K BAHAN PVC
1 PVC 2,5" X 4.00 m type D m' 11,500.00
2 PVC 3/4" X 4.00 m type D m' 25,000.00
3 PVC 3/4" X 4.00 m type D m' 35,000.00
4 PVC 3" X 4.00 m type D m' 11,000.00
5 PVC 4" X 4.00 m type D m' 14,000.00
6 Pipa PVC 4" type AW pj 6 m ljr 350,000.00
7 Pipa PVC 3" type AW pj 6 m ljr 254,500.00
8 Pipa PVC 2,5" type AW pj 6 m ljr 225,000.00
9 PVC 5/8" X 4.00 m (pralon) ljr 5,500.00
I PEKERJAAN PERSIAPAN
1 Pengukuran & Bouwplank 8.00 7.00
II PEKERJAAN TANAH
1 Galian Tanah Pondasi 41.50 0.60 0.50
2 Urugan Tanah Kembali & Perataan
2 Benangan Dinding
4 Kol-kolan 69.00
V PEKERJAAN BETON
1 Beton sloof pondasi (12/18) 41.50 0.12 0.18
IX PEKERJAAN UTILITAS
1 Floor drain
2 Bak mandi fiberglass
3 Closet jongkok
4 Pipa PVC dia. 1/2" (Type D)
5 Pipa PVC dia. 2" (Type D) 11.21
6 Pipa PVC dia. 3" (Type D)
7 Bak kontrol + tutup
8 Sumur bor 3m + pompa listrik
9 Septictank & Resapan
10 Pipa PVC dia. 3/4" (AW)
11 Kran air
X PEKERJAAN FINISHING
1 Cat tembok exterior weatherbond
XI PEKERJAAN LAIN-LAIN
1 Rabatan car port t = 6 cm
2 Plat jembatan masuk
3 Pembersihan akhir
Volume Satuan
38.00 m'
12.45 m3
4.98 m3
8.10
9.00
17.10 m3
66.30
115.15
181.45 m2
4.94 pj1
3.78 j2
2.16
pj2
0.90
1.87 j3
1.30 j4
2.52 j1
1.37 p2
3.85 p1
2.13 j5
0.32 j6
25.15 luas kusen t.bt p. bt
156.30 m2 0.045 0.21 0.01495
10454.90 bh
t. pas. Semen
8.82 m' 0.02
196.00 bh
0.02 312.60 m2
6.25 m3
17.84
24.32
13.2
8.40
12.72
10.88
13.20
10.64
111.20 m'
62.76 m'
0.90 m3
0.22
0.68
0.90 m3
0.54 m3
0.29
0.07
0.36 m3
1.32
0.33
1.66 m3
0.07
0.05
0.11 m3
24.94
32.93
57.88 m2
21.40 m'
57.88 m2
1331.13 bh
7.60 m'
49.4 m2
17.15 lbr
7.32
11.87
8.68
4.00
5.21
2.15
2.00
4.90
10.36
56.49 m'
1.00 bh
3.00 bh
1.00 bh
5.00 bh
60.59 m'
1.00 bh
3.00 bh
3.00 bh
9.00 bh
5.00 bh
1.00 set
10.00 bh
9.00
9.00
12.00
5.00
35.00 m2
2.64 m2
5.80
4.35
10.15
9.14 m2
4.80
0.40
5.20 m2
1.00 bh
1.00 bh
1.00 bh
2.00 bh
1.00 bh
1.00 bh
2.00 bh
46.89 m2
3.94
3.94
7.02
14.89 m2
RENCANA ANGGARAN BIAYA
( RAB )
Harga
No. JENIS PEKERJAAN Volume Sat.
( Rp.)
I PEKERJAAN PERSIAPAN
1 Pengukuran & bowplank 38.00 m'
II PEKERJAAN TANAH
1 Galian tanah pondasi 12.45 m3
2 Urug tanah kembali & perataan 4.98 m3
3 Urug sirtu peninggian lantai 17.10 m3
IV PEKERJAAN PLESTERAN
1 Plester dinding (1 : 6) + aci 6.25 m3
2 Benangan dinding
3 Tali air 111.20 m'
4 Kol - kolan 62.76 m'
V PEKERJAAN BETON
1 Beton sloof pondasi (12/18) 0.90 m3
2 Beton kolom praktis (12/12) 0.90 m3
3 Beton kolom (12/25)
4 Beton ring-balk (12/12) + Balok gantung 0.54 m3
5 Beton gewel (12/12) 0.36 m3
6 Plat kanopy 0.11 m3
IX PEKERJAAN UTILITAS
1 Floor drain
2 Bak mandi fiber
3 Closet jongkok
4 Pipa PVC dia. 3" (Type D)
5 Pipa PVC dia. 4" (Type D)
6 Bak kontrol + tutup
7 Sumur bor 12 m + pompa listrik
8 Septictank & Resapan
9 Pipa PVC dia. 3/4" (AW)
10 Kran air
X PEKERJAAN FINISHING
1 Cat tembok Exterior WeatherBond
2 Cat tembok interior + plafon
3 Cat kosen + lisplank ex-emco
4 Cat daun pintu
5 Cat genting MATEX
XI PEKERJAAN LISTRIK
1 Instalasi titik lampu
2 Saklar tunggal
3 Saklar ganda
4 Stop Kontak
5 Fitting lampu biasa