2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) T.01.c 650 bh 34,913.00 22,693,450.00
TOTAL 48,629,276.00
Jumlah 1,551,464,435.20
Dibulatkan 1,706,611,000.00
KHAERUDDIN, ST
Team Leader
LAPORAN MINGGUAN KE - 1
Periode : Thursday, October 03, 2019 s/d Thursday, October 10, 2019
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 0.00% 0.49% 0.49% 7,676,661.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.00 0.00% 0.20 0.29% 0.20 0.29% 4,510,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 0.00 0.00% 87.00 0.20% 87.00 0.20% 3,037,431.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 0.00 0.00% 10.00 0.01% 10.00 0.01% 129,230.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 0.49% 0.33% 0.83% 12,855,010.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.20 0.29% 0.20 0.29% 0.40 0.58% 9,020,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 87.00 0.20% 11.00 0.02% 98.00 0.22% 3,421,474.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 10.00 0.01% 22.00 0.02% 32.00 0.03% 413,536.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 0.83% 0.18% 1.01% 15,682,687.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.40 0.58% 0.10 0.15% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 98.00 0.22% 9.00 0.02% 107.00 0.24% 3,735,691.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 32.00 0.03% 20.00 0.02% 52.00 0.04% 671,996.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.01% 0.02% 1.03% 15,966,993.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 107.00 0.24% - 0.00% 107.00 0.24% 3,735,691.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 52.00 0.04% 22.00 0.02% 74.00 0.06% 956,302.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.03% 0.05% 1.08% 16,767,282.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 107.00 0.24% 17.00 0.04% 124.00 0.28% 4,329,212.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 74.00 0.06% 16.00 0.01% 90.00 0.07% 1,163,070.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.08% 0.02% 1.10% 17,025,742.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 124.00 0.28% - 0.00% 124.00 0.28% 4,329,212.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 90.00 0.07% 20.00 0.02% 110.00 0.09% 1,421,530.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.10% 0.06% 1.15% 17,885,435.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 124.00 0.28% 15.00 0.03% 139.00 0.31% 4,852,907.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 110.00 0.09% 26.00 0.02% 136.00 0.11% 1,757,528.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.15% 0.06% 1.21% 18,768,473.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 139.00 0.31% 19.00 0.04% 158.00 0.36% 5,516,254.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 136.00 0.11% 17.00 0.01% 153.00 0.13% 1,977,219.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.21% 0.18% 1.39% 21,625,919.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 158.00 0.36% 70.00 0.16% 228.00 0.51% 7,960,164.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 153.00 0.13% 32.00 0.03% 185.00 0.15% 2,390,755.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.39% 0.14% 1.53% 23,759,259.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 228.00 0.51% 50.00 0.11% 278.00 0.63% 9,705,814.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 185.00 0.15% 30.00 0.02% 215.00 0.18% 2,778,445.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.53% 0.87% 2.40% 37,263,815.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% - 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 278.00 0.63% 372.00 0.84% 650.00 1.46% 22,693,450.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 215.00 0.18% 40.00 0.03% 255.00 0.21% 3,295,365.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 2.40% 0.73% 3.13% 48,629,276.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% 0.50 0.73% 1.00 1.45% 22,550,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 650.00 1.46% - 0.00% 650.00 1.46% 22,693,450.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 255.00 0.21% 7.00 0.01% 262.00 0.22% 3,385,826.00
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 0.00% 1.03% 1.03% 15,966,993.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.00 0.00% 0.50 0.73% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 0.00 0.00% 107.00 0.24% 107.00 0.24% 3,735,691.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 0.00 0.00% 74.00 0.06% 74.00 0.06% 956,302.00
REALISASI PEKERJAAN
BOBOT
Jumlah S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN
Harga (Rp) % Jumlah Bobot Jumlah Bobot Jumlah Bobot
Harga (Rp) (%) Harga (Rp) (%) Harga (Rp) (%)
I PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13 - 0.00 15,966,993 0.48 15,966,993 1.03
Muh. Yahya Saleh, ST., M. Eng SUMAILA, S. Pd. I SAATIL AUNIAH, ST AGUSSALIM, SE
NIP. 19750403 200212 1 007 NIP. 19730304 200903 1 003 Site Engineer Direktur
LAPORAN BULANAN KE - 2
Periode : Sunday, November 03, 2019 s/d Tuesday, December 03, 2019
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.03% 0.22% 1.25% 19,362,931.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% 0.00% 0.50 0.73% 11,275,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 107.00 0.24% 51.00 0.11% 158.00 0.36% 5,516,254.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 74.00 0.06% 125.00 0.10% 199.00 0.17% 2,571,677.00
REALISASI PEKERJAAN
BOBOT
Jumlah S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN
Harga (Rp) % Jumlah Bobot Jumlah Bobot Jumlah Bobot
Harga (Rp) (%) Harga (Rp) (%) Harga (Rp) (%)
I PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13 15,966,993 1.03 3,395,938 0.22 19,362,931 1.25
II PEMBUATAN SALURAN 1,502,835,159.20 96.87 482,765,586 31.12 494,578,290 31.88 977,343,876 62.99
A REAL COSH 1,551,464,435.20 100.00 498,732,578.54 32.15 497,974,228.00 32.10 996,706,806.54 64.24
B PPN 10 % 155,146,443.52 Bobot Rencana = 70.15% (%) 99,670,680.65
Muh. Yahya Saleh, ST., M. Eng SUMAILA, S. Pd. I SAATIL AUNIAH, ST AGUSSALIM, SE
NIP. 19750403 200212 1 007 NIP. 19730304 200903 1 003 Site Engineer Direktur
LAPORAN BULANAN KE - 3
Periode : Wednesday, December 04, 2019 s/d Saturday, December 28, 2019
NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7
I. PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13% 1.25% 1.89% 3.13% 48,629,276.00
1 Mobilisasi LS 1.0 Rp 22,550,000.00 22,550,000.00 1.45% 0.50 0.73% 0.50 0.73% 1.00 1.45% 22,550,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 650.0 Rp 34,913.00 22,693,450.00 1.46% 158.00 0.36% 492.00 1.11% 650.00 1.46% 22,693,450.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 262.0 Rp 12,923.00 3,385,826.00 0.22% 199.00 0.17% 63.00 0.05% 262.00 0.22% 3,385,826.00
REALISASI PEKERJAAN
BOBOT
Jumlah S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN
Harga (Rp) % Jumlah Bobot Jumlah Bobot Jumlah Bobot
Harga (Rp) (%) Harga (Rp) (%) Harga (Rp) (%)
I PEKERJAAN PERSIAPAN DAN LAINNYA 48,629,276.00 3.13 19,362,931 1.25 29,266,345 1.89 48,629,276 3.13
II PEMBUATAN SALURAN 1,502,835,159.20 96.87 977,343,876 62.99 525,491,284 33.87 1,502,835,159 96.87
A REAL COSH 1,551,464,435.20 100.00 996,706,806.54 64.24 554,757,628.66 35.76 1,551,464,435.20 100.00
B PPN 10 % 155,146,443.52 Bobot Rencana = 100.00% (%) 155,146,443.52
Muh. Yahya Saleh, ST., M. Eng SUMAILA, S. Pd. I SAATIL AUNIAH, ST AGUSSALIM, SE
NIP. 19750403 200212 1 007 NIP. 19730304 200903 1 003 Site Engineer Direktur
TIME SCHEDULE
3 Oktober 2019 - 28 Oktober 2019
SKPD : Dinas Pekerjaan Umum dan Penataan Ruang Kabupaten Mamuju Tengah
No. Paket Kontrak : -600/213-611.41/PSDA/DAK/IX/2019
Nama Paket : Pembangunan Saluran Buang Desa Sinabatta (BKK)
Prop / Kab / Kodya : Kab. Mamuju Tengah
(A) Jumlah Harga Pekerjaan (termasuk biaya umum dan keuntungan) Rp 1,551,464,435
90 (SEMBILAN PULUH) HARI KALENDER
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) Rp 155,146,444
100.00%
(C) Jumlah Total Harga Pekerjaan = (A) + (B) Rp 1,706,610,879 Rencana
(D) Jumlah Total Harga Pekerjaan (Dibulatkan) Rp 1,706,000,000 Realisasi
BOBOT REALISASI (%) 6.31% 9.39% 8.06% 8.38% 6.42% 7.89% 11.26% 6.49% 12.78% 12.11% 10.18% 0.73%
BOBOT KOMULATIF REALISASI (%) 0 6.31% 15.70% 23.76% 32.15% 38.56% 46.46% 57.72% 64.20% 76.98% 89.09% 99.27% 100.00%
BOBOT RENCANA (%) 0.73% 10.00% 10.00% 10.00% 10.00% 10.00% 9.71% 9.71% 9.71% 9.71% 9.71% 0.73%
BOBOT KOMULATIF RENCANA (%) 0 0.73% 10.73% 20.73% 30.73% 40.73% 50.73% 60.44% 70.15% 79.86% 89.56% 99.27% 100.00%
DEVIASI (%) 0 5.58% 4.97% 3.04% 1.42% -2.17% -4.28% -2.72% -5.94% -2.88% -0.48% -0.01% 0.00%
Sketsa Gambar :
Luas
URAIAN Galian Saluran Luas Rata-rata Volume
Dimensi m2 m2 m3
SUBTANSI
Jarak a b c d e f x=((a*(b+c)/2)+(d*(e+f)/2)))
y=( x'+x")*0,5 z=y*a
STA
0 + 000 3.0 0.70 0.70 3.0 0.70 0.70 4.20
100 4.2 420.0
0 + 100 3.0 0.70 0.70 3.0 0.70 0.70 4.20
100 4.2 420.0
0 + 200 3.0 0.70 0.70 3.0 0.70 0.70 4.20
100 5.4 535.0
0 + 300 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 400 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 500 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 600 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 700 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 800 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
0 + 900 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 + 000 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 100 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 200 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 300 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 400 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 500 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 600 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 700 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 800 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
1 900 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 000 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 100 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 200 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 300 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 400 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 500 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 600 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 700 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 800 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
2 900 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
3 000 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
3 100 5.0 0.65 0.65 5.0 0.65 0.65 6.50
100 6.5 650.0
3 200 5.0 0.65 0.65 5.0 0.65 0.65 6.50
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG BACK UP DATA
KAB. MAMUJU TENGAH CV. AWANI CIPTA SARANA
Alamat : Jl. Tammauni Pue Ballung KTM Tobadak, 91563
Tobadak, 4-Dec-2019
BURHANUDDIN M, A. Md Syafruddin, ST
Inspektor Site Manager
Disetujui oleh,
Pejabat Pelaksana Teknis Kegiatan (PPTK)
Dinas Pekerjaan Umum dan Penataan Ruang
Kab. Mamuju Tengah
SUMAILA, S. Pd. I
NIP. 19730304 200903 1 003