MINGGU KE
NO JENIS PEKERJAAN KET
I II III IV
A PEMBANGUNAN KM/WC
I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
II. PEKERJAAN BETON
Menyetujui
Kepala Panitia Pelaksana Rehabilitasi
KB DARUL ULUM
KAYU
1 Kayu Jati Balok 8/12, 6/12 m3 Rp 10,901,250.00
2 Kayu Jati Usuk 5/7, 4/6 m3 Rp 10,602,000.00
3 Kayu Jati Papan 2/20 m3 Rp 11,328,750.00
4 Kayu Jati Reng 2/3, 3/5 m3 Rp 6,198,750.00
1 Kayu Meranti Balok 8/12, 6/12 m3 Rp 5,602,500.00
2 Kayu Meranti Usuk 5/7, 4/6 m3 Rp 4,876,200.00
3 Kayu Meranti Papan 2/20 m3 Rp 6,787,800.00
4 Kayu Meranti Reng 2/3, 3/5 m3 Rp 4,050,000.00
5 Kayu Kruing Balok 8/12, 6/12 m3 Rp 6,300,000.00
6 Kayu Kruing Usuk 5/7, 4/6 m3 Rp 4,500,000.00
7 Kayu Kruing Papan 2/20 m3 Rp 6,000,000.00
8 Kayu Kruing Reng 2/3, 3/5 m3 Rp 4,000,000.00
5 Kayu Kamper Balok 8/12, 6/12 m3 Rp 6,812,100.00
6 Kayu Kamper Usuk 5/7, 4/6 m3 Rp 6,409,800.00
7 Kayu Kamper Papan 2/20 m3 Rp 7,422,300.00
8 Kayu Kamper Reng 2/3, 3/5 m3 Rp 5,823,000.00
9 Kayu Bekisting Meranti (MC) Bekisting/Perancah m3 Rp 2,790,000.00
10 Dolken kayu gelam btg Rp 26,000.00
11 Triplek 3 mm (2.40 x 1.22) lbr Rp 56,250.00
12 Triplek 4 mm (2.40 x 1.22) lbr Rp 65,250.00
13 Triplek 9 mm (2.40 x 1.22) lbr Rp 112,500.00
14 Triplek 12 mm (2.40 x 1.22) lbr Rp 159,750.00
15 Triplek 18 mm (2.40 x 1.22) lbr Rp 202,500.00
16 Teak Wood 3 mm (2.40 x 1.22) lbr Rp 94,500.00
17 Teak Wood 4 mm (2.40 x 1.22) lbr Rp 108,000.00
18 Milamin 3 mm (2.40 x 1.22) lbr Rp 99,000.00
19 Milamin 4 mm (2.40 x 1.22) lbr Rp 108,000.00
20 Kusen + daun pintu PVC unit Rp 495,000.00
CAT - CATAN
1 Cat Tembok (Decolith/Vinilex) kg Rp 23,100.00
2 Cat Kayu (Emco) kg Rp 51,975.00
3 Cat Besi (Emco) kg Rp 51,975.00
3 Meni kg Rp 28,350.00
4 Plamur kg Rp 21,735.00
5 Politur kg Rp 56,700.00
6 Kuas bh Rp 9,450.00
7 Kertas Gosok Besi lbr Rp 5,000.00
8 Kertas Gosok Kayu lbr Rp 5,000.00
9 Kertas Gosok Tembok lbr Rp 5,000.00
10 Lem kayu kg Rp 11,000.00
11 Kapek bh Rp -
12 Wall Paper lebar 55 cm m' Rp -
13 Lem wallpaper kg Rp -
14 Dempul jadi impra kg Rp -
15 Plamur kayu kg Rp 21,735.00
16 Wood Filler kg Rp 27,000.00
17 Minyak Tanah ltr Rp 11,250.00
18 Solar ltr Rp 7,200.00
19 Premium ltr Rp 5,895.00
20 Pelumas/Olie ltr Rp 40,500.00
21 Minyak Aspal ltr Rp 20,000.00
22 Minyak Cat/Thinner A ltr Rp 25,000.00
23 Minyak Cat/Thinner B ltr Rp 19,800.00
24 Spirtus ltr Rp 13,500.00
25 Minyak begisting ltr Rp 22,500.00
26 Aspal/Bitumen kg Rp 6,525.00
27 Aspal Curah kg Rp 5,850.00
28 Coal Teer kg Rp 35,000.00
PAKU
1 Paku Reng / Usuk kg Rp 15,300.00
LISTRIK
1 Lampu TL 40 Watt bh Rp 12,500.00
3 Lampu Pijar 25 Watt bh Rp 4,000.00
2 Kabel NYA 1000 V 1,5 MM mtr Rp 5,000.00
3 Kabel NYA 1000 V 2,5 MM mtr Rp 9,000.00
4 Kabel NYA 1000 V 4 MM mtr Rp 15,000.00
5 Saklar Tunggal (Setara Broco/Nikko) bh Rp 13,000.00
6 Saklar Ganda (Setara Broco/Nikko) bh Rp 26,000.00
7 Stop Kontak (Setara Broco/Nikko) bh Rp 14,000.00
8 Sekering Kast bh Rp 21,000.00
9 Isolasi bh Rp 6,500.00
10 Kabel NYA 500 Volt 2 x 2,5 mm2 mtr Rp 3,500.00
11 Pipa Paralon 5/8 mtr Rp 3,125.00
12 T Doos pvc bh Rp 1,500.00
13 Reflektor Terbuka 40 W Single Set Rp 80,000.00
14 Reflektor Terbuka 40 W Doble Set Rp 35,000.00
15 Fiting Plafon bh Rp 12,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
JUMLAH #REF!
DIBULATKAN #REF!
PPN 10% #REF!
JUMLAH #REF!
Terbilang : Seratus Enam Puluh Dua Juta Sembilan Ratus Sembilan Puluh Sembilan Ribu Seratus Rupiah
Gresik, 2015
Menyetujui/Mengetahui Dibuat oleh
KEPALA BIDANG TATA KONSULTAN PERENCANA
BANGUNAN DAN PENGAWASAN CV. TITIAN CAHAYA CONSULTAN
Selaku
PEJABAT PEMBUAT KOMITMEN ( PPK )
Mengetahui
KEPALA DINAS PEKERJAAN UMUM
KABUPATEN GRESIK
Selaku
KUASA PENGGUNA ANGGARAN
Ir BAMBANG ISDIANTO, MM
NIP. 19580126 198512 1 002
RENCANA ANGGARAN BIAYA
( R. A. B )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pembongkaran genteng bubungan 24.50 m¹ Rp 2,500.00 Rp 61,250.00
2 Pembongkaran genteng 294.00 m² Rp 1,070.00 Rp 314,580.00
3 Pembongkaran litsplank 73.00 m¹ Rp 10,000.00 Rp 730,000.00
4 Pembongkaran gording 196.00 m¹ Rp 5,000.00 Rp 980,000.00
5 Pembongkaran usuk/reng 294.00 m² Rp 3,287.50 Rp 966,525.00
6 Pembongkaran Kuda - Kuda 6.00 bh Rp 91,094.06 Rp 546,564.38
7 Pembongkaran Kusen 27.41 m³ Rp 2,100.00 Rp 57,550.50
8 Pembongkaran plafond + rangka 179.93 m² Rp 10,437.50 Rp 1,877,986.76
Rp 5,534,456.63
II. PEKERJAAN TANAH
4 Urugkan bawah lantai tebal 20 cm #REF! m³ Rp 111,300.00 #REF!
#REF!
III. PEKERJAAN PASANGAN
1 Pasangan Peninggian 1/2 bata 1 : 5 #REF! m² Rp 112,478.50 #REF!
#REF!
IV. PEKERJAAN BETON
1 Rabat beton tebal 5 cm #REF! m³ Rp 813,710.00 #REF!
2 Kolom 12/15 #REF! m³ Rp 5,168,274.05 #REF!
3 Ring Balk/Ring gewel 12/15 #REF! m³ Rp 4,700,305.74 #REF!
#REF!
V. PEKERJAAN PLESTERAN DAN BENANGAN
1 Plesteran dinding 1 : 5 #REF! m² Rp 48,389.00 #REF!
#REF!
VI. PEKERJAAN RANGKA ATAP
1 Kuda-kuda Kayu Kruing 0.27 m³ Rp 10,363,180.00 Rp 2,848,299.30
2 Gording Kayu Meranti 8/12 Baru #REF! m³ Rp 8,280,900.00 #REF!
4 Ikatan angin Kruing 6/12 #REF! m³ Rp 10,363,180.00 #REF!
5 reng Kamper 2/3 Baru #REF! m² Rp 34,761.86 #REF!
reng Kamper 2/3 Lama #REF! m² Rp 22,500.00 #REF!
6 Usuk 5/7 Lama #REF! m² Rp 22,500.00 #REF!
7 Papan reuter Meranti 2/20 #REF! m¹ Rp 67,375.00 #REF!
8 Papan Kompres + seng #REF! m¹ Rp 71,772.75 #REF!
9 Papan listplank 3/25 ( Lama Dipasang kembali ) #REF! m¹ Rp 35,000.00 #REF!
#REF!
VII. PEKERJAAN PENUTUP ATAP
1 Pasang genteng Karangpilang #REF! m² Rp 136,875.00 #REF!
2 Bubungan Karangpilang #REF! m¹ Rp 148,580.00 #REF!
#REF!
VIII. PEKERJAAN PLAFOND
1 Pasang Rangka Plafond Kayu Meranti Baru #REF! m² Rp 106,294.40 #REF!
2 Pasang Rangka Plafond Kayu Lama #REF! m² Rp 46,250.00 #REF!
2 Kalsiboard #REF! m² Rp 40,860.75 #REF!
#REF!
IX. PEKERJAAN LANTAI
1 Lantai keramik 30 x30 #REF! m² Rp 199,093.13 #REF!
#REF!
X. PEKERJAAN PENGECATAN
1 Cat dinding #REF! m² Rp 20,364.50 #REF!
2 Cat plafon #REF! m² Rp 20,364.50 #REF!
3 Cat kayu/besi #REF! m² Rp 38,632.50 #REF!
#REF!
PEKERJAAN POER
ATAS
BAWAH
5.000
6.667
2.333
ATAS
BAWAH
ATAS
BAWAH
ATAS
8.000 ATAS BESI polos
BAWAH
BAWAH
ATAS
BAWAH
ATAS
BAWAH
ATAS
ATAS
KOLOM
Begel 0.008 0.39 0.150 371 55.556 148.400 58.580 30.00 1.75%
58.580
1 0.120 0.150
0.010 0.62 4 55.556 222.222 137.063
K 12/15 137.063
Begel 0.008 0.39 0.150 96 14.286 92.160 36.380 15.71 1.52%
36.380
1 0.200 0.350
0.013 1.04 8 14.286 114.286 119.128
K 15 / 35 119.128
Begel 0.008 0.39 0.150 89 13.333 85.440 33.727 14.67 1.42%
33.727
1 0.250 0.300
0.013 1.04 8 13.333 106.667 111.186
K 25 / 30 111.186
Begel 0.006 0.22 0.150 167 25.000 110.220 24.474 20.00 1.13%
24.474
1 0.200 0.200
0.012 0.89 4 25.000 100.000 88.817
K 20 / 20 88.817
Begel 0.006 0.22 0.150 297 44.444 136.620 30.335 26.67 2.01%
1 0.150 0.150 0.016 1.58 0 44.444 - - 188.233
KP
0.012 0.89 4 44.444 177.778 157.897
Begel 0.008 0.39 0.150 139 20.833 125.100 49.382 16.67 2.21%
1 0.120 0.400 0.016 1.58 0 20.833 - - 223.110
Sirip 12/40
0.013 1.04 8 20.833 166.667 173.728
Begel 0.008 0.39 0.150 75 11.111 79.500 31.382 13.33 0.00%
130.068
0.012 0.89 10 11.111 111.111 98.686
1 0.300 0.300
0.016 1.58 0 11.111 - -
K30/30 Lt. 2 -
0.012 0.89 0 11.111 - -
BALOK
Begel 0.008 0.39 0.125 134 16.667 115.240 45.490 45.490 13.33 2.35%
1 0.200 0.300
0.016 1.58 7 16.667 116.667 184.213 184.213
Blk Bordes
Begel 0.006 0.22 0.150 371 55.556 148.400 32.951 16.67 1.75%
1 0.120 0.150 0.016 1.58 0 55.556 - - 170.015
BR3
0.010 0.62 4 55.556 222.222 137.063
Begel 0.008 0.39 0.150 223 33.333 124.880 49.295 13.33 2.26%
1 0.150 0.200 0.016 1.58 0 33.333 - - 226.930
Blf
0.012 0.89 6 33.333 200.000 177.634
Begel 0.008 0.39 0.100 115 11.429 162.150 64.008 10.86 1.21%
84.309
0.012 0.89 2 11.429 22.857 20.301
1 0.250 0.350
0.013 1.04 5 11.429 57.143 59.564
Blk 25/35 95.302
0.013 1.04 3 11.429 34.286 35.738
Begel 0.008 0.39 0.100 126 12.500 177.660 70.130 12.50 1.33%
92.334
0.012 0.89 2 12.500 25.000 22.204
1 0.200 0.400
0.013 1.04 5 12.500 62.500 65.148
Blk 20/40 104.237
0.013 1.04 3 12.500 37.500 39.089
Begel 0.008 0.39 0.100 2 0.148 62.220 24.561 2.36 0.01%
24.824
0.012 0.89 2 0.148 0.296 0.263
1 15.000 0.450
0.012 0.89 3 0.148 0.444 0.395
Blk 15/45 1.316
0.012 0.89 5 0.148 0.741 0.658
Begel 0.008 0.39 0.100 167 16.667 202.070 79.766 13.33 1.11%
109.371
0.012 0.89 2 16.667 33.333 29.606
1 0.200 0.300
0.013 1.04 3 16.667 50.000 52.118
Blk 20/30 86.864
0.013 1.04 2 16.667 33.333 34.746
Begel 0.008 0.39 0.125 54 6.667 78.840 31.122 8.67 1.22%
1 0.300 0.500 0.016 1.58 8 6.667 53.333 84.212 127.176
BKNSL
0.012 0.89 2 6.667 13.333 11.842
Begel 0.008 0.39 0.125 134 16.667 162.140 64.004 13.33 1.68%
64.004
0.012 0.89 0 16.667 - -
1 0.200 0.300
0.019 2.23 0 16.667 - -
Blk 20/30 131.581
0.016 1.58 5 16.667 83.333 131.581
Begel 0.008 0.39 0.125 101 12.500 142.410 56.215 12.50 2.01%
78.420
0.012 0.89 2 12.500 25.000 22.204
1 0.200 0.400
0.016 1.58 8 12.500 100.000 157.897
Blk 20/40 157.897
0.013 1.04 0 12.500 - -
Begel 0.008 0.39 0.125 178 22.222 135.280 53.401 16.67 1.51%
1 0.150 0.300 0.016 1.58 0 22.222 - - 171.824
BLK
0.012 0.89 6 22.222 133.333 118.423
Begel 0.006 0.22 0.200 223 44.444 102.580 22.777 20.00 1.40%
1 0.150 0.150 0.016 1.58 0 44.444 - - 132.428
lis 15/15
0.010 0.62 4 44.444 177.778 109.651
Begel 0.008 0.39 0.150 223 33.333 124.880 49.295 13.33 1.51%
1 0.150 0.200 0.016 1.58 0 33.333 - - 167.718
RNG Blk 15/20
0.012 0.89 4 33.333 133.333 118.423
Begel 0.006 0.22 0.150 371 55.556 148.400 32.951 16.67 1.75%
1 0.120 0.150 0.016 1.58 0 55.556 - - 170.015
RNG Blk 12/15
0.010 0.62 4 55.556 222.222 137.063
Begel 0.008 0.39 0.150 297 44.444 136.620 53.930 13.33 2.01%
1 0.150 0.150 0.016 1.58 0 44.444 - - 211.827
BR3
0.012 0.89 4 44.444 177.778 157.897
Begel 0.008 0.39 0.150 223 33.333 124.880 49.295 13.33 1.51%
1 0.150 0.200 0.016 1.58 0 33.333 - - 167.718
balok luevel
0.012 0.89 4 33.333 133.333 118.423
SLOOF
Begel 0.008 0.39 0.150 149 22.222 113.240 44.701 13.33 1.51%
1 0.150 0.300 0.016 1.58 0 22.222 - - 163.124
SL15/30
0.012 0.89 6 22.222 133.333 118.423
Begel 0.008 0.39 0.150 84 12.500 89.040 35.148 57.352 10.00 2.29%
0.012 0.89 2 12.500 25.000 22.204
1 0.200 0.400
0.016 1.58 8 12.500 100.000 157.897 157.897
SL20/40
KOLOM
Begel 0.008 0.39 0.150 75 11.111 79.500 31.382 31.382 13.33 1.79%
1 0.300 0.300
0.016 1.58 8 11.111 88.889 140.353 140.353
K1
0.012 0.89 0 11.111 - -
Begel 0.008 0.39 0.150 75 11.111 79.500 31.382 31.382 13.33 1.34%
1 0.300 0.300
0.016 1.58 6 11.111 66.667 105.265 105.265
K2
0.012 0.89 0 11.111 - -
Begel 0.008 0.39 0.150 34 5.000 56.440 22.279 22.279 9.00 0.60%
1 0.400 0.500
0.016 1.58 6 5.000 30.000 47.369 47.369
KA
0.012 0.89 0 5.000 - -
Begel 0.008 0.39 0.150 34 5.000 56.440 22.279 9.00 0.60%
31.161
0.012 0.89 2 5.000 10.000 8.882
1 0.400 0.500
0.016 1.58 6 5.000 30.000 47.369 47.369
KB
0.012 0.89 0 5.000 - -
Begel 0.008 0.39 0.150 149 22.222 113.240 44.701 20.00 0.00%
163.124
0.012 0.89 6 22.222 133.333 118.423
1 0.150 0.300
0.016 1.58 0 22.222 - - -
KD
0.012 0.89 0 22.222 - -
Begel 0.008 0.39 0.150 149 22.222 113.240 44.701 13.33 0.00%
163.124
0.012 0.89 6 22.222 133.333 118.423
1 0.150 0.300
0.016 1.58 0 22.222 - - -
Pagar
0.012 0.89 0 22.222 - -
Begel 0.008 0.39 0.150 186 27.778 119.040 46.990 21.67 0.00%
195.019
0.012 0.89 6 27.778 166.667 148.029
1 0.150 0.240
0.016 1.58 0 27.778 - - -
KSR
0.012 0.89 0 27.778 - -
Begel 0.008 0.39 0.150 223 33.333 124.880 49.295 23.33 0.00%
226.930
0.012 0.89 6 33.333 200.000 177.634
1 0.150 0.200
0.016 1.58 0 33.333 - - -
K15/20 tandon air
0.012 0.89 0 33.333 - -
Begel 0.008 0.39 0.150 34 5.000 56.440 22.279 22.279 9.00 0.80%
1 0.400 0.500
0.016 1.58 8 5.000 40.000 63.159 63.159
K3
Begel 0.008 0.39 0.150 34 5.000 56.440 22.279 22.279 9.00 1.21%
1 0.400 0.500
0.016 1.58 12 5.000 60.000 94.738 94.738
K4
BALOK
Begel 0.008 0.39 0.150 223 33.333 124.880 49.295 18.33 1.51%
1 0.150 0.200 0.016 1.58 0 33.333 - - 167.718
BlF
1 0.150 0.200 167.718
BlF
0.012 0.89 4 33.333 133.333 118.423
Begel 0.008 0.39 0.150 297 44.444 136.620 53.930 20.00 2.01%
1 0.150 0.150 0.016 1.58 0 44.444 - - 211.827
BLT
0.012 0.89 4 44.444 177.778 157.897
Begel 0.008 0.39 0.150 178 26.667 117.480 46.374 17.33 1.51%
1 0.150 0.250 0.016 1.58 0 26.667 - - 164.797
BGT
0.012 0.89 5 26.667 133.333 118.423
0.09 0.9
19.06 186.140994
205.21
POLOS
POLOS
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
POLOS
ULIR
ENGINEERING ESTIMATE ( EE )
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
JUMLAH Rp 63,941,012.44
DIBULATKAN Rp 63,941,000.00
PPN 10% Rp 6,394,100.00
JUMLAH Rp 70,335,100.00
Terbilang : Seratus Enam Puluh Dua Juta Sembilan Ratus Sembilan Puluh Sembilan Ribu Seratus Rupiah
Gresik, 2015
Menyetujui/Mengetahui Dibuat oleh
KEPALA BIDANG TATA KONSULTAN PERENCANA
BANGUNAN DAN PENGAWASAN CV. TITIAN CAHAYA CONSULTAN
Selaku
PEJABAT PEMBUAT KOMITMEN ( PPK )
Mengetahui
KEPALA DINAS PEKERJAAN UMUM
KABUPATEN GRESIK
Selaku
KUASA PENGGUNA ANGGARAN
Ir BAMBANG ISDIANTO, MM
NIP. 19580126 198512 1 002
RENCANA ANGGARAN BIAYA
( R. A. B )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pembongkaran genteng bubungan 23.15 m¹ Rp 2,500.00 Rp 57,875.00
2 Pembongkaran genteng 282.00 m² Rp 2,000.00 Rp 564,000.00
3 Pembongkaran litsplank 81.00 m¹ Rp 10,000.00 Rp 810,000.00
4 Pembongkaran gording 185.20 m¹ Rp 5,000.00 Rp 926,000.00
5 Pembongkaran usuk/reng 282.00 m² Rp 3,287.50 Rp 927,075.00
6 Pembongkaran Kuda - Kuda 7.00 bh Rp 91,094.06 Rp 637,658.44
7 Pembongkaran Kuda Kuda beton 2.91 m³ Rp 700,035.00 Rp 2,039,726.98
7 Pembongkaran plafond + rangka 238.67 m² Rp 5,218.75 Rp 1,245,572.11
Rp 7,207,907.53
II. PEKERJAAN TANAH
1 Galian pondasi 1.27 m³ Rp 75,000.00 Rp 95,062.50
2 Urug pasir bawah pondasi tebal 10 cm 0.22 m³ Rp 243,600.00 Rp 52,617.60
Rp 147,680.10
III. PEKERJAAN PASANGAN
1 Pasangan dinding Retak + Peninggian 1/2 bata 1 : 5 6.62 m² Rp 112,478.50 Rp 744,045.28
Rp 744,045.28
IV. PEKERJAAN BETON
2 Kolom 12/15 - m³ Rp 5,168,274.05 Rp -
4 Kolom 20/20 - m³ Rp 7,035,578.41 Rp -
9 Sloof 20/30 - m³ Rp 4,445,733.80 Rp -
10 Sloof 20/25 - m³ Rp 4,336,882.47 Rp -
3 Balok latei 12/15 - m³ Rp 5,055,671.23 Rp -
11 Balok lantai 15/20 - m³ Rp 6,652,814.99 Rp -
5 Plat leuvel tebal 10 cm - m³ Rp 5,111,989.17 Rp -
13 Plat leuvel tebal 8 cm - m³ Rp 6,137,383.84 Rp -
12 Plat leuvel tebal 10 cm 4.76 m³ Rp -
5 Balok 20/35 - m³ Rp 5,922,692.42 Rp -
15 Balok B2 20/40 - m³ Rp 6,539,878.77 Rp -
16 Balok B3 15/20 - m³ Rp 6,652,814.99 Rp -
19 Balok B4 15/45 - m³ Rp 1,964,372.59 Rp -
6 Plat dek tebal 12 cm - m³ Rp 5,271,064.53 Rp -
18 Plat tangga tebal 15 cm - m³ Rp 6,139,459.15 Rp -
19 Plat bordes tebal 15 cm - m³ Rp 6,139,459.15 Rp -
20 Balok bordes 20/40 - m³ Rp 6,539,878.77 Rp -
3 Ring Balk/Ring gewel 12/15 0.51 m³ Rp 4,700,305.74 Rp 2,377,414.64
Rp 4,911,036.56
V. PEKERJAAN PLESTERAN DAN BENANGAN
1 Plesteran dinding 1 : 5 13.23 m² Rp 48,389.00 Rp 640,186.47
Rp 640,186.47
VI. PEKERJAAN KUSEN KAYU KAMPER
1 Kusen Pintu/ Jendela Kayu Kamper 6/15 - m³ Rp 600,000.00 Rp -
1 Daun pintu Panil Kayu Kamper - m² Rp - Rp -
2 Daun jendela Kayu Kamper - m² Rp - Rp -
2 Pasang Daun Jendela - m² Rp 350,000.00 Rp -
Rp -
VII. PEKERJAAN RANGKA ATAP
1 Kuda-kuda Kayu Kruing 1.37 ls Rp - Rp -
2 Gording Kayu Meranti 8/12 Baru 1.95 m³ Rp 45,900.00 Rp 89,538.05
4 Ikatan angin Kruing 6/12 - m³ Rp - Rp -
5 reng Kamper 2/3 Baru - m² Rp - Rp -
6 Usuk 5/7 Kamper - m² Rp 22,500.00 Rp -
7 Papan reuter Meranti 2/20 - m¹ Rp - Rp -
8 Papan Kompres + seng - m¹ Rp 71,772.75 Rp -
9 Papan listplank 3/25 74.80 m¹ Rp - Rp -
Rp 89,538.05
VIII. PEKERJAAN PENUTUP ATAP
1 Pasang genteng Karangpilang - m² Rp - Rp -
2 Bubungan Karangpilang - m¹ Rp - Rp -
Rp -
IX. PEKERJAAN PLAFOND
1 Pasang Rangka Plafond Kayu Meranti Baru 238.51 m² Rp - Rp -
2 Pasang Kalsiboard 238.51 m² Rp - Rp -
Rp -
X. PEKERJAAN LANTAI
1 Lantai keramik 30 x30 203.11 m² Rp 189,612.50 Rp 38,511,720.84
2 Keramik dinding 20 x 25 - m² Rp 226,285.00 Rp -
Rp 38,511,720.84
XI. PEKERJAAN PENGGANTUNG KUNCI / KACA
1 Kunci pintu 2 x putar - bh Rp 81,000.00 Rp -
2 Engsel pintu - bh Rp 40,000.00 Rp -
3 Engsel jendela - bh Rp 18,000.00 Rp -
4 Hak angin - bh Rp 33,500.00 Rp -
5 Grendel jendela - bh Rp 11,250.00 Rp -
6 Grendel Tanam - bh Rp 50,000.00 Rp -
7 Kaca polos tebal 5 mm - m² Rp - Rp -
Rp -
XII. PEKERJAAN PENGECATAN
1 Cat dinding 689.86 m² Rp 10,489.50 Rp 7,236,286.47
2 Cat plafon 238.51 m² Rp 10,489.50 Rp 2,501,824.42
3 Cat kayu/besi 50.50 m² Rp 38,632.50 Rp 1,950,786.72
Rp 11,688,897.61
RINCIAN PERHITUNGAN VOLUME PEKERJAAN
SDN DOORO KEC CERME KAB GRESIK
NO
PERHITUNGAN Satuan
1
P x L x T x JUMLAH
1 PEKERJAAN TANAH
a Boor strous = -
b GALIAN PLAT 0.65 X 0.65 X 0.5 X 6 = 1.27 1.27
b URUKAN PASIR BAWAH PONDASI 0.6 X 0.6 X 0.1 X 6 = 0.22 0.22
a URUKAN SIRTU DALAM 1 KELAS 8.05 x 7.15 x 0.3 = 17.27
URUG SIRTU TERAS 8.05 x 1.9 x 0.3 = 4.59
21.86 m3
b URUKAN PASIR BAWAH LANTAI 7.9 x 8.9 x 0.1 = 7.03 m3
1 PEKERJAAN PASANGAN
a Pasangan Tempat Duduk 8.64 + 5.76 = 14.40 m2
a Pasangan dinding 1/2 bata 1 : 5 8.05 x 0.15 x 2 = 2.42
B Pasangan dinding 1/2 bata 1 : 5 7 x 0.6 x 1 = 4.20
6.62 m2
a Pas. Rolag 8.05 x 0.3 + 1.9 x 0.3 = 2.99 m2
2 PEKERJAAN BETON
a Pekerjaan Bour strous -
a Pekerjaan Poer 0.6 X 0.6 X 0.25 X 6 = 0.54
b Sloof 15/20 = 0.00
c Kolom 20 x 20 0.15 X 0.15 X 2.5 X 6 = 0.34
a Kolom 12/15 = 0.00
b Balok Latei = 0.00
b Balok Konsol = 0.00
Balok Gantung 23.4 X 0.15 X 0.2 = 0.70
c Ring balk 12/15 8.05 x 0.12 x 0.15 x 2 = 0.29 m3
d Ring Gewel 12/15 12 x 0.12 x 0.15 x 1 = 0.22 m3
3 PEKERJAAN PLESTERAN
a Plesteran dinding trasram 1 : 3 = 0.00
= 0.00
4 PEKERJAAN KUSEN ALUMUNIUM
a1 Kusen Jendela Alumunium = 0.00
a2 Kusen Pintu Alumunium = 0.00
a3 Kusen Pintu Alumunium = 0.00
a4 Kusen Pintu Alumunium = 0.00 -
b Pekerjaan Pintu = 0.00
c1 Pekerjaan Daun Jendela = 0.00
c2 Pekerjaan Daun Jendela = 0.00
d Pekerjaan Kaca = 0.00
Pekerjaan Kaca = 0.00
26
5 PEKERJAAN RANGKA ATAP
a Pekerjaan Kuda Kuda 1.45728 + 0.248 = 1.71
b Gording + nok Kayu Meranti 8/12 25.4 x 0.08 x 0.12 x 8 = 1.95
c Gording + nok Kayu Meranti 8/12 = 0.00
Usuk 5/7 25.4 x 12 = 304.80
Reng 2/3 25.4 x 12 = 304.80
d Ikatan angin Kruing 6/12 = 0.00
a Pasang Galvalum = 0.00
f Papan reuter Meranti 2/20 = 0.00
b Papan Kompres Seng = 0.00
c Pas. Listplang 12 x 2 + 25.4 x 2 = 74.80
6 PEKERJAAN PENUTUP ATAP
a Pas. Genteng 25.4 x 12 = 304.80
b Pas. Bubungan = 0.00
7 PEKERJAAN PLAFOND RANGKA HOOLOW
a Pasang Plafond Rangka Hoolow 22.95 x 8.85 + 23.4 + 12 = 238.51
b List Palfon gipsun = 0.00
9 PEKERJAAN LANTAI
9. a Lantai Keramik 30 x 30 22.95 x 8.85 = 203.11 m2
Lantai Alam 1 x 0.8 x 4 = 3.20
b Keramik Dinding 20 X 25 T = 1.50m 16.1 x 1.2 - 7.57 = 11.75 m2
10. a Kunci Pintu 2 x putar = 0.00
b Engsel pintu = 0.00
c Engsel jendela = 0.00
d Hak angin = 0.00
e Grendel tanam = 0.00
f Grendel jendela = 0.00
g Kaca polos tebal 5 mm = 0.00
Lantai Keramik 20 x 25 = 0.00
b Keramik Dinding 20 X 25 T = 1.50m = 0.00
10 PEKERJAAN PENGGANTUNG KUNCI / KACA
a Pekerjaan Kunci pintu 0.00
b Pekerjaan Engsel pintu 0.00
c Pekerjaan engsel Jendela 0.00
d Pekerjaan Hak Angin 0.00
e Grendel Jendela 0.00
f Grendel tanam 0.00
8 PEKERJAAN PENGECATAN
a Cat dinding 707.44 - 17.58 = 689.86
b Cat plafon = 239
c Cat kayu 35.4384 + 15.058 = 50.50
27
RENCANA ANGGARAN BIAYA ( RAB )
Kegiatan : Pembangunan KM/WC
Pekerjaan : Pembangunan KM/WC KB DARUL ULUM
Lokasi : Dsn. Sidojangkung Kec. Menganti Kab. Gresik
Tahun : 2017
A PEMBANGUNAN KM/WC
I PEKERJAAN TANAH 562,500.00
II PEKERJAAN PASANGAN 14,916,473.61
III PEKERJAAN BETON 9,522,385.27
JUMLAH 25,001,358.88
DIBULATKAN 25,000,000.00
Terbilang : Dua Puluh Lima Juta Rupiah
Gresik, 2017
Mengetahui Dibuat oleh
Panitia Pelaksana Rehabilitasi Tim Perencana
....................... SUPARDI, ST
Menyetujui
Kepala Sekolah
KB DARUL ULUM
NISWATUN HIDAYAH,S.Pd
RENCANA ANGGARAN BIAYA ( RAB )
Kegiatan : Pembangunan KM/WC
Pekerjaan : Pembangunan KM/WC KB DARUL ULUM
Lokasi : Dsn. Sidojangkung Kec. Menganti Kab. Gresik
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
Rp. Rp.
A PEMBANGUNAN KM/WC
I PEKERJAAN TANAH
1 Galian Tanah m3 7.50 75,000.00 562,500.00
JUMLAH A 562,500.00
II PEKERJAAN PASANGAN
1 Pas. Dinding Bata 1 Pc : 3 Ps m2 8.96 115,094.00 1,031,242.24
2 Pas. Dinding Bata 1 Pc : 5 Ps m2 56.92 112,478.50 6,402,276.22
3 Pas. Batu Kumbung m2 8.89 465,442.50 4,137,783.83
4 Pek. Plesteran 1 Pc : 5 Ps m2 56.92 58,769.70 3,345,171.32
JUMLAH i 14,916,473.61
III PEKERJAAN BETON
1 Rabat Beton t = 5 cm m3 0.75 813,710.00 610,282.50
2 Beton Sloof 15/20 m3 0.63 3,426,504.71 2,158,697.97
3 Beton Kolom 15/15 m3 0.61 5,168,274.05 3,135,075.04
4 Beton Ring Gewel 12/15 m3 0.77 4,699,129.57 3,618,329.77
JUMLAH ii 9,522,385.27
RENCANA ANGGARAN BIAYA ( RAB )
Program : PROGRAM MANAJEMEN PELAYANAN PENDIDIKAN
Kegiatan : Pembangunan KM/WC
Pekerjaan : #NAME?
Lokasi : Dsn. Sidojangkung Kec. Menganti Kab. Gresik
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
Rp. Rp.
JUMLAH 3,000,000.00
DIBULATKAN 3,000,000.00
PPN 10% 300,000.00
JUMLAH 3,300,000.00
Terbilang : Tiga Juta Tiga Ratus Rupiah
ANALISA HARGA SATUAN MATA PEKERJAAN
PEKERJAAN PASANGAN
9 Sloof 15/20 cm / m3
Bahan & Upah :
Beton Mutu Fc = 19*,3 Mpa ( K225 ) 1.0000 m3 Rp 1,014,545.71 Rp 1,014,545.71
Pembesian Polos 153.0000 kg Rp 10,728.00 Rp 1,641,384.00
Begisting 5.0000 m2 Rp 154,115.00 Rp 770,575.00
Jumlah Harga Satuan Rp 3,426,504.71
7 Kolom Praktis 15/15 cm / m3
Bahan & Upah :
Beton Mutu Fc = 19*,3 Mpa ( K225 ) 1.0000 m3 Rp 1,014,545.71 Rp 1,014,545.71
Pembesian Polos 195.6433 kg Rp 10,728.00 Rp 2,098,861.67
Begisting 26.6667 m2 Rp 77,057.50 Rp 2,054,866.67
Jumlah Harga Satuan Rp 5,168,274.05
Overhead & Profit 7% Rp -
Jumlah Total Rp 5,168,274.05
7 Ring Balk 12/15 cm/ m3
Bahan & Upah :
Beton Mutu Fc = 19*,3 Mpa ( K225 ) 1.0000 m3 Rp 1,014,545.71 Rp 1,014,545.71
Pembesian Polos 170.0147 kg Rp 10,728.00 Rp 1,823,917.19
Begisting 13.3333 m2 Rp 139,550.00 Rp 1,860,666.67
Jumlah Harga Satuan Rp 4,699,129.57
PEKERJAAN PLESTERAN