No.

Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, Tgl. Efektif : 1 Oktober 2020
TENAGA, DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBER NUSANTARA


PROYEK : GEM CITY (21-03)
HARI / TANGGAL : Jumat, 19 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Pekerjaan Tanah
Urug Limestone Padat Dozer 123.947,20 86.819 1.506 88.325 m3 3.344,00 5.034.458,88

TOTAL PRODUKTIVITAS 5.034.458,88


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Dozer D65 52 230 9 380.000 3.420.000
2 Dozer D65 RENTAL 180 7 380.000 2.660.000
3 PC 200 209 90 7 285.000 1.995.000
4

TOTAL PENGELUARAN 8.075.000


TOTAL PRODUKTIVITAS (A) : Rp 5.034.459 PENGELUARAN (B): Rp 8.075.000 DEVIASI (C = A-B) : Rp - 3.040.541
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 Solar 590 1400 500 1.490
2
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 2.007,36 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1
T. HARIAN 2

Jumlah 7
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA
*) KETERANGAN 24 1 2 Kontraktor,
23 3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

10
: HUJAN : GERIMIS 11
12 13 14
15
No. Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, Tgl. Efektif : 1 Oktober 2020
TENAGA, DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBER NUSANTARA


PROYEK : GEM CITY (21-03)
HARI / TANGGAL : Sabtu, 20 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Pekerjaan Tanah
Urug Limestone Padat Dozer 123.947,20 88.325 1.698 90.023 m3 3.344,00 5.678.683,16

TOTAL PRODUKTIVITAS 5.678.683,16


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Dozer D65 52 200 8 380.000 3.040.000
2 Dozer D65 RENTAL - 0 380.000 0

TOTAL PENGELUARAN 3.040.000


TOTAL PRODUKTIVITAS (A) : Rp 5.678.683 PENGELUARAN (B): Rp 3.040.000 DEVIASI (C = A-B) : Rp 2.638.683
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 Solar 1.490 300 1.190
2
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 2.497,31 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1
T. HARIAN 2

Jumlah 7
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA
*) KETERANGAN 24 1 2 Kontraktor,
23 3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

10
: HUJAN : GERIMIS 11
12 13 14
15
No. Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, TENAGA, Tgl. Efektif : 1 Oktober 2020
DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBERNUSANTARA


PROYEK : Add GEM City Manyar (21-03)
HARI / TANGGAL : Sabtu, 20 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Galian lumpur diganti full limestone


Mobilisasi 1,00 ls 2.250.000
Demobilisasi 1,00 ls 2.250.000
Galian lumpur (asumsi vol 2 x 1 x 335m') 670,00 597 37 634 m3 13.714 507.418
Buang lumpur dalam lokasi jarak ±1km
-Buang 670,00 399 399 m3 14.769 0
-Perataan 670,00 222 222 m3 4.677 0
Timbunan limestone pengganti lumpur 670,00 573 46 619 m3 9.600 441.600
rata excavator

Urugan Limestone sd top +3.90


Timbunan limestone padat Dozer 2.757,36 m3 3.344

TOTAL PRODUKTIVITAS 949.018


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Exca PC 200 209 100 8 285.000 2.280.000

Dozer Rental 180

TOTAL PENGELUARAN 2.280.000


TOTAL PRODUKTIVITAS (A) : Rp 949.018 PENGELUARAN (B): Rp 2.280.000 DEVIASI (C = A-B) : Rp -1.330.982
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 SOLAR 1.490 300 1.190
2 BENSIN
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 2.497,31 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1

Jumlah 5
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA

*) coret salah satuKETERANGAN 23


24 1 2 Kontraktor,
3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

: HUJAN : GERIMIS
10
11 15
12 13 14
No. Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, Tgl. Efektif : 1 Oktober 2020
TENAGA, DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBER NUSANTARA


PROYEK : GEM CITY (21-03)
HARI / TANGGAL : Minggu, 21 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Pekerjaan Tanah
Urug Limestone Padat Dozer 123.947,20 90.023 1.306 91.329 m3 3.344,00 4.368.768,80

TOTAL PRODUKTIVITAS 4.368.768,80


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Dozer D65 52 200 8 380.000 3.040.000
2 Dozer D65 RENTAL - 0 380.000 0
3
4

TOTAL PENGELUARAN 3.040.000


TOTAL PRODUKTIVITAS (A) : Rp 4.368.769 PENGELUARAN (B): Rp 3.040.000 DEVIASI (C = A-B) : Rp 1.328.769
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 Solar 1.190 290 900
2
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 706,45 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1
T. HARIAN 2

Jumlah 7
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA
*) KETERANGAN 24 1 2 Kontraktor,
23 3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

10
: HUJAN : GERIMIS 11
12 13 14
15
No. Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, TENAGA, Tgl. Efektif : 1 Oktober 2020
DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBERNUSANTARA


PROYEK : Add GEM City Manyar (21-03)
HARI / TANGGAL : Minggu, 21 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Galian lumpur diganti full limestone


Mobilisasi 1,00 ls 2.250.000
Demobilisasi 1,00 ls 2.250.000
Galian lumpur (asumsi vol 2 x 1 x 335m') 670,00 634 36 670 m3 13.714 493.704
Buang lumpur dalam lokasi jarak ±1km
-Buang 670,00 399 399 m3 14.769 0
-Perataan 670,00 222 222 m3 4.677 0
Timbunan limestone pengganti lumpur 670,00 619 51 670 m3 9.600 489.600
rata excavator

Urugan Limestone sd top +3.90


Timbunan limestone padat Dozer 2.757,36 428 428 m3 3.344 1.431.232

TOTAL PRODUKTIVITAS 2.414.536


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Exca PC 200 209 90 7 285.000 1.995.000
2

TOTAL PENGELUARAN 1.995.000


TOTAL PRODUKTIVITAS (A) : Rp 2.414.536 PENGELUARAN (B): Rp 1.995.000 DEVIASI (C = A-B) : Rp 419.536
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 SOLAR 1.190 290 900
2 BENSIN
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 706,45 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1

Jumlah 5
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA

*) coret salah satuKETERANGAN 23


24 1 2 Kontraktor,
3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

: HUJAN : GERIMIS
10
11 15
12 13 14