Anda di halaman 1dari 15

HARGA SATUAN UPAH & BAHAN

PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT

A UPAH TENAGA
1 Kepala Tukang OH
2 Tukang Kayu Khusus OH
3 Tukang (Batu, Besi, Kayu) OH
4 Tenaga Instalatir OH
5 Mandor OH
6 Pekerja / Pembantu Tukang OH
B MATERIAL BETON
1 Semen PC @50 Kg Kg
2 Semen Putih Kg
3 Semen warna Kg
4 Semen Gypsum / Cornice Kg
5 Tanah Urug m3
6 Pasir Pasang / Pasir Beton m3
7 Pasir Urug m3
8 Batu Kali / Belah / Gunung m3
9 Kerikil m3
10 Batu Bata Bh
11 Batako Bh
C MATERIAL BESI / ALUM / S.STEEL / KACA
1 Besi Kg
2 Baja Ringan Profil C.75x39x0.75mm m'
3 Baja Ringan Profil U 39x33x20x0.75 m'
4 Baja Ringan Hollow 4x4 m'
5 Besi Hollow 40 x 40 x 1.5 mm m'
6 Besi Hollow 40 x 60 x 1.5 mm m'
7 Stainles Steel Dia. 3/4" / Hollow 40 x 40 x 1.5mm m'
8 Stainles Steel Dia. 2" m'
9 Besi Siku 60 x 60 x 6 mm m'
10 Besi Siku 70 x 70 x 6 mm m'
27 Besi Strip 40 x 5 mm m'
11 Profil-C Alumunium m'
12 Profil-M Kusen Alumunium 4" m'
13 Profil tutup Kusen Alumunium 4" m'
14 Profil L Spigot m'
15 Profil Alumunium Silver Tegak Pintu (Moher / Polos) m'
16 Profil Alumunium Silver Ambang Atas Pintu m'
17 Profil Alumunium Silver Ambang Bawah Pintu m'
18 Profil Alumunium Silver Tutup Ambang Bawah Pintu m'
19 Profil Bingkai Jendela Alumunium Silver m'
20 Profil Tutup Bingkai Jendela Alumunium Silver m'
21 Profil Jendela (Skoneng) m'
22 Bendrat / Kawat Beton Kg
23 Angker Besi 14 mm Bh
24 Baut + Mur Angker Psg
25 Paku Screw / Skrup Bh
26 Dynabolt 10 mm Bh
28 Paku Kg
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT
29 Paku Tripleks Kg
30 Paku Seng Kg
31 Paku Atap Bitumen Selulosa Bh
32 Kaca Rayban 5mm m2
33 Kaca Bening 5 mm m2
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT

D MATERIAL KAYU
1 Kayu Kelas I Lokal - Kayu Kosen m3
2 Kayu Kelas I Lokal - Kayu Kusen / Daun Pintu Jendela m3
3 Kayu Kelas II - Kayu Rangka Plafond / Atap / Kusen m3
4 Kayu Kelas III - Kayu Bekisting m3
5 Tripleks 4 mm Lbr
6 Multipleks 9 mm m2
7 Multipleks 12 mm m2
8 Multipleks 16 mm m2
9 Kayu Profil List 5 cm / SP.5 m'
10 Lem Kayu Kg
11 Dolken Kayu dia.8-10cm, 4 meter Btg
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT

E AKSESORIS PINTU DAN JENDELA


1 Kunci Pintu 2 Slag Kw.Baik Set
2 Espagnyolet Tanam Bh
3 Tarikan Jendela Bh
4 Engsel Pintu 4" Bh
5 Engsel Jendela 3" Bh
6 Grendel Pintu Bh
7 Grendel Jendela Bh
8 Kait Angin Biasa Psg
9 Kait Jendela Casement Psg
10 Door Closer Bh
11 Karet Kaca m'
12 Sealant Tube
13 Kaca Tempered 12mm m2
14 Top Hinge Bh
15 Floor Hinge Bh
16 Sandblast Sticker kaca m²
17 Fitting Sudut Bh
18 Fitting Lock Bh
19 Door Holder/Handle (Biasa) Psg
20 Door Holder/Handle ~ 1 1/2" (40 cm) Stainless Psg

F MATERIAL PENUTUP ATAP & AKSESORIS


1 Atap Gelombang Zincalume/Galvalume Coating (Warna) Lbr
2 Atap Gelombang BJLS (Seng) m'
3 Atap Gelombang Bitumen Selulosa m2
4 Seng Plat BJLS 28 m'
5 Genteng Metal Lbr
6 Genteng Bitumen Selulosa Lbr
7 Bubungan / Nok Paten Seng m'
8 Bubungan / Nok Paten Genteng Metal m'
9 Bubungan / Nok Paten Bitumen Selulosa m'
10 Talang U - PVC m'
11 Talang U - PVC (Besi Kait Dudukan ) Bh
12 Talang U - PVC (Corong) Bh
13 Talang U - PVC (Penutup) Bh
14 Talang U - PVC (Sambungan) Bh
G MATERIAL PENUTUP LANTAI & AKSESORIS
1 Keramik Plint 10 x 40 cm Bh
2 Keramik Lantai 20 x 20 cm Dos
3 Keramik Lantai 30 x 30 cm Dos
4 Keramik Lantai 40 x 40 cm Dos
5 Keramik Dinding 20 x 20 cm Bh
6 Keramik Dinding 20 x 25 cm Bh
7 Keramik Dinding 20 x 40 cm Bh
8 Granit 30 x 30 cm Dos
9 Granit 40 x 40 cm Dos
10 Granit 60 x 60 cm Dos
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT
11 Parquet Kayu m2
12 Batu Alam Andesit / Candi / Palimanan m2
13 Pavingblock 6 cm Bh
14 Pavingblock 8 cm Bh
H MATERIAL LANGIT-LANGIT
1 Gypsum 9 mm Lbr
2 Gypsum Profil 7-10 cm m'
3 Kalsiboard 3.8 mm / 4 mm Lbr
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT

I MATERIAL CAT
1 Cat Tembok Indoor Kw.1 (5 kg) Kg
2 Cat Tembok Indoor Kw.2 (Setara Metrolite) 5 Kg Kg
3 Cat Besi / Kayu Kg
4 Plamur @ 5 Kg Kg
5 Cat Menie (Besi / Kayu) Kg
6 Minyak Cat / Thinner / Pengencer Kg
7 Kuas Bh
8 Amplas Lbr
J MATERIAL SANITASI
1 Pipa PVC Dia. 1/2 " m'
2 Pipa PVC-AW 3/4" m'
3 Pipa PVC Dia. 2 " m'
4 Pipa PVC Dia. 4 " m'
5 Pipa Galvanis Dia. 1/2" inci m'
6 Pipa PE Dia. 1/2 inci m'
7 Mata Kran 1/2" Stainlses Bh
8 Klosed Duduk Non Tabung + Tutup Bh
9 Klosed Jongkok Lokal Bh
10 Urinoir Bh
11 Bak Cuci Stainless 1 mata Bh
12 Wastafel Lengkap Bh
13 Flooor Drain Bh
14 Seal Tape Bh
15 Ijuk Gulung
K MATERIAL LISTRIK
1 Kabel NYM 3 x 2,5 mm m'
2 Pipa PVC 5/8" Btg
3 MCB 16 Amp Bh
4 Rumah 1-2 MCB Bh
5 Rumah 3-4 MCB Bh
6 Rumah Saklar / Kontak (Mongkok) Bh
7 Saklar Tunggal Tanam Bh
8 Saklar Ganda Tanam Bh
9 Stop Kontak Tanam 1 Mata Bh
9 Stop Kontak Tanam 2 Mata Bh
10 Selotip Listrik Unibell / setara Bh
11 Tee Dos / Box Saklar / Box Kontak Bh
12 L-Bow Bh
13 Klem Kabel Bh
14 Lampu TL 1 x 38/40 Watt (Neon) + Armatur + Trafo Set
15 Lampu LED 13 Watt Bh
16 Lampu LED 9 Watt Bh
17 Lampu LED 6 Watt Bh
18 Lampu LED 3 Watt Bh
19 Fitting Downlight Bh
20 Fitting Tempel Bh
L LAIN - LAIN / ALAT BANTU
HARGA SATUAN UPAH & BAHAN
PEKERJAAN ………………………
LOKASI ………………………
ANGGARAN 2017

NO URAIAN SAT
1 Cetak Informasi Proyek m2
2 Pengelasan cm
3 Benang Nylon Bh
4 Bensin Ltr
5 Solar Ltr
6 Concrete Mixer Jam
7 Perlengkapan Alat bantu (Batu,Kayu, Plumbing, Listrik,Las) Ls
8 Terpal 3 x 4 m Bh
9 Selang Air m1
10 Pelumas Bekisting Ltr
11 Air Ltr
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN

125,000.00
100,000.00
100,000.00
50,000.00
90,000.00
80,000.00

1,400.00
2,500.00
15,000.00
2,400.00
75,000.00
135,000.00
100,000.00
165,000.00
165,000.00
825.00
3,000.00

11,000.00
14,167.00
10,000.00
9,167.00
14,167.00
20,833.00
29,167.00
37,500.00
64,167.00
70,833.00
9,167.00
47,500.00
54,167.00
29,167.00
9,167.00
71,591.00
79,545.00
96,591.00
30,833.00
70,833.00
29,167.00
29,167.00
18,000.00
12,000.00
5,000.00
500.00
7,500.00
28,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN
28,000.00
28,000.00
1,000.00
135,000.00
120,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN

7,000,000.00
7,000,000.00
4,000,000.00
2,800,000.00
76,000.00
43,403.00
55,556.00
76,389.00
8,750.00
27,000.00
15,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN

175,000.00
40,000.00
7,500.00
17,500.00
13,500.00
12,000.00
8,000.00
22,000.00
35,000.00
325,000.00
2,500.00
37,000.00
1,200,000.00
450,000.00
1,200,000.00
68,000.00
450,000.00
750,000.00
75,000.00
175,000.00

49,000.00
34,444.00
158,000.00
34,444.00
36,000.00
58,000.00
12,000.00
52,000.00
88,000.00
18,750.00
6,000.00
9,000.00
5,000.00
5,000.00

2,750.00
55,000.00
60,000.00
68,000.00
2,151.00
2,925.00
6,415.00
215,000.00
285,000.00
325,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN
425,000.00
250,000.00
4,000.00
5,000.00

76,000.00
17,500.00
79,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN

55,000.00
25,000.00
62,000.00
45,000.00
24,000.00
20,000.00
5,000.00
5,000.00

2,000.00
4,000.00
20,833.00
54,167.00
6,000.00
8,000.00
125,000.00
550,000.00
325,000.00
4,500,000.00
450,000.00
1,750,000.00
75,000.00
5,000.00
30,000.00

9,500.00
15,000.00
60,000.00
15,000.00
25,000.00
4,000.00
20,000.00
24,000.00
20,000.00
24,000.00
12,500.00
5,000.00
3,000.00
250.00
150,000.00
85,000.00
85,000.00
65,000.00
42,000.00
45,000.00
25,000.00
RGA SATUAN UPAH & BAHAN

HARGA
SATUAN
50,000.00
2,500.00
7,500.00
11,000.00
10,500.00
40,000.00
35%
90,000.00
8,500.00
30,000.00
10.00
ANALISA HARGA SATUAN PEKERJAAN

1 Penggalian 1 M3 tanah biasa sedalam 1 M


0.75 OH pekerja RP ### = RP ###
0.03 OH mandor RP ### = RP ###
RP ###

2 Pemasangan 1 M3 pondasi batu belah cmpuran 1SP : 3PP


A TENAGA
### OH pekerja RP 80000 = RP 120000
0.75 OH Tukang batuRP 100000 = RP 75000
0.08 OH Kepala Tuka RP 125000 = RP 9375

B BAHAN
### OH batu belah RP ### = RP ###

Anda mungkin juga menyukai