LAPORAN HARIAN PROYEK (PRODUKTIVITAS, Tgl. Efektif : 1 Oktober 2020
TENAGA, DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBER NUSANTARA


PROYEK : GEM CITY (21-03)
HARI / TANGGAL : Jumat, 26 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Pekerjaan Tanah
Urug Limestone Padat Dozer 123.947,20 95.973 581 96.554 m3 3.344,00 1.942.864,00

TOTAL PRODUKTIVITAS 1.942.864,00


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Dozer D65 52 200 8 380.000 3.040.000
2 Dozer D65 RENTAL - 0 380.000 0

TOTAL PENGELUARAN 3.040.000


TOTAL PRODUKTIVITAS (A) : Rp 1.942.864 PENGELUARAN (B): Rp 3.040.000 DEVIASI (C = A-B) : Rp - 1.097.136
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 Solar 800 200 600
2
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 0,00 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1
T. HARIAN 2

Jumlah 7
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA
*) KETERANGAN 24 1 2 Kontraktor,
23 3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

10
: HUJAN : GERIMIS 11
12 13 14
15