HARGA DASAR SATUAN UPAH

PEKERJAAN PENINGKATAN JALAN DAN JEMBATAN

WILAYAH 3&4

HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1. Pekerja L01 Jam 16,428.57


2. Tukang L02 Jam 18,571.43
3. Mandor L03 Jam 21,428.57
4. Operator L04 Jam 21,428.57
5. Pembantu Operator L05 Jam 18,571.43
6. Sopir / Driver L06 Jam 21,428.57
7. Pembantu Sopir / Driver L07 Jam 18,571.43
8. Mekanik L08 Jam 21,428.57
9. Pembantu Mekanik L09 Jam 18,571.43
10. Kepala Tukang L10 Jam 21,428.57
DAFTAR HARGA DASAR SATUAN BAHAN
PEKERJAAN PENINGKATAN JALAN DAN JEMBATAN
WILAYAH 3&4
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Kawat Beton M14 Kg 23,500.00


2 Kawat Bronjong M15 Unit 500,000.00
3 Paku M18 Kg 17,500.00
4 Kayu Perancah M19 M3 2,900,000.00
5 Bensin M20 LITER 12,250.00
6 Solar M21 LITER 15,673.28
7 Minyak Pelumas / Olie M22 LITER 45,000.00
8 Bahan Agr.Base Kelas A M26 M3 254,000.00
9 Bahan Agr.Base Kelas B M27 M3 251,000.00
10 Geotextile M30 M2 11,642.07
11 Cat M42 Kg 55,000.00
12 Baja Tulangan (Polos) U32 M57a Kg 10,883.97
13 Beton K-400 M69 M3 1,144,200.00
14 Joint Sealent M94 Kg 38,380.91
15 Polytene 125 mikron M97 Kg 29,366.67
16 Curing Compound M98 Ltr 42,275.20
17 Kayu Acuan M99 M3 2,750,000.00
18 Beton B0 --- M3 856,000.00
19 Box Culvert 100 x 100 x 100 Bh 3,363,750.00
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
PEKERJAAN PENINGKATAN JALAN DAN JEMBATAN

BIAYA
SEWA
No. URAIAN KODE HP
ALAT/JAM
(di luar PPN)

1 COMPRESSOR 4000-6500 L\M E05 60.0 219,355.48


2 CONCRETE MIXER 0.3-0.6 M3 E06 20.0 214,081.29
3 DUMP TRUCK 3.5 TON E08 100.0 378,845.19
4 EXCAVATOR 80-140 HP E10 133.0 593,520.58
5 FLAT BED TRUCK 3-4 M3 E11 190.0 603,997.19
6 MOTOR GRADER >100 HP E13 135.0 540,373.19
7 WHEEL LOADER 1.0-1.6 M3 E15 96.0 414,640.80
8 TANDEM ROLLER 6-8 T. E17 82.0 573,393.57
9 CONCRETE VIBRATOR E20 5.5 59,418.69
10 WATER TANKER 3000-4500 L. E23 100.0 321,225.68
11 JACK HAMMER E26 0.0 52,699.42
12 TRUK MIXER (AGITATOR) E49 220.0 775,969.15
WILAYAH 3&4

KET.
DAFTAR HARGA SATUAN
PEKERJAAN PENINGKATAN JALAN DAN JEMBATAN

WILAYAH 3&4

Harga
No. Mata Uraian Satuan Satuan
Pembayaran
(Rupiah)

DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 70,444.73
2.2.(1) Pasangan Batu dengan Mortar M3 938,344.66
2.2.(2) Plesteran untuk Selokan Drainase dan Saluran Air M2 109,188.59
2.3.(12) Beton K250 (fc’ 20) untuk struktur drainase beton minor M 3 1,261,425.83
2.3.(13) Baja Tulangan untuk struktur drainase beton minor Kg 17,851.64
2.3.(15) Acuan untuk struktur drainase beton minor M2 184,862.50
2.3 (3) Gorong2 Box Culvert, Diameter dalam 100 cm Bh 4,849,760.22

DIVISI 3. PEKERJAAN TANAH


3.1.(1c) Galian Biasa (alat) M3 149,221.53
3.3.(1) Penyiapan Badan Jalan M2 1,827.84
3.4.(1) Pembersihan dan Pengupasan Lahan M2 4,833.82

DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.(1) Lapis Pondasi Agregat Kelas A (untuk pelebaran) M3 389,551.05
4.2.(2a) Lapis Pondasi Agregat Kelas B (untuk pelebaran) M3 384,455.59
4.2.(2c) Timbunan Bahu Jalan (Agregat Kelas A) M3 376,543.41
4.2.(2d) Timbunan Bahu Jalan (Agregat Kelas B) M3 372,201.21

DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M3 386,341.44
5.1.(2) Lapis Pondasi Agregat Kelas B M3 376,702.83
5.3.(1) Perkerasan Beton Semen M3 1,673,780.96
5.3.(3) Lapis Pondasi bawah Beton Kurus M3 1,154,261.98
5.3.(4) Baja Tulangan Untuk Perkerasan Beton Kg 20,317.47
5.3.(5) Acuan Untuk Perkerasan Beton M2 184,862.50

DIVISI 6. ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair M2 11,868.36
6.1 (2)(a) Lapis Perekat - Aspal Cair M2 5,274.79
6.3(3a) Lataston Lapis Aus (HRS-WC) M2 140,570.13
6.3(3c) Lataston Lapis Aus (HRS-WC) (Menggunakan Buruh) M2 141,187.04
6.3(5a) Laston Lapis Aus (AC-WC) M2 177,511.42
6.3(5e) Laston Lapis Aus (AC-WC) (Menggunakan Buruh) M2 178,150.01
6.6.(1) Lapis Permukaan Penetrasi Macadam M2 149,952.28

DIVISI 7. STRUKTUR
7.15.(2) Pembongkaran Beton M3 859,381.17
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.1.(1)


JENIS PEKERJAAN : Galian untuk Selokan Drainase dan Saluran Air
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.4353 16,428.57


2. Mandor ( L03 ) jam 0.0109 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) jam 0.1343 378,845.19


2. Alat Bantu Ls 1.0000 3,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.2.(1)


JENIS PEKERJAAN : Pasangan Batu dengan Mortar
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 4.0161 16,428.57


2. Tukang ( L02 ) jam 1.2048 18,571.43
3 Mandor ( L03 ) jam 0.4016 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Batu ( M02 ) M3 1.0800 240,000.00


2. Semen (PC) ( M12a) Kg 161.0000 1,400.00
3. Pasir Pasang ( M01b ) M3 0.4829 305,289.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Conc. Mixer ( E06 ) jam 0.4016 214,081.29
2. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.2.(2)


JENIS PEKERJAAN : Plesteran untuk Selokan Drainase dan Saluran Air
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.8000 16,428.57


2. Tukang ( L02 ) jam 1.5400 18,571.43
3 Mandor ( L03 ) jam 0.1400 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
1. Pasir Pasang ( M01b ) M3 0.0194 305,289.00
2. Semen PC (50 Kg) ( M12 ) zak 0.1632 70,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.3.(12)


JENIS PEKERJAAN : Beton K250 (fc’ 20) untuk struktur drainase beton minor
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 2.8112 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3 Mandor ( L03 ) jam 0.1147 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Semen ( M12a) Kg 370.8000 1,400.00


2. Pasir Beton ( M01a ) M3 0.5250 310,000.00
3. Aggregat Kasar ( M03 ) M3 0.7425 309,956.08

JUMLAH HARGA BAHAN

C. PERALATAN

1. Beton Mixer ( E06 ) Jam 0.4016 214,081.29


2. Water Tanker ( E23 ) Jam 0.0558 321,225.68
3. Concrete Vibrator ( E20 ) Jam 0.4016 59,418.69
4. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 2.3.(13)
JENIS PEKERJAAN : Baja Tulangan untuk struktur drainase beton minor
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3 Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Polos) U24 ( M57a ) Kg 1.0500 10,883.97


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.3.(15)


JENIS PEKERJAAN : Acuan untuk struktur drainase beton minor
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.4500 16,428.57


2. Tukang ( L02 ) jam 1.4000 18,571.43
3 Mandor ( L03 ) jam 0.3500 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Acuan ( M99 ) M3 0.0300 2,750,000.00


2. Paku ( M18 ) Kg 0.2000 17,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00


JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

7,151.18
233.19

7,384.38

0.00

50,871.91
3,000.00

53,871.91

61,256.29
9,188.44
70,444.73

AN

JUMLAH
HARGA
(Rp.)

65,978.19
22,375.22
8,605.85

96,959.26

259,200.00
225,400.00
147,416.20

632,016.20
85,976.42
1,000.00

86,976.42

815,951.88
122,392.78
938,344.66

AN

JUMLAH
HARGA
(Rp.)

46,000.00
28,600.00
3,000.00

77,600.00
5,922.61
11,424.00

17,346.61

94,946.60
14,241.99
109,188.59

AN

JUMLAH
HARGA
(Rp.)
46,184.73
7,458.41
2,458.81

56,101.95

519,120.00
162,750.00
230,142.39

912,012.39

85,976.42
17,938.33
23,862.93
1,000.00

128,777.68

1,096,892.02
164,533.80
1,261,425.83

AN
JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,428.17
470.00

11,898.17

500.00

500.00

15,523.16
2,328.47
17,851.64
AN

JUMLAH
HARGA
(Rp.)

40,250.00
26,000.00
7,500.00

73,750.00

82,500.00
3,500.00

86,000.00

1,000.00
1,000.00

160,750.00
24,112.50
184,862.50
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.1.(1a)


JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.4353 16,428.57


2. Mandor ( L03 ) jam 0.0109 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) jam 0.3105 378,845.19


2. Alat Bantu Ls 1.0000 6,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.1.(1c)


JENIS PEKERJAAN : Galian Biasa (alat)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0181 16,428.57


2. Mandor ( L03 ) jam 0.0090 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Excavator ( E10 ) jam 0.0109 593,520.58
2. Dump Truck ( E08 ) jam 0.3083 378,845.19
3 Alat Bantu Ls 1.0000 6,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.1.(10)


JENIS PEKERJAAN : Galian Tanah Untuk Konstruksi
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 5.2500 16,428.57


2. Mandor ( L03 ) jam 0.1750 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.2.(1)


JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 0.5038 16,428.57


2. Mandor ( L03 ) jam 0.0101 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Bahan timbunan ( M08 ) M3 1.1100 210,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Vibro Roller ( E19 ) Jam 0.0042 458,758.18


2. Water tank truck ( E23 ) Jam 0.0070 321,225.68
3. Alat Bantu Ls 1.0000 700.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 3.2.(1a)
JENIS PEKERJAAN : Timbunan Biasa (alat)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.3527 16,428.57


2. Mandor ( L03 ) jam 0.0101 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Bahan timbunan ( M08 ) M3 1.1100 210,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Vibro Roller ( E19 ) Jam 0.0042 458,758.18


2. Water tank truck ( E23 ) Jam 0.0070 321,225.68
3. Motor Grader ( E13 ) Jam 0.0037 540,373.19
4 Alat Bantu Ls 1.0000 450.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.2.(4)


JENIS PEKERJAAN : Timbunan Kembali
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.1310 16,428.57


2. Mandor ( L03 ) jam 0.5328 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1 Alat Bantu ### Ls 1.0000 700.00


JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.3.(1)


JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0024 16,428.57


2. Mandor ( L03 ) jam 0.0006 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
JUMLAH HARGA BAHAN

C. PERALATAN

1. Motor Grader ( E13 )### Jam 0.0006 540,373.19


2. Vibro Roller ( E19 ) Jam 0.0005 458,758.18
3 Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.4.(1)


JENIS PEKERJAAN : Pembersihan dan Pengupasan Lahan
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0700 16,428.57


2. Mandor ( L03 ) jam 0.0140 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E09 )### Jam 0.0020 624,152.72


2. Alat Bantu Ls 1.0000 1,500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.4.(2)


JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter 15 -30 cm
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 16,428.57


2. Mandor ( L03 ) jam 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. ( )### #N/A
2. ( )
3. Alat Bantu Ls 0.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.4.(6)


JENIS PEKERJAAN : Pembersihan Semak-Semak Pada Bahu
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.2333 16,428.57


2. Mandor ( L03 ) jam 0.0093 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

7,151.18
233.19

7,384.38

0.00

117,642.56
6,000.00

123,642.56

131,026.94
19,654.04
150,680.98

AN

JUMLAH
HARGA
(Rp.)

296.77
193.55

490.32

0.00
6,469.37
116,798.16
6,000.00

129,267.53

129,757.85
19,463.68
149,221.53

AN

JUMLAH
HARGA
(Rp.)

86,249.99
3,750.00

89,999.99
0.00

1,000.00

1,000.00

90,999.99
13,650.00
104,649.99

AN

JUMLAH
HARGA
(Rp.)
8,276.83
215.92

8,492.75

233,100.00

233,100.00

1,919.17
2,257.61
700.00

4,876.78

246,469.53
36,970.43
283,439.96

AN
JUMLAH
HARGA
(Rp.)

5,793.78
215.92

6,009.70

233,100.00

233,100.00

1,919.17
2,257.61
2,020.63
450.00

6,647.41

245,757.11
36,863.57
282,620.67
AN

JUMLAH
HARGA
(Rp.)

35,010.06
11,416.32

46,426.38

700.00
700.00

47,126.38
7,068.96
54,195.34

AN

JUMLAH
HARGA
(Rp.)

39.12
12.76

51.87
321.65
215.91
1,000.00

1,537.56

1,589.43
238.41
1,827.84

AN

JUMLAH
HARGA
(Rp.)

1,150.00
300.00

1,450.00

1,253.32
1,500.00

2,753.32

4,203.32
630.50
4,833.82

AN
JUMLAH
HARGA
(Rp.)

0.00
0.00

0.00

#N/A
0.00
0.00

#N/A

#N/A
#N/A
#N/A
AN

JUMLAH
HARGA
(Rp.)

3,833.33
200.00

4,033.33
4,033.33
605.00
4,638.33
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 4.2.(1)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A (untuk pelebaran)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.4248 16,428.57


2. Mandor ( L03 ) jam 0.0170 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat A ( M26 ) M3 1.2586 254,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Tandem Roller ( E17 ) Jam 0.0119 573,393.57


2. Water Tanker ( E23 ) Jam 0.0141 321,225.68
3. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 4.2.(2a)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B (untuk pelebaran)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.4248 16,428.57


2. Mandor ( L03 ) jam 0.0170 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat B ( M27 ) M3 1.2586 251,000.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Tandem Roller ( E17 ) Jam 0.0107 573,393.57
2. Water Tanker ( E23 ) Jam 0.0141 321,225.68
3. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 4.2.(2c)


JENIS PEKERJAAN : Timbunan Bahu Jalan (Agregat Kelas A)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.4248 16,428.57


2. Mandor ( L03 ) jam 0.0170 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
1. Agregat A ( M26 ) M3 1.2586 254,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 4.2.(2d)


JENIS PEKERJAAN : Timbunan Bahu Jalan (Agregat Kelas B)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 0.4248 16,428.57


2. Mandor ( L03 ) jam 0.0170 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat B ( M27 ) M3 1.2586 251,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

6,978.22
364.08

7,342.30

319,686.75

319,686.75

6,795.78
4,515.22
400.00

11,711.00

338,740.05
50,811.01
389,551.05

AN

JUMLAH
HARGA
(Rp.)

6,978.22
364.08

7,342.30

315,910.93

315,910.93
6,140.76
4,515.22
400.00

11,055.98

334,309.21
50,146.38
384,455.59

AN

JUMLAH
HARGA
(Rp.)

6,978.22
364.08

7,342.30
319,686.75

319,686.75

400.00

400.00

327,429.05
49,114.36
376,543.41

AN

JUMLAH
HARGA
(Rp.)
6,978.22
364.08

7,342.30

315,910.93

315,910.93

400.00

400.00

323,653.22
48,547.98
372,201.21
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.1.(1)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.2124 16,428.57


2. Mandor ( L03 ) jam 0.0085 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat A ( M26 ) M3 1.2586 254,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Tandem Roller ( E17 ) Jam 0.0134 573,393.57


2. Water Tanker ( E23 ) Jam 0.0141 321,225.68
3. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.1.(2)


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.2124 16,428.57


2. Mandor ( L03 ) jam 0.0085 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat B ( M27 ) M3 1.2586 251,000.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Tandem Roller ( E17 ) Jam 0.0054 573,393.57
2. Water Tanker ( E23 ) Jam 0.0141 321,225.68
3. Alat Bantu Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.3.(1)


JENIS PEKERJAAN : Perkerasan Beton Semen
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 1.4056 16,428.57


2. Tukang ( L02 ) jam 0.7028 18,571.43
3. Mandor ( L03 ) jam 0.1506 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
1. Beton K-400 --- M3 1.0250 1,144,200.00
2. Joint Sealent ( M94 ) Kg 0.9900 38,380.91
3. Polytene 125 mikron ( M97 ) Kg 0.4375 29,366.67
4. Curing Compound ( M98 ) Ltr 1.0000 42,275.20
5. Geotextile ( M30 ) M2 5.0000 11,642.07

JUMLAH HARGA BAHAN

C. PERALATAN

1. Tandem Roller ( E20 ) jam 0.0502 59,418.69


2. Water Tanker ( E23 ) jam 0.0422 321,225.68
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Conc. Paver ( E42 ) jam 0.0074 629,084.47
5. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.3.(1a)


JENIS PEKERJAAN : Perkerasan Beton Semen (K-250;Site Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 1.3655 16,428.57


2. Tukang ( L02 ) jam 0.6827 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Semen ( M12 ) Kg 422.3000 1,400.00


2. Pasir beton ( M01a ) M3 0.5412 310,000.00
3. Agregat Kasar ( M03 ) M3 0.7440 309,956.08
2. Joint Sealent ( M94 ) Kg 0.9900 38,380.91
3. Polytene 125 mikron ( M97 ) Kg 0.4375 29,366.67
4. Curing Compound ( M98 ) Ltr 1.0000 42,275.20
5. Geotextile ( M30 ) M2 5.0000 11,642.07

JUMLAH HARGA BAHAN

C. PERALATAN

1. Concrete Mixer ( E06 ) Jam 0.4016 214,081.29


2. Water Tanker ( E23 ) Jam 0.0558 321,225.68
3. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 5.3.(3)
JENIS PEKERJAAN : Lapis Pondasi bawah Beton Kurus
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 1.5060 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton B0 --- M3 1.0250 856,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Con. Vibrator ( E20 ) Jam 0.0502 59,418.69


2. Water Tank Truck ( E23 ) Jam 0.0422 321,225.68
3. Truck Mixer ( E49 ) Jam 0.0886 775,969.15
4. Conc. Paver ( E42 ) Jam 0.0074 629,084.47
3. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.3.(4)


JENIS PEKERJAAN : Baja Tulangan Untuk Perkerasan Beton
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Polos) U32 ( M57a ) Kg 1.1000 10,883.97


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00
3. Cat Anti Karat ( M42 ) Kg 0.0200 55,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00


JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.3.(5)


JENIS PEKERJAAN : Acuan Untuk Perkerasan Beton
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.4500 16,428.57


2. Tukang ( L02 ) jam 1.4000 18,571.43
3 Mandor ( L03 ) jam 0.3500 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Acuan ( M99 ) M3 0.0300 2,750,000.00


2. Paku ( M18 ) Kg 0.2000 17,500.00
JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

3,489.11
182.04

3,671.15

319,686.75

319,686.75

7,675.95
4,515.22
400.00

12,591.17

335,949.07
50,392.36
386,341.44

AN

JUMLAH
HARGA
(Rp.)

3,489.11
182.04

3,671.15

315,910.93

315,910.93
3,070.38
4,515.22
400.00

7,985.60

327,567.68
49,135.15
376,702.83

AN

JUMLAH
HARGA
(Rp.)

23,092.37
13,052.21
3,227.19

39,371.77
1,172,805.00
37,997.10
12,847.92
42,275.20
58,210.33

1,324,135.55

2,982.87
13,545.66
68,747.25
4,678.60
2,000.00

91,954.38

1,455,461.70
218,319.26
1,673,780.96

AN

JUMLAH
HARGA
(Rp.)
22,432.59
12,679.29
14,629.95

49,741.82

591,220.00
167,757.69
230,607.32
37,997.10
12,847.92
42,275.20
58,210.33

1,140,915.57

85,976.42
17,938.33
2,000.00

105,914.75

1,296,572.14
194,485.82
1,491,057.96

AN
JUMLAH
HARGA
(Rp.)

24,741.82
7,458.41
2,151.46

34,351.69

877,400.00

877,400.00

2,982.87
13,545.66
68,747.25
4,678.60
2,000.00

91,954.38

1,003,706.07
150,555.91
1,154,261.98
AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,972.36
470.00
1,100.00

13,542.36

1,000.00
1,000.00

17,667.36
2,650.10
20,317.47

AN

JUMLAH
HARGA
(Rp.)

40,250.00
26,000.00
7,500.00

73,750.00

82,500.00
3,500.00
86,000.00

1,000.00

1,000.00

160,750.00
24,112.50
184,862.50
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.1 (1)(a)


JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0017 16,428.57


2. Mandor ( L03 ) jam 0.0003 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Aspal ( M10 ) Kg 0.5432 12,419.35


2. Kerosene ( M11 ) liter 0.2966 11,550.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Asp. Distributor ( E41 ) Jam 0.0002 462,521.61


2. Compressor ( E05 ) Jam 0.0002 219,355.48

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.1 (2)(a)


JENIS PEKERJAAN : Lapis Perekat - Aspal Cair
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0007 16,428.57


2. Mandor ( L03 ) jam 0.0001 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Aspal ( M10 ) Kg 0.2971 12,419.35


2. Kerosene ( M11 ) liter 0.0721 11,550.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Asp. Distributor ( E41 ) Jam 0.0001 462,521.61
2. Compressor ( E05 ) Jam 0.0001 219,355.48

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.3(3a)


JENIS PEKERJAAN : Lataston Lapis Aus (HRS-WC)
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0089 16,428.57


2. Mandor ( L03 ) jam 0.0013 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
1. Hotmix HRS-WC Ton 0.0702 1,560,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) Jam 0.0247 378,845.19


2. Asphalt Finisher ( E02 ) Jam 0.0013 1,067,815.06
3. Tandem Roller ( E17 ) Jam 0.0010 573,393.57
4. P. Tyre Roller ( E18 ) Jam 0.0003 502,150.48
5. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.3(3c)


JENIS PEKERJAAN : Lataston Lapis Aus (HRS-WC) (Menggunakan Buruh)
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 0.1211 16,428.57


2. Mandor ( L03 ) jam 0.0038 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Hotmix HRS-WC Ton 0.0702 1,560,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) Jam 0.0247 378,845.19


2. Tandem Roller ( E17 ) Jam 0.0010 573,393.57
3. P. Tyre Roller ( E18 ) Jam 0.0003 502,150.48
4. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 6.3(5a)
JENIS PEKERJAAN : Laston Lapis Aus (AC-WC)
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0186 16,428.57


2. Mandor ( L03 ) jam 0.0019 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Hotmix AC-WC Ton 0.0974 1,450,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) Jam 0.0247 378,845.19


2. Asphalt Finisher ( E02 ) Jam 0.0013 1,067,815.06
3. Tandem Roller ( E17 ) Jam 0.0013 573,393.57
4. P. Tyre Roller ( E18 ) Jam 0.0005 502,150.48
5. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.3(5e)


JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) (Menggunakan Buruh)
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1304 16,428.57


2. Mandor ( L03 ) jam 0.0056 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Hotmix AC-WC Ton 0.0974 1,450,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Dump Truck ( E08 ) Jam 0.0247 378,845.19


2. Tandem Roller ( E17 ) Jam 0.0013 573,393.57
3. P. Tyre Roller ( E18 ) Jam 0.0005 502,150.48
4. Alat Bantu Ls 1.0000 1,000.00
JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.6.(1)


JENIS PEKERJAAN : Lapis Permukaan Penetrasi Macadam
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0099 16,428.57


2. Mandor ( L03 ) jam 0.0010 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat Kasar ( M03 ) M3 0.1168 309,956.08


2. Agregat Halus ( M04 ) M3 0.0104 309,956.08
3. Aspal ( M10 ) Kg 6.9010 12,419.35
JUMLAH HARGA BAHAN

C. PERALATAN

1. 3-Wheel Roller ( E16 ) Jam 0.0030 260,710.60


2. Asp. Sprayer ( E03 ) Jam 0.0265 86,304.26
3. Alat bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

27.38
7.14

34.52

6,745.95
3,426.19

10,172.14

77.09
36.56

113.65

10,320.31
1,548.05
11,868.36

AN

JUMLAH
HARGA
(Rp.)

11.98
3.13

15.10

3,689.19
832.76

4,521.95
33.73
15.99

49.72

4,586.77
688.02
5,274.79

AN

JUMLAH
HARGA
(Rp.)

146.62
27.32

173.94
109,582.20

109,582.20

9,372.27
1,361.40
600.35
144.74
1,000.00

12,478.76

122,234.90
18,335.23
140,570.13

AN

JUMLAH
HARGA
(Rp.)
1,989.82
81.96

2,071.78

109,582.20

109,582.20

9,372.27
600.35
144.74
1,000.00

11,117.36

122,771.34
18,415.70
141,187.04

AN
JUMLAH
HARGA
(Rp.)

306.14
39.93

346.07

141,288.00

141,288.00

9,372.27
1,361.40
719.62
270.39
1,000.00

12,723.69

154,357.76
23,153.66
177,511.42
AN

JUMLAH
HARGA
(Rp.)

2,142.97
119.79

2,262.77

141,288.00

141,288.00

9,372.27
719.62
270.39
1,000.00
11,362.29

154,913.05
23,236.96
178,150.01

AN

JUMLAH
HARGA
(Rp.)

163.00
21.26

184.27

36,212.47
3,208.70
85,705.93
125,127.11

793.54
2,288.37
2,000.00

5,081.91

130,393.29
19,558.99
149,952.28
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (2)


JENIS PEKERJAAN : Beton mutu tinggi fc’=45 MPa (K-500) (Ready Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.8032 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-500 ( M68 ) M3 1.0250 1,285,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Water Tang Truck ( E23 ) jam 0.0382 321,225.68


2. Concrete Vibrator ( E20 ) jam 0.1004 59,418.69
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (4)


JENIS PEKERJAAN : Beton mutu tinggi fc’=35 MPa (K-400) (Ready Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.8032 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-400 ( M69 ) M3 1.0250 1,144,200.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Water Tang Truck ( E23 ) jam 0.0382 321,225.68
2. Concrete Vibrator ( E20 ) jam 0.1004 59,418.69
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (5)


JENIS PEKERJAAN : Beton mutu sedang fc’=30 MPa (K-350) (Ready Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.8032 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN
1. Beton K-350 ( M72 ) M3 1.0250 1,091,400.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Water Tang Truck ( E23 ) jam 0.0382 321,225.68


2. Concrete Vibrator ( E20 ) jam 0.1004 59,418.69
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (6)


JENIS PEKERJAAN : Beton mutu sedang fc’= 25 MPa (K-300) (Ready Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 0.8032 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-300 ( M59 ) M3 1.0250 1,067,200.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Water Tang Truck ( E23 ) jam 0.0382 321,225.68


2. Concrete Vibrator ( E20 ) jam 0.1004 59,418.69
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 7.1 (7)
JENIS PEKERJAAN : Beton mutu sedang fc’= 20 MPa (K-250) (Ready Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.8032 16,428.57


2. Tukang ( L02 ) jam 0.4016 18,571.43
3. Mandor ( L03 ) jam 0.1004 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Beton K-250 ( M37 ) M3 1.0250 1,003,400.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Water Tang Truck ( E23 ) jam 0.0382 321,225.68


2. Concrete Vibrator ( E20 ) jam 0.1004 59,418.69
3. Truck Mixer ( E49 ) jam 0.0886 775,969.15
4. Alat Bantu Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (7a)


JENIS PEKERJAAN : Beton mutu sedang fc’= 20 MPa (K-250) (Site Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 1.3655 16,428.57


2. Tukang ( L02 ) jam 0.6827 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Semen ( M12a) Kg 422.3000 1,400.00


2. Pasir beton ( M01a ) M3 0.5412 310,000.00
3. Agregat Kasar ( M03 ) M3 0.7440 309,956.08

JUMLAH HARGA BAHAN

C. PERALATAN

1. Concrete Mixer ( E06 ) jam 0.4016 214,081.29


2. Water Tanker ( E23 ) jam 0.0558 321,225.68
3. Alat Bantu Ls 1.0000 2,000.00
JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (8)


JENIS PEKERJAAN : Beton mutu rendah fc’= 15 MPa (K-175) (Site mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 1.3655 16,428.57


2. Tukang ( L02 ) jam 0.6827 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Semen ( M12a) Kg 327.5400 1,400.00


2. Pasir beton ( M01a ) M3 0.5024 310,000.00
3. Agregat Kasar ( M03 ) M3 0.9053 309,956.08
JUMLAH HARGA BAHAN

C. PERALATAN

1. Concrete Mixer ( E06 ) jam 0.6827 214,081.29


2. Water Tanker ( E23 ) jam 0.0382 321,225.68
3. Alat Bantu Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (10)


JENIS PEKERJAAN : Beton mutu rendah fc’= 10 MPa (K-125) (Site Mix)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 1.3655 16,428.57


2. Tukang ( L02 ) jam 0.6827 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Semen ( M12a) Kg 311.0600 1,400.00


2. Pasir beton ( M01a ) M3 0.5113 310,000.00
3. Agregat Kasar ( M03 ) M3 0.9053 309,956.08

JUMLAH HARGA BAHAN

C. PERALATAN

1. Concrete Mixer ( E06 ) jam 0.6827 214,081.29


2. Water Tanker ( E23 ) jam 0.0382 321,225.68
3. Alat Bantu Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (11)


JENIS PEKERJAAN : Acuan Untuk Beton
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.4500 16,428.57


2. Tukang ( L02 ) jam 1.4000 18,571.43
3. Mandor ( L03 ) jam 0.3500 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Perancah ( M19 ) M3 0.0300 2,900,000.00


2. Paku ( M18 ) Kg 0.2000 17,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (12)


JENIS PEKERJAAN : Stoot Werk
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.4500 16,428.57


2. Tukang ( L02 ) jam 1.4000 18,571.43
3. Mandor ( L03 ) jam 0.3500 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Perancah ( M19 ) M3 0.0300 2,900,000.00


2. Paku ( M18 ) Kg 0.2000 17,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.1 (12)


JENIS PEKERJAAN : Stoot Werk
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 5.6000 16,428.57


2. Tukang ( L02 ) jam 5.6000 18,571.43
3. Mandor ( L03 ) jam 0.5600 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Perancah ( M19 ) M3 0.0675 2,900,000.00


2. Paku ( M18 ) Kg 0.3500 17,500.00

JUMLAH HARGA BAHAN


C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.3 (1)


JENIS PEKERJAAN : Baja Tulangan BJ 24 Polos
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA


B. BAHAN

1. Baja Tulangan (Polos) U24 ( M39a ) M3 1.1000 10,883.97


2. Kawat Beton ( M14 ) Kg 0.0025 23,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.3 (2)


JENIS PEKERJAAN : Baja Tulangan BJ 32 Polos
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Polos) U32 ( M57a ) M3 1.1000 10,883.97


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.3 (3)


JENIS PEKERJAAN : Baja Tulangan BJ 32 Ulir
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Ulir) D32 ( M39b ) M3 1.0500 10,960.44


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.3 (4)


JENIS PEKERJAAN : Baja Tulangan BJ 39 Ulir
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Ulir) D39 ( M39c ) M3 1.0500 10,960.44


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00


JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.3 (5)


JENIS PEKERJAAN : Baja Tulangan BJ 48 Ulir
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.1050 16,428.57


2. Tukang ( L02 ) jam 0.0350 18,571.43
3. Mandor ( L03 ) jam 0.0350 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Tulangan (Ulir) D48 ( M39d ) M3 1.0500 10,960.44


2. Kawat Beton ( M14 ) Kg 0.0200 23,500.00
JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.4 (3)


JENIS PEKERJAAN : Baja Struktur penyediaan dan pemasangan
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA

1. Pekerja ( L01 ) jam 0.0010 16,428.57


2. Tukang ( L02 ) jam 0.0001 18,571.43
3. Mandor ( L03 ) jam 0.0001 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Baja Struktur ( M57a ) M3 1.0000 10,883.97

JUMLAH HARGA BAHAN

C. PERALATAN

1. Tronton ( E35 ) jam 0.0004 672,934.11


2. Crane 10-15 Ton ( E07 ) jam 0.0001 731,576.79
3. Crane On Track ( E31 ) jam 0.0010 540,862.32
4. Alat Bantu Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
ITEM PEMBAYARAN NO. : 7.5 (1)
JENIS PEKERJAAN : Pemasangan jembatan rangka baja
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0161 16,428.57


2. Tukang ( L02 ) jam 0.0040 18,571.43
3. Mandor ( L03 ) jam 0.0008 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kayu Perancah ( M19 ) M3 0.0002 2,900,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Crane On Track ( E31 ) jam 0.0008 540,862.32


2. Alat Bantu Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.5 (2)


JENIS PEKERJAAN : Pengangkutan Bahan Jembatan
SATUAN PEMBAYARAN : Kg

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 0.0002 16,428.57


2. Mandor ( L03 ) jam 0.0000 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1. Trailer 1 ( E35 ) jam 0.0003 672,934.11


2. Trailer 2 ( E35 ) jam 0.0003 672,934.11
2. Crane 1 ( E07 ) jam 0.0001 731,576.79
3. Crane 2 ( E07 ) jam 0.0001 731,576.79
4. Crane 3 ( E07 ) jam 0.0001 731,576.79
5. Alat Bantu Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.9.(1)


JENIS PEKERJAAN : Pasangan Batu
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 5.4618 16,428.57


2. Tukang ( L02 ) jam 1.3655 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Batu Kali ( M02 ) M3 1.1700 240,000.00


2. Semen (PC) ( M12a) Kg 176.0000 1,400.00
3. Pasir Pasang ( M01b ) M3 0.5088 305,289.00
JUMLAH HARGA BAHAN

C. PERALATAN

1. Conc. Mixer ( E06 ) jam 0.6827 214,081.29


2. Water Tanker ( E23 ) jam 0.0014 321,225.68
3. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.9.(2)


JENIS PEKERJAAN : Plesteran
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 2.8000 16,428.57


2. Tukang ( L02 ) jam 1.5400 18,571.43
3. Mandor ( L03 ) jam 0.1400 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Pasir Pasang ( M01b ) M3 0.0194 305,289.00


2. Semen PC (50 Kg) ( M12 ) zak 0.1632 70,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.10.(3a)


JENIS PEKERJAAN : Bronjong
SATUAN PEMBAYARAN : M3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja ( L01 ) jam 5.4618 16,428.57


2. Tukang ( L02 ) jam 1.3655 18,571.43
3. Mandor ( L03 ) jam 0.6827 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Kawat Bronjong ( M15 ) Unit 1.0000 500,000.00


2. Batu ( M02 ) M3 1.1000 240,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Alat Bantu Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
AN

JUMLAH
HARGA
(Rp.)

13,195.64
7,458.41
2,151.46

22,805.51

1,317,125.00

1,317,125.00

12,255.60
5,965.73
68,747.25
2,000.00

88,968.59

1,428,899.09
214,334.86
1,643,233.96

AN

JUMLAH
HARGA
(Rp.)

13,195.64
7,458.41
2,151.46

22,805.51

1,172,805.00

1,172,805.00
12,255.60
5,965.73
68,747.25
2,000.00

88,968.59

1,284,579.09
192,686.86
1,477,265.96

AN

JUMLAH
HARGA
(Rp.)

13,195.64
7,458.41
2,151.46

22,805.51
1,118,685.00

1,118,685.00

12,255.60
5,965.73
68,747.25
2,000.00

88,968.59

1,230,459.09
184,568.86
1,415,027.96

AN

JUMLAH
HARGA
(Rp.)
13,195.64
7,458.41
2,151.46

22,805.51

1,093,880.00

1,093,880.00

12,255.60
5,965.73
68,747.25
2,000.00

88,968.59

1,205,654.09
180,848.11
1,386,502.21

AN
JUMLAH
HARGA
(Rp.)

13,195.64
7,458.41
2,151.46

22,805.51

1,028,485.00

1,028,485.00

12,255.60
5,965.73
68,747.25
2,000.00

88,968.59

1,140,259.09
171,038.86
1,311,297.96
AN

JUMLAH
HARGA
(Rp.)

22,432.59
12,679.29
14,629.95

49,741.82

591,220.00
167,757.69
230,607.32

989,585.02

85,976.42
17,938.33
2,000.00
105,914.75

1,145,241.59
171,786.24
1,317,027.82

AN

JUMLAH
HARGA
(Rp.)

22,432.59
12,679.29
14,629.95

49,741.82

458,556.00
155,739.23
280,587.74
894,882.97

146,159.92
12,255.60
500.00

158,915.52

1,103,540.31
165,531.05
1,269,071.36

AN

JUMLAH
HARGA
(Rp.)

22,432.59
12,679.29
14,629.95

49,741.82

435,484.00
158,493.46
280,587.74

874,565.20

146,159.92
12,255.60
500.00

158,915.52

1,083,222.54
162,483.38
1,245,705.92

AN
JUMLAH
HARGA
(Rp.)

40,250.00
26,000.00
7,500.00

73,750.00

87,000.00
3,500.00

90,500.00

1,000.00

1,000.00

165,250.00
24,787.50
190,037.50
AN

JUMLAH
HARGA
(Rp.)

40,250.00
26,000.00
7,500.00

73,750.00

87,000.00
3,500.00

90,500.00

1,000.00

1,000.00
165,250.00
24,787.50
190,037.50

AN

JUMLAH
HARGA
(Rp.)

91,999.99
104,000.00
12,000.00

207,999.99

195,750.00
6,125.00

201,875.00
1,000.00

1,000.00

410,874.99
61,631.25
472,506.24

AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00
11,972.36
58.75

12,031.11

1,000.00

1,000.00

16,156.11
2,423.42
18,579.53

AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,972.36
470.00

12,442.36

1,000.00

1,000.00

16,567.36
2,485.10
19,052.47
AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,508.47
470.00

11,978.47

1,000.00

1,000.00

16,103.47
2,415.52
18,518.99
AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,508.47
470.00

11,978.47

1,000.00
1,000.00

16,103.47
2,415.52
18,518.99

AN

JUMLAH
HARGA
(Rp.)

1,725.00
650.00
750.00

3,125.00

11,508.47
470.00
11,978.47

1,000.00

1,000.00

16,103.47
2,415.52
18,518.99

AN

JUMLAH
HARGA
(Rp.)
16.49
1.86
2.15

20.51

10,883.97

10,883.97

297.28
73.45
543.03
5,000.00

5,913.77

16,818.24
2,522.74
19,340.98

AN
JUMLAH
HARGA
(Rp.)

263.91
74.58
17.21

355.71

446.15

446.15

434.43
2,500.00

2,934.43

3,736.29
560.44
4,296.73
AN

JUMLAH
HARGA
(Rp.)

2.83
0.37

3.20

206.07
206.07
88.14
88.14
88.14
2,500.00

3,176.56

3,179.76
476.96
3,656.72

AN

JUMLAH
HARGA
(Rp.)

89,730.34
25,358.58
14,629.95

129,718.87

280,800.00
246,400.00
155,345.13
682,545.13

146,159.92
451.52
1,000.00

147,611.44

959,875.44
143,981.32
1,103,856.76

AN

JUMLAH
HARGA
(Rp.)

46,000.00
28,600.00
3,000.00

77,600.00

5,922.61
11,424.00

17,346.61

94,946.60
14,241.99
109,188.59

AN
JUMLAH
HARGA
(Rp.)

89,730.34
25,358.58
14,629.95

129,718.87

500,000.00
264,000.00

764,000.00

5,000.00

5,000.00

898,718.87
134,807.83
1,033,526.70
PEMBANGUNA
K
LEMBAR

Nomor Pekerjaan : 2.1.(1)


Nama Pekerjaan : Galian untuk Selokan Drainase dan Saluran Air
Satuan : M3
:

STA.
KIRI
LEBAR
TINGGI
VOLUME

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KANAN
LEBAR 0.80 0.80 0.80 0.80 0.80 0.80 0.80
TEBAL 0.80 0.80 0.80 0.80 0.80 0.80 0.80
VOLUME 32.00 32.00 32.00 32.00 32.00 32.00

Nomor Pekerjaan : 3.1.(1c)


Nama Pekerjaan : Galian Biasa (alat)
Satuan : M3

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KIRI
LEBAR 1.10 3.80 6.00 7.10 7.10 4.50
TINGGI 0.15 0.15 0.15 0.15 0.15 0.15
VOLUME 0.00 18.38 36.75 49.13 53.25 43.50

STA.
KANAN
LEBAR
TEBAL
VOLUME
PEMBANGUNA
K
LEMBAR

Nomor Pekerjaan : 3.3.(1)


Nama Pekerjaan : Penyiapan Badan Jalan
Satuan : M2
Nama Jembatan

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300

PANJANG 50.00 50.00 50.00 50.00 50.00 50.00


LEBAR 1.10 3.80 6.00 7.10 7.10 4.50
VOLUME 0.00 122.50 245.00 327.50 355.00 290.00

Nomor Pekerjaan : 3.4.(1)


Nama Pekerjaan : Pembersihan dan Pengupasan Lahan
Satuan : M2

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


PANJANG 50.00 50.00 50.00 50.00 50.00 50.00
LEBAR 1.10 3.80 6.00 7.10 7.10 4.50
VOLUME 0.00 122.50 245.00 327.50 355.00 290.00
PEMBANGUNA
K
LEMBAR

NOMOR PEKERJAAN : 5.1.(1)


NAMA PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN : M3

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KIRI
LEBAR 3.60 3.60 3.60 3.60 3.60 3.60 3.60
TINGGI 0.10 0.10 0.10 0.10 0.10 0.10 0.10
VOLUME 18.00 18.00 18.00 18.00 18.00 18.00

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KANAN
LEBAR 3.60 3.60 3.60 3.60 3.60 3.60 3.60
TINGGI 0.10 0.10 0.10 0.10 0.10 0.10 0.10
VOLUME 18.00 18.00 18.00 18.00 18.00 18.00

NOMOR PEKERJAAN : 5.1.(1)


NAMA PEKERJAAN : Perkerasan Beton Semen
SATUAN : M3

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KIRI
LEBAR 3.50 3.50 3.50 3.50 3.50 3.50 3.50
TINGGI 0.25 0.25 0.25 0.25 0.25 0.25 0.25
VOLUME 43.75 43.75 43.75 43.75 43.75 43.75

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KANAN
LEBAR 3.50 3.50 3.50 3.50 3.50 3.50 3.50
TINGGI 0.25 0.25 0.25 0.25 0.25 0.25 0.25
VOLUME 43.75 43.75 43.75 43.75 43.75 43.75
PEMBANGUNA
K
LEMBAR

Nomor Pekerjaan : 5.3.(3)


Nama Pekerjaan : Lapis Pondasi bawah Beton Kurus
Satuan : M3

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KIRI
LEBAR 3.60 3.60 3.60 3.60 3.60 3.60 3.60
TINGGI 0.12 0.12 0.12 0.12 0.12 0.12 0.12
VOLUME 21.60 21.60 21.60 21.60 21.60 21.60

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300


KANAN
LEBAR 3.60 3.60 3.60 3.60 3.60 3.60 3.60
TINGGI 0.12 0.12 0.12 0.12 0.12 0.12 0.12
VOLUME 21.60 21.60 21.60 21.60 21.60 21.60

NOMOR PEKERJAAN : 4.2.(2a)


NAMA PEKERJAAN : Lapis Pondasi Agregat Kelas B (untuk pelebaran)
SATUAN : M3
STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300
KIRI
LEBAR 1.10 3.80 6.00 7.10 7.10 4.50
TINGGI 0.15 0.15 0.15 0.15 0.15 0.15
VOLUME 0.00 18.38 36.75 49.13 53.25 43.50
PEMBANGUNA
K
LEMBAR

Nomor Pekerjaan : 5.3.(4)


Nama Pekerjaan : Baja Tulangan Untuk Perkerasan Beton
Satuan : KG

PERHTUNGAN VOLUME

Panjang Jalan
Lebar Jalan
Tebal Beton
Volume Beton

Besi Dowel D25-30


= 0.45 x

Besi Tiebar D16-60


= 0.70 x

Slof Dudukan Dowel 4-D8, Sen


= 6.00 x
= 0.45 x
Slof Dudukan Teibar 4-D8, Sen
= 5.00 x
= 0.45 x

Slof Tepi 4-D8, Sengkang D8-6


= 5.00 x
= 0.45 x
PEMBANGUNA
K
LEMBAR

Nomor Pekerjaan : 5.3.(5)


Nama Pekerjaan : Acuan Untuk Perkerasan Beton
Satuan : m2
Nama Struktur :

PERHTUNGAN VOLUME
Beton K-400
Panjang Jalan
Lebar Jalan
Tebal

Pondasi Beton Kurus


= 0.12 x
= 0.12 x

Beton K-400
= 0.25 x
= 0.25 x
PEMBANGUNA
K
LEMBAR

NOMOR PEKERJAAN : 5.1.(2)


NAMA PEKERJAAN : Lapis Pondasi Agregat Kelas B (untuk perbaikan)
SATUAN : M3

STA. 0+000 0+050 0+100 0+150 0+200 0+250 0+300

LEBAR 7.20 7.20 7.20 7.20 7.20 7.20 7.20


TINGGI 0.15 0.15 0.15 0.15 0.15 0.15 0.15
VOLUME 54.00 54.00 54.00 54.00 54.00 54.00
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

+300 0+350 0+400 0+450 0+500 0+550 0+610

.80 0.80 0.80 0.80 0.80 0.80 0.80


.80 0.80 0.80 0.80 0.80 0.80 0.80
32.00 32.00 32.00 32.00 32.00 38.40 390

+300 0+350 0+400 0+450 0+500 0+550 0+600

.50 2.70 2.40 3.00 3.40 3.50 3.50


.15 0.15 0.15 0.15 0.15 0.15 0.15
27.00 19.13 20.25 24.00 25.88 26.25 3.
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

+300 0+350 0+400 0+450 0+500 0+550 0+600

0.00 50.00 50.00 50.00 50.00 50.00 50.00


.50 2.70 2.40 3.00 3.40 3.50 3.50
180.00 127.50 135.00 160.00 172.50 175.00 25

+300 0+350 0+400 0+450 0+500 0+550 0+600


0.00 50.00 50.00 50.00 50.00 50.00 50.00
.50 2.70 2.40 3.00 3.40 3.50 3.50
180.00 127.50 135.00 160.00 172.50 175.00 25
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

+300 0+350 0+400 0+450 0+500 0+550 0+610

.60 3.60 3.60 3.60 3.60 3.60 3.60


.10 0.10 0.10 0.10 0.10 0.10 0.10
18.00 18.00 18.00 18.00 18.00 21.60 219

+300 0+350 0+400 0+450 0+500 0+550 0+610

.60 3.60 3.60 3.60 3.60 3.60 3.60


.10 0.10 0.10 0.10 0.10 0.10 0.10
18.00 18.00 18.00 18.00 18.00 21.60 219

Timbunan Median = 11 x 0.12 x 2 2.64

+300 0+350 0+400 0+450 0+500 0+550 0+610


.50 3.50 3.50 3.50 3.50 3.50 3.50
.25 0.25 0.25 0.25 0.25 0.25 0.25
43.75 43.75 43.75 43.75 43.75 52.50 533

+300 0+350 0+400 0+450 0+500 0+550 0+610

.50 3.50 3.50 3.50 3.50 3.50 3.50


.25 0.25 0.25 0.25 0.25 0.25 0.25
43.75 43.75 43.75 43.75 43.75 52.50 533
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

+300 0+350 0+400 0+450 0+500 0+550 0+610

.60 3.60 3.60 3.60 3.60 3.60 3.60


.12 0.12 0.12 0.12 0.12 0.12 0.12
21.60 21.60 21.60 21.60 21.60 25.92 263

+300 0+350 0+400 0+450 0+500 0+550 0+610

.60 3.60 3.60 3.60 3.60 3.60 3.60


.12 0.12 0.12 0.12 0.12 0.12 0.12
21.60 21.60 21.60 21.60 21.60 25.92 263
+300 0+350 0+400 0+450 0+500 0+550 0+600

.50 2.70 2.40 3.00 3.40 3.50 3.50


.15 0.15 0.15 0.15 0.15 0.15 0.15
27.00 19.13 20.25 24.00 25.88 26.25 3.
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

KUANTITAS =

N VOLUME

= 1,000 m Lebar 1 Segmen 3.00 m


= 6.00 m Panjang 1 Segmen 5.00 m
= 0.20 m panjang Dowel 0.45 m
= 1,200.00 m3 Jumlah Segmen 200.00 m
Jarak Dowel 0.3 m
panjang Tiebar 0.7 m
Jumlah tie bar 1 segmen 7.00 m

21.00 x 201.00 x 3.851 = 7,315.55 kg

7.00 x 200.00 x 1.578 = 1,545.99 kg

Dowel 4-D8, Sengkang D8-60


8.00 x 200.00 x 0.394 = 3,786.09 kg
22.00 x 200.00 x 0.394 = 780.88 kg
Teibar 4-D8, Sengkang D8-60
8.00 x 200.00 x 0.394 = 3,155.07 kg
16.67 x 200.00 x 0.394 = 591.58 kg

Sengkang D8-60
8.00 x 200.00 x 0.394 = 3,155.07 kg
16.67 x 200.00 x 0.394 = 591.58 kg

20,921.80 kg
17.435 kg/m3
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

KUANTITAS =

N VOLUME
Pondasi Beton Kurus
= 1,000 m Panjang Jalan = 1,000 m
= 6.00 m Lebar Jalan = 6.00 m
= 0.25 m Tebal = 0.12 m

Kurus
1,000.00 x 2.00 = 240.000 m2
6.00 x 2.00 = 1.440 m2

1,000.00 x 2.00 = 500.000 m2


6.00 x 2.00 = 3.000 m2

744.440 m2
EMBANGUNAN JALAN PUSPEMKAB LANJUTAN
KECAMATAN CIRUAS
LEMBAR PERHITUNGAN KUANTITAS

+300 0+350 0+400 0+450 0+500 0+550 0+610

.20 7.20 7.20 7.20 7.20 7.20 7.20


.15 0.15 0.15 0.15 0.15 0.15 0.15
54.00 54.00 54.00 54.00 54.00 64.80 658

Timbunan Median = 11 x 0.25 x 2 5.50


137.14
120.00 0.88
Over Lap
0+610 0+011

0.80 0.80
0.80 0.80
390.40 397.44
397.44

0+600 0+610

3.50 1.50
0.15 0.15
3.75 347.25

347.25
0+600 0+610

50.00 10.00
3.50 1.50
25.00 2315.00

2,315.00

0+600 0+610
50.00 10.00
3.50 1.50
25.00 2315.00

2,315.00
Over Lap
0+610 0+011

3.60 3.60
0.10 0.10
219.60 223.56

0+610 0+011

3.60 3.60
0.10 0.10
219.60 223.56

449.76

over lap
0+610 0+011
3.50 3.50
0.25 0.25
533.75 543.38

0+610 0+011

3.50 3.50
0.25 0.25
533.75 543.38

1,086.75
over lap
0+610 0+011

3.60 3.60
0.12 0.12
263.52 268.27

0+610 0+011

3.60 3.60
0.12 0.12
263.52 268.27

536.54
0+600 0+610

3.50 1.50
0.15 0.15
3.75 347.25

347.25
- KG
2.00 m2
0+610 0+011

7.20 7.20
0.15 0.15
658.80 670.68

676.18
137.14
0.88

-
HARGA PERKIRAAN SENDIRI (HPS)
REKAPITULASI HARGA
NAMA PROGRAM : PROGRAM PENYELENGGARAAN PEMBANGUNAN JALAN DAN
JEMBATAN
NAMA KEGIATAN : PEMBANGUNAN/PEMELIHARAAN DAN PENINGKATAN JALAN (DAU)
PAKET PEKERJAAN : PENINGKATAN JALAN KAWASAN PUSPEMKAB (LANJUTAN)
LOKASI : KECAMATAN CIRUAS
SUMBER DANA/TA. : DAU - APBD PERUBAHAN KABUPATEN SERANG TA. 2019

NO. JENIS URAIAN PEKERJAAN

I PEKERJAAN UMUM
II DIVISI 2. DRAINASE
III DIVISI 3. PEKERJAAN TANAH
IV DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
V DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN
VII DIVISI 7. STRUKTUR

JUMLAH
PPN 10%
JUMLAH TOTAL

TERBILANG : Tiga Milyar Sembilan Ratus Sembilan Puluh Sembilan Juta Sembilan Ratus Sembilan

Ditetapkan oleh :
Kepala Bidang Bina Marga
Selaku Pejabat Pembuat Komitmen
DPUPR Kab. Serang

YADI PRIYADI R., ST. MM


NIP. 19810622 200801 1 004
RAAN SENDIRI (HPS)
ULASI HARGA
PANJANG RUAS : -
PANJ. PROYEK : 621 M'
LEBAR : 7,0 M'
KONSTRUKSI : BETON
WILAYAH : III / (TIGA)

JUMLAH
KERJAAN
BIAYA

Rp. 68,372,391.03
Rp. 124,992,757.89
Rp. 67,238,919.19
Rp. 133,502,203.63
Rp. 3,241,081,969.88
Rp. 1,168,758.39

Rp. 3,636,357,000.00
Rp. 363,635,700.00
Rp. 3,999,992,700.00

luh Sembilan Juta Sembilan Ratus Sembilan Puluh Dua Ribu Tujuh Ratus Rupiah

Serang, September 2019

Dibuat oleh :
Kepala Seksi Perencanaan Teknis dan Evaluasi
Bidang Bina Marga DPUPR Kab. Serang

H. IFAN IRFANSYAH ST. MM


NIP. 19820808 201001 1 008
HARGA PERKIRAAN SENDIRI (HPS
DAFTAR KUANTITAS DAN HARGA
NAMA PROGRAM : PROGRAM PENYELENGGARAAN PEMBANGUNAN JALAN DAN JEMBATAN
NAMA KEGIATAN : PEMBANGUNAN/PEMELIHARAAN DAN PENINGKATAN JALAN (DAU)
PAKET PEKERJAAN : PENINGKATAN JALAN KAWASAN PUSPEMKAB (LANJUTAN)
LOKASI : KECAMATAN CIRUAS
SUMBER DANA/TA. : DAU - APBD PERUBAHAN KABUPATEN SERANG TA. 2019
NO.
MATA JENIS PEKERJAAN SAT. VOLUME
PEMBAYARAN

I PEKERJAAN UMUM
Sta. (-0+011) - Sta. 0+000 - Sta. 0+610 ( P = 621 m )
1.2 Mobilisasi Bh 1.00
- Pembuatan papan nama proyek
- Pengujian Laboratorium
- Direksikeet
- Dokumentasi dan Rekaman Proyek
- Pengukuran dan Pematokan
- Mobilisasi dan Demobilisasi Alat
- Pemindahan tiang listrik

1.8 (1) Pemeliharaan Lalu Lintas & Perlindungan K3 LS 1.00

II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 397.44
2.3 (3) Box Culvert Heavy Duty 100 x 100 M1 20.00

III DIVISI 3. PEKERJAAN TANAH


3.1.(1c) Galian Biasa (alat) M3 347.25
3.3.(1) Penyiapan Badan Jalan M2 2,315.00
3.4.(1) Pembersihan dan Pengupasan Lahan M2 2,315.00

IV DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.(2a) Lapis Pondasi Agregat Kelas B (untuk pelebaran) M3 347.25

V DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M3 449.76
5.1.(2) Lapis Pondasi Agregat Kelas B M3 676.18
5.3.(1) Perkerasan Beton Semen (K-400) M3 1,086.75
5.3.(3) Lapis Pondasi bawah Beton Kurus (B0) M3 536.54
5.3.(4) Baja Tulangan Untuk Perkerasan Beton KG 14,194.86
5.3.(5) Acuan Untuk Perkerasan Beton M2 464.72
VII DIVISI 7. STRUKTUR
7.15.(2) Pembongkaran Beton M3 1.36
KIRAAN SENDIRI (HPS)
ANTITAS DAN HARGA
PANJANG RUAS : -
PEMBANGUNAN JALAN DAN JEMBATAN
PANJ. PROYEK : 621 M'
DAN PENINGKATAN JALAN (DAU) LEBAR : 7,0 M'
USPEMKAB (LANJUTAN) KONSTRUKSI : BETON
WILAYAH : III / (TIGA)

HARGA JUMLAH TOTAL


SATUAN HARGA HARGA
(Rp.) (Rp.) (Rp.)

68,372,391.03

58,451,319.60 58,451,319.60

9,921,071.43 9,921,071.43

124,992,757.89
70,444.73 27,997,553.49
4,849,760.22 96,995,204.40

67,238,919.19
149,221.53 51,817,176.29
1,827.84 4,231,449.60
4,833.82 11,190,293.30

133,502,203.63
384,455.59 133,502,203.63

3,241,081,969.88
386,341.44 173,760,926.05
376,702.83 254,718,919.59
1,673,780.96 1,818,981,458.28
1,154,261.98 619,307,722.75
20,317.47 288,403,642.20
184,862.50 85,909,301.00
1,168,758.39
859,381.17 1,168,758.39
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI

HARGA
No. URAIAN SATUAN VOL. SATUAN
(Rp.)

A. MOBILISASI PERALATAN
Periksa lembar 1.2-2

B. PEKERJAAN UMUM
1 - Pembuatan Papan Nama Proyek bh 2 506,747
2 - Pengujian Laboratorium Ls 1 4,500,000
3 - Pengadaan Direksikeet M2 12 1,035,250
4 - Dokumentasi dan Pelaporan Ls 1 7,831,286
5 - Pengukuran dan Pematokan M1 1,000 4,500
6 - Pemindahan tiang listrik titik 3 5,000,000

C DEMOBILISASI LS 1 3,435,000

Total Biaya Mobilisasi

Catatan :Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI

KODE HARGA
No. JENIS ALAT ALAT SATUAN VOL. SATUAN
(Rp.)

B. PERALATAN

4 DUMP TRUCK 3.5 TON Unit 2 500,000


6 TRUCK MIXER Unit 3 650,000
7 EXCAVATOR 80-140 HP Unit 1 1,500,000
8 GENERATOR SET Unit 1 300,000
9 MOTOR GRADER >100 HP Unit 1 1,500,000
11 TANDEM ROLLER 6-8 T. Unit 1 1,500,000
12 VIBRATORY ROLLER 5-8 T. Unit 1 1,000,000
13 CONCRETE VIBRATOR Unit 1 200,000
14 WATER TANKER 3000-4500 L. Unit 1 500,000
18 CRANE ON TRACK 35 TON Unit 1 1,000,000
21 CONCRETE PAVER Unit 1 1,000,000

Total untuk Item B pada Lembar 1


Lembar 1.2-1
JUMLAH
HARGA
(Rp.)

11,450,000

1,013,494
4,500,000
12,423,000
7,831,286
4,500,000
15,000,000

3,435,000

60,152,780

da masing-masing item mobilisasi di atas sudah termasuk over-head dan laba


Lembar 1.2-2
JUMLAH
HARGA
(Rp.)

1,000,000
1,950,000
1,500,000
300,000
1,500,000
1,500,000
1,000,000
200,000
500,000
1,000,000
1,000,000

11,450,000
RINCIAN PEKERJAAN UMUM

I. PAPAN NAMA PROYEK (1BH)

HARGA SATUAN
URAIAN KOEF. SAT.
(Rp.)
- Kayu Acuan 0.155 m3 2,750,000.00
- Paku 0.250 kg 17,500.00
- Thinner 1.000 Ltr 27,000.00
- Penulisan 0.125 Ls 349,312.50
- Ongkos Pasang 0.125 Ls 43,664.06
JUMLAH TOTAL

II. PENGUJIAN LABORATORIUM (LS)

TARIF
URAIAN SAT. VOLUME
(Rp.)

1 Pengeboran Beton
c. Kedalaman lebih dari 20 cm s.d. 30 cm Per Titik 400,000.00 6
2 Hammer Test Per Titik 35,000.00 60

JUMLAH TOTAL

III. PEMBUATAN LOS KERJA/GUDANG (M2)

HARGA SATUAN
URAIAN KOEF. SAT.
(Rp.)

- Dolken 7-10 1.700 btg 25,000.00


- Kayu Terentang 0.210 m3 2,900,000.00
- Paku 4-7cm 0.300 kg 17,500.00
- Semen Portland (50kg/zak) 0.210 zak 70,000.00
- Pasir Beton 0.030 m3 310,000.00
- Batu Koral Beton Kali 0.050 m3 240,000.00
- Seng Gel. BJLS 28 80 x 180 1.500 Lbr 50,000.00
- Tukang 2.000 oh 130,000.00
Mandor 0.050 oh 150,000.00
-

JUMLAH TOTAL
JUMLAH HARGA
(Rp.)
426,250.00
4,375.00
27,000.00
43,664.06
5,458.01
506,747.07

JUMLAH HARGA
(Rp.)

2,400,000.00
2,100,000.00

4,500,000.00

JUMLAH HARGA
(Rp.)

42,500.00
609,000.00
5,250.00
14,700.00
9,300.00
12,000.00
75,000.00
260,000.00
7,500.00

1,035,250.00
ITEM PEMBAYARAN NO. : 1.8 (1)
JENIS PEKERJAAN : Pemeliharaan Lalu Lintas & Perlindungan K3

UNTUK PEKERJAAN PERKERASAN BETON

HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

I. Data & Asumsi

1 Jumlah lokasi pekerjaan Lokasi 1


2 Total Masa Pelaksanaan Proyek Hari 60
3 Masa Pemeliharaan & Perlindungan Lalin Hari 45
4 Sudah termasuk persiapan/pemasangan
5 Pembongkaran termasuk Demobilisasi

II. Pekerja Pengatur Lalu Lintas


Jumlah lokasi pekerjaan Lokasi 1
1 Petugas Rambu "Stop-Jalan" 2 Org/hari 90 16,429 1,478,571
2 Pengendali kecepatan kendaraan 2 Org/hari 90 16,429 1,478,571
3 Pemimpin Regu (Mandor) 1 Org/hari 45 24,643 1,108,929

III. Bahan & Perlengkapan


Jumlah lokasi pekerjaan Lokasi 1
1 Rambu "Stop-Jalan" Buah 2 50,000 100,000
2 Rambu lain (Batas kec., hati2, dll) Buah 3 50,000 150,000
3 Bendera Kuning/Hijau/Merah Buah 6 25,000 150,000
4 Barikade Kayu 1/2 lebar jalan Buah 2 100,000 200,000
5 Traffic Cone, jumlah per lokasi = 5 Buah 5 35,000 175,000
6 Baricade Tape / Police Line Set 3 40,000 120,000
7 Alat Komunikasi Bh 2 160,000 320,000

III. Perlengkapan Keselamatan Kerja

1 helm Bh 20 40,000 800,000


2 Rompi Bh 20 22,000 440,000
3 Sarung Tangan Pasang 20 40,000 800,000
3 Kacamata Bh 5 30,000 150,000
3 Sepatu Boot Pasang 20 100,000 2,000,000
3 Kotak P3K Buah 2 100,000 200,000
3 Pemadan Api Ringan Bh 1 250,000 250,000
Total Biaya Pemeliharaan & Perlindungan Lalu Lintas 9,921,071

Catatan :Jumlah yang tercantum pada masing-masing item di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
PENAWARAN HARGA SATUAN

ITEM PEMBAYARAN NO. : 2.3 (3)


JENIS PEKERJAAN : Gorong2 Box Culvert, Diameter dalam 100 cm
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja jam 16.0000 16,428.57


2. Tukang jam 4.0000 18,571.43
3. Mandor jam 4.0000 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

1. Box Culvert 100 x 100 x Buah 1.0000 3,363,750.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Tamper Jam 4.2931 63,703.20


2. Flat Bed Truck Jam 0.5758 603,997.19
3. Alat Bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 10.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
PENAWARAN HARGA SATUAN

JUMLAH
HARGA
(Rp.)

262,857.12
74,285.71
85,714.29

422,857.12

3,363,750.00

3,363,750.00

273,484.22
347,781.58
1,000.00

622,265.81

4,408,872.93
440,887.29
4,849,760.22
Urain Pekerjaan VOLUME SAT 0+011
Galian untuk Saluran Air 397.44 M3 5.12
Saluran Pasangan - M1
Gorong Box Culvert 20.00 M1
Galian Tanah Untuk Pelebaran 347.25 M3
Pembersihan dan Pengupasan Lahan 2,315.00 M2
Penyiapan Badan Jalan 2,315.00 M2
Pelebaran Lapis Pondasi Agregat Kelas A - M3
Pelebaran Lapis Pondasi Agregat Kelas B 347.25 M3
Timbunan Bahu Jalan (Agregat Kelas B) - M3
Perbaikan Lapis Pondasi Agregat Kelas A 449.76 M3 10.56
Perbaikan Lapis Pondasi Agregat Kelas B 676.18 M3 17.38
Lapis Pondasi bawah Beton Kurus (B - 0) 536.54 M3 9.50
Perkerasan Beton Semen (K-400) 1,086.75 M3 19.25
Baja Tulangan Untuk Perkerasan Beton 14,194.86 Kg 251.44
Acuan Untuk Perkerasan Beton 464.72 M2 8.23
Tembok Penahan Tanah - M1 -
0+000 0+100 0+200 0+300
5.12 64.00 64.00 64.00 64.00

1.00 9.00
18.38 85.88 96.75 46.13
61.25 61.25 286.25 286.25 322.50 322.50 153.75
61.25 61.25 286.25 286.25 322.50 322.50 153.75

18.38 85.88 96.75 46.13

10.56 72.00 72.00 72.00 72.00


17.38 108.00 108.00 108.00 108.00
9.50 86.40 86.40 86.40 86.40
19.25 175.00 175.00 175.00 175.00
251.44 2,285.81 2,285.81 2,285.81 2,285.81
8.23 74.83 74.83 74.83 74.83
- - - - - - - -
0+400 0+500 0+600 0+610 JUMLAH
64.00 64.00 64.00 6.40 =
=
10.00 =
46.13 44.25 52.13 3.75 =
153.75 147.50 147.50 173.75 173.75 12.50 12.50 =
153.75 147.50 147.50 173.75 173.75 12.50 12.50 =
=
46.13 44.25 52.13 3.75 =
=
72.00 72.00 72.00 7.20 =
108.00 108.00 108.00 10.80 =
86.40 86.40 86.40 8.64 =
175.00 175.00 175.00 17.50 =
2,285.81 2,285.81 2,285.81 228.58 =
74.83 74.83 74.83 7.48 =
- - - - - - - =
JUMLAH
395.52
-
20.00
347.25
2,315.00
2,315.00
-
347.25
-
449.76
676.18
536.54
1,086.75
14,194.86
464.72
-
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.15.(2)


JENIS PEKERJAAN : Pembongkaran Beton
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 12.5000 16,428.57


2. Mandor (L03) Jam 1.0417 21,428.57

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN
1. Compressor E05 Jam 1.0417 219,355.48
2. Jack Hammer E26 Jam 1.0417 52,699.42
3. Wheel Loader E15 Jam 0.0101 414,640.80
4. Dump Truck E08 Jam 0.6098 378,845.19
5 Alat bantu Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
ANALISA MASING-MASING HARGA SATUAN

JUMLAH
HARGA

(Rp.)

205,357.13
22,321.43

227,678.55

0.00

228,495.29
54,895.23
4,200.61
231,018.30
1,000.00

519,609.42

747,287.98
112,093.20
859,381.17
JADWAL PELAKSANAA

NAMA PROGRAM : PROGRAM PENYELENGGARAAN PEMBANGUNAN


JALAN DAN JEMBATAN
NAMA KEGIATAN : PEMBANGUNAN/PEMELIHARAAN DAN PENINGKATAN JALAN (DAU)
PAKET PEKERJAAN : PENINGKATAN JALAN KAWASAN PUSPEMKAB (LANJUTAN)
LOKASI : KECAMATAN CIRUAS
SUMBER DANA/TA. : DAU - APBD PERUBAHAN KABUPATEN SERANG TA. 2019
NO.
BULAN 1
MATA JENIS PEKERJAAN SAT. VOLUME BOBOT
PEMBAYARAN 1 2 3

I PEKERJAAN UMUM
Sta. 0+000 - Sta. 0+621 ( P = 621 m )
1.2 Mobilisasi Bh 1.00 1.64 0.409
- Pembuatan papan nama proyek
- Pengujian Laboratorium
- Direksikeet
- Dokumentasi dan Rekaman Proyek
- Pengukuran dan Pematokan
- Mobilisasi dan Demobilisasi Alat
- Pemindahan tiang listrik

1.8 (1) : Pemeliharaan & Perlindungan Lalu Lintas LS 1.00 0.33

II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 397.44 0.77 0.770
2.3 (3) Box Culvert Heavy Duty 100 x 100 M1 20.00 2.67 1.334 1.334

III DIVISI 3. PEKERJAAN TANAH


3.1.(1c) Galian Biasa (alat) M3 347.25 1.42 0.712 0.712
3.3.(1) Penyiapan Badan Jalan M2 2,315.00 0.12 0.058 0.058
3.4.(1) Pembersihan dan Pengupasan Lahan M2 2,315.00 0.31 0.308
IV DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
4.2.(2a) Lapis Pondasi Agregat Kelas B (untuk pelebaran) M3 347.25 3.67 1.836 1.836

V DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M3 447.12 4.75
5.1.(2) Lapis Pondasi Agregat Kelas B M3 670.68 6.95 2.084
5.3.(1) Perkerasan Beton Semen (K-400) M3 1,086.75 50.02
5.3.(3) Lapis Pondasi bawah Beton Kurus (B0) M3 536.54 17.03
5.3.(4) Baja Tulangan Untuk Perkerasan Beton KG 14,194.86 7.93
5.3.(5) Acuan Untuk Perkerasan Beton M2 464.72 2.36

VII DIVISI 7. STRUKTUR


7.15.(2) Pembongkaran Beton M3 1.36 0.03

100.00
1.487 4.710 5.254
0.00 1.487 6.197 11.451

Ditetapkan oleh :
Kepala Bidang Bina Marga
Selaku Pejabat Pembuat Komitmen
DPUPR Kab. Serang

YADI PRIYADI R., ST. MM


NIP. 19810622 200801 1 004
AL PELAKSANAAN

ULAN 1 BULAN 2 BULAN 3


KET
4 5 6 7 8 9 10 11 12

0.409 0.409 0.409


100.00

90.00

80.00

0.037 0.037 0.037 0.037 0.037 0.037 0.037 0.037 0.037

70.00

60.00

50.00
40.00

30.00
0.475 4.275
4.863
8.337 8.337 8.337 8.337 8.337 8.337 20.00
3.406 3.406 3.406 3.406 3.406
1.133 1.133 1.133 1.133 1.133 1.133 1.133
0.338 0.338 0.338 0.338 0.338 0.338 0.338 10.00

0.032 0.00

5.784 9.189 13.250 13.659 13.250 13.250 9.844 9.844 0.478


17.235 26.424 39.674 53.333 66.584 79.834 89.678 99.522 100.000

Serang, Agustus 2019

Dibuat oleh :
Kepala Seksi Perencanaan Teknis dan Evaluasi
Bidang Bina Marga DPUPR Kab. Serang

H. IFAN IRFANSYAH ST. MM


NIP. 19820808 201001 1 008
JADWAL PELAKSANAAN

NAMA PROGRAM : PROGRAM PENYELENGGARAAN PEMBANGUNAN JALAN DAN JEMBATAN

NAMA KEGIATAN : PROGRAM PENYELENGGARAAN PEMBANGUNAN JALAN DAN JEMBATAN


PAKET PEKERJAAN : PENINGKATAN JALAN KAWASAN PUSPEMKAB (LANJUTAN)
LOKASI : KECAMATAN CIRUAS
SUMBER DANA/TA. : DAU - APBD PERUBAHAN KABUPATEN SERANG TA. 2019
NO.
MATA JENIS PEKERJAAN SAT. VOLUME BOBOT
PEMBAYARAN 1

I PEKERJAAN UMUM
Sta. (-0+011) - Sta. 0+000 - Sta. 0+610 ( P = 621 m )
1.2 Mobilisasi Bh 1.00 1.61 0.536
- Pembuatan papan nama proyek
- Pengujian Laboratorium
- Direksikeet
- Dokumentasi dan Rekaman Proyek
- Pengukuran dan Pematokan
- Mobilisasi dan Demobilisasi Alat
- Pemindahan tiang listrik

1.8 (1) : Pemeliharaan & Perlindungan Lalu Lintas LS 1.00 0.27

II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 397.44 0.77 0.385
2.3 (3) Box Culvert Heavy Duty 100 x 100 M1 20.00 2.67

III DIVISI 3. PEKERJAAN TANAH


3.1.(1c) Galian Biasa (alat) M3 347.25 1.42 1.425
3.3.(1) Penyiapan Badan Jalan M2 2,315.00 0.12 0.116
3.4.(1) Pembersihan dan Pengupasan Lahan M2 2,315.00 0.31 0.308
IV DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
4.2.(2a) Lapis Pondasi Agregat Kelas B (untuk pelebaran) M3 347.25 3.67

V DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M3 447.12 4.78
5.1.(2) Lapis Pondasi Agregat Kelas B M3 670.68 7.00
5.3.(1) Perkerasan Beton Semen (K-400) M3 1,086.75 50.02
5.3.(3) Lapis Pondasi bawah Beton Kurus (B0) M3 536.54 17.03
5.3.(4) Baja Tulangan Untuk Perkerasan Beton KG 14,194.86 7.93
5.3.(5) Acuan Untuk Perkerasan Beton M2 464.72 2.36

VII DIVISI 7. STRUKTUR


7.15.(2) Pembongkaran Beton M3 1.36 0.03

100.00
2.770
0.00 2.770

Ditetapkan oleh :
Kepala Bidang Bina Marga
Selaku Pejabat Pembuat Komitmen
DPUPR Kab. Serang

YADI PRIYADI R., ST. MM


NIP. 19810622 200801 1 004
DWAL PELAKSANAAN

BULAN 1 BULAN 2
KET
2 3 4 5 6 7 8

0.536 0.536
100.00

90.00

80.00

0.045 0.045 0.045 0.045 0.045 0.045

70.00
0.385
2.667
60.00

50.00
40.00
3.671

30.00
4.778
3.502 3.502
12.506 12.506 12.506 12.506 20.00
4.258 4.258 4.258 4.258
1.983 1.983 1.983 1.983
0.473 0.473 0.473 0.473 0.473 10.00

0.032 0.00

10.226 13.057 19.800 19.264 19.264 15.006 0.613


12.996 26.052 45.852 65.116 84.380 99.387 100.000

Serang, September 2019

Dibuat oleh :
Kepala Seksi Perencanaan Teknis dan Evaluasi
Bidang Bina Marga DPUPR Kab. Serang

H. IFAN IRFANSYAH ST. MM


NIP. 19820808 201001 1 008

Anda mungkin juga menyukai