Analisis Sadfdf
Analisis Sadfdf
Koeff. Koeff.
No. Uraian Jenis pekerjaan Sat. Volume Sat Kebutuhan Tenaga Kerja
(Awal) (Akhir)
1 2 3 4 5 6 7 8=5x6
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Pekerja Oh 0.1600 0.1440 691.220 m2 99.536
Tukang cat Oh 0.2800 0.2520 691.220 m2 174.187
Kepala tukang cat Oh 0.0300 0.0270 691.220 m 2
18.663
Mandor Oh 0.0100 0.0090 691.220 m2 6.221
Jumlah 298.607
X.2 PENGECATAN KUSEN, DAUN PINTU, DAN JENDELA
Pekerja Oh 0.2000 0.1800 87.250 m2 15.705
Tukang cat Oh 0.3000 0.2700 87.250 m 2
23.558
Kepala tukang cat Oh 0.0300 0.0270 87.250 m2 2.356
Mandor Oh 0.0100 0.0090 87.250 m 2
0.785
Jumlah 42.404
X.3 PENGECATAN PLAFOND
Pekerja Oh 0.2000 0.1800 52.870 m2 9.517
Tukang cat Oh 0.2800 0.2520 52.870 m2 13.323
Kepala tukang cat Oh 0.0300 0.0270 52.870 m 2
1.427
Mandor Oh 0.0100 0.0090 52.870 m2 0.476
Jumlah 24.743