Anda di halaman 1dari 6

HARGA JUMLAH JUMLAH

NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA


(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
16 BEKISTING KOLOM BETON 1 M2
Bahan :
Kayu/ Papan Kls. III 0.040 M3 Rp 2,000,000.00 Rp 80,000.00
Paku 0.400 Kg Rp 15,000.00 Rp 6,000.00
Minyak Bekisting 0.200 Ltr Rp 2,000.00 Rp 400.00
Kayu Kls. II ( Papan ) 0.015 M3 Rp 2,500,000.00 Rp 37,500.00
Dolken Kayu Galam/ Bambu 2.000 Btg Rp 7,500.00 Rp 15,000.00
Polywood 9 mm 0.350 Lbr Rp 90,000.00 Rp 31,500.00
Upah :
Pekerja 0.660 Org Rp 45,000.00 Rp 29,700.00
Tukang Kayu 0.330 Org Rp 50,000.00 Rp 16,500.00
Kepala Tukang 0.033 Org Rp 55,000.00 Rp 1,815.00
Mandor 0.033 Org Rp 55,000.00 Rp 1,815.00
Jumlah Rp 170,400.00 Rp 49,830.00
Harga Satuan 0.50 Rp 110,115.00
17 COR KOLOM K1 (40/40) BETON K-250/ M3
( A ) Beton K-250 1.000 M3 Rp 1,355,425.00 Rp 1,355,425.00
( B ) Pembesian 100 Kg 3.000 100Kg Rp 1,254,000.00 Rp 3,762,000.00
( C ) Bekisting/ Cetakan/ M3 10.000 M2 Rp 110,115.00 Rp 1,101,150.00
Jumlah Rp 4,863,150.00
Harga Satuan 1 Rp 4,863,150.00
18 COR KOLOM K2 (40/40) BETON K-250/ M3
( A ) Beton K-250 1.000 M3 Rp 1,355,425.00 Rp 1,355,425.00
( B ) Pembesian 100 Kg 3.000 100Kg Rp 1,254,000.00 Rp 3,762,000.00
( C ) Bekisting/ Cetakan/ M3 10.000 M2 Rp 110,115.00 Rp 1,101,150.00
Jumlah Rp 4,863,150.00
Harga Satuan 1 Rp 4,863,150.00
19 COR KOLOM PRAKTIS 12 x 12 BETON K-225/ M3
( A ) Beton K-225 1.000 M3 Rp 693,125.53 Rp 693,125.53
( B ) Pembesian 100 Kg 2.570 100Kg Rp 1,254,000.00 Rp 3,222,780.00
( C ) Bekisting/ Cetakan/ M3 16.667 M2 Rp 110,115.00 Rp 1,835,286.71
Jumlah Rp 5,058,066.71
Harga Satuan 1 Rp 5,058,066.71
20 COR BALOK PRAKTIS 12 x 15 BETON K-225/ M3
( A ) Beton K-225 1.000 M3 Rp 693,125.53 Rp 693,125.53
( B ) Pembesian 100 Kg 2.264 100Kg Rp 1,254,000.00 Rp 2,839,056.00
( C ) Bekisting/ Cetakan/ M3 16.667 M2 Rp 51,980.00 Rp 866,350.66
Jumlah Rp 3,705,406.66
Harga Satuan 1 Rp 3,705,406.66
21 COR BALOK LISTPLANK (15 x 40) BETON K-250/ M3
( A ) Beton K-250 1.000 M3 Rp 1,355,425.00 Rp 1,355,425.00
( B ) Pembesian 100 Kg 1.445 100Kg Rp 1,254,000.00 Rp 1,812,030.00
( C ) Bekisting/ Cetakan/ M3 13.333 M2 Rp 51,980.00 Rp 693,049.34
Jumlah Rp 2,505,079.34
Harga Satuan 1 Rp 2,505,079.34
22 PASANG KACA 5 mm/ M2
Bahan :
Kaca Polos 1.100 M2 Rp 110,000.00 Rp 121,000.00
Upah :
Pekerja 0.015 Org Rp 45,000.00 Rp 675.00
Tukang Kayu 0.150 Org Rp 50,000.00 Rp 7,500.00
Kepala Tukang 0.015 Org Rp 55,000.00 Rp 825.00
Mandor 0.001 Org Rp 55,000.00 Rp 55.00
Jumlah Rp 121,000.00 Rp 9,055.00
Harga Satuan 1 Rp 130,055.00
23 PASANG KUSEN ALUMUNIUM/ M
Bahan :
Kusen Alumunium 1.050 M1 Rp 45,000.00 Rp 47,250.00
Perlengkapan ( 15% x Kusen ) 0.100 Rp 6,750.00 Rp 675.00
Upah :
Pekerja 0.015 Org Rp 45,000.00 Rp 675.00
Tukang Kayu 0.150 Org Rp 50,000.00 Rp 7,500.00
Kepala Tukang 0.015 Org Rp 55,000.00 Rp 825.00
Mandor 0.0075 Org Rp 55,000.00 Rp 412.50
Jumlah Rp 47,925.00 Rp 9,412.50
Harga Satuan 1 Rp 57,337.50
24 VERTICAL BLINDS/ M2
Bahan :
Ventilation Blinds dan Vertical Blinds 1.000 M2 Rp 180,000.00 Rp 180,000.00
Upah :
Pekerja 0.350 Org Rp 45,000.00 Rp 15,750.00
Tukang Kayu 0.350 Org Rp 50,000.00 Rp 17,500.00
Kepala Tukang 0.035 Org Rp 55,000.00 Rp 1,925.00
Mandor 0.0180 Org Rp 55,000.00 Rp 990.00
Jumlah Rp 180,000.00 Rp 36,165.00
Harga Satuan 1 Rp 216,165.00
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
25 PASANG RANGKA JENDELA/ PINTU ALUMUNIUM/ M
Bahan :
Kusen Alumunium 1.050 M1 Rp 45,000.00 Rp 47,250.00
Perlengkapan ( 15% x Kusen ) 0.150 Rp 6,750.00 Rp 1,012.50
Upah :
Pekerja 0.015 Org Rp 45,000.00 Rp 675.00
Tukang Kayu 0.150 Org Rp 50,000.00 Rp 7,500.00
Kepala Tukang 0.015 Org Rp 55,000.00 Rp 825.00
Mandor 0.0008 Org Rp 55,000.00 Rp 44.00
Jumlah Rp 48,262.50 Rp 9,044.00
Harga Satuan 1 Rp 57,306.50
26 JENDELA J1 / UNIT
Bahan :
Frame Alumunium 27.900 M' Rp 57,337.50 Rp 1,599,716.25
Frame Daun Jendela 18.960 M' Rp 57,306.50 Rp 1,086,531.24
Kaca Polos 5 mm 10.200 M2 Rp 130,055.00 Rp 1,326,561.00
Karet Kaca/ Sealent 39.200 M' Rp 2,500.00 Rp 98,000.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 4.000 Bh Rp 10,000.00 Rp 40,000.00
Grendel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Engsel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Hak Angin Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Vertical Blinds 0.000 M2 Rp 216,165.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 4,390,808.49 Rp -
Harga Satuan 1 Rp 4,390,808.49
27 JENDELA J2 / UNIT
Bahan :
Frame Alumunium 39.200 M' Rp 57,337.50 Rp 2,247,630.00
Frame Daun Jendela 18.960 M' Rp 57,306.50 Rp 1,086,531.24
Kaca Polos 5 mm 16.320 M2 Rp 130,055.00 Rp 2,122,497.60
Karet Kaca/ Sealent 60.000 M' Rp 2,500.00 Rp 150,000.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp - Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 4.000 Bh Rp 10,000.00 Rp 40,000.00
Grendel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Engsel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Hak Angin Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Vertical Blinds 0.000 M2 Rp 216,165.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 5,886,658.84 Rp -
Harga Satuan 1 Rp 5,886,658.84
28 JENDELA J3 / UNIT
Bahan :
Frame Alumunium 23.550 M' Rp 57,337.50 Rp 1,350,298.13
Frame Daun Jendela 19.770 M' Rp 57,306.50 Rp 1,132,949.51
Kaca Polos 5 mm 9.180 M2 Rp 130,055.00 Rp 1,193,904.90
Karet Kaca/ Sealent 34.800 M' Rp 2,500.00 Rp 87,000.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp - Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 4.000 Bh Rp 10,000.00 Rp 40,000.00
Grendel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Engsel Jendela Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Hak Angin Alumunium 8.000 Bh Rp 10,000.00 Rp 80,000.00
Vertical Blinds 0.000 M2 Rp 216,165.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 4,044,152.53 Rp -
Harga Satuan 1 Rp 4,044,152.53
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
29 JENDELA J4 / UNIT
Bahan :
Frame Alumunium 15.000 M' Rp 57,337.50 Rp 860,062.50
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 5.440 M2 Rp 130,055.00 Rp 707,499.20
Karet Kaca/ Sealent 20.000 M' Rp 2,500.00 Rp 50,000.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp - Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 1,617,561.70 Rp -
Harga Satuan 1 Rp 1,617,561.70
30 JENDELA J7 / UNIT
Bahan :
Frame Alumunium 14.520 M' Rp 57,337.50 Rp 832,540.50
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 3.128 M2 Rp 130,055.00 Rp 406,812.04
Karet Kaca/ Sealent 14.520 M' Rp 2,500.00 Rp 36,300.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp - Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 1,275,652.54 Rp -
Harga Satuan 1 Rp 1,275,652.54
31 PINTU P1 / UNIT
Bahan :
Frame Alumunium 11.900 M' Rp 57,337.50 Rp 682,316.25
Frame Daun Jendela 20.240 M' Rp 57,306.50 Rp 1,159,883.56
Kaca Polos 5 mm 5.680 M2 Rp 130,055.00 Rp 738,712.40
Karet Kaca/ Sealent 13.500 M' Rp 2,500.00 Rp 33,750.00
Pintu Teak Wood 6 mm L/D (Jati) 0.000 Bh Rp - Rp -
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 4.000 Bh Rp 10,000.00 Rp 40,000.00
Engsel Pintu 6.000 Bh Rp 15,000.00 Rp 90,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 4.000 Bh Rp 10,000.00 Rp 40,000.00
Hak Angin Alumunium 4.000 Bh Rp 10,000.00 Rp 40,000.00
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 3,004,662.21 Rp -
Harga Satuan 1 Rp 3,004,662.21
32 PINTU P2 / UNIT
Bahan :
Frame Alumunium 39.700 M' Rp 57,337.50 Rp 2,276,298.75
Frame Daun Jendela 5.800 M' Rp 57,306.50 Rp 332,377.70
Kaca Polos 5 mm 8.648 M2 Rp 130,055.00 Rp 1,124,715.64
Karet Kaca/ Sealent 45.550 M' Rp 2,500.00 Rp 113,875.00
Gipsum Board 9 mm 7.682 Lbr Rp 60,000.00 Rp 460,920.00
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 2.000 Bh Rp 10,000.00 Rp 20,000.00
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 4,553,187.09 Rp -
Harga Satuan 1 Rp 4,553,187.09
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
33 PINTU P3 / UNIT
Bahan :
Frame Alumunium 28.600 M' Rp 57,337.50 Rp 1,639,852.50
Frame Daun Jendela 5.800 M' Rp 57,306.50 Rp 332,377.70
Kaca Polos 5 mm 6.768 M2 Rp 130,055.00 Rp 880,212.24
Karet Kaca/ Sealent 30.690 M' Rp 2,500.00 Rp 76,725.00
Gipsum Board 9 mm 6.012 Lbr Rp 60,000.00 Rp 360,720.00
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 2.000 Bh Rp 10,000.00 Rp 20,000.00
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 3,534,887.44 Rp -
Harga Satuan 1 Rp 3,534,887.44
34 PINTU P4 / UNIT
Bahan :
Frame Alumunium 11.100 M' Rp 57,337.50 Rp 636,446.25
Frame Daun Jendela 5.800 M' Rp 57,306.50 Rp 332,377.70
Kaca Polos 5 mm 1.880 M2 Rp 130,055.00 Rp 244,503.40
Karet Kaca/ Sealent 9.430 M' Rp 2,500.00 Rp 23,575.00
Gipsum Board 9 mm 1.670 Lbr Rp 60,000.00 Rp 100,200.00
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 2.000 Bh Rp 10,000.00 Rp 20,000.00
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 1,582,102.35 Rp -
Harga Satuan 1 Rp 1,582,102.35
35 PINTU P5 / UNIT
Bahan :
Frame Alumunium 5.000 M' Rp 57,337.50 Rp 286,687.50
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 0.000 M2 Rp 130,055.00 Rp -
Karet Kaca/ Sealent 0.000 M' Rp 2,500.00 Rp -
Pintu Alumunium+Asesoris 1.670 M2 Rp 3,000,000.00 Rp 5,010,000.00
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 2.000 Bh Rp 10,000.00 Rp 20,000.00
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 5,541,687.50 Rp -
Harga Satuan 1 Rp 5,541,687.50
36 PINTU P6 / UNIT
Bahan :
Frame Alumunium 32.150 M' Rp 57,337.50 Rp 1,843,400.63
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 6.768 M2 Rp 130,055.00 Rp 880,212.24
Karet Kaca/ Sealent 36.120 M' Rp 2,500.00 Rp 90,300.00
Gipsum Board 9 mm 6.012 Lbr Rp 60,000.00 Rp 360,720.00
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 3,219,632.87 Rp -
Harga Satuan 1 Rp 3,219,632.87
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
37 PINTU P7 / UNIT
Bahan :
Frame Alumunium 38.700 M' Rp 57,337.50 Rp 2,218,961.25
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 8.178 M2 Rp 130,055.00 Rp 1,063,589.79
Karet Kaca/ Sealent 0.000 M' Rp 2,500.00 Rp -
Gipsum Board 9 mm 7.265 Lbr Rp 60,000.00 Rp 435,900.00
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 3,718,451.04 Rp -
Harga Satuan 1 Rp 3,718,451.04
38 PINTU P13 / UNIT
Bahan :
Frame Alumunium 30.800 M' Rp 57,337.50 Rp 1,765,995.00
Frame Daun Jendela 5.800 M' Rp 57,306.50 Rp 332,377.70
Kaca Polos 5 mm 7.740 M2 Rp 130,055.00 Rp 1,006,625.70
Karet Kaca/ Sealent 36.120 M' Rp 2,500.00 Rp 90,300.00
Gipsum Board 9 mm 4.068 Lbr Rp 60,000.00 Rp 244,080.00
Kunci Pintu 2 x Slagh 1.000 Bh Rp 180,000.00 Rp 180,000.00
Grendel Pintu 2.000 Bh Rp 10,000.00 Rp 20,000.00
Engsel Pintu 3.000 Bh Rp 15,000.00 Rp 45,000.00
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 3,684,378.40 Rp -
Harga Satuan 1 Rp 3,684,378.40
39 VENTILASI V1 / UNIT
Bahan :
Frame Alumunium 2.000 M' Rp 57,337.50 Rp 114,675.00
Frame Daun Jendela 0.000 M' Rp 57,306.50 Rp -
Kaca Polos 5 mm 0.240 M2 Rp 130,055.00 Rp 31,213.20
Karet Kaca/ Sealent 0.000 M' Rp 2,500.00 Rp -
Gipsum Board 9 mm 0.000 Lbr Rp 60,000.00 Rp -
Kunci Pintu 2 x Slagh 0.000 Bh Rp 180,000.00 Rp -
Grendel Pintu 0.000 Bh Rp 10,000.00 Rp -
Engsel Pintu 0.000 Bh Rp 15,000.00 Rp -
Tarikan Jendela/ Ventilasi Alumunium 0.000 Bh Rp 10,000.00 Rp -
Grendel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Engsel Jendela Alumunium 0.000 Bh Rp 10,000.00 Rp -
Hak Angin Alumunium 0.000 Bh Rp 10,000.00 Rp -
Upah :
Pemasangan 0.000 Bhn Rp - Rp -
Jumlah Rp 145,888.20 Rp -
Harga Satuan 1 Rp 145,888.20
40 PEKERJAAN PENGELASAN/ 10 Cm
Bahan :
Solar 0.300 Ltr Rp 5,500.00 Rp 1,650.00
Minyak Pelumas 0.040 Ltr Rp 30,000.00 Rp 1,200.00
Kawat Las 0.400 Btg Rp 5,000.00 Rp 2,000.00
Upah :
Pekerja 0.040 Org Rp 45,000.00 Rp 1,800.00
Tukang 0.020 Org Rp 50,000.00 Rp 1,000.00
Kepala Tukang 0.002 Org Rp 55,000.00 Rp 110.00
Mandor 0.002 Org Rp 55,000.00 Rp 110.00
Alat 0.170 Bhn Rp 4,850.00 Rp 824.50
Jumlah Rp 4,850.00 Rp 3,844.50
Harga Satuan 1 Rp 8,694.50
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN KOFESIEN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
41 PASANG TERALIS PINTU/ JENDELA/ M2
Bahan :
Besi Beton Ø 10 6.000 Kg Rp 11,000.00 Rp 66,000.00
Besi Strip # 5 mm 0.230 Kg Rp 10,000.00 Rp 2,300.00
Pengelasan 0.043 10 Cm Rp 8,694.50 Rp 373.86
Upah :
Pekerja 1.670 Org Rp 45,000.00 Rp 75,150.00
Tukang 1.670 Org Rp 50,000.00 Rp 83,500.00
Kepala Tukang 0.167 Org Rp 55,000.00 Rp 9,185.00
Mandor 0.083 Org Rp 55,000.00 Rp 4,565.00
Jumlah Rp 68,673.86 Rp 172,400.00
Harga Satuan 1 Rp 241,073.86
42 PAS. BATU BATA 1:4/ M2
Bahan :
Batu Bata 70.000 Bh Rp 1,000.00 Rp 70,000.00
Portland Cement (PC) 11.500 Kg Rp 1,140.00 Rp 13,110.00
Pasir Pasang 0.043 M3 Rp 80,000.00 Rp 3,440.00
Upah :
Pekerja 0.300 Org Rp 45,000.00 Rp 13,500.00
Tukang Batu 0.100 Org Rp 50,000.00 Rp 5,000.00
Kepala Tukang 0.010 Org Rp 55,000.00 Rp 550.00
Mandor 0.015 Org Rp 55,000.00 Rp 825.00
Jumlah Rp 86,550.00 Rp 19,875.00
Harga Satuan 1 Rp 106,425.00
43 PAS. BATU BATA 1:2/ M2
Bahan :
Batu Bata 70.000 Bh Rp 1,000.00 Rp 70,000.00
Portland Cement (PC) 18.950 Kg Rp 1,140.00 Rp 21,603.00
Pasir Pasang 0.038 M3 Rp 80,000.00 Rp 3,040.00
Upah :
Pekerja 0.300 Org Rp 45,000.00 Rp 13,500.00
Tukang Batu 0.100 Org Rp 50,000.00 Rp 5,000.00
Kepala Tukang 0.010 Org Rp 55,000.00 Rp 550.00
Mandor 0.015 Org Rp 55,000.00 Rp 825.00
Jumlah Rp 94,643.00 Rp 19,875.00
Harga Satuan 1 Rp 114,518.00
44 PLESTERAN 1:4/ M2
Bahan :
Portland Cement (PC) 6.240 Kg Rp 1,140.00 Rp 7,113.60
Pasir Pasang 0.024 M3 Rp 80,000.00 Rp 1,920.00
Upah :
Pekerja 0.300 Org Rp 45,000.00 Rp 13,500.00
Tukang Batu 0.150 Org Rp 50,000.00 Rp 7,500.00
Kepala Tukang 0.015 Org Rp 55,000.00 Rp 825.00
Mandor 0.015 Org Rp 55,000.00 Rp 825.00
Jumlah Rp 9,033.60 Rp 22,650.00
Harga Satuan 1 Rp 31,683.60
45 PLESTERAN 1:2/ M2
Bahan :
Portland Cement (PC) 10.224 Kg Rp 1,140.00 Rp 11,655.36
Pasir Pasang 0.024 M3 Rp 80,000.00 Rp 1,920.00
Upah :
Pekerja 0.300 Org Rp 45,000.00 Rp 13,500.00
Tukang Batu 0.150 Org Rp 50,000.00 Rp 7,500.00
Kepala Tukang 0.015 Org Rp 55,000.00 Rp 825.00
Mandor 0.010 Org Rp 55,000.00 Rp 550.00
Jumlah Rp 13,575.36 Rp 22,375.00
Harga Satuan 1 Rp 35,950.36
46 PASANG KERAMIK DINDING KM/ WC Uk. 25x40 Cm/ M2
Bahan :
Keramik Dinding KM/ WC Uk. 25 x 40 10.000 Bh Rp 5,000.00 Rp 50,000.00
Portland Cement (PC) 0.228 Zak Rp 57,000.00 Rp 12,996.00
Pasir Pasang 0.042 M3 Rp 80,000.00 Rp 3,360.00
Tepung AA 1.500 Kg Rp 4,000.00 Rp 6,000.00
Upah :
Pekerja 0.620 Org Rp 45,000.00 Rp 27,900.00
Tukang Batu 0.350 Org Rp 50,000.00 Rp 17,500.00
Kepala Tukang 0.035 Org Rp 55,000.00 Rp 1,925.00
Mandor 0.030 Org Rp 55,000.00 Rp 1,650.00
Jumlah Rp 72,356.00 Rp 48,975.00
Harga Satuan 1 Rp 121,331.00