JUMLAH HARGA
NO U RAIAN PE K E R JAAN
( Rp )
JUMLAH 21,053,721,089.45
PPN 10% 2,105,372,108.95
JUMLAH TOTAL 23,159,093,198.40
DIBULATKAN 23,159,000,000.00
TOTAL 23,159,000,000.00
Terbilang : DUA PULUH TIGA MILYAR SERATUS LIMA PULUH SEMBILAN JUTA RUPIAH
2 Pek.Sloop 20 x 40
- Cor beton mutu beton K - 225 m³ 77.78 3,159,723.14 245,765,793.45
- Besi 8 Ø 16 mutu baja BJTP 24 ( polos ) kg 12,291.64 21,125.39 259,665,669.26
- Besi sengkang Ø 8 - 200 mutu baja BJTP 24 ( polos ) kg 2,035.76 21,125.39 43,006,241.93
- Bakesting di pakai Bakesting kayu Kls II m² 583.36 215,538.80 125,735,849.88
3 Pek.Plat Lantai t 8 cm
- Cor beton mutu beton K - 225 m³ 186.72 3,159,723.14 589,983,504.33
- Besi sengkang Ø 8 - 200 ( bawah ) mutu baja BJTP 24 ( polos ) kg 7,375.84 21,125.39 155,817,559.62
- Bakesting di pakai Bakesting kayu Kls II m² 33.50 271,379.57 9,091,215.53
2 Pek.Penutup Atap
-Pek.Penutup atap Zingcalum + Lap.Insulasi Panas termasuk alumunium voil +glass m2 2,809.62 416,432.41 1,170,016,836.21
-Pek Bubung atap metal sheet m' 142.20 92,382.41 13,136,779.13
-Pek.Zincalium 20 x 35 m2 2,809.62 81,354.00 228,573,825.48
-Pek.Zincalium 40 x 75 m2 2,809.62 96,720.00 271,746,446.40
-Pek.Seng Talang ( Jurai ) m' 215.12 278,341.91 59,876,910.60
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 162.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
1 Plat Lantai t = 12 cm
Beton K.250 169.47 kg/m3 m3 123.12 Dilaksanakan Tahap - 1
Besi polos kg 20,865.06 Dilaksanakan Tahap - 1
Bekisting m2 19.59 Dilaksanakan Tahap - 1
2 Tie Beam TB1. 300x500
Beton K.250 315.35 kg/m3 m3 72.55 Dilaksanakan Tahap - 1
Besi polos kg 4,091.25 Dilaksanakan Tahap - 1
Besi Peminggang kg 626.65 Dilaksanakan Tahap - 1
Besi ulir kg 18,159.71 Dilaksanakan Tahap - 1
Bekisting m2 483.64 Dilaksanakan Tahap - 1
3 Tie Beam CTB. 300x500
Beton K.250 315.35 kg/m3 m3 4.20 Dilaksanakan Tahap - 1
Besi polos kg 236.86 Dilaksanakan Tahap - 1
Besi Peminggang kg 36.28 Dilaksanakan Tahap - 1
Besi ulir kg 1,051.34 Dilaksanakan Tahap - 1
Bekisting m2 28.00 Dilaksanakan Tahap - 1
4 Tie Beam CTB.1 250x450
Beton K.250 234.52 kg/m3 m3 11.25 Dilaksanakan Tahap - 1
Besi polos kg 740.19 Dilaksanakan Tahap - 1
Besi Peminggang kg 259.14 Dilaksanakan Tahap - 1
Besi ulir kg 1,639.05 Dilaksanakan Tahap - 1
Bekisting m2 90.00 Dilaksanakan Tahap - 1
3 Kolom K1. 500x500
Beton K.250 194.87 kg/m3 m3 15.00 Dilaksanakan Tahap - 1
Besi ulir ( Sengkang ) kg 693.91 Dilaksanakan Tahap - 1
Besi ulir kg 2,229.11 Dilaksanakan Tahap - 1
Bekisting m2 120.00 Dilaksanakan Tahap - 1
4 Kolom K2.Ø. 500.
Beton K.250 204.56 kg/m3 m3 31.4 Dilaksanakan Tahap - 1
Besi ulir ( Sengkang ) kg 1,328.11 Dilaksanakan Tahap - 1
Besi ulir kg 5,095.10 Dilaksanakan Tahap - 1
A 404288434.xls Divisi : Strutkur
Hal. 5 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 0.000
1 Plat Lantai t = 13 cm .
Beton K.250 156.43 kg/m3 m3 127.03 Dilaksanakan Tahap - 1
Besi polos kg 19,871.64 Dilaksanakan Tahap - 1
Bekisting m2 977.15 Dilaksanakan Tahap - 1
2 Kolom K3. 500x500
Beton K.250 200.80 kg/m3 m3 12.00 Dilaksanakan Tahap - 1
Besi ulir ( Sengkang ) kg 555.13 Dilaksanakan Tahap - 1
Besi ulir kg 1,854.47 Dilaksanakan Tahap - 1
Bekisting m2 96.00 Dilaksanakan Tahap - 1
3 Kolom K4.dia. 500.
Beton K.250 211.04 kg/m3 m3 21.98 Dilaksanakan Tahap - 1
Besi ulir ( Sengkang ) kg 929.68 Dilaksanakan Tahap - 1
Besi ulir kg 3,708.94 Dilaksanakan Tahap - 1
Bekisting m2 175.84 Dilaksanakan Tahap - 1
4 Balok G1. 400x700
Beton K.250 231.41 kg/m3 m3 14.27 Dilaksanakan Tahap - 1
Besi polos kg 1,457.52 Dilaksanakan Tahap - 1
Besi Peminggang kg 407.50 Dilaksanakan Tahap - 1
Besi ulir kg 1,437.86 Dilaksanakan Tahap - 1
Bekisting m2 87.64 Dilaksanakan Tahap - 1
5 Balok G2. 400x700
Beton K.250 251.56 kg/m3 m3 29.18 Dilaksanakan Tahap - 1
Besi polos kg 2,980.23 Dilaksanakan Tahap - 1
A 404288434.xls Divisi : Strutkur
Hal. 6 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 0.000
1 Plat Canopy t = 12 cm .
Beton K.250 139.82 kg/m3 m3 18.85 Dilaksanakan Tahap - 1
A 404288434.xls Divisi : Strutkur
Hal. 7 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 0.000
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 200.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
1 Plat Lantai t = 12 cm
Beton K.250 231.33 kg/m3 m3 98.40 #REF! #REF!
Besi polos kg 22,762.44 #REF! #REF!
Bekisting m2 23.63 #REF! #REF!
2 Kolom K1. 300x300
Beton K.250 216.43 kg/m3 m3 2.70 #REF! #REF!
Besi polos kg 148.08 #REF! #REF!
Besi ulir kg 436.27 #REF! #REF!
Bekisting m2 36.00 #REF! #REF!
3 Kolom K2. 250x250
Beton K.250 298.49 kg/m3 m3 1.88 #REF! #REF!
Besi polos kg 123.40 #REF! #REF!
Besi ulir kg 436.27 #REF! #REF!
Bekisting m2 30.00 #REF! #REF!
4 Kolom K2A. Ø.300
Beton K.250 260.68 kg/m3 m3 4.24 #REF! #REF!
Besi polos kg 232.49 #REF! #REF!
Besi ulir kg 872.54 #REF! #REF!
Bekisting m2 56.52 #REF! #REF!
5 Kolom K3. 300x400
Beton K.250 350.96 kg/m3 m3 9.60 #REF! #REF!
B 404288434.xls Divisi : Strutkur
Hal. 14 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
: Kabupaten Maybrat - Papua Barat
Tahun Anggara : 2017 0.000
1 Plat Lantai t = 12 cm
Beton K.250 105.92 kg/m3 m3 102.30 #REF! #REF!
Besi polos kg 10,835.19 #REF! #REF!
Bekisting m2 852.48 #REF! #REF!
2 Kolom K1. 300x300
Beton K.250 216.43 kg/m3 m3 0.90 #REF! #REF!
Besi polos kg 49.36 #REF! #REF!
Besi ulir kg 145.42 #REF! #REF!
Bekisting m2 12.00 #REF! #REF!
3 Kolom K2. 250x250
Beton K.250 298.49 kg/m3 m3 1.88 #REF! #REF!
Besi polos kg 123.40 #REF! #REF!
Besi ulir kg 436.27 #REF! #REF!
Bekisting m2 30.00 #REF! #REF!
B 404288434.xls Divisi : Strutkur
Hal. 16 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
: Kabupaten Maybrat - Papua Barat
Tahun Anggara : 2017 0.000
1 Plat Lantai t = 12 cm
Beton K.250 105.92 kg/m3 m3 48.30 #REF! #REF!
Besi polos kg 5,115.60 #REF! #REF!
Bekisting m2 402.48 #REF! #REF!
2 Balok B1. 300x650
Beton K.250 199.98 kg/m3 m3 26.91 #REF! #REF!
Besi polos kg 1,992.91 #REF! #REF!
Besi ulir kg 3,388.62 #REF! #REF!
Bekisting m2 220.80 #REF! #REF!
3 Balok B2. 300x500
Beton K.250 237.76 kg/m3 m3 1.80 #REF! #REF!
Besi polos kg 133.31 #REF! #REF!
Besi ulir kg 294.66 #REF! #REF!
Bekisting m2 15.60 #REF! #REF!
4 Balok B3. 200x300
Beton K.250 118.97 kg/m3 m3 0.54 #REF! #REF!
Besi polos kg 6.40 #REF! #REF!
Besi ulir kg 57.84 #REF! #REF!
Bekisting m2 7.20 #REF! #REF!
5 Balok B4. 200x300
Beton K.250 118.97 kg/m3 m3 0.36 #REF! #REF!
Besi polos kg 4.27 #REF! #REF!
Besi ulir kg 38.56 #REF! #REF!
Bekisting m2 4.80 #REF! #REF!
6 Balok B5. 250x400
Beton K.250 204.90 kg/m3 m3 10.20 #REF! #REF!
Besi polos kg 215.71 #REF! #REF!
Besi ulir kg 1,874.27 #REF! #REF!
Bekisting m2 107.10 #REF! #REF!
SUB TOTAL. III.2.3. LANTAI TRIBUNE. : #REF!
15 a 6 0.2 23 4.6 0.22 1.02
b 6 0.3 23 6.9 0.22 1.53
kait 6 0.06 23 1.38 0.22 0.31
15
30
100
8
20
20 20
30
30
20 20
30
30
20
bekisting 226.7587
a 6 1 8 8 0.22 1.78
kait 6 0.06 8 0.48 0.22 0.11
a 8 1 8 8 0.40 3.16
kait 8 0.08 8 0.64 0.40 0.25
20 280 20
20 20 20
20 280 20
300
20 280 20
20 20 20
20 280 20
300
55
15
50
10 105
30 5
120
145
165
100
125
40
5 30
15 10
5 5
105
40 20 40
100
5000
105 41 17 42 510
100
Jumlah Dimensi
No Uraian Satuan Volume Ket.
Item Panjang Lebar Tinggi Luasan
11
c
a
32
a 10 0.32 7 2.24 0.62 1.38
b 10 0.66 7 4.62 0.62 2.85
c 10 0.22 7 1.54 0.62 0.95
kait 10 0.1 7 0.7 0.62 0.43
11
c
15
a
40
10 105
80
135
10 20
5 10 80 10 5
Jumlah Dimensi
No Uraian Satuan Volume Ket.
Item Panjang Lebar Tinggi Luasan
c PEKERJAAN PLAFOND
1 Pas.Gypsum 9mm + Rangka Hollo galvanis ,ukuran 40 x 40 mm m² 1,458.48 167,523.47 244,329,630.53
f PEKERJAAN PENGECETAN
1 Pek.Pengecetan Dinding Interior dgn Cat tembok Interior ex.Dulux m² 5,384.80 24,744.12 133,242,134.15
2 Pek.Pengecetan Dinding Exterior dgn Cat tembok Exterior ex.Dulux m² 1,703.48 26,954.12 45,915,803.32
3 Pek.Pengecetan Dinding Interior ( OK,Tindakan Kebidanan )dgn Cat Epoxy m² 207.91 210,840.33 43,835,812.89
4 Pek.Pengecetan Plafound dgn Cat tembok Interior ex.Dulux m² 1,628.22 35,051.13 57,070,950.89
5 Pek.Pengecetan Plafound dgn Cat tembok Exterior ex.Dulux m² 853.29 37,261.13 31,794,549.62
6 Pek.Water Profing Liquid di topi Jendela m² 21.73 246,640.57 5,359,499.59
A PEKERJAAN ELEKTRIKAL
I. Pekerjaan Penyambungan Daya Listrik
- Penyambungan Daya Listrik 90 KVA lot 1.00 315,000,000.00 315,000,000.00
-Terminal Penangkal Petir Non Radio Aktip ( Radius proteksi Max.100 mtr ) c/w Tiang GIP dia 2" set 1.00 32,581,340.00 32,581,340.00
tinggi 7 mtr + dudukan dan lampu Obstruction 100 W
- Instalasi kabel,NYY 70 mm2 dalam pipa PVC Class AW dia 40 mm m 31.00 283,428.85 8,786,294.35
- Grounding System max 2 ohm unit 1.00 3,229,309.20 3,229,309.20
- Bak Kontrol 40 x 40 x40 cm unit 1.00 575,400.00 575,400.00
- Certificate Tes dan surat Perijinan Depnaker Lot 1.00 9,590,000.00 9,590,000.00
3. Pekerjaan KabelPower
- Kabel ITC 10 Pairs 2 x 0,6 mm2 dari TB Telkom ke MDF - TP m 15.00 82,768.55 1,241,528.25
- Kabel ITC 50 Pairs 2 x 0,6 mm2 dari MDF - TP ke PABX m 10.00 372,605.75 3,726,057.50
- Kabel ITC 30 Pairs 2 x 0,6 mm2 dari PABX ke TB-TLP m 10.00 227,691.15 2,276,911.50
2. Pekerjaan Kabel
- Kabel dari Switch Hub ke Patch Panel 30 Port,Belden Cat 6 m 10.00 250,984.00 2,509,840.00
- Assesories
- Wall Outlet Oksigen bh 63.00 1,771,382.60 111,597,103.80
- Bed Head unit 50.00 4,603,200.00 230,160,000.00
- Ruang Radiologi
- Pipa Liquit Ø 6,4 mm m 5.00 47,643.12 238,215.60
- Pipa Gas Ø 12,7 mm m 5.00 93,052.97 465,264.85
- Ruang Farmasi
- Pipa Liquit Ø 6,4 mm m 3.00 47,643.12 142,929.36
- Pipa Gas Ø 9,5 mm m 3.00 70,720.26 212,160.78
- Ruang OK
- Pipa Liquit Ø 9,5 mm m 15.00 70,720.26 1,060,803.90
- Pipa Gas Ø 22,5 mm m 15.00 167,495.35 2,512,430.25
3. Pekerjaan Pemipaan Drain dengan Isolasi tebal 1", density 24 Kg/m ³ c/w Fiitting - fitting
- Pipa PVC Ø 25 mm m 13.00 231,667.00 3,011,671.00
- Pipa PVC Ø 20 mm m 30.00 175,579.00 5,267,370.00
- Exhaust Fan Type Axial Wall Kap 300 CFM ,125 w/ 1P c/w EAG di R Pompa m 24.00 65,828.50 1,579,884.00
- Kabel Power NYM 3 x 2,5 mm2
- Pekerjaan Kabel Power untuk semua unit Exhaust Fan di area toilet di gabung dengan instalasi lampu yang
di toilet ( NYM 3 x 2,5 mm2 ) m 20.00 65,828.50 1,316,570.00
b.Pengadaan dan Pemasangan Pompa Transfer c/w Panel Kontrol dan Accessories Unit 1.00 6,400,468.75 6,400,468.75
Kapasitas : 75 ltr/menit
Head : 60 meter
Putaran : 3000 Rpm
Daya : 250 w / 220 / 1P / 50 Hz
c.Pengadaan dan Pemasangan Sand Filler c/w Panel Kontrol dan Accessories Unit 1.00 14,037,705.00 14,037,705.00
Type Filler : SF - 1865
Dimensi : Ø 450 x 1650 mm ( T )
Material : Fiberglass Reinforced Plastice
Kapasitas : 3,5 m3/Jam
Media Filler : 115 litter Sand Silica
Media Pendukung : 50 litter Sand Gravel
Sistem Backwash : Manual
Kelengkapan :
1 bh FRP Tank Ø 450 x 1650 mm (T)
1 bh Multiport Valve
1 bh Top stainer
1 bh Bottom stainer
d.Pengadaan dan Pemasangan Carbon Filler c/w Panel Kontrol dan Accessories Unit 1.00 19,158,080.00 19,158,080.00
Type Filler : SF - 1865
Dimensi : Ø 450 x 1650 mm ( T )
Material : Fiberglass Reinforced Plastice
Kapasitas : 3,5 m3/Jam
Media Filler : 165 litter Carbon Active
Sistem Backwash : Manual
Kelengkapan :
1 bh FRP Tank Ø 450 x 1650 mm (T)
1 bh Multiport Valve
1 bh Top stainer
1 bh Bottom stainer
b. Pengadaan dan Pemasangan Gresse Trap Kap 30 Ltr c/w Material Bantu Unit 1.00 6,165,000.00 6,165,000.00
e. Clean Out
- Ø 100 mm bh 18.00 321,059.50 5,779,071.00
- Ø 50 mm bh 22.00 169,092.25 3,720,029.50
Sub Total Pekerjaan Instalasi Air Kotor & Air Bekas 212,935,640.95
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 213.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
1 Plat Lantai t = 12 cm
Beton K.250 169.47 kg/m3 m3 239.94 Dilaksanakan Tahap - 1
Besi polos kg 40,662.07 Dilaksanakan Tahap - 1
Bekisting m2 35.79 Dilaksanakan Tahap - 1
2 Balok TB1. 300x500
Beton K.250 301.95 kg/m3 m3 123.51 Dilaksanakan Tahap - 1
Besi polos kg 6,965.39 Dilaksanakan Tahap - 1
Besi Peminggang kg 1,046.56 Dilaksanakan Tahap - 1
Besi ulir kg 30,328.13 Dilaksanakan Tahap - 1
Bekisting m2 823.40 Dilaksanakan Tahap - 1
3 Kolom K1. 400x400
Beton K.250 193.63 kg/m3 m3 48.00 Dilaksanakan Tahap - 1
Besi polos kg 2,866.99 Dilaksanakan Tahap - 1
Besi ulir kg 6,427.44 Dilaksanakan Tahap - 1
Bekisting m2 480.00 Dilaksanakan Tahap - 1
4 Kolom K2. 400x400
Beton K.250 171.32 kg/m3 m3 9.60 Dilaksanakan Tahap - 1
Besi polos kg 573.40 Dilaksanakan Tahap - 1
Besi ulir kg 1,071.24 Dilaksanakan Tahap - 1
Bekisting m2 96.00 Dilaksanakan Tahap - 1
5 Kolom K3. 350x350
Beton K.250 184.86 kg/m3 m3 33.69 Dilaksanakan Tahap - 1
Besi polos kg 2,299.56 Dilaksanakan Tahap - 1
Besi ulir kg 3,927.88 Dilaksanakan Tahap - 1
Bekisting m2 385.00 Dilaksanakan Tahap - 1
6 Balok BT. 200x350
Beton K.250 251.29 kg/m3 m3 0.42 Dilaksanakan Tahap - 1
Besi polos kg 34.10 Dilaksanakan Tahap - 1
E 404288434.xls Divisi : Strutkur
Hal. 45 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 0.000
1 Plat Lantai t = 13 cm .
Beton K.250 156.43 kg/m3 m3 250.85 Dilaksanakan Tahap - 1
Besi polos kg 39,241.78 Dilaksanakan Tahap - 1
Bekisting m2 1,929.64 Dilaksanakan Tahap - 1
2 Kolom K1. 400x400
Beton K.250 197.49 kg/m3 m3 34.56 Dilaksanakan Tahap - 1
Besi polos kg 2,064.23 Dilaksanakan Tahap - 1
Besi ulir kg 4,760.86 Dilaksanakan Tahap - 1
Bekisting m2 345.60 Dilaksanakan Tahap - 1
3 Kolom K2. 400x400
Beton K.250 174.53 kg/m3 m3 7.68 Dilaksanakan Tahap - 1
Besi polos kg 458.72 Dilaksanakan Tahap - 1
Besi ulir kg 881.64 Dilaksanakan Tahap - 1
Bekisting m2 76.80 Dilaksanakan Tahap - 1
4 Kolom K3. 350x350
Beton K.250 188.21 kg/m3 m3 27.44 Dilaksanakan Tahap - 1
Besi polos kg 1,873.10 Dilaksanakan Tahap - 1
Besi ulir kg 3,291.46 Dilaksanakan Tahap - 1
Bekisting m2 313.60 Dilaksanakan Tahap - 1
5 Balok G1. 400x800
Beton K.250 271.94 kg/m3 m3 21.44 Dilaksanakan Tahap - 1
Besi polos kg 2,844.27 Dilaksanakan Tahap - 1
Besi Peminggang kg 781.15 Dilaksanakan Tahap - 1
Besi ulir kg 2,205.02 Dilaksanakan Tahap - 1
Bekisting m2 107.20 Dilaksanakan Tahap - 1
6 Balok G2. 300x500
Beton K.250 312.53 kg/m3 m3 37.85 Dilaksanakan Tahap - 1
E 404288434.xls Divisi : Strutkur
Hal. 46 dari 150
REKAPITULASI
0.000
Pekerjaan : Pembangunan Rumah Sakit Pratama
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 0.000
E RADIOLOGI
1 Mobile X-Ray Unit 100MA 1 unit 545,301,000.00 545,301,000.00
2 Vertikal Bucky Stand 1 unit 5,000,000.00 5,000,000.00
3 Peralatan Protective Radiasi Terdiri Dari : 3 set 27,500,000.00 82,500,000.00
- Lead Apron, Tebal 0.25 - 0.5 mm Pb,
- Sarung Tangan, Tebal 0.25 - 0.5 mm Pb,
- Kacamata Pb, Tebal 1 mm Pb,
- Pelindung Tiroid Pb, Tebal 1 mm Pb,
- Pelindung gonad Pb, Tebal 0.25 - 0.5 mm Pb,
- Tabir mobile minimal 200mm (t}x 100cm
4 Perlengkapan Proteksi Radiasi Terdiri Dari : 3 set 27,500,000.00 82,500,000.00
5 - Survei Meter
6 - Digital Pocket Dosimeter
7 - Film Badge/ TDL
8 Film Viewer 4 film 1 unit 12,100,000.00 12,100,000.00
9 Cassete & Film X-Ray Semua ukuran : 12 set 15,958,800.00 191,505,600.00
- 18 x 24 cm
- 24 x 30 cm
- 30 x 40 cm
- 35 x 35 cm
12 Film Drayer 12 film 1 unit 31,231,200.00 31,231,200.00
13 X-Ray Protection screen with lead glass (untuk Operator) 1 unit 6,362,000.00 6,362,000.00
Harga Satuan JUMLAH HARGA
NO Uraian Material Satuan VOLUME
( Rp ) ( Rp )
F INSTALASI FARMASI
Cawan + Mortir Obat 5 unit 15,000,000.00 75,000,000.00
Timbangan Gram & miligram 2 unit 10,000,000.00 20,000,000.00
Refrigerator medical grade 1 unit 59,800,000.00 59,800,000.00
Meja Peracik Obat (work table for medicine) 1 unit 6,500,000.00 6,500,000.00
G RUANG GIZI/PANTRY
Kitchen Set 1 set 90,000,000.00 90,000,000.00
Kulkas 4 unit 5,000,000.00 20,000,000.00
Kompor Gas 4 unit 750,000.00 3,000,000.00
Tabung Gas 8 unit 1,200,000.00 9,600,000.00
Timbangan 1 unit 1,100,000.00 1,100,000.00
Perlengkapan Masak Set 4 set 7,000,000.00 28,000,000.00
Perlengkapan Makan Set 100 set 250,000.00 25,000,000.00
Pantry Trolley 9 unit 3,000,000.00 27,000,000.00
Food model 1 set 10,000,000.00 10,000,000.00
H RUANG STERILISASI & LOUNDRY
Autoclave 1 unit 108,680,000.00 108,680,000.00
Washing Machine 2 unit 9,000,000.00 18,000,000.00
Instrument Cabinet 1 unit 12,375,000.00 12,375,000.00
Laundry Trolley, SS 6 unit 3,055,000.00 18,330,000.00
Meja Setrika + Setrika 1 unit 5,000,000.00 5,000,000.00
Instrument Tray + Tutup 1 unit 6,110,000.00 6,110,000.00
I RUANG REKAM MEDIK
Filling Cabinet 2 unit 3,000,000.00 6,000,000.00
Writing Desk 1 unit 750,000.00 750,000.00
Chair 3 unit 650,000.00 1,950,000.00
Komputer + Printer + UPS + Table 1 set 12,000,000.00 12,000,000.00
Lemari Arsip 2 unit 5,300,000.00 10,600,000.00
J RUANG ADM /KANTOR
Filling Cabinet 1 unit 3,000,000.00 3,000,000.00
Writing Desk 1 unit 750,000.00 750,000.00
Chair 3 unit 650,000.00 1,950,000.00
Komputer + Printer + UPS + Table 1 set 12,000,000.00 12,000,000.00
Lemari Arsip 2 unit 5,300,000.00 10,600,000.00
K GENERATOR SET
Genset 400 KVA 2 Unit 400,000,000.00 800,000,000.00
RENCANA ANGGARAN BIAYA ( RAB )
TAPAK
Pekerjaan : Pembangunan Rumah Sakit Pratama
Lokasi
Tahun : Kabupaten Maybrat - Papua Barat
Anggaran : 2017 -
C PEKERJAAN PENGHIJAUAN
1 PEKERJAAN PERSIAPAN.
II PEKERJAAN TANAH
Rp 2,395,022.96
Anl.SNI 6.10, 1 M2 Pasang Batu Tela Tebal 1/2 Bata Camp. 1 Pc: 3Ps
0.3000 OH Pekerja Rp 100,000.00 = Rp 30,000.00
0.0150 OH Mandor Rp 191,283.00 = Rp 2,869.25
0.1000 OH Tukang Batu Rp 191,283.00 = Rp 19,128.30
0.0100 OH Kepala Tukang Rp 191,283.00 = Rp 1,912.83
70.0000 Bh Batu Tela 8 x 14 x 28 Rp 4,500.00 = Rp 315,000.00
14.3700 Kg Semen Portland Rp 3,360.00 = Rp 48,283.20
0.0400 M3 Pasir Rp 860,674.00 = Rp 34,426.96
Rp 451,620.54
Anl.SNI 6.12, 1 M2 Pasang Bata Merah Tebal 1/2 Bata Camp. 1 Pc: 5Ps
0.3000 OH Pekerja Rp 100,000.00 = Rp 30,000.00
0.0150 OH Mandor Rp 191,283.00 = Rp 2,869.25
0.1000 OH Tukang Batu Rp 191,283.00 = Rp 19,128.30
0.0100 OH Kepala Tukang Rp 191,283.00 = Rp 1,912.83
25.0000 Bh Batu Tela 8 x 14 x 28 Rp 4,500.00 = Rp 112,500.00
9.6800 Kg Semen Portland Rp 3,360.00 = Rp 32,524.80
0.0450 M3 Pasir Rp 860,674.00 = Rp 38,730.33
Rp 237,665.51
An. SNI 6.35 1 M' Membuat kolom praktis beton bertulang (11 x 11) cm
0.0020 m3 Kayu Daerah Rp 2,033,300.00 = Rp 4,066.60
0.0100 kg Paku Biasa Rp 34,600.00 = Rp 346.00
3.0000 kg Besi beton polos Rp 17,500.00 = Rp 52,500.00
An. 1 M2 Pekerjaan Pasang Lantai Keramik (40 x 40) cm anti Selip Corak
0.2500 OH Pekerja Rp 100,000.00 = Rp 25,000.00
0.0130 OH Mandor Rp 191,283.00 = Rp 2,486.68
0.1250 OH Tukang batu Rp 191,283.00 = Rp 23,910.38
0.0130 OH Kepala tukang Rp 191,283.00 = Rp 2,486.68
9.8000 kg Portland Cement Rp 3,360.00 = Rp 32,928.00
0.0450 M3 Pasir Pasang Rp 860,674.00 = Rp 38,730.33
1.5000 M2 Tegel Keramik Uk. 40 x 40 cm Rp 125,000.00 = Rp 187,500.00
1.3000 kg Semen Warna Rp 42,000.00 = Rp 54,600.00
Rp 367,642.06
Rp 92,382.41
An. SNI 6.14 1 M2 Pengecetan Tembok Baru ( Exterior)( 1 lapis plamir,1 lapis Cat dasar, 2 Lapis Cat Penutup )
0.0200 OH Pekerja Rp 100,000.00 = Rp 2,000.00
0.0025 OH Mandor Rp 191,283.00 = Rp 478.21
0.0630 OH Tukang Cat Rp 191,283.00 = Rp 12,050.83
0.0063 OH Kepala tukang Cat Rp 191,283.00 = Rp 1,205.08
0.1000 Kg Plamir Rp 18,600.00 = Rp 1,860.00
0.1300 Kg Cat Dasar Rp 15,000.00 = Rp 1,950.00
0.2600 Kg Cat Penutup 2 kali Rp 28,500.00 = Rp 7,410.00
Rp 26,954.12
An. SNI 6.14 1 M2 Pengecetan Plafond ( 1 lapis plamir,1 lapis Cat dasar, 2 Lapis Cat Penutup )
0.0500 OH Pekerja Rp 100,000.00 = Rp 5,000.00
0.0050 OH Mandor Rp 191,283.00 = Rp 956.42
0.1000 OH Tukang Cat Rp 191,283.00 = Rp 19,128.30
0.0050 OH Kepala tukang Cat Rp 191,283.00 = Rp 956.42
0.1000 Kg Plamir Rp 18,600.00 = Rp 1,860.00
0.1300 Kg Cat Dasar Rp 15,000.00 = Rp 1,950.00
0.2600 Kg Cat Penutup 2 kali Rp 20,000.00 = Rp 5,200.00
Rp 35,051.13
An. 1 M2 Pengecetan Plafond Exterior ( 1 lapis plamir,1 lapis Cat dasar, 2 Lapis Cat Penutup )
0.0500 OH Pekerja Rp 100,000.00 = Rp 5,000.00
0.0050 OH Mandor Rp 191,283.00 = Rp 956.42
0.1000 OH Tukang Cat Rp 191,283.00 = Rp 19,128.30
Pekerjaan Rabat
0.3000 O/H Pekerja Rp 100,000.00 = Rp 30,000.00
0.1000 O/H Kepala Tukang Rp 191,283.00 = Rp 19,128.30
0.0200 O/H Mandor Rp 191,283.00 = Rp 3,825.66
320.0000 kg Semen Rp 3,360.00 = Rp 1,075,200.00
0.7200 m3 Pasir Rp 860,674.00 = Rp 619,685.28
0.6000 m3 Kerikil Rp 956,418.00 = Rp 573,850.80
2,321,690.04
116,084.50
1 Kuzen Type P1
a Bahan
Kuzen Aluminium m' 8.60 200,000.00 1,720,000.00
Daun Pintu Doble Teakwood fin Politur unit 2.00 1,200,000.00 2,400,000.00
Kaca 5 mm m2 0.73 110,000.00 80,300.00
Engsel Pintu 4" psg 6.00 38,300.00 229,800.00
Pull Handle psg 2.00 278,460.00 556,920.00
Lockcase bh 1.00 405,600.00 405,600.00
Double Cylinder bh 1.00 220,610.00 220,610.00
Sealant m' 8.00 11,700.00 93,600.00
b Upah
Upah Pasang Kuzen m' 8.60 19,500.00 167,700.00
Upah Pasang Pintu unit 2.00 195,000.00 390,000.00
Upah Pasang Sealant m' 8.60 5,850.00 50,310.00
6,314,840.00
6,314,800.00
2 Kuzen Type P2
a Bahan
Kuzen Aluminium m' 8.20 200,000.00 1,640,000.00
Daun Pintu Doble Teakwood fin Politur unit 2.00 1,200,000.00 2,400,000.00
Kaca 5 mm m2 0.35 110,000.00 38,500.00
Engsel Pintu 4" psg 2.00 38,300.00 76,600.00
Pull Handle psg 2.00 278,460.00 556,920.00
Lockcase bh 1.00 405,600.00 405,600.00
Double Cylinder bh 1.00 220,610.00 220,610.00
Sealant m' 8.20 11,700.00 95,940.00
Plat Stainless m' 0.66 500,000.00 330,000.00
b Upah
Upah Pasang Kuzen m' 8.20 19,500.00 159,900.00
Upah Pasang Pintu unit 2.00 195,000.00 390,000.00
Upah Pasang Sealant m' 8.20 5,850.00 47,970.00
6,362,040.00
6,362,000.00
b Upah
Upah Pasang Kuzen m' 18.36 19,500.00 358,020.00
Upah Pasang Pintu unit 2.00 195,000.00 390,000.00
Upah Pasang Sealant m' 18.36 5,850.00 107,406.00
11,041,634.40
11,041,600.00
4 Kuzen Type P4
a Bahan
Kuzen Aluminium 4" m' 7.20 200,000.00 1,440,000.00
Daun Pintu Doble Teakwood fin Politur unit 1.00 1,200,000.00 1,200,000.00
Kaca 5 mm m2 0.28 110,000.00 30,800.00
Engsel Pintu 4" psg 3.00 38,300.00 114,900.00
Pull Handle ps 1.00 278,460.00 278,460.00
Lockcase bh 1.00 405,600.00 405,600.00
Double Cylinder bh 1.00 220,610.00 220,610.00
Sealant m' 7.20 11,700.00 84,240.00
b Upah
Upah Pasang Kuzen m' 7.20 19,500.00 140,400.00
Upah Pasang Pintu unit 1.00 195,000.00 195,000.00
Upah Pasang Sealant m' 7.20 5,850.00 42,120.00
4,152,130.00
4,152,100.00
5 Kuzen Type P5
a Bahan
Kuzen Aluminium 4" m' 7.20 200,000.00 1,440,000.00
Daun Pintu Doble Teakwood fin Politur unit 1.00 1,200,000.00 1,200,000.00
Kaca 5 mm m2 0.28 110,000.00 30,800.00
Engsel Pintu 4" psg 3.00 38,300.00 114,900.00
Pull Handle ps 1.00 278,460.00 278,460.00
Lockcase bh 1.00 405,600.00 405,600.00
Double Cylinder bh 1.00 220,610.00 220,610.00
Sealant m' 7.20 11,700.00 84,240.00
b Upah
Upah Pasang Kuzen m' 7.20 19,500.00 140,400.00
Upah Pasang Pintu unit 1.00 195,000.00 195,000.00
Upah Pasang Sealant m' 7.20 5,850.00 42,120.00
4,152,130.00
4,152,100.00
8 Kuzen Type P8
a Bahan
Kuzen Aluminium 4" m' 8.60 200,000.00 1,720,000.00
Daun Pintu Doble Teakwood fin Politur unit 2.00 1,200,000.00 2,400,000.00
Kaca 5 mm m2 2.52 110,000.00 277,200.00
Engsel Pintu 4" psg 6.00 38,300.00 229,800.00
Pull Handle ps 2.00 278,460.00 556,920.00
Lockcase bh 1.00 405,600.00 405,600.00
Double Cylinder bh 1.00 220,610.00 220,610.00
Sealant m' 8.60 11,700.00 100,620.00
Plat Stainless m' 0.66 500,000.00 330,000.00
b Upah
Upah Pasang Kuzen m' 8.60 19,500.00 167,700.00
Upah Pasang Pintu unit 2.00 195,000.00 390,000.00
Upah Pasang Sealant m' 8.60 5,850.00 50,310.00
6,848,760.00
6,848,700.00
RENCANA ANGGARAN BIAYA ( RAB )
9 Kuzen Type P9
a Bahan
Kuzen Aluminium 4" m' 3.30 200,000.00 660,000.00
Daun Pintu Doble Teakwood fin Politur unit 1.00 600,000.00 600,000.00
Pull Handle ps 3.70 117,196.30 433,157.52
Engsel Pintu 4" psg 2.00 38,300.00 76,600.00
b Upah
Upah Pasang Kuzen m' 3.30 19,500.00 64,350.00
1,834,107.52
1,834,100.00
11 Kuzen Type J1
a Bahan
Kuzen Aluminium 4" m' 11.00 200,000.00 2,200,000.00
Kaca 5 mm m2 2.48 110,000.00 272,800.00
Daun Jendela Rangka Aluminium m2 6.72 119,340.00 801,964.80
Engsel casement 12" psg 2.00 182,460.00 364,920.00
Rambuncis bh 2.00 62,250.00 124,500.00
Sealant m' 11.00 11,700.00 128,700.00
b Upah
Upah Pasang Kuzen m' 11.00 19,500.00 214,500.00
Upah Pasang Jendela unit 2.00 195,000.00 390,000.00
Upah Pasang Sealant m' 11.00 5,850.00 64,350.00
4,561,734.80
4,561,700.00
RENCANA ANGGARAN BIAYA ( RAB )
12 Kuzen Type J2
a Bahan
Kuzen Aluminium 4" m' 22.20 200,000.00 4,440,000.00
Kaca 5 mm m2 5.04 110,000.00 554,400.00
Daun Jendela Rangka Aluminium m2 13.44 119,340.00 1,603,929.60
Engsel casement 12" psg 4.00 182,460.00 729,840.00
Rambuncis bh 4.00 62,250.00 249,000.00
Sealant m' 22.20 11,700.00 259,740.00
b Upah
Upah Pasang Kuzen m' 22.20 19,500.00 432,900.00
Upah Pasang Jendela unit 4.00 195,000.00 780,000.00
Upah Pasang Sealant m' 22.20 5,850.00 129,870.00
9,179,679.60
9,179,600.00
13 Kuzen Type J3
a Bahan
Kuzen Aluminium 4" m' 7.50 200,000.00 1,500,000.00
Kaca 5 mm m2 2.04 110,000.00 224,400.00
Sealant m' 7.50 11,700.00 87,750.00
b Upah
Upah Pasang Kuzen m' 7.50 19,500.00 146,250.00
Upah Pasang Sealant m' 7.50 5,850.00 43,875.00
2,002,275.00
2,002,200.00
15 Kuzen Type L1
a Bahan
Kaca t = 10 mm m2 2.12 425,000.00 898,875.00
Sealant m' 4.75 11,700.00 55,575.00
b Upah
Upah Pasang Jendela m' 1.00 19,500.00 19,500.00
Upah Pasang Sealant m' 4.75 5,850.00 27,787.50
1,001,737.50
1,001,700.00
RENCANA ANGGARAN BIAYA ( RAB )
16 Kuzen Type B1
a Bahan
Kuzen Aluminium 4" m' 2.80 200,000.00 560,000.00
Kaca 5 mm m2 0.48 110,000.00 52,800.00
Sealant m' 2.80 11,700.00 32,760.00
b Upah
Upah Pasang Kuzen m' 2.80 19,500.00 54,600.00
Upah Pasang Sealant m' 2.80 5,850.00 16,380.00
716,540.00
716,500.00
17 Kuzen Type B2
a Bahan
Kuzen Aluminium 4" m' 4.90 200,000.00 980,000.00
Kaca 5 mm m2 0.93 110,000.00 102,300.00
Sealant m' 4.90 11,700.00 57,330.00
b Upah
Upah Pasang Kuzen m' 4.90 19,500.00 95,550.00
Upah Pasang Sealant m' 4.90 5,850.00 28,665.00
1,263,845.00
1,263,800.00
1 Terminal Penangkal Petir Non Radio Aktip,Radius Proteksi Max 100 mtr
Material :
- Terminal Penangkal Petir Non Radio Aktip,( Radius Proteksi Max 100 mtr ) Unit 1.00 23,290,000.00 23,290,000.00
- Tiang GIP dia 2" setinggi 7 meter + dudukan m 7.00 219,200.00 1,534,400.00
- Lampu Obstruction 100 w bh 1.00 3,425,000.00 3,425,000.00
- Material Bantu lot 1.00 1,370,000.00 1,370,000.00
Harga Material : 29,619,400.00
Upah :
- Pemasangan Lot 1.00 2,961,940.00 2,961,940.00
Harga Upah : 2,961,940.00
Jumlah Harga Satuan 32,581,340.00
4 PANEL DB-LTG
Material :
- Panel DB-LTG bh 1.00 14,167,822.12 14,167,822.12
Harga Material : 14,167,822.12
Upah :
- Wiring Kabel dan Pemasangan Lot 1.00 354,195.55 354,195.55
Harga Upah : 354,195.55
Jumlah Harga Satuan 14,522,017.67
5 PP-AC (PP-POWER)
Material :
- Panel AC bh 1.00 16,253,680.00 16,253,680.00
Harga Material : 16,253,680.00
Upah :
- Wiring Kabel dan Pemasangan Lot 1.00 406,342.00 406,342.00
Harga Upah : 406,342.00
Jumlah Harga Satuan 16,660,022.00
6 PANEL DB-R.OK
Material :
- Panel-DB-OK bh 1.00 10,930,912.16 10,930,912.16
- UPS Kap 16 KVA / 1P bh 1.00 26,690,594.82 26,690,594.82
Harga Material : 37,621,506.98
Upah :
- Wiring kabel dan pemasangan Lot 1.00 940,537.67 940,537.67
Harga Upah : 940,537.67
7 PANEL DB-R.IGD Jumlah Harga Satuan 38,562,044.65
Material :
- Panel -DB-R.IGD bh 1.00 8,353,187.29 8,353,187.29
- UPS Kap 3 KVA/1P bh 1.00 26,380,236.39 26,380,236.39
Harga Material : 34,733,423.68
Upah :
- Wiring Kabel dan Pemasangan Lot 1.00 868,335.59 868,335.59
Harga Upah : 868,335.59
Jumlah Harga Satuan 35,601,759.27
8 PANEL DB-R.BERSALIN
Material :
- Panel-DB-BERSALIN bh 1.00 8,353,187.29 8,353,187.29
- UPS Kap 3 KVA/1P bh 1.00 26,380,236.39 26,380,236.39
Harga Material : 34,733,423.68
Upah :
- Wiring kabel dan pemasangan Lot 1.00 868,335.59 868,335.59
Harga Upah : 868,335.59
Jumlah Harga Satuan 35,601,759.27
9 PANEL DB-R.RADIOLOGI
Material :
- Panel -DB-R.RADIOLOGI bh 1.00 10,347,637.40 10,347,637.40
- UPS Kap 10 KVA/1P bh 1.00 26,594,075.58 26,594,075.58
Harga Material : 36,941,712.98
Upah :
- Wiring kabel dan pemasangan Lot 1.00 923,542.82 923,542.82
Harga Upah : 923,542.82
Jumlah Harga Satuan 37,865,255.80
10 PANEL PP-AC
Material :
- Panel PP-AC bh 1.00 12,400,331.69 12,400,331.69
Harga Material : 12,400,331.69
Upah :
- Wiring kabel dan pemasangan Lot 1.00 310,008.29 310,008.29
Harga Upah : 310,008.29
Jumlah Harga Satuan 12,710,339.98
11 PP-POMPA
Material :
- Panel PP-AC bh 1.00 12,187,324.09 12,187,324.09
Harga Material : 12,187,324.09
Upah :
- Wiring kabel dan pemasangan Lot 1.00 304,683.10 304,683.10
Harga Upah : 304,683.10
Jumlah Harga Satuan 12,492,007.19
12 PP-LUAR
Material :
- Panel PP-AC bh 1.00 12,868,782.64 12,868,782.64
Harga Material : 12,868,782.64
Upah :
- wiring kabel dan pemasangan Lot 1.00 321,719.57 321,719.57
Harga Upah : 321,719.57
Jumlah Harga Satuan 13,190,502.21
Upah :
- Material Bantu & Supporting Lot 1.00 19,101.23 19,101.23
- Pemasangan Lot 1.00 17,125.00 17,125.00
Harga Upah : 36,226.23
Jumlah Harga Satuan 227,238.48
25 Fitting Kabel Tray UK.400
Material :
- Elbow 90 º m' 1.00 233,132.90 233,132.90
Harga Material : 233,132.90
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 246,147.90
26 Fitting Kabel Tray UK.300
Material :
- Elbow 90 º m' 1.00 202,075.00 202,075.00
Harga Material : 202,075.00
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 215,090.00
27 Fitting Kabel Tray
Material :
- Reducer Uk. 400 x 300 mm m' 1.00 262,629.00 262,629.00
Harga Material : 262,629.00
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 275,644.00
28 Fitting Kabel Tray
Material :
- Reducer Uk. 300 x 200 mm m' 1.00 243,723.00 243,723.00
Harga Material : 243,723.00
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 256,738.00
29 Fitting Kabel Tray
Material :
- TEE Uk. 400 x 400 mm m' 1.00 386,888.00 386,888.00
Harga Material : 386,888.00
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 399,903.00
30 Fitting Kabel Tray
Material :
- TEE Uk. 300 x 300 mm m' 1.00 349,076.00 349,076.00
Harga Material : 349,076.00
Upah :
- Pemasangan Lot 1.00 13,015.00 13,015.00
Harga Upah : 13,015.00
Jumlah Harga Satuan 362,091.00
31 Instalasi Pemasangan NYM 3 x 2,5 mm2 + conduid 20 mm
Material :
- Kabel NYM 3 x 2,5 mm m' 9.00 55,485.00 499,365.00
- Pipa Conduit E20 m' 9.00 9,590.00 86,310.00
Harga Material : 585,675.00
Upah & Material Bantu :
- Fitting dan Material Bantu Lot 1.00 28,359.00 28,359.00
- Wiring Kabel dan Conduit Lot 1.00 14,179.00 14,179.00
Harga Upah : 42,538.00
Jumlah Harga Satuan 628,213.00
32 Instalasi Stop Kontak 1P NYM 3 x 2,5 mm2 + Conduit 20 mm
Material :
- Kabel NYM 3 x 2,5 mm m' 11.00 55,485.00 610,335.00
- Pipa Conduit E20 m' 11.00 9,590.00 105,490.00
Harga Material : 715,825.00
Upah & Material Bantu :
- Fitting dan Material Bantu Lot 1.00 34,661.00 34,661.00
- Wiring Kabel dan Conduit Lot 1.00 17,330.50 17,330.50
Harga Upah : 51,991.50
Jumlah Harga Satuan 767,816.50
33 Instalasi Stop Kontak 3P NYM 4 x 4 mm2 + Conduit 25 mm
Material :
- Kabel NYM 4 x 4 mm m' 11.00 73,980.00 813,780.00
- Pipa Conduit E25 m' 11.00 19,180.00 210,980.00
Harga Material : 1,024,760.00
Upah & Material Bantu :
- Fitting dan Material Bantu Lot 1.00 51,238.00 51,238.00
- Wiring Kabel dan Conduit Lot 1.00 6,165.00 6,165.00
Harga Upah : 57,403.00
Jumlah Harga Satuan 1,082,163.00
34 Instalasi Lampu Taman NYMGBy 3 x 2,5 mm2 + Conduit 32 mm
Material :
- Kabel NYMGBy 3 x 2,5 mm m' 25.00 69,870.00 1,746,750.00
- Pipa Conduit E20 m' 25.00 9,590.00 239,750.00
Harga Material : 1,986,500.00
Upah & Material Bantu :
- Fitting dan Material Bantu Lot 1.00 99,325.00 99,325.00
- Wiring Kabel dan Conduit Lot 1.00 6,165.00 6,165.00
Harga Upah : 105,490.00
Jumlah Harga Satuan 2,091,990.00
35 Instalasi Lampu PJU NYMGBy 3 x 2,5 mm2 + Conduit 32 mm
Material :
- Kabel NYMGBy 3 x 2,5 mm m' 30.00 69,870.00 2,096,100.00
- Pipa Conduit E25 m' 30.00 19,180.00 575,400.00
Harga Material : 2,671,500.00
Upah & Material Bantu :
- Fitting dan Material Bantu Lot 1.00 119,190.00 119,190.00
- Wiring Kabel dan Conduit Lot 1.00 6,165.00 6,165.00
Harga Upah : 125,355.00
Jumlah Harga Satuan 2,796,855.00
36 Stop Kontak 1P/13A
Material :
- Stop Kontak 1P/13A type S4151 Whi bh 1.00 82,885.00 82,885.00
- Inbowdus bh 1.00 13,700.00 13,700.00
Harga Material : 96,585.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 6,165.00 6,165.00
Harga Upah : 6,165.00
Jumlah Harga Satuan 102,750.00
37 Stop Kontak AC 1P/13A c/w Saklar
Meterial :
- Stop Kontak 1P/13A Type S2757 Whi bh 1.00 128,396.00 128,396.00
- Inbowdus bh 1.00 13,700.00 13,700.00
Harga Material : 142,096.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 6,165.00 6,165.00
Harga Upah : 6,165.00
Jumlah Harga Satuan 148,261.00
38 Stop kontak Lantai 3P/1500 A ( Stainless steel )Merk MK
Meterial :
- Stop Kontak Lantai 1P/13A Type A777 s/s + Box bh 1.00 1,193,270.00 1,193,270.00
Harga Material : 1,193,270.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 6,165.00 6,165.00
Harga Upah : 6,165.00
Jumlah Harga Satuan 1,199,435.00
39 Saklar Tunggal
Meterial :
- Saklar Tunggal Type S 4781 Wi Whi (1 way) bh 1.00 84,994.80 84,994.80
- Inbowdus bh 1.00 13,700.00 13,700.00
Harga Material : 98,694.80
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 6,165.00 6,165.00
Harga Upah : 6,165.00
Jumlah Harga Satuan 104,859.80
40 Saklar Ganda (2 gang)
Meterial :
- Saklar Ganda Type S4782 W1 Whi (1 way) bh 1.00 123,875.40 123,875.40
- Inbowdus bh 1.00 13,700.00 13,700.00
Harga Material : 137,575.40
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 6,165.00 6,165.00
Harga Upah : 6,165.00
Jumlah Harga Satuan 143,740.40
41 Downlight, LED 6 watt, Cahaya Putih (66055 dia 3" Con 65K White 6W Recessed LED)
Meterial :
- LP Downlight, LED 6w bh 1.00 1,044,762.00 1,044,762.00
Harga Material : 1,044,762.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 26,119.05 26,119.05
Harga Upah : 26,119.05
Jumlah Harga Satuan 1,070,881.05
42 Downlight,LED 6 watt, Cahaya Putih (66067 dia 3" Flat 65K white 6w Recessed LED)
Meterial :
- LP Downlight, LED 6w + Nicad bh 1.00 2,825,762.00 2,825,762.00
Harga Material : 2,825,762.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 70,644.05 70,644.05
Harga Upah : 70,644.05
Jumlah Harga Satuan 2,896,406.05
43 Downlight, LED 3,5 Watt (66054 2.5" Con 65K White 3.5w Recessed )
Meterial :
- LP Downlight, LED 3.5 w bh 1.00 797,614.00 797,614.00
Harga Material : 797,614.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 19,940.35 19,940.35
Harga Upah : 19,940.35
Jumlah Harga Satuan 817,554.35
44 Downlight, LED 3,5 Watt (66054 2.5" Con 65K White 3.5w Recessed )
Meterial :
- LP Downlight, LED 3.5 w + Nicad bh 1.00 2,578,614.00 2,578,614.00
Harga Material : 2,578,614.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 64,465.35 64,465.35
Harga Upah : 64,465.35
Jumlah Harga Satuan 2,643,079.35
45 Armature Tanam LED Natural White (CR418B LED40/NW lampu clean room CPOB kaca temp)
Meterial :
- RMOT CBOP 2 x 36 W bh 1.00 7,124,000.00 7,124,000.00
Harga Material : 7,124,000.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 178,100.00 178,100.00
Harga Upah : 178,100.00
Jumlah Harga Satuan 7,302,100.00
46 TL Balok LED Cool White 8 watt (BN096C LED8/CW L600,Lampu baca)
Meterial :
- TL Balok LED Cool White 8 watt bh 1.00 997,360.00 997,360.00
Harga Material : 997,360.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 24,934.00 24,934.00
Harga Upah : 24,934.00
Jumlah Harga Satuan 1,022,294.00
47 Lampu Taman CDMT 150 watt / Putih (CDS570 C 1 x CDM-T150W 220V-50Hz TT)
Meterial :
- Lampu Taman CDMT 60 watt bh 1.00 2,604,370.00 2,604,370.00
Harga Material : 2,604,370.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 65,109.25 65,109.25
- Tiang Lampu Pipa GIP dia 40 mm + Finish Cat m 1.50 668,167.50 1,002,251.25
- Material Bantu Lot 1.00 63,472.10 63,472.10
Harga Upah : 1,130,832.60
Jumlah Harga Satuan 3,735,202.60
48 Lampu PJU HPLN 125 watt/Putih (CDS570 C 1 x CDM-T150W 220V-50Hz TT)
Meterial :
- Lampu PJU HPLN LED 125 watt bh 1.00 3,425,000.00 3,425,000.00
Harga Material : 3,425,000.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 85,625.00 85,625.00
- Tiang Lampu PJU T 9 mtr m 9.00 842,500.00 7,582,500.00
- Material Bantu Lot 1.00 308,250.00 308,250.00
Harga Upah : 7,976,375.00
Jumlah Harga Satuan 11,401,375.00
49 Lampu Exit FI 1 x 10w
Material :
- Lampu Exit FI 1 x 10w bh 1.00 2,558,338.00 2,558,338.00
Harga Material : 2,558,338.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 63,958.45 63,958.45
Harga Upah : 63,958.45
Jumlah Harga Satuan 2,622,296.45
50 Lampu Indikator (Lampu Tanda Operasi)
Material :
- Lampu Indikator (Lampu Tanda Operasi) bh 1.00 988,592.00 988,592.00
Harga Material : 988,592.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 24,714.80 24,714.80
Harga Upah : 24,714.80
Jumlah Harga Satuan 1,013,306.80
51 MCFA Conventional Kap 25 Zone
Material :
- MCFA Conventional Kap 25 Zone Unit 1.00 66,915,732.00 66,915,732.00
- Rectifier dan back-up battery Unit 1.00 2,740,000.00 2,740,000.00
- Master Telephone Unit 1.00 1,781,000.00 1,781,000.00
- Main Bell & Lamp Indikator Unit 1.00 2,055,000.00 2,055,000.00
Harga Material : 73,491,732.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 1,837,293.30 1,837,293.30
Harga Upah : 1,837,293.30
Jumlah Harga Satuan 75,329,025.30
52 Announciator Kap 25 Zone
Material :
- Announciator Kap 25 Zone Unit 1.00 33,159,726.60 33,159,726.60
Harga Material : 33,159,726.60
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 828,993.17 828,993.17
Harga Upah : 828,993.17
Jumlah Harga Satuan 33,988,719.77
53 MDF-FA
Material :
- MDF-FA Unit 1.00 6,850,000.00 6,850,000.00
Harga Material : 6,850,000.00
Upah :
- Wiring Kabel Dan Pemasangan Lot 1.00 171,250.00 171,250.00
Harga Upah : 171,250.00
Jumlah Harga Satuan 7,021,250.00
54 Kabel Power MCFA NYM 3 x 2,5 mm2 + Conduit 20 mm
Material :
- Kabel Power NYM 3 x 2,5 mm2 m 1.00 55,485.00 55,485.00
- Conduit 20 mm m 1.00 9,590.00 9,590.00
Harga Material : 65,075.00
Upah :
- Material Bantu Lot 1.00 6,302.00 6,302.00
- Wiring Kabel Dan Pemasangan Lot 1.00 1,575.00 1,575.00
Harga Upah : 7,877.00
55 Kabel Power MCFA Kabel ITC 2 Pair (2x0,6 mm2) + Conduit 20 mm Jumlah Harga Satuan 72,952.00
Material :
- Kabel ITC 2 Pair ( 2x0,6 mm2) m 1.00 35,606.30 35,606.30
- Conduit 20 mm m 1.00 9,590.00 9,590.00
Harga Material : 45,196.30
Upah :
- Material Bantu Lot 1.00 4,519.63 4,519.63
- Wiring Kabel Dan Pemasangan Lot 1.00 1,129.91 1,129.91
Harga Upah : 5,649.54
Jumlah Harga Satuan 50,845.84
56 Smoke Detector (ROR) Konvetional ( Photo electric )
Material :
- Smoke Detector (ROR) Konvetional ( Photo electric ) m 1.00 1,575,815.10 1,575,815.10
Harga Material : 1,575,815.10
Upah :
- Pemasangan Lot 1.00 19,697.69 19,697.69
Harga Upah : 19,697.69
Jumlah Harga Satuan 1,595,512.79
60 Alarm Bell
Material :
- Alarm Bell m 1.00 1,263,235.90 1,263,235.90
Harga Material : 1,263,235.90
Upah & Material Bantu
- Pemasangan Lot 1.00 15,790.45 15,790.45
Harga Upah : 15,790.45
Jumlah Harga Satuan 1,279,026.35
61 Fire Intercom Jack Phone
Material :
- Fire Intercom Jack Phone m 1.00 553,000.50 553,000.50
Harga Material : 553,000.50
Upah & Material Bantu
- Pemasangan Lot 1.00 6,912.51 6,912.51
Harga Upah : 6,912.51
Jumlah Harga Satuan 559,913.01
72 Corridor Lamp
Material :
- Corridor Lamp bh 1.00 372,229.00 372,229.00
Harga Material : 372,229.00
Upah & Material Bantu
- wiring kabel dan pemasangan Lot 1.00 9,305.73 9,305.73
Harga Upah : 9,305.73
Jumlah Harga Satuan 381,534.73
73 Reset Button
Material :
- Reset Button bh 1.00 479,089.00 479,089.00
Harga Material : 479,089.00
Upah & Material Bantu
- wiring kabel dan pemasangan Lot 1.00 11,977.23 11,977.23
Harga Upah : 11,977.23
Jumlah Harga Satuan 491,066.23
76 Instalasi Nurse Call Kabel NYMHY 2 x 1,5 mm2 c/w Pipa Conduit 20 mm + Accessories
Material :
- Kabel NYMHY 2 x 1,5 mm2 m' 9.00 36,990.00 332,910.00
- Pipa Conduit E20 m' 9.00 9,590.00 86,310.00
Harga Material : 419,220.00
Upah & Material Bantu
- fitting Dan material bantu Lot 1.00 20,961.00 20,961.00
- wiring kabel dan pemasangan Lot 1.00 10,480.50 10,480.50
Harga Upah : 31,441.50
Jumlah Harga Satuan 450,661.50
PC-Server
Material :
- PC-Server Unit 1.00 41,100,000.00 41,100,000.00
- Sofware Data Lot 1.00 19,180,000.00 19,180,000.00
Harga Material : 60,280,000.00
Upah :
- wiring kabel dan pemasangan Lot 1.00 3,014,000.00 3,014,000.00
Harga Upah : 3,014,000.00
Jumlah Harga Satuan 63,294,000.00
86 Hansed Standar
Material :
- Hansed Standar bh 1.00 1,737,434.00 1,737,434.00
Harga Material : 1,737,434.00
Upah :
- wiring kabel dan pemasangan Lot 1.00 43,435.85 43,435.85
Harga Upah : 43,435.85
Jumlah Harga Satuan 1,780,869.85
89 Instalasi Telepone Kabel ITC 2 x 2 x 0,6 mm2 c/w Pipa Conduit 20 mm+Accessories
Material :
- Kabel ITC 2 x 2 x 0,6 mm2 m' 45.00 35,606.30 1,602,283.50
- Pipa Conduit E20 m' 45.00 9,590.00 431,550.00
Harga Material : 2,033,833.50
Upah & Material Bantu
- fitting Dan material bantu Lot 1.00 203,383.35 203,383.35
- wiring kabel dan pemasangan Lot 1.00 50,845.84 50,845.84
Harga Upah : 254,229.19
Jumlah Harga Satuan 2,288,062.69
90 Switch Hub 30 Port
Material :
- Switch hub 30 Port bh 1.00 11,557,320.00 11,557,320.00
Harga Material : 11,557,320.00
Upah :
- wiring kabel dan pemasangan Lot 1.00 288,933.00 288,933.00
Harga Upah : 288,933.00
Jumlah Harga Satuan 11,846,253.00
Upah :
- Material Bantu Lot 1.00 31,768.38 31,768.38
- wiring kabel dan pemasangan Lot 1.00 5,343.00 5,343.00
Harga Upah : 37,111.38
Jumlah Harga Satuan 354,795.20
Upah :
- Pemasangan Lot 1.00 20,550.00 20,550.00
Harga Upah : 20,550.00
Jumlah Harga Satuan 431,550.00
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 194.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 194.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
A. PEKERJAAN STRUKTUR.
I. PEKERJAAN PERSIAPAN
1 Pek. Bouwplank m1 194.00 Dilaksanakan Tahap - 1
TOTAL. I. PEKERJAAN PERSIAPAN : -
Keterangan HARGA
JUMLAH HARGA
NO ITEM PE K E R JAAN SAT. VOLUME SATUAN
Spek Material yg Dipakai
( Rp ) ( Rp )
a b c d e f g = (e x f )
2 Pek.Penutup Atap
-Pek.Penutup atap metal sheet + Lap.Insulasi Panas m2 2,809.62 175,000.00 491,683,500.00
-Pek Bubung atap metal sheet m' 142.20 120,000.00 17,064,000.00
-Pek.Zincalium 20 x 35 m2
2,809.62 75,000.00 210,721,500.00
-Pek.Zincalium 40 x 75 m2 2,809.62 34,000.00 95,527,080.00
-Pek.Seng Talang ( Jurai ) m' 215.12 120,000.00 25,814,400.00
Jumlah-2 840,810,480.00
Total = Jumlah-1 + Jumlah-2 1,650,039,336.00
Dibulatkan 1,650,000,000.00
TERBILANG : DUA PULUH TIGA MILYAR SERATUS LIMA PULUH SEMBILAN JUTA RUPIAH
6 Bad Head
Material :
- Bad Head m 1.00 3,836,000.00 3,836,000.00
Harga Material : 3,836,000.00
Upah dan Material Bantu :
- Material Bantu Unit 1.00 575,400.00 575,400.00
- Pemasangan Unit 1.00 191,800.00 191,800.00
Harga Upah : 767,200.00
Jumlah Harga Satuan 4,603,200.00
DAFTAR ANALISA HARGA SATUAN
Plambing
9 Gate Valve Ø 50 mm
Material :
- Gate Valve Ø 50 mm unit 1.00 1,440,280.00 1,440,280.00
Harga Material : 1,440,280.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 144,028.00 144,028.00
- Pemasangan Lot 1.00 36,007.03 36,007.03
Harga Upah : 180,035.03
Jumlah Harga Satuan 1,620,315.03
10 Gate Valve Ø 40 mm
Material :
- Gate Valve Ø 40 mm unit 1.00 957,630.00 957,630.00
Harga Material : 957,630.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 95,763.00 95,763.00
- Pemasangan Lot 1.00 23,940.75 23,940.75
Harga Upah : 119,703.75
Jumlah Harga Satuan 1,077,333.75
11 Gate Valve Ø 32 mm
Material :
- Gate Valve Ø 32 mm unit 1.00 755,280.00 755,280.00
Harga Material : 755,280.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 75,528.00 75,528.00
- Pemasangan Lot 1.00 18,882.03 18,882.03
Harga Upah : 94,410.03
Jumlah Harga Satuan 849,690.03
DAFTAR ANALISA HARGA SATUAN
Plambing
13 Gate Valve Ø 20 mm
Material :
- Gate Valve Ø 20 mm unit 1.00 389,490.00 389,490.00
Harga Material : 389,490.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 38,949.00 38,949.00
- Pemasangan Lot 1.00 9,737.28 9,737.28
Harga Upah : 48,686.28
Jumlah Harga Satuan 438,176.28
14 Gate Valve Ø 15 mm
Material :
- Gate Valve Ø 20 mm unit 1.00 311,670.00 311,670.00
Harga Material : 311,670.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 31,167.00 31,167.00
- Pemasangan Lot 1.00 7,791.88 7,791.88
Harga Upah : 38,958.88
Jumlah Harga Satuan 350,628.88
15 Check Valve Ø 50 mm
Material :
- Check Valve Ø 50 mm unit 1.00 1,891,690.00 1,891,690.00
Harga Material : 1,891,690.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 189,169.00 189,169.00
- Pemasangan Lot 1.00 47,292.40 47,292.40
Harga Upah : 236,461.40
Jumlah Harga Satuan 2,128,151.40
16 Strainer Ø 50 mm
Material :
- Strainer Ø 50 mm unit 1.00 2,521,340.00 2,521,340.00
Harga Material : 2,521,340.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 252,134.00 252,134.00
- Pemasangan Lot 1.00 63,033.70 63,033.70
Harga Upah : 315,167.70
Jumlah Harga Satuan 2,836,507.70
DAFTAR ANALISA HARGA SATUAN
Plambing
18 Foot Valve Ø 50 mm
Material :
- Foot Valve Ø 50 mm unit 1.00 2,594,780.00 2,594,780.00
Harga Material : 2,594,780.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 259,478.00 259,478.00
- Pemasangan Lot 1.00 64,869.50 64,869.50
Harga Upah : 324,347.50
Jumlah Harga Satuan 2,919,127.50
20 WLC
Material :
- WLC unit 1.00 411,000.00 411,000.00
Harga Material : 411,000.00
Upah dan Material Bantu :
- Material Bantu Lot 1.00 41,100.00 41,100.00
- Pemasangan Lot 1.00 10,275.00 10,275.00
Harga Upah : 51,375.00
Jumlah Harga Satuan 462,375.00
21 Pipa Header
Material :
- Pipa GIP Medium Ø 80 mm m' 4.00 506,440.00 2,025,760.00
- Flange las 80 mm bh 2.00 140,800.00 281,600.00
- Flange Bind 80 mm bh 2.00 212,940.00 425,880.00
- Paking seat 80 mm bh 2.00 41,100.00 82,200.00
- Mur Baut 5/8 x 2,5' bh 12.00 15,070.00 180,840.00
- Fitting Hanger,Support 20% ls 1.00 202,577.33 202,577.33
Harga Material : 3,198,857.33
Upah
- Pemasangan Lot 1.00 239,750.00 239,750.00
Harga Upah : 239,750.00
Jumlah Harga Satuan 3,438,607.33
DAFTAR ANALISA HARGA SATUAN
Plambing
36 Roof Drain
Material :
- Roff Drain Ø 100mm bh 1.00 250,025.00 250,025.00
Harga Material : 250,025.00
Upah :
- Pemasangan Lot 1.00 17,125.00 17,125.00
Harga Upah : 17,125.00
Jumlah Harga Satuan 267,150.00
DAFTAR ANALISA HARGA SATUAN
Plambing
37 Vent Cap Ø 65 mm
Material :
- Vent Cap Ø 65 mm m' 1.00 342,157.50 342,157.50
Harga Material : 342,157.50
Upah & Material
- Accesoriess & Material Bantu m' 1.00 34,215.75 34,215.75
- Pemasangan m' 1.00 17,107.88 17,107.88
Harga Upah : 51,323.63
Jumlah Harga Satuan 393,481.13
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
6 BAHAN KAPUR
Kapur halus/bersih (batu tela) M³ 956,418.00
Kapur Kotor (Timbunan) M³ 956,418.00
7 BAHAN KARANG
a. Karang Kasar / Karang timbun M³ 956,418.00
b. Karang Halus Cor M³ 956,418.00
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
8 BAHAN SEMEN
a. Semen Tiga Roda 50 Kg (PC) Zak 168,000.00
b. Semen Gresik Zak 168,000.00
c. Semen Nusantara Zak -
d. - Semen Tonasa 50 Kg (PC) Zak 168,000.00
- Semen Tiga Roda 50 Kg (PCC) Zak -
- Semen Tiga Roda 40 Kg (PPC) Zak 148,000.00
e. SemenBosowa 50 Kg (PC) Zak -
f. Semen Asano Zak -
g. Semen Putih 1 Kg Kg 36,000.00
h. Semen Warna 1 Kg Kg 42,000.00
i. Semen Merah ( Bks 8 ons ) Kg 27,000.00
9 BAHAN LANTAI
a. Ubin PC :
Ubin PC : Abu-abu 20 Cm x 20 Cm M² 104,400.00
Ubin PC : Warna 20 Cm x 20 Cm M² 112,140.00
b. Ubin Marmer 30 Cm x 30 Cm M² -
c. Ubin Teraso DN 15 Cm x 20 Cm M² -
Ubin Teraso DN 30 Cm x 30 Cm M² 134,000.00
d. Ubin Mozaik DN 30 Cm x 30 Cm M² -
Mosaik Km/Wc 20 Cm x 20 Cm M² -
e. Ubin Porselin DN 11 x 11 ( isi 120 bh / dos ) M² -
Ubin Porselin DN 10 Cm x 15 Cm M² -
Ubin Porselin DN 15 Cm x 15 Cm M² -
Ubin Porsein DN 20 Cm x 20 Cm M² -
f. Ubin Wafel DN 15 Cm x 15 Cm M² -
Ubin Wafel DN 20 Cm x 20 Cm M² -
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
10 BAHAN KAYU
a. Kayu Besi ( Sejenis ) :
Balok ukuran 10 x 10 M³ 3,500,000.00
Balok ukuran 5 x 10 M³ 3,500,000.00
Balok ukuran 5x5 M³ 3,550,000.00
Papan Ukuran 2 x 20 x 400 M³ 3,833,000.00
Papan Ukuran 2,5 x 20 x 400 M³ 3,833,000.00
Papan Ukuran 3 x 30 x 400 M³ 3,850,000.00
b. Kayu Matoa/Campuran :
Balok ukuran 10 x 10 M³ 2,033,300.00
Balok ukuran 5 x 10 M³ 2,033,300.00
Balok ukuran 5x5 M³ 2,033,300.00
Balok ukuran 5,5 x 20 M³ 2,033,300.00
Papan ukuran 2 x 20 x 400 M³ 2,316,700.00
Papan ukuran 2,5 x 20 x 400 M³ 2,316,700.00
Papan ukuran 3 x 20 x 400 M³ 2,316,700.00
Papan ukuran 1,5 x 20 x 400 M³ 2,316,700.00
d. Kayu Lat :
Lat papan kayu besi 4 mtr Btg -
Lat papan kayu matoa 4 mtr Btg 13,000.00
Lat kayu profil kecil 4 mtr Btg
Lat kayu profil besar 4 mtr Btg
List plafond rata sudut SP3 = 3 Cm Btg 17,000.00
SP3 = 4 Cm Btg 18,000.00
SP5 = 5 Cm Btg 19,000.00
SP7 = 7 Cm Btg 22,000.00
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
l. Papan Ulin M³ -
11 BAHAN ATAP
a. Seng Gelombang Bjls 20 ( Gajah ) LBR 95,566.00
Seng Gelombang Bjls 30 ( Gajah ) LBR 133,893.00
i. Lain-Lain :
Galvanis Listplank LBR 140,000.00
DHSBU 404288434.xls Divisi : Strutkur
Hal. 141 dari 150
DAFTAR HARGA BAHAN BANGUNAN,DAN UPAH KERJA DI KAB.MAYBRAT
PERIODE : OKTOBER- DESEMBER 2016 ( TRIWULAN IV )
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
Pek.Zincalium 20 x 35 M2 81,354.00
Pek.Zincalium 40 x 75 M2 96,720.00
Harflex/Tilus LBR -
Kalsiboard Lisplank M' 300,000.00
Pek.4" Black Stell SCH 40 t = 6mm Kg 87,672.00
Baut M.16 (HTB) bh 40,000.00
Besi Plate t = 10 mm Kg 45,000.00
Rib Plate t = 10 mm Kg 45,000.00
Stifner t = 8 mm Kg 45,000.00
Angker Ø 16, L= 40 cm bh 90,000.00
-
12 BAHAN PLAFOND -
Akustik Ukuran 30 x 30 cm LBR 100,000.00
Akustik Ukuran 30 x 60 cm LBR 99,000.00
Enternit Ukuran 100 x 100 cm LBR -
Soft Board Ukuran 122 x 244 cm LBR -
Kalsiboard 122 x 244 cm LBR 300,000.00
13 BAHAN KACA -
Ukuran 122 182 cm -
a. Kaca Bening T.3 mm 122 x 152 cm LBR 498,600.00
Kaca Bening T.5 mm 183 x 132 cm LBR 736,600.00
-
b. Kaca Buram T.3 mm 183 x 132 cm LBR -
Kaca Buram T.4 mm 183 x 132 cm LBR -
Kaca Buram T.5 183 x 153 cm LBR 841,000.00
-
c. Kaca Rayband T.3 mm 122 x 152 cm LBR 668,000.00
Kaca Rayband T.5 mm 153 x 203 cm LBR 925,400.00
-
d. Kaca Cermin T.5 mm 153 x 203 cm LBR 560,000.00
-
14 BAHAN JENDELA LOVERS -
a. Lovers / nako tanpa teralis -
4 Klips SET 106,600.00
5 Klips SET 126,600.00
6 Klips SET 149,400.00
7 Klips SET 202,000.00
8 Klips SET 227,400.00
9 Klips SET 369,400.00
10 klips SET 424,600.00
b. Lovers / Nako tralis (Kaca Riben) -
4 Klips SET 242,000.00
5 Klips SET 300,000.00
6 Klips SET 349,400.00
7 Klips SET 372,000.00
8 Klips SET 428,000.00
9 Klips SET 484,000.00
10 Klips SET 516,000.00
c. Stang Lovers / Klips -
4 Klips Psg 144,000.00
5 Klips Psg 163,400.00
6 Klips Psg 182,600.00
7 klips Psg 202,000.00
8 Klips Psg 221,400.00
9 Klips Psg 244,000.00
10 Klips Psg 266,600.00
d. - Besi Tralis Nako/Firkan (Kotak) 8 mm = 6 mtr Btg 63,400.00
- Besi Tralis Nako/Firkan (Kotak) 10 mm = 6 mtr Btg 68,000.00
- Besi Tralis Nako/Firkan (Kotak) 12 mm = 6 mtr Btg 89,400.00
- Besi Tralis Nako/Firkan (Kotak) 14 mm = 6 mtr Btg 160,000.00
-
e. Kaca Louvers Bening Lbr 20,600.00
-
f. Kaca Louvers Buram Lbr 31,000.00
-
g. Kaca Louvers Raybend Lbr 26,600.00
-
15 BAHAN PENGUNCI / PENGGANTUNG -
a. Kunci Tanam : -
Union 3 Slang SET 305,000.00
Union 2 Slang SET 310,000.00
Merk Janes 2 Slang SET 260,000.00
Yale 2 Slang SET 276,000.00
DHSBU 404288434.xls Divisi : Strutkur
Hal. 142 dari 150
DAFTAR HARGA BAHAN BANGUNAN,DAN UPAH KERJA DI KAB.MAYBRAT
PERIODE : OKTOBER- DESEMBER 2016 ( TRIWULAN IV )
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4
HARGA BAHAN
NO URAIAN PE K E RJAAN SAT. BANGUNAN
Rata-Rata
1 2 3 4