Anda di halaman 1dari 4

DAFTAR KUANTITAS DAN HARGA SATUAN (MC.

0)
KEGIATAN : BALAI PRASARANA PERMUKIMAN WILAYAH NTB
PEKERJAAN : PENATAAN KAWASAN PENGEMBANGAN DESTINASI WISATA KWS. MANDALIKA KAB. LOMBOK TENGAH
LOKASI : KAWASAN MANDALIKA KEC. PUJUT KAB. LOMBOK TENGAH
TAHUN ANGGARAN : 2019

Kode Volume Volume Tambah/Kurang Harga Satuan Total Harga Total Harga Tambah/Kurang Keterangan
No. Uraian Sat Keterangan
Analisa Kontrak MC.0 Tambah Kurang Kontrak Kontrak Mc.0 Tambah Kurang (Harga Timpang)
1 SISTEM MANAJEMEN K3 187,875,000 187,875,000

A Alat Pelindung Diri 5,600,000 5,600,000 TETAP


1 Topi Peindung/Sefety Helmet Buah - 25.00 25.00 - - 65,000 1,625,000 1,625,000.00 - - TETAP TIMPANG
2 Masker Buah - 50.00 50.00 - - 2,000 100,000 100,000.00 - - TETAP TIMPANG
3 Sarung Tangan Buah - 25.00 25.00 - - 5,000 125,000 125,000.00 - - TETAP TIDAK TIMPANG
4 Sepatu Keselamatan Buah - 25.00 25.00 - - 100,000 2,500,000 2,500,000.00 - - TETAP TIMPANG
5 Rompi Keselamatan Buah - 25.00 25.00 - - 50,000 1,250,000 1,250,000.00 - - TETAP TIMPANG

B Asuransi dan Perizinan 94,650,000 94,650,000


BPJS ketenaga kerjaan dan kesehatan kerja (6 Bulan) OB - 25.00 25.00 - - 631,000 94,650,000 94,650,000.00 - - TETAP TIMPANG

C Personil K3 82,500,000 82,500,000


Petugas K3 (6 Bulan) OB - 1.00 1.00 - - 13,750,000 82,500,000 82,500,000.00 - - TETAP TIMPANG

D Fasilitas Sarana Kesehatan 3,000,000 3,000,000


Peralatan P3K (Kotak P3K, Tandu, Obat luka, Perban) OB - 1.00 1.00 - - 3,000,000 3,000,000 3,000,000.00 - - TETAP TIMPANG

E Rambu - Rambu 1,500,000 1,500,000


Rambu Petunjuk Buah - 5.00 5.00 - - 100,000 500,000 500,000.00 - - TETAP TIMPANG
Rambu Larangan Buah - 5.00 5.00 - - 100,000 500,000 500,000.00 - - TETAP TIMPANG
Rambu Peringatan Buah - 5.00 5.00 - - 100,000 500,000 500,000.00 - - TETAP TIMPANG

F Penyiapan RK3K 625,000 625,000


Pembuatan Manual, prosedur, Instruksi Kerja, Ijin Kerja. LS - 1.00 1.00 - - 500,000 500,000 500,000.00 - - TETAP TIDAK TIMPANG
Pembuatan Kartu Identitas Pekerjaan (KIP) Buah - 25.00 25.00 - - 5,000 125,000 125,000.00 - - TETAP TIDAK TIMPANG

2 PEKERJAAN SEGMEN A 532,946,805


2.1 PEKERJAAN PERSIAPAN SEGMEN A 6,000,000
1 Papan Nama Proyek ls Ls 2.00 - 2.00 500,000 1,000,000 - - - BERKURANG TIDAK TIMPANG
2 Pengukuran lapangan ls Ls 1.00 - 1.00 5,000,000 5,000,000 - - - BERKURANG TIDAK TIMPANG

2.2 PEKERJAAN PEDESTRIAN SEGMEN A 94,098,744


1 Pemasangan Batu Alam Tempel m2 LS 8 267.29 - 267.29 255,725.50 68,352,971 - - - BERKURANG TIDAK TIMPANG
2 Pembesihan pedestrian m2 A. 2.2.1.9 1,427.85 - 1,427.85 15,881.50 22,676,400 - - - BERKURANG TIDAK TIMPANG
3 Cor beton dilatasi m3 A.4.1.1.6 2.81 - 2.81 1,093,081.72 3,069,373 - - - BERKURANG TIDAK TIMPANG

2.3 PEKERJAAN JEMBATAN SEGMEN A 103,710,706


1 Rabat beton K 250 m3 A.4.1.1.8 16.85 - 16.85 1,133,369.75 19,092,293 - - - BERKURANG TIDAK TIMPANG
2 Pemasangan Keramik Granik 20 x 60 m2 A.4.4.3.12 130.20 - 130.20 649,911.00 84,618,412 - - - BERKURANG TIDAK TIMPANG

2.4 PEKERJAAN TOILET SEGMEN A 329,137,354


A Pek. Persiapan
1 Pek. Pengukuran dan Pemasangan Bouplank m2 A. 2.2.1.4 54.80 - - 54.80 460,026.45 25,209,449 - - - BERKURANG TIDAK TIMPANG

B Pek Tanah dan Pasir


1 galian tanah m3 A.2.3.1.1 30.85 - - 30.85 72,823.75 2,246,321 - - - BERKURANG TIDAK TIMPANG
2 urugan pasir m3 A.2.3.1.11 18.51 - - 18.51 180,929.50 3,348,571 - - - BERKURANG TIDAK TIMPANG
3 urugan kembali tanah pilihan m3 A.2.3.1.9 54.80 - - 54.80 52,957.50 2,902,071 - - - BERKURANG TIDAK TIMPANG
4 pemadatan tanah m3 A.2.3.1.10 54.80 - - 54.80 56,982.50 3,122,641 - - - BERKURANG TIDAK TIMPANG

C Pek. Pondasi
1 Lantai Pondasi m3 A.4.1.1.7 2.06 - - 2.06 1,118,581.00 2,300,250 - - - BERKURANG TIDAK TIMPANG
2 Pas. Batu Kosong m3 A.3.2.1.9 8.23 - - 8.23 472,601.70 3,887,433 - - - BERKURANG TIDAK TIMPANG
3 Pas. Batu Kali m3 A.3.2.1.3 18.51 - - 18.51 792,292.50 14,663,433 - - - BERKURANG TIDAK TIMPANG

D Pek. Beton
1 sloof 15/20 K=200 m3 A.4.1.1.29 1.93 - - 1.93 6,471,402.35 12,476,055 - - - BERKURANG TIDAK TIMPANG
2 kolom praktis 13x13 m3 A.4.1.1.30.f 0.63 - - 0.63 9,932,555.08 6,294,757 - - - BERKURANG TIDAK TIMPANG
3 ring balok 15/20 m3 A.4.1.1.31.c 1.54 - - 1.54 7,613,114.20 11,741,706 - - - BERKURANG TIDAK TIMPANG
Kode Volume Volume Tambah/Kurang Harga Satuan Total Harga Total Harga Tambah/Kurang Keterangan
No. Uraian Sat Keterangan
Analisa Kontrak MC.0 Tambah Kurang Kontrak Kontrak Mc.0 Tambah Kurang (Harga Timpang)
4 rabat lantai beton m3 A.4.1.1.5 2.74 - - 2.74 1,061,174.09 2,907,617 - - - BERKURANG TIDAK TIMPANG

E Pek. Pasangan
1 Pemasangan 1m2 dinding batako 1/2 1SP : 2PP m2 A. 4.4.1.1 12.85 - - 12.85 285,096.50 3,664,203 - - - BERKURANG TIDAK TIMPANG
2 Pemasangan 1m2 dinding batako 1/2 1SP : 5PP m2 A. 4.4.1.4 105.45 - - 105.45 259,497.50 27,362,973 - - - BERKURANG TIDAK TIMPANG
3 plesteran 1/2 m2 A.4.4.2.2 25.71 - - 25.71 64,513.62 1,658,323 - - - BERKURANG TIDAK TIMPANG
4 plesteran 1/5 m2 A.4.4.2.5 210.89 - - 210.89 58,593.42 12,356,884 - - - BERKURANG TIDAK TIMPANG
5 acian dinding Trasram m2 A.4.4.2.27 25.71 - - 25.71 35,788.00 919,931 - - - BERKURANG TIDAK TIMPANG
6 Acian Dinding pasangan m2 A.4.4.2.27 134.20 - - 134.20 35,788.00 4,802,893 - - - BERKURANG TIDAK TIMPANG

F Pek. Atap
1 rangka kuda kuda atap 6/12 m3 A.4.6.1.13 0.36 - - 0.36 24,392,805.25 8,851,661 - - - BERKURANG TIDAK TIMPANG
2 nok 6/12 m3 A.4.6.1.13 0.10 - - 0.10 24,392,805.25 2,529,046 - - - BERKURANG TIDAK TIMPANG
3 reng 3/5 m3 A.4.6.1.13 0.21 - - 0.21 24,392,805.25 5,071,264 - - - BERKURANG TIDAK TIMPANG
4 atap alang alang m2 LS 54 50.40 - - 50.40 155,266.51 7,825,432 - - - BERKURANG TIDAK TIMPANG
5 listplank m3 A.4.6.1.22 0.18 - - 0.18 223,887.75 41,016 - - - BERKURANG TIDAK TIMPANG
6 plafond kalsiboard m2 A.4.5.1.5 51.41 - - 51.41 60,892.50 3,130,483 - - - BERKURANG TIDAK TIMPANG

G Pek. Penutup Lantai


1 keramik 40x40 granit m2 A.4.4.3.11a 54.80 - - 54.80 159,206.00 8,724,489 - - - BERKURANG TIDAK TIMPANG
2 keramik dinding m2 A.4.4.3.54 11.85 - - 11.85 263,407.50 3,121,379 - - - BERKURANG TIDAK TIMPANG

H Pek. Finishing Cat


1 cat dinding m2 A.4.7.1.10 47.93 - - 47.93 60,774.63 2,912,928 - - - BERKURANG TIDAK TIMPANG
2 cat kusen m2 A.4.7.1.4 0.29 - - 0.29 58,630.45 16,768 - - - BERKURANG TIDAK TIMPANG
3 cat kayu m2 A.4.7.1.4 203.40 - - 203.40 58,630.45 11,925,434 - - - BERKURANG TIDAK TIMPANG

I Pek. Elektrikal
1 Lampu bh LS 15.00 - - 15.00 80,000.00 1,200,000 - - - BERKURANG TIDAK TIMPANG
2 Saklar Tunggal bh LS 5.00 - - 5.00 25,000.00 125,000 - - - BERKURANG TIDAK TIMPANG

J Pek. Kusen
1 Pek. Pasangan kusen kayu m3 A.4.6.1.1 0.26 - - 0.26 22,159,608.75 5,816,897 - - - BERKURANG TIDAK TIMPANG
2 Pek. Pas daun pintu panil m2 A.4.6.1.5 11.76 - - 11.76 1,160,120.00 13,643,011 - - - BERKURANG TIDAK TIMPANG

K Pek. Pasangan Pengunci


1 Kunci bh A.4.6.2.2 7.00 - - 7.00 211,865.65 1,483,060 - - - BERKURANG TIDAK TIMPANG
2 Engsel Pintu bh A.4.6.2.5 21.00 - - 21.00 38,784.90 814,483 - - - BERKURANG TIDAK TIMPANG

L Pek. Mechanical
1 Septictank unit Ls 1.00 - - 1.00 2,500,000.00 2,500,000 - - - BERKURANG TIDAK TIMPANG
2 Tower Air + Rangka Baja unit Ls 1.00 - - 1.00 20,000,000.00 20,000,000 - - - BERKURANG TIDAK TIMPANG
3 Pipa PVC AW 3/4" m A.5.1.1.26 35.00 - - 35.00 25,974.59 909,111 - - - BERKURANG TIDAK TIMPANG
4 Pipa PVC AW 1/2" m A.5.1.1.25 55.00 - - 55.00 22,409.59 1,232,527 - - - BERKURANG TIDAK TIMPANG
5 Pipa PVC AW 3" m A.5.1.1.31 40.00 - - 40.00 281,233.77 11,249,351 - - - BERKURANG TIDAK TIMPANG
6 Pipa PVC AW 4" m A.5.1.1.32 40.00 - - 40.00 296,206.77 11,848,271 - - - BERKURANG TIDAK TIMPANG
7 Urinoir unit A.5.1.1.4 3.00 - - 3.00 2,504,872.50 7,514,618 - - - BERKURANG TIDAK TIMPANG
8 Closed duduk unit A.5.1.1.2a 6.00 - - 6.00 3,875,787.50 23,254,725 - - - BERKURANG TIDAK TIMPANG
9 Floor Drain unit A.5.1.1.14 11.00 - - 11.00 32,695.65 359,652 - - - BERKURANG TIDAK TIMPANG
10 Kran air dia. 1/2" bh A.5.1.1.19 6.00 - - 6.00 124,158.03 744,948 - - - BERKURANG TIDAK TIMPANG
11 Shower unit A.5.1.1.6 2.00 - - 2.00 4,839,625.50 9,679,251 - - - BERKURANG TIDAK TIMPANG
12 Kaca Cermin bh Ls 5.00 - - 5.00 250,000.00 1,250,000 - - - BERKURANG TIDAK TIMPANG
13 Wastafel unit A.5.1.1.5 6.00 - - 6.00 3,249,506.70 19,497,040 - - - BERKURANG TIDAK TIMPANG

3 PEKERJAAN SEGMEN B 10,072,053,476 11,263,274,990


3.1 PEKERJAAN PERSIAPAN SEGMEN B 16,500,000 16,500,000
1 Papan Nama Proyek ls Ls 1.00 1.00 - - 500,000 500,000 500,000.00 - - TETAP TIDAK TIMPANG
2 Sewa Direksi Keet ls Ls 1.00 1.00 - - 6,000,000 6,000,000 6,000,000.00 - - TETAP TIDAK TIMPANG
3 Pengukuran lapangan ls Ls 1.00 1.00 - - 10,000,000 10,000,000 10,000,000.00 - - TETAP TIDAK TIMPANG
3.2 PEDESTRIAN JALAN PARIWISATA KUTA SEGMEN B 4,993,537,382 6,691,350,717
1 Pek. Pembersihan site m2 A. 2.2.1.9 10890 9490 1,400.00 15,881.50 172,949,535 150,715,435.00 22,234,100.00 BERKURANG TIDAK TIMPANG
2 Pek. Galian Tanah m3 A.2.3.1.1 243.936 423.09 179.15 72,823.75 17,764,334 30,811,000.39 13,046,666.11 BERTAMBAH TIDAK TIMPANG
3 Pek. Normalisasi Saluran Drainase m3 A.2.3.1.1 1806.00 72.00 1,734.00 72,823.75 131,519,693 5,243,310.00 126,276,382.50 BERKURANG TIDAK TIMPANG
4 Pek. Urugan Tanah m3 A.2.3.1.14 1265.06 1314.54 49.49 136,878.75 173,159,147 179,932,865.78 6,773,718.70 BERTAMBAH TIDAK TIMPANG
5 Pek. Urugan Tanah Subur m3 A.2.3.1.15 381.15 381.15 178,278.75 67,950,946 67,950,945.56 TETAP TIMPANG
5.1 Pek. Urugan Tanah Subur (HARGA HPS) m3 A.2.3.1.15 0.00 57.71 57.71 146,518.63 0 8,455,589.85 8,455,589.85 BERTAMBAH TIMPANG
6 Pek. Pasir Urug m3 A.2.3.1.11 0.00 32.85 180,929.50 5,944,348.26 5,944,348.26 BERTAMBAH TIDAK TIMPANG
6 Pek. Rabatan K-250 m3 A.4.1.1.8 181.5 386.57 205.07 1,133,369.75 205,706,610 438,126,744.26 232,420,134.63 BERTAMBAH TIDAK TIMPANG
7 Pek. Beton K.250 Pondasi Tiang Lampu m3 A.4.1.1.8 26.14 26.14 1,133,369.75 29,621,752 29,621,751.79 TETAP TIDAK TIMPANG
Kode Volume Volume Tambah/Kurang Harga Satuan Total Harga Total Harga Tambah/Kurang Keterangan
No. Uraian Sat Keterangan
Analisa Kontrak MC.0 Tambah Kurang Kontrak Kontrak Mc.0 Tambah Kurang (Harga Timpang)
8 Pek. Pembesian Pondasi Tiang Lampu kg A.4.1.1.17.a 1,268.83 2,646.17 1,377.35 23,496.46 29,812,950 62,175,702.75 32,362,752.94 BERTAMBAH TIDAK TIMPANG
9 Pek. Begisting Pondasi Tiang Lampu m2 A.4.1.1.22 58.08 58.08 156,475.33 0 9,088,087.17 9,088,087.17 BERTAMBAH TIDAK TIMPANG
10 Pek. Begisting Ponadi Bollard m2 A.4.1.1.22
11 Pek. Beton K.250 Kolom praktis m3 A.4.1.1.8 27.22 13.01 14.21 1,133,369.75 30,851,746 14,745,049.78 16,106,695.78 BERKURANG TIDAK TIMPANG
12 Pek. Pembesian Kolom Praktis kg A.4.1.1.17.a 6,155.63 2,719.29 3,436.34 23,496.46 144,635,581 63,893,653.00 80,741,927.99 BERKURANG TIDAK TIMPANG
13 Pek. Bekisting Kolom Praktis m2 A.4.1.1.22 435.54 68.99 366.55 156,475.33 68,151,275 10,795,545.97 57,355,728.65 BERKURANG TIDAK TIMPANG
14 Pek. Pas. Keramik Granito 20cm x 20cm m2 LS 7.a 667.92 0 667.92 1,163,248.00 776,956,604 - 776,956,604.16 BERKURANG TIMPANG
15 Pek. Pas. Keramik Granito 40cm x 40cm m2 LS 7.b 813.12 0 813.12 493,373.00 401,171,454 - 401,171,453.76 BERKURANG TIDAK TIMPANG
16 Pek. Pas. Paving Block m2 LS 2 2541 247.05 2,293.95 278,166.60 706,821,331 68,722,310.28 638,099,020.32 BERKURANG TIDAK TIMPANG
17 Pas. Keramik Aksesbilitas m2 LS 7 1089 1202.58 113.58 566,513.00 616,932,657 681,277,203.54 64,344,546.54 BERTAMBAH TIDAK TIMPANG
18 Pas. Kanstin Type s m LS 57a 3630 230.2 3,399.80 133,458.08 484,452,830 30,722,050.02 453,730,780.38 BERKURANG TIDAK TIMPANG
19 Pas. Kanstin Type I m LS57 0 3362 3,362.00 134,277.45 451,440,786.90 451,440,786.90 TIDAK TIMPANG
20 Pek. Pengecatan Kanstin m2 A.4.7.1.10 3811.5 1595.772 2,215.73 60,774.63 231,642,502 96,982,452.86 134,660,049.38 BERKURANG TIDAK TIMPANG
21 Pek. Pas. Trasraam 1/2 Bata m2 A. 4.4.1.8 2377.14 4141.44 1,764.30 132,363.85 314,647,369 548,176,942.94 233,529,574.31 BERTAMBAH TIDAK TIMPANG
22 Pek. Plesteran Trasraam m2 A.4.4.2.3 1252.35 1378.42 126.07 61,652.88 77,210,984 84,983,562.85 7,772,578.58 BERTAMBAH TIDAK TIMPANG
23 Pek. Acian m2 A.4.4.2.27 1252.35 1378.42 126.07 35,788.00 44,819,102 49,330,894.96 4,511,793.16 BERTAMBAH TIDAK TIMPANG
24 Pek. Gebalan Rumput m2 LS 33 2541 2194.3 346.70 34,918.60 88,728,163 76,621,883.98 12,106,278.62 BERKURANG TIDAK TIMPANG
25 Pek. Pas. Koral Sikat m2 LS 4 1197.9 0 1,197.90 148,619.10 178,030,820 - 178,030,819.89 BERKURANG TIDAK TIMPANG
26 Pek. Pas Granito 60 cm x 60 cm (ITEM BARU) m2 LS 7.c 3316.5 3,316.50 498,548.00 1,653,434,442.00 1,653,434,442.00 BERTAMBAH TIDAK TIMPANG
27 Pek. Pas Granito 30 cm x 60 cm (ITEM BARU) m2 LS 7.d 1989.9 1,989.90 498,548.00 992,060,665.20 992,060,665.20 BERTAMBAH TIDAK TIMPANG
28 Pek. Intalasi Kabel Lampu Taman (ITEM BARU) m' LS.66 3965.4 3,965.40 119,352.75 473,281,394.85 473,281,394.85 BERTAMBAH TIDAK TIMPANG
32 Pek. KWH 3500 VA (6 Unit) ,Box Panel dan SLO (ITEM BARU) unit Ls 1 1.00 30500000 30,500,000.00 30,500,000.00 BERTAMBAH TIDAK TIMPANG
33 Pek. Pipa PVC D Ø 4" (ITEM BARU) m' LS 67 1811.73 1,811.73 70274.89 127,319,360.71 127,319,360.71 BERTAMBAH TIDAK TIMPANG
34 Pek. Batu Andesit (Posisi Jalan Masuk) m2 A.4.4.3.58.b 489.6 489.60 270,963.00 132,663,484.80 132,663,484.80 BERTAMBAH TIDAK TIMPANG
35 Pek. Pipa Gi Ø 2 " (Kanopi) m' LS 41 621 621.00 170,442.94 105,845,065.74 105,845,065.74 BERTAMBAH TIDAK TIMPANG
36 Pek. Beton K. 250 ( Kanopi) m3 A.4.1.1.8 3.6 3.60 1,133,369.75 4,080,131.10 4,080,131.10 BERTAMBAH TIDAK TIMPANG
37 Pek. Batu Andesit (Kanopi) m2 A.4.4.3.58.b 10.8 10.80 270,963.00 2,926,400.40 2,926,400.40 BERTAMBAH TIDAK TIMPANG
38 Pek. Pengecatan (Kanopi) m2 A.4.7.1.12 98.2682 35,430.12 3,481,654.12 3,481,654.12 BERTAMBAH TIDAK TIMPANG
Kode Volume Volume Tambah/Kurang Harga Satuan Total Harga Total Harga Tambah/Kurang Keterangan
No. Uraian Sat Keterangan
Analisa Kontrak MC.0 Tambah Kurang Kontrak Kontrak Mc.0 Tambah Kurang (Harga Timpang)
3.3 MEDIAN JALAN PARIWISATA KUTA SEGMEN B 1,707,766,094 1,842,924,273
1 Galian Tanah m2 A.2.3.1.1 62.10 114.98 52.88 72,823.75 4,522,355 8,373,347.60 3,850,992.72 BERTAMBAH TIDAK TIMPANG
2 Urugan Tanah Subur m3 A.2.3.1.15 1,872.00 1,872.00 178,278.75 333,737,820 333,737,820.00 TETAP TIMPANG
2.1 Urugan Tanah Subur (HARGA HPS) m3 A.2.3.1.15 - 630.74 630.74 146,518.63 0 92,415,853.50 92,415,853.50 BERTAMBAH TIMPANG
3 Pasangan Bata 1/2 Bata m2 A. 4.4.1.7 1,863.00 2,682.89 819.89 138,339.25 257,726,023 371,148,990.43 113,422,967.68 BERTAMBAH TIDAK TIMPANG
4 Pek. Plesteran 1 :2 m2 A.4.4.2.3 2,691.00 2,393.20 297.80 61,652.88 165,907,900 147,547,487.46 18,360,412.62 BERKURANG TIDAK TIMPANG
5 Kolom Praktis 10/10 m3 A.4.1.1.30.f 1.98 - 1.98 9,932,555.08 19,666,459 - 19,666,459.06 BERKURANG TIDAK TIMPANG
6 Pek. Acian m2 A.4.4.2.27 2,691.00 748.44 1,942.56 35,788.00 96,305,508 26,785,170.72 69,520,337.28 BERKURANG TIDAK TIMPANG
7 Pek. Pengecatan Planter Box m2 A.4.7.1.10 2,691.00 - 2,691.00 60,774.63 163,544,529 - 163,544,529.33 BERKURANG TIDAK TIMPANG
8 Pek. Beton K.250 Kolom praktis m3 A.4.1.1.8 - 20.86 20.86 1,133,369.75 23,643,917.71 23,643,917.71 BERTAMBAH TIDAK TIMPANG
9 Pek. Pembesian Kolom Praktis kg A.4.1.1.17.a - 3,739.56 3,739.56 23,496.46 87,866,421.02 87,866,421.02 BERTAMBAH TIDAK TIMPANG
10 Pek. Bekisting Kolom Praktis m2 A.4.1.1.22 - 254.27 254.27 156,475.33 39,786,199.78 39,786,199.78 BERTAMBAH TIDAK TIMPANG
11 Pek. Batu Andesit m2 A.4.4.3.58.b 1,149.60 1,149.60 270,963.00 311,499,064.80 311,499,064.80 BERTAMBAH TIDAK TIMPANG
12 Ararea Ungu bh Ls 1,463.00 - 1,463.00 7,500.00 10,972,500 - 10,972,500.00 BERKURANG TIDAK TIMPANG
13 Areksi bh Ls 1,518.00 - 1,518.00 7,500.00 11,385,000 - 11,385,000.00 BERKURANG TIDAK TIMPANG
14 Arpah Merah/blego bh Ls 260.00 - 260.00 3,500.00 910,000 - 910,000.00 BERKURANG TIDAK TIMPANG
15 Bawang - Bawangan bh Ls 478.00 - 478.00 3,500.00 1,673,000 - 1,673,000.00 BERKURANG TIDAK TIMPANG
16 Bayam - Bayaman bh Ls 953.00 - 953.00 7,500.00 7,147,500 - 7,147,500.00 BERKURANG TIDAK TIMPANG
17 Bonsai Kuning bh Ls 588.00 - 588.00 3,500.00 2,058,000 - 2,058,000.00 BERKURANG TIDAK TIMPANG
18 Bulu Ayam Putih bh Ls 1,229.00 - 1,229.00 3,500.00 4,301,500 - 4,301,500.00 BERKURANG TIDAK TIMPANG
19 Bunga Ungu bh Ls 125.00 - 125.00 7,500.00 937,500 - 937,500.00 BERKURANG TIDAK TIMPANG
20 Daun perak bh Ls 112.00 - 112.00 3,500.00 392,000 - 392,000.00 BERKURANG TIDAK TIMPANG
21 Glori Morning bh Ls 1,735.00 - 1,735.00 7,500.00 13,012,500 - 13,012,500.00 BERKURANG TIDAK TIMPANG
22 Jasmin bh Ls 26.00 - 26.00 250,000.00 6,500,000 - 6,500,000.00 BERKURANG TIDAK TIMPANG
23 Karambosa bh Ls 510.00 4,917.00 4,407.00 7,500.00 3,825,000 36,877,500.00 33,052,500.00 BERTAMBAH TIDAK TIMPANG
24 Krokot Merah bh Ls 1,497.00 - 1,497.00 3,500.00 5,239,500 - 5,239,500.00 BERKURANG TIDAK TIMPANG
25 Krokot Putih bh Ls 272.00 - 272.00 3,500.00 952,000 - 952,000.00 BERKURANG TIDAK TIMPANG
26 Lamtana bh Ls 754.00 - 754.00 3,500.00 2,639,000 - 2,639,000.00 BERKURANG TIDAK TIMPANG
27 Melati Prancis bh Ls 274.00 - 274.00 7,500.00 2,055,000 - 2,055,000.00 BERKURANG TIDAK TIMPANG
28 Palem Botol bh Ls 35.00 - 35.00 175,000.00 6,125,000 - 6,125,000.00 BERKURANG TIDAK TIMPANG
29 Palem Ponix bh Ls 36.00 - 36.00 110,000.00 3,960,000 - 3,960,000.00 BERKURANG TIDAK TIMPANG
30 Puring Bangkok bh Ls 203.00 3,817.00 3,614.00 7,500.00 1,522,500 28,627,500.00 27,105,000.00 BERTAMBAH TIDAK TIMPANG
31 Puring merah bh Ls 256.00 - 256.00 7,500.00 1,920,000 - 1,920,000.00 BERKURANG TIDAK TIMPANG
32 Puring Nuri bh Ls 1,137.00 - 1,137.00 7,500.00 8,527,500 - 8,527,500.00 BERKURANG TIDAK TIMPANG
33 Seribu Bintang bh Ls 1,443.00 - 1,443.00 3,500.00 5,050,500 - 5,050,500.00 BERKURANG TIDAK TIMPANG
34 Pohon Tabe Buya Warna (min. H= 300 cm, Ø= 10 cm) bh Ls 665.00 280.00 385.00 850,000.00 565,250,000 238,000,000.00 327,250,000.00 BERKURANG TIDAK TIMPANG
35 Puring Ketimun (ITEM BARU) bh Ls 3,817.00 3,817.00 7,500.00 0 28,627,500.00 28,627,500.00 BERTAMBAH TIDAK TIMPANG
36 Angsoka (ITEM BARU) bh Ls 4,147.00 4,147.00 7,500.00 0 31,102,500.00 31,102,500.00 BERTAMBAH TIDAK TIMPANG
37 Ararea Kuning (ITEM BARU) bh Ls 4,918.00 4,918.00 7,500.00 0 36,885,000.00 36,885,000.00 BERTAMBAH TIDAK TIMPANG

3.4 PEKERJAAN STREET FURNITURE SEGMEN B 3,116,250,000 2,712,500,000


1 Pek. Pas. Lampu Taman bh Ls 242.00 242.00 10,000,000.00 2,420,000,000 2,420,000,000.00 TETAP TIDAK TIMPANG
2 Pek. Pas. Bollard bh Ls 121.00 13.00 108.00 3,500,000.00 423,500,000 45,500,000.00 378,000,000.00 BERKURANG TIDAK TIMPANG
3 Pek. Bangku Taman bh Ls 121.00 12.00 109.00 1,750,000.00 211,750,000 21,000,000.00 190,750,000.00 BERKURANG TIDAK TIMPANG
4 Bak Sampah bh LS 55 61.00 13.00 48.00 1,000,000.00 61,000,000 13,000,000.00 48,000,000.00 BERKURANG TIDAK TIMPANG
5 Pek. Shelter (ITEM BARU) bh LS 3.00 71,000,000.00 213,000,000.00 213,000,000.00 BERTAMBAH TIDAK TIMPANG

3.5 PEKERJAAN LAIN-LAIN SEGMEN B 238,000,000 0 Dihilangkan


1 Pemindahan Tiang Listrik PLN bh Ls 67.00 - 67.00 3,000,000.00 201,000,000 - 201,000,000.00 BERKURANG TIDAK TIMPANG
2 Pemindahan Lampu PJU bh Ls 4.00 - 4.00 2,500,000.00 10,000,000 - 10,000,000.00 BERKURANG TIDAK TIMPANG
3 Pemindahan Gardu Listrik bh Ls 2.00 - 2.00 13,500,000.00 27,000,000 - 27,000,000.00 BERKURANG TIDAK TIMPANG