Anda di halaman 1dari 2

PENAWARAN HARGA PEKERJAAN (RAB)

PEMBUATAN SUMUR BOR AIR TANAH DALAM (DEEP WELL)


Lokasi : Proyek Pemuatan Sumur Bor Air Tanah di Kabupaten Gorontalo Utara
Konstruksi : Pipa PVC - AW, Diameter Sumur Ø 6" Lurus, Total Kedalaman 360 meter dibagi 3 (tiga) Lokasi
Sumur Bor @ 120 Meter.

HARGA
TOTAL BIAYA
NO. URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi & Demobilisasi Alat Bor & Personil Trip 2.00 6,000,000 12,000,000
1.2 Pembersihan Lokasi, Pembuatan Bak Sirkulasi Sumur Ls 1.00 3,000,000 3,000,000
Bor dan Pemasangan Rig Mesin Bor
SUB TOTAL I 15,000,000
II PEKERJAAN PEMBORAN
2.1 Pemboran Lubang Awal Dia. Ø 8" m 120.00 750,000 90,000,000
2.2 Diskripsi contoh cutting bor (pemerian litologi) m 120.00 20,000 2,400,000
2.1 Pembesaran Lubang (Reaming) Dia. Ø 8" ke 12" m 120.00 550,000 66,000,000
2.3 Pembersihan Sumur (Well Development)
a. Sirkulasi Air (Water circulation) Jam 20.00 75,000 1,500,000
b. Kompresor (Air Jetting) Jam 12.00 500,000 6,000,000
2.4 Pemasangan Pipa Sumur Dia. 6" Smur 1.00 1,500,000 1,500,000
2.5 Pengisian Gravel Pack m³ 6.00 75,000 450,000
2.6 Pemasangan Pompa & Panel Sumur Unit 1.00 1,000,000 1,000,000
2.7 Pekerjaan Cementing dan Flooring
a. Semen Grouting Bag. Atas Dinding Sumur Lokasi 1.00 750,000 750,000
b. Semen Lantai Sumur (Flooring) Lokasi 1.00 350,000 350,000
2.8 Pemompaan Uji meliputi :
a. Uji Debit Tetap (Continue Drawdown Test) Jam 48.00 70,000 3,360,000
b. Uji Pemulihan (Recovery Test) Jam 12.00 60,000 720,000
2.9 Pengambilan Contoh dan Analisa
Kualitas Air Contoh 2.00 1,600,000 3,200,000
SUB TOTAL II 177,230,000
III PENGADAAN BAHAN DAN MATERIAL
3.1 Pengadaan Pipa Jambang PVC S.10 - Dia. 6" m' 42.00 465,000 19,530,000
3.1 Pengadaan Pipa Blank PVC S.10 - Dia. 6" m' 42.00 450,000 18,900,000
3.2 Pengadaan Pipa Screen : PVC S.10 Dia. 6" m' 36.00 700,000 25,200,000
3.3 Lem Pipa, Pen Penguat Pipa, dll. Unit 1.00 500,000 500,000
3.4 Pengadaan Bottom Plug Bh 1.00 650,000 650,000
3.5 Pengadaan & Pemasangan Tutup Sumur Dia. 6" Bh 1.00 800,000 800,000
3.6 Pengadaan Gravel Pack M³ 6.00 400,000 2,400,000
3.7 Pompa Submersible H=100 m, Q= 2-3 lt/det Unit 1.00 28,500,000 28,500,000
3.8 Panel Pompa 3-Phase Unit 1.00 5,500,000 5,500,000
3.9 Kabel Pompa NYY-Hitam ( 1 roll) m' 100.00 28,500 2,850,000
3.10 Kabel Elektroda NYY-Putih (1 roll) m' 100.00 18,000 1,800,000
3.11 Elektroda - Water Level Swicth Control Bh 3.00 150,000 450,000
3.12 Pipa Isap / Hantar - Galvanis Med. A = 2-2,50" SNI m' 48.00 375,000 18,000,000
3.13 Labrang Baja 4 mm - Pengaman Pompa m' 50.00 10,000 500,000
3.13 Labrang Baja 4 mm - Pengaman Pompa m' 50.00 10,000 500,000
SUB TOTAL III 126,080,000
JumlahTotalL Biaya Pembuatan Sumur Bor Dalam ( I + II + III ) 318,310,000
Terbilang : Tiga ratus delapan belas juta tiga ratus sepuluh ribu rupiah

Gorontalo, 14 Nopember 2017

Bari Uya
Deep Well Expert