Anda di halaman 1dari 6

Analisa Harga Satuan Pekerjaan Penutup Lantai dan

Dinding (AHS SNI 2011)


Berikut adalah analisa harga satuan pekerjaan penutup landat dan dinding untuk menghitung
biaaya penutup lantai per meter persegi, seperti lantai keramik, lantai marmer dll.

SATUA VOLUM HARGA


No.   URAIAN HARGA
N E SATUAN
      (Rp) (Rp)
I- 1 M2 Lantai Ubin Granito ukuran 40 x 40 cm Setara
01 Essenza
345,000.0 362,250.0
  - Granito 40 x 40 cm m2 1.0500
0 0
  - Semen portland Kg 9.8000 1,406.00 13,778.80
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 1.3000 15,700.00 20,410.00
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
421,656.9
    Jumlah
0
421,657.0
  Dibulatkan
0
I- 1 M2 Lantai Ubin Granito ukuran 30 x 30 cm Setara
02 Essenza
322,800.0 338,940.0
  - Granito 30 x 30 cm m2 1.0500
0 0
  - Semen portland Kg 10.0000 1,406.00 14,060.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 1.5000 15,700.00 23,550.00
  - Pekerja Oh 0.2600 42,000.00 10,920.00
  - Tukang batu Oh 0.1250 65,000.00 8,125.00
  - Kepala tukang Oh 0.0125 75,000.00 937.50
  - Mandor Oh 0.0130 80,000.00 1,040.00
402,590.6
    Jumlah
0
402,591.0
  Dibulatkan
0
I- 1 M¹ Plint Ubin Granito ukuran 10 x 40 cm Setara
03 Essenza
  - Plint granito 10 x 40 cm Bh 2.6500 27,600.00 73,140.00
  - Semen portland Kg 1.2000 1,406.00 1,687.20
233,400.0
  - Pasir pasang M3 0.0030 700.20
0
  - Semen warna Kg 0.1000 15,700.00 1,570.00
  -Pekerja Oh 0.0600 42,000.00 2,520.00
  -Tukang batu Oh 0.0300 65,000.00 1,950.00
  -Kepala tukang Oh 0.0030 75,000.00 225.00
  -Mandor Oh 0.0030 80,000.00 240.00
    Jumlah 82,032.40
  Dibulatkan 82,032.00
I- 1 M¹ Plint Ubin Granito ukuran 10 x 30 cm Setara
04 Essenza
  - Plint granito 10 x 30 cm Bh 3.3300 25,900.00 86,247.00
  - Semen portland Kg 1.6500 1,406.00 2,319.90
233,400.0
  - Pasir pasang M3 0.0032 746.88
0
  - Semen warna Kg 0.1000 15,700.00 1,570.00
  - Pekerja Oh 0.0900 42,000.00 3,780.00
  - Tukang batu Oh 0.0900 65,000.00 5,850.00
  - Kepala tukang Oh 0.0090 75,000.00 675.00
  - Mandor Oh 0.0045 80,000.00 360.00
101,548.7
    Jumlah
8
101,549.0
  Dibulatkan
0
I-
1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia
05
  - Keramik corak 10 x 20 cm m2 1.0000 56,000.00 56,000.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
    Jumlah 92,670.20
  Dibulatkan 92,670.00
I-
1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia
06
  - Keramik corak 20 x 20 cm m2 1.0000 62,500.00 62,500.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
    Jumlah 99,170.20
  Dibulatkan 99,170.00
I-
1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia
07
  - Keramik polos 30 x 30 cm m2 1.0000 53,000.00 53,000.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
    Jumlah 89,670.20
  Dibulatkan 89,670.00
I-
1 M2 Lantai Keramik corak 30 x 30 cm Setara Mulia
08
  - Keramik corak 30 x 30 cm m2 1.0000 58,000.00 58,000.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
    Jumlah 94,670.20
  Dibulatkan 94,670.00
I-
1 M2 Lantai Keramik polos 40 x 40 cm Setara Mulia
09
  - Keramik polos 40 x 40 cm m2 1.0000 56,800.00 56,800.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
    Jumlah 93,470.20
  Dibulatkan 93,470.00
I-
1 M2 Lantai Keramik corak 40 x 40 cm Setara Mulia
10
  - Keramik corak 40 x 40 cm m2 1.0000 65,500.00 65,500.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
102,170.2
    Jumlah
0
102,170.0
  Dibulatkan
0
I-
1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
11
  - Keramik corak 10 x 20 cm m2 1.0000 72,200.00 72,200.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
108,870.2
    Jumlah
0
108,870.0
  Dibulatkan
0
I- 1 M2 Lantai Keramik corak 20 x 20 cm setara
12 Roman
  - Keramik corak 20 x 20 cm m2 1.0000 75,200.00 75,200.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
111,870.2
    Jumlah
0
111,870.0
  Dibulatkan
0
I- 1 M2 Lantai Keramik polos 30 x 30 cm setara
13 Roman
  - Keramik polos 30 x 30 cm m2 1.0000 68,900.00 68,900.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
105,570.2
    Jumlah
0
105,570.0
  Dibulatkan
0
I- 1 M2 Lantai Keramik corak 30 x 30 cm Setara
14 Roman
  - Keramik corak 30 x 30 cm M2 1.0000 76,600.00 76,600.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
113,270.2
    Jumlah
0
113,270.0
  Dibulatkan
0
I- 1 M2 Lantai Keramik polos 40 x 40 cm setara
15 Roman
  - Keramik polos 40 x 40 cm m2 1.0000 72,500.00 72,500.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
109,170.2
    Jumlah
0
109,170.0
  Dibulatkan
0
I- 1 M2 Lantai Keramik corak 40 x 40 cm Setara
16 Roman
  - Keramik corak 40 x 40 cm m2 1.0000 77,000.00 77,000.00
  - Semen portland Kg 8.0000 1,406.00 11,248.00
233,400.0
  - Pasir pasang M3 0.0215 5,018.10
0
  - Semen warna Kg 0.0130 15,700.00 204.10
  - Pekerja Oh 0.2500 42,000.00 10,500.00
  - Tukang batu Oh 0.1200 65,000.00 7,800.00
  - Kepala tukang Oh 0.0120 75,000.00 900.00
  - Mandor Oh 0.0125 80,000.00 1,000.00
113,670.2
    Jumlah
0
  Dibulatkan 113,670.0
0
I-
1 M2 Lantai Marmer
17
550,000.0 583,000.0
  - Marmer m2 1.0600
0 0
  - Semen portland Kg 8.1900 1,406.00 11,515.14
233,400.0
  - Pasir pasang M3 0.0450 10,503.00
0
  - Semen warna Kg 0.6500 15,700.00 10,205.00
  - Pekerja Oh 0.7000 42,000.00 29,400.00
  - Tukang batu Oh 0.3500 65,000.00 22,750.00
  - Kepala tukang Oh 0.0350 75,000.00 2,625.00
  - Mandor Oh 0.0350 80,000.00 2,800.00
672,798.1
    Jumlah
4
672,798.0
  Dibulatkan
0
I-
1 M2 Lantai Parquet Jati
18
375,400.0 394,170.0
  - Parquet jati M2 1.0500
0 0
  - Lem vinyl Kg 0.6000 44,000.00 26,400.00
  - Pekerja Oh 0.6500 42,000.00 27,300.00
  - Tukang Oh 0.3500 65,000.00 22,750.00
  - Kepala tukang Oh 0.0350 75,000.00 2,625.00
  - Mandor Oh 0.0325 80,000.00 2,600.00
475,845.0
    Jumlah
0
475,845.0
  Dibulatkan
0