PERINCIAN BAHAN DAN UPAH 361,29 M2

1 Semen 30 Sak x 64,000 = 1,920,000


2 Pasir Pasang 2 Truk x 400,000 = 800,000
3 Upah Kerja 361.29 M2 x 45,000 = 16,258,050
Total 18,978,050

PERINCIAN BAHAN
COR KASAR LANTAI DALAM MUSHOLLAH 108 M2 - ( tebal cor 7,5 cm )
( 108 M2 x 0,075 M = 8,1 M3 )

1 Semen 60 Sak x 64,000 = 3,840,000


2 Pasir Cor 2 Truk x 500,000 = 1,000,000
3 Kerikil 2 Truk x 650,000 = 1,300,000
Total 6,140,000
4 Upah ( jika semua alat dr Pekerja/Molen) = 6,480,000
18,760,000

ESTIMASI BIAYA UNTUK PLASTER DINDING DAN COR LANTAI KASAR = 37,738,050
31,618,050