A. TENAGA KERJA
1 Mandor OH 0.0563 107,000.00 6,024.100
2 Pekerja OH 0.5630 61,000.00 34,343.00
JUMLAH 40,367.10
JUMLAH 40,367.10
HARGA SATUAN PEKERJAAN 40,367.10
A. TENAGA KERJA
1 Mandor OH 0.0330 107,000.00 3,531.000
2 Pekerja OH 0.3300 61,000.00 20,130.00
JUMLAH 23,661.00
JUMLAH 23,661.00
HARGA SATUAN PEKERJAAN 23,661.00
A. TENAGA KERJA
1 Mandor OH 0.0500 107,000.00 5,350.000
2 Pekerja OH 0.5000 61,000.00 30,500.00
JUMLAH 35,850.00
JUMLAH 35,850.00
HARGA SATUAN PEKERJAAN 35,850.00
ANALISA HARGA SATUAN
A. TENAGA KERJA
1 Mandor OH 0.004 107,000.00 438.700
2 Tukang OH 0.257 76,000.00 19,532.00
3 Pekerja OH 0.081 61,000.00 4,941.00
SUB JUMLAH (A) 24,911.70
B. BAHAN
1 PIPA PVC AW 4" M' 1.200 73,650.00 88,380.000
SUB JUMLAH (B) 88,380.00
HARGA HARGA
NO. URAIAN PEKERJAAN SAT VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
a b c d e f = (d x e)
A BELANJA UPAH
1 Pekerjaan Galian Tanah Biasa ≤ 1 M M3 90.00 40,367.10 3,633,039.00
2 Pekerjaan Timbunan Tanah Kembali M3 44.78 23,661.00 1,059,634.22
3 Pekerjaan Pemadatan Tanah M3 44.78 35,850.00 1,605,506.40
4 Pekerjaan Pemasangan Pipa AW 4" M' 360.00 24,911.70 8,968,212.00
JUMLAH (A) 15,266,391.62
B BELANJA BAHAN
1 Pekerjaan Galian Tanah Biasa ≤ 1 M M3 90.00 0.00 0.00
2 Pekerjaan Timbunan Tanah Kembali M3 44.78 0.00 0.00
3 Pekerjaan Pemadatan Tanah M3 44.78 0.00 0.00
4 Pekerjaan Pemasangan Pipa AW 4" M' 360.00 88,380.00 31,816,800.00
5 Pemasangan Tee Ø 4" BH 12.00 85,000.00 1,020,000.00
6 Pemasangan Knee 90° Ø 4" BH 12.00 63,800.00 765,600.00
7 Pemasangan Knee 45° Ø 4" BH 12.00 62,200.00 746,400.00
8 Lem PVC Vinilon Kaleng 10.00 68,550.00 685,500.00
JUMLAH (B) 35,034,300.00
JUMLAH ( A + B ) 50,300,691.62
JUMLAH DIBULATKAN 50,300,000.00
TERBILANG : TUJUH PULUH SATU JUTA DUA RATUS DUA PULUH DELAPAN RIBU RUPIAH
CIREBON, 2017
DISETUJUI :
SATUAN KERJA OP SDA CIMANUK - CISANGGARUNG
PEJABAT PEMBUAT KOMITMEN
O & P SDA III
A. TENAGA KERJA
1 Mandor OH 0.298 108,000.00 32,184.000
2 Tukang (Penganyam) OH 0.380 77,000.00 29,260.000
3 Pekerja (Pengisi Batu) OH 0.325 61,000.00 19,825.00
SUB JUMLAH (A) 81,269.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 107,000.00 31,886.000
2 Tukang (Penganyam) OH 0.380 76,000.00 28,880.000
3 Pekerja (Pengisi Batu) OH 0.325 61,000.00 19,825.00
SUB JUMLAH (A) 80,591.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 112,000.00 33,376.000
2 Tukang (Penganyam) OH 0.380 80,000.00 30,400.000
3 Pekerja (Pengisi Batu) OH 0.325 64,000.00 20,800.00
SUB JUMLAH (A) 84,576.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 94,000.00 28,012.000
2 Tukang (Penganyam) OH 0.380 67,000.00 25,460.000
3 Pekerja (Pengisi Batu) OH 0.325 54,000.00 17,550.00
SUB JUMLAH (A) 71,022.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 91,000.00 27,118.000
2 Tukang (Penganyam) OH 0.380 65,000.00 24,700.000
3 Pekerja (Pengisi Batu) OH 0.325 52,000.00 16,900.00
SUB JUMLAH (A) 68,718.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 153,000.00 45,594.000
2 Tukang (Penganyam) OH 0.380 109,000.00 41,420.000
3 Pekerja (Pengisi Batu) OH 0.325 87,000.00 28,275.00
SUB JUMLAH (A) 115,289.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 95,000.00 28,310.000
2 Tukang (Penganyam) OH 0.380 68,000.00 25,840.000
3 Pekerja (Pengisi Batu) OH 0.325 54,000.00 17,550.00
SUB JUMLAH (A) 71,700.00
B. BAHAN
1 Batu Belah M3 1.300 296,500.00 385,450.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 385,450.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -
A. TENAGA KERJA
1 Mandor OH 0.298 80,000.00 23,840.000
2 Tukang (Penganyam) OH 0.380 68,000.00 25,840.000
3 Pekerja (Pengisi Batu) OH 0.325 55,000.00 17,875.00
SUB JUMLAH (A) 67,555.00
B. BAHAN
1 Batu Belah M3 1.300 196,700.00 255,710.000
2 Kawat Bronjong Ø 3mm KG 15.100 43,000.00 649,300.000
SUB JUMLAH (B) 255,710.00
C. PERALATAN
- -
- -
SUB JUMLAH (C) -