HARGA
NO URAIAN VOLUME SATUAN
SATUAN
I. SIPIL
A. PEKERJAAN PERSIAPAN
1 Pagar Pengaman Proyek 30.00 M'
2 Papan nama proyek 1.00 Ls
3 Mobilisasi Alat Berat 1.00 Ls
4 Pembuatan Direksi Keet 24.00 M²
5 Air kerja 1.00 Ls
6 Listrik kerja 1.00 Ls
7 Laporan administrasi & Dokumentasi proyek 3.00 Ls
8 K3 (Rencana Keselamatan Konstruksi, APD, APK, Asuransi, Personil K3, Fasilitas dan Prasarana, APAR) 1.00 Ls
9 As built drawing 1.00 Ls
10 Keamanan Lingkungan Kerja 1.00 Ls
B PEKERJAAN ELEKTRIKAL
1 PEKERJAAN PENERANGAN SITE
1 Instalasi Penerangan Luar 65.00 titik
2 Spot Light 20.00 Buah
3 Lampu Taman Type 1 6.00 Buah
4 Lampu Taman Type 2 23.00 Buah
5 Lampu LED Strip 140.00 M¹
6 Panel LP.Taman 1.00 Buah
HARGA
NO URAIAN VOLUME SATUAN
SATUAN
7 Saklar Tunggal ex Panasonic/setara 1.00 Buah
8 Saklar Ganda ex Panasonic/setara 1.00 Buah
11 Penangkal Petir Radius R 50 m 1.00 Set
12 Sistem Pentanahan Panel Unit Rumah dan Pos Jaga 14.00 Titik
Testing & comissioning 1.00 ls
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- Coating
-
-
-
-
-
- Taco TH 305 H
-
- Dulux Charcoal Choice
-
-
-
-
JUMLAH KETERANGAN
- Roman
-
-
-
-
-
-
- Natural White/ Warm white
- Panasonic
- Panasonic
-
-
-
-
- Cisangkan TruePave
-
-
-
-
-
-
-
-
-
-
- READY MIX K300
- Sika Grout 215
- Conwood Deck
- Batas Taman & Jalan
- Batu koral abu
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- Dulux Woodsmoke
-
-
-
-
-
-
-
-
-
-
-
-
- Phillips Warm white
-
-
- Selang SMD 2835 Natural White
-
JUMLAH KETERANGAN
- Panasonic
- Panasonic
-
-
-
-
BILL OF QUANTITY (BQ)
PEKERJAAN RUNAH TYPE 1
PROYEK : RUMAH PRIBADI
LOKASI : TARAKAN
6. KOLOM PENDESTAL P1 uk 20 X 20 cm
Lantai 1
6.1 Bekisting 0.80 M2 Rp 124,180.83 Rp 99,345
6.2 Besi
- Tulangan Utama ø 12 7.10 Kg Rp 16,251.95 Rp 115,454
- Tulangan Sengkang ø 8 - 200 1.82 Kg Rp 16,251.95 Rp 29,581
6.3 Beton Site Mix K250 0.040 M3 Rp 1,454,667.50 Rp 58,187
7.0 Sloof SI 20 x 40
6.1 Bekisting 25.24 M2 Rp 229,680.00 Rp 5,797,031
6.2 Besi
- Tulangan Utama ø 12 173.34 Kg Rp 16,251.95 Rp 2,817,074
- Tulangan Sengkang ø 8 - 200 90.47 Kg Rp 16,251.95 Rp 1,470,374
6.3 Beton Site Mix K250 2.524 M3 Rp 1,454,667.50 Rp 3,671,523
1.5 Galian 7.49 M3 Rp 94,875.00 Rp 711,031
1.6 Urugan 4.97 M3 Rp 216,150.00 Rp 1,074,361
NO. URAIAN VOLUME SATUAN HARSAT JUMLAH
11.0 KOLOM K2 15 x 30 cm
Lantai 1
11.1 Bekisting 7.56 M2 Rp 124,180.83 Rp 938,807
11.2 Besi
- Tulangan Utama ø 12 29.62 Kg Rp 16,251.95 Rp 481,318
- Tulangan Sengkang ø 8 - 200 16.02 Kg Rp 16,251.95 Rp 260,376
11.3 Beton Site Mix K250 0.378 M3 Rp 1,454,667.50 Rp 549,864
15.0 CANOPY
15.1 Bekisting (termasuk stop cor) 142.57 m2 Rp 188,746.25 Rp 26,909,930
15.2 Besi
15.3 - Tulangan Sengkang ø 10 - 150 ( Dua Lapis) 144.95 Kg Rp 16,251.95 Rp 2,355,707
15.4 Beton Site Mix K250 11.09 M3 Rp 1,454,667.50 Rp 16,129,720
16.0 ATAP
16.1 Pekerjaan Kuda-Kuda Baja Ringan C 75 + Reng Baja ringan 183.06 M2 Rp 267,374.80 Rp 48,945,631
16.2 Atap genteng metal 183.06 M2 Rp 144,606.00 Rp 26,471,574
16.3 genteng tepi / nok pinggir 41.39 m' Rp 116,974.00 Rp 4,841,554
16.4 Bubungan / nok 8.81 m' Rp 116,974.00 Rp 1,030,541
16.5 Lisplank 41.39 m' Rp 72,248.00 Rp 2,990,345
16.6 Flashing atap + ban2an 5.67 M2 Rp 200,000.00 Rp 1,134,000
16.7 Aluminium foil 183.06 M2 Rp 35,000.00 Rp 6,407,100
16.8 balok atap / sopi - sopi
16.9 Bekisting 9.84 M2 Rp 128,030.83 Rp 1,259,823
20.0 Besi
- Tulangan Utama ø 10 125.87 Kg Rp 16,251.95 Rp 2,045,600
- Tulangan Sengkang ø 8 - 150 24.42 Kg Rp 16,251.95 Rp 396,880
20.1 Beton Site Mix K250 0.492 M3 Rp 1,454,667.50 Rp 715,696
1.0 DINDING
1.1 - Pasangan Bata Merah 371.06 M2 Rp 156,755.50 Rp 58,165,696
1.2 - Plesteran 609.28 M2 Rp 74,801.10 Rp 45,574,814
1.3 - Acian 600.04 M2 Rp 46,090.00 Rp 27,655,844
1.4 - Kamprot Halus 5.47 M2 Rp 60,662.80 Rp 331,826
1.5 - Pekerjaan Granit (Dtravertine noce GT1262001R) 9.24 M2 Rp 364,550.08 Rp 3,368,443
NO. URAIAN VOLUME SATUAN HARSAT JUMLAH
1. PEKERJAAN KERAMIK
1.1 Keramik polish 60 x 60 Roman 92.55 M² Rp 364,550.08 Rp 33,739,110
1.2 Keramik Unpolish 60 x 60 Roman 51.40 M² Rp 364,550.08 Rp 18,737,874
E PEKERJAAN PLAFOND
Plafond area dalam dan luar
1.1 Pekerjaan Hollow Galvanis 40 x 40 mm 143.95 M² Rp 164,642.50 Rp 23,700,288
1.2 Pekerjaan Plafond Gypsum Board 9 mm 98.85 M² Rp 78,072.50 Rp 7,717,467
1.3 Pekerjaan plafond WR Gypsum board 9mm 45.10 M² Rp 78,072.50 Rp 3,521,070
1.4 Pekerjaan Cove Lampu 26.67 M Rp 20,000.00 Rp 533,400
NO. URAIAN VOLUME SATUAN HARSAT JUMLAH
F PEKERJAAN PENGECETAN
1 Pekerjaan Pengecetan Lantai 1
1.1 Cat Dinding Luar Setara Dulux White On White WeatherShield 228.97 M² Rp 37,153.05 Rp 8,506,934
1.2 Cat Dinding Dalam Setara Dulux White On White For Interior 380.40 M² Rp 33,193.05 Rp 12,626,636
G. Meja Dapur
1 Area Dapur Bersih
1.0 Bekisting (termasuk stop cor) 3.28 M² Rp 188,746.25 Rp 619,465
2.0 Besi
- Tulangan /utama ø 8 - 150 ( Dua Lapis) 6.80 Kg Rp 16,251.95 Rp 110,544
3.0 Beton Site Mix K250 0.33 m3 Rp 1,454,667.50 Rp 477,422
4.0 Granit Infinity Staturio Grey 60 x 60 3.28 m2 Rp 364,550.08 Rp 1,196,453
5.0 K. dinding Subway tile 10 x 20 1.73 m2 Rp 364,550.08 Rp 630,672
3 Laundry
2.0 Bekisting (termasuk stop cor) 0.71 M² Rp 188,746.25 Rp 133,632
2.1 Besi
- Tulangan Sengkang ø 8 - 150 ( Dua Lapis) 1.99 Kg Rp 16,251.95 Rp 32,354
2.2 Beton Site Mix K250 0.07 m3 Rp 1,454,667.50 Rp 102,990
2.3 Granit Infinity Staturio Grey 60 x 60 0.71 m2 Rp 364,550.08 Rp 258,101
G PEKERJAAN SANITARI
1 Closet Duduk Winplus ccst ex American Standard 3.00 Buah Rp 3,000,000.00 Rp 9,000,000
2 Jet Washer American Standard tp 404 3.00 Buah Rp 300,000.00 Rp 900,000
3 Wastafel American Standard Type CLC031I0-XXACPLW00 3.00 Buah Rp 1,000,000.00 Rp 3,000,000
4 Kaca Cermin Watafel Uk.50x70cm 3.00 Buah Rp 300,000.00 Rp 900,000
5 Hand Shower A6014-HS ex.American Standard dengan Shower Valve 3.00 Buah Rp 300,000.00 Rp 900,000
6 Kran Air Tembok AMM A-7300C Wall 3.00 Buah Rp 300,000.00 Rp 900,000
7 Tisu Holder American Standard 3.00 Buah Rp 300,000.00 Rp 900,000
8 Kran Cuci Piring American Standard Ffast 607 2.00 Buah Rp 300,000.00 Rp 600,000
9 Royal Bak Cuci Piring / Kitchen Sink / Sink Tabel Stainless 2.00 Buah Rp 2,000,000.00 Rp 4,000,000
10 Floor Drain f074a267 American Standard 3.00 Buah Rp 300,000.00 Rp 900,000
B. PEKRJAAN ELEKTRIKAL
IV PEKERJAAN HARDSCAPE
A TANAMAN
B. PEKERJAAN PAGAR
1.0 Struktur
1.1 Bekisting 2.00 M2 Rp 229,680.00 Rp 459,360
1.2 Besi
- Tulangan Utama ø 12 247.22 Kg Rp 16,251.95 Rp 4,017,794
1.3 Beton Site Mix K250 0.900 M3 Rp 1,454,667.50 Rp 1,309,201
1.4 Cerucuk 6.00 bh Rp 75,000.00 Rp 450,000
1.5 Galian 2.10 M3 Rp 94,875.00 Rp 199,238
1.6 Urugan 1.20 M3 Rp 216,150.00 Rp 259,380
2.0 Arsitektur
2.1 Dinding Pagar samping
2.2 Pasangan bata merah 204.21 M2 Rp 156,755.50 Rp 32,011,041
2.3 Plester 419.62 M2 Rp 74,801.10 Rp 31,388,038
2.4 Acian 419.62 M2 Rp 46,090.00 Rp 19,340,286
2.5 Kamprot Alus 419.62 M2 Rp 60,662.80 Rp 25,455,324
2.6 Cat Dinding Luar Setara Dulux Woodsmoke WeatherShield 419.62 M2 Rp 37,153.05 Rp 15,590,163
2.7 Roster uk 20 x 20 cm 264.00 bh Rp 50,000.00 Rp 13,200,000
2.8 rangka canopy; hollow besi 40 x 40 mm (termasuk cat) 14.92 M2 Rp 267,374.80 Rp 3,989,232
2.9 tiang canopy; hollow besi 40 x 60 mm (termasuk cat) 27.50 m' Rp 150,000.00 Rp 4,125,000
3.0 atap canopy kaca laminated 5 mm 14.92 M2 Rp 500,000.00 Rp 7,460,000
3.1 Pot tanaman 3.00 bh Rp 200,000.00 Rp 600,000
NO. URAIAN VOLUME SATUAN HARSAT JUMLAH
JUMLAH Rp 947,943,313.63
REKAPITULASI
ESTIMATE ENGINEERING ( EE )
KEGIATAN : PERENCANAAN GUDANG PERALATAN KANTOR PENCARIAN DAN PERTOLONGAN KOTA TARAKAN
LOKASI : BASARNAS KOTA TARAKAN
TAHUN ANGGARAN : 2022
JUMLAH HARGA
Err:509
Err:509
Err:509
52,191,511.83
Err:509
Err:509
148,005,738.66
2,309,402.37
Err:509
18,413,417.51
Err:509
Err:509
54,350,919.56
Err:509
13,132,258.78
Err:509
117,135,359.67
7,184,427.16
Err:509
12,029,095.12
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Dibuat Oleh :
CV. INDOTEC NUSANTARA
PAKET KEGIATAN : PERENCANAAN GUDANG PERALATAN KANTOR PENCARIAN DAN PERTOLONGAN KOTA TARAKAN
LOKASI : BASARNAS KOTA TARAKAN
TAHUN ANGGARAN : 2022
A Tenaga
1 Pekerja L.01 OH 0.125 110,000.00 13,750.00
2 Mandor L.04 OH 0.030 150,000.00 4,500.00
Jumlah Tenaga Kerja 18,250.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
1 Alat bantu 1.000 10,000.00 10,000.00
Jumlah Harga Peralatan 10,000.00
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 28,250.00
E Overhead + Profit ( Contoh 10% ) 10% x D 2,825.00
F Harga Satuan Pekerjaan ( D + E ) 31,075.00
A Tenaga
1 Pekerja L.01 OH 1.000 110,000.00 110,000.00
2 Tukang Kayu L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 135,000.00 3,375.00
4 Mandor L.04 OH 0.100 150,000.00 15,000.00
Jumlah Tenaga Kerja 159,625.00
B Bahan
1 Campuran Beton Ready Mixed M3 1.020 1,335,000.00 1,361,700.00
Jumlah Harga Bahan 1,361,700.00
C Peralatan
A Tenaga
1 Pekerja L.01 OH 1.000 110,000.00 110,000.00
2 Tukang Kayu L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 135,000.00 3,375.00
4 Mandor L.04 OH 0.100 150,000.00 15,000.00
Jumlah Tenaga Kerja 159,625.00
B Bahan
1 Campuran Beton Ready Mixed M3 1.020 1,140,000.00 1,162,800.00
Jumlah Harga Bahan 1,162,800.00
C Peralatan
A Tenaga
1 Pekerja L.01 OH 1.000 110,000.00 110,000.00
2 Tukang Kayu L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 135,000.00 3,375.00
4 Mandor L.04 OH 0.100 150,000.00 15,000.00
Jumlah Tenaga Kerja 159,625.00
B Bahan
1 Campuran Beton Ready Mixed M3 1.020 925,000.00 943,500.00
Jumlah Harga Bahan 943,500.00
C Peralatan
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala Tukang L.03 OH 0.010 135,000.00 1,350.00
4 Mandor L.04 OH 0.001 150,000.00 150.00
Jumlah Tenaga Kerja 36,000.00
B Bahan
1 Genteng metal Buah 1.300 70,000.00 91,000.00
2 Paku biasa 1/2"-1" kg 0.200 22,300.00 4,460.00
Jumlah Harga Bahan 95,460.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 131,460.00
E Overhead + Profit ( Contoh 15% ) 10% x D 13,146.00
F Harga Satuan Pekerjaan ( D + E ) 144,606.00
A.4.5.2.37 Pemasangan 1 m' nok genteng metal
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 110,000.00 27,500.00
2 Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
3 Kepala Tukang L.03 OH 0.015 135,000.00 2,025.00
4 Mandor L.04 OH 0.013 150,000.00 1,950.00
Jumlah Tenaga Kerja 50,225.00
B Bahan
1 Nok genteng metal Buah 1.100 50,000.00 55,000.00
2 Paku biasa 1/2"-1" kg 0.050 22,300.00 1,115.00
Jumlah Harga Bahan 56,115.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 106,340.00
E Overhead + Profit ( Contoh 15% ) 10% x D 10,634.00
F Harga Satuan Pekerjaan ( D + E ) 116,974.00
A.4.6.1.21.Pemasangan 1 m¹ Caslsiplank
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 110,000.00 11,000.00
2 Tukang Kayu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala Tukang L.03 OH 0.020 135,000.00 2,700.00
4 Mandor L.04 OH 0.005 150,000.00 750.00
Jumlah Tenaga Kerja 39,450.00
B Bahan
1 Kalsiplank M' 1.200 20,000.00 24,000.00
2 Paku 5 cm dan 7 cm Kg 0.100 22,300.00 2,230.00
Jumlah Harga Bahan 26,230.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 65,680.00
E Overhead + Profit ( Contoh 15% ) 10% x D 6,568.00
F Harga Satuan Pekerjaan ( D + E ) 72,248.00
A Tenaga
1 Pekerja L.01 OH 0.043 110,000.00 4,730.00
2 Tukang Kayu L.02 OH 0.043 125,000.00 5,375.00
3 Kepala Tukang L.03 OH 0.0043 135,000.00 580.50
4 Mandor L.04 OH 0.002 150,000.00 315.00
Jumlah Tenaga Kerja 11,000.50
B Bahan
1 Profil alluminium M 1.100 180,000.00 198,000.00
2 Skrup fixer buah 2.000 400.00 800.00
3 Sealant Tube 0.060 30,000.00 1,800.00
Jumlah Harga Bahan 200,600.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 211,600.50
E Overhead + Profit ( Contoh 15% ) 10% x D 21,160.05
F Harga Satuan Pekerjaan ( D + E ) 232,760.55
A.4.6.2.2.Pemasangan 1 buah kunci tanam biasa
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 110,000.00 1,100.00
2 Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
3 Kepala Tukang L.03 OH 0.0500 135,000.00 6,750.00
4 Mandor L.04 OH 0.005 150,000.00 750.00
Jumlah Tenaga Kerja 63,600.00
B Bahan
1 Kunci Tanam Biasa Buah 1.000 171,000.00 171,000.00
Jumlah Harga Bahan 171,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 234,600.00
E Overhead + Profit ( Contoh 10% ) 10% x D 23,460.00
F Harga Satuan Pekerjaan ( D + E ) 258,060.00
A Tenaga
1 Pekerja L.01 OH 0.010 110,000.00 1,100.00
2 Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala Tukang L.03 OH 0.0100 135,000.00 1,350.00
4 Mandor L.04 OH 0.0005 150,000.00 75.00
Jumlah Tenaga Kerja 15,025.00
B Bahan
1 Engsel Casement Jendela Aluminium Pasng 1.000 30,000.00 30,000.00
Jumlah Harga Bahan 30,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 45,025.00
E Overhead + Profit ( Contoh 10% ) 10% x D 4,502.50
F Harga Satuan Pekerjaan ( D + E ) 49,527.50
A.4.6.2.17. Pemasangan 1 m² kaca tebal 5 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 110,000.00 1,650.00
2 Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
3 Kepala Tukang L.03 OH 0.0015 135,000.00 202.50
4 Mandor L.04 OH 0.0008 150,000.00 120.00
Jumlah Tenaga Kerja 20,722.50
B Bahan
1 Kaca Tebal 5 mm m² 1.100 179,000.00 196,900.00
2 Sealant Kg 0.050 30,000.00 1,500.00
Jumlah Harga Bahan 198,400.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 219,122.50
E Overhead + Profit ( Contoh 10% ) 10% x D 21,912.25
F Harga Satuan Pekerjaan ( D + E ) 241,034.75
A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 110,000.00 2,200.00
2 Tukang Cat L.02 OH 0.063 125,000.00 7,875.00
3 Kepala Tukang L.03 OH 0.0063 135,000.00 850.50
4 Mandor L.04 OH 0.003 150,000.00 450.00
Jumlah Tenaga Kerja 11,375.50
B Bahan
1 Plamir Kg 0.100 44,000.00 4,400.00
2 Cat Dasar Kg 0.100 40,000.00 4,000.00
3 Cat Penutup Kg 0.260 40,000.00 10,400.00
Jumlah Harga Bahan 18,800.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 30,175.50
E Overhead + Profit ( Contoh 10% ) 10% x D 3,017.55
F Harga Satuan Pekerjaan ( D + E ) 33,193.05
A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 110,000.00 2,200.00
2 Tukang Cat L.02 OH 0.063 125,000.00 7,875.00
3 Kepala Tukang L.03 OH 0.0063 135,000.00 850.50
4 Mandor L.04 OH 0.003 150,000.00 450.00
Jumlah Tenaga Kerja 11,375.50
B Bahan
1 Plamir Kg 0.100 44,000.00 4,400.00
2 Cat Dasar Kg 0.100 50,000.00 5,000.00
3 Cat Penutup Kg 0.260 50,000.00 13,000.00
Jumlah Harga Bahan 22,400.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 33,775.50
E Overhead + Profit ( Contoh 10% ) 10% x D 3,377.55
F Harga Satuan Pekerjaan ( D + E ) 37,153.05
A.4.7.1.5. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Cat L.02 OH 0.105 125,000.00 13,125.00
3 Kepala Tukang L.03 OH 0.004 135,000.00 540.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
Jumlah Tenaga Kerja 21,815.00
B Bahan
1 Cat Menie Kg 0.200 31,000.00 6,200.00
2 Plamir Kg 0.150 44,000.00 6,600.00
3 Cat Dasar Kg 0.170 60,000.00 10,200.00
4 Cat Penutup Kg 0.350 60,000.00 21,000.00
5 Kuas Buah 0.010 20,000.00 200.00
6 Pengencer Kg 0.030 18,000.00 540.00
7 Ampelas Lembar 0.200 5,000.00 1,000.00
Jumlah Harga Bahan 45,740.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 67,555.00
E Overhead + Profit ( Contoh 10% ) 10% x D 6,755.50
F Harga Satuan Pekerjaan ( D + E ) 74,310.50
A Tenaga
1 Pekerja L.01 OH 0.081 110,000.00 8,910.00
2 Tukang Batu L.02 OH 0.135 125,000.00 16,875.00
3 Kepala Tukang L.03 OH 0.0135 135,000.00 1,822.50
4 Mandor L.04 OH 0.004 150,000.00 600.00
Jumlah Tenaga Kerja 28,207.50
B Bahan
1 Pipa PVC Ø4" m¹ 1.200 77,500.00 93,000.00
2 Perlengkapan % 35.000 27,125.00 27,125.00
Jumlah Harga Bahan 120,125.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 148,332.50
E Overhead + Profit ( Contoh 15% ) 10% x D 14,833.25
F Harga Satuan Pekerjaan ( D + E ) 163,165.75
A Tenaga
1 Pekerja L.01 OH 0.081 110,000.00 8,910.00
2 Tukang Batu L.02 OH 0.135 125,000.00 16,875.00
3 Kepala Tukang L.03 OH 0.0135 135,000.00 1,822.50
4 Mandor L.04 OH 0.004 150,000.00 600.00
Jumlah Tenaga Kerja 28,207.50
B Bahan
1 Pipa PVC Ø3" m¹ 1.200 47,500.00 57,000.00
2 Perlengkapan % 35.000 16,625.00 16,625.00
Jumlah Harga Bahan 73,625.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 101,832.50
E Overhead + Profit ( Contoh 15% ) 10% x D 10,183.25
F Harga Satuan Pekerjaan ( D + E ) 112,015.75
A Tenaga
1 Pekerja L.01 OH 0.081 110,000.00 8,910.00
2 Tukang Batu L.02 OH 0.135 125,000.00 16,875.00
3 Kepala Tukang L.03 OH 0.0135 135,000.00 1,822.50
4 Mandor L.04 OH 0.004 150,000.00 600.00
Jumlah Tenaga Kerja 28,207.50
B Bahan
1 Pipa PVC Ø2" m¹ 1.200 30,000.00 36,000.00
2 Perlengkapan % 35.000 10,500.00 10,500.00
Jumlah Harga Bahan 46,500.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 74,707.50
E Overhead + Profit ( Contoh 15% ) 10% x D 7,470.75
F Harga Satuan Pekerjaan ( D + E ) 82,178.25
A Tenaga
1 Pekerja L.01 OH 0.081 110,000.00 8,910.00
2 Tukang Batu L.02 OH 0.135 125,000.00 16,875.00
3 Kepala Tukang L.03 OH 0.0135 135,000.00 1,822.50
4 Mandor L.04 OH 0.004 150,000.00 600.00
Jumlah Tenaga Kerja 28,207.50
B Bahan
1 Pipa PVC Ø1/2" m¹ 1.200 13,750.00 16,500.00
2 Perlengkapan % 35.000 4,812.50 4,812.50
Jumlah Harga Bahan 21,312.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 49,520.00
E Overhead + Profit ( Contoh 15% ) 10% x D 4,952.00
F Harga Satuan Pekerjaan ( D + E ) 54,472.00
A.5.1.1.31. Pemasangan 1 m¹ PVC Ø3/4"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 110,000.00 8,910.00
2 Tukang Batu L.02 OH 0.135 125,000.00 16,875.00
3 Kepala Tukang L.03 OH 0.0135 135,000.00 1,822.50
4 Mandor L.04 OH 0.004 150,000.00 600.00
Jumlah Tenaga Kerja 28,207.50
B Bahan
1 Pipa PVC Ø1/2" m¹ 1.200 10,000.00 12,000.00
2 Perlengkapan % 35.000 3,500.00 3,500.00
Jumlah Harga Bahan 15,500.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 43,707.50
E Overhead + Profit ( Contoh 15% ) 10% x D 4,370.75
F Harga Satuan Pekerjaan ( D + E ) 48,078.25
JENIS
No. BAHAN, UPAH, SEWA ALAT DAN SATUAN HARGA SATUAN KETERANGAN
PERALATAN LABORATORIUM ( Tidak termasuk Ppn 10 %)
(1) (2) (3) (4) (5)
I UPAH
1 Pekerja Hari 110,000 15,714.29
2 Tukang Hari 125,000 17,857.14
3 Kepala Tukang Hari 135,000 19,285.71
4 Mandor Hari 150,000 21,428.57
II BAHAN
1 Pasir Pasang M3 135,000 96
2 Pasir Urug M3 135,000
3 Tanah Urug M3 70,000
4 Agregat Kasar/ Batu Pecah M3 500,000 370
5 Semen (50kg) Zak 70,000 1,400
6 Semen Putih (50kg) / Zak 163,000 4,075
7 Besi beton polos Kg 12,000
8 Besi beton ulir Kg 14,000
9 Kawat Beton / Kg 25,000
10 Bata Merah / Bh 1,300
11 Air Bersih Ltr 64
12 Plywood 9 mm / Lbr 150,000
13 Plywood 18 mm / Lbr 420,000
14 Gypsumboard 120 x 240 x 9 mm / Lbr 75,000
15 List Plafond gypsum M' 30,000
16 Tepung Gypsum /Kg 6,600
17 Rangka Metal Hollow 40.40.2 mm M' 12,000
18 Lampu Downlight LED, 15 W / Bh 100,000
19 Lampu LED Strip Waterproof AMD 2835; natural white M' 50,000
20 Lampu Taman LED 8w Natural White / Bh 295,000
21 Lampu Spot light 8w Warm White / Bh 295,000
22 Lampu Spot Light wall warm white / Bh 295,000
23 Genteng Metal Surya Colour /Lbr 70,000
24 Bubungan Surya Colour /Lbr 50,000
25 Calsiplank /Lbr 60,000 20,000
26 Paku Biasa / Kg 22,300
27 Paku Payung / Kg 31,000
28 Paku Skrup / Kg 25,000 400
29 Tegel ( 60/60 ) / M2 250,000 83,333
30 Meni besi / Kg 28,000
31 Meni Kayu / Kg 31,000
32 Dempul / plamir / Kg 44,000
33 Kuas Bh 20,000
34 Amplas / Lbr 5,000
JENIS
No. BAHAN, UPAH, SEWA ALAT DAN SATUAN HARGA SATUAN KETERANGAN
PERALATAN LABORATORIUM ( Tidak termasuk Ppn 10 %)
(1) (2) (3) (4) (5)
35 Cat Kilap untuk kayu / Kg 60,000
36 Cat Tembok Ex .Dulux wheater shield/Setara / Kg 50,000
37 Cat Tembok In. Dulux /Setara / Kg 40,000
38 Minyak Cat 1 Kg / Kg 18,000
39 Minyak Begesting Ltr 10,000
40 Dolken kayu Ø 8 -10 / 300 cm / Btg 31,300
41 Kayu Meranti / M3 2,600,000
42 Kayu Bengkirai /Kruing / M3 3,500,000
43 Kayu Ulin / M3 7,500,000
44 Kaca Polos T. 5 mm / M2 179,000
45 Kunci Pintu Besar Standart 1 x slag / Bh 171,000
46 Engsel Pintu Standart 4' / Psg 35,000
47 Engsel Casement Pintu / Psg 30,000
48 Rambuncis/Handle Jendela / Bh 25,000
49 Grendel / Bh 20,000
50 kait Angin / Bh 11,300
51 Door closer / Bh 355,000 DECKSON
52 Kusen Allumunium SF 4" / M1 180,000
53 Skrup Fixer Bh 400
54 Sealant Tube 30,000
55 Kusen Pintu Uk. Standart 1 Daun Bh 550,000
56 Daun Pintu Pnil 1 Daun Bh 1,750,000
57 Daun Pintu Pnil 2 Daun Bh 3,500,000
58 Roster (20x20) Bh 50,000
59 Titik Lampu + Instalasi / Titik 300,000
60 Stop kontak + Instalasi / Titik 300,000
61 Saklar Tunggal / Bh 30,000 Panasonic/setara
62 Saklar Ganda / Bh 35,000 Panasonic/setara
63 Canal C-75 tebal 0,65 mm / btg 80,500 18,000
64 Canal C-75 tebal 0,75 mm / btg 92,000 21,500
65 Reng Baja Ringan / btg 45,600 9,500
66 Dynabolt Buah 24,000
67 Pipa PVC ( Diameter 3/4" ) / Btg 40,000 10,000
68 Pipa PVC ( Diameter 1" ) / Btg 55,000 13,750
69 Pipa PVC ( Diameter 2" D ) / Btg 120,000 30,000
70 Pipa PVC ( Diameter 3 ) / Btg 190,000 47,500
71 Pipa PVC ( Diameter 4" D ) / Btg 310,000 77,500
72 Elbow 1/2 " - 4 " / Bh 30,000
73 Floor Drain f074a267 American Standard / Bh 500,000
74 Kran Cuci Piring American Standard Ffast 607 / Bh 800,000
75 Royal Bak Cuci Piring / Kitchen Sink / Sink Tabel Stainless / Bh 1,800,000
76 Waterprofing / 5 Kg 200,000 40,000
77 Beton Ready mix ( K-100 ) / M3 925,000.00
78 Beton Ready mix ( K-250 ) / M3 1,140,000.00
79 Beton Ready mix ( K-300 ) / M3 1,335,000.00
79 Pompa dan conveyor beton / M3 700,000.00
80 Rumput mini Gajah / M2 90,000.00
81 Alat Bantu / Ls 10,000.00
KETERANGAN
(5)
Per Jam
Per Jam
Per Jam
Per Jam
Kg
Kg
Per Kg
Per Kg
/M
/bh
KETERANGAN
(5)
Panasonic/setara
Panasonic/setara
/M
/M
/M
/M
/M
/M
/M
/M
/ Bh
RENCANA ANGGARAN BIAYA (RAB) RUMAH TYPE 1
PROYEK : PEMBANGUNAN RUMAH DINAS BRI KARANG TINGGAL
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
I. PEKERJAAN STRUKTUR
A. PEKERJAAN PERSIAPAN
1 Listrik dan air kerja 1.00 Ls -
2 Gudang Penyimpanan Material (Gudang Sederhana) 12.00 M² -
3 Pekerjaan Pembersihan Lokasi (Manual) 43.29 M² -
4 Pekerjaan Bowplank 46.90 M¹ -
-
B PEKERJAAN PONDASI
1 Pile Cap Type FP1 Uk. (1m x 1m) (3 Unit)
1.1 Galian Tanah 7.13 M³ -
1.2 Urugan Pasir Tebal 5 cm 0.17 M³ -
1.3 Lantai Kerja Tebal 5 cm Site Mix K100 0.66 M³ -
1.4 Bekisting Batako 2.40 M² -
Beton Pondasi Pedestal Ready Mix K300 + Tulangan Baja Tulangan Deform/Ulir, BJTD,
1.5 1.05 M³ -
fy 400 Mpa
1.6 Urugan Tanah Kembali Dipadatkan 4.63 M³ -
2 Pile Cap Type FP2 Uk. (0,8m x 0,8m) (6 Unit)
2.1 Galian Tanah 9.90 M³ -
2.2 Urugan Pasir Tebal 5 cm 0.19 M³ -
2.3 Lantai Kerja Tebal 5 cm Site Mix K100 0.19 M³ -
2.4 Bekisting Batako 3.84 M² -
2.5 Beton Ready Mix K300 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 1.00 M³ -
2.6 Urugan Tanah Kembali Dipadatkan 6.44 M³ -
3 Pekerjaan Pondasi Batu Belah Camp. 1 PC : 4 PP
3.1 Pekerjaan Galian Tanah Manual 19.74 M³ -
3.2 Lantai Kerja Tebal 5 cm Site Mix K100 1.65 M³ -
3.3 Pekerjaan Batu Aanstamping 5.98 M³ -
3.4 Pekerjaan Pasangan Batu Belah (Camp. 1 PC : 4 PP) 12.91 M³ -
-
C PEKERJAAN SLOOF
1 Sloof 20/30
1.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.82 M³ -
1.2 Bekisting Batako 28.20 M² -
-
D PEKERJAAN KOLOM
1 Pek. Kolom Lantai 1
Kolom Struktur (K1) Uk. (15x50 cm) Tinggi 3m, 9 Unit
1.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.03 M³ -
1.2 Bekisting Kolom Multiplex 12 mm + Rangka Kaso 35.10 M² -
2 Pek. Kolom Lantai 2
Kolom Struktur (K1) Uk. (15x50 cm) Tinggi 3m, 9 Unit
2.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.03 M³ -
2.2 Bekisting Kolom Multiplex 12 mm + Rangka Kaso 35.10 M² -
-
E PEKERJAAN BALOK
1 Pek. Balok Lantai 2
Balok B1 Uk. 20x30cm Panjang 48m
1.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.88 M³ -
1.2 Bekisting Balok Multiplex 12 mm + Rangka Kaso 38.40 M² -
Balok B2 Uk. 15x20cm Panjang 48m
1.3 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.61 M³ -
1.4 Bekisting Balok Multiplex 12 mm + Rangka Kaso 11.11 M² -
Balok B3 Uk. 15x40cm Panjang 7m
1.5 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.42 M³ -
1.6 Bekisting Balok Multiplex 12 mm + Rangka Kaso 6.65 M² -
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
2 Balok LT Atap
Balok B1 Uk. 20x30cm Panjang 48m
2.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 1.68 M³ -
2.2 Bekisting Balok Multiplex 12 mm + Rangka Kaso 22.40 M² -
Balok B2 Uk. 15x20cm Panjang 48m
2.3 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.54 M³ -
2.4 Bekisting Balok Multiplex 12 mm + Rangka Kaso 9.90 M² -
-
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
F PEKERJAAN PLAT LANTAI
Plat Lantai 2 Tebal 12 cm Luas 37,6 m2
1 Beton Ready Mix K250 + Wiremesh 2 layer U 50 4.51 M³ -
2 Bekisting Bondeck Metalsheet JAP < = 0,8 m 37.60 M² -
Plat Lantai Atap + Canopy Beton Tebal 12 cm
3 Beton Ready Mix K250 + Wiremesh 2 layer U 50 6.08 M³ -
4 Bekisting Bondeck Metalsheet JAP < = 0,8 m 50.70 M² -
5 Waterproofing Lantai Plat Atap & Canopy Beton 44.00 M² -
Plat Lantai Meja Dapur Tebal 10 cm
6 Beton Site Mix K 175 0.20 M³ -
7 Pekerjaan Bekisting Multiplex 12 mm Rangka Kaso 2.00 M² -
-
G PEKERJAAN TANGGA BETON
1 Pekerjaan Pondasi Tangga
1.1 Pekerjaan Galian Pondasi Tangga 0.50 M³ -
1.2 Pekerjaan Urugan Pasir 5 cm 0.05 M³ -
1.3 Lantai Kerja Tebal 5 cm Site Mix K100 0.05 M³ -
1.4 Pekerjaan Bekisting Batako 0.80 M² -
1.5 Pekerjaan Beton Pondasi Tangga 0.17 M³ -
-
B PEKERJAAN KUSEN
1 Pintu Utama P1
1.1 Kusen Kayu Kamper Oven Samarinda 6.10 M¹ -
1.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. Veener Natural 1.00 Bh -
1.3 Aksesoris Pintu ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
2 Pintu Geser P2
2.1 Kusen Kayu Kamper Oven Samarinda 5.35 M¹ -
2.2 Daun Pintu Kaca 5 mm Rangka kayu Kamper Fin. Veener Natural 1.00 Buah -
2.3 Aksesoris Pintu Dorong ( Rel Pintu, Kunci, & Handle ) 1.00 Unit -
3 Pintu P3
3.1 Kusen Kayu Kamper Oven Samarinda 15.30 M¹ -
3.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. Veener Natural 3.00 Buah -
3.3 Aksesoris Pintu (Rel Pintu, Engsel, Kunci, & Handle ) 3.00 Unit -
4 Pintu P4
4.1 Kusen Kayu Kamper Oven Samarinda 10.20 M¹ -
4.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. Veener Natural 2.00 Buah -
4.3 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 2.00 Unit -
5 Pintu P5
5.1 Kusen Kayu Kamper Oven Samarinda 5.00 M¹ -
5.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. Veener Natural 1.00 Buah -
5.3 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
6 Pintu P5
6.1 Kusen Kayu Kamper Oven Samarinda 5.00 M¹ -
6.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. Veener Natural 1.00 Buah -
6.3 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
7 Jendela J1
7.1 Kusen Besi Hollow 2x50x50 Finishing Coating Hitam 11.20 M¹ -
7.2 Daun Jendela Expanding Metal Sheet + Kaca 5mm Fin. Coating Hitam 6.00 Buah -
7.3 Aksesoris Jendela ( Engsel, Kunci ) 6.00 Unit -
8 Jendela J2
8.1 Kusen Kayu Kamper Oven Samarinda 5.70 M¹ -
8.2 Daun Jendela Kayu Kamper Oven solid Fin. Veener Natural & Kaca 5mm 1.00 Buah -
8.3 Aksesoris Jendela ( Engsel, Kunci ) 1.00 Unit -
9 Jendela J3
9.1 Kusen Kayu Kamper Oven Samarinda 5.70 M¹ -
9.2 Daun Jendela Kayu Kamper Oven solid Fin. Veener Natural & Kaca 5mm 1.00 Buah -
9.3 Aksesoris Jendela ( Engsel, Kunci ) 1.00 Unit -
10 Jendela J4
9.1 Kusen Kayu Kamper Oven Samarinda 12.00 M¹ -
9.2 Daun Jendela Kayu Kamper Oven solid Fin. Veener Natural & Kaca 5mm 2.00 Buah -
9.3 Aksesoris Jendela ( Engsel, Kunci ) 2.00 Unit -
11 Jendela J5
9.1 Kusen Kayu Kamper Oven Samarinda 7.00 M¹ -
9.2 Daun Jendela Kayu Kamper Oven solid Fin. Veener Natural & Kaca 5mm 1.00 Buah -
9.3 Aksesoris Jendela ( Engsel, Kunci ) 1.00 Unit -
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
12 Jendela J6
12.1 Kaca tempered 10 mm 0.60 M² -
13 Jendela J7
13.1 Kaca tempered 10 mm dengan cove untuk rollerblind pada plafon 4.80 M² -
-
C PEKERJAAN ATAP
1 Atap Manhole
1.1 Pekerjaan Rangka Hollow 1.00 M² -
1.2 Pekerjaan Penutup Atap Polycarbonat 1.00 M² -
-
D PEKERJAAN LANTAI
1 Keramik Lantai 1
1.1 Urugan Tanah Padat Stemper Rata-Rata Ketinggian 30 cm 12.60 M³ -
1.2 Pasir Urug Tebal 10 cm Padat Stemper 4.20 M³ -
1.3 Homogenius Tile 60x60 Granito -Salsa Polished 29.00 M² -
1.4 Homogenius Tile 60x60 Granito-Salsa Unpolished 11.00 M² -
1.5 Homogenius Tile 60x60 Granito-Salsa Unpolished Tangga 6.00 M² -
1.6 Dinding Toilet Homogenius Tle 60x60 Granito -Salsa Polished 10.01 M² -
1.7 Homogenius Tile 10x10 (Meja dapur) 2.00 M² -
1.8 Homogenius Tile 10x10 dinding Meja Dapur 2.00 M² -
1.9 Waterproofing Lantai & Dinding Toilet 18.01 M² -
1.10 Dinding Bata Tempel Ex.Karang Pilang 15.20 M² -
2 Keramik Lantai 2
2.1 Homogenius Tile 60x60 Granito -Salsa Polished 30.50 M² -
2.2 Homogenius Tile 60x60 Granito-Salsa Unpolished 4.00 M² -
2.3 Dinding Toilet Homogenius Tle 60x60 Granito -Salsa Polished 14.52 M² -
2.4 Waterproofing Lantai & Dinding Toilet 18.52 M² -
3 Floor Hardener
3.1 Pekerjaan Floor Hardener 0.66 M³ -
3.2 Pekerjaan Beton Ram K225 Site Mix 0.46 M³ -
3.3 Pekerjaan Rumput Gajah Mini 1.20 M² -
-
E PEKERJAAN PLAFOND
1 Plafond Gypsum Board Rangka Hollow (Lantai 1) 31.00 M² -
2 Plafond Gypsum Board Rangka Hollow (Lantai 2) 36.00 M² -
3 Lis Plafond Alumunium Shadowline 106.30 M¹ -
4 Plafond Calsibord Rangka Hollow (Toilet) 6.00 M² -
-
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
F PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Lantai 1
1.1 Cat Dinding Dalam setara Dulux White on White for Interior 149.06 M² -
1.2 Cat Dinding Luar setara Dulux Wheathershield Woodsmoke for Exterior 65.40 M² -
1.3 Cat Plafond Gypsum/GRC Dulux/setara 33.00 M² -
2 Pekerjaan Pengecatan Lantai 2
2.1 Cat Dinding Dalam setara Dulux White on White for Interior 160.81 M² -
2.2 Cat Dinding Luar setara Dulux Wheathershield Woodsmoke for Exterior 76.20 M² -
2.3 Cat Plafond Gypsum Dulux/setara 40.00 M² -
3 Pekerjaan Pengecatan Lantai Atap
3.1 Cat Dinding Luar setara Dulux Wheathershield Woodsmoke for Exterior 78.00 M² -
3.2 Cat Atap Canopy Beton Dulux White on White for Interior 12.00 M² -
-
G PEKERJAAN SANITARI
-
H PEKERJAAN SEPTIC TANK BIOFIL TYPE BF 08
1 Pekerjaan Rumah Biofil
2.1 Pengadaan dan pemasangan Septic Tank Biofil (Type BF-08) 1.00 Buah -
3 Pekerjaan Sumur Resapan
-
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
I PEKERJAAN LAIN-LAIN
A PEKERJAAN MEKANIKAL
1 Sumur dan Pompa Air
Pondasi Tengah
Pondasi Pinggir
Sika
Lakasi Pintu :
Lokasi Pintu :
Lokasi Pintu :
LT.1 Toilet
Lokasi Pintu :
LT.2 Toilet
Lokasi Jendela:
Lokasi Jendela:
LT.1 R.Makan
Lokasi Jendela:
Lokasi Jendela:
Lokasi Jendela:
Lokasi Jendela:
LT.2 Toilet
Lokasi Jendela:
Twinlite Transparan
Pasir Urug
Dulux Woodsmoke
Dulux Woodsmoke
Dulux Woodsmoke
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
Taco TH1202 FC
Shimizu
Onda
Penguin
Wavin Rucika
Wavin Rucika
Wavin Rucika
Wavin Rucika
Wavin Rucika
Panasonic
Panasonic
Panasonic
RENCANA ANGGARAN BIAYA (RAB) GUESTHOUSE
PROYEK : PEMBANGUNAN RUMAH DINAS BRI KARANG TINGGAL
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
I. PEKERJAAN STRUKTUR
A. PEKERJAAN PERSIAPAN
1 Listrik dan air kerja 1.00 Ls -
2 Gudang Penyimpanan Material (Gudang Sederhana) 9.00 M² -
3 Pekerjaan Pembersihan Lokasi (Manual) 58.30 M² -
4 Pekerjaan Bowplank 49.40 M¹ -
-
B PEKERJAAN PONDASI
1 Pile Cap Type FP Uk. (1m x 1m) (9 Unit)
1.1 Galian Tanah 21.78 M³ -
1.2 Urugan Pasir Tebal 10 cm 0.99 M³ -
1.3 Lantai Kerja Tebal 5 cm Site Mix K 100 0.50 M³ -
1.4 Bekisting Batako 9.00 M² -
1.5 Beton Ready Mix K300 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.25 M³ -
Kolom Pedestal Uk. 40x40x130 cm
1.6 Bekisting Batako 18.72 M² -
1.7 Beton Ready Mix K300 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 1.87 M³ -
1.8 Urugan Tanah Kembali Dipadatkan 14.16 M³ -
-
C PEKERJAAN SLOOF
Beton Sloof Uk. 20/30
1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 2.96 M³ -
2 Bekisting Batako 29.64 M² -
-
D PEKERJAAN KOLOM
1 Pek. Kolom ELV.+ 0,00 (Beton Ready Mix K250 + Besi)
Kolom Struktur (K1) Uk. (25x50 cm)
1.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 3.59 M³ -
1.2 Bekisting Kolom Multiplex 12 mm + Rangka Kaso 43.07 M² -
Kolom Struktur (K2) Uk. (15x40 cm)
1.3 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.57 M³ -
1.4 Bekisting Kolom Multiplex 12 mm + Rangka Kaso 10.53 M² -
Kolom Praktis (KP) Uk. (14x14 cm)
1.5 Beton Struktur K-175 Site Mix + Tulangan Baja Polos, BJTP, fy 240 Mpa 0.44 M³ -
1.6 Bekisting Kolom Multiplex 12 mm + Rangka Kaso 6.25 M² -
-
E PEKERJAAN BALOK
1 Pek. Balok ELV.+3,19 (Beton Ready Mix K250 + Besi)
Balok B1 Uk. 20x45cm
1.1 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 4.45 M³ -
1.2 Bekisting Balok Multiplex 12 mm + Rangka Kaso 54.34 M² -
Balok B2 Uk. 20x40cm
1.3 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.99 M³ -
1.4 Bekisting Balok Multiplex 12 mm + Rangka Kaso 12.35 M² -
Balok B3 Uk. 15x20 cm
1.5 Beton Ready Mix K250 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.33 M³ -
1.6 Bekisting Balok Multiplex 12 mm + Rangka Kaso 4.34 M² -
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
-
F PEKERJAAN PLAT LANTAI BETON READY MIX K300
1 Plat Lantai Tebal 12 cm ELV.+3,04 (Beton Ready Mix K300 )
1.1 Pekerjaan Bekisting Plat Bondeck T. 0,75mm 55.89 M² -
1.2 Plat Lantai Tebal 12 cm Tulangan Wiremesh M-8 (1 Layer) 6.71 M³ -
1.3 Plat Lantai Meja Dapur Tebal 10 cm Besi Tulangan Double 0.16 M³ -
1.4 Bekisting Balok Multiplex 12 mm + Rangka Kaso 1.35 M² -
-
G PEKERJAAN TANGGA BETON
1 Pekerjaan Pondasi Tangga
1.1 Pekerjaan Galian Pondasi Tangga 0.50 M³ -
1.2 Pekerjaan Urugan Pasir 5 cm 0.05 M³ -
1.3 Lantai Kerja Tebal 5 cm Site Mix K 100 0.05 M³ -
1.4 Pekerjaan Bekisting Batako 0.80 M² -
1.5 Beton Ready Mix K300 + Tulangan Baja Tulangan Deform/Ulir, BJTD, fy 400 Mpa 0.17 M³ -
-
B PEKERJAAN KUSEN
1 Pintu Utama P1
1.1 Kusen Kayu Kamper Oven Samarinda 6.10 M¹ -
1.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. HPL 1.00 Bh -
1.3 Aksesoris Pintu ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
2 Pintu P2
2.1 Kusen Kayu Kamper Oven Samarinda 5.00 M¹ -
2.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. HPL 1.00 Buah -
2.3 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
3 Pintu P3
3.1 Kusen Kayu Kamper Oven Samarinda 5.00 M¹ -
3.2 Daun Pintu Multiplex Rangka kayu Kamper Fin. HPL 1.00 Buah -
3.3 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
4 Jendela J1
4.1 Kusen Besi Hollow 2x50x50 Finishing Coating Hitam 11.20 M¹ -
4.2 Daun Jendela Expanding Metal Sheet + Kaca 5mm Fin. Coating Hitam 5.00 Buah -
4.3 Aksesoris Jendela ( Engsel, Kunci ) 5.00 Unit -
5 Jendela PJ1
5.1 Kusen Aluminium Powder Coating 4" 30.52 M¹ -
5.2 Kaca Bening Tebal 6 mm 12.60 M² -
5.3 Daun Pintu Alumunium Powder Coat Putih 1.00 Buah -
5.4 Aksesoris Pintu Dan Jendela ( Engsel, Kunci, Door Closer, & Handle ) 1.00 Unit -
6 Jendela J3
8.1 Kaca tempered 10 mm 6.60 M² -
7 Jendela J4
8.1 Kaca tempered 10 mm 5.27 M² -
8 Jendela J2
8.1 Kaca tempered 10 mm 0.85 M² -
9 Jendela Bouvenlicht
9.1 Kaca Sandblast Tempered 10 mm 4.50 M² -
9.2 Plat Baja Hitam 6 mm (0,3 m x 13 m) finishing Hitam antikarat 191.10 kg -
-
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
C PEKERJAAN ATAP
1.1 Pekerjaan Rangka Atap Baja Ringan 114.10 M² -
1.2 Pekerjaan Penutup Atap Bitumen Tegola Ecoroof 114.10 M² -
1.3 Bubungan Atap Bitumen Aspal 17.50 M¹ -
-
D PEKERJAAN LANTAI
1 Keramik Lantai 1
1.1 Urugan Tanah Padat Stemper Rata-Rata Ketinggian 30 cm 18.30 M³ -
1.2 Pasir Urug Tebal 10 cm Padat Stemper 6.10 M³ -
1.3 Homogenius Tile 60x60 Granito -Salsa Polished 25.00 M² -
1.4 Homogenius Tile 60x60 Granito-Salsa Unpolished 2.00 M² -
1.5 Homogenius Tile 60x60 Granito-Salsa Unpolished Tangga 6.00 M² -
1.6 Dinding Toilet Homogenius Tle 60x60 Granito -Salsa Polished 9.24 M² -
1.7 Homogenius Tile 60x60 (Meja dapur) 2.00 M² -
1.8 Homogenius Tile 60x60 dinding Meja Dapur 2.00 M² -
1.9 Waterproofing Lantai & Dinding Toilet 17.24 M² -
1.10 Dinding Bata Tempel Ex. Karang Pilang 67.60 M² -
2 Keramik Lantai 2
2.1 Homogenius Tile 60x60 Granito -Salsa Polished 43.00 M² -
2.2 Homogenius Tile 60x60 Granito-Salsa Unpolished 7.00 M² -
2.3 Dinding Toilet Homogenius Tle 60x60 Granito -Salsa Polished 15.50 M² -
2.4 Waterproofing Lantai & Dinding Toilet 22.50 M² -
2.5 Dinding Bata Tempel Ex.Karangpilang 30.00 M² -
3 Floor Hardener
3.1 Pekerjaan Beton Ram K225 Site Mix 0.46 M³ -
3.2 Pekerjaan Rumput Gajah Mini 1.20 M² -
-
E PEKERJAAN PLAFOND
1 Plafond Gypsum Board Rangka Hollow (Lantai 1) 51.00 M² -
2 Plafond Gypsum Board Rangka Hollow (Lantai 2) 51.40 M² -
3 Lis Plafond Lis Profil Alumunium Shadowline 106.30 M¹ -
4 Plafond Calsibord Rangka Hollow (Toilet) 8.00 M² -
-
F PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Lantai 1
1.1 Cat Dinding Dalam setara Dulux White on White for Interior 99.51 M² -
1.2 Cat Dinding Luar setara Dulux Wheathershield Woodsmoke for Exterior 31.91 M² -
1.3 Cat Plafond Gypsum/GRC Dulux/setara 51.00 M² -
2 Pekerjaan Pengecatan Lantai 2
2.1 Cat Dinding Dalam setara Dulux White on White for Interior 150.00 M² -
2.2 Cat Dinding Luar setara Dulux Wheathershield Woodsmoke for Exterior 120.00 M² -
2.3 Cat Plafond Gypsum Dulux/setara 55.40 M² -
-
HARGA
NO URAIAN VOLUME SATUAN JUMLAH
SATUAN
G PEKERJAAN SANITARI
1 Closet Duduk Winplus ccst ex American Standard 2.00 Buah -
2 Jet Washer American Standard tp 404 2.00 Buah -
3 Wastafel ex American standrd Type LA02T3Cxx 2.00 Buah -
4 Kaca cermin wastafel Uk. 50x70cm 2.00 Buah -
5 Hand Shower A6014-HS ex. American standrd sek. 2.00 Buah -
6 Kran air tembok AMM A-7300C Wall 2.00 Buah -
7 Tisu Holder American Standart 2.00 Buah -
8 Kran Cuci Piring American Standard Ffast 607 1.00 Buah -
9 Royal Bak Cuci Piring /Kitchen Sink /Sink Tebal Stainless 1.00 Buah -
10 Floor Drain f074a267 American Standard 3.00 Buah -
-
H PEKERJAAN SEPTIC TANK BIOFIL TYPE BF 08
2.1 Pengadaan dan pemasangan Septic Tank Biofil (Type BF-08) 1.00 Buah -
3 Pekerjaan Sumur Resapan
-
I PEKERJAAN LAIN-LAIN
A PEKERJAAN MEKANIKAL
1 Sumur dan Pompa Air
Lokasi Pintu :
LT.1 Toilet
Lokasi Pintu :
LT.2 Toilet
Lokasi Jendela:
Lokasi Jendela:
Lokasi Jendela:
Kamar Tidur
Lokasi Jendela:
LT.2 Toilet
Lokasi Jendela:
LT.1 Toilet
Bouvenlicht
Kanopi Bouvenlicht
KETERANGAN
Pasir Urug
Dulux Woodsmoke
Dulux Woodsmoke
KETERANGAN
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
American Standard
Taco TH1202 FC
KETERANGAN
Shimizu
Onda
Penguin
Wavin Rucika
Wavin Rucika
Wavin Rucika
Wavin Rucika
Wavin Rucika
Panasonic
Panasonic
Panasonic