Pembuatan monitor stock untuk alat


1 100% 26/06/21 24/06/21 26/07/21 excel
kerja

pembuatan monitor stock untuk alat


2 100% 26/06/21 24/06/21 26/07/21 excel
ukur

3 barang aktiva 100% 26/07/21 26/07/21 26/07/21 excel

4 List Supplier 100% 10/08/21 03/08/21 10/08/21 excel

5 List Supplier revisi 100% 23/08/21 16/08/21 24/08/21 excel

6 List Supplier revisi ke 2 100% 26/08/21 25/08/21 26/08/21 excel

Report status barang aktifa( asset


7 100% 07/09/21 30/08/21 04/09/21 excel
MAI)

Report status barang aktifa( asset


8 50% 13/09/21 06/09/21 excel