A UPAH
1 Pekerja 88,000.00 OH
2 Tukang Batu 93,500.00 OH
3 Tukang Kayu 93,500.00 OH
4 Tukang Besi 93,500.00 OH
5 Tukang Cat 93,500.00 OH
6 Tukang Las Konstruksi 93,500.00 OH
7 Kepala Tukang 125,000.00 OH
8 Mandor 100,000.00 OH
B BAHAN
B.1 Tanah/Timbunan
1 Pasir urug 136,000.00 m3
2 Pasir pasang 140,000.00 m3
3 Pasir beton 140,000.00 m3
4 Tanah urug 60,000.00 m3
6 Tanah merah 157,300.00 m3
B.9 Cat/Minyak/Lem
1 Cat dasar 32,492.00 kg
2 Cat antara 12,450.00 kg
3 Cat tembok interior 36,092.00 kg
4 Cat tembok eksterior 100,000.00 kg
5 Cat besi 77,800.00 kg
6 Cat kayu 39,400.00 kg
7 Plamir 25,000.00 kg
8 Minyak bekisting 5,500.00 liter
10 Cat menie 31,700.00 kg
11 Lem kayu 27,500.00 liter
12 Lem Kayu kg 3,500.00 kg
13 Kuas 15,000.00 buah
14 Pengencer 30,000.00 kg
15 Wood filler 38,870.00 kg
16 Woodstain 169,000.00 kg
17 Sanding 80,600.00 kg
No. Uraian Harga Satuan
(1) (2) (3) (4)
18 Melamic 78,000.00 kg
19 Tiner 13,700.00 liter
20 Ampelas 7,000.00 lembar
B.12 Elektrikal
1 Instalasi pemasangan titik lampu 200,000.00 titik
2 MCB 3 phase 50 ampere 356,821.05 buah
3 Meteran listrik metbelosa 104,000.00 buah
4 Sakelar tunggal 10,100.00 buah
5 Sakelar ganda 13,000.00 buah
6 Stop kontak 11,300.00 buah
7 Kabel NYM Inti 4 Uk 1,5 mm2 12,000.00 m
8 Lighting panel (LP) 2,300,000.00 buah
9 Sub distribution panel (SDP) 9,000,000.00 buah
10 Lampu TKO 2×40 watt 212,000.00 buah
11 Lampu down light 212,300.00 buah
12 Lampu SL 1×18 watt 111,000.00 buah
13 Panel box listrik 600,000.00 buah
B.13 Kusen/Pintu/Jendela/Kaca/Aksesoris
1 Kaca polos tebal 5 mm 130,400.00 m2
2 Kunci tanam 94,100.00 buah
3 Kunci tanam KM 100,000.00 buah
4 Engsel pintu 20,000.00 buah
5 Engsel kupu-kupu 17,500.00 buah
6 Engsel angin 54,000.00 buah
7 Spring knip 37,000.00 buah
8 Kait angin Kuningan 10,000.00 buah
9 Door closer 50,000.00 buah
10 Floor hinge 1,560,000.00 buah
11 Over panel 361,400.00 buah
12 Top patch fitting 165,100.00 buah
13 Bottom patch fitting 176,800.00 buah
14 Bottom patch lock + silinder 1,250,000.00 buah
15 Pull handle 2,250,000.00 buah
16 Pintu Panel Ulin 80x210 775,000.00 buah
17 Daun angin-angin 450,000.00 buah
18 Daun pintu kaca 9 mm rangka aluminium standar 2,472,500.00 buah
19 Daun pintu kaca 9 mm rangka aluminium besar 3,450,000.00 buah
20 Daun jendela kaca 5 mm rangka aluminium standar 546,250.00 buah
21 Kusen dan pintu PVC toilet 500,000.00 buah
22 Rel sliding track PG aluminium 240 cm 455,000.00 m
23 Gerendel jendela kuningan 20,000.00 bh
24 Gerendel Pintu panjang 40,000.00 bh
25 Tarikan jendela 17,500.00 bh
26 Pintu panil kayu meranti uk. 80 x 190 cm 770,000.00 bh
REKAPITULASI ANALISA PEKERJAAN
No. Kode Uraian Pekerjaan Harga Satuan (Rp) Satuan
(1) (2) (3) (4) (5)
A PEKERJAAN PERSIAPAN
1 A.1 Pengukuran dan pemasangan Bouwplank 202,652.66 1m
2 A.1 Pengukuran dan pemasangan Bouwplank 202,652.66 1m
3 A.2 Pembongkaran dinding tembok bata 712,995.40 1 m3
4 A.3 Pembongkaran dinding kayu 13,814.38 1 m2
5 A.4 Pembongkaran Atap dan Plafon 4,144.31 1 m2
B PEKERJAAN TANAH
6 B.1 Penggalian tanah biasa sedalam 1 m 59,160.60 1 m3
7 B.2 Penggalian tanah keras sedalam 1 m 104,880.00 1 m3
8 B.3 Penggalian tanah lumpur sedalam 1 m 126,615.00 1 m3
9 B.4 Pengurugan kembali galian tanah 26,220.00 1 m3
10 B.5 Pengurugan dengan pasir urug 219,190.00 1 m3
11 B.6 Pengurugan situ padat 490,199.00 1 m2
12 B.7 Pengurugan dengan tanah merah 254,293.75 1 m3
13 B.8 Pengurugan dengan tanah urug 247,003.24 1 m3
C PEKERJAAN PONDASI
14 C.1 Pemasangan pondasi batu belah campuran 1 SP : 4 PP 850,310.00 1 m3
15 C.2 Pemasangan batu kosong (anstamping) 488,326.80 1 m3
16 C.3 Pancangan kayu galam Ø8-10 22,630.56 1m
D PEKERJAAN BETON
17 D.1 Membuat lantai kerja beton mutu f'c = 7,4 MPa (K-100), slump (3-6) cm, w/c = 0,87 909,043.87 1 m3
18 D.2 Membuat beton mutu f'c = 19,3 MPa (K-225), slump (12±2) cm, w/c = 0,58 1,143,862.02 1 m3
19 D.3 Pembesian dengan besi polos 16,528.95 1 kg
20 D.4 Pemasangan bekisting untuk pondasi 404,326.20 1 m2
21 D.5 Pemasangan bekisting untuk sloof 442,679.85 1 m2
22 D.6 Pemasangan bekisting untuk kolom 359,401.80 1 m2
23 D.7 Pemasangan bekisting untuk balok 386,325.25 1 m2
24 D.8 Pemasangan bekisting untuk lantai 357,188.28 1 m2
25 D.9 Pemasangan bekisting untuk dinding 411,260.70 1 m2
26 D.10 Pemasangan bekisting untuk tangga 329,272.03 1 m2
27 D.11 Membuat kolom praktis beton bertulang (11 × 11) cm 107,556.17 1m
28 D.12 Membuat ring balok beton bertulang (10 × 15) cm 134,339.09 1m
E PEKERJAAN BESI DAN ALUMINIUM
29 E.1 Pemasangan kusen pintu aluminium 137,772.30 1m
30 E.2 Pemasangan talang 1/2 lingkaran dia. 15 cm, seng plat BJLS 30 lebar 45 cm 115,956.80 1m
31 E.3 Pemasangan rangka besi hollow 1 × 40.40.2 mm, modul 60 × 60 cm, untuk plafon 114,655.00 1 m2
F PEKERJAAN PASANGAN DINDING
32 F.1 Pemasangan dinding bata ringan tebal 7,5 cm campuran 1 SP : 3PP 387,299.30 1 m2
33 F.2 Pemasangan dinding bata merah 5×11×22 cm tebal ½ batu campuran 1 SP : 4 PP 122,268.00 1 m2
34 F.0 Pemasangan dinding bata merah (5 × 11 × 22) cm tebal 1 batu campuran 1 SP : 2 PP 265,190.00 1 m2
G PEKERJAAN PLESTERAN
35 G.2 Pemasangan plesteran 1 SP : 4 PP tebal 15 mm 64,803.88 1 m2
36 G.3 Pemasangan acian 62,845.20 1 m2
37 H.1 Pemasangan lantai ubin warna ukuran 40 cm×40 cm 38,065.00 1 m2
H PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
38 H.2 Pemasangan lantai ubin warna ukuran 30 cm × 30 cm 103,755.88 1 m2
39 H.3 Pemasangan lantai ubin warna ukuran 20 cm × 20 cm 103,755.88 1 m2
40 H.4 Pemasangan plint ubin warna ukuran 10 cm × 40 cm 40,998.08 1m
41 H.5 Pemasangan lantai ubin teralux marmer ukuran 60 cm × 60 cm 340,653.00
I PEKERJAAN LANGIT-LANGIT (PLAFON)
42 I.1 Pemasangan langit-langit gypsum board ukuran (120×240×) mm, tebal 3 mm 65,283.78 m2
43 I.3 Pemasangan 1 m’ list langit-langit kayu profil 42,031.35 1m
44 J.1 Pemasangan genteng metal ukuran 80 × 100 atap pelana 167,497.50 1 m2
45 J.2 Pemasangan genteng metal ukuran 80 × 100 atap jurai 197,616.00 1 m2
J PEKERJAAN PENUTUP ATAP
46 J.3 Pemasangan nok genteng metal 78,297.75 1m
47 J.4 Pemasangan listplank ukuran (3 × 30) cm 103,597.75 1m
48 K.1 Pembuatan dan pemasangan kusen pintu , kayu kelas I 14,041,666.75 1 m3
49 K.2 Pekerjaan Rangka Bawah Ulin Pjg 4 meter 13,024,923.00 1 m3
K PEKERJAAN KAYU
50 K.3 Pekerjaan Rangka Bawah Ulin Pjg 2 meter 12,235,183.50 1 m3
51 K.4 Pekerjaan Rangka Badan Ulin 13,153,263.00 1 m3
52 K.5 Pekerjaan Rangka Badan Ulin Kayu Kelas II dan III 12,363,523.50 1 m3
53 K.6 Pemasangan 1 m2 dinding pemisah plywood rangkap. rangka kayu kelas II 305,342.25 1 m3
54 K.7 Pekerjaan Lantai Papan ulin pjg 4 m kelas 1 187,390.20 1 m3
55 K.8 Pasangan tongkat ulin 10/10 cm tinggi 3,8 m 524,091.34 1 btg
56 K.9 Pasangan suai 5/7 13,669,716.50 1 m3
57 K.10 Pasangan sloof dan gelagar 13,343,473.00 1 m3
58 K.11 Pemasangan 1m2 Dinding papan kayu kelas II dan III 239,957.16 1 m2
59 L.1 Pemasangan kunci tanam biasa 170,752.00 1 bh
60 L.2 Pemasangan kunci kamar mandi 176,801.00 1 bh
No. Kode Uraian Pekerjaan Harga Satuan (Rp) Satuan
(1) (2) (3) (4) (5)
M PEKERJAAN PENGECATAN
50 M.1 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 51,847.91 1 m2
51 M.2 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) interior 27,451.79 1 m2
52 M.3 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) eksterior 46,560.28 1 m2
K PEKERJAAN KAYU
53 K.6 Pemasangan 1 m2 dinding pemisah plywood rangkap. rangka kayu kelas II 170,752.00 1 m3
54 K.7 Pekerjaan Lantai Papan ulin pjg 4 m kelas 1 176,801.00 1 m3
55 K.8 Pasangan tongkat ulin 10/10 cm tinggi 3,8 m 42,895.00 1 btg
56 K.9 Pasangan suai 5/7 33,384.50 1 m3
57 K.10 Pasangan sloof dan gelagar 97,462.50 1 m3
58 K.11 Pemasangan 1m2 Dinding papan kayu kelas II dan III 36,794.25 1 m2
59 L.1 Pemasangan kunci tanam biasa 123,855.00 1 bh
60 L.2 Pemasangan kunci kamar mandi 184,851.00 1 bh
L PEKERJAAN KUNCI DAN KACA
61 L.3 Pemasangan engsel pintu 51,847.91 1 bh
62 L.4 Pemasangan engsel jendela kupu-kupu 27,451.79 1 bh
63 L.5 Pemasangan engsel angin 46,560.28 1 bh
N LAIN - LAIN
64 N.1 Pemasangan kusen kayu daun Pintu kayu meranti P1 4,307,000.00 1 bh
65 N.2 Pemasangan kusen daun kayu J1 3,842,000.00 1 bh
66 N.3 Pemasangan kusen daun kayu J2 5,833,000.00 1 bh
67 N.4 Pemasangan kusen kayu daun Pintu kayu meranti P2 6,818,000.00 1 bh
68 N.5 Ventelasi & Jendela Alimunium 1,867,000.00 1 bh
M SANITASI
69 K.3 Pemasangan bak mandi batu bata volume 0,30 m3 2,229,045.00 1 bh
70 K.4 Pemasangan kloset jongkok porselen 870,090.00 1 bh
71 K.5 Pemasangan urinoir 953,649.00 1 bh
72 K.6 Pemasangan wastafel 1,622,191.15 1 bh
73 K.8 Pemasangan floor drain 64,147.00 1 bh
74 K.9 Pemasangan pipa PVC tipe AW diameter ½" 64,662.20 1 bh
75 K.10 Pemasangan pipa PVC tipe AW diameter 2" 117,670.30 1 bh
76 K.11 Pemasangan pipa PVC tipe AW diameter 4" 707,775.55 1 bh
77 Paving Blok 264,989.90 m2
78 Pemasangan Kran Air 113,740.75 1 bh
79 Pemasangan 1 unit septicktank 7,429,000.00
80 Pemasangan 1 m' saluran keliling bangunan 145,000.00
REKAPITULASI
Pekerjaan : Sarana Toilet Umum RTH Tapin
Lokasi : Kab. Tapin
Tahun Anggaran : 2018
No. Uraian Pekerjaan Kode Analisa Volume Harga Satuan (Rp) Jumlah Harga (Rp)
A PEKERJAAN PERSIAPAN
1 Uitzen, pembersihan dan pengukuran lapangan -- 1.00 Ls 750,000.00 750,000.00
2 Papan nama proyek -- 1.00 Ls 334,000.00 334,000.00
3 Pemasangan bouwplank -- 1.00 Ls 1,000,000.00 1,000,000.00
Jumlah 2,084,000.00
B PEKERJAAN STRUKTURAL
Sub Struktur
Pekerjaan Pondasi
1 Galian Tanah pondasi B.2 21.93 m3 104,880.00 2,300,018.00
2 Tanah Urug B.8 30.60 m3 247,003.24 7,558,299.00
3 Pasir Urug bawah pondasi B.5 5.81 m3 219,190.00 1,272,398.00
4 Pondasi batu kali C.1 18.92 m3 850,310.00 16,087,865.00
5 Pasangan Batu Kosong (Anstamping) C.2 5.81 m3 488,326.80 2,834,737.00
6 Pondasi Poer (P1) 80 x 80
Beton D.2 0.77 m3 1,143,862.02 878,486.00
Besi D.3 7.20 kg 16,528.95 119,079.00
Bekisting D.4 9.60 m2 404,326.20 3,881,532.00
7 Pondasi poer (P2) 80 x 120 -
Beton D.2 0.77 m3 1,143,862.02 878,486.00
Besi D.3 8.68 kg 16,528.95 143,536.00
Bekisting D.4 9.60 m2 404,326.20 3,881,532.00
8 Pasir Urug bawah poer 10 cm B.5 0.94 m3 219,190.00 205,162.00
9 Lantai Kerja 5 cm D.1 0.47 m3 909,043.87 425,433.00
10 Rollag Bata F.0 16.26 m2 265,190.00 4,311,989.00
11 Sloof 20/25 -
Beton D.2 m3 1,143,862.02 -
Besi D.3 kg 16,528.95 -
Bekisting D.5 m2 442,679.85 -
Jumlah 44,778,552.00
Pekerjaan Beton
1 Kolom 20/20
Beton D.2 1.30 m3 1,143,862.02 1,482,445.18
Besi D.3 152.70 kg 16,528.95 2,523,894.00
Bekisting D.6 10.80 m2 359,401.80 3,881,539.00
2 Kolom 20/60
Beton D.2 0.58 m3 1,143,862.02 658,864.52
Besi D.3 188.99 kg 16,528.95 3,123,842.00
Bekisting D.6 11.52 m2 329,272.03 3,793,214.00
3 Balok 20/30
Beton D.2 0.72 m3 1,143,862.02 823,581.00
Besi D.3 117.02 kg 16,528.95 1,934,300.00
Bekisting D.7 9.60 m2 386,325.25 3,708,722.00
4 Ring balk
Beton D.2 0.17 m3 1,143,862.02 192,169.00
Besi D.3 26.18 kg 16,528.95 432,739.00
Bekisting D.7 3.08 m2 386,325.25 1,189,882.00
5 Dak Beton
Beton D.2 1.15 m3 1,143,862.02 1,310,866.00
Besi D.3 264.93 kg 16,528.95 4,378,952.00
Bekisting D.8 35.58 m2 357,188.28 12,708,759.00
Jumlah 42,143,768.70
Jumlah Pekerjaan Struktural 86,922,320.70
C PEKERJAAN ATAP
1 Rangka Atap Baja Ringan -- 46.24 m2 160,000.00 7,398,400.00
2 Penutup atap genteng metal J.1 46.24 m2 78,297.75 3,620,488.00
3 Lisplank kalsiplank tebal 8 mm' J.4 27.56 m 103,597.75 2,855,154.00
Jumlah 13,874,042.00
No. Uraian Pekerjaan Kode Analisa Volume Harga Satuan (Rp) Jumlah Harga (Rp)
2 Fondasi
Panjang Lebar Bawah Lebar Atas Tinggi Jumlah Luas
Galian Tanah 43.00 0.90 0.30 0.85 1.00 0.51 21.93
0.47
Lantai Kerja Bawah Pondasi 0.90 0.90 6.00 0.05 0.24
0.90 1.25 4.00 0.05 0.23
4 Balok Lantai
Balok 20/30 12.00 0.20 0.30 0.720 - 0.72
4 Kolom
Panjang Lebar Tinggi Volume Jumlah
a Neut 30/30 (N1) 0.30 0.30 0.70 0.06 24.00 1.51 1.51
Neut 20/20 (N2) 0.20 0.20 0.70 0.03 7.00 0.20 0.20
b Kolom 20/30 (K1) 0.20 0.30 3.60 0.22 6.00 1.30
Kolom 20/60(K2) 0.20 0.20 3.60 0.14 4.00 0.58
5 Ringbalk 15/20
Panjang Lebar Tinggi Volume Jumlah
5.60 0.15 0.20 0.17 0.17
6 Dinding Bata Panjang Tinggi Luas Jumlah Luasan Kusen Luasan Kolom
a Depan 6.00 4.40 26.40 1.00 11.04 15.36
b Belakang 6.00 3.35 20.10 1.00 5.06 15.05
c Samping 3.40 4.00 6.80 2.00 13.60
d Dalam 2.00 3.50 7.00 2.00 14.00
4.00 3.50 14.00 1.00 14.00
Jumlah 58.01
7 Plesteran 58.01
Ls
m3
m3
m3
m3
m3
m2
m3
m3
m3
m3
btg
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m2
m2
m2
m3
m2
m2
m2
m2
m
m
m
BACK UP RUANG KELAS
Satuan
m2
m2
m2
m2
m2
m2
m2
bh
m3
m2
bh
m3
bh
m3
bh
m3
m2
m2
m2
m2
m2
m'
m2
m2
RINCIAN BERAT PEMBESIAN
BETON TULANGAN UTAMA TULANGAN SENGKANG UTAMA M3 BERAT BERAT CEK
No. UNIT PEKERJAAN B H T VOL Jarak P JLH dia. FB KG Panjang Jarak Jumlah dia. FB KG + BETON BESI (KG) BESI KUBIKASI
cm mm. kg/m Sengkang cm Sengkang mm. kg/m SENGKANG MAX BESI
A Bangunan Kelas
2 Poer 80/80 0.80 0.80 0.25 0.16 15.00 0.25 6.00 13 1.042 1.56 3.05 12.5 3.00 10 0.617 5.64 7.20 1 45 200 OK Pokok D 13, Senglang 10 polos
2 Poer 80/120 0.80 1.20 0.25 0.24 15.00 0.25 6.00 13 1.042 1.56 3.85 12.5 3.00 10 0.617 7.12 8.68 1 36 200 OK Pokok D 13, Senglang 10 polos
3 Balok sloof 20/25 0.20 0.25 86.00 4.30 86.00 7.00 12 0.888 534.46 0.75 15 575.00 8 0.395 170.16 704.63 1 164 200 OK
4 Balok Lantai 20/30 0.20 0.30 12.00 0.72 12.00 7.00 12 0.888 74.58 0.85 15 81.00 10 0.617 42.45 117.02 1 163 200 OK
6 Kolom 20/30 0.20 0.30 21.60 1.30 21.60 4.00 12 0.888 76.71 0.85 15 145.00 10 0.617 75.99 152.70 1 118 300 OK
7 Kolom 20/60 0.20 0.60 14.40 1.73 14.40 8.00 12 0.888 102.28 1.45 15 97.00 10 0.617 86.72 188.99 1 109 300 OK
8 Neut 30/30 0.30 0.30 19.20 1.73 19.20 6.00 12 0.888 102.28 1.05 15 129.00 10 0.617 83.51 185.79 1 108 300 OK #REF!
9 Neut 20/20 0.30 0.30 5.60 0.50 5.60 4.00 12 0.888 19.89 1.05 15 39.00 10 0.617 25.25 45.13 1 90 300 OK #REF!
10 Ring Balk 15/20 0.15 0.20 5.60 0.17 5.60 4.00 12 0.888 19.89 0.55 20 29.00 8 0.395 6.29 26.18 1 156 200 OK
11 Plat Lantai tebal 10 cm 5.73 6 0.12 4.13 15.00 6.17 40.00 10 0.617 152.16 5.90 20.0 31.00 10 0.617 112.76 264.93 1 64 150 OK
BETON BEKISTING
Tnggi/
NO. URAIAN PEKERJAAN Jumlah B H panjang Vol 1 M3 Luas B Luas H Jumlah Jumlah Keperluan Keperluan Total Luas Total Satuan
n Beton M2 M2 B H Bekisting B Bekisting H Bekisting Bekisting
B Bangunan Kelas
1 Poer 80/80 6 0.8 0.8 0.30 1.15 0.87 0.64 0.24 1 4 0.64 0.96 9.6 8.33 M2
1 Poer 80/120 4 0.8 1.2 0.30 1.15 0.87 0.96 0.36 1 4 0.96 1.44 9.6 8.33 M2
2 Sloof 20/25 1 0.2 0.25 86.00 4.30 0.23 17.20 21.50 1 2 17.20 43.00 30.1 7.00 M2
3 Kolom 20/30(K1) 6 0.2 0.3 3.6 1.30 0.77 0.72 1.08 1 1 0.72 1.08 10.8 8.33 M2
4 Kolom 20/60(K2) 4 0.2 0.6 3.6 1.73 0.58 0.72 2.16 1 1 0.72 2.16 11.5 6.67 M2
5 Ring Balk 15/20 1 0.15 0.2 5.60 0.17 5.95 0.84 1.12 1 2 0.84 2.24 3.1 18.33 M2
6 Balok Lantai 20/30 1 0.2 0.3 12.00 0.72 1.39 2.40 3.60 1 2 2.40 7.20 9.6 13.33 M2
8 Plat Lantai 1 5.73 6 0.20 6.45 0.16 34.38 1.20 1 1 34.38 1.20 35.6 5.52 M2
RENCANA ANGGARAN BIAYA
HARGA
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN SATUAN
(Rp)
1 2 3 4 5 6
I PEKERJAAN TANAH
1 Pek.Pasir Urug bawah bata press SNI-ABK. A.2.3.1.11 8.09 M³ 219,190.00
Sub Jumlah
II PEKERJAAN PASANGAN
1 Pemasangan Bata Press (Paving Block) SNI-ABK.012 60.80 M² 264,989.90
Sub Jumlah
Sub Jumlah
IV PEKERJAAN DRAINASE
1 Drainase sekeliling bangunan A.7.1.1.2. 31.20 M 145,000.00
Sub Jumlah
JUMLAH TOTAL
JUMLAH
HARGA
(Rp)
7
1,773,269.02
1,773,269.02
16,111,385.92
16,111,385.92
9,253,958.14
1,671,641.13
10,925,599.26
4,524,000.00
4,524,000.00
33,334,254.20