 12420000 12420000 13455000 13455000 13455000 14490000 16560000 16560000 17595000 17595000 18630000 18630000 20700000 20700000
3. Uji Vacuum Box (Rp. 1.000.000) 1000000 1000000 2000000 2000000 2000000 2000000 3000000 4000000 5000000 5000000 7000000 6000000 10000000 8000000 11000000 12000000
4. Uji Tekanan/Pressure (Rp.1.000.000) 2000000 2000000 2000000 2000000 2000000 2000000 2000000 3000000 3000000 3000000 4000000 4000000 4000000 4000000 4000000 4000000
5. Uji Hidrostatis (Rp. 1.000.000) 4000000 6000000 6000000 6000000 5000000 6000000 5000000 6000000 5000000 7000000 7000000 7000000 8000000 8000000 9000000 8000000
TOTAL BIAYA UJI TANGKI 17800000 23940000 24940000 26200000 26235000 27235000 28495000 40090000 37120000 46680000 48195000 56015000 82210000 77690000 97620000 86280000

IV Pengeacatan Tangki
1. Aplikasi Coating incl Sewa alat, tenaga kerja 27365524 40287683 48733971 57762437 64680536 69376227 74180033 116970918 139549004 175746786 207608605 200350801 313850842 279767087 345761869 384684945
2. Sewa Scaffolding (100.000) 875000 1025000 900000 980000 1060000 1120000 1140000 962500 1062500 1287500 1475000 1425000 1425000 1283333.3 1246666.667 1360000
TOTAL Pengecetan Tangki 28240524 41312683 49633971 58742437 65740536 70496227 75320033 117933418 140611504 177034286 209083605 201775801 315275842 281050420 347008535 386044945

V TOTAL 58290524 77502683 86823971 97192437 104225536 109981227 116065033 170273418 189981504 236464286 270028605 270540801 410235842 371490420 457378535 485074945