JUMLAH 181,484,089.09
PPN 10% 18,148,408.91
TOTAL 199,632,497.99
DIBULATKAN 199,632,000.00
I. PEKERJAAN PERSIAPAN
I.1 1 M' Pengukuran dan Pemasangan Bouwplank
0.0120 M3 Kayu 5/7 2,500,000.00 - 30,000.00
0.0200 Kg Paku biasa 2'' - 5'' 27,500.00 - 550.00
0.0070 M3 Kayu papan 2/20 1,875,000.00 - 13,125.00
0.1000 Oh Tukang kayu 126,000.00 12,600.00 -
0.1000 Oh Pekerja 110,250.00 11,025.00 -
0.0100 Oh Kepala Tukang 131,250.00 1,312.50 -
0.0050 Oh Mandor 136,500.00 682.50 -
25,620.00 43,675.00 69,295.00
TP. 6 M3 Memasang Sloof, Gelagar, Tiang Dirian & Balok Penjepit Lantai
1.1000 M3 Kayu ulin 13,125,000.00 - 14,437,500.00
5.2238 Oh Paku ulin 22,500.00 - 117,535.50
10.0000 Oh Tukang kayu 126,000.00 1,260,000.00 -
6.0000 Oh Pekerja 110,250.00 661,500.00 -
1.0000 Oh Kepala tukang 131,250.00 131,250.00 -
0.3000 Oh Mandor 136,500.00 40,950.00 -
2,093,700.00 14,555,035.50 16,648,735.50
A. UPAH
B. BAHAN / MATERIAL
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Rp 1,149,500.00 0.63 0.63
2 Papan Nama Proyek Rp 150,000.00 0.08 0.08 100%
3 Pek. Pengukuran dan Pemasangan Bouwplank Rp 2,938,108.00 1.62 1.62
M. FAHMI AMROZY, SE
Direktur