HARGA PERKIRAAN SENDIRI (HPS)

NO. JENIS/ BARANG JASA

A PEKERJAAN REHABILITASI GEDUNG ASRAMA

I PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik
2 Pembongkaran dinding pas. Bata
3 Pembongkaran Plafon
4 Pembongkaran Rangka Atap
5 Pembongkaran Penutup Atap
6 Pembuangan Sisa Bongkaran

II PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasang Dinding Batu bata 1 5
2 Pasang Plesteran Dinding 1 5
3 Pasang Acian Dinding
4 Benangan/Pasang Tali air
5 PEKERJAAN BETON
6 Beton Balok latei 15/20 (Mutu fc = 14,5 MPa (K 175))
7 Pembesian
8 Bekisting balok

III PEKERJAAN LANTAI DAN KERAMIK


1 Beton Rabat Lantai Keliling Bangunan (Mutu fc = 7,4 MPa (K 100)) t=7cm
2 Pasang Keramik Lantai 50x50 cm
3 Pasang Keramik Lantai 25x25 Nonslip
4 Pasang Keramik Dinding 25x40
5 Pasang Plin Lantai 10x50 cm

IV PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pasang Kusen Aluminium
2 Pasang Daun Daun Kaca 5 mm Rangka Aluminium
3 Pasang Daun Pintu Double Plywood Rangka Kayu
4 Pasang Daun Pintu Double Plywood Lapis Aluminium
5 Pasang Daun Jendela Kaca 5 mm Rangka Aluminium
6 Pasang Kaca Bening 5 mm

V PEKERJAAN ENGSEL, KUNCI DAN PENGGANTUNG


1 Pasang Engsel Jendela Casement
2 Pasang Slot Jendela Rambuncis
3 Pasang Engsel Pintu
4 Pasang Slot Pintu
5 Pasang Kunci Pintu
6 PEKERJAAN LANGIT-LANGIT
7 Pasang Rangka dan Gantungan Besi Hollow/Galvalum
8 Pasang Plafond Gypsumboard 9 mm
9 Pasang Lisplafond gypsum

VI PEKERJAAN ATAP
1 Pasang/Rehab Gording Baja C.150.50.20.3,2
2 Pasang Penutup Atap Spandeck Warna
3 Pasang Bubungan Atap
4 Pasang Patahan Atap
5 Pasang Lisplank Super Plank
6 Pasang Manumata Kisi-kisi Aluminium

VII PEKERJAAN PENGECATAN & FINISHING DINDING


1 Pengecatan Daun Pintu Plywood dengan Politur Natural Gloss
2 Pengecatan Dinding Luar
3 Pengecatan Dinding Dalam
4 Pengecatan Plafon

VIII PEKERJAAN INSTALASI LISTRIK


1 Pasang Instalasi Penerangan
2 Pasang Instalasi Stop Kontak
3 Pasang RM 2x18 watt
4 Pasang Downlight dia 15 cm 11W
5 Pasang Downlight dia 20 cm 23W
6 Pasang Stop Kontak
7 Pasang Saklar Tunggal
8 Pasang Saklar Ganda
9 Pasang Panel MCB
10 Pasang Box Panel MCB

IX PEKERJAAN SANITAIR
1 Pasang Pipa PVC 4
2 Pasang Pipa PVC 3
3 Pasang Pipa PVC 1
4 Pasang Pipa PVC 1/2
5 Pasang Kloset Duduk
6 Pasang Washtafel
7 Pasang Kran Washer
8 Pasang Kran air
9 Pasang Floor Drain
10 Pasang Kaca Cermin
11 Pasang Bio Septic PVC Kapasitas 2m3
12 Pasang Bak Cuci Stainless 1 Lubang

X PEKERJAAN ANTI RAYAP


1 Penyemprotan anti rayap

B PEKERJAAN REHABILITASI GEDUNG LABORATORIUM 3


I PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik
2 Pembongkaran dinding pas. Bata
3 Pembongkaran Plafon
4 Pembongkaran Rangka Atap
5 Pembongkaran Penutup Atap
6 Pembuangan Sisa Bongkaran

II PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasang Dinding Batu bata 1 5
2 Pasang Plesteran Dinding 1 5
3 Pasang Acian Dinding
4 Benangan/Pasang Tali air

III PEKERJAAN BETON


1 Beton Balok latei 15/20 (Mutu fc = 14,5 MPa (K 175))
2 Pembesian
3 Bekisting balok

IV PEKERJAAN LANTAI DAN KERAMIK


1 Beton Rabat Lantai Keliling Bangunan (Mutu fc = 7,4 MPa (K 100)) t=7cm
2 Pasang Keramik Lantai 50x50 cm
3 Pasang Plin Lantai 10x50 cm

V PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pasang Kusen Aluminium
2 Pasang Daun Daun Kaca 5 mm Rangka Aluminium
3 Pasang Kaca Bening 5 mm

VI PEKERJAAN ENGSEL, KUNCI DAN PENGGANTUNG


1 Pasang Engsel Pintu
2 Pasang Slot Pintu
3 Pasang Kunci Pintu

VII PEKERJAAN LANGIT-LANGIT


1 Pasang Rangka dan Gantungan Besi Hollow/Galvalum
2 Pasang Plafond Gypsumboard 9 mm
3 Pasang Lisplafond gypsum
VIII PEKERJAAN ATAP
1 Pasang Rangka Atap Baja Ringan
2 Pasang Penutup Atap Spandeck Warna
3 Pasang Bubungan Atap
4 Pasang Lisplank Super Plank
5 Pasang Manumata Kisi-kisi Aluminium

IX PEKERJAAN PENGECATAN & FINISHING DINDING


1 Pengecatan Dinding Luar
2 Pengecatan Dinding Dalam
3 Pengecatan Plafon

X PEKERJAAN INSTALASI LISTRIK


1 Pasang Instalasi Penerangan
2 Pasang Instalasi Stop Kontak
3 Pasang RM 2x18 watt
4 Pasang Downlight dia 15 cm 11W
5 Pasang Stop Kontak
6 Pasang Stop Kontak AC
7 Pasang Saklar Ganda
8 Pasang Panel MCB
9 Pasang Box Panel MCB
10 PEKERJAAN ANTI RAYAP
11 Penyemprotan anti rayap

C PEKERJAAN REHABILITASI RUMAH DINAS KOPEL (4 UNIT)


B PEKERJAAN PEMBONGKARAN
1 Pembongkaran Lantai Keramik
2 Pembongkaran dinding pas. Bata
3 Pembongkaran Plafon
4 Pembongkaran Rangka Atap
5 Pembongkaran Penutup Atap
6 Pembuangan Sisa Bongkaran

B PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasang Dinding Batu bata 1 5
2 Pasang Plesteran Dinding 1 5
3 Pasang Acian Dinding
4 Benangan/Pasang Tali air

III PEKERJAAN BETON


1 Beton Balok latei 15/20 (Mutu fc = 14,5 MPa (K 175))
2 Pembesian
3 Bekisting balok
IV PEKERJAAN LANTAI DAN KERAMIK
1 Beton Rabat Lantai Keliling Bangunan (Mutu fc = 7,4 MPa (K 100)) t=7cm
2 Pasang Keramik Lantai 40x40 cm
3 Pasang Keramik Lantai 25x25 Nonslip
4 Pasang Keramik Dinding 25x40
5 Pasang Plin Lantai 10x50 cm

V PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pasang Kusen Aluminium
2 Pasang Daun Pintu Double Plywood Lapis Aluminium
3 Pasang Daun Jendela Kaca 5 mm Rangka Aluminium
4 Pasang Kaca Bening 5 mm
5 PEKERJAAN ENGSEL, KUNCI DAN PENGGANTUNG
6 Pasang Engsel Jendela Casement
7 Pasang Slot Jendela Rambuncis
8 Pasang Engsel Pintu
9 Pasang Slot Pintu
10 Pasang Kunci Pintu

VI PEKERJAAN LANGIT-LANGIT
1 Pasang Rangka dan Gantungan Besi Hollow/Galvalum
2 Pasang Plafond Gypsumboard 9 mm
3 Pasang Lisplafond gypsum

VII PEKERJAAN ATAP


1 Pasang Rangka Atap Baja Ringan
2 Pasang Penutup Atap Spandeck Warna
3 Pasang Bubungan Atap
4 Pasang Lisplank Super Plank
5 Pasang Manumata Kisi-kisi Aluminium

VIII PEKERJAAN PENGECATAN & FINISHING DINDING


1 Pengecatan Daun Pintu Plywood dengan Politur Natural Gloss
2 Pengecatan Dinding Luar
3 Pengecatan Dinding Dalam
4 Pengecatan Plafon

IX PEKERJAAN INSTALASI LISTRIK


1 Pasang Instalasi Penerangan
2 Pasang Instalasi Stop Kontak
3 Pasang Downlight dia 15 cm 11W
4 Pasang Downlight dia 20 cm 23W
5 Pasang Stop Kontak
6 Pasang Saklar Tunggal
7 Pasang Saklar Ganda
8 Pasang Panel MCB
9 Pasang Box Panel MCB

X PEKERJAAN SANITAIR
1 Pasang Pipa PVC 4
2 Pasang Pipa PVC 3
3 Pasang Pipa PVC 1
4 Pasang Pipa PVC 1/2
5 Pasang Kloset Duduk
6 Pasang Kran Washer
7 Pasang Kran air
8 Pasang Floor Drain
9 Pasang Bio Septic PVC Kapasitas 2m3

XI PEKERJAAN ANTI RAYAP


1 Penyemprotan anti rayap

D PEKERJAAN UTILITAS AIR DAN LISTRIK


I PEKERJAAN INSTALASI LISTRIK
1 Penyambungan Daya PLN 131.000 watt
2 Kabel Jaringan NYFGBY 4x35 (dari MDP ke SDP)
3 Kabel Jaringan NYFGBY 4x25 (dari MDP ke SDP)
4 Kabel Jaringan NYY 4x35 (dari SDP ke Panel MCB masing2 Gedung)
5 Kabel Jaringan NYY 4x25 (dari SDP ke Panel MCB masing2 Gedung)
6 Kabel Jaringan NYY 4x16 (dari SDP ke Panel MCB masing2 Gedung)
7 Kabel Jaringan NYY 4x10 (dari SDP ke Panel MCB masing2 Gedung)
8 Panel Genset / ATS Motorized
9 Main Distribution Panel ( MDP )
10 Sub Distribution Panel ( SDP 1 , 3 )
11 Sub Distribution Panel ( SDP 2 )
12 Sub Distribution Panel ( SDP 4 & 5 )
13 PJU Solar cell , LED 50watt , Tiang Hexagonal Single Arm ( t=5m)
14 PJU Solar cell, LED 50watt , Tiang Hexagonal Double Arm ( t=5m)
15 Lampu taman solar cell 20watt

II PEKERJAAN SUMUR BOR


1 Pengeboran Sumur Dalam 100 m
2 Electric Logging
3 Pengeboran diameter 4 inch
4 Reaming diameter 6 inch
5 Pengadaan dan Pemasangan Pipa Casing Black Steel dia. 4 inch
6 Pengadaan dan Pemasangan Pipa LC Screen dia. 4 inch
7 Pengadaan Dan Pemasangan Gravel Pack
8 Pencucian sumur
9 Pengujian pompa sumur
10 Uji sampling
11 Pengadaan dan pemasangan pompa summersible dan instalasi
12 Socket GIP 1
13 Elbow / Blend GIP 1
14 Pasang Pipa Pompa GIP 1
15 Pompa Sumbersible
16 - Material Stanlies steel
17 - Kapasitas max 50 liter/menit
18 - Head max 110 m
19 - Out let 1
20 - Power 1,5 Kw
21 Box Panel MCB Lengkap Dengan Otomatis Start
22 Pengadaan Kabel Pompa NYM - 4 x 10
23 Pengadaan Kabel Induk NYM - 4 x 10
24 Pengadaan Kabel Leveling NYY - 3 x 2,5

II PEKERJAAN JARINGAN AIR BERSIH


1 Perbaikan Menara Air
2 Pengecatan Dinding Luar
3 Pengadaan dan pemasangan Pipa Distribusi - Pipa Gip 2
4 Pengadaan dan pemasangan Pipa Jaringan Distribusi - Pipa Gip 1
5 Pengadaan dan pemasangan Pipa Jaringan Distribusi - Pipa HDPE 1
6 Socket 2
7 Socket 1
8 Tee Reducer 2 - 1
9 Elbow 2
10 Elbow 1
11 Clamp Sadle 1 - 3/4
12 Gate Valve 2
13 Gate Valve 1
14 Galian Pipa
15 Urugan Pasir Pada Dasar Galian
16 Box Beton Gate Valve
17 Pembesian
18 Bekisting

E PEKERJAAN DERMAGA
I PEKERJAAN TANAH & PASIR
1 Pengadaan tiang pancang beton bulat dia 400mm p=6m (K300FC=26,4 Mpa)
2 Mobilisasi tiang pancang
3 Pengangkatan dan penyetelan tiang dari tempat penyimpanan ke lokasi
4 Pemancangan tiang
5 Pemotongan tiang
6 Pasir Pengisi Tiang Pancang
II PEKERJAAN BETON
1 Beton Abutment (Mutu fc = 21,7 MPa (K 250))
2 Pembesian
3 Bekisting
4 Beton Poer 80x80x80 cm (Mutu fc = 21,7 MPa (K 250))
5 Pembesian
6 Bekisting
7 Beton Balok Memanjang 40/70 (Mutu fc = 21,7 MPa (K 250))
8 Pembesian
9 Bekisting balok
10 Beton Balok Melintang 40/40 (Mutu fc = 21,7 MPa (K 250))
11 Pembesian
12 Bekisting balok
13 Beton Plat Lantai t=25cm (Mutu fc = 21,7 MPa (K 250))
14 Pembesian
15 Bekisting Lantai
16 Kanstin beton 12/15 (Mutu fc = 21.5 MPa (K 175))
17 Pembesian
18 Bekisting

III PEKERJAAN PELENGKAP DERMAGA


1 Pengecatan Kanstin
2 Karet vender Type V
3 Bollard tipe SR
4 Expantion joint 70 x 70 x 7

E PEKERJAAN LANDSCAPE
I PEKERJAAN TANAH
1 Timbunan Tanah Biasa (dengan peralatan)

II PEKERJAAN PERKERASAN
1 Pasang Paving Blok
2 Beton Kanstin ( MUTU fc = 21,7 MPa (K 250)
3 Pembesian
4 Bekisting
5 Penyiapan Badan Jalan
6 Lapis Pondasi Agregat Kelas A
7 Lapis Resap Pengikat - Aspal Cair
8 Lataston Lapis Pondasi (HRS-Base) (gradasi senjang/semi senjang)

III PEKERJAAN DRAINASE DAN PEDESTRIAN


1 Pekerjaan Galian Drainase
2 Pekerjaan Timbunan Trotoar
3 Pasangan Batu Kali
4 Plesteran
5 Beton Plat Penutup (k250)
6 Pembesian
7 Bekisting
8 Lubang Biopore pada dasar drainase setiap 10m (t=1m)
9 Pasir Bawah Lantai
10 Lantai Kerja (t=7cm)
11 Beton Kanstin ( MUTU fc = 21,7 MPa (K 250)
12 Pembesian
13 Bekisting
14 Sumur Resapan
15 Pekerjaan Rabat Beton Trotoar
16 Pekerjaan Lantai Koral Sikat
17 Pekerjaan Guiding Block
18 Ramp Beton Akses Masuk masing-masing Gedung
19 Railling
20 Rambu Rambu Evakuasi Bencana
21 Tabung Alat Pemadam Api Ringan (APAR)

IV PEKERJAAN GAPURA
1 Galian Tanah Pondasi
2 Timbunan Tanah Pondasi Kembali
3 Pasir Pasang Bawah Pondasi
4 Beton Rabat Lantai Kerja (Mutu fc = 7,4 MPa (K 100)) t=7cm
5 Beton Pondasi Footplate (Mutu fc = 14,5 MPa (K 175))
6 Pembesian
7 Bekisting Kolom
8 Beton Kolom (Mutu fc = 14,5 MPa (K 175))
9 Pembesian
10 Bekisting Kolom
11 Beton Sloof 20/30 (Mutu fc = 14,5 MPa (K 175))
12 Pembesian
13 Bekisting Sloof
14 Beton Balok (Mutu fc = 14,5 MPa (K 175))
15 Pembesian
16 Bekisting balok
17 Acian Dinding 1 2
18 Pekerjaan Pengecatan
19 Pasang Rangka Besi Holo
20 Pekerjaan Pengecatan Besi
21 Tulisan/Ornamen/Hiasan
22 PEKERJAAN PENGHIJAUAN
23 Penanaman Rumput Gajah Mini
24 Penanaman Pohon
F PEKERJAAN REHABILITASI SLIPWAY
I PEKERJAAN TANAH
1 Galian Pondasi
2 Urugan Tanah Kembali
3 Timbunan Tanah Bawah Lantai
4 Urugan Pasir Bawah Pondasi
5 Urugan Pasir Bawah Lantai

II PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasang Plesteran Dinding 1 5
2 Pas. Batu Kali
3 Pasang Acian Dinding
4 Pasang Dinding Batu bata 1 5

III PEKERJAAN DUDUKAN DOCK TARIK


1 Plat Dudukan Beton (Mutu fc = 21,7 MPa (K 250)
2 Pondasi Sumuran Beton (Mutu fc = 21,7 MPa (K 250)
3 Bakesting
4 Pembesian
5 Buis Beton

III PEKERJAAN BETON


1 Poer Beton 80x80x25 (Mutu fc = 21,7 MPa (K 250)
2 Pembesian
3 Bekisting
4 Kolom Beton 30x30 (Mutu fc = 21,7 MPa (K 250)
5 Pembesian
6 Bekisting
7 Sloof Beton 25x30 (Mutu fc = 21,7 MPa (K 250)
8 Pembesian
9 Bekisting balok
10 Reng Balok Beton 25x45 (Mutu fc = 21,7 MPa (K 250)
11 Pembesian
12 Bekisting balok
13 Plat Dack (Mutu fc = 21,7 MPa (K 250)
14 Pembesian
15 Bekisting balok

IV PEKERJAAN PENGECATAN & FINISHING DINDING


1 Pengecatan Dinding Luar

V PEKERJAAN PENGECATAN & FINISHING DINDING


1 Pemasangan Pintu Harmonika

VI PEKERJAAN INSTALASI LISTRIK


1 Pasang Instalasi Penerangan
2 Pasang Instalasi Stop Kontak
3 Pasang RM 2x18 watt
4 Pasang Stop Kontak
5 Pasang Saklar Tunggal
6 Pasang Panel MCB
7 Pasang Box Panel MCB

VII PEKERJAAN INSTALASI LISTRIK


1 Pemasangan rell slipway dan Dock Tarik

G PEKERJAAN KOLAM LARVA


I PEKERJAAN TANAH & PASIR
1 Galian Tanah Pondasi
2 Timbunan Tanah
3 Pasir Pasang Bawah Pondasi
4 Pasir Pasang Bawah lantai dudukan

II PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasang Batu Kali
2 Pasang Plesteran

III PEKERJAAN BETON


1 Pekerjaan Lantai Beton Tulangan
2 Pembesian
3 Bekisting
4 Pekerjaan Balok Plat Lantai 25/40
5 Pembesian
6 Bekisting

IV PEKERJAAN LAIN LAIN


1 Pemasangan Instalasi Pipa
2 Profil Tank

H PEKERJAAN KOLAM BENIH


I PEKERJAAN TANAH & PASIR
1 Galian Dasar Kolam
2 Galian Tanah Pondasi
3 Timbunan Tanah
4 Pasir Pasang Bawah Pondasi
5 Pasir Pasang Bawah lantai Kolam
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasang Batu Kali
2 Pasang Plesteran
III PEKERJAAN BETON
1 Pekerjaan Lantai Beton Tulangan
2 Pembesian
3 Bekisting

IV PEKERJAAN LAIN LAIN


1 Perbaikan Instalasi Pipa

V PEKERJAAN K3 KONSTRUKSI DAN PENCEGAHAN COVID 19


VI PEKERJAAN K3 KONSTRUKSI
VII DIVISI VIII. K 3 KONSTRUKSI
1 Alat Pelindung Diri (APD)
2 Topi pelindung (Safet Helmet)
3 Pelindung pernapasan
4 Sarung tangan (Safety)
5 Sepatu Keselamatan (Safety Lars)
6 Rompi Keselamatan (Safety Vast)
7 Sabuk keselamatan (Safety belt)
8 Fasilitas Sarana Kesehatan
9 P3K

IX PENCEGAHAN COVID 19
1 Hand Sanitizer
2 Disinfektan
3 Tempat Cuci Tangan
4 Aicare Thermometer Infrared
KIRAAN SENDIRI (HPS)

SATUAN VOLUME HARGA %TASE PPN JUMLAH HARGA

m2 884 24,000.00 0.1 23,337,600.00


m3 18.09 673,300.00 0.1 13,397,996.70
m2 1164 3,000.00 0.1 3,841,200.00
m2 1338.6 18,000.00 0.1 26,504,280.00
m2 1338.6 12,000.00 0.1 17,669,520.00
ls 1 50,000,000.00 0.1 55,000,000.00

m2 120.66 324,624.30 0.1 43,086,084.84


m2 241.32 81,294.84 0.1 21,579,877.87
m2 241.32 48,400.00 0.1 12,847,876.80
m 402.2 31,724.00 0.1 14,035,332.08

m3 3.22 1,555,974.20 0.1 5,511,260.62


kg 451.92 20,219.10 0.1 10,051,157.24
m2 21.52 337,029.00 0.1 7,978,150.49

m3 12.6 1,425,169.90 0.1 19,752,854.81


m2 784.25 414,313.90 0.1 357,418,243.68
m2 99.75 368,989.50 0.1 40,487,372.89
m2 333.6 406,967.00 0.1 149,340,610.32
m 741.6 77,658.90 0.1 63,351,024.26

m 733 186,718.40 0.1 150,551,045.92


m 16.8 995,467.00 0.1 18,396,230.16
m2 50.4 770,000.00 0.1 42,688,800.00
m2 36.75 863,060.00 0.1 34,889,200.50
m2 59.52 850,267.00 0.1 55,668,681.02
m2 44.4 285,285.00 0.1 13,933,319.40

psg 62 183,535.00 0.1 12,517,087.00


bh 62 94,380.00 0.1 6,436,716.00
psg 65 156,035.00 0.1 11,156,502.50
bh 65 77,880.00 0.1 5,568,420.00
bh 60 369,600.00 0.1 24,393,600.00

m2 1164 175,890.00 0.1 225,209,556.00


m2 1164 55,605.00 0.1 71,196,642.00
m 922.2 50,677.00 0.1 51,407,762.34

kg 1123.26 41,118.00 0.1 50,804,825.15


m2 1338.6 218,878.00 0.1 322,289,099.88
m 115 144,980.00 0.1 18,339,970.00
m 22.8 164,505.00 0.1 4,125,785.40
m 192.6 237,105.00 0.1 50,233,065.30
m 37.95 1,259,910.96 0.1 52,594,983.03

m2 137.55 83,681.84 0.1 12,661,480.80


619.06 76,652.40 0.1 52,197,678.22
m2 1017.47 52,892.40 0.1 59,198,073.25
m2 1164 52,892.40 0.1 67,723,428.96

ttk 93 276,265.00 0.1 28,261,909.50


ttk 40 276,265.00 0.1 12,155,660.00
bh 12 578,380.00 0.1 7,634,616.00
bh 45 162,360.00 0.1 8,036,820.00
bh 36 178,860.00 0.1 7,082,856.00
bh 40 50,820.00 0.1 2,236,080.00
bh 19 50,820.00 0.1 1,062,138.00
bh 24 58,520.00 0.1 1,544,928.00
bh 7 240,900.00 0.1 1,854,930.00
unit 1 427,900.00 0.1 470,690.00

m 24 188,006.50 0.1 4,963,371.60


m 24 127,492.75 0.1 3,365,808.60
m 24 74,404.00 0.1 1,964,265.60
m 12 69,206.50 0.1 913,525.80
bh 23 3,203,398.00 0.1 81,045,969.40
bh 4 2,284,645.00 0.1 10,052,438.00
bh 23 243,430.00 0.1 6,158,779.00
bh 28 132,055.00 0.1 4,067,294.00
bh 27 48,180.00 0.1 1,430,946.00
m2 2 271,535.00 0.1 597,377.00
unit 4 12,500,000.00 0.1 55,000,000.00
unit 4 1,232,440.00 0.1 5,422,736.00

Ls 1 25,000,000.00 0.1 27,500,000.00

m2 125.4 24,000.00 0.1 3,310,560.00


m3 4.27 673,300.00 0.1 3,162,490.10
m2 189 3,000.00 0.1 623,700.00
m2 217.35 18,000.00 0.1 4,303,530.00
m2 217.35 12,000.00 0.1 2,869,020.00
ls 1 5,000,000.00 0.1 5,500,000.00

m2 28.53 324,624.30 0.1 10,187,684.41


m2 57.06 81,294.84 0.1 5,102,551.93
m2 57.06 48,400.00 0.1 3,037,874.40
m 95.1 31,724.00 0.1 3,318,647.64

m3 0.8 1,555,974.20 0.1 1,369,257.30


kg 112.98 20,219.10 0.1 2,512,789.31
m2 5.38 337,029.00 0.1 1,994,537.62

m3 3.37 1,425,169.90 0.1 5,283,104.82


m2 125.4 414,313.90 0.1 57,150,459.37
m 77.8 77,658.90 0.1 6,646,048.66

m 88.4 186,718.40 0.1 18,156,497.22


m 8.4 995,467.00 0.1 9,198,115.08
m2 10.8 285,285.00 0.1 3,389,185.80

psg 5 156,035.00 0.1 858,192.50


bh 5 77,880.00 0.1 428,340.00
bh 4 369,600.00 0.1 1,626,240.00

m2 189 175,890.00 0.1 36,567,531.00


m2 189 55,605.00 0.1 11,560,279.50
m 122 50,677.00 0.1 6,800,853.40
m2 217.35 319,825.00 0.1 76,465,360.13
m2 217.35 218,878.00 0.1 52,330,446.63
m 28 144,980.00 0.1 4,465,384.00
m 57.8 237,105.00 0.1 15,075,135.90
m 36 1,259,910.96 0.1 49,892,474.02

86.88 76,652.40 0.1 7,325,516.56


m2 137.92 52,892.40 0.1 8,024,411.79
m2 189 52,892.40 0.1 10,996,329.96

ttk 21 276,265.00 0.1 6,381,721.50


ttk 10 276,265.00 0.1 3,038,915.00
bh 18 578,380.00 0.1 11,451,924.00
bh 3 162,360.00 0.1 535,788.00
bh 10 50,820.00 0.1 559,020.00
bh 5 86,020.00 0.1 473,110.00
bh 7 58,520.00 0.1 450,604.00
bh 5 240,900.00 0.1 1,324,950.00
unit 1 427,900.00 0.1 470,690.00

Ls 1 25,000,000.00 0.1 27,500,000.00

m2 360 24,000.00 0.1 9,504,000.00


m3 20.8 673,300.00 0.1 15,405,104.00
m2 572 3,000.00 0.1 1,887,600.00
m2 657.8 18,000.00 0.1 13,024,440.00
m2 657.8 12,000.00 0.1 8,682,960.00
ls 4 8,000,000.00 0.1 35,200,000.00

m2 138.72 324,624.30 0.1 49,535,071.19


m2 277.44 81,294.84 0.1 24,809,884.45
m2 277.44 48,400.00 0.1 14,770,905.60
m 462.4 31,724.00 0.1 16,136,095.36

m3 3.56 1,555,974.20 0.1 6,093,194.97


kg 500.64 20,219.10 0.1 11,134,739.25
m2 23.84 337,029.00 0.1 8,838,248.50
m3 10.92 1,425,169.90 0.1 17,119,140.84
m2 342 336,301.90 0.1 126,516,774.78
m2 18 368,989.50 0.1 7,305,992.10
m2 83.2 406,967.00 0.1 37,245,619.84
m 416 77,658.90 0.1 35,536,712.64

m 584 186,718.40 0.1 119,947,900.16


m2 58.8 863,060.00 0.1 55,822,720.80
m2 61.44 850,267.00 0.1 57,464,444.93
m2 32 285,285.00 0.1 10,042,032.00

psg 64 183,535.00 0.1 12,920,864.00


bh 64 94,380.00 0.1 6,644,352.00
psg 40 156,035.00 0.1 6,865,540.00
bh 40 77,880.00 0.1 3,426,720.00
bh 40 369,600.00 0.1 16,262,400.00

m2 572 175,890.00 0.1 110,669,988.00


m2 572 55,605.00 0.1 34,986,666.00
m 572 50,677.00 0.1 31,885,968.40

m2 657.8 319,825.00 0.1 231,418,973.50


m2 657.8 218,878.00 0.1 158,375,743.24
m 91.2 144,980.00 0.1 14,544,393.60
m 194.4 237,105.00 0.1 50,702,533.20
m 10.8 1,259,910.96 0.1 14,967,742.20

m2 58.8 83,681.84 0.1 5,412,541.41


m2 374.4 76,652.40 0.1 31,568,524.42
m2 617.36 52,892.40 0.1 35,919,017.27
m2 572 52,892.40 0.1 33,279,898.08

ttk 48 276,265.00 0.1 14,586,792.00


ttk 32 276,265.00 0.1 9,724,528.00
bh 16 162,360.00 0.1 2,857,536.00
bh 32 178,860.00 0.1 6,295,872.00
bh 32 50,820.00 0.1 1,788,864.00
bh 32 50,820.00 0.1 1,788,864.00
bh 8 58,520.00 0.1 514,976.00
bh 8 240,900.00 0.1 2,119,920.00
unit 8 427,900.00 0.1 3,765,520.00

m 64 188,006.50 0.1 13,235,657.60


m 64 127,492.75 0.1 8,975,489.60
m 64 74,404.00 0.1 5,238,041.60
m 32 69,206.50 0.1 2,436,068.80
bh 8 3,203,398.00 0.1 28,189,902.40
bh 8 243,430.00 0.1 2,142,184.00
bh 16 132,055.00 0.1 2,324,168.00
bh 8 48,180.00 0.1 423,984.00
unit 8 12,500,000.00 0.1 110,000,000.00

Ls 4 25,000,000.00 0.1 110,000,000.00

Ls 1 180,000,000.00 0.1 198,000,000.00


m 415 315,000.00 0.1 143,797,500.00
m 368 245,000.00 0.1 99,176,000.00
m 40 200,000.00 0.1 8,800,000.00
m 60 185,000.00 0.1 12,210,000.00
m 45 160,000.00 0.1 7,920,000.00
m 90 140,000.00 0.1 13,860,000.00
Unit 1 6,000,000.00 0.1 6,600,000.00
Unit 1 31,895,250.00 0.1 35,084,775.00
Unit 2 6,214,968.00 0.1 13,672,929.60
Unit 1 6,754,824.00 0.1 7,430,306.40
Unit 2 6,214,968.00 0.1 13,672,929.60
Unit 65 19,500,000.00 0.1 1,394,250,000.00
Unit 8 27,500,000.00 0.1 242,000,000.00
Unit 50 12,500,000.00 0.1 687,500,000.00

titik 3 11,594,000.00 0.1 38,260,200.00


m 100 1,093,966.50 0.1 120,336,315.00
m 100 1,011,835.00 0.1 111,301,850.00
m 60 344,630.00 0.1 22,745,580.00
m 40 345,895.00 0.1 15,219,380.00
m3 1 2,223,320.00 0.1 2,445,652.00
ls 1 2,000,000.00 0.1 2,200,000.00
jam 24 429,055.00 0.1 11,327,052.00
ls 1 330,000.00 0.1 363,000.00

bh 10 20,000.00 0.1 220,000.00


bh 1 30,000.00 0.1 33,000.00
m 90 140,000.00 0.1 13,860,000.00
Unit 1 20,000,000.00 0.1 22,000,000.00

Unit 1 15,000,000.00 0.1 16,500,000.00


m 200 80,000.00 0.1 17,600,000.00
m 10 80,000.00 0.1 880,000.00
m 25 15,000.00 0.1 412,500.00

ls 1 15,000,000.00 0.1 16,500,000.00


m2 192 76,652.40 0.1 16,188,986.88
m 380 270,583.50 0.1 113,103,903.00
m 110 191,041.83 0.1 23,116,061.83
m 120 282,083.50 0.1 37,235,022.00
bh 65 27,500.00 0.1 1,966,250.00
bh 20 22,000.00 0.1 484,000.00
bh 4 82,500.00 0.1 363,000.00
bh 8 95,000.00 0.1 836,000.00
bh 6 42,500.00 0.1 280,500.00
bh 12 72,500.00 0.1 957,000.00
bh 3 1,350,000.00 0.1 4,455,000.00
bh 6 600,000.00 0.1 3,960,000.00
m3 73.5 88,000.00 0.1 7,114,800.00
m3 2.45 352,000.00 0.1 948,640.00
m3 0.72 1,648,237.80 0.1 1,305,404.34
kg 64.8 20,219.10 0.1 1,441,217.45
m2 0.864 172,238.00 0.1 163,695.00

m 2694 1,050,000.00 0.1 3,111,570,000.00


ton 536.106 450,000.00 0.1 265,372,470.00
bh 449 479,205.00 0.1 236,679,349.50
m 1536 651,935.00 0.1 1,101,509,376.00
bh 449 236,152.50 0.1 116,635,719.75
m3 148.0353 352,000.00 0.1 57,319,268.16
m3 37.68 1,648,237.80 0.1 68,316,160.33
kg 2160.5712 20,219.10 0.1 48,053,285.66
m2 100.3 325,479.00 0.1 35,910,098.07
m3 117.9648 1,648,237.80 0.1 213,877,446.67
kg 17104.896 20,219.10 0.1 380,430,162.98
m2 235.9296 337,029.00 0.1 87,466,628.87
m3 108.416 1,648,237.80 0.1 196,564,884.26
kg 13009.92 20,219.10 0.1 289,353,760.82
m2 735.68 337,029.00 0.1 272,740,044.19
m3 42.24 1,648,237.80 0.1 76,583,721.14
kg 5068.8 20,219.10 0.1 112,735,231.49
m2 316.8 337,029.00 0.1 117,447,865.92
m3 179.25 1,648,237.80 0.1 324,991,288.22
kg 12547.5 20,219.10 0.1 279,069,072.98
m2 735 325,479.00 0.1 263,149,771.50
m3 11.96 1,555,974.20 0.1 20,470,396.58
kg 1076.4 20,219.10 0.1 23,940,223.16
m2 14.352 179,113.00 0.1 2,827,692.75

m2 90.09 76,652.40 0.1 7,596,176.19


bh 15 9,000,000.00 0.1 148,500,000.00
bh 8 3,250,000.00 0.1 28,600,000.00
m 22.5 100,000.00 0.1 2,475,000.00

m3 5281 312,400.00 0.1 1,814,762,840.00

m2 9603 265,937.50 0.1 2,809,177,593.75


m3 124.2 1,648,237.80 0.1 225,182,248.24
kg 4968 20,219.10 0.1 110,493,337.68
m2 102.34 172,238.00 0.1 19,389,520.61
m2 7200 4,890.78 0.1 38,734,977.60
m3 2775 570,114.26 0.1 1,740,273,789.94
L 7200 16,522.92 0.1 130,861,526.40
ton 3360 1,879,375.57 0.1 6,946,172,106.72

m3 840 88,000.00 0.1 81,312,000.00


m3 540 312,400.00 0.1 185,565,600.00
m3 888.6375 1,165,604.00 0.1 1,139,379,367.01
m2 4080 81,294.84 0.1 364,851,241.92
m3 108 1,555,974.20 0.1 184,849,734.96
kg 5130 20,219.10 0.1 114,096,381.30
m2 502 172,238.00 0.1 95,109,823.60
titik 240 125,000.00 0.1 33,000,000.00
m3 144 352,000.00 0.1 55,756,800.00
m3 100.8 1,425,169.90 0.1 158,022,838.51
m3 67.575 1,648,237.80 0.1 122,517,636.27
kg 2703 20,219.10 0.1 60,117,450.03
m2 39.72 172,238.00 0.1 7,525,422.70
bh 4 2,500,000.00 0.1 11,000,000.00
m3 216 1,425,169.90 0.1 338,620,368.24
m2 1560 357,822.50 0.1 614,023,410.00
m2 240 265,937.50 0.1 70,207,500.00
m3 12.2 1,648,237.80 0.1 22,119,351.28
m2 76.5 1,073,079.48 0.1 90,299,638.24
paket 1 2,000,000.00 0.1 2,200,000.00
bh 40 675,000.00 0.1 29,700,000.00

m3 44.8 92,000.00 0.1 4,533,760.00


m3 15.68 30,666.66 0.1 528,938.55
m3 3.92 230,000.00 0.1 991,760.00
m3 0.14 1,351,813.50 0.1 208,179.28
m3 0.64 1,472,588.80 0.1 1,036,702.52
kg 32 19,501.12 0.1 686,439.42
m2 1.6 156,227.50 0.1 274,960.40
m3 2.16 1,472,588.80 0.1 3,498,870.99
kg 129.6 19,501.12 0.1 2,780,079.67
m2 8.64 326,513.75 0.1 3,103,186.68
m3 0.56 1,472,588.80 0.1 907,114.70
kg 33.84 19,501.12 0.1 725,909.69
m2 2.25 160,827.50 0.1 398,048.06
m3 3.55 1,472,588.80 0.1 5,750,459.26
kg 426.6 19,501.12 0.1 9,151,095.57
m2 28.44 336,173.75 0.1 10,516,859.60
m2 26.25 48,420.75 0.1 1,398,149.16
m2 26.25 29,695.87 0.1 857,468.25
m2 5.5 1,094,412.45 0.1 6,621,195.32
m2 5.5 90,614.25 0.1 548,216.21
ls 1 15,000,000.00 0.1 16,500,000.00

m3 9721 134,205.00 0.1 1,435,067,485.50


bh 200 2,026,875.00 0.1 445,912,500.00
m3 26.032 88,000.00 0.1 2,519,897.60
m3 2.208 29,333.33 0.1 71,244.80
m3 3 312,400.00 0.1 1,030,920.00
m3 0.128 352,000.00 0.1 49,561.60
m3 0.75 352,000.00 0.1 290,400.00

m2 49 81,294.84 0.1 4,381,791.88


m3 4.05 1,165,604.00 0.1 5,192,765.82
m2 49 48,400.00 0.1 2,608,760.00
m2 10.5 324,624.30 0.1 3,749,410.67

m3 4.5 1,648,237.80 0.1 8,158,777.11


m3 12.72 1,648,237.80 0.1 23,062,143.30
kg 6 325,479.00 0.1 2,148,161.40
m3 293 20,219.10 0.1 6,516,615.93
bh 40 250,000.00 0.1 11,000,000.00

m3 0.64 1,648,237.80 0.1 1,160,359.41


kg 76.184 20,219.10 0.1 1,694,409.11
m2 3.2 325,479.00 0.1 1,145,686.08
m3 2.05625 1,648,237.80 0.1 3,728,107.87
kg 306.60432 20,219.10 0.1 6,819,189.67
m2 32.9 325,479.00 0.1 11,779,085.01
m3 2.1 1,648,237.80 0.1 3,807,429.32
kg 211.3489 20,219.10 0.1 4,700,613.00
m2 16.8 179,113.00 0.1 3,310,008.24
m3 5.315625 1,648,237.80 0.1 9,637,555.46
kg 387.1665 20,219.10 0.1 8,610,974.00
m2 108.675 337,029.00 0.1 40,289,289.23
m3 7.35 1,648,237.80 0.1 13,326,002.61
kg 502.89167 20,219.10 0.1 11,184,818.59
m2 67.55 325,479.00 0.1 24,184,717.10

98 76,652.40 0.1 8,263,128.72

unit 1 3,750,000.00 0.1 4,125,000.00


ttk 1 276,265.00 0.1 303,891.50
ttk 1 276,265.00 0.1 303,891.50
bh 2 578,380.00 0.1 1,272,436.00
bh 2 50,820.00 0.1 111,804.00
bh 1 50,820.00 0.1 55,902.00
bh 1 240,900.00 0.1 264,990.00
unit 1 427,900.00 0.1 470,690.00

Ls 1 250,000,000.00 0.1 275,000,000.00

m3 25.2 88,000.00 0.1 2,439,360.00


m3 90 312,400.00 0.1 30,927,600.00
m3 2.1 352,000.00 0.1 813,120.00
m3 3.75 352,000.00 0.1 1,452,000.00

m3 58.8 1,165,604.00 0.1 75,391,266.72


m2 154.2 81,294.84 0.1 13,789,230.76

m3 11.25 1,425,169.90 0.1 17,636,477.51


kg 649.995 20,219.10 0.1 14,456,545.29
m2 6.75 325,479.00 0.1 2,416,681.58
m3 5.25 1,425,169.90 0.1 8,230,356.17
kg 607.5 20,219.10 0.1 13,511,413.58
m2 42 337,029.00 0.1 15,570,739.80

Ls 1 25,000,000.00 0.1 27,500,000.00


Bh 8 1,750,000.00 0.1 15,400,000.00

m3 119.556 88,000.00 0.1 11,573,020.80


m3 264.405 88,000.00 0.1 25,594,404.00
m3 122.28 312,400.00 0.1 42,020,299.20
m3 9.915 352,000.00 0.1 3,839,088.00
m3 66.42 352,000.00 0.1 25,717,824.00

m3 388.32 1,165,604.00 0.1 497,890,079.81


m2 2508.376 81,294.84 0.1 224,309,828.14
m3 19.926 1,425,169.90 0.1 31,237,728.97
kg 143.91 20,219.10 0.1 3,200,703.75
m2 5.508 325,479.00 0.1 1,972,012.17

Ls 1 25,000,000.00 0.1 27,500,000.00

Bh 300 75,000.00 0.1 24,750,000.00


Bh 300 10,000.00 0.1 3,300,000.00
Pcs 300 25,000.00 0.1 8,250,000.00
Pcs 250 150,000.00 0.1 41,250,000.00
Bh 300 60,000.00 0.1 19,800,000.00
Bh 150 175,000.00 0.1 28,875,000.00

Set 1 5,000,000.00 0.1 5,500,000.00

Bh 20 150,000.00 0.1 3,300,000.00


Ls 1 10,000,000.00 0.1 11,000,000.00
Titik 5 1,000,000.00 0.1 5,500,000.00
Titik 3 1,700,000.00 0.1 5,610,000.00

37,627,657,258.04