REKAPITULASI TOTAL

Nama Proyek : Pembangunan kandang ayam close house 3 lantai

JUMLAH HARGA
NO URAIAN
(Rp)
A PEKERJAAN PENDAHULUAN INSTALASI AIR + TANGKI AIR 657,350,000.00

B PEKERJAAN TANAH PONDASI LANTAI DAN DINDING DRAINASE 1,170,377,284.00

C PEKERJAAN KONSTRUKSI BAJA 922,838,720.00

D PEKERJAAN ATAP DAN AKSESORIS 555,425,000.00

E PEKERJAAN PINTU DAN TANGGA 60,000,000.00


F PEKERJAAN DAN PEMASANGAN ALAT KANDANG 1,534,009,050.00

A JUMLAH HARGA PEKERJAAN 4,900,000,054.00

B HASIL TOTAL DIBULATKAN 4,900,000,000,000.00

TOTAL 4,900,000,000,000.00
Terbilang : Empat Miliar Sembilan Ratus Juta Rupiah

Pandeglang, April 2021

KONTRAKTOR KANDANG AYAM CLOSE HOUSE

HJ FURKON
Direktur
RENCANA BIAYA : Pembangunan kandang ayam close house 3 lantai
DANA/TH.ANGGARAN : Cadasari
LOKASI : BANTEN / Pandeglang

KODE HARGA SATUAN JUMLAH


NO. URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.

A PEKERJAAN PENDAHULUAN
1 Pekerjaan pengukuran dan bouwplank - 1.00 ls 2,750,000.00 2,750,000.00
2 Biaya Operasional Listrik dan Air Kerja - 3.00 bula 22,500,000.00 67,500,000.00
3 Mobilisasi dan Demobilisasi - 2.00 ls 9,500,000.00 19,000,000.00
4 Gudang dan Barak 3 x 9 M - 23.00 ls 700,000.00 16,100,000.00
5 Pemasangan Tiang Listrik - 6.00 ls 2,000,000.00 12,000,000.00
5 Tiang Listrik 12M PLN - 6.00 ls
12,000,000.00 72,000,000.00
5 CUMMINS Generator Set Silent Type - 1.00 ls 374,000,000.00 374,000,000.00
5 Dudukan gengset - 1.00 ls 50,000,000.00 50,000,000.00
5 Biaya Penyelenggaraan K3 - 1.00 ls 12,000,000.00 12,000,000.00
6 Instalasi air dan tangki air - 1.00 ls 32,000,000.00 32,000,000.00
657,350,000.00

B PEKERJAAN Tanah , Pondasi , Lantai dan


I PEKERJAAN PERSIAPAN
1 Pek. Pasangan Bowplank Kayu Meranti Jambi 24.00 m¹ 71,000.00 1,704,000.00
2 Pekerjaan Drainase 1440.00 m² 150,000.00 216,000,000.00

II PEKERJAAN TANAH & PONDASI


1 Pekerjaan Perapihan Lahan - 1.00 ls 650,000.00 650,000.00
2 Galian Tanah Keras u/ Pondasi 60.74 m³ 160,000.00 9,718,400.00
3 Pekerjaan Pembesian Besi D12, Rd 8 - 1802.6 KG 13,500.00 24,335,100.00
4 Pekerjaan Pengecoran K-175 - 16.00 m³ 850,000.00 13,600,000.00
5 Pek. Pondasi Plat Beton Setempat 160x60 cm, 0.00 m³ 5,104,500.00 -
6 Pas. Pondasi Batu Kali 1:5 12.64 m³ 871,500.00 11,015,760.00

III PEK. BETON BERTULANG


1 Pek. Kolom Beton 15/20 12.00 m³ 560,000.00 6,720,000.00
2 Pek. Sloof 15/20 12.00 m³ 550,000.00 6,600,000.00
3 Pek. Ring Balok 15/20 12.00 m³ 470,000.00 5,640,000.00
4 Pek. Bekisting Multiplek 106.00 m² 120,000.00 12,720,000.00
5 Pek. Cakar Ayam 60 x 60 x 160 - 66.00 ls 450,000.00 29,700,000.00
6 Pekerjaan Pengecoran K-175 - 8.20 m³ 750,000.00 6,150,000.00

IV PEKERJAAN LANTAI BETON Lt. 1


1 Lantai Kerja Bawah Pondasi Plat Beton SNI G.04 120.08 m² 58,300.00 7,000,664.00
2 Wiremess 5mm - 147.00 m² 310,000.00 45,570,000.00
3 Pekerjaan Pengecoran K-175 - 120.00 m³ 750,000.00 90,000,000.00
4 Pek.Selasar T.10cm X L 100cm (K150) Behel - 120.08 m² 200,000.00 24,016,000.00

V PEKERJAAN LANTAI BETON Lt. 2


1 Bondex T.1,2mm - 120.08 m² 71,000.00 8,525,680.00
2 Wiremess 6mm - 388.00 m² 580,000.00 225,040,000.00

VI PEKERJAAN LANTAI BETON Lt. 3


1 Bondex T.1,2mm - 120.08 m² 71,000.00 8,525,680.00
2 Wiremess 6mm - 388.00 m² 580,000.00 225,040,000.00

VII PEKERJAAN DINDING lt 1 , 2 & 3

1 Pas. Bata Hebel uk.10x20x60 cm A.4.4.1.26. 360.00 m² 149,600.00 53,856,000.00


2 Pek. Plesteran Biasa 1:5 + Acian Dinding SNI 2837 - 6.5 120.00 m² 76,000.00 9,120,000.00
3 Pek. Rangka Dinding Hollo 4x4cm .T.1,2mm - 247.00 m² 140,000.00 34,580,000.00
4 Pek. Penutup Dinding (Zincalum T.0,45mm) - 247.00 m2 150,000.00 37,050,000.00
5 Penutup Dinding Bagian Luar Terpal Kain - 500.00 m² 115,000.00 57,500,000.00

1,170,377,284.00
C PEKERJAAN KONSTRUKSI BAJA
1 Pas. Angkur Ø 16 mm - 264.00 bh 29,000.00 7,656,000.00
2 Pas. Baut Mur Ø 16 mm - 1120.00 bh 5,100.00 5,712,000.00
3 Pek. Base Plate 6mm 10 x 10 - 396.00 bh 55,000.00 21,780,000.00
4 Pek. Base Plate 8mm 20 x 20 - 66.00 bh 290,000.00 19,140,000.00
5 Pek. Base Plate 8mm 8 x 35 - 88.00 bh 280,000.00 24,640,000.00
6 Pek. Kolom WF 150.75.5.7 - 5075.00 kg 18,000.00 91,350,000.00
7 Pek. Span WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
8 Pek. Gelagar Antar Kolom WF 150 - 3999.00 kg 18,000.00 71,982,000.00
9 Pek. Balok induk lantai 2 WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
10 Pek. Balok induk lantai 3 WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
11 Pek. Balok anak 2 = 6 jalur IWF 150 - 6730.00 kg 18,000.00 121,140,000.00
12 Pek. Gording Rangka CNP 100 - 398.00 bh 210,000.00 83,580,000.00
13 Pas. Baut Mur Ø 2 mm P 4cm - 3471.60 bh 4,200.00 14,580,720.00
14 PLAT JOIN - -
15 Plat 8mm 20 x 20 - 66.00 bh 200,000.00 13,200,000.00
16 Plat 8mm 8 x 35 - 88.00 bh 190,000.00 16,720,000.00
17 Plat 8mm 8 x 25 - 504.00 bh 120,000.00 60,480,000.00
18 Plat 8mm 8 x 50 - 44.00 bh 180,000.00 7,920,000.00
19 Pek. Ikatan Angin - 1200.00 kg 16,000.00 19,200,000.00
20 Voute - 960.00 kg 16,000.00 15,360,000.00
21 Pek. Trektank - 788.00 kg 19,000.00 14,972,000.00
22 Kawat Ram T.120 510.00 m 35,000.00 17,850,000.00
23 Zincromate Kanzai - 40.00 kgl 550,000.00 22,000,000.00

922,838,720.00

PEKERJAAN Atap dan Aksesoris


PEKERJAAN Atap
1 Pemasangan Atap Zincalum A.4.5.2.40 1880.00 m² 75,500.00 141,940,000.00
2 pemasangan Tutup Nok Atas L.60cm P.128m 129.00 m² 120,000.00 15,480,000.00
3 pemasangan tusukan angin12mm 336.00 bh 40,000.00 13,440,000.00
4 pemasangan Galvalum 03 400.00 m¹ 40,000.00 16,000,000.00
pemasangan anti gempa 40.00 bh

5 250,000.00 10,000,000.00
pemasangan ampling 25.00 bh

6 250,000.00 6,250,000.00

PEKERJAAN PLAFON
1 Alumunium Foil & Glasswool+ Rangka Hollow - 1440.00 m² 49,500.00 71,280,000.00
2 Alumunium Foil & Glasswool+ Rangka Hollow - 1440.00 m² 49,500.00 71,280,000.00

PEKERJAAN PLAFON GANTUNG HOLLOW


1 hollow 2mm 810 x 6 88.00 bh 280,000.00 24,640,000.00
1 hollow 1,5 m 40 x 40 315.00 bh 115,000.00 36,225,000.00
1 hollow 40 x 40 dudukan terpal 252.00 bh 95,000.00 23,940,000.00
1 hollow 30 x 30 336.00 bh 55,000.00 18,480,000.00
1 hollow 3 x 3 dudukan kawat harmonika 252.00 bh 55,000.00 13,860,000.00
1 kawat harmonika 504.00 m 60,000.00 30,240,000.00
1 plat strip p 300 756.00 bh 7,500.00 5,670,000.00
1 terpal 7.00 roll 1,800,000.00 12,600,000.00
1 metal seal galvalum 630.00 m 70,000.00 44,100,000.00

555,425,000.00

PEKERJAAN Pintu dan Tangga


1 PEKERJAAN PINTU
Pas. Kusen Pintu frame plat 2mm daun plat - 8.00 BH 1,500,000.00 12,000,000.00

PEKERJAAN TANGGA
2
Tangga frame unp 5 double , plat gordes - 5.00 BH 12,000,000.00 60,000,000.00
72,000,000.00
C PERALATAN KANDANG AYAM

1 Cone Fan 50" - 24 unit NEWLINE 1.00 LS 389,759,400.00 389,759,400.00


1 Nipple watering system - 4 line NEWLINE 1.00 LS 233,637,350.00 233,637,350.00
1 Pan feeding system - 3 line NEWLINE 1.00 LS 418,799,050.00 418,799,050.00
1 Cooling pad ( 150 pcs + talang PVC ) NEWLINE 1.00 LS 183,586,250.00 183,586,250.00
1 Curtain system - Type A8 NEWLINE 1.00 LS 90,395,950.00 90,395,950.00
1 Super Saver Heater - 6 unit NEWLINE 1.00 LS 81,290,550.00 81,290,550.00
1 Support lokal dan aksesoris Lokal 1.00 LS 98,540,500.00 98,540,500.00
1 Pengiriman dan Pemasangan 1.00 LS 38,000,000.00 38,000,000.00
1,534,009,050.00