BILL OF QUANTITY

PEKERJAAN : PEMBUATAN KANOPI PARKIRAN


PROYEK : PT. GUDANG GARAM SURABAYA
CV. ANUGRAH JAYA ABADI

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOL
RP RP
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan + Pembersihan Akhir ls 1.0 Rp 3,000,000.00 Rp 3,000,000.00
2 Air Kerja ls 1.0 Rp 500,000.00 Rp 500,000.00
3 Listrik Kerja ls 1.0 Rp 1,500,000.00 Rp 1,500,000.00
TOTAL PEKERJAAN PERSIAPAN Rp 5,000,000.00

II PEKERJAAN GALIAN, PAVING, PONDASI & KOLOM


1 Galian Pondasi 80x60 t=100cm m³ 9.6 Rp 59,000.00 Rp 566,400.00
2 Urugan Sirtu Pondasi + Pemadatan m³ 8.2 Rp 250,000.00 Rp 2,050,000.00
3 Pondasi Tapak 80x60 Rp -
- Beton K300 m³ 2.8 Rp 980,000.00 Rp 2,744,000.00
- Besi Dia 13 kg 145.6 Rp 12,000.00 Rp 1,747,200.00
- Bekisting m² 6.0 Rp 125,000.00 Rp 750,000.00
4 Kolom Pedestal uk. 30x30 cm (10 kolom)
- Beton K300 m³ 3.8 Rp 980,000.00 Rp 3,724,000.00
- Besi Dia 6 kg 42.0 Rp 12,000.00 Rp 504,000.00
- Besi Dia 10 kg 74.0 Rp 12,000.00 Rp 888,000.00
- Pasang Angkur Nut Bolt 16" + Chemical pc 40.0 Rp 85,000.00 Rp 3,400,000.00
- Bekisting m² 8.0 Rp 275,000.00 Rp 2,200,000.00
5 Bongkar Pasang Paving Block m² 10.0 Rp 25,000.00 Rp 250,000.00
TOTAL PEKERJAAN GALIAN, PAVING, PONDASI & KOLOM Rp 18,823,600.00

IV PEKERJAAN KANOPI
1 Pekerjaan Struktur Kanopi Besi Pipa Galvanis
- Pipa 10" m¹ 30.0 Rp 1,850,000.00 Rp 55,500,000.00
- Pipa 4" m¹ 180.0 Rp 485,000.00 Rp 87,300,000.00
- Plat Penahan Ikatan + Nut Bolt kg 235.0 Rp 18,000.00 Rp 4,230,000.00
2 Pekerjaan Atap Zincalume + Rangka CNP 100 m² 330.0 Rp 225,000.00 Rp 74,250,000.00
TOTAL PEKERJAAN KANOPI Rp 221,280,000.00

V PEKERJAAN INSTALASI LISTRIK


1 Instalasi Kabel Lampu ttk 10.0 Rp 200,000.00 Rp 2,000,000.00
2 Instalasi Stop Kontak + Saklar Tunggal ttk 5.0 Rp 250,000.00 Rp 1,250,000.00
3 Kelengkapan lain :
- Lampu Gantung Industri Ø38cm unit 10.0 Rp 75,000.00 Rp 750,000.00
- Saklar Double unit 5.0 Rp 55,000.00 Rp 275,000.00
TOTAL PEKERJAAN INSTALASI LISTRIK Rp 4,275,000.00

JUMLAH TOTAL Rp 249,378,600.00