Pasangan batu Pondasi pagar perhari

Komulatif Volume
Panjang Komulatif
No. Hari/Tanggal Panjang Pekerjaan keterangan
(m') (m') (m3) volume (m3)

1 06 Februari 2022 12.50 12.500 5.400 5.400 sisi timur


2 07 Februari 2022 11.50 24.000 4.5 9.900 sisi timur
3 08 Februari 2022 11.00 35.000 8.82 18.720 sisi timur
4 09 Februari 2022 28.40 63.400 16.29 35.010 sisi timur
5 10 Februari 2022 10.00 73.400 8.271 43.281 Sisi barat dan timur
6 11 Februari 2022 10.50 83.900 17.442 60.723 Sisi barat dan timur
7 12 Februari 2022 9.7821 70.505
8 13 Februari 2022 6.552 77.057
9 14 Februari 2022 4.788 81.845
10 15 Februari 2022 15.12 96.965
11 16 Februari 2022 8.874 105.839
12 17 Februari 2022 22.05 127.889
13 18 Februari 2022 10.584 138.473
Panjang 12.5 m
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 6 = 2.43 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 6 = 3.024 m3 +


jumlah = 5.454 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 6 = 0.054 m3

= 5.454 - 0.054 = 5.4 m3


Panjang 11.5 m
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 5 = 2.025 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 5 = 2.520 m3 +


2 jumlah = 4.545 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 5 = 0.045 m3

= 4.545 - 0.045 = 4.5 m3


1 0.3 + 0.55 x 0.7 x
2
2 0.9 + 0.6 x 0.6 x
10 = 2.975

13 = 5.85
8.825
Panjang 11 m
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 5 = 2.025 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 5 = 2.520 m3 +


2 jumlah = 4.545 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 5 = 0.045 m3

= 4.545 - 0.045 = 4.5 m3

atas
Panjang 10.5 m

Kolom ( 0.5 + 0.9 ) 0.9 x 0.9 x 5 = 2.835 m3


2
Lajur ( 0.3 + 0.6 ) 1.2 x 0.7 x 5 = 1.890 m3 +
2 = 4.725 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 5 = 0.405 m3

= 4.725 - 0.405 = 4.32 m3

jumlah 4.5 + 4.32 = 8.82 m3


Panjang 28 m
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 14 = 5.67 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 13 = 6.552 m3


= 12.222 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 14 = 0.126 m3

= 12.096 - 0.126 = 11.97 m3

atas
Panjang 10.5 m
( 0.5 + 0.9 ) 0.9 x 0.9 x 5 = 2.835 m3
2
( 0.3 + 0.6 ) 1.2 x 0.7 x 5 = 1.890 m3
2 = 4.725 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 5 = 0.405 m3

= 4.725 - 0.405 = 4.32 m3

jumlah 11.97 + 4.32 = 16.29 m3


+

+
Panjang 10 m sisi barat
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 5 = 2.025 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 4 = 2.016 m3


= 4.041 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 5 = 0.045 m3

= 3.996 - 0.045 = 3.951 m3

atas
Panjang 10.5 m sisi timur
( 0.5 + 0.9 ) 0.9 x 0.9 x 5 = 2.835 m3
2
( 0.3 + 0.6 ) 1.2 x 0.7 x 5 = 1.890 m3
2 = 4.725 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 5 = 0.405 m3

= 4.725 - 0.405 = 4.32 m3

jumlah 3.951 + 4.32 = 8.271 m3


+

+
Panjang 10 m sisi barat
Bawah
Kolom a ( 0.5 x 0.9 x 0.9 ) 5 = 2.025 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 4 = 2.016 m3 +


= 4.041 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 5 = 0.045 m3

= 4.041 - 0.045 = 3.996 m3

atas
Panjang 10.5 m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 5 = 2.835 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 4 = 1.512 m3 +
2 = 4.347 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 5 = 0.405 m3

= 4.347 - 0.405 = 3.942 m3

atas
Panjang 23.1 m sisi timur
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 11 = 6.237 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 11 = 4.158 m3 +
2 = 10.395 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 11 = 0.891 m3

= 10.395 - 0.891 = 9.504 m3

jumlah 3.996 + 3.942 + 9.504 = 17.442 m3


Panjang 7m sisi timur
atas
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 3 = 1.701 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 3 = 1.134 m3
2 = 2.835 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 0.9 = 0.0729 m3

= 2.835 - 0.0729 = 2.7621 m3

bawah
Panjang 7m sisi barat
Kolom a ( 0.5 x 0.9 x 0.9 ) 3 = 1.215 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 3 = 1.512 m3


= 2.727 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 3 = 0.027 m3

= 2.727 - 0.027 = 2.7 m3

atas
Panjang 10 m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 5 = 2.835 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 5 = 1.890 m3
2 = 4.725 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 5 = 0.405 m3

= 4.725 - 0.405 = 4.32 m3

jumlah 2.7621 + 2.7 + 4.32 = 9.7821 m3


6.3

+
bawah
Panjang 8m sisi barat
Kolom a ( 0.5 x 0.9 x 0.9 ) 4 = 1.620 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 3 = 1.512 m3


2 = 3.132 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 4 = 0.036 m3

= 3.132 - 0.036 = 3.096 m3

atas
Panjang 9m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 4 = 2.268 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 4 = 1.512 m3
2 = 3.780 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 4 = 0.324 m3

= 3.780 - 0.324 = 3.456 m3

jumlah 3.096 + 3.456 = 6.552 m3


bawah
Panjang 7m sisi barat
Kolom a ( 0.5 x 0.9 x 0.9 ) 3 = 1.215 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 2 = 1.008 m3


= 2.223 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 3 = 0.027 m3

= 2.223 - 0.027 = 2.196 m3

atas
Panjang 7m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 3 = 1.701 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 3 = 1.134 m3
2 = 2.835 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 3 = 0.243 m3

= 2.835 - 0.243 = 2.592 m3

jumlah 2.196 + 2.592 = 4.788 m3


bawah
Panjang 16 m sisi barat
Kolom a ( 0.5 x 0.9 x 0.9 ) 8 = 3.240 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 10 = 5.040 m3


= 8.280 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 8 = 0.072 m3

= 8.280 - 0.072 = 8.208 m3

atas
Panjang 17 m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 8 = 4.536 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 8 = 3.024 m3
2 = 7.560 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 8 = 0.648 m3

= 7.560 - 0.648 = 6.912 m3

jumlah 8.208 + 6.912 = 15.12 m3


bawah
Panjang 6m sisi barat

Lajur b ( 0.7 x 0.6 x 1.2 ) 2 = 1.008 m3


= 1.008 m3

= 1.008 = 1.008 m3

atas
Panjang 8m sisi barat
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 4 = 2.268 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 4 = 1.512 m3
2 = 3.780 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 4 = 0.324 m3

= 3.780 - 0.324 = 3.456 m3

bawah
Panjang 6m sisi utara
Kolom a ( 0.5 x 0.9 x 0.9 ) 3 = 1.215 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 2 = 1.008 m3


2 = 2.223 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 3 = 0.027 m3

= 2.223 - 0.027 = 2.196 m3

atas
Panjang 6m sisi utara
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 3 = 1.701 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 2 = 0.756 m3
2 = 2.457 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 3 = 0.243 m3

= 2.457 - 0.243 = 2.214 m3


jumlah 1.008 + 3.456 + 2.196 + 2.214 = 8.874 m3
bawah
Panjang 28 m sisi utara
Kolom a ( 0.5 x 0.9 x 0.9 ) 13 = 5.265 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 12 = 6.048 m3


2 = 11.313 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 13 = 0.117 m3

= 11.313 - 0.117 = 11.196 m3

atas
Panjang 28 m sisi utara
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 13 = 7.371 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 12 = 4.536 m3
2 = 11.907 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 13 = 1.053 m3

= 11.907 - 1.053 = 10.854 m3

jumlah 11.196 + 10.854 = 22.05 m3


bawah
Panjang 12 m sisi utara
Kolom a ( 0.5 x 0.9 x 0.9 ) 6 = 2.430 m3

Lajur b ( 0.7 x 0.6 x 1.2 ) 6 = 3.024 m3


2 = 5.454 m3

lobang kolom
( 0.3 x 0.3 x 0.1 ) 6 = 0.054 m3

= 5.454 - 0.054 = 5.4 m3

atas
Panjang 12 m sisi utara
Kolom a ( 0.5 + 0.9 ) 0.9 x 0.9 x 6 = 3.402 m3
2
Lajur b ( 0.3 + 0.6 ) 1.2 x 0.7 x 6 = 2.268 m3
2 = 5.670 m3

lobang kolom
( 0.3 x 0.3 x 0.9 ) 6 = 0.486 m3

= 5.670 - 0.486 = 5.184 m3

jumlah 5.4 + 5.184 = 10.584 m3