Anda di halaman 1dari 10

KEPOLISIAN NEGARA REPUBLIK INDONESIA

DAERAH JAWA TIMUR


RESORT GRESIK

Lampiran I
Nomor : .................................
Tanggal : Januari 2019
Tentang : Penetapan Harga Perkiraan Sendiri (HPS) untuk paket pekerjaan Harwat
bangunan gedung kantor dan harwat halaman pada Polres Gresik T.A 2019.

REKAPITULASI HARGA PERKIRAAN SENDIRI

NO KOMPONEN PEKERJAAN VOL. SAT. HARGA SATUAN JMLH HARGA


(Rp.) (Rp.)
1 PEKERJAAN PERSIAPAN 1 Ls 7.500.000 7.500.000
2 PEKERJAAN RUANG SELASAR DAMPING R. KAPOLRES 1 Gdg 25.709.031 25.709.031
3 PEKERJAAN RUANG SUBAG UMUM 1 Gdg 12.183.920 12.183.920
4 PEKERJAAN RUANG SAT. NARKOBA 1 Gdg 10.877.374 10.877.374
5 PEKERJAAN RUANG SAT. RESKRIM + KAMAR 1 Gdg 52.362.654 52.362.654
MANDI
6 PEKERJAAN RUANG BAG. SUMDA 1 Gdg 51.936.978 51.936.978
7 PEKERJAAN RUANG MIN. OPS. 1 Gdg 12.167.789 12.167.789
8 PEKERJAAN RUANG DEPAN GUDANG SKCK 1 Gdg 7.704.175 7.704.175
9 PEKERJAAN RUANG KASI KEU. 1 Gdg 7.643.033 7.643.033
10 PEKERJAAN RUANG PINTU MASUK KAPOLRES 1 Gdg 3.500.000 3.500.000
11 PEKERJAAN RUANG SUBAG. DALOPS 1 Gdg 6.918.869 6.918.869
12 PEKERJAAN RUANG SUBAG. BINOPS 1 Gdg 7.200.318 7.200.318
13 PEKERJAAN RUANG SABARA 1 Gdg 5.696.599 5.696.599
14 PEKERJAAN RUANG TAHANAN 1 Gdg 26.145.243 26.145.243
15 PEKERJAAN RUANG TINDAK PIDANA EKONOMI 1 Gdg 5.827.458 5.827.458
16 PEKERJAAN RUANG SIUM 1 Gdg 15.500.000 15.500.000
17 PEKERJAAN GAPURA PINTU MASUK 1 Gdg 5.494.340 5.494.340
18 PEKERJAAN RUANG SAPRAS 1 Gdg 6.180.263 6.180.263
19 PEKERJAAN ATAP GARASI 1 Pkt 9.999.712 9.999.712
Jumlah Total 280.547.756
Harga sudah termasuk pajak

Terbilang : Dua ratus delapan puluh juta lima ratus empat puluh tujuh ribu tujuh ratus lima
puluh delapan rupiah.

Ditetapkan di : Gresik
Pada tanggal : .................
PEJABAT PEMBUAT KOMITMEN

SHOLEH LUKMAN HADI, S.H.


AKP / 64060124
KEPOLISIAN NEGARA REPUBLIK INDONESIA
DAERAH JAWA TIMUR
RESORT GRESIK

Lampiran I
Nomor : ............................
Tanggal : ...................
Tentang : Penetapan Harga Perkiraan Sendiri (HPS) untuk paket pekerjaan Harwat bangunan
gedung kantor dan harwat halaman pada Polres Gresik

HARGA PERKIRAAN SENDIRI

NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA


             
I   PEKERJAAN PERSIAPAN        
1   Survey Data dan Pengukuran ls Rp 2.500.000 Rp 2.500.000
1,00
2   Pembersihan ls Rp 5.000.000 Rp 5.000.000
1,00
    Sub Total Rp 7.500.000
PEKERJAAN RUANG SELASAR
II          
SAMPING R. KAPOLRES
1   Bongkar Plafond M² Rp 27.981 Rp 811.456
29,00
2   Perbaikan Atap Bocor M² Rp 144.728 Rp 12.591.345
87,00
3   Pasang Plafon M² Rp 192.971 Rp 8.490.715
44,00
4   Pengecatan Plafon M² Rp 36.269 Rp 1.595.843
44,00
5   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 2.219.672
61,20
    Sub Total Rp 25.709.031
III   PEKERJAAN RUANG Subag Hukum        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 6.440.400
44,50
2   Perbaikan Plafon M² Rp 192.971 Rp 1.883.395
9,76
3   Pengecatan Plafon M² Rp 36.269 Rp 680.409
18,76
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.179.716
87,67
    Sub Total Rp 12.183.920
IV   PEKERJAAN RUANG Sat. Narkoba        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 4.848.391
33,50
2   Perbaikan Plafon M² Rp 192.971 Rp 2.275.126
11,79
3   Pengecatan Plafon M² Rp 36.269 Rp 634.710
17,50
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.119.147
86,00
    Sub Total Rp 10.877.374
PEKERJAAN RUANG Sat. Reskrim +
V          
Kamar Mandi
1   Perbaikan Atap Spandek M² Rp 256.389 Rp 19.936.774
77,76
2   Perbaikan Atap Asbes M² Rp 144.728 Rp 17.936.153
123,93
3   Nok/wuwung asbes M1 Rp 121.000 Rp 2.940.300
24,30
4   Perbaikan Talang M1 Rp 206.674 Rp 2.831.434
13,70
5   Perbaikan Plafon M² Rp 192.971 Rp 3.473.474
18,00
6   Pengecatan Plafon M² Rp 36.269 Rp 1.305.689
36,00
1
7   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.938.830
08,60
    Sub Total Rp 52.362.654
VI   PEKERJAAN RUANG Bag. Sumda        
1   Perbaikan Atap Spandek yang Bocor M² Rp 256.389 Rp 19.762.429
77,08
2   Perbaikan Talang Datar M1 Rp 206.674 Rp 4.856.840
23,50
3   Perbaikan Plafon M² Rp 192.971 Rp 7.718.832
40,00
4   Pengecatan Plafon M² Rp 36.269 Rp 2.618.633
72,20
Bongkar + Pasang Lisplank Baru dari
5   m1 Rp 325.000 Rp 7.637.500
kalsi L=40cm 23,50
6   Pengecatan Lispank M² Rp 36.269 Rp 681.860
18,80
1
7   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 6.360.884
75,38
8   Bongkar + Ganti Kusen Jendela unit Rp 2.300.000 Rp 2.300.000
1,00
    Sub Total Rp 51.936.978
VII   PEKERJAAN RUANG Min. Ops        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 4.153.696
28,70
2   Perbaikan Plafon M² Rp 192.971 Rp 3.589.257
18,60
3   Pengecatan Plafon M² Rp 36.269 Rp 1.269.420
35,00
Pengecatan dinding Ruang Dalam ruang
4   M² Rp 36.269 Rp 3.155.416
Min. Ops 87,00
    Sub Total Rp 12.167.789
PEKERJAAN RUANG Depan Gudang
VIII          
SKCK
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 1.490.699
10,30
2   Perbaikan Plafon M² Rp 192.971 Rp 2.574.230
13,34
3   Pengecatan Plafon M² Rp 36.269 Rp 483.830
13,34
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.155.416
87,00
    Sub Total Rp 7.704.175

IX   PEKERJAAN RUANG Kasi. Keu        


1   Perbaikan Atap Bocor M² Rp 144.728 Rp 1.736.737
12,00
2   Perbaikan Plafon M² Rp 192.971 Rp 2.315.650
12,00
3   Pengecatan Plafon M² Rp 36.269 Rp 435.230
12,00
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.155.416
87,00
    Sub Total Rp 7.643.033
PEKERJAAN RUANG Pintu Masuk
X          
Kapolres
Perbaikan Kusen Alminium Kemasukan
1   M1 Rp 125.000 Rp 3.500.000
air 28,00
    Sub Total Rp 3.500.000
XI   PEKERJAAN RUANG Subag. Dalops        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 1.519.645
10,50
2   Perbaikan Plafon M² Rp 192.971 Rp 2.026.193
10,50
3   Pengecatan Plafon M² Rp 36.269 Rp 565.799
15,60
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 2.807.232
77,40
    Sub Total Rp 6.918.869
XII   PEKERJAAN RUANG Subag. Binops        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 1.519.645
10,50
2   Perbaikan Plafon M² Rp 192.971 Rp 2.026.193
10,50
3   Pengecatan Plafon M² Rp 36.269 Rp 565.799
15,60
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 3.088.681
85,16
    Sub Total Rp 7.200.318
XIII   PEKERJAAN RUANG Sabara        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 1.519.645
10,50
2   Perbaikan Plafon M² Rp 192.971 Rp 2.026.193
10,50
3   Pengecatan Plafon M² Rp 36.269 Rp 605.695
16,70
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 1.545.066
42,60
    Sub Total Rp 5.696.599
XIV   PEKERJAAN RUANG Tahanan        
1   Perbaikan Atap Bocor M² Rp 144.728 Rp 6.512.765
45,00
2   Perbaikan Plafon M² Rp 192.971 Rp 14.665.781
76,00
3   Pengecatan Plafon M² Rp 36.269 Rp 2.756.455
76,00
4   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 2.210.242
60,94
    Sub Total Rp 26.145.243
PEKERJAAN RUANG Tindak Pidana
XV          
Ekonomi
1   Perbaikan Talang Datar M² Rp 206.674 Rp 1.426.051
6,90
2   Perbaikan Plafon M² Rp 192.971 Rp 3.705.039
19,20
3   Pengecatan Plafon M² Rp 36.269 Rp 696.368
19,20
    Sub Total Rp 5.827.458
XVI   PEKERJAAN RUANG Sium        
Pembuatan Kichen shet Beserta
1   ls Rp 5.500.000 Rp 5.500.000
aksesoris kran 1,00
2   Mebeler area kitchenshet ls Rp 10.000.000 Rp 10.000.000
1,00
    Sub Total Rp 15.500.000
XVII   PEKERJAAN Gapura Pintu Masuk        
1   Pengecatan Ulang dinding gapura M² Rp 49.622 Rp 3.349.451
67,50
2   Pengecatan Ulang genteng M² Rp 49.622 Rp 2.144.889
43,23
  Sub Total Rp 5.494.340
XVII
  PEKERJAAN RUANG Sapras        
I
1   Pengecatan Plafon M² Rp 36.269 Rp 1.450.766
40,00
1
2   Pengecatan dinding Ruang Dalam M² Rp 36.269 Rp 4.729.497
30,40
    Sub Total Rp 6.180.263
XIX   PEKERJAAN ATAP GARASI        
1   Bongkar Penutup Canopi Lama 79,44 M² Rp 5.482 Rp 435.458
Pasang Penutup Canopi Polycarbonat
2   79,44 M² Rp 120.400 Rp 9.564.254
Lengkung
    Sub Total Rp 9.999.712
             

Ditetapkan di : GRESIK
Pada tanggal : ..................
PEJABAT PEMBUAT KOMITMEN

SHOLEH LUKMAN HADI, SH.


AKP / 64060124
KEPOLISIAN NEGARA REPUBLIK INDONESIA
DAERAH JAWA TIMUR
RESORT GRESIK

Lampiran I
Nomor : ..............
Tanggal : ..............
Tentang : Penetapan Harga Perkiraan Sendiri (HPS) untuk paket pekerjaan Harwat bangunan
gedung kantor dan harwat halaman pada Polres Gresik.

BILL OF QUANTITY (B / Q)

NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA

             

I   PEKERJAAN PERSIAPAN        

1   Survey Data dan Pengukuran ls ................................. .................................


1,00
2   Pembersihan ls ................................. .................................
1,00
    Sub Total .................................
PEKERJAAN RUANG SELASAR
II          
SAMPING R. KAPOLRES
................................. .................................
1   Bongkar Plafond M²
29,00
................................. .................................
2   Perbaikan Atap Bocor M²
87,00
................................. .................................
3   Pasang Plafon M²
44,00
................................. .................................
4   Pengecatan Plafon M²
44,00
................................. .................................
5   Pengecatan dinding Ruang Dalam M²
61,20
    Sub Total .................................
III   PEKERJAAN RUANG Subag Hukum        
................................. .................................
1   Perbaikan Atap Bocor M²
44,50
................................. .................................
2   Perbaikan Plafon M²
9,76
................................. .................................
3   Pengecatan Plafon M²
18,76
................................. .................................
4   Pengecatan dinding Ruang Dalam M²
87,67
    Sub Total .................................
IV   PEKERJAAN RUANG Sat. Narkoba        
.................................
1   Perbaikan Atap Bocor M² .................................
33,50
.................................
2   Perbaikan Plafon M² .................................
11,79
3   Pengecatan Plafon M² ................................. .................................
17,50
4   Pengecatan dinding Ruang Dalam M² ................................. .................................
86,00
    Sub Total .................................

PEKERJAAN RUANG Sat. Reskrim +


V          
Kamar Mandi
................................. .................................
1   Perbaikan Atap Spandek M²
77,76
................................. .................................
2   Perbaikan Atap Asbes M²
123,93
................................. .................................
3   Nok/wuwung asbes M1
24,30
................................. .................................
4   Perbaikan Talang M1
13,70
................................. .................................
5   Perbaikan Plafon M²
18,00
................................. .................................
6   Pengecatan Plafon M²
36,00
1 ................................. .................................
7   Pengecatan dinding Ruang Dalam M²
08,60
    Sub Total
VI   PEKERJAAN RUANG Bag. Sumda        
................................. .................................
1   Perbaikan Atap Spandek yang Bocor M²
77,08
................................. .................................
2   Perbaikan Talang Datar M1
23,50
................................. .................................
3   Perbaikan Plafon M²
40,00
................................. .................................
4   Pengecatan Plafon M²
72,20
Bongkar + Pasang Lisplank Baru dari ................................. .................................
5   m1
kalsi L=40cm 23,50
................................. .................................
6   Pengecatan Lispank M²
18,80
1 ................................. .................................
7   Pengecatan dinding Ruang Dalam M²
75,38
................................. .................................
8   Bongkar + Ganti Kusen Jendela unit
1,00
    Sub Total .................................
VII   PEKERJAAN RUANG Min. Ops        
................................. .................................
1   Perbaikan Atap Bocor M²
28,70
................................. .................................
2   Perbaikan Plafon M²
18,60
................................. .................................
3   Pengecatan Plafon M²
35,00
Pengecatan dinding Ruang Dalam ruang ................................. .................................
4   M²
Min. Ops 87,00
    Sub Total .................................
PEKERJAAN RUANG Depan Gudang
VIII          
SKCK
1   Perbaikan Atap Bocor M² ................................. .................................
10,30
................................. .................................
2   Perbaikan Plafon M²
13,34
................................. .................................
3   Pengecatan Plafon M²
13,34
................................. .................................
4   Pengecatan dinding Ruang Dalam M²
87,00
    Sub Total .................................

IX   PEKERJAAN RUANG Kasi. Keu        


................................ ................................
1   Perbaikan Atap Bocor M²
12,00
................................ ................................
2   Perbaikan Plafon M²
12,00
................................ ................................
3   Pengecatan Plafon M²
12,00
................................ ................................
4   Pengecatan dinding Ruang Dalam M²
87,00
    Sub Total ................................
PEKERJAAN RUANG Pintu Masuk
X          
Kapolres
Perbaikan Kusen Alminium Kemasukan
1   M1 ................................ ................................
air 28,00
    Sub Total ................................
XI   PEKERJAAN RUANG Subag. Dalops        
................................ ................................
1   Perbaikan Atap Bocor M²
10,50
................................ ................................
2   Perbaikan Plafon M²
10,50
................................ ................................
3   Pengecatan Plafon M²
15,60
................................ ................................
4   Pengecatan dinding Ruang Dalam M²
77,40
    Sub Total ................................
XII   PEKERJAAN RUANG Subag. Binops        
................................ ................................
1   Perbaikan Atap Bocor M²
10,50
................................ ................................
2   Perbaikan Plafon M²
10,50
................................ ................................
3   Pengecatan Plafon M²
15,60
................................ ................................
4   Pengecatan dinding Ruang Dalam M²
85,16
    Sub Total ................................
XIII   PEKERJAAN RUANG Sabara        
................................ ................................
1   Perbaikan Atap Bocor M²
10,50
................................ ................................
2   Perbaikan Plafon M²
10,50
................................ ................................
3   Pengecatan Plafon M²
16,70
................................ ................................
4   Pengecatan dinding Ruang Dalam M²
42,60
    Sub Total ................................
XIV   PEKERJAAN RUANG Tahanan        
................................ ................................
1   Perbaikan Atap Bocor M²
45,00
................................ ................................
2   Perbaikan Plafon M²
76,00
................................ ................................
3   Pengecatan Plafon M²
76,00
................................ ................................
4   Pengecatan dinding Ruang Dalam M²
60,94
    Sub Total ................................

PEKERJAAN RUANG Tindak Pidana


XV          
Ekonomi
................................ ................................
1   Perbaikan Talang Datar M²
6,90
................................ ................................
2   Perbaikan Plafon M²
19,20
................................ ................................
3   Pengecatan Plafon M²
19,20
    Sub Total ................................
XVI   PEKERJAAN RUANG Sium        
Pembuatan Kichen shet Beserta ................................ ................................
1   ls
aksesoris kran 1,00
................................ ................................
2   Mebeler area kitchenshet ls
1,00
    Sub Total ................................
XVII   PEKERJAAN Gapura Pintu Masuk        
................................ ................................
1   Pengecatan Ulang dinding gapura M²
67,50
................................ ................................
2   Pengecatan Ulang genteng M²
43,23
  Sub Total ................................
XVII
  PEKERJAAN RUANG Sapras        
I
................................ ................................
1   Pengecatan Plafon M²
40,00
1 ................................ ................................
2   Pengecatan dinding Ruang Dalam M²
30,40
    Sub Total ................................
XIX   PEKERJAAN HAR HALAMAN        
1   Bongkar Penutup Canopi Lama 79,44 M² ................................ ................................
Pasang Penutup Canopi Polycarbonat ................................ ................................
2   79,44 M²
Lengkung
    Sub Total ................................
             

Ditetapkan di : GRESIK
PEJABAT PEMBUAT
Pada tanggal : KOMITMEN
Januari 2019

SHOLEH LUKMAN HADI, S.H.


AKP / 64060124

Anda mungkin juga menyukai