JUMLAH HARGA
NO URAIAN
(Rp)
A PEKERJAAN PENDAHULUAN INSTALASI AIR + TANGKI AIR 657,350,000.00
TOTAL 4,900,000,000,000.00
Terbilang : Empat Miliar Sembilan Ratus Juta Rupiah
HJ FURKON
Direktur
RENCANA BIAYA : Pembangunan kandang ayam close house 3 lantai
DANA/TH.ANGGARAN : Cadasari
LOKASI : BANTEN / Pandeglang
A PEKERJAAN PENDAHULUAN
1 Pekerjaan pengukuran dan bouwplank - 1.00 ls 2,750,000.00 2,750,000.00
2 Biaya Operasional Listrik dan Air Kerja - 3.00 bula 22,500,000.00 67,500,000.00
3 Mobilisasi dan Demobilisasi - 2.00 ls 9,500,000.00 19,000,000.00
4 Gudang dan Barak 3 x 9 M - 23.00 ls 700,000.00 16,100,000.00
5 Pemasangan Tiang Listrik - 6.00 ls 2,000,000.00 12,000,000.00
5 Tiang Listrik 12M PLN - 6.00 ls
12,000,000.00 72,000,000.00
5 CUMMINS Generator Set Silent Type - 1.00 ls 374,000,000.00 374,000,000.00
5 Dudukan gengset - 1.00 ls 50,000,000.00 50,000,000.00
5 Biaya Penyelenggaraan K3 - 1.00 ls 12,000,000.00 12,000,000.00
6 Instalasi air dan tangki air - 1.00 ls 32,000,000.00 32,000,000.00
657,350,000.00
1,170,377,284.00
C PEKERJAAN KONSTRUKSI BAJA
1 Pas. Angkur Ø 16 mm - 264.00 bh 29,000.00 7,656,000.00
2 Pas. Baut Mur Ø 16 mm - 1120.00 bh 5,100.00 5,712,000.00
3 Pek. Base Plate 6mm 10 x 10 - 396.00 bh 55,000.00 21,780,000.00
4 Pek. Base Plate 8mm 20 x 20 - 66.00 bh 290,000.00 19,140,000.00
5 Pek. Base Plate 8mm 8 x 35 - 88.00 bh 280,000.00 24,640,000.00
6 Pek. Kolom WF 150.75.5.7 - 5075.00 kg 18,000.00 91,350,000.00
7 Pek. Span WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
8 Pek. Gelagar Antar Kolom WF 150 - 3999.00 kg 18,000.00 71,982,000.00
9 Pek. Balok induk lantai 2 WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
10 Pek. Balok induk lantai 3 WF 150.75.5.7 - 5208.00 kg 18,000.00 93,744,000.00
11 Pek. Balok anak 2 = 6 jalur IWF 150 - 6730.00 kg 18,000.00 121,140,000.00
12 Pek. Gording Rangka CNP 100 - 398.00 bh 210,000.00 83,580,000.00
13 Pas. Baut Mur Ø 2 mm P 4cm - 3471.60 bh 4,200.00 14,580,720.00
14 PLAT JOIN - -
15 Plat 8mm 20 x 20 - 66.00 bh 200,000.00 13,200,000.00
16 Plat 8mm 8 x 35 - 88.00 bh 190,000.00 16,720,000.00
17 Plat 8mm 8 x 25 - 504.00 bh 120,000.00 60,480,000.00
18 Plat 8mm 8 x 50 - 44.00 bh 180,000.00 7,920,000.00
19 Pek. Ikatan Angin - 1200.00 kg 16,000.00 19,200,000.00
20 Voute - 960.00 kg 16,000.00 15,360,000.00
21 Pek. Trektank - 788.00 kg 19,000.00 14,972,000.00
22 Kawat Ram T.120 510.00 m 35,000.00 17,850,000.00
23 Zincromate Kanzai - 40.00 kgl 550,000.00 22,000,000.00
922,838,720.00
5 250,000.00 10,000,000.00
pemasangan ampling 25.00 bh
6 250,000.00 6,250,000.00
PEKERJAAN PLAFON
1 Alumunium Foil & Glasswool+ Rangka Hollow - 1440.00 m² 49,500.00 71,280,000.00
2 Alumunium Foil & Glasswool+ Rangka Hollow - 1440.00 m² 49,500.00 71,280,000.00
555,425,000.00
PEKERJAAN TANGGA
2
Tangga frame unp 5 double , plat gordes - 5.00 BH 12,000,000.00 60,000,000.00
72,000,000.00
C PERALATAN KANDANG AYAM