HARGA MATERIAL

LOKASI : KALIMANTAN BARAT


NO MATERIAL SAT
I BAHAN PASIR dan BATU
1 Batako ( Camp. Semen, Pasir dan Abu batu ). Uk. 9x19x39 Cm Bh
2 Bata 5 x 10 x 20 cm Bh
3 Batu Belah 15/20 M
4 Batu Pecah Mesin 2/3 M
5 Pasir Beton/Cor M
6 Pasir Pasang M
7 Pasir Urug M
8 Readmix Beton K 100, ( PRICE LIST )
9 Readmix Beton K 125, ( PRICE LIST )
10 Readmix Beton K 175, ( PRICE LIST ) M
11 Readmix Beton K 225, ( PRICE LIST ) M
12 Readmix Beton K 250, ( PRICE LIST ) M
13 Readmix Beton K 300, ( PRICE LIST ) M
14 Readmix Beton K 350, ( PRICE LIST ) M
15 Sirtu M
16 Tanah Urug M
17 Pompa Hydraulic Per 8 Jam
II BAHAN SEMEN dan PEREKAT
1 Semen PC Type 1 @ 50 Kg Zak
2 Semen PC Type 1 @ 50 Kg Kg

367593161.xls-Printed on -10/03/2017-03:02:56 1/16


HARGA MATERIAL
LOKASI : KALIMANTAN BARAT
NO MATERIAL SAT

III BAHAN KAYU


A KAYU KELAS I
1 Kayu Balok ( Kamper Samarinda Oven ) M
2 Kayu Papan ( Kamper Samarinda Oven ) M
3 Kayu Jat M

B KAYU KELAS II M
1 Kayu Balok 3/4 - 4 m Btg
2 Kayu Balok 4/6 - 4 m Btg
3 Kayu Balok 5/10 - 4 m Btg
4 Kayu Balok 5/7 - 4 m Btg
5 Kayu Balok 6/12 - 4 m Btg
6 Kayu Balok 6/15 - 4 m Btg
7 Kayu Balok 8/12 - 4 m Btg
8 Kayu Balok 8/15 - 4 m Btg
9 Kayu Papan 2/20 - 4 m Lbr
10 Kayu Papan 3/20 - 4 m Lbr
11 Kayu Papan 3/25 - 4 m Lbr
12 Kayu Papan 3/30 - 4 m Lbr

C KAYU KELAS III M


1 Kayu Balok 4/6 - 4 m Btg
2 Kayu Balok 5/7 - 4 m Btg
3 Kayu Papan 2/20 - 4 m Lbr

367593161.xls-Printed on -10/03/2017-03:02:56 2/16


HARGA MATERIAL
LOKASI : KALIMANTAN BARAT
NO MATERIAL SAT

D KAYU LAPIS
1 Multplek Uk. 120 x 240 x 12mm Lbr
2 Multplek Uk. 120 x 240 x 12mm M
3 Multplek Uk. 120 x 240 x 9mm Lbr
4 Multplek Uk. 120 x 240 x 9mm M
5 Multplek Uk. 120 x 240 x 18mm Lbr
6 Multplek Uk. 120 x 240 x 18mm M
7 Plywood Uk. 120 x 240 x 4mm Lbr

E LAINNYA
1 Bambu Dia. 8-10 x 400-550 Cm Btg
2 Kayu Dolken Dia. 5-7 x 350-400 Cm Btg
3 Kayu Dolken Dia. 8-10 x 350-400 Cm Btg
4 Kayu Reng 2/3 Borneo Super M'
5 Kayu Reng 2/3 Kamper Banjar M'
6 Kayu Reng 3/4 Kamper Banjar M'
7 List Profil Kamper 1 x 1 Cm M'
8 List Profil Kamper 10 x 1.5 Cm M'
9 List Profil Kamper 2 x 1 Cm M'
10 List Profil Kamper 4 x 1 Cm M'
11 List Profil Kamper 5 x 1 Cm M'
12 Pegangan Tangga Profil Jat M'
13 Pegangan Tangga Profil Kamper M'

IV BAHAN ATAP dan PENUTUP RANGKA PLAFON


1 Akustik Amstrong 60 x 120 Cm Lbr
2 Akustik Daikan ( Jepang ) Lbr
3 Akustik Nova ( Amerika ) Lbr
4 Asbes Semen 1M x 1M Lbr
5 Asbes Semen 5mm M
6 Eternit 4mm ( Bola Dunia ) M
7 Genteng Beton Bh
8 Genteng Keramik Bh
9 Genteng Kodok Bh
10 Genteng Merk Munir Bh
11 Genteng Plentong Bh
12 Glass Fibre Concrete ( GRC ) t = 4mm Lbr
13 Glass Fibre Concrete ( GRC ) t = 6mm Lbr
14 Glass Fibre Concrete ( GRC ) t = 9mm Lbr
15 Gypstone Lbr
16 Gypsum 120 x 240 x 0.4 Cm Ex. DN ( Jayaboard ) Lbr
17 Gypsum 120 x 240 x 0.9 Cm Ex. DN ( Jayaboard ) Lbr
18 Gypsum 120 x 240 x 0.9 Cm Ex. LN Lbr
19 Hardpleks 120 x 240 x 0.5 Cm Lbr
20 Nok Genteng Keramik Bh
21 Nok Genteng Kodok Bh
22 Seng BJLS 30 L=90 cm Lbr
23 Seng Gelombang BJLS 28 Uk. 80 x 180 cm Lbr
367593161.xls-Printed on -10/03/2017-03:02:56 3/16
HARGA MATERIAL
LOKASI : KALIMANTAN BARAT
NO MATERIAL SAT
24 Seng Plat BJLS 28 M
25 Seng Plat Tebal 0.3 mm. Lebar 0.9 M M

V BAHAN LOGAM dan BAHAN JADINYA


1 Besi Beton < 12 mm Kg
2 Besi Beton > 12 mm Kg
3 Besi C Lip Channel Kg
4 Besi Profil DIN SII Kg
5 Besi Strip Kg
6 IWF Ex. DIN SII Kg
7 Kawat Beton/Bendrat Kg
8 Paku Biasa Kg
9 Plat Baja Hitam < 8 mm Kg
10 Plat Baja Hitam > 8 mm Kg
11 25 x 400 mm H.D Bolts c/w Nuts & Washers Set
12 Wire Mesh M5 Per Lbr lbr
13 Wire Mesh M5 Per M2 M
14 Wire Mesh M6 Per Lbr lbr
15 Wire Mesh M6 Per M2 M
16 Wire Mesh M7 Per Lbr
17 Wire Mesh M7 Per M2
18 Wire Mesh M8 Per Lbr Lbr
19 Wire Mesh M8 Per M2 M
20 Wire Mesh M10 Per Lbr Lbr
21 Wire Mesh M10 Per M2 M
22 Atap Hi-Ten TCT 0,45 mm Colorbond - Golden SR-1000 M
23 Clading Hi-Ten TCT 0,45 mm Colorbond M
24 Self Drilling Screw 1/4-65mm Bh
25 Self Drilling Screw 1/4-25mm Bh

VI BAHAN ALAT PENGGANTUNG dan KUNCI


1 Kunci 2 Slag Anchor Asli Bh
1 Kunci 2 Slag Selinder Utama Standard Bh
VII BAHAN KACA
1 Glass Block 20 x 20 ( Kedawung ) Bh
2 Glass Block DN 20 x 20 Ex. LN M
3 Kaca Cermin Pcs
4 Kaca Graveer 5mm M
5 Kaca Patri LNl Terpasang( ASAHI) M
6 Kaca Patri Lokal Terpasang( ASAHI) M
7 Kaca Polos 2mm ( ASAHI) M
8 Kaca Polos 3mm ( ASAHI) M
9 Kaca Polos 5mm ( ASAHI) M
10 Kaca Polos 8mm ( ASAHI) M
11 Kaca Rayband 12mm ( ASAHI) M
12 Kaca Rayband 5mm ( ASAHI) M
13 Kaca Rayband 8mm ( ASAHI) M

367593161.xls-Printed on -10/03/2017-03:02:56 4/16


DAFTAR HARGA SATUAN UPAH

No. Jabatan Vol Sat Harga Sat

1.5000
1 Pekerja 1.00 Org 90,000
2 Mandor 1.00 Org 135,000
3 Tukang Gali 1.00 Org 120,000
4 Tukang Batu 1.00 Org 120,000
5 Kepala Tukang Batu 1.00 Org 127,500
6 Tukang Kayu 1.00 Org 120,000
7 Kepala Tukang Kayu 1.00 Org 127,500
8 Tukang Besi 1.00 Org 120,000
9 Kepala Tukang Besi 1.00 Org 127,500
10 Tukang Cat 1.00 Org 120,000
11 Kepala Tukang Cat 1.00 Org 127,500
12 Tukang Molen 1.00 Org 120,000
13 Tukang Keramik 1.00 Org 120,000
14 Kepala Tukang Keramik 1.00 Org 127,500
15 Tukang Marmer/Ganito/Slab 1.00 Org 120,000
16 Tukang Las 1.00 Org 120,000
17 Tukang Baja 1.00 Org 120,000
18 Kepala Tukang Baja 1.00 Org 127,500
19 Tukang Kaca 1.00 Org 120,000
20 Kepala Tukang Kaca 1.00 Org 127,500
21 Tukang Pipa/Ledeng 1.00 Org 120,000
22 Kepala Tukang Pipa/Ledeng 1.00 Org 127,500
23 Tukang Listrik 1.00 Org 120,000
24 Kepala Tukang Listrik 1.00 Org 127,500
25 Masinis 1.00 Org 135,000
26 Pembantu masinis 1.00 Org 120,000
27 Penjaga 1.00 Org 120,000
28 Tukang masak aspal 1.00 Org 120,000
29 Operator Alat Berat 1.00 Org 135,000

PT. WJK - 367593161.xls - Printed on - 10/03/2017 5/16


DAFTAR HARGA SATUAN PEKERJAAN dan UPAH

NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA


BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )

1 PEKERJAAN PERSIAPAN
1 1 M Pembersihan Lokasi
2 1 M Pembongkaran Dinding Tembok Bata Merah
3 1 M Pembongkaran Beton Bertulang
4 1 M Pembongkaran Bekesting
5 1 M' Pagar Sementara dari Kayu, h = 2M
6 1 M' Pagar Sementara dari Seng Glb, h= 2M
7 1 M' Pagar Sementara dari Kawat Duri, h = 1.8 M
8 1 M' Pengukuran / Pasang Bowplank
9 1 M Site Office (Kantor Sementara)
10 1 M Gudang Logistik
11 1 M Pembuatan Rumah Jaga / Konstruksi Kayu
12 1 M Barak Pekerja
13 1 M Pembuatan Bak Adukan Uk. 40 x 50 x 25
14 1 M Pembuatan Stegger
15 1 M Pembuatan Jalan Sementara
16 1 M Pasang pagar kawat Jaring Galvanis panjang 240 cm
17 1 M Pembuatan Rumah Jaga / Konstruksi Beton
18 1 Ls Penyediaan Listrik Kerja dan Penerangan
19 1 Ls Penyediaan Air Kerja
20 1 Bln Keamanan
21 1 Ls Mobilisasi De Mobilisasi

2 PEKERJAAN TANAH ( SNI 2835 : 2008 )


1 1 M Galian Tanah Biasa h = 1M
2 1 M Galian Tanah Biasa h = 2M
3 1 M Galian Tanah Biasa h = 3M
4 1 M Galian Tanah Keras h = 1M
5 1 M Galian Tanah Cadas h = 1M
6 1 M Galian Tanah Lumpur h = 1M
7 1 M Pekerjaan Stripping h = 1M
8 1 M Buang Tanah Sejauh 150 m
9 1 M Urugan Kembali
10 1 M Pemadatan Tanah
11 1 M Urugan Pasir
12 1 M Urugan Tanah Dengan Mesin Stamper
13 1 M Lapisan Pudel Camp. 1 Kp : 3 Ps : 7 TL
14 1 M Lapisan Pudel Camp. 1 Kp : 5 TL
15 1 M Pemasangan Lapisan Ijuk
16 1 M Urugan Sirtu
17 1 M Urugan Hardcore
18 1 M Pembuatan Jalan Sementara thk = 25 cm
19 1 M Galian Tanah Dengan Alat Berat
20 1 M Buang Tanah Dengan Dump Truk

3 PEKERJAAN PONDASI BATU KALI ( SNI 2837 : 2008 )


1 1 M Pasang Pondasi. Bt Kali, 1 Pc : 1 Ps
2 1 M Pasang Pondasi. Bt Kali, 1 Pc : 2 Ps
3 1 M Pasang Pondasi. Bt Kali, 1 Pc : 2,5 Ps
4 1 M Pasang Pondasi. Bt Kali, 1 Pc : 3 Ps
5 1 M Pasang Pondasi. Bt Kali, 1 Pc : 4 Ps
6 1 M Pasang Pondasi. Bt Kali, 1 Pc : 5 Ps
7 1 M Pasang Pondasi. Bt Kali, 1 Pc : 6 Ps
8 1 M Pasang Pondasi. Bt Kali, 1 Pc : 8 Ps
9 1 M Pasang Pondasi. Bt Kali, 1 Kp : 1 Sm : 1 Ps
10 1 M Pasang Pondasi. Bt Kali, 1 Kp : 1 Sm : 2 Ps
11 1 M Pasang Pondasi. Bt Kali, 1 Pc : 1/4 Kp : 4 Ps
12 1 M Pasang Pondasi. Bt Kali, 1 Pc : 3 Kp : 10 Ps
13 1 M Pasang Pondasi. Bt Kali, 1/4 Pc : 1 Kp : 4 Ps
14 1 M Pasang Pondasi Batu Kosong
15 1 M Pasang Pondasi Siklop, 40% Batu Kali
16 1 M Pasang Pondasi Sumuran, Dia. 100 cm
17 1 M Pembuatan Tiang Pancang 40x40 cm
18 1 M Pembuatan Tiang Pancang 35x35 cm

03 PEKERJAAN STEEL SRUKTUR


1 1 Kg Pekerjaan Baja WF (Fabrikasi/Erection)
2 1 Kg Pekerjaan Baja CNP (Fabrikasi/Erection)
3 1 Kg Pekerjaan Baja Siku (Fabrikasi/Erection)
4 1 Kg Pekerjaan Baja Plat Strip (Fabrikasi/Erection)
5 1 Kg Pekerjaan Baja Plat < 8 mm (Fabrikasi/Erection)
6 1 Kg Pekerjaan Baja Plat > 8 mm (Fabrikasi/Erection)
7 1 Kg Pekerjaan Grating Cover

367593161.xls-Printed on -10/03/2017-03:02:57 6/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
04 PEKERJAAN PASANGAN DINDING ( SNI 6897 : 2008 )
1 1 M Pasangan 1Bata 1 Pc : 1 Ps I Bata
2 1 M Pasangan 1Bata 1 Pc : 2 Ps I Bata
3 1 M Pasangan 1Bata 1 Pc : 3 Ps I Bata
4 1 M Pasangan 1Bata 1 Pc : 4 Ps I Bata
5 1 M Pasangan 1Bata 1 Pc : 5 Ps I Bata
6 1 M Pasangan 1Bata 1 Pc : 6 Ps I Bata
7 1 M Pasangan 1Bata 1 Pc : 3 Kp : 10 Ps I Bata
8 1 M Pasangan 1/2 Bata 1 Pc : 2 Ps I/2 Bata
9 1 M Pasangan 1/2 Bata 1 Pc : 3 Ps I/2 Bata
10 1 M Pasangan 1/2 Bata 1 Pc : 4 Ps I/2 Bata
11 1 M Pasangan 1/2 Bata 1 Pc : 5 Ps I/2 Bata
12 1 M Pasangan 1/2 Bata 1 Pc : 6 Ps I/2 Bata
13 1 M Pasangan 1/2 Bata 1 Pc : 8 Ps I/2 Bata
14 1 M Pasangan 1/2 Bata 1 Pc : 3 Kp : 10 Ps I/2 Bata
15 1 M Pasangan 1/2 Bata 1 Pc : 1 Kp : 1 Ps I/2 Bata
16 1 M Pasangan 1/2 Bata 1 Pc : 1 Kp : 2 Ps I/2 Bata
17 1 M Pasangan Dinding Batako 1 Pc : 4 Ps
18 1 M Pasangan Dinding Hollowblock (HB 20) 1 Pc : 3 Ps
19 1 M Pasangan Dinding Hollowblock (HB 20) 1 Pc : 4 Ps
20 1 M Pasangan Dinding Hollowblock (HB 15) 1 Pc : 3 Ps
21 1 M Pasangan Dinding Hollowblock (HB 15) 1 Pc : 4 Ps
22 1 M Pasangan Dinding Hollowblock (HB 10) 1 Pc : 3 Ps
23 1 M Pasangan Dinding Hollowblock (HB 10) 1 Pc : 4 Ps
24 1 M Pasangan Dinding Conblock (CB 20)
25 1 M Pasangan Dinding Conblock (CB 15)
26 1 M Pasangan Dinding Conblock (CB 10)
27 1 M Pasang Dinding Latei
28 1 M Pasang Dinding Roster/Krawang 12 x 11 x 24 1PC : 3PS
29 1 M Pasang Dinding Roster/krawang 12 x 11 x 24 1PC : 4PS
30 1 M Pasang Bata Berongga uk. 5 x 11 x 24 cm 1PC : 3PS
31 1 M Pasang Bata Berongga uk. 5 x 11 x 24 cm 1PC : 2PS
32 1 M Pasang Dinding Anyaman Bambu, Rangka Kayu

05 PEKERJAAN PELESTERAN
1 1 M Plesteran 1 : 1, thk = 15 mm
2 1 M Plesteran 1 : 2, thk = 15 mm
3 1 M Plesteran 1 : 3, thk = 15 mm
4 1 M Plesteran 1 : 4, thk = 15 mm
5 1 M Plesteran 1 : 5, thk = 15 mm
6 1 M Plesteran 1 : 6, thk = 15 mm
7 1 M Plesteran 1 : 8, thk = 15 mm
8 1 M Plesteran 1 : 0.5 : 3 thk = 15 mm
9 1 M Plesteran 1 : 3 : 10 thk = 15 mm
10 1 M Plesteran 0.5 : 1 : 4, thk = 15 mm
11 1 M Plesteran 1 : 1 : 1, thk = 15 mm
12 1 M Plesteran 1 : 1 : 2, thk = 15 mm
13 1 M Plesteran 1 : 5 , thk = 20 mm
14 1 M Plesteran 1 : 6 , thk = 20 mm
15 1 M Plesteran 1 : 1 : 2, thk = 20 mm
16 1 M Plesteran 1 : 2 , thk = 25 mm
17 1 M Plesteran 1 : 3 , thk = 25 mm
18 1 M Plesteran 1 : 4 , thk = 25 mm
19 1 M Plesteran 1 : 5 , thk = 25 mm
20 1 M Plesteran 1 : 2 , thk = 30 mm
21 1 M Plesteran 1 : 3 , thk = 30 mm
22 1 M Plesteran 1 : 4 , thk = 30 mm
23 1 M Plesteran 1 : 5 , thk = 30 mm
24 1 M Berapen 1 : 3 , thk = 30 mm
25 1 M Berapen 1 : 5 , thk = 15 mm
26 1 M Plesteran Beton 1 : 2 , thk = 15 mm
27 1 M Plesteran Beton 1 : 3 , thk = 15 mm
28 1 M Plesteran Skoning 1 : 2
29 1 M Plesteran Granito 1 : 2 , thk = 10 mm
30 1 M Plesteran Teraso 1 : 2 , thk = 10 mm
31 1 M Plesteran Ciprat
32 1 M Plesteran Siar Ad. 1 : 2
33 1 M Plesteran Waterproof Batacote 3 Lapis

06 PEKERJAAN KAYU
1 1 M Pasang Kusen Pintu dan Jendela
2 1 M Pasang Pintu Klam Kayu Kamper
3 1 M Pasang Pintu Klam Kayu Borneo
4 1 M Pasang Pintu Panel Jati
5 1 M Pasang Pintu Panel Kayu Kamper
6 1 M Pasang Pintu dan Jendela Kaca Kayu Jati
7 1 M Pasang Pintu dan Jendela Kaca Kayu Kamper
8 1 M Pasang Pintu dan Jendela Kaca Kayu Borneo
9 1 M Pasang Pintu dan Jendela Jalusi Kayu Jati
10 1 M Pasang Pintu dan Jendela Jalusi Kayu Kamper
11 1 M Pasang Pintu Double Plywood Kayu Jati
12 1 M Pasang Pintu Double Plywood Kayu Kamper
13 1 M Pasang Jalusi Mati Kusen Kayu Jati
14 1 M Pasang Jalusi Mati Kusen Kayu Kamper
15 1 M Pasang Kontruksi Kuda-kuda Kayu Borneo
16 1 M Pasang Lisplank Ukuran 2 x 2 x 20 Cm Kayu Borneo
17 1 M Pasang Rangka Dinding Pemisah Kayu Kamper
18 1 M Pasang Kontruksi Kuda-kuda Konvensional ,Kayu kelas I, II dan III bentang 6 m
19 1 M Pasang Rangka Dinding Pemisah Kayu Borneo
20 1 M Pasang Dinding Pemisah Double Plywood + Rangka Kayu Kamper
21 1 M Pasang Dinding Pemisah Double Plywood + Rangka Kayu Borneo
22 1 M Pasang 1 m 2 Rangka atap genteng keramik, kayu kelas II
23 1 M Pasang Dinding Pemisah Double Gypsum + Rangka Kayu Borneo
24 1 M Pasang Plywood t=4mm Untuk Dinding
25 1 M Pasang List - Kayu Profil
26 1 M Pasang Dinding Pemisah Double Plywood + Rangka Kayu Borneo + List Profil

367593161.xls-Printed on -10/03/2017-03:02:57 7/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
V PEKERJAAN INSTALASI AIR
1 1 Ttk Bongkar Instalasi Air Bersih
2 1 Ttk Bongkar Instalasi Air Kotor 2"
3 1 Ttk Bongkar Instalasi Air Kotor 4"
4 1 Ttk Pasang Instalasi Air Bersih 1/2" - 3/4"
5 1 Ttk Pasang Instalasi Air Kotor 2"
6 1 Ttk Pasang Instalasi Air Kotor 4"
7 1 Bh Pasang Kloset Duduk TOTO/CW 820 PJ Waite
8 1 Bh Pasang Wastafel Type LW 986
9 1 Bh Pasang Urinoir Toto Type U 57
10 1 Bh Pasang Kran Tembok 1/2"
11 1 Bh Pasang Floor Drain
12 1 M' Pipa 65
13 1 M' Pipa 80
14 1 M' Pipa 100
15 1 M' Pipa 150
16 1 M' Header Black Steel Sch 40, 200
17 1 M' GIP Schedule 40, 150
18 1 M' GIP Schedule 40, 65
19 1 M' Header GIP Medium Class 150
20 1 M' Pipa GIP Class Medium 100 mm
21 1 Bh Flow Meter Indikator
22 1 Bh Flexible Joint 150
23 1 Bh Flexible Joint 100
24 1 Bh Flexible Joint 65
25 1 Bh Check Valve 100
26 1 Bh Check Valve 20
27 1 Bh Gate Valve 150
28 1 Bh Gate Valve 100
29 1 Bh Gate Valve 65
30 1 Bh Gate Valve 20
31 1 Bh Gate Valve 15
32 1 Bh Strainer 150
33 1 Bh Strainer 100
34 1 Bh Strainer 65
35 1 Bh Fire Extinguisher Kap. 2.5 Kg
36 1 Bh Fire Extinguisher Kap. 5 Kg
37 1 Set Hydrant Box Out Door c/w A
38 1 Set Hydrant Box Indoor c/w
39 1 Bh Automatic Air Release Valve
40 1 Bh Pillar Hydrant Two Way
41 1 Bh Pressure Tank
42 1 Bh Pressure Gauge ( 15 Bar )
43 1 Bh Pressure Safety Valve 65
44 1 Bh Siamese Conection Two Way

VI PEKERJAAN INSTALASI LISTRIK


1 1 Ttk Bongkar Instalasi Penerangan
2 1 Ttk Bongkar Instalasi Stop Kontak 200 W
3 1 Ttk Bongkar Instalasi Stop Kontak AC
4 1 Ttk Pekerjaan Titik Instalasi Lampu Penerangan
5 1 Ttk Pasang Titik Instalasi Stop Kontak 200 W
6 1 Ttk Pasang Titik Instalasi Stop Kontak Khusus
7 1 Bh Pekerjaan Lampu TL 2 x 18
8 1 Bh Pasang TL. TKI RM 1 x 20 W
9 1 Bh Pasang TL. TKI RM 1 x 40 W
10 1 Bh Pasang TL. TKI RM 3 x 20 W
11 1 Bh Pasang Lampu Baret Isi TL Bulat 20 W
12 1 Bh Pasang Lampu Downlight PLS 11 W
13 1 Bh Pasang Saklar Engkel
14 1 Bh Pekerjaan Saklar Lampu
15 1 Bh Pasang Stop Kontak 200 W. MK
16 1 Bh Pasang Stop Kontak Khusus
17 1 Bh Pasang AC Split Type Model Dinding STY 22A ( Wirless 8900 Btu/h )

367593161.xls-Printed on -10/03/2017-03:02:57 8/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
PEKERJAAN KABEL TOEVOER
1 1 M' Pas. Kabel Toevoer NYFGBY 4 x 50 mm2. Dari KWH Meter ke Panel Induk
2 1 M Galian Tanah
3 1 M Urugan Kembali
4 1 M' Pas. Kabel Toevoer NYFGBY 4 x 25 mm2.

PEKERJAAN PANEL INDUK


1 1 Bh Bok Panel Uk. 129 x 120 x 40
2 1 Bh MCCB 3P/200A-250A
3 1 Bh MCCB 3P/50A
4 1 Bh Kunci Lips
5 1 Bh Lampu Pilot
6 1 Bh Volt Meter 0-500 VA
7 1 Bh Ampere Meter
8 1 Bh Selector Switch ( A/M )
9 1 Btg Cu Busbar
10 1 Lot Interal Wearing

PEKERJAAN PANEL TENAGA dan PENERANGAN


1 1 Bh Bok Panel Uk. 69 x 59 x 40
2 1 Bh MCCB 3P/25A
3 1 Bh MCCB 3P/40A
3 1 Bh MCB 1P/6A
4 1 Bh MCB 1P/10A
5 1 Bh MCB 1P/16A

07 PEKERJAAN BETON

1 1 M Membuat beton tumbuk, 1Pc : 3Ps : 5Kr


2 1 M Membuat beton tumbuk, 1Pc : 3Ps : 6Kr
3 1 M Membuat beton tumbuk, 1Pc : 4Ps : 6Kr
4 1 M Membuat lantai kerja beton tumbuk, 1Pc : 3Ps : 5Kr, tebal 5 Cm
5 1 M Membuat beton tumbuk, 1Pc : 2Ps : 3Kr
6 1 M Membuat beton bertulang, 1Pc : 2Ps : 4Kr
7 1 M Membuat beton bertulang, 1Pc : 2Ps : 2.5Kr
8 1 M Membuat beton bertulang, 1Pc : 1.5Ps : 3Kr
9 1 M Membuat beton bertulang, 1Pc : 1.5Ps : 2.5Kr
10 1 M Membuat beton bertulang, 1Pc : 1Ps : 2Kr
11 1 M Membuat tiang pancang prestressed beton
12 1 M Membuat beton dengan puzzolith 100 x R
13 1 M Membuat beton bertulang, 1Pc : 2Ps : 3Split
14 1 M Membuat beton bertulang, 1Pc : 2Ps : 4Split
15 1 M Membuat beton bertulang, 1Pc : 1.5Ps : 3Split
16 1 M Membuat beton bertulang, 1Pc : 1.5Ps : 2.5Split
17 1 M Membuat beton bertulang, 1Pc : 1Ps : 1Split
18 1 M Membuat beton kedap air dengan strorox 100
19 1 M' Memasang PVC Waterstop lebar 150 mm
20 1 M' Memasang PVC Waterstop lebar 200 mm
21 1 M' Memasang PVC Waterstop lebar 230 mm
22 1 M' Memasang PVC Waterstop lebar 250 mm
23 1 M' Memasang PVC Waterstop lebar 300 mm
24 1 M' Memasang PVC Waterstop lebar 320 mm
25 1 Kg Pembesian dengan besi polos atau ulir
26 1 Kg Kabel presstresed polos/strands
27 1 Kg Jaring kawat baja
28 1 M Pasang bekesting untuk pondasi
29 1 M Pasang bekesting untuk sloof
30 1 M Pasang bekesting untuk kolom ( a )
31 1 M Pasang bekesting untuk balok
32 1 M Pasang bekesting untuk lantai
33 1 M Pasang bekesting untuk kolom ( b )
34 1 M Pasang bekesting untuk kolom ( c )
35 1 M Bekesting Multiplek 9mm
36 M Bekesting Dengan Papan
37 1 M Pasangan Stoot Werk
38 1 M Pasangan Stoot Werk ( Scafolding )
38 1 M Membuat Beton Dengan Mutu K - 175
39 1 M Membuat Beton Dengan Mutu K - 225
40 1 M Membuat Beton Dengan Mutu K - 250
41 1 M Membuat Beton Dengan Mutu K - 275
42 1 M Membuat Beton Dengan Mutu K - 300
43 1 M Pasang jembatan cor
44 1 M Membuat Pond. Beton Bertulang ( 150 Kg Besi + Bekesting )
45 1 M Membuat Sloof Beton Bertulang ( 200 Kg Besi + Bekesting )
46 1 M Membuat Kolom Beton Bertulang ( 300 Kg Besi + Bekesting )
47 1 M Membuat Kolom Beton Bertulang ( 150 Kg Besi + Bekesting )
48 1 M Membuat Dinding Beton Bertulang ( 150 Kg Besi + Bekesting )
49 1 M Membuat Dinding Beton Bertulang ( 200 Kg Besi + Bekesting )
50 1 M Membuat Kolom Penguat Beton Bertulang ( 11 x 11 Cm )
51 1 M Membuat Ring Balok Beton Bertulang ( 10 x 15 Cm )
52 1 M Cor Beton Ready Mix K350. Berikut Slang
53 1 M Cor Beton Ready Mix K300. Berikut Slang
54 1 M Cor Beton Ready Mix K250. Berikut Slang

367593161.xls-Printed on -10/03/2017-03:02:57 9/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
08 PEKERJAAN LANTAI

1 1 M Lantai Keramik 60 x 60 ( GRANITO )


2 1 M Lantai Keramik 40 x 40 ( GRANITO )
3 1 M Lantai Keramik 20 x 20 ( ROMAN )
4 1 M Dinding Keramik 20 x 25 ( ROMAN )
5 1 M Plint Keramik 8 x 20 ( ROMAN )
6 1 M Lantai Keramik 40 x 40
7 1 M Lantai Keramik 30 x 30 ( ROMAN )
8 1 M Lantai Keramik 40 x 40 ( ROMAN )
9 1 M' Plint Keramik 15 x 40 ( ROMAN )
10 1 M' Plint Keramik 15 x 30 ( ROMAN )

09 PEKERJAAN PENUTUP ATAP

1 1 M Pasang atap genteng palentong kecil


2 1 M Pasang atap genteng kodok / glazzur
3 1 M Pasang atap genteng palentong super / besar
4 1 M Pasang atap genteng bubung palentong
5 1 M' Pasang bubung genteng kodok glazzur
6 1 M' Pasang bubung genteng palentong besar
7 1 M Pasang Atap Genteng Glazur
8 1 Bh Pasang Hiasan Akhir Genteng Glazur
9 1 Bh Pasang Pemanas Air Genteng Glazur
10 1 M' Pasang Nok Genteng Glazur
11 1 Bh Pasang Penangkal Petir Genteng Glazur
12 1 M' Pasang Lisplank Kiri Genteng Glazur
13 1 M' Pasang Lisplank Kiri Hiasan Akhir Genteng Glazur ( Type KE. 3 HA )
14 1 M' Pasang Lisplank Kanan Genteng Glazur
15 1 M' Pasang Lisplank Kanan Hiasan Akhir Genteng Glazur ( Type KE. 4 HA )
16 1 Bh Pasang Setengah Genteng Glazur
17 1 Bh Pasang Ujung Jurai Genteng Glazur
18 1 Bh Pasang Ujung Nok Kanan Genteng Glazur
19 1 Bh Pasang Ujung Nok Kiri Genteng Glazur
20 1 Bh Pasang Nok 3 Arah Kanan Genteng Glazur
21 1 Bh Pasang Nok 3 Arah Kiri Genteng Glazur
22 1 Bh Pasang Hiasan Sudut Jurai Genteng Glazur
23 1 Bh Pasang Nok 2 Arah Genteng Glazur
24 1 M Pasang Nok 2 Arah Kanan Genteng Glazur
25 1 M Pasang Nok 2 Arah Kiri Genteng Glazur
26 1 M Pasang Nok 4 Arah Jurai Genteng Glazur
27 1 M Pasang Genteng Talang
28 1 M Pasang roof light fibreglass ( 180 x 90 ) cm
29 1 M Pasang atap asbes gelombang 2.5 x 0.92 x 5
30 1 M Pasang atap asbes gelombang 2250 x 920 x 5 mm
31 1 M Pasang atap asbes gelombang 2000 x 920 x 5 mm
32 1 M Pasang atap asbes gelombang 1800 x 920 x 5 mm
33 1 M Pasang atap asbes gelombang 3000 x 1050 x 4 mm
34 1 M Pasang atap asbes gelombang 2700 x 1050 x 4 mm
35 1 M Pasang atap asbes gelombang 2400 x 1050 x 4 mm
36 1 M Pasang atap asbes gelombang 2100 x 1050 x 4 mm
37 1 M Pasang atap asbes gelombang 1800 x 1050 x 4 mm
38 1 M Pasang atap asbes gelombang 1500 x 1050 x 4 mm
39 1 M Pasang atap asbes gelombang 3000 x 1080 x 6 mm
40 1 M Pasang atap asbes gelombang 2700 x 1080 x 6 mm
41 1 M Pasang atap asbes gelombang 2400 x 1080 x 6 mm
42 1 M Pasang atap asbes gelombang 2100 x 1080 x 6 mm
43 1 M Pasang atap asbes gelombang 1800 x 1080 x 6 mm
44 1 M Pasang bubung stel gelombang 0.92 m
45 1 M Pasang nok stel gelombang 1.05 m
46 1 M Pasang nok stel gelombang 1.08 m
47 1 M Pasang nok paten 1.92 m
48 1 M Pasang nok paten 1.05 m
49 1 M Pasang nok stel rata 0.92 m
50 1 M Pasang atap genteng beton
51 1 M Pasang atap genteng aspal
52 1 M Pasang atap genteng metal
53 1 M Pasang atap sirap
54 1 M Pasang atap nok genteng beton
55 1 M Pasang atap nok genteng aspal
56 1 M Pasang atap nok genteng metal
57 1 M Pasang nok sirap
58 1 M Pasang atap seng gelombang
59 1 M Pasang atap nok seng
60 1 M Pasang atap aluminium
61 1 M Pasang nok aluminium
62 1 M Pasang Atap Hi-Ten TCT 0,45 mm Colorbond - Golden SR-1000
63 1 M Pasang Clading Hi-Ten TCT 0,45 mm Colorbond
64 1 M Capping Flashing
65 1 M Ridge Flashing
66 1 M Pasang aluminium foil
67 1 M Pasang atap genteng Keramik
68 1 M
69 1 M
70 1 M
71 1 M
72 1 M
73 1 M

367593161.xls-Printed on -10/03/2017-03:02:57 10/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
09 PEKERJAAN LANGIT-LANGIT

1 1 M Langit - langit asbes 1 x 1m , tebal 6 mm


2 1 M Langit - langit asbes 1 x 1m , tebal 5 mm
3 1 M Langit - langit asbes 1 x 1m , tebal 4 mm
4 1 M Langit - langit asbes 1 x 1m , tebal 3,5 mm
5 1 M Langit - langit akustik 30 x 30 cm
6 1 M Langit - langit akustik 30 x 60 cm
7 1 M Langit - langit akustik 60 x 120 cm
8 1 M Langit - langit plywood 30 x 60 x 0,4 cm
9 1 M Langit - langit plywood 30 x 60 x 0,6 cm
10 1 M Langit - langit plywood 60 x 120 x 0,4 cm
11 1 M Langit - langit plywood 60 x 120 x 0,6 cm
12 1 M Langit - langit teakwood 30 x 60 x 0,4 cm
13 1 M Langit - langit teakwood 60 x 120 x 0,4 cm
14 1 M Langit - langit lat kayu jati
15 1 M Langit - langit lat kayu ramin
16 1 M Langit - langit lat kayu kamper
17 1 M Langit - langit softboard
18 1 M Langit - langit akustik 60 x 120 + rangka alumunium
19 1 M' List langit - langit kayu propil
20 1 M' List langit - langit gypsum
21 1 M Langit - langit asbes 1 x 1 m (t =3,2 mm), rangka borneo
22 1 M Langit - langit plywood 4 mm + rangka kayu borneo
23 1 M Langit - langit akustik 30 x 60 cm + rangka kayu borneo
24 1 M Langit - langit akustik 30 x 30 cm + rangka kayu borneo
25 1 M Langit - langit gypsum board 9 mm + rangka kayu borneo
26 1 M Langit - langit GRC board 6 mm + rangka kayu borneo
27 1 M Langit - langit gypsumboard , tebal 9 mm

10 PEKERJAAN PIPA dan SANITER

1 1 Bh Memasang 1 buah kloset duduk / monoblok


2 1 Bh Memasang 1 buah kloset jongkok porselen
3 1 Bh Memasang 1 buah kloset jongkok teraso
4 1 Bh Memasang 1 buah urinoir
5 1 Bh Memasang 1 buah washtafel
6 1 Bh
7 1 Bh
8 1 Bh
9 1 Bh
10 1 Bh
11 1 Bh
12 1 Bh
13 1 Bh
14 1 Bh
15 1 Bh
16 1 Bh
17 1 Bh
18 1 Bh
19 1 Bh
20 1 Bh
21 1 Bh
22 1 Bh
23 1 Bh
24 1 M' Memasang 1M' pipa PVC tipe AW dia. 1/2"
25 1 Bh Memasang 1M' pipa PVC tipe AW dia. 3/4"
26 1 Bh Memasang 1M' pipa PVC tipe AW dia. 1"
27 1 M' Memasang 1M' pipa PVC tipe AW dia. 1,5"
28 1 M' Memasang 1M' pipa PVC tipe AW dia. 2"
29 1 M' Memasang 1M' pipa PVC tipe AW dia. 2,5"
30 1 M' Memasang 1M' pipa PVC tipe AW dia. 3"
31 1 M' Memasang 1M' pipa PVC tipe AW dia. 4"
32 1 M' Memasang 1M' pipa PVC tipe AW dia. 6"
33 1 M' Memasang 1M' pipa PVC tipe AW dia. 8"
34 1 M' Memasang 1M' pipa BSP. SCH 40 - Dia. 65
35 1 M' Memasang 1M' pipa BSP. SCH 40 - Dia. 80
36 1 M' Memasang 1M' pipa BSP. SCH 40 - Dia. 100
37 1 M' Memasang 1M' pipa BSP. SCH 40 - Dia. 150
38 1 Bh Memasang 1 buah bak cuci piring stainless steel 1 Lobang
39 1 Bh Memasang 1 buah bak cuci piring stainless steel 2 Lobang
40 1 Bh Memasang 1 buah bak cuci piring teraso
41 1 Bh Memasang 1 buah kran dia. 3/4" atau 1/2"
42 1 Bh Memasang 1 buah Floor Drain
43 1 Bh Memasang 1 Buah Kran Angsa
44 1 Bh Memasang 1 Buah Tempat Sabun
45 1 Bh Memasang 1 Buah Kaca Cermin
46 1 Bh Memasang 1 Buah Buth-Tab
47 1 Bh Memasang 1 Buah Box Shower
48 1 Bh Memasang 1 Buah Hand Shower
49 1 Bh Memasang 1 Buah Jet Washer
50 1 Bh Memasang 1 Buah Tissue Holder
51 1 Bh Memasang 1 Buah Towel Holder
52 1 Bh Memasang 1 Buah Cloth Holder
53 1 M Memasang Grouting

367593161.xls-Printed on -10/03/2017-03:02:57 11/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )
11 PEKERJAAN BESI / ALUMINIUM

1 1 Kg Pasang rangka atap baja


2 1 M
3 1 Unit Pasang Pintu Slidding Besi
4
5 1 M Pasang pintu alumunium
6
7
8 1 M Pasang pintu rolling door Per M2
9 1 Unit Pasang pintu rolling door Per Unit

10 PEKERJAAN KUSEN/PINTU ALUMINIUM HITAM ( CENTRAL OFFICE )


1 1 Unit Pasang Pintu Alumunium Type P1
2 1 Unit Pasang Pintu Alumunium Type P2
3 1 Unit Pasang Pintu Alumunium Type P3
4 Pi 1 Unit Pasang Pintu PVC
5 1 Unit Pasang Pintu Alumunium Type P2a
6 1 Unit Pasang Jendela Alumunium Type J1
7 1 Unit Pasang Jendela Alumunium Type J1a
8 1 Unit Pasang Jendela Alumunium Type J2
9 1 Unit Pasang Jendela Alumunium Type J2a
10 1 Unit Pasang Pintu Alumunium Type P2B
11 1 Unit Pasang Jendela Alumunium Type BV1
12 1 Unit Pasang Jendela Alumunium Type JL1
13 1 Unit Pasang Ornamen Sopi-sopi

10 PEKERJAAN KUSEN/PINTU ALUMINIUM HITAM ( MILL OFFICE )


1 1 Unit Pasang Pintu Alumunium Type P.1-MO
2 1 Unit Pasang Pintu Alumunium Type P.1a-MO
3 1 Unit Pasang Pintu Alumunium Type P.2-MO
4 Pi 1 Unit Pasang Pintu PVC
5 1 Unit Pasang Pintu Alumunium Type P.2a-MO
6 1 Unit Pasang Jendela Alumunium Type J.1-MO
7 1 Unit Pasang Jendela Alumunium Type J.2-MO
8 1 Unit Pasang Jendela Alumunium Type J.3-MO
9 1 Unit Pasang Jendela Alumunium Type J.4-MO
10 1 Unit Pasang Jendela Alumunium Type J.5-MO
11 1 Unit Pasang Jendela Alumunium Type J.6-MO
12 1 Unit Pasang Jendela Alumunium Type BV.1-MO
13 1 Unit Pasang Jendela Alumunium Type BV.2-MO
14 1 Unit Pasang Jendela Alumunium Type BV.3-MO
15 1 Unit Pasang Jendela Alumunium Type BV.4-MO

12 PEKERJAAN CAT / PELITUR

1 1 M Mendempul, sekali cat dasar ( baru )


2 1 M Dua kali mencat mengkilap
3 1 M Mendasar, menggosok dan 2 kali mencat kilap
4 1 M Pekerjaan plitur sederhana
5 1 M Pekerjaan cat tembok ( a )
6 10 M Pekerjaan cat tembok ( b )
7 10 M Pekerjaan cat kayu / besi
8 1 M Pekerjaan Cat Tembok ( Weathershield )
9 1 M Pekerjaan Cat Tembok ( Maxilite )
10 1 M Pekerjaan Melamik
11 1 Kg Pekerjaan Cat Baja
12 1 M Waterproof + Screed Dak

13 PEKERJAAN PERKERASAN JALAN

1 1 Bln Biaya menggilas


2 1 M Pemasangan alas jalan t=15 Cm ( Paklaag batu kali )
3 1 M Pemasangan Lap. Kulit penahan t=8 Cm, setelah digilas
4 1 Bln Biaya gilas selama 1 Bln ( 30 Hari ), pakai Wals
5 1 M Pengaspalan dengan aspal panas
6 1 M Pasir dibawah alas jalan
7 1 M Lapis batu pecah t=10 Cm
8 1 M Lapis pondasi t=5 Cm
9 1 M Lapis permukaan t = 6 Cm
10 1 M Sosotan aspal
11 1 M Beton Bertulang 1 : 2 : 3 U/ Plat Duiker Type A/B, Besi = 110 Kg/M3
12 1 M Pasangan Cor Beton Kanstin 1 : 2 : 3
13 1 M' Pasangan Cor Beton Kanstin 1 : 2 : 3 Per M'
14 1 M' Pasangan Kanstin Batu Bata 1 : 2 Per M'
15 1 M' Pasangan Kanstin Batu Bata 1 : 4 Per M'
16 1 M Pasangan Paving Block

14 PEKERJAAN TIANG PANCANG


1 1 M' Pengadaan 1 M' Tiang Pancang Segi Empat Uk. 200 x 200mm
2 1 M' Pengangkatan 1 M' Tiang Pancang Segi Empat Uk. 200 x 200mm
3 1 M' Pemancangan 1 M' Tiang Pancang Segi Empat Uk. 200 x 200mm
3a 1 M' Pemancangan 1 M' Tiang Pancang Segi Empat Uk. 250 x 250mm ( Jack Push )
4 1 Bh Pemotongan 1 Bh Tiang Pancang Segi Empat Uk. 250 x 250mm

1 1 M' Pengadaan 1 M' Tiang Pancang Segi Empat Uk. 400 x 400mm
2 1 M' Pengangkatan 1 M' Tiang Pancang Segi Empat Uk. 400 x 400mm
3 1 M' Pemancangan 1 M' Tiang Pancang Segi Empat Uk. 400 x 400mm
4 1 Bh Pemotongan 1 Bh Tiang Pancang Segi Empat Uk. 400 x 400mm

15 PEKERJAAN WATERPROFING
1 1 M Waterprofing Membran

367593161.xls-Printed on -10/03/2017-03:02:57 12/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )

367593161.xls-Printed on -10/03/2017-03:02:57 13/16


NO URAIAN PEKERJAAN HAR. SATUAN HAR. SATUAN TOTAL HARGA
BAHAN UPAH UPAH + BAHAN
( Rp ) ( Rp ) ( Rp )

367593161.xls-Printed on -10/03/2017-03:02:57 14/16


Civil and Structure Works
Dimension
No Description Total Lot Panjang (m)
1 Guard Office 1 4
2 Weighbridge 1 6
3 General Office 1 21
4 Garage/Car Building 1 21.5
Motorcycle Building 1 19.5
5 Laboratory 1
6 Workshop and Store Building 1 34
7 CMC Auto Control/Supervisor Room 1 6
8 Schedule Waste Store & Scrap Yard 1
9 Worker Toilet 1
10 FFB Ramp Hopper 1
11 Sterilizer Building 1 85
12 Main Process Building 1
13 Power House and Foundation 1
14 Boiler House and Foundation 1
15 EFB Shredding/Press Building Foundation 1
16 To concrete the EFB Dump Site 1
17 All Floor Slab and Machinery Foundation for 60 ton/hr 1
18 Internal Road (Mill Compound) 1
19 Fencing and Gate (Provisional Sum) 1
20 Effluent Pond Piping 1
21 General
22 Grader Shed 1 6
23 Steriliser Pit & Pump House 1
24 Hydrocyclone Waste Pit & Pump House 1
25 Sludge Pit & Pump House 1
26 Effluent Recycle Pump House 1 6
27 Final Dischage Pump House 1 6
28 Perimeter Drain 1 894
29 Monsoon Drain 1
30 Boiler Ash Collection Site 1
31 Any Other items necessary but not stated above
Reservoir Pump House 1
Structure Works
Dimension
Tinggi/Tebal Volume/Luas Volume sesuai
Lebar (m) Satuan
(m) (Pembulatan) Gambar
3.5 14.00 m2
4 24.00 m2
15 315.00 m2
4.5 96.75 m2
4 78 m2

15 510 m2
4 24 m2

1550 m2
32.5 2762.5 m2
1704 m2

4 24 m2

4 24 m2
4 24 m2
894 m2