A. PEKERJAAN PERSIAPAN
- Mobilisasi dan Demobilisasi 1.00 Ls 24,500,000.00 24,500,000.00
- Pembuatan Papan Proyek 1.00 Ls 1,000,000.00 1,000,000.00
- Pengukuran sebelum dan sesudah 14,000.00 m1 1,464.09 20,497,312.50
- Pembersihan Lahan 21,000.00 m2 15,375.68 322,889,220.20
- Pemasangan Bowplank 14,000.00 m' 26,787.81 375,029,375.00
B. PEKERJAAN KONSTRUKSI
- Galian tanah 4,247.17 M3 132,365.56 562,178,508.17
- Lantai Kerja 293.79 M3 937,522.50 275,434,852.47
- Pasir Urug 293.79 M3 321,037.50 94,317,647.25
- Bekisting 21,345.35 M2 126,616.00 2,702,662,835.60
- Pembesian 289,481.80 Kg 15,262.28 4,418,150,870.94
- Pondasi Beton Cor K-175 3,555.15 M3 1,390,454.75 4,943,269,990.26
- Fence Double Wire 200 + Pipa persegi 14,000.00 M' 1,419,012.50 19,866,175,000.00
- Kawat Silet 14,000.00 M' 102,132.50 1,429,855,000.00
- Pancang Kayu Galam Dia. 8 cm - 2 meter 19,600.00 Titik 66,060.00 1,294,776,000.00
TOTAL 36,330,736,612.38
PPN 10 % 3,633,073,661.24
GRAND TOTAL 39,963,810,273.62
PEMBULATAN 39,963,810,000.00
Terbilang :
Tiga Puluh Sembilan Milyar Sembilan Ratus Enam Puluh Tiga Juta Delapan Ratus Sepuluh Ribu Rupiah
Galian tanah
Pondasi Talud Type 1 1.00 1.00
Pondasi Talud Type 2 1.00 1.00
Pondasi Skur 1.00 1.00
Pondasi Tanpa Skur 1.00 1.00
Sloof Talud 1.55 0.20
Sloof Pondasi 1.55 0.25
Lantai Kerja
Pondasi Talud Type 1 1.00 1.00 0.05
Pondasi Talud Type 2 1.00 1.00 0.05
Pondasi Skur 1.00 1.00 0.05
Pondasi Tanpa Skur 1.00 0.50 0.05
Sloof Talud 1.55 0.20 0.05
Sloof Pondasi 1.55 0.25 0.05
Pasir Urug
Pondasi Talud Type 1 1.00 1.00 0.05
Pondasi Talud Type 2 1.00 1.00 0.05
Pondasi Skur 1.00 1.00 0.05
Pondasi Tanpa Skur 1.00 0.50 0.05
Sloof Talud 1.55 0.20 0.05
Sloof Pondasi 1.55 0.25 0.05
Bekisting
Pondasi Talud Type 1
Sisi Kanan 1.00 1.00
Sisi Kiri 1.00 1.00
Depan 1.00 1.00
Belakang 1.00 1.00
Pembesian
Pondasi Talud Type 1
Diameter a b c d e f
12.00 0.95
10.00 0.25 0.90 0.25 0.90 0.20
10.00
12.00 0.95
10.00 0.70 0.30 0.70
10.00 0.50
Pondasi Skur
Diameter a b c d e f
12.00 0.95 0.45 0.95 0.45 0.20
12.00 0.95 0.45 0.95 0.45 0.20
Sloof Talud
Diameter a b c d e f
12.00 2.55
10.00 0.95 0.15 0.95 0.15 0.20
Sloof Pondasi
Diameter a b c d e f
12.00 2.55
10.00 0.45 0.20 0.45 0.20 0.20
4,247.17 m3
0.90 1,400.00 1,260.00 m3
0.90 1,400.00 1,260.00 m3
0.40 1,400.00 560.00 m3
0.40 1,400.00 560.00 m3
0.90 1,399.00 390.32 m3
0.40 1,399.00 216.85 m3
293.79 m3
1,400.00 70.00 m3
1,400.00 70.00 m3
1,400.00 70.00 m3
1,400.00 35.00 m3
1,399.00 21.68 m3
1,399.00 27.11 m3
293.79 m3
1,400.00 70.00 m3
1,400.00 70.00 m3
1,400.00 70.00 m3
1,400.00 35.00 m3
1,399.00 21.68 m3
1,399.00 27.11 m3
21,345.35 m2
1,400.00 1,400.00 m2
1,400.00 1,400.00 m2
1,400.00 1,400.00 m2
1,400.00 1,400.00 m2
1,400.00 910.00 m2
1,400.00 910.00 m2
1,400.00 1,120.00 m2
1,400.00 1,400.00 m2
1,400.00 2,800.00 m2
1,400.00 2,100.00 m2
1,399.00 4,336.90 m2
1,399.00 2,168.45 m2
289,481.80 kg
42.15 kg
panjang jumlah total panjang koefisien volume
0.95 12.00 11.40 0.888 10.12 kg
2.50 7.00 17.50 0.617 10.79 kg
2.10 7.00 14.70 0.617 9.06 kg
0.95 8.00 7.60 0.888 6.75 kg
1.70 4.00 6.80 0.617 4.19 kg
0.50 4.00 2.00 0.617 1.23 kg
36.72 kg
panjang jumlah total panjang koefisien volume
0.95 12.00 11.40 0.888 10.12 kg
2.50 7.00 17.50 0.617 10.79 kg
2.10 7.00 14.70 0.617 9.06 kg
0.95 8.00 7.60 0.888 6.75 kg
31.96 kg
panjang jumlah total panjang koefisien volume
3.00 6.00 18.00 0.888 15.98 kg
3.00 6.00 18.00 0.888 15.98 kg
26.37 kg
panjang jumlah total panjang koefisien volume
3.00 6.00 18.00 0.888 15.98 kg
1.95 6.00 11.70 0.888 10.39 kg
44.93 kg
panjang jumlah total panjang koefisien volume
2.55 12.00 30.60 0.888 27.17 kg
2.40 12.00 28.80 0.617 17.76 kg
24.68 kg
panjang jumlah total panjang koefisien volume
2.55 6.00 15.30 0.888 13.58 kg
1.50 12.00 18.00 0.617 11.10 kg
3,555.15 m3
1,400.00 812.00 m3
1,400.00 176.40 m3
1,400.00 812.00 m3
1,400.00 700.00 m3
1,400.00 350.00 m3
1,399.00 433.69 m3
1,399.00 271.06 m3
14,000.00 m1
II PERALATAN
1 Theodolite Jam 0.0038 50,000.00 187.50
2 Water Pass Jam 0.0035 21,428.57 75.00
3 Mistar ukur Jam 0.0035 7,142.86 25.00
4 Alat Bantu Ls 1.0000 500.00 500.00
Jumlah 1,464.09
overhead % Profit 10 %
Jumlah 1,464.09
1 m2 Pembersihan Lahan
Harga Satuan Jumlah Harga
No Uraian Satuan Kuantitas
(Rp) Satuan (Rp)
I UPAH
1 Pekerja OH 0.0545 150,000.00 8,175.00
2 Mandor OH 0.0091 183,750.00 1,672.13
II PERALATAN
1 Excavator Jam 0.0091 497,643.09 4,528.55
2 Alat bantu Ls 1.0000 1,000.00 1,000.00
Jumlah 15,375.68
overhead % Profit 10 %
Jumlah 15,375.68
II BAHAN
1 Kayu meranti balok m3 0.012 3,850,000.00 46,200.00
2 Paku biasa 2" - 5" Kg 0.020 30,000.00 600.00
3 Kayu meranti papan m3 0.007 3,850,000.00 26,950.00
Jumlah 107,151.25
overhead % Profit 10 %
Jumlah 107,151.25
Asumsi 4x Pakai 26,787.81
Pekerjaan : 1 M3 Galian Batu
II PERALATAN
Jumlah 132,365.56
overhead % Profit 10 %
Jumlah 132,365.56
Pekerjaan : Beton K - 175
II BAHAN
1 Portland Cement Kg 75.000 2,500.00 187,500.00
2 Aggregat 2-3 M3 1.029 720,000.00 740,880.00
3 Pasir M3 0.760 228,500.00 173,660.00
Jumlah 1,390,454.75
overhead % Profit 10 %
Jumlah 1,390,454.75
II BAHAN
1 Batu Lokal M3 1.200 350,000.00 420,000.00
2 Portland Cement Kg 100.000 2,500.00 250,000.00
3 Pasir M3 0.520 228,500.00 118,820.00
4 Concrete mixer Jam 1.000 20,000.00 20,000.00
5 Water tanker Jam 1.000 115,000.00 115,000.00
6 Alat bantu Ls 1.000 1,000.00 1,000.00
Jumlah 1,281,726.25
overhead % Profit 10 %
Jumlah 1,281,726.25
II BAHAN
1 Mur/baut buah 15.000 30,000.00 450,000.00
2 Klem buah 12.000 6,000.00 72,000.00
3 Wire mesh M6 M1 10.000 1,310,000.00 13,100,000.00
4 Pipa GIP persegi 1.5" dan tutup Pipa Batang 1.000 300,000.00 300,000.00
Jumlah 14,190,125.00
Harga per meter 1,419,012.50
overhead % Profit 10 %
Jumlah 1,419,012.50
ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2020
Alat :
- Molen 0.25 Hari 160,000.00 40,000.00
TOTAL 311,497.50 586,025.00 40,000.00 937,522.50
Pekerjaan Pembesian / 10 Kg
No. Uraian Koef Sat Harga Satuan Harga Upah Harga Bahan Harga alat Jumlah Harga
Upah :
- Pekerja 0.0700 Oh 150,000.00 10,500.00
- Tukang Batu 0.0700 Oh 157,500.00 11,025.00
- Kepala Tukang 0.0070 Oh 173,250.00 1,212.75
- Mandor 0.0040 Oh 183,750.00 735.00
Bahan :
- Besi beton 10.5000 KG 12,000.00 126,000.00
- Kawat beton 0.1500 Kg 21,000.00 3,150.00
TOTAL 23,472.75 129,150.00 152,622.75
Per Kg 15,262.28
Upah
No. Uraian Satuan Harian
(Rp.)
HARGA
No. URAIAN SATUAN KET
(Rp.)
Harga
No. Uraian Sewa/Jam Keterangan
(Rp.)
Harga
No. Uraian Sewa/Jam Keterangan
(Rp.)