SOURCE
No EQUIPMENT TYPE NUMBER POWER REQ. / UNIT KVA
PLN GENSET
1 Crane
1.1CT 1 TBA 1 70 KW 100 - -
1.2CT2 TBA 1 70 KW 100 - -
2 Lifting
2.1LT 1 TBA TBA TBA TBA - -
2.2LT2 TBA TBA TBA TBA - -
3 Bar Bender and Cutter
3.1Bar Bender TBA 2 3.8 KVA 7.6 - 7.6
3.2Cutter TBA 2 3.8 KVA 7.6 - 7.6
4 Pompa Air
4.1PA 1 Deep Well 2 1.2 KVA 2.4 - 2.4
4.2PA 2 Sump 4 4 KVA 16 - 16
5 Lampu Penerangan
5.1Lampu sorot lapangan HPIT 18 400 W 7.2 - 7.2
5.2Lampu Sorot T/C HPIT 10 400 W 4 - 4
5.3Lampu T/L lapangan Balk 1 x 36 W 40 36 W 21.6 - 21.6
5.4Lampu BilBoard Balk 1 x 3g W 40 36 W 1.73 - 1.73
6 Kantor Proyek, kantor Kontraktor, Gudang, dll
6.1 Lampu Penerangan Balk 1 x 36 W 30 36 W 1.87 1.87 -
6.2Komputer PC 4 150 W 1.36 1.36 -
6.3Dispenser - 2 300 W 1.05 1.05 -
6.4A/C Split 4 1.5 KVA 12 KVA 12 KVA -
6.5Alat Lain - - - - - -
7 Kantor Owner & pengawas, Gudang, dll
7.1 Lampu Penerangan Balk 1 x 36 W 6 36 W 2.16 2.16 -
7.2Komputer PC 1 150 W 0.15 0.15 -
7.3Dispenser - 1 350 W 0.35 0.35 -
7.4A/C Split 2 1 KVA 2 2 -
7.5Alat Lain - - - - - -
8 Power Kerja Sub Kontraktor
8.1Panel Power Panel 4 4 KVA 168 168 -
Disiapkan
Diperiksa
Diketahui
Keterangan :
1 No. V 5.3. Lampu T/L Lapangan = Diperlukan penerangan kurang lebih 200 Lux, dengan lampu TL 36 W dibutuhkan untuk setiap 8 m2 luas lapangan 1 buah lampu TL atau 8 m2 /bh
2 No. VI 6.1. Lampu Penerangan ruang kantor= Diperlukan penerangan kurang lebih 350 lux, dengan lampu TL 36 W dibutuhkan untuk setiap 5 m2 luas ruangan 1 bh lampu TL atau 5 m
3 Batching Plant untuk Pembuatan Mortar (Beton Molen)
SUMBER AIR
No PENGGUNAAN AIR VOLUME / HARI (M3) JENIS TANGKI KAPASITAS TANGKI M3 LOKASI TANGKI
PDAM SUMUR / DANAU
4 Pekerjaan beton -
6 Pengujian peralatanmekanikal - - - - - -
Disiapkan
Diperiksa
Diketahui
Keterangan :