NO URAIAN PEKERJAAN
1 PEKERJAAN PERSIAPAN
2 PEKERJAN BONGKARAN
18,983,652.44
12,665,688.00
4,499,382.62
18,894,000.00
26,506,080.56
8,952,600.00
9,939,545.00
1,000,000.00
113,244,660.62
12,456,912.67
125,701,573.29
125,700,000.00
Puluh Lima Juta Tujuh Ratus Ribu Rupiah
DAFTAR KUANTITAS DAN HARGA
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M²
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00
M²
IX PEKERJAAN PENGECATAN
Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota
1 Lama 160.30 M²
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00
M²
TOTAL
HARGA
1,000,000.00 1,000,000.00
42,490.00 6,258,777.00
1,000,000.00 1,000,000.00
750,000.00 750,000.00
Jumlah I 9,008,777.00
716,650.00 2,794,935.00
Jumlah II 2,794,935.00
78,750.00 793,327.50
700,500.00 3,152,250.00
700,500.00 5,430,276.00
68,215.00
6,350,816.50
781,707.05 3,256,982.44
Jumlah III 18,983,652.44
78,750.00 476,280.00
700,500.00 3,765,888.00
64,800.00 3,048,192.00
68,215.00 4,584,048.00
157,000.00 791,280.00
Jumlah IV 12,665,688.00
811,075.36 1,379,639.19
19,935.27 1,297,786.09
152,210.30 1,821,957.34
Jumlah V 4,499,382.62
524,833.33 18,894,000.00
Jumlah VI 18,894,000.00
186,055.56
21,368,480.56
67,600.00
5,137,600.00
Jumlah VII 26,506,080.56
225,000.00 1,587,600.00
225,000.00 1,800,000.00
150,000.00 3,150,000.00
35,000.00 2,415,000.00
Jumlah VIII 8,952,600.00
53,150.00 8,519,945.00
67,600.00
1,419,600.00
Jumlah IX 9,939,545.00
1,000,000.00 1,000,000.00
Jumlah X 1,000,000.00
TOTAL I s/d X 113,244,660.62
AGUSTA M. NDUN, ST
Direktur
DAFTAR KUANTITAS DAN HARGA
PEMILIK PEKERJAAN PEKERJAAN : Universitas Nusa Cendana MINGGU I
PEKERJAAN : Pekerjaan Pagar FKIP UNDANA (Pagar Keliling Taman) Star Saturday, May 28, 2022
LOKASI : Kampus FKIP UNDANA, Jl. Adi Sucipto Penfui Kupang s/d Saturday, June 4, 2022
TAHUN ANGGARAN : 2022 Realisasi Bobot: 8.15
KONSULTAN PENGAWAS : CV. CITRA PLANINDO Deviasi Bobot: 91.85
KONTRAKTOR PELAKSANA : CV.XXXXXXX
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 - - - 0% -
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 - - - 0% -
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 7.75 4.80 -
Kantor FKIP Lama) M³ 700,500.00 5,430,276.00 - - 0% -
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 93.10 68,215.00 5.61 -
Merapikannya Kembali M² 6,350,816.50 - - 0% -
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 - - - 0% -
Jumlah III 18,983,652.44 16.76 0.00 0.00
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 - - - 0% -
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 - - - 0% -
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 - - - 0% -
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 - - - 0% -
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - - 0% -
Jumlah IV 12,665,688.00 11.18 0.00 0.00
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 - - - 0% -
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 - - - 0% -
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 - - - 0% -
Jumlah V 4,499,382.62 3.97 0.00 0.00
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 -
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm
- - 0% -
Jumlah VI 18,894,000.00 16.68 0.00 0.00
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 18.87 -
21,368,480.56 - - 0% -
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - - - 0% -
Jumlah VII 26,506,080.56 23.41 0.00 0.00
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 8.15 8.15
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.20 20% 0.18 0.20 20% 0.18 0.40 40% 0.35
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 6.92 0.18 7.09
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 1.95 50% 1.23 1.95 50% 1.23 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 1.23 1.23 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 - 0% - 10.07 100% 0.70 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 - 0% - 4.50 100% 2.78 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 3.10
M³ 700,500.00 5,430,276.00 - 0% - 40% 1.92 3.10 40% 1.92
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 Merapikannya Kembali 93.10 68,215.00 5.61 -
M² 6,350,816.50 - 0% - - - 0% -
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 - 0% - - - - 0% -
Jumlah III 18,983,652.44 16.76 0.00 5.40 5.40
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 - 0% - 6.05 100% 0.42 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 - 0% - 5.38 100% 3.33 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 - 0% - - - - 0% -
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 - 0% - - - - 0% -
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - 0% - - - 0% -
Jumlah IV 12,665,688.00 11.18 0.00 3.75 3.75
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 - 0% - - - - 0% -
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 - 0% - - - - 0% -
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 - 0% - - - - 0% -
Jumlah V 4,499,382.62 3.97 0.00 0.00 0.00
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 -
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm - 0% - - - 0% -
Jumlah VI 18,894,000.00 16.68 0.00 0.00 0.00
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 18.87 -
21,368,480.56 - 0% - - - 0% -
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - - - - 0% -
Jumlah VII 26,506,080.56 23.41 0.00 0.00 0.00
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - 0% - - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 8.15 10.56 18.71
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.40 40% 0.35 - - 0.40 40% 0.35
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 7.09 - 7.09
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 4.65
M³ 700,500.00 5,430,276.00 3.10 40% 1.92 60% 2.88 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 Merapikannya Kembali 93.10 68,215.00 5.61 -
M² 6,350,816.50 - 0% - - - 0% -
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 - 0% - - - - 0% -
Jumlah III 18,983,652.44 16.76 5.40 2.88 8.28
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 - 0% - 16.46 35% 0.94 16.46 35% 0.94
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 - 0% - - - - 0% -
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - 0% - - - 0% -
Jumlah IV 12,665,688.00 11.18 3.75 0.94 4.69
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 - 0% - - - - 0% -
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 - 0% - 65.10 100% 1.15 65.10 100% 1.15
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 - 0% - - - - 0% -
Jumlah V 4,499,382.62 3.97 0.00 1.15 1.15
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 -
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm - 0% - - - 0% -
Jumlah VI 18,894,000.00 16.68 0.00 0.00 0.00
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 - 0% - 45.94 40% 7.55 45.94 40% 7.55
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - - - - 0% -
Jumlah VII 26,506,080.56 23.41 0.00 7.55 7.55
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - 0% - - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 18.71 12.51 31.22
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.40 40% 0.35 0.10 10% 0.09 0.50 50% 0.44
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 7.09 0.09 7.18
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 -
M³ 700,500.00 5,430,276.00 7.75 100% 4.80 - 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 Merapikannya Kembali 93.10 68,215.00 5.61 -
M² 6,350,816.50 - 0% - - - 0% -
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 - 0% - - - - 0% -
Jumlah III 18,983,652.44 16.76 8.28 0.00 8.28
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 16.46 35% 0.94 30.58 65% 1.75 47.04 100% 2.69
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 - 0% - - - - 0% -
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - 0% - - - 0% -
Jumlah IV 12,665,688.00 11.18 4.69 1.75 6.44
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 - 0% - 1.70 100% 1.22 1.70 100% 1.22
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 65.10 100% 1.15 - - 65.10 100% 1.15
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 - 0% - 11.97 100% 1.61 11.97 100% 1.61
Jumlah V 4,499,382.62 3.97 1.15 2.83 3.97
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 -
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm - 0% - - - 0% -
Jumlah VI 18,894,000.00 16.68 0.00 0.00 0.00
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 45.94 40% 7.55 42.49 37% 6.98 88.43 77% 14.53
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - - - - 0% -
Jumlah VII 26,506,080.56 23.41 7.55 6.98 14.53
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - 0% - - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 31.22 11.65 42.87
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.50 50% 0.44 0.10 10% 0.09 0.60 60% 0.53
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 7.18 0.09 7.27
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 -
M³ 700,500.00 5,430,276.00 7.75 100% 4.80 - 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 93.10 M² 68,215.00 6,350,816.50 5.61 - 0% - - - - 0% -
Merapikannya Kembali
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 - 0% - 2.37 57% 1.64 2.37 57% 1.64
Jumlah III 18,983,652.44 16.76 8.28 1.64 9.92
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 47.04 100% 2.69 - - 47.04 100% 2.69
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 - 0% - 25.54 38% 1.54 25.54 38% 1.54
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - 0% - - - 0% -
Jumlah IV 12,665,688.00 11.18 6.44 1.54 7.98
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 1.70 100% 1.22 - - 1.70 100% 1.22
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 65.10 100% 1.15 - - 65.10 100% 1.15
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 11.97 100% 1.61 - - 11.97 100% 1.61
Jumlah V 4,499,382.62 3.97 3.97 0.00 3.97
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 18.00
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm - 0% - 50% 8.34 18.00 50% 8.34
Jumlah VI 18,894,000.00 16.68 0.00 8.34 8.34
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 88.43 77% 14.53 26.42 23% 4.34 114.85 100% 18.87
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - - - - 0% -
Jumlah VII 26,506,080.56 23.41 14.53 4.34 18.87
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - 0% - - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 42.87 15.95 58.82
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.60 60% 0.53 0.10 10% 0.09 0.70 70% 0.62
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 7.27 0.09 7.36
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 -
M³ 700,500.00 5,430,276.00 7.75 100% 4.80 - 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 93.10 M² 68,215.00 6,350,816.50 5.61 - 0% - 58.65 63% 3.53 58.65 63% 3.53
Merapikannya Kembali
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 2.37 57% 1.64 1.79 43% 1.24 4.17 100% 2.88
Jumlah III 18,983,652.44 16.76 9.92 4.77 14.69
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 47.04 100% 2.69 - - 47.04 100% 2.69
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 25.54 38% 1.54 30.91 46% 1.86 56.45 84% 3.40
5 0.70 -
Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 - 0% - - - 0% -
Jumlah IV 12,665,688.00 11.18 7.98 1.86 9.84
V PEKERJAAN BETON KUBUS (Untuk Pot) 21 Bh
1 Beton Kolom (Cor Setempat + Pembesian)
a. Beton 1:2:3 1.70 M³ 811,075.36 1,379,639.19 1.22 1.70 100% 1.22 - - 1.70 100% 1.22
B. Besi U24 65.10 Kg 19,935.27 1,297,786.09 1.15 65.10 100% 1.15 - - 65.10 100% 1.15
c. Bekisting 11.97 M² 152,210.30 1,821,957.34 1.61 11.97 100% 1.61 - - 11.97 100% 1.61
Jumlah V 4,499,382.62 3.97 3.97 0.00 3.97
VI PEKERJAAN PAGAR BESI (Ukuran Gambar Terlampir)
Pek. Pagar Besi Hollow 4x4 Palangan Palangan Besi Beton 12mm + Mata Tombak
1 36.00 M² 524,833.33 18,894,000.00 16.68 18.00 50% 8.34 18.00 50% 8.34 36.00 100% 16.68
Dibagian Atas Tinggi 50cm Jarak Jelusi Antar Besi Beton= 15 cm
Jumlah VI 18,894,000.00 16.68 8.34 8.34 16.68
VII PEKERJAAN PAGAR RANTAI
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 114.85 100% 18.87 - - 114.85 100% 18.87
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - - - - 0% -
Jumlah VII 26,506,080.56 23.41 18.87 0.00 18.87
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - - - - 0% -
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - - - - 0% -
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 0.00 0.00
IX PEKERJAAN PENGECATAN
7.52 -
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 - 0% - - - 0% -
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - - - - 0% -
Jumlah IX 9,939,545.00 8.78 0.00 0.00 0.00
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 58.82 15.06 73.88
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.70 70% 0.62 0.10 10% 0.09 0.80 80% 0.71
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 - - 0.50 50% 0.33
Jumlah I 9,008,777.00 7.96 7.36 0.09 7.45
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 -
M³ 700,500.00 5,430,276.00 7.75 100% 4.80 - 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 93.10 M² 68,215.00 6,350,816.50 5.61 58.65 63% 3.53 34.45 37% 2.07 93.10 100% 5.61
Merapikannya Kembali
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 4.17 100% 2.88 - - 4.17 100% 2.88
Jumlah III 18,983,652.44 16.76 14.69 2.07 16.76
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 47.04 100% 2.69 - - 47.04 100% 2.69
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 56.45 84% 3.40 10.75 16% 0.65 67.20 100% 4.05
5 Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 0.70 - 0% - 5.04 100% 0.70 5.04 100% 0.70
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 114.85 100% 18.87 - - 114.85 100% 18.87
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 - 0% - 66.12 87% 3.95 66.12 87% 3.95
Jumlah VII 26,506,080.56 23.41 18.87 3.95 22.82
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 - 0% - 7.06 100% 1.40 7.06 100% 1.40
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 - 0% - 8.00 100% 1.59 8.00 100% 1.59
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - - - - 0% -
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - - - - 0% -
Jumlah VIII 8,952,600.00 7.91 0.00 2.99 2.99
IX PEKERJAAN PENGECATAN
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 7.52 - 0% - 60.91 38% 2.86 60.91 38% 2.86
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 - 0% - 17.64 84% 1.05 17.64 84% 1.05
Jumlah IX 9,939,545.00 8.78 0.00 3.91 3.91
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 -
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - - - 0% -
Jumlah X 1,000,000.00 0.88 0.00 0.00 0.00
TOTAL I s/d X 113,244,660.62 100.00 73.88 14.36 88.24
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 0.88 1.00 100% 0.88 - - 1.00 100% 0.88
2 Pek. Bowplank Pondasi & Kubus Pot 147.30 M 42,490.00 6,258,777.00 5.53 147.30 100% 5.53 - - 147.30 100% 5.53
3 Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00 0.88 0.80 80% 0.71 0.20 20% 0.18 1.00 100% 0.88
4 Dokumentasi 1.00 Ls 750,000.00 750,000.00 0.66 0.50 50% 0.33 0.50 50% 0.33 1.00 100% 0.66
Jumlah I 9,008,777.00 7.96 7.45 0.51 7.96
II PEKERJAN BONGKARAN
1 Pek. Membongkar Les Atas Pot Lama 3.90 M² 716,650.00 2,794,935.00 2.47 3.90 100% 2.47 - - 3.90 100% 2.47
Jumlah II 2,794,935.00 2.47 2.47 - 2.47
III PEKERJAAN PONDASI DALAM/BOULEVARD, PEK. TAMBAL POT LAMA, PLESTERAN &
ACIAN
1 Pek. Galian Lubang Pondasi (Trotoar & Area Pagar (2)+(3) 10.07 M³ 78,750.00 793,327.50 0.70 10.07 100% 0.70 - - 10.07 100% 0.70
2 Pek. Pas. Pondasi Batu Karang 1:5 (Trotoar Dalam Boulevard) 4.50 M³ 700,500.00 3,152,250.00 2.78 4.50 100% 2.78 - - 4.50 100% 2.78
Pek. Pas. Pondasi Batu Karang 1:5 (Pagar Kubus Sisi Area Pek. Pagar (2) & (3) / Depan
3 Kantor FKIP Lama) 7.75 4.80 -
M³ 700,500.00 5,430,276.00 7.75 100% 4.80 - 7.75 100% 4.80
Plesteran & Acian Pondasi Trotoar Dalam Dan Tambahan Peninggi Pot Serta
4 93.10 M² 68,215.00 6,350,816.50 5.61 93.10 100% 5.61 - - 93.10 100% 5.61
Merapikannya Kembali
5 Pek. Pas. Tambalan/Renovasi Elevasi Pot (Beton Non Pembesian) 4.17 M³ 781,707.05 3,256,982.44 2.88 4.17 100% 2.88 - - 4.17 100% 2.88
Jumlah III 18,983,652.44 16.76 16.76 0.00 16.76
IV PEKERJAAN POT KUBUS
1 Pek. GalianPondasi Kubus 6.05 M³ 78,750.00 476,280.00 0.42 6.05 100% 0.42 - - 6.05 100% 0.42
2 Pek. Pondasi (Batu Karang) Kubus 1:5) 5.38 M² 700,500.00 3,765,888.00 3.33 5.38 100% 3.33 - - 5.38 100% 3.33
3 Pek. Pas. Batako 47.04 M² 64,800.00 3,048,192.00 2.69 47.04 100% 2.69 - - 47.04 100% 2.69
4 Pek. Plesteran & acian Keliling Kubus Pot 67.20 M² 68,215.00 4,584,048.00 4.05 67.20 100% 4.05 - - 67.20 100% 4.05
5 Pek. Keramik Tempel ( Dinding Depan Pot, Tekstur Dikonsultasikan KE Owner FKIP) 5.04 157,000.00 791,280.00 0.70 5.04 100% 0.70 - - 5.04 100% 0.70
1 Pek. Pagar Rantai Dengan Menggunakan Tiang/Kolom Pippa Galvanis Tinggi Maks. 1m 114.85 M 186,055.56 21,368,480.56 18.87 114.85 100% 18.87 - - 114.85 100% 18.87
2 Pek. Pengecatan Permukaan Besi Dengan Meni Besi Yang Ditentukan 76.00 M² 67,600.00 5,137,600.00 4.54 66.12 87% 3.95 9.88 13% 0.59 76.00 100% 4.54
Jumlah VII 26,506,080.56 23.41 22.82 0.59 23.41
VIII PEKERJAAN TAMAN KUBUS & BOULEVARD
1 Urugan Tanah Hitam (Untuk Kubus Taman Bungan) 7.06 M³ 225,000.00 1,587,600.00 1.40 7.06 100% 1.40 - - 7.06 100% 1.40
2 Urugan Tanah Hitam (Untuk Boulevard/Trotoar Dalam) 8.00 M³ 225,000.00 1,800,000.00 1.59 8.00 100% 1.59 - - 8.00 100% 1.59
3 Pupuk Kandang (Fases Sapi) 21.00 Pot 150,000.00 3,150,000.00 2.78 - 0% - 21.00 100% 2.78 21.00 100% 2.78
4 Lantana (Tahi Ayam) 69.00 Pot 35,000.00 2,415,000.00 2.13 - 0% - 69.00 100% 2.13 69.00 100% 2.13
Jumlah VIII 8,952,600.00 7.91 2.99 4.91 7.91
IX PEKERJAAN PENGECATAN
1 Pek. Pengcatan Kolom, Kubus, Pondasi Trotoar & Tambahan Peninggi Pota Lama 160.30 M² 53,150.00 8,519,945.00 7.52 60.91 38% 2.86 99.39 62% 4.66 160.30 100% 7.52
2 Pek. Pengacatan Permukaan Baja Dengan Meni Besi (Pagar Tombak) 21.00 M² 67,600.00 1,419,600.00 1.25 17.64 84% 1.05 3.36 16% 0.20 21.00 100% 1.25
Jumlah IX 9,939,545.00 8.78 3.91 4.87 8.78
X PEKERJAAN PEMBERSIHAN LOKASI
Pek. Pembersihan Lokasi (Pembersihan Material Areal Lokasi Pekerjaan & Sekitarnya, 0.88 1.00
1 Diangkut Keluar) 1.00 LS 1,000,000.00 1,000,000.00 - 0% - 100% 0.88 1.00 100% 0.88
Jumlah X 1,000,000.00 0.88 0.00 0.88 0.88
TOTAL I s/d X 113,244,660.62 100.00 88.24 11.76 100.00