Anda di halaman 1dari 91

RENCANA PROGRESS : 59.

952 ( % )
Rutin Jalan REALISASI PROGRESS : 35.693 ( % )
DEVIASI : ### ( % )
RENCANA PROGRESS : ( % )
Terhadap Induk REALISASI PROGRESS : ( % )
DEVIASI : - ( % )

RENCANA PROGRESS : 58.629 ( % )


Rutin Jembatan REALISASI PROGRESS : 25.642 ( % )
DEVIASI : ### ( % )
RENCANA PROGRESS : ( % )
Terhadap Induk REALISASI PROGRESS : ( % )
DEVIASI : - ( % )

RENCANA PROGRESS : 61.697 ( % )


Rekonstruksi REALISASI PROGRESS : 9.746 ( % )
DEVIASI : ### ( % )
RENCANA PROGRESS : ( % )
Terhadap Induk REALISASI PROGRESS : ( % )
DEVIASI : - ( % )

RENCANA PROGRESS : 59.921 ( % )


Umum REALISASI PROGRESS : 10.320 ( % )
DEVIASI : ### ( % )

file:///conversion/tmp/scratch/416541299.xlsx
FORM LAPORAN MINGGUAN ke KASATKER P2JN

NAMA PAKET : Paket 9, Pengawasan Teknis Preservasi Rekonstruksi Jalan dan Penggantian Jembatan Sei. Kelik - Siduk

NO. KONTRAK : 117/HK.02.03/SATKERP2JN-KB/I/2018

TANGGAL KONTRAK : Friday, January 05, 2018

NO. SPMK : 146 /HK.01.24/SATKER P2JN- KB/I/2018

TANGGAL SPMK : ###


NAMA SE : Ir. Totok Kusmanto

PRESERVASI DENGAN CARA LONG SEGMENT

PROGRES PERMASALA
No JENIS PEKERJAAN
RENCANA (%) REALISASI (%) DEVIASI (%) USULAN TEKNIS UNTU

1 Pekerjaan Rutin Jembatan 58.629 25.642 -32.987 Segera dilakukan pembers

STRIPMAP RENCANA
STRIPMAP RUTIN JEMBATAN
Sta 0+000 / KM 360+620 Sta 7+390 / KM 375+105 Sta 20+797 / KM 381+417 Sta 28+803 / KM 389+423 Sta 31+280 / KM 391+900

Sta 0+105 / KM 367+715 Sta 15+070 / KM 375+690 Sta 22+510 / KM 383+130 Sta 30+550 / KM 391+170 Sta 32+054 / KM 392+67

Sta 35+005 / KM 395+625 Sta 38+825 / KM 399+445 Sta 40+775 / KM 401+395 Sta 44+031 / KM 404+651 Sta 45+820 / KM 406+440 Sta 51+51

Sta 35+690 / KM 396+310 Sta 39+290 / KM 399+910 Sta 43+903 / KM 404+523 Sta 44+626 / KM 405+246 Sta 48+263 / KM 408+88

Sta 54+948 / KM 415+568 Sta 57+515 / KM 418+135 Sta 59+662 / KM 420+282 Sta 61+700 / KM 422+320
Sta 57+025 / KM 417+645 Sta 58+650 / KM 419+270 Sta 60+315 / KM 420+935

STRIPMAP REALISASI SAMPAI DENGAN MINGGU KE 30


STRIPMAP RUTIN JEMBATAN
Sta 0+000 / KM 360+620 Sta 7+390 / KM 375+105 Sta 20+797 / KM 381+417 Sta 28+803 / KM 389+423 Sta 31+280 / KM 391+900

Sta 0+105 / KM 367+715 Sta 15+070 / KM 375+690 Sta 22+510 / KM 383+130 Sta 30+550 / KM 391+170 Sta 32+054 / KM 392+67

Sta 35+005 / KM 395+625 Sta 38+825 / KM 399+445 Sta 40+775 / KM 401+395 Sta 44+031 / KM 404+651 Sta 45+820 / KM 406+440 Sta 51+51

Sta 35+690 / KM 396+310 Sta 39+290 / KM 399+910 Sta 43+903 / KM 404+523 Sta 44+626 / KM 405+246 Sta 48+263 / KM 408+88

Sta 54+948 / KM 415+568 Sta 57+515 / KM 418+135 Sta 59+662 / KM 420+282 Sta 61+700 / KM 422+320

Sta 57+025 / KM 417+645 Sta 58+650 / KM 419+270 Sta 60+315 / KM 420+935


Keterangan :
Jembatan Dalam Kondisi Sudah Ditangani Jembatan Dalam Kondisi Belum Tertangani
GUAN ke KASATKER P2JN

N CARA LONG SEGMENT

PERMASALAHAN dan
USULAN TEKNIS UNTUK PENYEDIA JASA

Segera dilakukan pembersihan jembatan kembali

P RENCANA
UTIN JEMBATAN
Sta 33+620 / KM 394+240

Sta 32+054 / KM 392+674 Sta 34+525 / KM 395+145

Sta 51+510 / KM 412+130

Sta 48+263 / KM 408+883 Sta 52+415 / KM 413+035


MPAI DENGAN MINGGU KE 30
UTIN JEMBATAN
Sta 33+620 / KM 394+240

Sta 32+054 / KM 392+674 Sta 34+525 / KM 395+145

Sta 51+510 / KM 412+130

Sta 48+263 / KM 408+883 Sta 52+415 / KM 413+035


FORM LAPORAN

NAMA PAKET : Paket 9, Pengawasan Teknis Preservasi Rekonstruksi Jalan dan Penggantian Jembatan Sei. Kelik - Siduk
NO. KONTRAK : 117/HK.02.03/SATKERP2JN-KB/I/2018
TANGGAL KONTRAK : 05 Januari 2018
NO. SPMK : 146 /HK.01.24/SATKER P2JN- KB/I/2018
TANGGAL SPMK : 08 Januari 2018
NAMA SE : Ir. Totok Kusmanto

PRESERVASI DENGAN CARA LONG SE


PROGRES
NO JENIS PEKERJAAN
RENCANA (%) REALISASI (%) DE

1 PEKERJAAN RUTIN JALAN 59.952 35.693 -

STRIPMAP RENCANA
STRRIPMAP RUTIN JALAN
KM 360+620 TUGU KELIK KM 368+845 KM 370+945
KM 366+995 KM 367+970 KM 370+045 KM 371+920
KM 375+690 KM 376+070 KM 376+770 KM 377+445

KM 375+920 KM 376+270 KM 377+120

KM 379+130 KM 379+410 KM 379+840 KM 380+510

KM 379+295 KM 379+470 KM 380+295

KM 383+595 KM 383+670 KM 383+765 KM 384+145


KM 383+650 KM 383+695 KM 383+795
KM 385+895 KM 386+170 KM 386+970 KM 387+170

KM 386+070 KM 386+470 KM 387+070

KM 388+120 KM 383+670 KM 388+620 KM 389+920

KM 388+220 KM 388+395 KM 388+770

KM 391+625 KM 392+195 KM 392+720 KM 393+020


KM 392+020 KM 392+420 KM 392+970

KM 383+595 KM 395+145 KM 395+620 KM 396+570

KM 394+920 KM 395+470 KM 396+320

KM 398+020 KM 398+520 KM 400+120 KM 400+570

KM 398+370 KM 398+870 KM 400+245

KM 410+120

PAKET TAHUN 2018


Keterangan :
Badan Jalan kondisi baik / Mantap Lokasi Kerusakan Lokasi Badan Jalan Kondisi Sudah Tertimbun Tanah
Bahu Jalan kondisi baik / Mantap Lokasi Penanganan
Drainase kondisi baik / Mantap Lokasi Sudah Tertangani
STRIPMAP REALISASI SAMPAI DENGAN
STRRIPMAP RUTIN JALAN
KM 360+620 TUGU KELIK KM 368+845 KM 370+945

KM 366+995 KM 367+970 KM 370+045 KM 371+920


KM 375+690 KM 376+070 KM 376+770 KM 377+445

KM 375+920 KM 376+270 KM 377+120

KM 379+130 KM 379+410 KM 379+840 KM 380+510


KM 379+295 KM 379+470 KM 380+295

KM 383+595 KM 383+670 KM 383+765 KM 384+145

KM 383+650 KM 383+695 KM 383+795

KM 385+895 KM 386+170 386+970 KM 387+170

KM 386+070 KM 386+470 KM 387+070

KM 388+120 KM 388+670 KM 388+920 KM 389+920


KM 388+220 KM 388+395 KM 388+770
KM 391+625 KM 392+195 KM 392+720 KM 393+020

KM 392+020 KM 392+420 KM 392+970

KM 383+595 KM 395+145 KM 395+620 KM 396+570

KM 394+920 KM 395+470 KM 396+320

KM 398+020 KM 398+520 KM 400+120 KM 400+570


KM 398+370 KM 398+870 KM 400+245

KM 400+895 KM 410+120

PAKET TAHUN 2018

KM 401+120
Keterangan :
Badan Jalan kondisi baik / Mantap Lokasi Kerusakan Lokasi Badan Jalan Kondisi Sudah Tertimbun Tanah
Bahu Jalan kondisi baik / Mantap Lokasi Penanganan Realisasi Marka jalan
Drainase kondisi baik / Mantap Lokasi Sudah Tertangani Realisasi Timbunan Pilihan
M LAPORAN MINGGUAN

n Sei. Kelik - Siduk

N CARA LONG SEGMENT


RES PERMASALAHAN DAN
DEVIASI (%) USULAN TEKNIS UNTUK PENYEDIA JASA

-24.259 Diharapkan segera lakukan pengendalian tanaman dan Patching

MAP RENCANA
MAP RUTIN JALAN
KM 372+345 KM 373+995 KM 375+220
KM 373+120 KM 374+645
KM 378+445 KM 378+845

KM 377+620 KM 378+620 KM 379+070

KM 381+115 KM 383+190

KM 380+635 KM 382+980 KM 383+470

KM 385+095 KM 385+740
KM 384+825 KM 385+145 KM 385+795
KM 387+520 KM 387+920

KM 387+420 KM 387+770 KM 388+020

KM 390+620 KM 391+170

KM 390+470 KM 390+970 KM 391+470

KM 393+670 KM 394+420
KM 393+270 KM 394+070 KM 394+480

KM 396+770 KM 397+120

KM 396+645 KM 397+070 KM 397+420

KM 400+945 KM 401+120

KM 400+845 KM 401+070

Badan Jalan kondisi baik / Mantap


KM 421+620

Tertimbun Tanah
AMPAI DENGAN MINGGU KE 30
MAP RUTIN JALAN
KM 372+345 KM 373+995 KM 375+220

KM 373+120 KM 374+645
KM 378+445 KM 378+845

KM 377+620 KM 378+620 KM 379+070

KM 381+115 KM 383+190
KM 380+635 KM 382+980 KM 383+470

KM 385+095 KM 385+740

KM 384+825 KM 385+145 KM 385+795

KM 387+520 KM 387+920

KM 387+420 KM 387+770 KM 388+020

KM 390+620 KM 391+170
KM 390+470 KM 390+970 KM 391+470
KM 393+670 KM 394+420

KM 393+270 KM 394+070 KM 394+480

KM 396+770 KM 397+120

KM 396+645 KM 397+070 KM 397+420


KM 401+120
KM 400+945 401+120
KM 400+845 KM 401+070 KM 401+370

Badan Jalan kondisi baik / Mantap

KM 421+620

Tertimbun Tanah
KM 414+000 KM 418+000
Nama Pekerjaan : PRESERVASI REKONTRUKSI JALAN DAN RUTIN JEMBATAN RUAS SEI.KELIK - SIDUK
Paket Kontrak/No : IK.02.04/PJN.WIL.I-KB/2018/03
Penyedia Jasa : PT. DAMAI CITRA MANDIRI
Konsultan Supervis
: PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN PT. WIRAWIDYATAMA

BULAN KE 1 BULAN KE 2

8-Jan-18 15-Jan-18 22-Jan-18 29-Jan-18 5-Feb-18 12-Feb-18 19-Feb-18

NOMOR MATA NILAI PEKERJAAN NILAI PEKERJAAN


14-Jan-18 21-Jan-18 28-Jan-18 4-Feb-18 11-Feb-18 18-Feb-18 25-Feb-18
U R A I A N
PEMBAYARAN (%) ADD 1 (%)

MINGGU KE MINGGU KE

1 2 3 4 5 6 7

DIVISI 1 UMUM
1.2 Mobilisasi 0.81 0.81 0.10 0.10 0.10 0.10 0.10 0.10 0.10
1.8(1) Manajemen dan Keselamatan Lalu Lintas 0.22 0.22 0.01 0.01 0.01 0.01 0.01 0.01 0.01
1.17 Pengamanan Lingkungan Hidup 0.20 0.20 0.01 0.01 0.01 0.01 0.01 0.01 0.01
1.21 Manajemen Mutu 0.19 0.19 0.01 0.01 0.01 0.01 0.01 0.01 0.01

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air 1.00 0.38
2.2.(1) Pasangan Batu dengan Mortar 5.35 0.19
2.3.4 Gorong-gorong Pipa Beton Bertulang, diameter dalam 95 - 105 cm 0.30

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa 1.48 4.39 0.25 0.25 0.25
3.1.(1b) Galian Batu Lunak 0.39 0.98 0.06 0.06 0.06
3.2.(1a) Timbunan Biasa dari Sumber Galian 0.32 1.17
3.2.(2a) Timbunan Pilihan dari Sumber Galian 3.34 9.79
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) 0.15 0.17
DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN
4.2.2b Lapis Pondasi Agregat Kelas S 2.45 3.49
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan 1.07 0.86

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB 1.13
5.5.(1b) Semen Untuk CTB 0.30
SKH 5.6.(1a) Semen Untuk CTRB 11.21 9.89
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) 28.21 22.12

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi 2.15 -
6.1 (2)(b) Lapis Perekat - Aspal Emulsi 0.34 2.69
6.3 (3a) Lataston Lapis Aus ( HRS - WC ) ( gradasi senjang / semi senjan 14.19 16.39
6.3 (4a) Lataston Lapis Pondasi ( HRS - Base ) ( gradasi senjang / semi 18.21 21.38
6.3 (8) Bahan Anti Pengelupasan - -

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa 0.06 0.02
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa 0.00 -
7.3 (1) Baja Tulangan U24 polos 0.02 -
7.3 (3) Baja Tulangan U32 Ulir 0.10 0.05
7.9 Pasangan Batu 1.50 0.08
7.10 (2) Pasangan Batu Kosong 0.05 -
7.13.(1) Sandaran (Railing) 0.00 0.00

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR


8.4 (1) Marka Jalan Termoplastik 1.22 1.37
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade 0.08 0.08
8.4.(6a) Patok Kilometer 0.01 0.01
8.4.(6b) Patok Hektometer / ROW 0.07 0.07
SKh-1.10a PEMELIHARAAN KINERJA JALAN
SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B 4.83 0.61 0.10 0.10 0.10 0.10 0.10 0.10 0.10
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S 0.03 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 10 ) Campuran Aspal Panas 0.08 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 11 ) Campuran Aspal Dingin 0.04 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 12 ) Penetrasi Macadam 0.04 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) 0.01 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija 0.27 0.27 0.01 0.01 0.01 0.01 0.01 0.01 0.01

REALISA
SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN
SKh.1.10.b ( 1 ) Pembersihan Jembatan 0.15 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.a ( 3 ) Pengecatan Sederhana 0.15 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SKh.1.10.b ( 10 ) Perbaikan sandaran 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH NILAI PEKERJAAN 100.00 100.00


KEMAJUAN PEKERJAAN MINGGUAN ( % ) 0.24 0.24 0.24 0.24 0.55 0.55 0.55
RENCANA
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 0.24 0.48 0.71 0.95 1.50 2.05 2.60
KEMAJUAN PEKERJAAN MINGGUAN ( % ) 0.00 0.16 0.03 0.02 0.12 0.03 0.00
REALISASI
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 0.00 0.16 0.19 0.21 0.33 0.36 0.36
KEMAJUAN PEKERJAAN MINGGUAN ( % )
RENCANA ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )
KEMAJUAN PEKERJAAN MINGGUAN ( % )
REALISASI ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )

(PPK-7) NANGA TAYAP - SEI. KELIK - KETAPANG

TITO PURNOMO R, ST, MT


NIP. 1968112 199703 1 003
JADWAL PELAKSANAAN

Add 1

BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5

26-Feb-18 5-Mar-18 12-Mar-18 19-Mar-18 26-Mar-18 2-Apr-18 9-Apr-18 16-Apr-18 23-Apr-18 30-Apr-18 7-May-18

4-Mar-18 11-Mar-18 18-Mar-18 25-Mar-18 1-Apr-18 8-Apr-18 15-Apr-18 22-Apr-18 29-Apr-18 6-May-18 13-May-18

MINGGU KE MINGGU KE MINGGU KE MINGGU KE

8 9 10 11 12 13 14 15 16 17 18

0.10 0.24
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

0.10 0.10 0.10 0.10 0.10 0.09


0.45 0.45 0.45 0.45 0.45 0.19
0.30

0.25 0.25 0.25 0.32 0.32 0.32 0.32 0.32


0.06 0.06 0.06 0.66
0.08 0.08 0.08 0.08 0.85
0.67 0.67 0.39 0.72 0.72 0.61 0.61
0.01 0.01 0.01 0.01 0.01
1.58 1.58
2.36 0.32 0.02 1.58 1.58

SCHEDULE AWAL
0.10 0.10 0.10 0.10 0.10 0.10
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00

REALISASI
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.55 1.07 1.07 0.76 1.43 1.35


3.15 4.22 5.29 6.06 7.49 8.84
0.97 0.14 0.55 0.20 0.52 0.40
1.331 1.47 2.02 2.22 2.74 3.14
5.13 1.39 1.39 4.13 4.13
10.19 11.58 12.96 17.09 21.22
0.40 0.03 0.03 0.07 0.98
3.54 3.57 3.61 3.67 4.65
AKSANAAN PEKERJAAN

AN KE 5 BULAN KE 6 BULAN KE 7 BULAN KE 8 BULAN KE 9

14-May-18 21-May-18 28-May-18 4-Jun-18 11-Jun-18 18-Jun-18 25-Jun-18 2-Jul-18 9-Jul-18 16-Jul-18 23-Jul-18 30-Jul-18 6-Aug-18 13-Aug-18 20-Aug-18 27-Aug-18 3-Sep-18 10-Sep-18 17-Sep-18

20-May-18 27-May-18 3-Jun-18 10-Jun-18 17-Jun-18 24-Jun-18 1-Jul-18 8-Jul-18 15-Jul-18 22-Jul-18 29-Jul-18 5-Aug-18 12-Aug-18 19-Aug-18 26-Aug-18 2-Sep-18 9-Sep-18 16-Sep-18 23-Sep-18

GGU KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

0.32 0.32 0.32 0.32 0.32

L
0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21
I
0.01 0.01 0.01 0.01 0.01 SCHEDULE ADD 1
B
B
0.87 0.87 0.87 0.87
U 0.17 0.17 0.17 0.17

R
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48
1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16

I
0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
D 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17 1.17
1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53
U

ULE AWAL 0.02 0.02


0.05
0.02

I
0.18 0.18 0.18
T

I
I
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2.30 2.30 2.30 2.30 0.00 0.00 5.19 4.86 4.86 4.86 4.86 4.86 4.86 4.86 4.86 5.91 4.36 4.36 4.42
23.52 25.82 28.11 30.41 30.41 30.41 35.60 40.46 45.33 50.19 55.06 59.92 64.79 69.65 74.51 80.42 84.79 89.15 93.57
0.82 0.11 2.25 -0.03 0.00 0.00 0.00 2.51 0.00 0.00 0.00 0.00
5.47 5.58 7.84 7.81 7.81 7.81 7.81 10.32 10.32 10.32 10.32 10.32

PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN PT.


WIRAWIDYATAMA

Ir. TOTOK KUSMANTO


Site Engineer
BULAN KE 10 BULAN KE 11 BULAN KE 12 BULAN KE 13

24-Sep-18 1-Oct-18 8-Oct-18 15-Oct-18 22-Oct-18 29-Oct-18 5-Nov-18 12-Nov-18 19-Nov-18 26-Nov-18 3-Dec-18 10-Dec-18 17-Dec-18 24-Dec-18

30-Sep-18 7-Oct-18 14-Oct-18 21-Oct-18 28-Oct-18 4-Nov-18 11-Nov-18 18-Nov-18 25-Nov-18 2-Dec-18 9-Dec-18 16-Dec-18 23-Dec-18 31-Dec-18

MINGGU KE MINGGU KE MINGGU KE MINGGU KE

38 39 40 41 42 43 44 45 46 47 48 49 50 51

0.01 0.01
0.01 0.01
0.01 0.01

0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21
0.17

0.19
1.17
1.53

0.02

0.02

0.00

0.18 0.18
0.08
0.01 0.01
0.03 0.03
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.55 0.53 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.00
97.12 97.66 97.87 98.08 98.30 98.51 98.72 98.94 99.15 99.36 99.58 99.79 100.00 100.00

PT. DAMAI CITRA MANDIRI

KOES WIDARYANTO
General Superintendent
Nama Pekerjaan : PRESERVASI REKONTRUKSI JALAN DAN RUTIN JEMBATAN RUAS SEI.KELIK - SIDUK
Paket Kontrak/No : IK.02.04/PJN.WIL.I-KB/2018/03
Penyedia Jasa : PT. DAMAI CITRA MANDIRI
Konsultan Supervisi : PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN PT. WIRAWIDYATAMA

BULAN KE 1 BULAN KE 2
NILAI 8-Jan-18 15-Jan-18 22-Jan-18 29-Jan-18 5-Feb-18 12-Feb-18 19-Feb-18
NOMOR MATA NILAI
U R A I A N PEKERJAAN 14-Jan-18 21-Jan-18 28-Jan-18 4-Feb-18 11-Feb-18 18-Feb-18 25-Feb-18
PEMBAYARAN PEKERJAAN (%)
ADD 1 (%) MINGGU KE MINGGU KE
1 2 3 4 5 6 7

DIVISI 1 UMUM
1.2 Mobilisasi 0.87 0.87 0.11 0.11 0.11 0.11 0.11 0.11 0.11
1.8(1) Manajemen dan Keselamatan Lalu Lintas 0.24 0.24 0.01 0.01 0.01 0.01 0.01 0.01 0.01
1.17 Pengamanan Lingkungan Hidup 0.21 0.21 0.01 0.01 0.01 0.01 0.01 0.01 0.01
1.21 Manajemen Mutu 0.20 0.20 0.01 0.01 0.01 0.01 0.01 0.01 0.01

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air 1.07 0.41
2.2.(1) Pasangan Batu dengan Mortar 5.73 0.21
2.3.4 Gorong-gorong Pipa Beton Bertulang, diameter dalam 95 - 105 cm 0.32

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa 1.59 4.70 0.26 0.26 0.26
3.1.(1b) Galian Batu Lunak 0.41 1.04 0.07 0.07 0.07
3.2.(1a) Timbunan Biasa dari Sumber Galian 0.35 1.26
3.2.(2a) Timbunan Pilihan dari Sumber Galian 3.01 5.32
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) 0.16 0.19

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S 2.62 3.74
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan 1.15 0.92

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB 1.21
5.5.(1b) Semen Untuk CTB 0.32
SKH 5.6.(1a) Semen Untuk CTRB 12.00 10.59
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) 30.21 23.69

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi 2.30 -
6.1 (2)(b) Lapis Perekat - Aspal Emulsi 0.37 2.88
6.3 (3a) Lataston Lapis Aus ( HRS - WC ) ( gradasi senjang / semi senjang ) 15.20 17.55
6.3 (4a) Lataston Lapis Pondasi ( HRS - Base ) ( gradasi senjang / semi senjang ) 19.50 22.89
6.3 (8) Bahan Anti Pengelupasan -

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa 0.06 0.02
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa 0.01 -
7.3 (1) Baja Tulangan U24 polos 0.02 -
7.3 (3) Baja Tulangan U32 Ulir 0.11 0.06
7.9 Pasangan Batu 1.61 0.09
7.10 (2) Pasangan Batu Kosong 0.05 -
7.13.(1) Sandaran (Railing) 0.00 0.00

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR


8.4 (1) Marka Jalan Termoplastik 0.78 0.90
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade 0.09 0.09
8.4.(6a) Patok Kilometer 0.01 0.01
8.4.(6b) Patok Hektometer / ROW 0.07 0.07

JUMLAH NILAI PEKERJAAN 100.00 100.00


KEMAJUAN PEKERJAAN MINGGUAN ( % ) 0.13 0.13 0.13 0.13 0.46 0.46 0.46
RENCANA
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 0.13 0.25 0.38 0.51 0.97 1.43 1.89
KEMAJUAN PEKERJAAN MINGGUAN ( % ) 0.00 0.00 0.00 0.00 0.35 0.52 0.12
REALISASI
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 0.00 0.00 0.00 0.00 0.35 0.87 1.00
KEMAJUAN PEKERJAAN MINGGUAN ( % )
RENCANA ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )
KEMAJUAN PEKERJAAN MINGGUAN ( % )
REALISASI ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )

DEVIASI 0.00 -0.25 -0.38 -0.51 -0.62 -0.55 -0.89

(PPK-7) NANGA TAYAP - SEI. KELIK - KETAPANG

TITO PURNOMO R, ST, MT


NIP. 1968112 199703 1 003
JADWAL PELAKSANAAN PEKERJAAN
MONITORING ONLY
Add 1

BULAN KE 2 BULAN KE 3 BULAN KE 4


26-Feb-18 5-Mar-18 12-Mar-18 19-Mar-18 26-Mar-18 2-Apr-18 9-Apr-18
4-Mar-18 11-Mar-18 18-Mar-18 25-Mar-18 1-Apr-18 8-Apr-18 15-Apr-18
MINGGU KE MINGGU KE MINGGU KE
8 9 10 11 12 13 14

0.11 0.26
0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01

0.11 0.11 0.11 0.11 0.11 0.09


0.48 0.48 0.48 0.48 0.48 0.21

0.26 0.26 0.26 0.34


0.07 0.07 0.07 0.71
0.09 0.09 0.09 0.09 0.91
0.60 0.60 0.53
0.01

2.52
REALISASI

0.46 1.02 1.02 0.69 1.29 1.20


2.35 3.37 4.39 5.08 6.37 7.58
0.22 0.00 0.06 0.00 0.49 0.40
1.22 1.22 1.28 1.28 1.76 2.16
5.60
8.78
0.43
2.59

-1.13 -2.15 -3.12 -3.81 -4.61 -5.42 -6.20

PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN PT.


WIRAWIDYATAMA
NAAN PEKERJAAN
NG ONLY

AN KE 4 BULAN KE 5 BULAN KE 6 BULAN KE 7 BULAN KE 8


16-Apr-18 23-Apr-18 30-Apr-18 7-May-18 14-May-18 21-May-18 28-May-18 4-Jun-18 11-Jun-18 18-Jun-18 25-Jun-18 2-Jul-18 9-Jul-18 16-Jul-18 23-Jul-18 30-Jul-18 6-Aug-18 13-Aug-18 20-Aug-18
22-Apr-18 29-Apr-18 6-May-18 13-May-18 20-May-18 27-May-18 3-Jun-18 10-Jun-18 17-Jun-18 24-Jun-18 1-Jul-18 8-Jul-18 15-Jul-18 22-Jul-18 29-Jul-18 5-Aug-18 12-Aug-18 19-Aug-18 26-Aug-18
GGU KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

I
0.32

B SCHEDULE ADD 1
0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34
U

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 R 0.53


0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

I
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
D
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
1.70 1.70 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51 0.51
0.34 0.02 1.70 1.70 1.24 1.24 1.24 1.24 U 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24

0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21


1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25
1.64 1.64 1.64 1.64 1.64 1.64 1.64 1.64 1.64

SCHEDULE AWAL F

I
L

SCHEDULE AWAL F

I
SI

1.24 1.24 4.29 4.29 2.77 2.77 2.77 2.77 0.00 0.00 5.86 4.98 4.98 4.98 4.98 4.98 4.98 4.98 4.98
10.03 11.27 15.57 19.86 22.63 25.39 28.16 30.93 30.93 30.93 36.79 41.77 46.75 51.74 56.72 61.70 66.68 71.66 76.64
0.14 0.09 0.08 1.21 1.02 0.28 0.52 0.00 0.00 0.00 0.00 3.83 0.00 0.00 0.00 0.00
2.73 2.82 2.90 4.11 5.12 5.40 5.92 5.92 5.92 5.92 5.92 9.75 9.75 9.75 9.75 9.75

-7.30 -8.45 -12.67 -15.75 -17.50 -19.99 -22.24 -25.01 -25.01 -25.01 -30.87 -32.02 -37.00 -41.99 -46.97 -51.95

YA WIDYAJASA JO PT. SAICLE JASA DAN PT.


WIRAWIDYATAMA

Ir. TOTOK KUSMANTO


Site Engineer
BULAN KE 9 BULAN KE 10
27-Aug-18 3-Sep-18 10-Sep-18 17-Sep-18 24-Sep-18 1-Oct-18
2-Sep-18 9-Sep-18 16-Sep-18 23-Sep-18 30-Sep-18 5-Oct-18
MINGGU KE MINGGU KE
34 35 36 37 38 39

0.01 0.01 0.01 0.01 0.01 0.01


0.01 0.01 0.01 0.01 0.01 0.01
0.01 0.01 0.01 0.01 0.01 0.01

0.94 0.94 0.94 0.94


0.18 0.18 0.18 0.18 0.18

0.09
0.02
0.51
1.24

0.21 0.21 0.21 0.21 0.21


1.25 1.25 1.25 1.25 1.25
1.64 1.64 1.64 1.64 1.64
0.02

0.06
0.02 0.02 0.02 0.02

0.00

0.18 0.18 0.18 0.18 0.18


0.09
0.01 0.01
0.04 0.04

6.10 4.44 4.44 4.49 3.57 0.33


82.74 87.17 91.61 96.10 99.67 100.00

PT. DAMAI CITRA MANDIRI

KOES WIDARYANTO
General Superintendent
Nama Pekerjaan : PRESERVASI REKONTRUKSI JALAN DAN RUTIN JEMBATAN RUAS SEI.KELIK - SIDUK
Paket Kontrak/No : IK.02.04/PJN.WIL.I-KB/2018/03
Penyedia Jasa : PT. DAMAI CITRA MANDIRI
Konsultan Supervisi : PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN PT. WIRAWIDYATAMA

BULAN KE 1 BULAN KE 2
NILAI 8-Jan-18 15-Jan-18 22-Jan-18 29-Jan-18 5-Feb-18 12-Feb-18 19-Feb-18
NOMOR MATA NILAI
U R A I A N PEKERJAAN 14-Jan-18 21-Jan-18 28-Jan-18 4-Feb-18 11-Feb-18 18-Feb-18 25-Feb-18
PEMBAYARAN PEKERJAAN (%)
ADD 1 (%) MINGGU KE MINGGU KE
1 2 3 4 5 6 7

DIVISI 1 UMUM
1.2 Mobilisasi - -
1.8(1) Manajemen dan Keselamatan Lalu Lintas - -
1.17 Pengamanan Lingkungan Hidup - -
1.21 Manajemen Mutu - -

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air - -
2.2.(1) Pasangan Batu dengan Mortar - -

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa - -
3.1.(1b) Galian Batu Lunak - -
3.2.(1a) Timbunan Biasa dari Sumber Galian - -
3.2.(2a) Timbunan Pilihan dari Sumber Galian - -
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) - -

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S - -
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan - -

DIVISI 5 PERKERASAN BERBUTIR


SKH 5.6.(1a) Semen Untuk CTRB - -
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) - -

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi - -
6.1 (2)(b) Lapis Perekat - Aspal Emulsi - -
6.3 (3a) Lataston Lapis Aus ( HRS - WC ) ( gradasi senjang / semi senjang ) - -
6.3 (4a) Lataston Lapis Pondasi ( HRS - Base ) ( gradasi senjang / semi senjang ) - -
6.3 (8) Bahan Anti Pengelupasan - -

DIVISI 7 STRUKTUR - -
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa - -
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa - -
7.3 (1) Baja Tulangan U24 polos - -
7.3 (3) Baja Tulangan U32 Ulir - -
7.9 Pasangan Batu - -
7.10 (2) Pasangan Batu Kosong - -
7.13.(1) Sandaran (Railing) - -

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR - -


8.4 (1) Marka Jalan Termoplastik - -
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade - - SCHEDULE AWA
8.4.(6a) Patok Kilometer - -
8.4.(6b) Patok Hektometer / ROW - -

SKh-1.10a PEMELIHARAAN KINERJA JALAN


SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B - -
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S - -
SKh.1.10.a ( 10 ) Campuran Aspal Panas - -
SKh.1.10.a ( 11 )
SKh.1.10.a ( 12 )
Campuran Aspal Dingin
Penetrasi Macadam
-
-
-
-
REALISASI
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) - -
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija - -

SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN


SKh.1.10.b ( 1 ) Pembersihan Jembatan 48.42 48.42 1.03 1.03 1.03 1.03 1.03 1.03 1.03
SKh.1.10.a ( 3 ) Pengecatan Sederhana 48.35 48.35 1.03 1.03 1.03 1.03 1.03 1.03 1.03
SKh.1.10.b ( 10 ) Perbaikan sandaran 3.22 3.22 0.07 0.07 0.07 0.07 0.07 0.07 0.07

JUMLAH NILAI PEKERJAAN 100.00 100.00


KEMAJUAN PEKERJAAN MINGGUAN ( % ) 2.13 2.13 2.13 2.13 2.13 2.13 2.13
RENCANA
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 2.13 4.26 6.38 8.51 10.64 12.77 14.89
KEMAJUAN PEKERJAAN MINGGUAN ( % ) 0.00 0.00 0.00 0.00 0.00 0.00 11.61
REALISASI
KEMAJUAN PEKERJAAN KUMULATIF ( % ) 0.00 0.00 0.00 0.00 0.00 0.00 11.61
KEMAJUAN PEKERJAAN MINGGUAN ( % )
RENCANA ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )
KEMAJUAN PEKERJAAN MINGGUAN ( % )
REALISASI ADD 1
KEMAJUAN PEKERJAAN KUMULATIF ( % )

DEVIASI 0.00 -4.26 -6.38 -8.51 -10.64 -12.77 -3.28

(PPK-7) NANGA TAYAP - SEI. KELIK - KETAPANG

TITO PURNOMO R, ST, MT


NIP. 1968112 199703 1 003
JADWAL PELAKSANAAN PEKERJAAN RUTIN JE
MONITORING ONLY
Add 1

BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5 BULAN KE 6


26-Feb-18 5-Mar-18 12-Mar-18 19-Mar-18 26-Mar-18 2-Apr-18 9-Apr-18 16-Apr-18 23-Apr-18 30-Apr-18 7-May-18 14-May-18 21-May-18 28-May-18 4-Jun-18 11-Jun-18
4-Mar-18 11-Mar-18 18-Mar-18 25-Mar-18 1-Apr-18 8-Apr-18 15-Apr-18 22-Apr-18 29-Apr-18 6-May-18 13-May-18 20-May-18 27-May-18 3-Jun-18 10-Jun-18 17-Jun-18
MINGGU KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

SCHEDULE ADD 1 D

L
L

SCHEDULE AWAL F

1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03
1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07

2.13 2.13 2.13 2.13 2.13 2.13


17.02 19.15 21.28 23.40 25.53 27.66
2.79 0.00 0.00 9.06 0.61 1.57
14.40 14.40 14.40 23.47 24.07 25.64
2.13 2.13 2.13 2.13 2.13 2.13 2.13 2.13 2.13 0.00
29.79 31.91 34.04 36.17 38.30 40.43 42.55 44.68 46.81 46.81
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
25.64 25.64 25.64 25.64 25.64 25.64 25.64 25.64 25.64 25.64

-2.62 -4.75 -6.87 0.06 -1.46 -2.02 -4.15 -6.27 -8.40 -10.53 -12.66 -14.78 -16.91 -19.04 -21.17 -21.17

PT. ADIYA WIDYAJASA JO PT. SAICLE JASA DAN


WIRAWIDYATAMA

Ir. TOTOK KUSMANTO


Site Engineer
RUTIN JEMBATAN

6 BULAN KE 7 BULAN KE 8 BULAN KE 9 BULAN KE 10 B


18-Jun-18 25-Jun-18 2-Jul-18 9-Jul-18 16-Jul-18 23-Jul-18 30-Jul-18 6-Aug-18 13-Aug-18 20-Aug-18 27-Aug-18 3-Sep-18 10-Sep-18 17-Sep-18 24-Sep-18 1-Oct-18 8-Oct-18 15-Oct-18
24-Jun-18 1-Jul-18 8-Jul-18 15-Jul-18 22-Jul-18 29-Jul-18 5-Aug-18 12-Aug-18 19-Aug-18 26-Aug-18 2-Sep-18 9-Sep-18 16-Sep-18 23-Sep-18 30-Sep-18 7-Oct-18 14-Oct-18 21-Oct-18
KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE M
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

L
L

0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

0.00 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97
46.81 48.78 50.75 52.72 54.69 56.66 58.63 60.60 62.57 64.54 66.51 68.48 70.45 72.42 74.39 76.36 78.33 80.30
0.00 0.00 0.00 0.00 0.00 0.00 0.00
25.64 25.64 25.64 25.64 25.64 25.64 25.64

-21.17 -23.14 -25.11 -27.08 -29.05 -31.02 -32.99

O PT. SAICLE JASA DAN PT.


IDYATAMA

KUSMANTO
ngineer
BULAN KE 11 BULAN KE 12 BULAN KE 13
22-Oct-18 29-Oct-18 5-Nov-18 12-Nov-18 19-Nov-18 26-Nov-18 3-Dec-18 10-Dec-18 17-Dec-18 24-Dec-18
28-Oct-18 4-Nov-18 11-Nov-18 18-Nov-18 25-Nov-18 2-Dec-18 9-Dec-18 16-Dec-18 23-Dec-18 31-Dec-18
MINGGU KE MINGGU KE MINGGU KE
42 43 44 45 46 47 48 49 50 51
0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97
82.27 84.24 86.21 88.18 90.15 92.12 94.09 96.06 98.03 100.00

PT. DAMAI CITRA MANDIRI

KOES WIDARYANTO
General Superintendent
LAPORAN MINGGUAN ( UMUM / GABUNGAN
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)

DIVISI 1 UMUM
1.2 Mobilisasi Ls 1.00 0.815 0.58 0.476
1.8(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.221 0.31 0.070
1.17 Pengamanan Lingkungan Hidup LS 1.00 0.199 0.32 0.063
1.21 Manajemen Mutu LS 1.00 0.188 0.31 0.059

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air M3 6,384.37 0.408 2,141.86 0.137
2.2.(1) Pasangan Batu dengan Mortar M3 287.80 0.512 - -
2.3.4 Gorong-gorong Pipa Beton Bertulang, diameter dalam 95 - 105 c M1 44.00 0.303 - -

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa M3 22,275.00 1.630 22,275.00 1.630
3.1.(1a)a Galian Biasa M3 37,688.66 2.687 7,210.20 0.514
3.1.(1b) Galian Batu Lunak M3 1,567.50 0.424 603.40 0.163
3.1.(1b)a Galian Batu Lunak M3 2,041.84 0.552 - -
3.2.(1a) Timbunan Biasa dari Sumber Galian M3 1,393.70 0.301 480.00 0.104
3.2.(1a)a Timbunan Biasa dari Sumber Galian M3 3,192.52 0.690 - -
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 10,307.55 3.679 3,883.73 1.386
3.2.(2a)a Timbunan Pilihan dari Sumber Galian M3 17,135.03 6.108 - -
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) M2 26,100.00 0.094 26,100.00 0.094

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S M3 2,079.00 2.692 - -
4.2.2ba Lapis Pondasi Agregat Kelas S M3 621.00 0.789 - -
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan Liter 21,600.00 0.860 - -

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB M3 602.25 1.127 - -
5.5.(1b) Semen Untuk CTB Ton 81.62 0.299 - -
SKH 5.6.(1a) Semen Untuk CTRB Ton 2,700.49 9.892 567.00 2.077
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) M3 19,053.02 22.130 2,372.27 2.755

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi Liter - - - -
6.1 (2)(b) Lapis Perekat - Aspal Emulsi Liter 8,910.00 0.377 - -
6.1 (2)(b)a Lapis Perekat - Aspal Emulsi Liter 54,810.00 2.291 - -
6.2 (1) Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 4,098.60 15.620 - -
6.2 (1)a Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 203.41 0.770 - -
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
6.3(5a) Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton 5,464.80 20.040 - -
6.3(5a)a Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton 367.18 1.339 - -

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa M3 4.32 0.019 - -
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa M3 - - - -
7.3 (1) Baja Tulangan U24 polos Kg - - - -
7.3 (3) Baja Tulangan U32 Ulir Kg 1,131.30 0.053 - -
7.9 Pasangan Batu M3 46.35 0.082 - -
7.10 (2) Pasangan Batu Kosong M3 - - - -
7.13.(1) Sandaran (Railing) M1 4.00 0.003 - -

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR


8.4 (1) Marka Jalan Termoplastik M2 4,950.00 1.339 1,970.62 0.533
8.4.(1) a Marka Jalan Termoplastik M2 132.57 0.036 - -
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade Buah 48.00 0.083 - -
8.4.(6a) Patok Kilometer Buah 9.00 0.011 - -
8.4.(6b) Patok Hektometer / ROW Buah 81.00 0.070 - -

SKh-1.10a PEMELIHARAAN KINERJA JALAN


SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B M3 378.11 0.615 - -
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S M3 - - - -
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
SKh.1.10.a ( 10 ) Campuran Aspal Panas M3 8.45 0.074 - -
SKh.1.10.a ( 11 ) Campuran Aspal Dingin M3 - - - -
SKh.1.10.a ( 12 ) Penetrasi Macadam M3 - - - -
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) Kg - - - -
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija Ls 1.00 0.270 0.67 0.180

SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN


SKh.1.10.b ( 1 ) Pembersihan Jembatan M2 24,034.62 0.148 11,647.35 0.072
SKh.1.10.a ( 3 ) Pengecatan Sederhana M2 400.00 0.148 18.00 0.007
SKh.1.10.b ( 10 ) Perbaikan sandaran M' 20.00 0.010 - -

JUMLAH 100.00 10.320

Disetujui Oleh Diperiksa Oleh


KOORDINATOR LAPANGAN Konsultan Supervisi
PT. ADIYA WIDYAJASA

( …………………………………………………… ) Ir. TOTOK KUSMANTO


Site Engineer
N ( UMUM / GABUNGAN )
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- - 0.58 0.476
- - 0.31 0.070
- - 0.32 0.063
- - 0.31 0.059
-
-
- - 2,141.86 0.137
- - - -
- - - -

- - 22,275.00 1.630
- - 7,210.20 0.514
- - 603.40 0.163
- - -
- - 480.00 0.104
- - - -
- - 3,883.73 1.386
- - - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
- - 26,100.00 0.094

- - - -
- - - -
- - - -

- - - -
- - - -
- - 567.00 2.077
- - 2,372.27 2.755

- - - -
- - - -
- - - -
- - - -
- - - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -

- - 1,970.62 0.533
- - - -
- - - -
- - - -
- - - -

- - - -
- - - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
- - - -
- - - -
- - - -
- - - -
- - 0.67 0.180

- - 11,647.35 0.072
- - 18.00 0.007
- - - -

- 10.320

RENCANA PROGRESS : 59.921 ( % )


REALISASI PROGRESS : 10.320 ( % )
DEVIASI : (49.601) ( % )

DIBUAT OLEH
KONTRAKTOR
PT. DAMAI CITRA MANDIRI

KOES WIDARYANTO, ST
General Superintendent
LAPORAN MINGGUAN ( REKONSTRUKSI JALA
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)

DIVISI 1 UMUM
1.2 Mobilisasi Ls 1.00 0.87 0.70 0.61
1.8(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.24 0.31 0.07
1.17 Pengamanan Lingkungan Hidup LS 1.00 0.21 0.32 0.07
1.21 Manajemen Mutu LS 1.00 0.20 0.31 0.06

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air M3 6,384.37 0.44 2,141.86 0.15
2.2.(1) Pasangan Batu dengan Mortar M3 287.80 0.55 - -
2.3.4 Gorong-gorong Pipa Beton Bertulang, diameter dalam 95 - 105 c M1 44.00 0.32 - -

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa M3 22,275.00 1.74 22,275.00 1.74
3.1.(1a)a Galian Biasa M3 37,688.66 2.94 7,210.20 0.56
3.1.(1b) Galian Batu Lunak M3 1,567.50 0.45 603.40 0.17
3.1.(1b)a Galian Batu Lunak M3 2,041.84 0.59 - -
3.2.(1a) Timbunan Biasa dari Sumber Galian M3 1,393.70 0.38 727.52 0.20
3.2.(1a)a Timbunan Biasa dari Sumber Galian M3 3,192.52 0.87 - -
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 8,662.50 3.30 2,238.68 0.85
3.2.(2a)a Timbunan Pilihan dari Sumber Galian M3 5,265.00 2.01 - -
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) M2 26,100.00 0.10 26,100.00 0.10

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S M3 2,079.00 2.87 - -
4.2.2ba Lapis Pondasi Agregat Kelas S M3 621.00 0.86 - -
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan Liter 21,600.00 0.92 - -

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB M3 602.25 1.20 - -
5.5.(1b) Semen Untuk CTB Ton 81.62 0.32 - -
SKH 5.6.(1a) Semen Untuk CTRB Ton 2,700.49 10.56 567.00 2.22
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) M3 19,053.02 23.62 2,372.27 2.94

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi Liter - - - -
6.1 (2)(b) Lapis Perekat - Aspal Emulsi Liter 8,910.00 0.40 - -
6.1 (2)(b)a Lapis Perekat - Aspal Emulsi Liter 54,810.00 2.47 - -
6.2 (1) Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 4,098.60 16.67 - -
6.2 (1)a Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 203.41 0.83
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
6.3(5a) Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton 5,464.80 21.39
6.3(5a)a Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton 367.18 1.44

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa M3 4.32 0.02 - -
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa M3 - - - -
7.3 (1) Baja Tulangan U24 polos Kg - - - -
7.3 (3) Baja Tulangan U32 Ulir Kg 1,131.30 0.06 - -
7.9 Pasangan Batu M3 46.35 0.09 - -
7.10 (2) Pasangan Batu Kosong M3 - - - -
7.13.(1) Sandaran (Railing) M1 4.00 0.00 - -

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR -


8.4 (1) Marka Jalan Termoplastik M2 2,970.00 0.86 - -
8.4.(1) a Marka Jalan Termoplastik M2 141.96 0.04 - -
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade Buah 48.00 0.09 - -
8.4.(6a) Patok Kilometer Buah 9.00 0.01 - -
8.4.(6b) Patok Hektometer / ROW Buah 81.00 0.07 - -

SKh-1.10a PEMELIHARAAN KINERJA JALAN


SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B M3
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S M3
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
SKh.1.10.a ( 10 ) Campuran Aspal Panas M3
SKh.1.10.a ( 11 ) Campuran Aspal Dingin M3
SKh.1.10.a ( 12 ) Penetrasi Macadam M3
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) Kg
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija Ls

SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN


SKh.1.10.b ( 1 ) Pembersihan Jembatan M2
SKh.1.10.a ( 3 ) Pengecatan Sederhana M2
SKh.1.10.b ( 10 ) Perbaikan sandaran M'

JUMLAH 100.00 9.746

Disetujui Oleh Diperiksa Oleh


KOORDINATOR LAPANGAN Konsultan Supervisi
PT. ADIYA WIDYAJASA

( …………………………………………………… ) Ir. TOTOK KUSMANTO


Site Engineer
( REKONSTRUKSI JALAN )
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- 0.70 0.61
- 0.31 0.07
- 0.32 0.07
- 0.31 0.06

- 2,141.86 0.15
- - -
- - -

- 22,275.00 1.74
- 7,210.20 0.56
- 603.40 0.17
- - - -
- 727.52 0.20
- - - -
- 2,238.68 0.85
- - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
- 26,100.00 0.10

- - -
- - -
- - -

- - -
- - -
- 567.00 2.22
- 2,372.27 2.94

- - -
- - -
- - -
- - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- - -
- - -
- - -
- - -
- - -
- - -
- - -

- - -
- - -
- - -
- - -
- - -
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- 9.746

RENCANA PROGRESS : 61.697 ( % )


REALISASI PROGRESS : 9.746 ( % )
DEVIASI : (51.951) ( % )

DIBUAT OLEH
KONTRAKTOR
PT. DAMAI CITRA MANDIRI

KOES WIDARYANTO, ST
General Superintendent
LAPORAN MINGGUAN ( RUTIN JALAN )
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)

DIVISI 1 UMUM
1.2 Mobilisasi LS
1.8(1) Manajemen dan Keselamatan Lalu Lintas LS
1.17 Pengamanan Lingkungan Hidup LS
1.21 Manajemen Mutu LS

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air M3
2.2.(1) Pasangan Batu dengan Mortar M3

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa M3
3.1.(1a)a Galian Biasa M3
3.1.(1b) Galian Batu Lunak M3
3.1.(1b)a Galian Batu Lunak M3
3.2.(1a) Timbunan Biasa dari Sumber Galian M3
3.2.(1a)a Timbunan Biasa dari Sumber Galian M3
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 1,645.05 9.30 1,645.05 9.30
3.2.(2a)a Timbunan Pilihan dari Sumber Galian M3 11,870.03 67.08 2,672.95 15.10
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) M2

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S M3
4.2.2ba Lapis Pondasi Agregat Kelas S M3
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan Liter

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB M3
5.5.(1b) Semen Untuk CTB Ton
SKH 5.6.(1a) Semen Untuk CTRB Ton
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) M3

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi Liter
6.1 (2)(b) Lapis Perekat - Aspal Emulsi Liter
6.1 (2)(b)a Lapis Perekat - Aspal Emulsi Liter
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
6.2 (1) Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton
6.2 (1)a Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton
6.3(5a) Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton
6.3(5a)a Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa M3
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa M3
7.3 (1) Baja Tulangan U24 polos Kg
7.3 (3) Baja Tulangan U32 Ulir Kg
7.9 Pasangan Batu M3
7.10 (2) Pasangan Batu Kosong M3
7.13.(1) Sandaran (Railing) M1

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR


8.4 (1) Marka Jalan Termoplastik M2 1,970.62 8.44 1,970.62 8.44
8.4.(1) a Marka Jalan Termoplastik M2
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade Buah
8.4.(6a) Patok Kilometer Buah
8.4.(6b) Patok Hektometer / ROW Buah

SKh-1.10a PEMELIHARAAN KINERJA JALAN


PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B M3 378.11 9.74 - -
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S M3 - - - -
SKh.1.10.a ( 10 ) Campuran Aspal Panas M3 8.45 1.17 - -
SKh.1.10.a ( 11 ) Campuran Aspal Dingin M3 - - - -
SKh.1.10.a ( 12 ) Penetrasi Macadam M3 - - - -
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) Kg - - - -
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija Ls 1.00 4.28 0.67 2.85

SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN


SKh.1.10.b ( 1 ) Pembersihan Jembatan M2
SKh.1.10.a ( 3 ) Pengecatan Sederhana M2
SKh.1.10.b ( 10 ) Perbaikan sandaran M'

JUMLAH 100.00 35.693

Disetujui Oleh Diperiksa Oleh


KOORDINATOR LAPANGAN Konsultan Supervisi
PT. ADIYA WIDYAJASA
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
( …………………………………………………… ) Ir. TOTOK KUSMANTO
Site Engineer
UAN ( RUTIN JALAN )
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- 1,645.05 9.30
- 2,672.95 15.10
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- 1,970.62 8.44
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
- - -
- - -
- - -
- - -
- - -
- - -
- 0.67 2.85

- 35.693

RENCANA PROGRESS : 59.952 ( % )


REALISASI PROGRESS : 35.693 ( % )
DEVIASI : (24.259) ( % )

DIBUAT OLEH
KONTRAKTOR
PT. DAMAI CITRA MANDIRI
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KOES WIDARYANTO, ST
General Superintendent
LAPORAN MINGGUAN ( RUTIN JEMBATAN
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)

DIVISI 1 UMUM
1.2 Mobilisasi Ls
1.8(1) Manajemen dan Keselamatan Lalu Lintas LS
1.17 Pengamanan Lingkungan Hidup LS
1.21 Manajemen Mutu LS

DIVISI 2 DRAINASE
2.1 (1) Galian untuk Selokan Drainase dan Saluran Air M3
2.2.(1) Pasangan Batu dengan Mortar M3

DIVISI 3 PEKERJAAN TANAH


3.1.(1a) Galian Biasa M3
3.1.(1a)a Galian Biasa M3
3.1.(1b) Galian Batu Lunak M3
3.1.(1b)a Galian Batu Lunak M3
3.2.(1a) Timbunan Biasa dari Sumber Galian M3
3.2.(1a)a Timbunan Biasa dari Sumber Galian M3
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3
3.2.(2a)a Timbunan Pilihan dari Sumber Galian M3
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
3,3.(1) Penyiapan Badan Jalan ( L = 7 m ) M2

DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2b Lapis Pondasi Agregat Kelas S M3
4.2.2ba Lapis Pondasi Agregat Kelas S M3
4.2.6 Bahan Aspal untuk Pekerjaan Pelaburan Liter

DIVISI 5 PERKERASAN BERBUTIR


5.5.(1a) Lapis CTB M3
5.5.(1b) Semen Untuk CTB Ton
SKH 5.6.(1a) Semen Untuk CTRB Ton
SKH 5.6.(1b) Lapis Cement Treated Base Recycler Base ( CTRB ) M3

DIVISI 6 PERKERASAN ASPAL


6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi Liter
6.1 (2)(b) Lapis Perekat - Aspal Emulsi Liter
6.1 (2)(b)a Lapis Perekat - Aspal Emulsi Liter
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
6.2 (1) Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton
6.2 (1)a Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton
6.3(5a) Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton
6.3(5a)a Lataston Lapis Antara (HRS-Base) (gradasi senjang/semi senjang) Ton

DIVISI 7 STRUKTUR
7.1 (7).a Beton mutu sedang dengan fc’= 20 MPa M3
7.1 (10) Beton mutu rendah dengan fc’= 10 Mpa M3
7.3 (1) Baja Tulangan U24 polos Kg
7.3 (3) Baja Tulangan U32 Ulir Kg
7.9 Pasangan Batu M3
7.10 (2) Pasangan Batu Kosong M3
7.13.(1) Sandaran (Railing) M1

DIVISI 8 PENGEMBALIAN KONDISI DAN PEK. MINOR


8.4 (1) Marka Jalan Termoplastik M2
8.4.(1) a Marka Jalan Termoplastik M2
8.4.(3a) Rambu Jalan Tunggal dng Permukaan Pemantul Engineer Grade Buah
8.4.(6a) Patok Kilometer Buah
8.4.(6b) Patok Hektometer / ROW Buah

SKh-1.10a PEMELIHARAAN KINERJA JALAN


PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
SKh.1.10.a ( 5 ) Lapis Pondasi Agregat Kelas B M3
SKh.1.10.a ( 6 ) Lapis Pondasi Agregat Kelas S M3
SKh.1.10.a ( 10 ) Campuran Aspal Panas M3
SKh.1.10.a ( 11 ) Campuran Aspal Dingin M3
SKh.1.10.a ( 12 ) Penetrasi Macadam M3
SKh.1.10.a ( 17 ) Bahan Penutup ( sealent ) Kg
SKh.1.10.a ( 18 ) Pengendalian tanaman pada Rumija Ls

SKh-1.10b PEMELIHARAAN KINERJA JEMBATAN


SKh.1.10.b ( 1 ) Pembersihan Jembatan M2 24,034.62 48.42 11,647.35 23.47
SKh.1.10.a ( 3 ) Pengecatan Sederhana M2 400.00 48.35 18.00 2.18
SKh.1.10.b ( 10 ) Perbaikan sandaran M' 20.00 3.22 - -

JUMLAH 100.00 25.642

Disetujui Oleh Diperiksa Oleh


KOORDINATOR LAPANGAN Konsultan Supervisi
PT. ADIYA WIDYAJASA
PPK : NANGA TAYAP - SEI. KELIK - KETAPANG
NAMA PAKET : PRESERVASI REKONSTRUKSI JALAN DAN RUTIN JEMBATAN SEI. KELIK - SIDUK
NO. & TGL. KONTR: IK.02.04/PJN.WIL.I-KB/2018/03 - 12 JANUARI 2018
NO. & TGL. SPMK :
SUMBER DANA : APBN 2018

NOMOR KONTRAK AWAL


MATA VOL. BOBOT MINGGU LALU
U R A I A N
PEMBAYARAN Sat. PEKERJAAN PEKERJAAN VOLUME BOBOT
(%) (%)
( …………………………………………………… ) Ir. TOTOK KUSMANTO
Site Engineer
AN ( RUTIN JEMBATAN )
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)

- 11,647.35 23.47
- 18.00 2.18
- - -

- 25.642

RENCANA PROGRESS : 58.629 ( % )


REALISASI PROGRESS : 25.642 ( % )
DEVIASI : (32.987) ( % )

DIBUAT OLEH
KONTRAKTOR
PT. DAMAI CITRA MANDIRI
KONTRAKTOR : PT. DAMAI CITRA MANDIRI
KONSULTAN SUPERVISI : PT. ADIYA WIDYAJASA
MINGGU KE- : 30
TANGGAL AWAL MGG INI : 30 Juli 2018
TANGGAL AKHIR MGG INI : 05 Agustus 2018

PRESTASI
MINGGU INI S/D MINGGU INI KETERANGAN
VOLUME BOBOT VOLUME BOBOT
(%) (%)
KOES WIDARYANTO, ST
General Superintendent