No.

Dokumen : FM-PRY-01a
LAPORAN HARIAN PROYEK (PRODUKTIVITAS, Tgl. Efektif : 1 Oktober 2020
TENAGA, DAN BAHAN) No. Revisi : 0.0
Halaman :1/1

KONTRAKTOR : PT. SUMBER NUSANTARA


PROYEK : GEM CITY (21-03)
HARI / TANGGAL : Kamis, 25 Maret 2021
PRODUKTIVITAS
VOLUME
VOLUME s/d s/d HARI SATUAN HARGA JUMLAH
No PEKERJAAN HARI INI
KONTRAK KEMARIN INI
A B C = A+ B D E F=BxE

Pekerjaan Tanah
Urug Limestone Padat Dozer 123.947,20 94.967 1.006 95.973 m3 3.344,00 3.365.033,76

TOTAL PRODUKTIVITAS 3.365.033,76


PENGELUARAN
No. BBM (liter)
No ALAT BERAT JAM KERJA HARGA JUMLAH
LAMBUNG SOLAR BENSIN
1 Dozer D65 52 200 8 380.000 3.040.000
2 Dozer D65 RENTAL - 0 380.000 0

TOTAL PENGELUARAN 3.040.000


TOTAL PRODUKTIVITAS (A) : Rp 3.365.034 PENGELUARAN (B): Rp 3.040.000 DEVIASI (C = A-B) : Rp 325.034
BBM
STOK MASUK PAKAI SALDO
No JENIS BAHAN BAKAR KETERANGAN
(liter) (liter) (liter) (liter)
1 Solar 1.100 300 800
2
BAHAN-BAHAN YANG MASUK PEKERJAAN SIPIL YANG DILAKSANAKAN / TENAGA KERJA
JENIS BAHAN VOL SATUAN BAGIAN JUMLAH
Limestone 1.118,10 m3 SM 1
SURVEYOR 1
ADMIN 2
ASST SURVEY 1
T. HARIAN 2

Jumlah 7
: SEPENUHNYA *) Catatan :
HARI : SEBAGIAN TIDAK *)
DAPAT DIGUNAKAN UNTUK KERJA
*) KETERANGAN 23
24 1 2 Kontraktor,
3
22 PT. SUMBER NUSANTARA
JUMLAH JAM KERJA : JAM
21

4
18 19 20

5
6 7 8

: CERAH : BERAWAN
17
16

10
: HUJAN : GERIMIS 11
12 13 14
15