Quality Cost Study of XYZ Injection Plastic Plant- $/Month

1 Quality planning 70

2 Vendor qualification (supplier certification) 7150

3 Acceptance inspection and test planning (planning for inspection) 100

4 Process equipment design for quality 370

5 Quality task teams (special project related to quality) 1940

Turnaround planning –equipment (quality-related scheduled


6 maintenance) 330

Turnaround planning –Instruments (quality-related scheduled


7 maintenance) 650

8 Quality profiling (determining product specs to meet customer needs) 1000

9 Quality statistics (collection of data and analysis) 420

10 Planning quality motivational programs 170

11 Production engineers on quality 70

12 Process Control Engineering –QA department 27050

13 Process Control Engineering –Engineering department 12500

14 Systems conformance (audit to verify system’s conformance) 70

ISYE6094 – Quality Engineering


This study source was downloaded by 100000834699216 from CourseHero.com on 03-11-2022 05:52:40 GMT -06:00

https://www.coursehero.com/file/126121282/2112-ISYE6094037-TCDA-TP1-W2-S3-R0-2301939954-TANTRI-WIJAYAdocx/
Design /development of quality measurement /control equipment
15 Engineering department 740
QA department 900

16 Quality training 1050

17 Raw material acceptance testing 3345

18 Process testing –operators 13300

19 Review production analysis data 530

20 Environmental testing (as it relates to product quality) 70

21 QA in no. 1,no. 2,lot analysis, instrument calibration , and aging checks 61313

22 Off-grade burned 3300

23 Off-grade blended off labor 210

Jawab :

Quality Cost adalah kategori biaya yang terkait dengan memproduksi, mengidentifikasi,
menghindari, atau memperbaiki produk yang tidak memenuhi persyaratan.

Quality Cost Sendiri terdiri dari 4 kategori yaitu

 Biaya Pencegahan (Prevention Cost) Biaya yang dikeluarkan untuk mencegah


produksi produk cacat adalah bagian dari biaya pencegahan
 Biaya Penilaian (Appraisal Cost) Biaya penilaian adalah biaya yang dikeluarkan
dalam menilai kondisi produk atau bahan dengan mengacu pada spesifikasi.
 Biaya Kegagalan Internal (Internal Failure Cost) Biaya kegagalan internal adalah
biaya yang timbul dari unit yang rusak diproduksi yang membelot dalam pabrik.
 Biaya Kegagalan Eksternal (External Failure Cost) Biaya kegagalan eksternal adalah
biaya yang timbul dari produk cacat mencapai pelanggan.

Biaya pencegahan dan penilaian adalah biaya yang masuk dalam kategori produksi
kualitas/penjagaan kualitas. Untuk biaya kegagalan internal dan external adalah faktor quality
cost namun dalam hal ini juga masuk kedalam rincian biaya tak terduga.

Biaya Biaya Biaya Biaya


Quality Cost Study of XYZ Injection Plastic Plant- $/Month Perencanaan Penialain Kegagalan Kegagalan
Internal External

1 Quality planning 70 v

2 Vendor qualification (supplier certification) 7150 v

Acceptance inspection and test planning v

3 (planning for inspection) 100

4 Process equipment design for quality 370 v

ISYE6094 – Quality Engineering


This study source was downloaded by 100000834699216 from CourseHero.com on 03-11-2022 05:52:40 GMT -06:00

https://www.coursehero.com/file/126121282/2112-ISYE6094037-TCDA-TP1-W2-S3-R0-2301939954-TANTRI-WIJAYAdocx/
Quality task teams (special project related to v

5 quality) 1940

Turnaround planning –equipment (quality- v

6 related scheduled maintenance) 330

Turnaround planning –Instruments (quality- v

7 related scheduled maintenance) 650

Quality profiling (determining product specs v

8 to meet customer needs) 1000

Quality statistics (collection of data and v

9 analysis) 420

10 Planning quality motivational programs 170 v

11 Production engineers on quality 70 v

12 Process Control Engineering –QA department 27050 v

Process Control Engineering –Engineering v

13 department 12500

Systems conformance (audit to verify system’s v

14 conformance) 70

Design /development of quality measurement /control v


740
15
equipment Engineering department
900
QA department

16 Quality training 1050 v

17 Raw material acceptance testing 3345 v

18 Process testing –operators 13300 v

19 Review production analysis data 530 v

20 Environmental testing (as it relates to product quality) 70 v

QA in no. 1,no. 2,lot analysis, instrument calibration , and v

21 aging checks 61313

22 Off-grade burned 3300 v

23 Off-grade blended off labor 210 v

Total (per bulan) 136648 46910 86228 3510 0

Total quality cost (pertahun) 1639776 562920 1034736 42120 0

persentase (%) 34,32% 63,10% 2,56% 0%

ISYE6094 – Quality Engineering


This study source was downloaded by 100000834699216 from CourseHero.com on 03-11-2022 05:52:40 GMT -06:00

https://www.coursehero.com/file/126121282/2112-ISYE6094037-TCDA-TP1-W2-S3-R0-2301939954-TANTRI-WIJAYAdocx/
Penjualan Tahunan 100000000

budget operasi 34000000

Persentase quality cost pada total budget operasi 4,82%

persentase quality cost pada penjualan tahunan 1,64%

Dari data ditabel dapat dilihat bahwa saya memasukan biaya perencanaan dalam hal
pengembangan intelektual sdm, program program untuk menambah nilai uji kualitas, training
dll. Namun dalam hal biaya penilaian saya mengkategorikan dengan melihat pengembangan
kualitas melalui perantara kualitas mesin, bahan, lingkungan dll. Sementara factor internal
seperti jadwal yang tidak sesuai, pengulangan karena produk gagal dll.

Total quality perbulan yang didapat adalah $136648 dan jika dihitung dalam skala tahun
menjadi $1639776 yang tediri dari nilai biaya perencanaan sebesar $562920 dalam setahun
dan biaya penilaian sebesar $1034736 dalam setahun biaya kerugian akibat factor internal
sebesar $42120, dan factor external sebesar $0.

Dapat dilihat dari analisis data yang dilakukan bahwa nilai dari kerugian akibat factor internal
dan external hanya sebesar 2,56 % saja. Sementara nilai biaya perencanaan dan penilaian
jauh lebih besar yaitu 63,10% dan 34,32% persen.

Hal ini mengindikasikan bahwa kegagalan produk akibat factor external maupun internal
sudah sangat minim, dengan penggunaan system quality control diatas, dimana kegagalan
produk sangatlah kecil. Dan juga system quality cost total hanya mengambil 4,82% saja dari
budget operasi yang ada. Dan 1,64% dari budget penjualan tahunan.

ISYE6094 – Quality Engineering

*Pada kolom 15 {(Design /development of quality measurement /control equipment


This study source was downloaded by 100000834699216 from CourseHero.com on 03-11-2022 05:52:40 GMT -06:00

Engineering department) Terdapat 2 angka, saya bingung angka mana yang dipilih,
https://www.coursehero.com/file/126121282/2112-ISYE6094037-TCDA-TP1-W2-S3-R0-2301939954-TANTRI-WIJAYAdocx/
Powered by TCPDF (www.tcpdf.org)
sehingga saya menambahkan kedua angka tersebut} Terima kasih

Anda mungkin juga menyukai