RENCANA ANGGARAN BIAYA

PEMBANGUNAN GEDUNG WORKSHOP


PEKERJAAN :
KOMPUTER BLK KOMUNITAS
PEMBERI TUGAS : KEMENTERIAN KETENAGAKERJAAN RI
TAHUN ANGGARAN : 2018
Harga
Jumlah Harga
No. Uraian pekerjaan Vol Sat. Satuan
( Rp. ) ( Rp. )
A PEKERJAAN PERSIAPAN 11,690,000
1 Papan Proyek 1 unt 500,000 500,000
2 Pek. Pengukuran dan Bowplank 52 m' 157,500 8,190,000
3 Pek. Listrik & Air Kerja 1 ls 2,500,000 2,500,000
4 Pek. Laporan & Dokumentasi 1 ls 1,000,000 1,000,000
B PEKERJAAN PONDASI & TANAH 74,489,747
1 Pek. Galian Tanah Pondasi 77.38 m3 36,740 2,842,941
2 Pek. Urug Tanah Kembali 25.79 m3 13,400 345,586
Pek. Urug Tanah Peninggian Peil Lantai (t = 10
3 19.55 m3 183,900 3,595,245
cm)
4 Pek. Pasir Urug -
Bawah Pondasi 11.9 m3 110,000 1,309,000
Bawah Lantai 19.9 m3 110,000 2,189,000
5 Pek. Pondasi Tapak P1 (100x100x20- 40) -
Beton K-225 3.92 m3 1,230,825 4,824,834
Pembesian 473.59 kg 11,300 5,351,567
Bekisting 21.28 m2 770,000 16,385,600
6 Pek. Pondasi Batu Belah P2 24.26 m3 730,825 17,729,815
7 Pek. Sloof Beton (20/30) -
Beton K-225 3.83 m3 1,230,825 4,714,060
Pembesian 816.72 kg 11,300 9,228,936
Bekisting 51.03 m2 117,052 5,973,164
C PEKERJAAN STRUKTUR 120,307,947
1 Pek. Kolom Beton K1 (30/30)
Beton K-225 6.91 m3 1,230,825 8,505,001
Pembesian 1005.9 kg 11,316 11,382,764
Bekisting 92.16 m2 295,290 27,213,926
2 Pek. Kolom Praktis KP (12/12) -
Beton K-175 1.08 m3 1,124,383 1,214,334
Pembesian 193.78 kg 11,316 2,192,814
Bekisting 28.8 m2 295,290 8,504,352
3 Pek. Balok Beton B1 (20/30) -
Beton K-225 3.33 m3 1,230,825 4,098,647
Pembesian 663.71 kg 11,316 7,510,542
Bekisting 44.4 m2 295,290 13,110,876
4 Pek. Balok Beton Lintel RB (12/15) -
Beton K-175 1.8 m3 1,124,383 2,023,889
Pembesian 408.26 kg 11,316 4,619,870
Bekisting 34.66 m2 295,290 10,234,751
5 Pek. Ramp Beton T = 10 cm -
Beton K-175 0.35 m3 1,124,383 393,534
Pembesian 42.24 kg 11,316 477,988
Bekisting 0.69 m2 295,290 203,750
6 Rek Kolom Sopi 60/60 -
beton K-225 0.75 m3 1,230,825 923,119
Pembesian 84.12 kg 11,316 951,902
Bekisting 9.96 m2 295,290 2,941,088
7 Pek, Ring Balok Praktis Sopi-sopi -
Beton K-175 0.96 m3 1,124,383 1,079,408
Pembesian 194.91 kg 11,316 2,205,602
Bekisting 12.81 m2 295,290 3,782,665
8 Pek. plat Beton Topi-topi -
Beton K-225 0.86 m3 1,230,825 1,058,510
Pembesian 182.42 kg 11,316 2,064,265
Bekisting 12.24 m2 295,290 3,614,350
D PEKERJAAN ATAP & PLAFOND 83,777,760
D.1 PEKERJAAN ATAP 62,644,900
1 Rangka Atap baja Ringan 205.53 m2 165,000 33,912,450
2 Atap Spandek t=0,35 205.53 m2 65,000 13,359,450
3 Lisplank GRC 73.8 M' 85,000 6,273,000
4 Pasang Aluminium foil, Glaswool, Roofmesh 140 m2 65,000 9,100,000
D.2 PEKERJAAN PLAFOND 21,132,860
1 Plafond Gipsum +Rangka hollow 4/4; t= 136.49 m2 97,000 13,239,530
2 Plafond Calsiboard 4,5 mm + Rangka 53.31 m2 68,000 3,625,080
3 List Gipsum 5 cm 94.85 m2 45,000 4,268,250
E PEKERJAAN PASANGAN 110,064,060
1 Pasangan Dinding Bata 250.73 m2 66,440 16,658,501
2 Plester + Acian 496.17 m3 45,440 22,545,965
3 Pasangan Rolaag Bata 19.8 m' 381,840 7,560,432
4 Pasangan Saluran Terbuka 40 m' 260,045 10,401,800
Pekerjaan Rabat Beton t = 5 cm bawah lantai
5 9.96 m3 115,104 1,146,436
keramik
Pekerjaan Rabat Beton t = 5 cm keliling bang
6 2.04 m3 115,104 234,812
lbr = 60 cm
7 Pekerjaan Meja Beton Wastafel t = 8 cm 0.1 m3 875,100 87,510
8 Pasangan Keramik Lantai 40/40 Polished 136.4 m2 123,246 16,810,754
9 Pasangan Keramik Lantai 30/30 Polished 52 m2 257,496 13,389,792
10 Pasangan Keramik Lantai 20/20 Unpolished 3.04 m2 156,780 476,611
11 Pasangan Plint Keramik Lantai 40/10 polished 97.4 m' 48,168 4,691,563
Pasangan Keramik Bak & Meja Wastafel 20/20
12 1.77 m2 1,464,989 2,593,031
Polished
13 Pasangan Keramik Dinding 30/60 Polished 5.29 m2 618,750 3,273,188
14 Pasangan Batu Alam Candi Kolom Entrace 7.62 m2 656,418 5,001,905
15 Pek. Logo & Tulisan 1 ls 1,200,000 1,200,000
16 List Dinding Kusen 97.36 M1 41,000 3,991,760
F PEKERJAAN KUSEN PINTU & JENDELA 64,473,180
1 Kusen/Pintu type P1 1 unt 4,330,040 4,330,040
2 Kusen/Pintu type P2 3 unt 4,174,360 12,523,080
3 Kusen/Pintu type P3 (Spandrel) 1 unt 2,461,080 2,461,080
4 Kusen/Jendela type J1 2 unt 3,909,000 7,818,000
5 Kusen/Jendela type J2 9 unt 3,445,920 31,013,280
6 Kusen/Jendela type J3 1 unt 3,404,520 3,404,520
7 Kusen/Jendela type BV 1 unt 595,680 595,680
Teralis Ventilasi Teras (besi Hollow) 7 m1 350,000 2,327,500
G PEKERJAAN PENGECATAN 16,125,026
1 Pek. Pengecatan Dinding Interior 248.08 m2 25,391 6,298,999
2 Pek. Pengecatan Dinding Exterior 248.08 m2 21,360 5,298,989
3 Pek. Pengecatan Plafond 189.8 m2 21,360 4,054,128
4 Pek. Pengecatan Listplank 22.14 m2 21,360 472,910
H PEKERJAAN PLUMBING & SANITAIR 15,670,043
1 Instalasi Pipa PVC AW 4" 16 m' 180,519 2,888,304
2 Instalasi Pipa PVC AW 2" 12 m' 103,218 1,238,616
3 Instalasi Pipa PVC AW 3/4" 20 m' 98,180 1,963,600
4 Instalasi Pipa PVC AW 1/2" 15 m' 79,323 1,189,845
5 Septic Tank dan Rembesan 1 unt 4,407,413 4,407,413
6 Pemasangan Closed Jongkok 1 bh 627,947 627,947
7 Pemasangan Kran Air 2 bh 216,452 432,904
8 Pemasangan Wastafel + Kran 2 bh 875,074 1,750,148
9 Pemasangan Cermin Wastafel 100x200 1 unt 1,171,266 1,171,266
I PEKERJAAN LISTRIK 67,667,437
1 Penyambungan Daya Listrik 5.500 VA ### VA 1,000 5,500,000
Perijinan Sertifikat Layak Operasi (SLO) 5.500
2 ### VA 1,000 5,500,000
VA
3 Panel Listrik 1 unt 467,280 467,280
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2 m' 1,506,600 3,013,200
Pek. Instalasi Penerangan & Power NYM
5 66 ttk 241,760 15,956,160
3x2,5 mm2 + conduit
6 Pek. Instalasi Power AC 2 ttk 1,800,000 3,600,000
7 Pemasangan Lampu TKI 2x36W 16 bh 317,400 5,078,400
8 Pemasangan Lampu Baret Kotak 22W 7 bh 95,274 666,918
9 Pemasangan Lampu E27ESS 8 Watt + Fitting 3 bh 2,908,080 8,724,240
10 Pemasangan Saklar Engkle 5 bh 105,360 526,800
11 Pemasangan Saklar Double 4 bh 118,440 473,760
12 Pemasangan Stop Kontak Single 9 bh 198,240 1,784,160
13 Pemasangan Stop Kontak Ganda 16 bh 228,660 3,658,560
14 Pemasangan Stop Kontak AC 2 bh 318,480 636,960
15 Pemasangan AC split wall 2 PK 2 unit 6,540,000 13,080,000
16 Grounding (max 2 Ohm) 1 lot 1,850,000 1,850,000
L LAIN – LAIN 15,000,000
1 IMB 1 dok 5,000,000 5,000,000
2 Transportasi 2 paket 1,000,000 2,000,000
3 Ketua Unit Pengelola Teknis 4 OB 400,000 1,600,000
4 Ketua Unit Pengelola Keuangan 4 OB 400,000 1,600,000
5 Anggota Pengelola Teknis 8 OB 300,000 2,400,000
6 Anggota Pengelola Keuangan 8 OB 300,000 2,400,000
RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG WORKSHOP
PEKERJAAN :
KOMPUTER - BLK KOMUNITAS
PEMBERI TUGAS : KEMENTERIAN KETENAGAKERJAAN RI
TAHUN ANGGARAN : 2018

NO ITEM PEKERJAAN TOTAL

A PEKERJAAN PERSIAPAN 11,690,000


B PEKERJAAN PONDASI & TANAH 74,489,747
C PEKERJAAN STRUKTUR 120,307,947
D PEKERJAAN ATAP & PLAFOND 83,777,760
E PEKERJAAN PASANGAN 110,064,060
F PEKERJAAN KUSEN PINTU & JENDELA 64,473,180
G PEKERJAAN PENGECATAN 16,125,026
H PEKERJAAN PLUMBING & SANITAIR 15,670,043
I PEKERJAAN LISTRIK 67,667,437
J LAIN - LAIN 15,000,000
TOTAL 511,597,764
PEMBULATAN 500,000,000
TERBILANG : Lima Ratus Juta Rupiah

Sukabumi, 17 Juli 2018


Pimpinan Pondok Pesantren Ketua Unit Ketua Unit
Nurul Hasanah Pengelola Kegiatan Pengelola Kuangan

Nurhayat, S.Pd.I.,SE. Ade Yunus, S.Pd.I. Yuswandi, S.Pd.I