PERMOHONAN PENGAJUAN DANA

PENAWARAN SURVEY GEOTEKNIK


UNTUK PEMBANGUNAN JEMBATAN DI BERAU COAL
KABUPATEN BERAU
TAHUN 2014
Nego BCC
No. POSISI VOLUME ( RATE (Rp.) TOTAL (Rp.) Ket RATE (Rp.) TOTAL (Rp.) Ket
A Survey Geoteknik
I Mob / Demob 24,320,000 12,000,000
Sewa Truck ke Berau 1 PP 8,000,000 8,000,000 8,000,000 8,000,000
Sewa Penginapan 1 LS 4,000,000 4,000,000 4,000,000 0
Sewa Base Camp dilokasi 1 5 LS 5,000,000 5,000,000 (X) 5,000,000 2,000,000 (X)
Mob antar titik 6 x 5 HO 100,000 3,000,000 100,000 2,000,000
Nunggu induksi perusahaan 6 x 5 HO 100,000 3,000,000 (X) 100,000 0 (X)
Jaga Alat 6 x 2 HO 110,000 1,320,000 (X) 110,000 0 (X)

II Peralatan 31,100,000 25,650,000


Sondir 4 Titik 1,500,000 6,000,000 1,500,000 6,000,000
1 Bor Mesin 2 x 40 METER 250,000 20,000,000 250,000 15,000,000
Standart Penetration Test 2 x 13 Titik 75,000 1,950,000 75,000 1,500,000 30
Pengambilan Sample 2 x 1 Sample 75,000 150,000 75,000 150,000 10
Laboratorium 2 x 1 Sample 1,500,000 3,000,000 1,500,000 3,000,000
* Attergberg Limit
* Analisa Saringan
* Berat Volume
* Kadar Air dan Berat Isi
* Berat Jenis
* Direct Shear Test
* Unconfined Test

III Laporan 2,000,000 1,500,000


Laporan Penyelidikan Tanah 1 x 1 SET 2,000,000 2,000,000 1,500,000 1,500,000
dan foto dokumentasi
TOTAL 57,420,000 39,150,000
DP 20,000,000
SISA PEMBAYARAN 19,150,000
Ket : (X) Bila diperlukan

Nb : * Mohon segera ditransfer sisa pembayaran ke Rekening Bank Mandiri 148 000 4144 716 a/n Bapak Ir. I Putu Resika M, Sc