REKAPITULASI RAB

JUDUL PROYEK : RUMAH TINGGAL TYPE 36

NO URAIAN PEKERJAN JUMLAH Rp.


I PEKERJAAN PERSIAPAN 31,698,897.12
II PEKERJAAN TANAH 3,820,736.70
III PEKERJAAN PONDASI 16,492,836.73
IV PEKERJAAN KUSEN 4,430,948.50
V PEKERJAAN KUNCI DAN KACA 2,001,492.80
VI PEKERJAAN DINDING, PLESTERAN, DAN ACIAN 27,540,512.64
VII PEKERJAAN BETON 3,245,282.26
VIII PEKERJAAN BESI DAN ALUMUNIUM 5,196,752.80
IX PEKERJAAN RANGKA ATAP 15,346,321.10
X PEKERJAAN PENUTUP ATAP 4,678,783.20
XI PEKERJAAN LANGIT-LANGIT 13,352,781.42
XII PEKERJAAN PENUTUP LANTAI & DINDING 51,701,867.53
XII PEKERJAAN PENGECATAN 8,137,026.70
XIV PEKERJAAN INSTALASI LISTRIK 4,851,528.00
XV PEKERJAAN SANITASI 14,976,113.71

JUMLAH TOTAL 207,471,881.21


DIBULATKAN 207,472,000.00
RENCANA ANGGARAN BIAYA (RAB)
JUDUL PROYEK : RUMAH TINGGAL TYPE 36

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA TOTAL HARGA Rp.

I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm m' 276,760.00 25,295,864.00
Pengukuran dan Pemasangan Bouwplank m2 141,487.50 3,678,675.00
Pembuatan Gudang Semen dan Peralatan m2 581,130.00 1,162,260.00
Membersihkan Lapangan dan Peralatan m2 17,325.00 1,143,450.00
Pembuatan Pagar Steger/Perancah dari Bambu Uk.40x60x20cm Ls 418,648.12 418,648.12
Sub Total 31,698,897.12
II PEKERJAAN TANAH
Menggali Tanah Pondasi m3 95,782.50 2,774,819.03
Pengurugan Kembali di hitung dari 1/3 kali Koefisien Pekerjaan Galian m3 56,925.00 539,421.30
Urugan Pasir m3 321,585.00 506,496.38
Sub Total 3,820,736.70
III PEKERJAAN PONDASI
Pemasangan Pondasi Batu Kali m3 886,435.00 12,027,150.08
Pemasangan Batu Kosong/Aanstamping m3 665,725.50 4,465,686.65
Sub Total 16,492,836.73
IV PEKERJAAN KUSEN
Pekerjaan Pintu m2 300,245.00 2,371,935.50
Pekerjaan Jendela m2 278,245.00 2,059,013.00
Sub Total 4,430,948.50
V PEKERJAAN KUNCI DAN KACA
Pemasangan Engsel Pintu bh 33,948.75 271,590.00
Pemasangan Kunci Pintu bh 238,232.50 952,930.00
Pemasangan Engsel Jendela bh 22,632.50 135,795.00
Pemasangan Grendel Jendela bh 23,732.50 71,197.50
Pemasangan Penyangga Jendela bh 46,123.00 276,738.00
Pemasangan Kaca Jendela m2 137,996.38 293,242.30
Sub Total 2,001,492.80
VI PEKERJAAN DINDING, PLESTERAN, DAN ACIAN
Pekerjaan Dinding 1:2 m2 282,535.00 3,195,470.85
Pekerjaan Dinding 1:5 m2 263,373.00 #VALUE!
Pekerjaan Plesteran Dinding 1:2 m2 75,013.18 #VALUE!
Pekerjaan Plesteran Dinding 1:5 m2 70,802.38 #VALUE!
Pekerjaan Plesteran Tali Air m2 30,865.56 #VALUE!
Pekerjaan Acian m2 39,875.00 #VALUE!
Sub Total 27,540,512.64
VII PEKERJAAN BETON
Pekerjaan Sloof m3 110,424.38 110,424.38
Pemasangan Bekesting Sloof m2 210,221.00 2,522,652.00
Pekerjaan Kolom m3 134,460.76 134,460.76
Pemasangan Bekesting Kolom m2 338,530.50 #VALUE!
Pemasangan Balok Latey m3 110,424.38 110,424.38
Pemasangan Plat Leufel m3 83,561.50 7,771,219.50
Pemasangan Bekestig Plat Leufel m2 331,358.50 14,248,415.50
Sub Total 3,245,282.26
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof Kg 110,424.38 2,749,567.06
Pemasangan Tulangan Kolom Kg 134,460.76 2,447,185.74
Sub Total 5,196,752.80
IX PEKERJAAN RANGKA ATAP
Pekerjaan Kuda-Kuda Baja Ringan m2 277,040.50 7,867,950.20
Pekerjaan Usuk / Reng m2 197,840.50 7,478,370.90
Sub Total 15,346,321.10

X PEKERJAAN PENUTUP ATAP


Pemasangan Genteng m2 24,330.00 919,674.00
Pemasangan Genteng Kerpus m2 132,363.00 3,759,109.20
Sub Total 4,678,783.20
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) m2 256,773.00 5,204,788.71
Pekerjaan Penutup Plafon m2 401,973.00 8,147,992.71
Sub Total 13,352,781.42
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 m2 1,199,258.50 20,795,142.39
Pemasangan Keramik Tekstur Uk.30x30 m2 3,118,978.50 9,138,607.01
Pemasangan Keramik Dinding KM Uk.30x30 m2 2,485,444.50 18,441,998.19
Pemasangan Lis Keramik KM Uk.10x30 m2 180,348.30 2,128,109.94
Pemasangan Batu Alam m2 299,502.50 1,198,010.00
SUB Total 51,701,867.53
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Kusen m2 48,603.50 724,192.15
Pekerjaan Pengecatan Pintu m2 55,863.50 625,671.20
Pekerjaan Pengecatan Jendela m2 55,863.50 4,798,674.65
Pekerjaan Pengecatan Dinding Eksterior m2 24,040.50 423,112.80
Pekerjaan Pengecatan Dinding Interior m2 68,777.50 1,565,375.90
Sub Total 8,137,026.70
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan Lampu bh 431,508.00 4,315,080.00
Pemasangan MCB bh 536,448.00 536,448.00
Sub Total 4,851,528.00
XV PEKERJAAN SANITASI
Pemasangan Pipa Ø1/2 " m' 67,691.03 1,705,813.96
Pemasangan Pipa Ø4" m' 462,173.25 1,848,693.00
Pemasangan Kran bh 108,444.88 650,669.25
Pemasangan Bak Mandi bh 1,415,205.00 1,415,205.00
Pemasangan Floor Drain bh 109,532.50 109,532.50
Pemasangan Closet Duduk bh 2,246,200.00 2,246,200.00
Pemasangan Septictank Ls 7,000,000.00 7,000,000.00
Sub Total 14,976,113.71
HARGA SATUAN PEKERJAAN
JUDUL PROYEK : RUMAH TINGGAL TYPE 21
TEMPAT PROYEK : SEMARANG
KONSULTAN : PT JAYA ABADI
KONTRAKTOR : PT MEGA JAYA

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN

I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm m' 276,760.00
Pengukuran dan Pemasangan Bouwplank m2 141,487.50
Pembuatan Gudang Semen dan Peralatan m2 581,130.00
Membersihkan Lapangan dan Peralatan m2 17,325.00
Pembuatan Pagar Steger/Perancah dari Bambu Uk.40x60x20cm Ls 418,648.12
II PEKERJAAN TANAH
Menggali Tanah Pondasi m3 95,782.50
Pengurugan Kembali di hitung dari 1/3 kali Koefisien Pekerjaan Galian m3 56,925.00
Urugan Pasir m3 321,585.00
III PEKERJAAN PONDASI
Pemasangan Pondasi Batu Kali m3 886,435.00
Pemasangan Batu Kosong/Aanstamping m3 665,725.50
IV PEKERJAAN KUSEN
Pekerjaan Pintu m2 300,245.00
Pekerjaan Jendela m2 278,245.00
V PEKERJAAN KUNCI DAN KACA
Pemasangan Engsel Pintu bh 33,948.75
Pemasangan Kunci Pintu bh 238,232.50
Pemasangan Engsel Jendela bh 22,632.50
Pemasangan Grendel Jendela bh 23,732.50
Pemasangan Penyangga Jendela bh 46,123.00
Pemasangan Kaca Jendela m2 137,996.38
VI PEKERJAAN DINDING, PLESTERAN, DAN ACIAN
Pekerjaan Dinding 1:2 m2 282,535.00
Pekerjaan Dinding 1:5 m2 263,373.00
Pekerjaan Plesteran Dinding 1:2 m2 75,013.18
Pekerjaan Plesteran Dinding 1:5 m2 70,802.38
Pekerjaan Plesteran Tali Air m2 30,865.56
Pekerjaan Acian m2 39,875.00
VII PEKERJAAN BETON
Pekerjaan Sloof m3 110,424.38
Pemasangan Bekesting Sloof m2 210,221.00
Pekerjaan Kolom m3 134,460.76
Pemasangan Bekesting Kolom m2 338,530.50
Pemasangan Balok Latey m3 110,424.38
Pemasangan Plat Leufel m3 83,561.50
Pemasangan Bekestig Plat Leufel m2 331,358.50
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof Kg 110,424.38
Pemasangan Tulangan Kolom Kg 134,460.76
IX PEKERJAAN RANGKA ATAP
Pekerjaan Kuda-Kuda Baja Ringan m2 277,040.50
Pekerjaan Usuk / Reng m2 197,840.50
X PEKERJAAN PENUTUP ATAP
Pemasangan Genteng m2 24,330.00
Pemasangan Genteng Kerpus m2 132,363.00
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) m2 256,773.00
Pekerjaan Penutup Plafon m2 401,973.00
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 m2 1,199,258.50
Pemasangan Keramik Tekstur Uk.30x30 m2 3,118,978.50
Pemasangan Keramik Dinding KM Uk.30x30 m2 2,485,444.50
Pemasangan Lis Keramik KM Uk.10x30 m2 180,348.30
Pemasangan Batu Alam m2 299,502.50
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Kusen m2 48,603.50
Pekerjaan Pengecatan Pintu m2 55,863.50
Pekerjaan Pengecatan Jendela m2 55,863.50
Pekerjaan Pengecatan Dinding Eksterior m2 24,040.50
Pekerjaan Pengecatan Dinding Interior m2 68,777.50
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan Lampu bh 431,508.00
Pemasangan MCB bh 536,448.00
XV PEKERJAAN SANITASI
Pemasangan Pipa Ø1/2 " m' 67,691.03
Pemasangan Pipa Ø4" m' 462,173.25
Pemasangan Kran bh 108,444.88
Pemasangan Bak Mandi bh 1,415,205.00
Pemasangan Floor Drain bh 109,532.50
Pemasangan Closet Duduk bh 2,246,200.00
Pemasangan Septictank Ls 7,000,000.00
ANALISA HARGA SATUAN PEKERJAAN
JUDUL PROYEK : RUMAH TINGGAL TYPE 36

HARGA BAHAN/UPAH JUMLAH


SNI KODE KOEF SAT. URAIAN PEKERJAAN
MINIMUM MAKSIMUM MINIMUM MAKSIMUM
A.2.2. 1 K.3 PEKERJAAN PERSIAPAN
A.2.2.1 .2 1 m' Pagar Sementara BJLS 0,18 panjang 108 cm 169,138.75 276,760.00
A TENAGA 66,500.00 150,700.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.4 OH Tukang Kayu 120,000.00 130,000.00 48,000.00 130,000.00
L.04 0.02 OH Mandor 125,000.00 135,000.00 2,500.00 2,700.00
B BAHAN 87,262.50 100,900.00
1.25 m3 Kayu Dolken Ø 8-10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portland Cement 1,125.00 1,200.00 2,812.50 3,000.00
1.2 Lbr Seng Gelombang BJLS 0,20 panjang 180 cm 47,000.00 55,000.00 56,400.00 66,000.00
0.005 m3 Pasir Beton 360,000.00 380,000.00 1,800.00 1,900.00
C PERALATAN
D Jumlah (A+B+C) 153,762.50 251,600.00
E Overhead & Profil 11% 15,376.25 25,160.00
F Harga Satuan Pekerjaan (D+E) 169,138.75 276,760.00

A.2.2.1 .4 1 m' Pengukuran dan Pemasangan Bouwplank 105,517.50 141,487.50


A TENAGA 20,625.00 22,675.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 75,300.00 105,950.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 6,250,000.00 8,800,000.00 75,000.00 105,600.00
0.02 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 300.00 350.00
C PERALATAN
D Jumlah (A+B+C) 95,925.00 128,625.00
E Overhead & Profil 11% 9,592.50 12,862.50
F Harga Satuan Pekerjaan (D+E) 105,517.50 141,487.50

A.2.2.1 .7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 522,018.75 581,130.00


A TENAGA 326,250.00 356,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN 148,312.50 171,550.00
1.7 m3 Kayu Dolken Ø 8-10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.3 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 4,500.00 5,250.00
10.5 Kg Portland Cement 1,125.00 1,200.00 11,812.50 12,600.00
0.03 m3 Pasir Beton 360,000.00 380,000.00 10,800.00 11,400.00
0.05 m3 Kerikil Beton 0,5/1 300,000.00 380,000.00 15,000.00 19,000.00
1.5 Lbr Seng Gelombang BJLS 0,20 panjang 180 cm 47,000.00 55,000.00 70,500.00 82,500.00
C PERALATAN
D Jumlah (A+B+C) 474,562.50 528,300.00
E Overhead & Profil 11% 47,456.25 52,830.00
F Harga Satuan Pekerjaan (D+E) 522,018.75 581,130.00

A.2.2.1 .9 K.3 1 m2 Membersihkan Lapangan dan Peralatan 15,675.00 17,325.00


A TENAGA 14,250.00 15,750.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah (A+B+C) 14,250.00 15,750.00
E Overhead & Profil 11% 1,425.00 1,575.00
F Harga Satuan Pekerjaan (D+E) 15,675.00 17,325.00

A.2.2.1 .10 K.3 1 m2 Pembuatan Steger/perancah 376,807.20 418,648.12


A TENAGA 326,250.00 356,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN 16,302.00 23,839.20
1.25 Btg Bambu Ø6-8 / 600 cm 12,000.00 18,000.00 15,000.00 22,500.00
0.186 Kg Tali Ijuk 7,000.00 7,200.00 1,302.00 1,339.20
C PERALATAN
D Jumlah (A+B+C) 342,552.00 380,589.20
E Overhead & Profil 11% 34,255.20 38,058.92
F Harga Satuan Pekerjaan (D+E) 376,807.20 418,648.12

A.2.3.1 PEKERJAAN TANAH


A.2.3.1.1 1 m3 Menggali Tanah Pondasi 85,387.50 95,782.50
A TENAGA 77,625.00 87,075.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN
C PERALATAN
D Jumlah A+B+C 77,625.00 87,075.00
E Overhead & Profil 11% 7,762.50 8,707.50
F Harga Satuan Pekerjaan (D+E) 85,387.50 95,782.50

A.2.3.1.9 1 m3 Pengukuran Kembali di hitung dari 1/3 kali koefisien 50,875.00 56,925.00
Pekerja Galian
A TENAGA 46,250.00 51,750.00
L.01 0.5 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah A+B+C 46,250.00 51,750.00
E Overhead & Profil 11% 4,625.00 5,175.00
F Harga Satuan Pekerjaan (D+E) 50,875.00 56,925.00

A.2.3.1.11 1 m3 Urugan Pasir 238,975.00 321,585.00


A TENAGA 25,250.00 28,350.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 192,000.00 264,000.00
1.2 m3 Pasir Urug 160,000.00 220,000.00 192,000.00 264,000.00
C PERALATAN
D Jumlah A+B+C 217,250.00 292,350.00
E Overhead & Profil 11% 21,725.00 29,235.00
F Harga Satuan Pekerjaan (D+E) 238,975.00 321,585.00

A.3.2.1 PEKERJAAN PONDASI


A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Kali 800,965.00 886,435.00
A TENAGA 223,125.00 242,625.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.75 OH Tukang Batu 125,000.00 130,000.00 93,750.00 97,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN
1.2 m3 Batu Belah 280,000.00 320,000.00 336,000.00 384,000.00
202 Kg Portland Cement 1,125.00 1,200.00 227,250.00 242,400.00
0.485 m3 Pasir Pasang 340,000.00 370,000.00 164,900.00 179,450.00
C PERALATAN
D Jumlah A+B+C 728,150.00 805,850.00
E Overhead & Profil 11% 72,815.00 80,585.00
F Harga Satuan Pekerjaan (D+E) 800,965.00 886,435.00

A.3.2.1.9 1 m3 Pemasangan Batu kosong / Aanstamping 573,259.50 665,725.50


A TENAGA 116,025.00 126,165.00
0.78 OH Pekerja 80,000.00 90,000.00 62,400.00 70,200.00
0.39 OH Tukang Batu 125,000.00 130,000.00 48,750.00 50,700.00
0.039 OH Mandor 125,000.00 135,000.00 4,875.00 5,265.00
B BAHAN 405,120.00 479,040.00
1.2 m3 Batu Belah 280,000.00 320,000.00 336,000.00 384,000.00
0.432 m3 Pasir Urug 160,000.00 220,000.00 69,120.00 95,040.00
C PERALATAN
D Jumlah A+B+C 521,145.00 605,205.00
E Overhead & Profil 11% 52,114.50 60,520.50
F Harga Satuan Pekerjaan (D+E) 573,259.50 665,725.50

A.4.6.1 PEKERJAAN KUSEN


A.4.6.1.6 1 m2 Pemasangan Pintu 262,955.00 300,245.00
A TENAGA 201,250.00 221,350.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1 OH Tukang Kayu 120,000.00 130,000.00 120,000.00 130,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 37,800.00 51,600.00
1 m3 Kayu Meranti 25,000.00 31,250.00 25,000.00 31,250.00
0.02 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 300.00 350.00
1 Buah Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A+B+C 239,050.00 272,950.00
E Overhead & Profil 11% 23,905.00 27,295.00
F Harga Satuan Pekerjaan (D+E) 262,955.00 300,245.00

A.4.6.1.6 1 m2 Pemasangan Jendela 249,205.00 278,245.00


A TENAGA 201,250.00 221,350.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1 OH Tukang Kayu 120,000.00 130,000.00 120,000.00 130,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 25,300.00 31,600.00
1 m3 Kayu Meranti 25,000.00 31,250.00 25,000.00 31,250.00
0.02 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 300.00 350.00
1 Buah Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A+B+C 226,550.00 252,950.00
E Overhead & Profil 11% 22,655.00 25,295.00
F Harga Satuan Pekerjaan (D+E) 249,205.00 278,245.00
A.4.4.1 PEKERJAAN DINDING, PLESTERAN, DAN ACIAN
A.4.4.1.1 1 m2 Pekerjaan Dinding 1:2 260,576.25 282,535.00
A TENAGA 76,750.00 84,050.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 125,000.00 130,000.00 25,000.00 26,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B BAHAN 160,137.50 172,800.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
43.5 Kg Portland Cement 1,125.00 1,200.00 48,937.50 52,200.00
0.08 m3 Pasir Pasang 340,000.00 370,000.00 27,200.00 29,600.00
C PERALATAN
D Jumlah A+B+C 236,887.50 256,850.00
E Overhead & Profil 11% 23,688.75 25,685.00
F Harga Satuan Pekerjaan (D+E) 260,576.25 282,535.00

A.4.4.1.4 1 m2 Pekerjaan Dinding 1:5 242,445.50 263,373.00


A TENAGA 76,750.00 84,050.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 125,000.00 130,000.00 25,000.00 26,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B BAHAN 143,655.00 155,380.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
22.2 Kg Portland Cement 1,125.00 1,200.00 24,975.00 26,640.00
0.102 m3 Pasir Pasang 340,000.00 370,000.00 34,680.00 37,740.00
C PERALATAN
D Jumlah A+B+C 220,405.00 239,430.00
E Overhead & Profil 11% 22,040.50 23,943.00
F Harga Satuan Pekerjaan (D+E) 242,445.50 263,373.00

A.4.4.2.2 1 m2 Pekerjaan Plesteran Dinding 1:2 69,219.70 75,013.18


A TENAGA 44,625.00 48,525.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.15 OH Tukang Batu 125,000.00 130,000.00 18,750.00 19,500.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B BAHAN 18,302.00 19,668.80
10.224 Kg Portland Cement 1,125.00 1,200.00 11,502.00 12,268.80
0.02 m3 Pasir Pasang 340,000.00 370,000.00 6,800.00 7,400.00
C PERALATAN
D Jumlah A+B+C 62,927.00 68,193.80
E Overhead & Profil 11% 6,292.70 6,819.38
F Harga Satuan Pekerjaan (D+E) 69,219.70 75,013.18
A.4.4.2.5 1 m2 Pekerjaan Plesteran Dinding 1:5 65,226.70 70,802.38
A TENAGA 44,625.00 48,525.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.15 OH Tukang Batu 125,000.00 130,000.00 18,750.00 19,500.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B BAHAN 14,672.00 15,840.80
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.026 m3 Pasir Pasang 340,000.00 370,000.00 8,840.00 9,620.00
C PERALATAN
D Jumlah A+B+C 59,297.00 64,365.80
E Overhead & Profil 11% 5,929.70 6,436.58
F Harga Satuan Pekerjaan (D+E) 65,226.70 70,802.38

A.4.4.2.23 1 m2 Pekerjaan Plesteran Tali Air 28,458.65 30,865.56


A TENAGA 22,375.00 24,330.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Batu 125,000.00 130,000.00 9,375.00 9,750.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B BAHAN 3,496.50 3,729.60
3.108 Kg Portland Cement 1,125.00 1,200.00 3,496.50 3,729.60
C PERALATAN
D Jumlah A+B+C 25,871.50 28,059.60
E Overhead & Profil 11% 2,587.15 2,805.96
F Harga Satuan Pekerjaan (D+E) 28,458.65 30,865.56

A.4.4.2.27 1 m2 Pekerjaan Acian 36,746.88 39,875.00


A TENAGA 29,750.00 32,350.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.1 OH Tukang Batu 125,000.00 130,000.00 12,500.00 13,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 3,656.25 3,900.00
3.25 Kg Portland Cement 1,125.00 1,200.00 3,656.25 3,900.00
C PERALATAN
D Jumlah A+B+C 33,406.25 36,250.00
E Overhead & Profil 11% 3,340.63 3,625.00
F Harga Satuan Pekerjaan (D+E) 36,746.88 39,875.00

A.4.1.1 PEKERJAAN BETON


A.4.1.1.21 1 m2 Pekerjaan Sloof 101,455.20 110,424.38
A TENAGA 80,100.00 86,980.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.28 OH Tukang Besi 125,000.00 130,000.00 35,000.00 36,400.00
L.04 0.028 OH Mandor 125,000.00 135,000.00 3,500.00 3,780.00
B BAHAN 12,132.00 13,405.80
0.045 Kg Besi Beton Polos 10,000.00 12,000.00 450.00 540.00
0.045 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 810.00 945.00
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 92,232.00 100,385.80
E Overhead & Profil 11% 9,223.20 10,038.58
F Harga Satuan Pekerjaan (D+E) 101,455.20 110,424.38

A.4.1.1.21 1 m2 Pemasangan Bekisting Sloof 190,245.00 210,221.00


A TENAGA 76,050.00 84,110.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.26 OH Tukang Kayu 120,000.00 130,000.00 31,200.00 33,800.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B BAHAN 96,900.00 107,000.00
0.045 m3 Kayu kelas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.4 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 6,000.00 7,000.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A+B+C 172,950.00 191,110.00
E Overhead & Profil 11% 17,295.00 19,111.00
F Harga Satuan Pekerjaan (D+E) 190,245.00 210,221.00

A.4.1.1.22 1 m2 Pekerjaan Kolom 123,543.20 134,460.76


A TENAGA 99,550.00 108,190.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.34 OH Tukang Besi 125,000.00 130,000.00 42,500.00 44,200.00
L.04 0.034 OH Mandor 125,000.00 135,000.00 4,250.00 4,590.00
B BAHAN 12,762.00 14,047.05
0.045 Kg Besi Beton Polos 10,000.00 12,000.00 450.00 540.00
0.045 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 810.00 945.00
0.045 Kg Besi Plat (Besi Strip) 14,000.00 14,250.00 630.00 641.25
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 112,312.00 122,237.05
E Overhead & Profil 10% 11,231.20 12,223.71
F Harga Satuan Pekerjaan (D+E) 123,543.20 134,460.76

A.4.1.1.22 1 m2 Pemasangan Bekisting Kolom 291,307.50 338,530.50


A TENAGA 96,525.00 106,755.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B BAHAN 168,300.00 201,000.00
0.04 m3 Kayu kelas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg PAKU - ukuran 1" s/d 4'' 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Kayu Dolken Ø 8-10 / 400 cm 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A+B+C 264,825.00 307,755.00
E Overhead & Profil 11% 26,482.50 30,775.50
F Harga Satuan Pekerjaan (D+E) 291,307.50 338,530.50

A.4.1.1.23 1 m2 Pemasangan Balok Latey 101,455.20 110,424.38


A TENAGA 80,100.00 86,980.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.28 OH Tukang Besi 125,000.00 130,000.00 35,000.00 36,400.00
L.04 0.028 OH Mandor 125,000.00 135,000.00 3,500.00 3,780.00
B BAHAN 12,132.00 13,405.80
0.045 Kg Besi Beton Polos 10,000.00 12,000.00 450.00 540.00
0.045 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 810.00 945.00
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 92,232.00 100,385.80
E Overhead & Profil 11% 9,223.20 10,038.58
F Harga Satuan Pekerjaan (D+E) 101,455.20 110,424.38

A.4.1.1.23 1 m2 Pemasangan Plat Leufel 72,231.50 83,561.50


A TENAGA 18,025.00 20,015.00
L.01 0.18 OH Pekerja 80,000.00 90,000.00 14,400.00 16,200.00
L.02 0.02 OH Tukang Besi 125,000.00 130,000.00 2,500.00 2,600.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B BAHAN 47,640.00 55,950.00
3 Kg Besi Beton Polos 10,000.00 12,000.00 30,000.00 36,000.00
0.45 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 8,100.00 9,450.00
4 Kg Portland Cement 1,125.00 1,200.00 4,500.00 4,800.00
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 65,665.00 75,965.00
E Overhead & Profil 11% 6,566.50 7,596.50
F Harga Satuan Pekerjaan (D+E) 72,231.50 83,561.50

A.4.1.1.23 1 m2 Pemasangan Bekesting Plat Leufel 285,202.50 331,358.50


A TENAGA 96,525.00 106,755.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B BAHAN 162,750.00 194,480.00
0.04 m3 Kayu kelas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Portland Cement 1,125.00 1,200.00 450.00 480.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Kayu Dolken Ø 8-10 / 400 cm 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A+B+C 259,275.00 301,235.00
E Overhead & Profil 11% 25,927.50 30,123.50
F Harga Satuan Pekerjaan (D+E) 285,202.50 331,358.50

A.4.6.2 PEKERJAAN KUNCI DAN KACA


A.4.6.2.5 1 m2 Pemasangan Engsel Pintu 30,401.25 33,948.75
A TENAGA 20,137.50 21,862.50
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.04 0.0075 OH Mandor 125,000.00 135,000.00 937.50 1,012.50
B BAHAN 7,500.00 9,000.00
1 Buah Engsel Pintu 7,500.00 9,000.00 7,500.00 9,000.00
C PERALATAN
D Jumlah A+B+C 27,637.50 30,862.50
E Overhead & Profil 11% 2,763.75 3,086.25
F Harga Satuan Pekerjaan (D+E) 30,401.25 33,948.75

A.4.6.2.2 1 m2 Pemasangan Kunci Pintu 172,067.50 238,232.50


A TENAGA 61,425.00 66,575.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 95,000.00 150,000.00
1 Buah Kunci tanam Yale 1 slag 95,000.00 150,000.00 95,000.00 150,000.00
C PERALATAN
D Jumlah A+B+C 156,425.00 216,575.00
E Overhead & Profil 11% 15,642.50 21,657.50
F Harga Satuan Pekerjaan (D+E) 172,067.50 238,232.50

A.4.6.2.6 1 m2 Pemasangan Engsel Jendela 19,717.50 22,632.50


A TENAGA 13,425.00 14,575.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 4,500.00 6,000.00
1 Buah Engsel Jendela 4,500.00 6,000.00 4,500.00 6,000.00
C PERALATAN
D Jumlah A+B+C 17,925.00 20,575.00
E Overhead & Profil 11% 1,792.50 2,057.50
F Harga Satuan Pekerjaan (D+E) 19,717.50 22,632.50

A.4.6.2.6 1 m2 Pemasangan Grendel Jendela 20,267.50 23,732.50


A TENAGA 13,425.00 14,575.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 5,000.00 7,000.00
1 Buah Grendel Jendela 5,000.00 7,000.00 5,000.00 7,000.00
C PERALATAN
D Jumlah A+B+C 18,425.00 21,575.00
E Overhead & Profil 11% 1,842.50 2,157.50
F Harga Satuan Pekerjaan (D+E) 20,267.50 23,732.50

A.4.6.2.9 1 m2 Pemasangan Penyangga Jendela 41,470.00 46,123.00


A TENAGA 20,200.00 21,930.00
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B BAHAN 17,500.00 20,000.00
1 Buah Kait Angin 17,500.00 20,000.00 17,500.00 20,000.00
C PERALATAN
D Jumlah A+B+C 37,700.00 41,930.00
E Overhead & Profil 11% 3,770.00 4,193.00
F Harga Satuan Pekerjaan (D+E) 41,470.00 46,123.00

A.4.6.2.16 1 m2 Pemasangan Kaca Jendela 130,123.13 137,996.38


A TENAGA 19,293.75 20,951.25
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B BAHAN 99,000.00 104,500.00
1.1 m2 Kaca tebal 5mm 90,000.00 95,000.00 99,000.00 104,500.00
C PERALATAN
D Jumlah A+B+C 118,293.75 125,451.25
E Overhead & Profil 11% 11,829.38 12,545.13
F Harga Satuan Pekerjaan (D+E) 130,123.13 137,996.38

A.4.2.1 PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.1 1 m2 Pemasangan Tulangan Sloof 101,455.20 110,424.38
A TENAGA 80,100.00 86,980.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.28 OH Tukang Besi 125,000.00 130,000.00 35,000.00 36,400.00
L.04 0.028 OH Mandor 125,000.00 135,000.00 3,500.00 3,780.00
B BAHAN 12,132.00 13,405.80
0.045 Kg Besi Beton Polos 10,000.00 12,000.00 450.00 540.00
0.045 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 810.00 945.00
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 92,232.00 100,385.80
E Overhead & Profil 11% 9,223.20 10,038.58
F Harga Satuan Pekerjaan (D+E) 101,455.20 110,424.38

A.4.2.1.2 1 m2 Pemasangan Tulangan Kolom 123,543.20 134,460.76


A TENAGA 99,550.00 108,190.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.34 OH Tukang Besi 125,000.00 130,000.00 42,500.00 44,200.00
L.04 0.034 OH Mandor 125,000.00 135,000.00 4,250.00 4,590.00
B BAHAN 12,762.00 14,047.05
0.045 Kg Besi Beton Polos 10,000.00 12,000.00 450.00 540.00
0.045 Kg Ikat Beton/Bendrat 18,000.00 21,000.00 810.00 945.00
0.045 Kg Besi Plat (Besi Strip) 14,000.00 14,250.00 630.00 641.25
5.184 Kg Portland Cement 1,125.00 1,200.00 5,832.00 6,220.80
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 380,000.00 2,880.00 3,420.00
C PERALATAN
D Jumlah A+B+C 112,312.00 122,237.05
E Overhead & Profil 11% 11,231.20 12,223.71
F Harga Satuan Pekerjaan (D+E) 123,543.20 134,460.76

A.4.2.1 PEKERJAAN RANGKA ATAP


A.4.2.1.22 1 m2 Pekerjaan Kuda-Kuda Baja Ringan 247,967.50 277,040.50
A TENAGA 12,675.00 13,605.00
L.01 0.06 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.06 OH Tukang Besi 125,000.00 130,000.00 7,500.00 7,800.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 152,750.00 166,250.00
1.15 btg Baja Ringan type CT 75 lebar:7,5cm tebal:0,75mm 105,000.00 115,000.00 120,750.00 132,250.00
1 **) Assesories (perkuatan,las,dll) 100% x rangka 32,000.00 34,000.00 32,000.00 34,000.00
C PERALATAN 60,000.00 72,000.00
0.8 jam Sewa Alat 75,000.00 90,000.00 60,000.00 72,000.00
D Jumlah A+B+C 225,425.00 251,855.00
E Overhead & Profil 11% 22,542.50 25,185.50
F Harga Satuan Pekerjaan (D+E) 247,967.50 277,040.50

A.4.2.1.23 1 m2 Pekerjaan Usuk/Reng 181,967.50 197,840.50


A TENAGA 12,675.00 13,605.00
L.01 0.06 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.06 OH Tukang Besi 125,000.00 130,000.00 7,500.00 7,800.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 152,750.00 166,250.00
1.15 btg Baja Ringan 105,000.00 115,000.00 120,750.00 132,250.00
1 **) Assesories (perkuatan,las,dll) 100% x rangka 32,000.00 34,000.00 32,000.00 34,000.00
C PERALATAN
D Jumlah A+B+C 165,425.00 179,855.00
E Overhead & Profil 11% 16,542.50 17,985.50
F Harga Satuan Pekerjaan (D+E) 181,967.50 197,840.50

A.4.5.2 PEKERJAAN PENUTUP ATAP


A.4.5.2.1 1 m2 Pemasangan Genteng Plentong Super/Besar
A TENAGA 22,000.00 24,330.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B BAHAN 91,800.00 96,300.00
12 Buah Genteng Plentong Super Besar 18 bh/m2 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A+B+C 113,800.00 120,630.00
E Overhead & Profil 11% 11,380.00 12,063.00
F Harga Satuan Pekerjaan (D+E) 125,180.00 132,693.00

A.4.5.2.38 1 m2 Pemasangan Genteng Kerpus 116,600.00 132,363.00


A TENAGA 22,000.00 24,330.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B BAHAN 84,000.00 96,000.00
12 Buah Genteng Kerpus 7,000.00 8,000.00 84,000.00 96,000.00
C PERALATAN
D Jumlah A+B+C 106,000.00 120,330.00
E Overhead & Profil 11% 10,600.00 12,033.00
F Harga Satuan Pekerjaan (D+E) 116,600.00 132,363.00

A.4.5.1 PEKERJAAN LANGIT-LANGIT


A.4.5.1.6 1 m2 Pekerjaan Rangka Plafon (Hollow) 235,400.00 256,773.00
A TENAGA 74,000.00 79,430.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.35 OH Tukang Besi 125,000.00 130,000.00 43,750.00 45,500.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B BAHAN 140,000.00 154,000.00
4 m' Hollow Galvanis Lipat tinggi 4 cm; tebal 0,3 mm 27,000.00 30,000.00 108,000.00 120,000.00
1 **) Assesories (perkuatan,las,dll) 100% x rangka 32,000.00 34,000.00 32,000.00 34,000.00
C PERALATAN
D Jumlah A+B+C 214,000.00 233,430.00
E Overhead & Profil 11% 21,400.00 23,343.00
F Harga Satuan Pekerjaan (D+E) 235,400.00 256,773.00

A.4.5.1.7 1 m2 Pekerjaan Penutup Plafon 359,700.00 401,973.00


A TENAGA 74,000.00 79,430.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.35 OH Tukang Besi 125,000.00 130,000.00 43,750.00 45,500.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B BAHAN 253,000.00 286,000.00
4 m' Gypsum tebal 9mm 60,000.00 68,000.00 240,000.00 272,000.00
1 Kg Mur Baut 13,000.00 14,000.00 13,000.00 14,000.00
C PERALATAN
D Jumlah A+B+C 327,000.00 365,430.00
E Overhead & Profil 11% 32,700.00 36,543.00
F Harga Satuan Pekerjaan (D+E) 359,700.00 401,973.00

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN DINDING


A.4.4.3.34 1 m2 Pemasangan Keramik Polos Uk.30x30 945,312.50 1,199,258.50
A TENAGA 104,125.00 113,225.00
L.01 0.7 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 125,000.00 130,000.00 43,750.00 45,500.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B BAHAN 755,250.00 977,010.00
11.87 Buah Ubin Keramik 30x30 cm 60,000.00 78,000.00 712,200.00 925,860.00
10 Kg Portland Cement 1,125.00 1,200.00 11,250.00 12,000.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
1.5 Kg Semen Warna 11,000.00 15,000.00 16,500.00 22,500.00
C PERALATAN
D Jumlah A+B+C 859,375.00 1,090,235.00
E Overhead & Profil 11% 85,937.50 109,023.50
F Harga Satuan Pekerjaan (D+E) 945,312.50 1,199,258.50

A.4.4.3.34 1 m2 Pemasangan Keramik Tekstur Uk.30x30 2,429,234.50 3,118,978.50


A TENAGA 154,000.00 167,475.00
L.01 1.05 OH Pekerja 80,000.00 90,000.00 84,000.00 94,500.00
L.02 0.525 OH Tukang Batu 125,000.00 130,000.00 65,625.00 68,250.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B BAHAN 2,054,395.00 2,667,960.00
33 Buah Ubin Keramik 30x30 cm 60,000.00 78,000.00 1,980,000.00 2,574,000.00
9.8 Kg Portland Cement 1,125.00 1,200.00 11,025.00 11,760.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
4.37 Kg Semen Warna 11,000.00 15,000.00 48,070.00 65,550.00
C PERALATAN
D Jumlah A+B+C 2,208,395.00 2,835,435.00
E Overhead & Profil 11% 220,839.50 283,543.50
F Harga Satuan Pekerjaan (D+E) 2,429,234.50 3,118,978.50

A.4.4.3.54 1 m2 Pemasangan Keramik Dinding KM Uk.30x30 1,937,977.25 2,485,444.50


A TENAGA 133,875.00 145,575.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.02 0.45 OH Tukang Batu 125,000.00 130,000.00 56,250.00 58,500.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN 1,627,922.50 2,113,920.00
26.5 Buah Keramik 60,000.00 78,000.00 1,590,000.00 2,067,000.00
9.3 Kg Portland Cement 1,125.00 1,200.00 10,462.50 11,160.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A+B+C 1,761,797.50 2,259,495.00
E Overhead & Profil 11% 176,179.75 225,949.50
F Harga Satuan Pekerjaan (D+E) 1,937,977.25 2,485,444.50

A.4.4.3.39 1 m' Pemasangan Lis Keramik KM Uk.10x30 169,980.25 180,348.30


A TENAGA 19,075.00 20,475.00
L.01 0.09 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.09 OH Tukang Batu 125,000.00 130,000.00 11,250.00 11,700.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 135,452.50 143,478.00
25.5 Buah Tegel Plint PC Warna 10x30 5,200.00 5,500.00 132,600.00 140,250.00
1.14 Kg Portland Cement 1,125.00 1,200.00 1,282.50 1,368.00
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A+B+C 154,527.50 163,953.00
E Overhead & Profil 11% 15,452.75 16,395.30
F Harga Satuan Pekerjaan (D+E) 169,980.25 180,348.30

A.4.4.3.58 1 m2 Pemasangan Batu Alam 269,218.13 299,502.50


A TENAGA 104,125.00 113,225.00
L.01 0.7 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 125,000.00 130,000.00 43,750.00 45,500.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B BAHAN 140,618.75 159,050.00
1.1 m2 Batu Tempel Hitam 105,000.00 120,000.00 115,500.00 132,000.00
11.75 Kg Portland Cement 1,125.00 1,200.00 13,218.75 14,100.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A+B+C 244,743.75 272,275.00
E Overhead & Profil 11% 24,474.38 27,227.50
F Harga Satuan Pekerjaan (D+E) 269,218.13 299,502.50

A.4.7.1 PEKERJAAN PENGECATAN


A.4.7.1.4 1 m2 Pekerjaan Pengecatan Kusen dengan Politur 46,480.50 48,603.50
A TENAGA 11,075.00 11,805.00
L.01 0.04 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.06 OH Tukang Cat 125,000.00 130,000.00 7,500.00 7,800.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 31,180.00 32,380.00
0.372 Ltr Politur Jadi 65,000.00 65,000.00 24,180.00 24,180.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A+B+C 42,255.00 44,185.00
E Overhead & Profil 11% 4,225.50 4,418.50
F Harga Satuan Pekerjaan (D+E) 46,480.50 48,603.50

A.4.7.1.4 1 m2 Pekerjaan Pengecatan Pintu 53,245.50 55,863.50


A TENAGA 17,225.00 18,405.00
L.01 0.07 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00
L.02 0.09 OH Tukang Cat 125,000.00 130,000.00 11,250.00 11,700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 31,180.00 32,380.00
0.372 Ltr Politur Jadi 65,000.00 65,000.00 24,180.00 24,180.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A+B+C 48,405.00 50,785.00
E Overhead & Profil 11% 4,840.50 5,078.50
F Harga Satuan Pekerjaan (D+E) 53,245.50 55,863.50

A.4.7.1.4 1 m2 Pekerjaan Pengecatan Jendela 53,245.50 55,863.50


A TENAGA 17,225.00 18,405.00
L.01 0.07 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00
L.02 0.09 OH Tukang Cat 125,000.00 130,000.00 11,250.00 11,700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 31,180.00 32,380.00
0.372 Ltr Politur Jadi 65,000.00 65,000.00 24,180.00 24,180.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A+B+C 48,405.00 50,785.00
E Overhead & Profil 11% 4,840.50 5,078.50
F Harga Satuan Pekerjaan (D+E) 53,245.50 55,863.50
A.4.7.1.10 1 m2 Pekerjaan Pengecatan Dinding Eksterior 21,483.00 24,040.50
A TENAGA 9,850.00 10,395.00
L.01 0.02 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.063 OH Tukang Cat 125,000.00 130,000.00 7,875.00 8,190.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 9,680.00 11,460.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 Kali 23,000.00 26,000.00 5,980.00 6,760.00
C PERALATAN
D Jumlah A+B+C 19,530.00 21,855.00
E Overhead & Profil 11% 1,953.00 2,185.50
F Harga Satuan Pekerjaan (D+E) 21,483.00 24,040.50

A.4.7.1.10 1 m2 Pekerjaan Pengecatan Dinding Interior 64,960.50 68,777.50


A TENAGA 55,115.00 57,525.00
L.01 0.028 OH Pekerja 80,000.00 90,000.00 2,240.00 2,520.00
L.02 0.42 OH Tukang Cat 125,000.00 130,000.00 52,500.00 54,600.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B BAHAN 3,940.00 5,000.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
C PERALATAN
D Jumlah A+B+C 59,055.00 62,525.00
E Overhead & Profil 11% 5,905.50 6,252.50
F Harga Satuan Pekerjaan (D+E) 64,960.50 68,777.50

A.8.4.6 PEKERJAAN INSTALASI LISTRIK


A.8.4.6.1 1 Titik Pemasangan Lampu 385,880.00 431,508.00
A TENAGA 175,400.00 196,140.00
L.01 100 % Pekerja 175,400.00 196,140.00 175,400.00 196,140.00
B BAHAN 175,400.00 196,140.00
3 btg Pipa Listrik 5/8 **) 4,000.00 4,200.00 12,000.00 12,600.00
24 m Kabel **) 5,500.00 6,200.00 132,000.00 148,800.00
3 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00
1 buah Piting 12,000.00 13,000.00 12,000.00 13,000.00
C PERALATAN
D Jumlah A+B+C 350,800.00 392,280.00
E Overhead & Profil 11% 35,080.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 385,880.00 431,508.00

A.8.4.6.2 1 buah Pemasangan MCB 488,840.00 536,448.00


A TENAGA 222,200.00 243,840.00
L.01 100 % Pekerja 222,200.00 243,840.00 222,200.00 243,840.00
B BAHAN 222,200.00 243,840.00
3 btg Pipa Listrik 5/8 **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 5,500.00 6,200.00 82,500.00 93,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A+B+C 444,400.00 487,680.00
E Overhead & Profil 11% 44,440.00 48,768.00
F Harga Satuan Pekerjaan (D+E) 488,840.00 536,448.00

A.5.1.1 PEKERJAAN SANITASI


A.5.1.1.25 1 m' Pemasangan Pipa Ø1/2 " 64,884.77 67,691.03
A TENAGA 18,945.00 20,205.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.09 OH Tukang Batu 125,000.00 130,000.00 11,250.00 11,700.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B BAHAN 40,041.15 41,332.30
1.2 m' Pipa Galvanis Ø 1/2 '' 25,833.00 26,666.00 30,999.60 31,999.20
0.35 Ls Perlengkapan 35% x pipa 25,833.00 26,666.00 9,041.55 9,333.10
C PERALATAN
D Jumlah A+B+C 58,986.15 61,537.30
E Overhead & Profil 11% 5,898.62 6,153.73
F Harga Satuan Pekerjaan (D+E) 64,884.77 67,691.03

A.5.1.1.24 1 m' Pemasangan Pipa Ø4" 457,242.50 462,173.25


A TENAGA 39,800.00 42,345.00
L.01 0.135 OH Pekerja 80,000.00 90,000.00 10,800.00 12,150.00
L.02 0.225 OH Tukang Batu 125,000.00 130,000.00 28,125.00 29,250.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B BAHAN 375,875.00 377,812.50
1.2 m' Pipa Galvanis Ø 4 '' 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A+B+C 415,675.00 420,157.50
E Overhead & Profil 11% 41,567.50 42,015.75
F Harga Satuan Pekerjaan (D+E) 457,242.50 462,173.25

A.5.1.1.19 1 bh Pemasangan Kran 84,077.13 108,444.88


A TENAGA 51,425.00 53,575.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.4 OH Tukang Batu 125,000.00 130,000.00 50,000.00 52,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 25,008.75 45,011.25
1 bh Kran Air 25,000.00 45,000.00 25,000.00 45,000.00
0.0025 bh Seal Tape 3,500.00 4,500.00 8.75 11.25
C PERALATAN
D Jumlah A+B+C 76,433.75 98,586.25
E Overhead & Profil 11% 7,643.38 9,858.63
F Harga Satuan Pekerjaan (D+E) 84,077.13 108,444.88

A.5.1.1.8 1 Unit Pemasangan Bak Mandi 1,304,325.00 1,415,205.00


A TENAGA 858,750.00 934,050.00
L.01 6 OH Pekerja 80,000.00 90,000.00 480,000.00 540,000.00
L.02 3 OH Tukang Batu 125,000.00 130,000.00 375,000.00 390,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B BAHAN 327,000.00 352,500.00
150 bh Batu Bata 600.00 650.00 90,000.00 97,500.00
120 Kg Portland Cement 1,125.00 1,200.00 135,000.00 144,000.00
0.3 m3 Pasir Pasang 340,000.00 370,000.00 102,000.00 111,000.00
C PERALATAN
D Jumlah A+B+C 1,185,750.00 1,286,550.00
E Overhead & Profil 11% 118,575.00 128,655.00
F Harga Satuan Pekerjaan (D+E) 1,304,325.00 1,415,205.00

A.5.1.1.14 1 buah Pemasangan Floor Drain 92,317.50 109,532.50


A TENAGA 48,925.00 57,075.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.1 OH Tukang Batu 125,000.00 130,000.00 12,500.00 13,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN 35,000.00 42,500.00
1 bh Floor Drain 35,000.00 42,500.00 35,000.00 42,500.00
C PERALATAN
D Jumlah A+B+C 83,925.00 99,575.00
E Overhead & Profil 11% 8,392.50 9,957.50
F Harga Satuan Pekerjaan (D+E) 92,317.50 109,532.50

A.5.1.1.1 1 Unit Pemasangan Closet Duduk 1,944,800.00 2,246,200.00


A TENAGA 421,500.00 461,600.00
L.01 3.3 OH Pekerja 80,000.00 90,000.00 264,000.00 297,000.00
L.02 1.1 OH Tukang Batu 125,000.00 130,000.00 137,500.00 143,000.00
L.04 0.16 OH Mandor 125,000.00 135,000.00 20,000.00 21,600.00
B BAHAN 1,696,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,600,000.00 1,850,000.00 1,600,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,600,000.00 1,850,000.00 96,000.00 111,000.00
C PERALATAN
D Jumlah A+B+C 1,768,000.00 2,042,000.00
E Overhead & Profil 11% 176,800.00 204,200.00
F Harga Satuan Pekerjaan (D+E) 1,944,800.00 2,246,200.00
BILL OF QUANTITY

JUDUL PROYEK : RUMAH TINGGAL TYPE 21


TEMPAT PROYEK : SEMARANG
KONSULTAN : PT JAYA ABADI
KONTRAKTOR : PT MEGA JAYA
NO SNI KODE URAIAN PEKERJAAN KUANTITAS SAT

I 03-2835-2002 A.2.2. 1 PEKERJAAN PERSIAPAN


A.2.2.1 .2 Pagar Sementara BJLS 0,18 panjang 108 cm 91,4 m'
A.2.2.1 .4 Pengukuran dan Pemasangan Bouwplank 26 m2
A.2.2.1 .7 Pembuatan Gudang Semen dan Peralatan 2 m2
A.2.2.1 .9 Membersihkan Lapangan dan Peralatan 66 m2
A.2.2.1 .10 Pembuatan Pagar Steger/Perancah dari Bambu Uk.40x60x20cm 1 Ls
A.2.2.1 .7 Penyedian Air dan Listrik Kerja 1 Ls
II 03-6861.1-2002 A.2.3.1 PEKERJAAN TANAH
A.2.3.1.1 Menggali Tanah Pondasi 28,97 m3
A.2.3.1.9 Pengurugan Kembali di hitung dari 1/3 kali Koefisien Pekerjaan Galian 9.476 m3
A.2.3.1.10 Urugan di bawah Lantai 7,74 m3
A.2.3.1.11 Urugan Pasir 1.575 m3

III 03-6861.1-2002 A.3.2.1 PEKERJAAN PONDASI


A.3.2.1.3 Pemasangan Pondasi Batu Kali 13.568 m3
A.3.2.1.9 Pemasangan Batu Kosong/Aanstamping 6.708 m3

IV 03-2445 1991 A.4.6.1 PEKERJAAN KUSEN


A.4.6.1.1 Volume Kusen 12.3 m3
A.4.6.1.6 Pekerjaan Pintu 7.9 m2
A.4.6.1.6 Pekerjaan Jendela 7.4 m2

V 03-6861.2-2002 A.4.6.2 PEKERJAAN KUNCI DAN KACA


A.4.6.2.5 Pemasangan Engsel Pintu 8 bh
A.4.6.2.2 Pemasangan Kunci Pintu 4 bh
A.4.6.2.6 Pemasangan Engsel Jendela 6 bh
A.4.6.2.6 Pemasangan Grendel Jendela 3 bh
A.4.6.2.9 Pemasangan Penyangga Jendela 6 bh
A.4.6.2.16 Pemasangan Kaca Jendela 2.125 m2

VI 03-6861.1-2002 A.4.4.1 PEKERJAAN DINDING, PLESTERAN, DAN ACIAN


03-6862-2002 A.4.4.1.1 Pekerjaan Dinding 1:2 11,31 m2
A.4.4.1.4 Pekerjaan Dinding 1:5 44,98 m2
A.4.4.2.2 Pekerjaan Plesteran Dinding 1:2 12,42 m2
A.4.4.2.5 Pekerjaan Plesteran Dinding 1:5 79,88 m2
A.4.4.2.23 Pekerjaan Plesteran Tali Air 77,31 m2
A.4.4.2.27 Pekerjaan Acian 88,4 m2

VII 03-2834-2000 A.4.1.1 PEKERJAAN BETON


A.4.1.1.21 Pekerjaan Sloof 1 m3
A.4.1.1.21 Pemasangan Bekesting Sloof 12 m2
A.4.1.1.22 Pekerjaan Kolom 1 m3
A.4.1.1.22 Pemasangan Bekesting Kolom 1,02 m2
A.4.1.1.23 Pemasangan Balok Latey 1 m3
A.4.1.1.23 Pemasangan Plat Leufel 0,093 m3
A.4.1.1.23 Pemasangan Bekestig Plat Leufel 0,043 m2

VIII 03-6861.2-2002 A.4.2.1 PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.1 Pemasangan Tulangan Sloof 24.9 Kg
A.4.2.1.2 Pemasangan Tulangan Kolom 18.2 Kg

IX 03-6861.1-2002 A.4.2.1 PEKERJAAN RANGKA ATAP


A.4.2.1.22 Pekerjaan Kuda-Kuda Baja Ringan 28,4 m2
A.4.2.1.23 Pekerjaan Usuk / Reng 37,8 m2

X 03-6861.1-2002 A.4.5.2 PEKERJAAN PENUTUP ATAP


A.4.5.2.1 Pemasangan Genteng 37,8 m2
A.4.5.2.38 Pemasangan Genteng Kerpus 28,4 m2

XI 03-6861.1-2002 A.4.5.1 PEKERJAAN LANGIT-LANGIT


A.4.5.1.6 Pekerjaan Rangka Plafon (Hollow) 20,27 m2
A.4.5.1.7 Pekerjaan Penutup Plafon 20,27 m2

XII 03-6862-2002 A.4.4.3 PEKERJAAN PENUTUP LANTAI & DINDING


A.4.4.3.34 Pemasangan Keramik Polos Uk.30x30 17,34 m2
A.4.4.3.34 Pemasangan Keramik Tekstur Uk.30x30 2,93 m2
A.4.4.3.54 Pemasangan Keramik Dinding KM Uk.30x30 7,42 m2
A.4.4.3.39 Pemasangan Lis Keramik KM Uk.10x30 11,8 m2
A.4.4.3.58 Pemasangan Batu Alam 4,035 m2

XIII 03-2408-1991 A.4.7.1 PEKERJAAN PENGECATAN


A.4.7.1.4 Pekerjaan Pengecatan Kusen 14.9 m2
A.4.7.1.4 Pekerjaan Pengecatan Pintu 11.2 m2
A.4.7.1.4 Pekerjaan Pengecatan Jendela 85.9 m2
A.4.7.1.10 Pekerjaan Pengecatan Dinding Eksterior 17.6 m2
A.4.7.1.10 Pekerjaan Pengecatan Dinding Interior 22.8 m2

XIV Peraturan Umum A.8.4.6 PEKERJAAN INSTALASI LISTRIK


Instalasi Listrik
A.8.4.6.1 Pemasangan Lampu Down Light 3 bh
A.8.4.6.1 Pemasangan Lampu Halogen 4 bh
A.8.4.6.1 Pemasangan Lampu Taman 2 bh
A.8.4.6.1 Pemasangan Lampu Gantung 1 bh
A.8.4.6.1 Pemasangan Saklar Tunggal T= +120cm 2 bh
A.8.4.6.1 Pemasangan Saklar Double T= +120cm 1 bh
A.8.4.6.1 Pemasangan Saklar Triple T= +120cm 2 bh
A.8.4.6.1 Pemasangan Stop Kontak Atas T= +120cm 2 bh
A.8.4.6.1 Pemasangan Stop Kontak Bawah T= +40cm 4 bh
A.8.4.6.1 Pemasangan Kontak TV T= +40cm 1 bh
A.8.4.6.1 Pemasangan Saklar AC 1 bh
A.8.4.6.1 Pemasangan Indoor AC 1 bh
A.8.4.6.2 Pemasangan MCB 1 bh
A.8.4.6.2 Pemasangan Box Meteran 1 bh

XV 03-6861.3-2002 A.5.1.1 PEKERJAAN SANITASI


A.5.1.1.25 Pemasangan Pipa Ø1/2 " 25.2 m'
A.5.1.1.24 Pemasangan Pipa Ø4" 4 m'
A.5.1.1.19 Pemasangan Kran Panas Dingin 2 bh
A.5.1.1.19 Pemasangan Kran Tempel 4 bh
A.5.1.1.8 Pemasangan Bak Mandi 1 bh
A.5.1.1.14 Pemasangan Floor Drain 1 bh
A.5.1.1.1 Pemasangan Closet Duduk 1 bh
A.5.1.1.1 Pemasangan Jet Flash 1 bh
A.5.1.1.26 Pemasangan septictank 1 Ls
DAFTAR HARGA SATUAN BAHAN BANGUNAN
SUMBER DATA : PASARAN BEBAS
DAERAH : KOTA SEMARANG & SEKITAR
EDISI 2019
NO URAIAN SATUAN HAEGA SATUAN KETERANGAN
(Rp)
a b c d e
I. BAHAN DASAR
1 BATU KALI
Bulat Belah m3 320,000.00
2 KERIKIL
Beton 0,5/1 m3 380,000.00
3 BATU BATA
ex lokal bh 650.00
4 PASIR
Urug m3 220,000.00
Pasang m3 370,000.00
Beton m3 380,000.00
5 TANAH
Padas m3 150,000.00
6 KAPUR
Pasang m3 310,000.00
7 PORTLAND CEMENT
Merk I 50 Kg Zak 60,000.00
Semen Warna Zak 15,000.00

II. BAHAN PENUTUP ATAP


1 Genteng Plentong Super Besar 18 bh/m2 bh 8,025.00
2 Asbes Gelombang 200cmX102cmX5mm bh 115,000.00
3 Nok Kerpus Genteng bh 40,000.00
4 Seng Gelombang BJLS 0,20 panjang 180 cm Lbr 55,000.00
III BAHAN KAYU
1 Dolken sedang 8 x 10 x 400 cm m3 24,000.00
2 Kruing papan m3 8,800,000.00
3 Bambu bt 18,000.00
4 Kayu Meranti m3 125,000.00 panjang : 4m
5 Kayu Klas III (Terentang) m3 2,200,000.00

IV. BAHAN PENUTUP DINDING/LANTAI


1 Keramik 30 X 30 cm m2 78,000.00
2 Tegel Plint PC Warna 10 X 30 cm bh 5,500.00
3 Batu Tempel Hitam m2 120,000.00

V. BAHAN CETAK
1 Lubang Angin (Roster) 15 X 25 cm bh 20,000.00

VI. BAHAN BESI


1 Besi Beton Polos kg 12,000.00
2 Besi Plat (Besi Strip) kg 14,250.00
3 Hollow Galvanis Lipat tinggi 4 cm; tebal 0,3 mm btg 30,000.00 panjang : 4 m
4 Ikat Beton/Bendrat kg 21,000.00
5 Baja Ringan type CT 75 lebar:7,5cm tebal:0,75mm btg 115,000.00 panjang : 6 m

VII. BAHAN PIPA


1 Pipa Galvanis Ø 1/2 '' btg 26,666.00 panjang : 6 m
2 Pipa Galvanis Ø 4 '' btg 243,750.00 panjang : 6 m

VIII. BAHAN LANGIT-LANGIT


1 Gypsum tebal 9 mm lbr 68,000.00
2 Plywood tebal 9mm lbr 125,000.00

IX. BAHAN FINISHING


1 KAYU
Ambril/amplas lbr 4,100.00
Plitur Jadi ltr 65,000.00
2 TEMBOK
Cat Tembok kg 26,000.00
Plamur kg 32,000.00
3 BESI
Cat Mengkilat kg 69,000.00

X. BAHAN KACA
1 Polos tebal 5 mm m2 95,000.00

XI. BAHAN INSTALASI LISTRIK


1 Kabel Listrik
N Y A (SPLN LMK) 1x2 1/2 m' 6,200.00
N Y M (Prima) 2 x2 1/2 m' 12,000.00
2 SKAKELAR
Out bauw Seri bh 25,000.00
Engkel bh 20,000.00
In bauw Seri bh 25,000.00
Engkel bh 17,500.00
3 FUSE BOX (SEKERING KASA)
1 group bh 165,000.00
4 STEKER
T Biasa bh 15,500.00
5 FITTING
Flaon bh 25,000.00
6 STOP KONTAK
Arde Out bauw putih bh 30,000.00

XII. ALAT-ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM
Yale : 1 slag bh 150,000.00
2 ENGSEL DAN GRENDEL
Engsel angin bh 30,000.00
Grendel Biasa bh 10,000.00
Kait Angin bh 20,000.00
Door Stop bh 350,000.00

XIII. BAHAN SANITAIR


1 KLOSET DUDUK bh 1,850,000.00
2 WASTAFEL BAK CUCI bh 165,000.00
3 TEMPAT SABUN TANAM bh 25,000.00
4 LAIN - LAIN
5 Kran Air bh 45,000.00
6 Seal Tape bh 4,500.00
7 Floor Drain bh 42,500.00

XIV. ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4'' Kg 17,500.00
2 MUR BAUT (kuda-kuda) Kg 14,000.00
3 ANGKUR BAUT bh 13,500.00
4 LEM KAYU bh 20,000.00
5 Tali Ijuk Kg 7,200.00

XV. POMPA AIR


1 POMPA AIR LISTRIK
Sanyo 100 Watt bh 1,100,000.00

XVI. PAVING BLOCK


1 SQUARE Abu-abu m2 90,000.00

XVII LAIN-LAIN
1 Minyak Bekesting Ltr 10,000.00
HARGA SATUAN UPAH PEKERJA
SUMBER DATA : PASARAN BEBAS
DAERAH : KOTA SEMARANG & SEKITAR
EDISI 2019
HARGA
NO URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 80,000.00 90,000.00
2 Mandor Hr 125,000.00 135,000.00
3 Tukang Listrik Hr 120,000.00 130,000.00
4 Tukang Kayu Hr 120,000.00 130,000.00
5 Tukang Batu Hr 125,000.00 130,000.00
6 Tukang Besi Hr 125,000.00 130,000.00
7 Tukang Cat Hr 125,000.00 130,000.00
8 Tukang Gali Hr 80,000.00 90,000.00
9 Tukang Ledeng Hr 130,000.00 140,000.00
KURVA S
JUDUL PROYEK : RUMAH TINGGAL TYPE 21
TEMPAT PROYEK : SEMARANG

NO URAIAN PEKERJAAN JUMLAH HARGA TOTAL HARGA Rp.

I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm 25,295,864.00
Pengukuran dan Pemasangan Bouwplank 3,678,675.00
Pembuatan Gudang Semen dan Peralatan 1,162,260.00
Membersihkan Lapangan dan Peralatan 1,143,450.00
Pembuatan Pagar Steger/Perancah dari Bambu Uk.40x60x20cm 418,648.12
Sub Total 31,698,897.12
II PEKERJAAN TANAH
Menggali Tanah Pondasi 2,774,819.03
Pengurugan Kembali di hitung dari 1/3 kali Koefisien Pekerjaan Galian 539,421.30
Urugan Pasir 506,496.38
Sub Total 3,820,736.70
III PEKERJAAN PONDASI
Pemasangan Pondasi Batu Kali 12,027,150.08
Pemasangan Batu Kosong/Aanstamping 4,465,686.65
Sub Total 16,492,836.73
IV PEKERJAAN KUSEN
Pekerjaan Pintu 2,371,935.50
Pekerjaan Jendela 2,059,013.00
Sub Total 4,430,948.50
V PEKERJAAN KUNCI DAN KACA
Pemasangan Engsel Pintu 271,590.00
Pemasangan Kunci Pintu 952,930.00
Pemasangan Engsel Jendela 135,795.00
Pemasangan Grendel Jendela 71,197.50
Pemasangan Penyangga Jendela 276,738.00
Pemasangan Kaca Jendela 293,242.30
Sub Total 2,001,492.80
VI PEKERJAAN DINDING, PLESTERAN, DAN ACIAN
Pekerjaan Dinding 1:2 3,195,470.85
Pekerjaan Dinding 1:5 #VALUE!
Pekerjaan Plesteran Dinding 1:2 #VALUE!
Pekerjaan Plesteran Dinding 1:5 #VALUE!
Pekerjaan Plesteran Tali Air #VALUE!
Pekerjaan Acian #VALUE!
Sub Total 27,540,512.64
VII PEKERJAAN BETON
Pekerjaan Sloof 110,424.38
Pemasangan Bekesting Sloof 2,522,652.00
Pekerjaan Kolom 134,460.76
Pemasangan Bekesting Kolom #VALUE!
Pemasangan Balok Latey 110,424.38
Pemasangan Plat Leufel 7,771,219.50
Pemasangan Bekestig Plat Leufel 14,248,415.50
Sub Total 3,245,282.26
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof 2,749,567.06
Pemasangan Tulangan Kolom 2,447,185.74
Sub Total 5,196,752.80
IX PEKERJAAN RANGKA ATAP
Pekerjaan Kuda-Kuda Baja Ringan 7,867,950.20
Pekerjaan Usuk / Reng 7,478,370.90
Sub Total 15,346,321.10
X PEKERJAAN PENUTUP ATAP
Pemasangan Genteng 919,674.00
Pemasangan Genteng Kerpus 3,759,109.20
Sub Total 4,678,783.20
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) 5,204,788.71
Pekerjaan Penutup Plafon 8,147,992.71
Sub Total 13,352,781.42
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 20,795,142.39
Pemasangan Keramik Tekstur Uk.30x30 9,138,607.01
Pemasangan Keramik Dinding KM Uk.30x30 18,441,998.19
Pemasangan Lis Keramik KM Uk.10x30 2,128,109.94
Pemasangan Batu Alam 1,198,010.00
SUB Total 51,701,867.53
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Kusen 724,192.15
Pekerjaan Pengecatan Pintu 625,671.20
Pekerjaan Pengecatan Jendela 4,798,674.65
Pekerjaan Pengecatan Dinding Eksterior 423,112.80
Pekerjaan Pengecatan Dinding Interior 1,565,375.90
Sub Total 8,137,026.70
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan Lampu 4,315,080.00
Pemasangan MCB 536,448.00
Sub Total 4,851,528.00
XV PEKERJAAN SANITASI
Pemasangan Pipa Ø1/2 " 1,705,813.96
Pemasangan Pipa Ø4" 1,848,693.00
Pemasangan Kran 650,669.25
Pemasangan Bak Mandi 1,415,205.00
Pemasangan Floor Drain 109,532.50
Pemasangan Closet Duduk 2,246,200.00
Pemasangan Septictank 7,000,000.00
Sub Total 14,976,113.71
RENCANA TIME SCHEDULE
JUDUL PROYEK : RUMAH TINGGAL TYPE 21
TEMPAT PROYEK : SEMARANG
KONSULTAN : PT JAYA ABADI
KONTRAKTOR : PT MEGA JAYA
MARET APRIL MEI JUNI
NO URAIAN PEKERJAAN TOTAL HARGA Rp. BOBOT PEK. 3/4/2019 3/11/2019 ### 3/25/2019 4/1/2019 4/8/2019 4/15/2019 4/22/2019 4/29/2019 5/6/2019 5/13/2019 5/20/2019 5/27/2019 6/3/2019 6/10/2019
%
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3

I PEKERJAAN PERSIAPAN 31,698,897.12 15.28 5.53 5.60 4.14


II PEKERJAAN TANAH 3,820,736.70 1.84 1.84
III PEKERJAAN PONDASI 16,492,836.73 7.95 2.00 5.95
IV PEKERJAAN KUSEN 4,430,948.50 2.14 2.14
V PEKERJAAN KUNCI DAN KACA 2,001,492.80 0.96 0.96

VI PEKERJAAN DINDING,PLESTERAN DAN ACIAN 27,540,512.64 13.27 2.88 7.55 2.85

VII PEKERJAAN BETON 3,245,282.26 1.56 1.22 0.28 0.06


VIII PEKERJAAN BESI DAN ALUMUNIUM 5,196,752.80 2.50 0.58 1.93
IX PEKERJAAN RANGKA ATAP 15,346,321.10 7.40 3.79 1.85 1.75
X PEKERJAAN PENUTUP ATAP 4,678,783.20 2.26 2.26
XII PEKERJAAN LANGIT-LANGIT 13,352,781.42 6.44 0.68 4.83 0.93
XII PEKERJAAN PENUTUP LANTAI&DINDING 51,701,867.53 24.92 5.69 6.63 6.68 5.04 0.88
XIII PEKERJAAN PENGECATAN 8,137,026.70 3.92 0.65 3.27
XIV PEKERJAAN INSTALASI LISTRIK 4,851,528.00 2.34 0.26
XV PEKERJAAN SANITASI 14,976,113.71 7.22 1.69 1.68 0.68 1.71
TOTAL 207,471,881.21 100.00

Kemajuan Pek.
Rencana
Mingguan %
5.53 5.60 5.83 6.74 6.82 7.91 8.23 6.71 6.50 6.58 6.62 6.63 6.68 5.69 4.41
Kemajuan Pek. 0.00
Kumulatif %
5.53 11.13 16.96 23.70 30.52 38.43 46.65 53.36 59.86 66.44 73.06 79.69 86.37 92.06 96.47
NA TIME SCHEDULE

JUNI
6/17/2019
4

2.08
1.45

3.53

100.00
RENCANA ANGGARAN BIAYA (RAB)
JUDUL PROYEK : RUAMH TINGGAL TYPE 21
TEMPAT PROYEK : SEMARANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm m' 91,4 276,760.00 25,295,864.00
Pengukuran dan Pemasangan Bouwplank m2 26 141,487.50 3,678,675.00
Pembuatan Gudang Semen dan Peralatan m2 2 581,130.00 1,162,260.00
Membersihkan Lapangan dan Peralatan m2 66 17,325.00 1,143,450.00
Pembuatan Pagar Steger/Perancah dari Bambu Uk.40x60x20cm Ls 1 418,648.12 418,648.12
Sub Total
II PEKERJAAN TANAH
Menggali Tanah Pondasi m3 28,97 95,782.50 2,774,819.03
Pengurugan Kembali di hitung dari 1/3 kali Koefisien Pekerjaan Galian m3 9.476 56,925.00 539,421.30
Urugan Pasir m3 1.575 321,585.00 506,496.38
Sub Total
III PEKERJAAN PONDASI
Pemasangan Pondasi Batu Kali m3 13.57 886,435.00 12,027,150.08
Pemasangan Batu Kosong/Aanstamping m3 6.71 665,725.50 4,465,686.65
Sub Total
IV PEKERJAAN KUSEN
Pekerjaan Pintu m2 7.9 300,245.00 2,371,935.50
Pekerjaan Jendela m2 7.4 278,245.00 2,059,013.00
Sub Total
V PEKERJAAN KUNCI DAN KACA
Pemasangan Engsel Pintu bh 8 33,948.75 271,590.00
Pemasangan Kunci Pintu bh 4 238,232.50 952,930.00
Pemasangan Engsel Jendela bh 6 22,632.50 135,795.00
Pemasangan Grendel Jendela bh 3 23,732.50 71,197.50
Pemasangan Penyangga Jendela bh 6 46,123.00 276,738.00
Pemasangan Kaca Jendela m2 2.125 137,996.38 293,242.30
Sub Total
VI PEKERJAAN DINDING, PLESTERAN, DAN ACIAN
Pekerjaan Dinding 1:2 m2 11,31 282,535.00 #VALUE!
Pekerjaan Dinding 1:5 m2 44,98 263,373.00 #VALUE!
Pekerjaan Plesteran Dinding 1:2 m2 12,42 75,013.18 #VALUE!
Pekerjaan Plesteran Dinding 1:5 m2 79,88 70,802.38 #VALUE!
Pekerjaan Plesteran Tali Air m2 77,31 30,865.56 #VALUE!
Pekerjaan Acian m2 88,4 39,875.00 #VALUE!
Sub Total
VII PEKERJAAN BETON
Pekerjaan Sloof m3 1 110,424.38 110,424.38
Pemasangan Bekesting Sloof m2 12 210,221.00 2,522,652.00
Pekerjaan Kolom m3 1 134,460.76 134,460.76
Pemasangan Bekesting Kolom m2 1,02 338,530.50 #VALUE!
Pemasangan Balok Latey m3 1 110,424.38 110,424.38
Pemasangan Plat Leufel m3 0,093 83,561.50 7,771,219.50
Pemasangan Bekestig Plat Leufel m2 0,043 331,358.50 14,248,415.50
Sub Total
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof Kg 24.9 110,424.38 2,749,567.06
Pemasangan Tulangan Kolom Kg 18.2 134,460.76 2,447,185.74
Sub Total
IX PEKERJAAN RANGKA ATAP
Pekerjaan Kuda-Kuda Baja Ringan m2 28,4 277,040.50 7,867,950.20
Pekerjaan Usuk / Reng m2 37,8 197,840.50 7,478,370.90
Sub Total

X PEKERJAAN PENUTUP ATAP


Pemasangan Genteng m2 37,8 24,330.00 919,674.00
Pemasangan Genteng Kerpus m2 28,4 132,363.00 3,759,109.20
Sub Total
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) m2 20,27 256,773.00 5,204,788.71
Pekerjaan Penutup Plafon m2 20,27 401,973.00 8,147,992.71
Sub Total
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 m2 17,34 1,199,258.50 20,795,142.39
Pemasangan Keramik Tekstur Uk.30x30 m2 2,93 3,118,978.50 9,138,607.01
Pemasangan Keramik Dinding KM Uk.30x30 m2 7,42 2,485,444.50 18,441,998.19
Pemasangan Lis Keramik KM Uk.10x30 m2 11,8 180,348.30 2,128,109.94
Pemasangan Batu Alam m2 4 299,502.50 1,198,010.00
SUB Total
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Kusen m2 14.9 48,603.50 724,192.15
Pekerjaan Pengecatan Pintu m2 11.2 55,863.50 625,671.20
Pekerjaan Pengecatan Jendela m2 85.9 55,863.50 4,798,674.65
Pekerjaan Pengecatan Dinding Eksterior m2 17.6 24,040.50 423,112.80
Pekerjaan Pengecatan Dinding Interior m2 22.8 68,777.50 1,565,375.90
Sub Total
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan Lampu bh 10 431,508.00 4,315,080.00
Pemasangan MCB bh 1 536,448.00 536,448.00
Sub Total
XV PEKERJAAN SANITASI
Pemasangan Pipa Ø1/2 " m' 25.2 67,691.03 1,705,813.96
Pemasangan Pipa Ø4" m' 4 462,173.25 1,848,693.00
Pemasangan Kran bh 6 108,444.88 650,669.25
Pemasangan Bak Mandi bh 1 1,415,205.00 1,415,205.00
Pemasangan Floor Drain bh 1 109,532.50 109,532.50
Pemasangan Closet Duduk bh 1 2,246,200.00 2,246,200.00
Pemasangan Septictank Ls 1 7,000,000.00 7,000,000.00
Sub Total
TOTAL HARGA Rp.

31,698,897.12

3,820,736.70

16,492,836.73

4,430,948.50
2,001,492.80

27,540,512.64

3,245,282.26

5,196,752.80

15,346,321.10
4,678,783.20

13,352,781.42

51,701,867.53

8,137,026.70

4,851,528.00
14,976,113.71
LAPORAN MINGGUAN
PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender
LOKASI : SEMARANG SISA WAKTU : 90 Hari Kalender
TAHUN : 2019 MINGGU KE : 1
PERIODE : 04/03/2019 - 11/03/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm 12.19 0 0 25 3.05 25 3.05
Pengukuran dan Pemasangan Bouwplank 1.77 0 0 50 0.89 50 0.89
Pembuatan Gudang Semen dan Peralatan 0.56 0 0 100 0.56 100 0.56
Membersihkan Lapangan dan Peralatan 0.55 0 0 100 0.55 100 0.55

TOTAL 15.08 0 5.05 5.05


RENCANA PRESTASI PEKERJAAN (%) 0 5.53 5.53
REALISASI PRESTASI PEKERJAAN (%) 0 5.05 5.05
DEVIASI 0 -0.49 -0.49
KESIMPULAN TERLAMBAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas


PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender
LOKASI : SEMARANG SISA WAKTU : 84 Hari Kalender
TAHUN : 2019 MINGGU KE : 2
PERIODE : 11/03/2019 - 18/03/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm 12.19 25 3.05 75 9.14 75 9.14
Pengukuran dan Pemasangan Bouwplank 1.77 50 0.89 100 1.77 100 1.77

TOTAL 13.97 3.93 10.92 10.92


RENCANA PRESTASI PEKERJAAN (%) 5.53 5.60 5.60
REALISASI PRESTASI PEKERJAAN (%) 5.05 10.92 10.92
DEVIASI -0.49 5.32 5.32
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas


PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender
LOKASI : SEMARANG SISA WAKTU : 78 Hari Kalender
TAHUN : 2019 MINGGU KE : 3
PERIODE : 18/03/2019 - 25/03/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
I PEKERJAAN PERSIAPAN
Pagar Sementara BJLS 0,18 panjang 108 cm 12.19 75 9.14 100 12.19 100 12.19
Pemasangan Septictank 3.37 0 0 50 1.69 50 1.69

TOTAL 15.57 9.14 13.88 13.88


RENCANA PRESTASI PEKERJAAN (%) 5.60 5.83 5.83
REALISASI PRESTASI PEKERJAAN (%) 10.92 13.88 13.88
DEVIASI 5.32 8.05 8.05
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis
Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 72 Hari Kalender
TAHUN : 2019 MINGGU KE : 4
PERIODE : 25/03/2019 - 01/04/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
I PEKERJAAN PERSIAPAN
Pembuatan Pagar Steger/Perancah dari Bambu 0.20
Uk.40x60x20cm 0 0 100 0.20 100 0.20
II PEKERJAAN TANAH
Menggali Tanah Pondasi 1.34 0 0 100 1.34 100 1.34
Pengurugan Kembali di hitung dari 1/3 kali Koefisien 0.26
Pekerjaan Galian 0 0 100 0.26 100 0.26
Urugan Pasir 0.24 0 0 100 0.24 100 0.24
III PEKERJAAN PONDASI
Pemasangan Pondasi Batu Kali 5.80 0 0 50 2.90 50 2.90
VII PEKERJAAN BETON
Pemasangan Bekesting Sloof 1.22 0 0 100 1.22 100 1.22
XV PEKERJAAN SANITASI
Pemasangan Septictank 3.37 50 1.69 100 3.37 100 3.37

TOTAL 12.43 1.69 9.53 9.53


RENCANA PRESTASI PEKERJAAN (%) 5.83 6.74 6.74
REALISASI PRESTASI PEKERJAAN (%) 13.88 9.53 9.53
DEVIASI 8.05 2.79 2.79
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 66 Hari Kalender
TAHUN : 2019 MINGGU KE : 5
PERIODE : 01/04/2019 - 08/04/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
III PERKEJAAN PONDASI
Pemasangan Pondasi Batu Kali 5.80 50 2.90 100 5.80 100 5.80
Pemasangan Batu Kosong/Aanstamping 2.15 0 0 100 2.15 100 2.15
VII PEKERJAAN BETON
Pekerjaan Sloof 0.05 0 0 100 0.05 100 0.05
Pekerjaan Kolom 0.06 0 0 100 0.06 100 0.06
Pemasangan Bekesting Kolom 0.17 0 0 100 0.17 100 0.17
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof 1.33 0 0 50 0.66 50 0.66

TOTAL 9.56 2.90 8.90 8.90


RENCANA PRESTASI PEKERJAAN (%) 6.74 6.82 6.82
REALISASI PRESTASI PEKERJAAN (%) 9.53 8.90 8.90
DEVIASI 2.79 2.08 2.08
KESIMPULAN LEBIH CEPAT
Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 60 Hari Kalender
TAHUN : 2019 MINGGU KE : 6
PERIODE : 08/04/2019 - 15/04/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
IV PEKERJAAN KUSEN
Pekerjaan Pintu 1.14 0 0 100 1.14 100 1.14
Pekerjaan Jendela 0.99 0 0 100 0.99 100 0.99
v PEKERJAAN KUNCI DAN KACA
Pemasangan Engsel Pintu 0.13 0 0 100 0.13 100 0.13
Pemasangan Kunci Pintu 0.46 0 0 100 0.46 100 0.46
Pemasangan Engsel Jendela 0.07 0 0 100 0.07 100 0.07
Pemasangan Grendel Jendela 0.03 0 0 100 0.03 100 0.03
Pemasangan Penyangga Jendela 0.13 0 0 100 0.13 100 0.13
Pemasangan Kaca Jendela 0.14 0 0 100 0.14 100 0.14
VI PEKERJAAN DINDING,PLESTERAN DAN ACIAN
Pekerjaan Dinding 1:2 1.54 0 0 50 0.77 50 0.77
Pekerjaan Dinding 1:5 5.71 0 0 50 2.85 50 2.85
VIII PEKERJAAN BESI DAN ALUMUNIUM
Pemasangan Tulangan Sloof 1.33 50 0.66 100 1.33 100 1.33
Pemasangan Tulangan Kolom 1.18 0 0 100 1.18 100 1.18

TOTAL 12.86 0.66 9.23 9.23


RENCANA PRESTASI PEKERJAAN (%) 6.82 7.91 7.91
REALISASI PRESTASI PEKERJAAN (%) 8.90 9.23 9.23
DEVIASI 2.08 1.32 1.32
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 54 Hari Kalender
TAHUN : 2019 MINGGU KE : 7
PERIODE : 15/04/2019 - 22/04/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
VI PEKERJAAN DINDING,PLESTERAN, DAN ACIAN
Pekerjaan Dinding 1:2 1.54 50 0.77 100 1.54 100 1.54
Pekerjaan Dinding 1:5 5.71 50 2.85 100 5.71 100 5.71
Pekerjaan Plesteran Dinding 1:2 0.45 0 0 100 0.45 100 0.45
Pekerjaan Plesteran Dinding 1:5 2.73 0 0 100 2.73 100 2.73
XV PEKERJAAN SANITASI
Pemasangan Bak Mandi 0.68 0 0 100 0.68 100 0.68

TOTAL 11.11 3.63 11.11 11.11


RENCANA PRESTASI PEKERJAAN (%) 7.91 8.23 8.23
REALISASI PRESTASI PEKERJAAN (%) 9.23 11.11 11.11
DEVIASI 1.32 2.88 2.88
KESIMPULAN LEBIH CEPAT
Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 48 Hari Kalender
TAHUN : 2019 MINGGU KE : 8
PERIODE : 22/04/2019B - 29/04/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
VI PEKERJAAN DINDING,PLESTERAN,DAN ACIAN
Pekerjaan Plesteran Tali Air 1.15 0 0 100 1.15 100 1.15
Pekerjaan Acian 1.70 0 0 100 1.70 100 1.70
VIII PEKERJAAN BETON
Pemasangan Balok Latey 0.05 0 0 100 0.05 100 0.05
Pemasangan Plat Leufel 0.00 0 0 100 0.00 100 0.00
Pemasangan Bekestig Plat Leufel 0.01 0 0 100 0.01 100 0.01
IX PEKERJAAN RANGKA ATAP
Pekerjaan Kuda-Kuda Baja Ringan 3.79 0 0 100 3.79 100 3.79
Pekerjaan Usuk / Reng 3.60 0 0 50 1.80 50 1.80

TOTAL 10.31 0.00 8.51 8.51


RENCANA PRESTASI PEKERJAAN (%) 8.23 6.71 6.71
REALISASI PRESTASI PEKERJAAN (%) 11.11 8.51 8.51
DEVIASI 2.88 1.80 1.80
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 42 Hari Kalender
TAHUN : 2019 MINGGU KE : 9
PERIODE : 29/04/2019 - 06/05/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
IX PEKERJAAN RANGKA ATAP
Pekerjaan Usuk / Reng 3.60 50 1.80 100 3.60 100 3.60
X PEKERJAAN PENUTUP ATAP
Pemasangan Genteng 0.44 0 0 100 0.44 100 0.44
Pemasangan Genteng Kerpus 1.81 0 0 100 1.81 100 1.81
IX PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) 2.51 0 0 50 1.25 50 1.25
XV PEKERJAAN SANITASI
Pemasangan Pipa Ø1/2 " 0.82 0 0 100 0.82 100 0.82
Pemasangan Pipa Ø4" 0.89 0 0 100 0.89 100 0.89
TOTAL 10.08 1.80 8.83 8.83
RENCANA PRESTASI PEKERJAAN (%) 6.71 6.50 6.50
REALISASI PRESTASI PEKERJAAN (%) 8.51 8.83 8.83
DEVIASI 1.80 2.33 2.33
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 36 Hari Kalender
TAHUN : 2019 MINGGU KE : 10
PERIODE : 06/05/2019 - 13/05/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Rangka Plafon (Hollow) 2.51 50 1.25 100 2.51 100 2.51
Pekerjaan Penutup Plafon 3.93 0 0 50 1.96 50 1.96

TOTAL 6.44 1.25 4.47 4.47


RENCANA PRESTASI PEKERJAAN (%) 6.50 6.58 6.58
REALISASI PRESTASI PEKERJAAN (%) 8.83 4.47 4.47
DEVIASI 2.33 -2.11 -2.11
KESIMPULAN TERLAMBAT
Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 30 Hari Kalender
TAHUN : 2019 MINGGU KE : 11
PERIODE : 13/05/2019 - 20/05/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XI PEKERJAAN LANGIT-LANGIT
Pekerjaan Penutup Plafon 3.93 50 1.96 100 3.93 100 3.93
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 10.02 0 0 25 2.51 25 2.51

TOTAL 13.95 1.96 6.43 6.43


RENCANA PRESTASI PEKERJAAN (%) 6.58 6.62 6.62
REALISASI PRESTASI PEKERJAAN (%) 4.47 6.43 6.43
DEVIASI -2.11 -0.19 -0.19
KESIMPULAN TERLAMBAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 24 Hari Kalender
TAHUN : 2019 MINGGU KE : 12
PERIODE : 20/05/2019 - 27/05/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 10.02 25 2.51 75 7.52 75 7.52
Pemasangan Keramik Tekstur Uk.30x30 4.40 0 0 50 2.20 50 2.20
TOTAL 14.43 2.51 9.72 9.72
RENCANA PRESTASI PEKERJAAN (%) 6.62 6.63 6.63
REALISASI PRESTASI PEKERJAAN (%) 6.43 9.72 9.72
DEVIASI -0.19 3.09 3.09
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 18 Hari Kalender
TAHUN : 2019 MINGGU KE : 13
PERIODE : 27/05/2019 - 03/06/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Polos Uk.30x30 10.02 75 7.52 100 10.02 100 10.02
Pemasangan Keramik Tekstur Uk.30x30 4.40 50 2.20 100 4.40 100 4.40
Pemasangan Keramik Dinding KM Uk.30x30 8.89 0 0 25 2.22 25 2.22

TOTAL 23.32 9.72 16.65 16.65


RENCANA PRESTASI PEKERJAAN (%) 6.63 6.68 6.68
REALISASI PRESTASI PEKERJAAN (%) 9.72 16.65 16.65
DEVIASI 3.09 9.97 9.97
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 12 Hari Kalender
TAHUN : 2019 MINGGU KE : 14
PERIODE : 03/06/2019 - 10/06/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Dinding KM Uk.30x30 8.89 25 2.22 75 6.67 75 6.67
Pemasangan Lis Keramik KM Uk.10x30 1.03 0 0 100 1.03 100 1.03
Pemasangan Batu Alam 0.58 0 0 100 0.58 100 0.58
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Kusen 0.35 0 0 100 0.35 100 0.35
Pekerjaan Pengecatan Pintu 0.30 0 0 100 0.30 100 0.30

TOTAL 11.14 2.22 8.92 8.92


RENCANA PRESTASI PEKERJAAN (%) 6.68 5.69 5.69
REALISASI PRESTASI PEKERJAAN (%) 16.65 8.92 8.92
DEVIASI 9.97 3.23 3.23
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 6 Hari Kalender
TAHUN : 2019 MINGGU KE : 15
PERIODE : 10/06/2019 - 17/06/2019

BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
%
NO JENIS PEKERJAAN BOBOT PEK.
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XII PEKERJAAN PENUTUP LANTAI & DINDING
Pemasangan Keramik Dinding KM Uk.30x30 8.89 75 6.67 100 8.89 100 8.89
XIII PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Jendela 2.31 0 0 100 2.31 100 2.31
Pekerjaan Pengecatan Dinding Eksterior 0.20 0 0 100 0.20 100 0.20
Pekerjaan Pengecatan Dinding Interior 0.75 0 0 100 0.75 100 0.75
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan MCB 0.26 0 0 100 0.26 100 0.26

TOTAL 12.42 6.67 12.42 12.42


RENCANA PRESTASI PEKERJAAN (%) 5.69 4.41 4.41
REALISASI PRESTASI PEKERJAAN (%) 8.92 12.42 12.42
DEVIASI 3.23 8.01 8.01
KESIMPULAN LEBIH CEPAT

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas

PEKERJAAN : RUMAH TINGGAL TYPE 21 WAKTU PELAKSANAAN : 96 Hari Kalender


LOKASI : SEMARANG SISA WAKTU : 0 Hari Kalender
TAHUN : 2019 MINGGU KE : 16
PERIODE : 17/06/2019
BOBOT PEK. S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO JENIS PEKERJAAN
% PRESENTASE BOBOT % PRESENTASE BOBOT % PRESENTASE BOBOT %
XIV PEKERJAAN INSTALASI LISTRIK
Pemasangan Lampu 2.08 0 0 100 2.08 100 2.08
XV PEKERJAAN SANITASI
Pemasangan Kran 0.31 0 0 100 0.31 100 0.31
Pemasangan Floor Drain 0.05 0 0 100 0.05 100 0.05
Pemasangan Closet Duduk 1.08 0 0 100 1.08 100 1.08

TOTAL 3.53 0.00 3.53 3.53


RENCANA PRESTASI PEKERJAAN (%) 4.41 3.53 3.53
REALISASI PRESTASI PEKERJAAN (%) 12.42 3.53 3.53
DEVIASI 8.01 0.00 0.00
KESIMPULAN SESUAI RENCANA

Semarang,
Diperiksa Diperiksa Pelaksana
Konsultan Perencana Tim Teknis

Koman Warsito E.W S.pd Kusmunawaroh S.pd Corry Puspitaningtyas


REALISASI TIME SCHEDULE
JUDUL PROYEK : RUMAH TINGGAL TYPE 21
TEMPAT PROYEK : SEMARANG
KONSULTAN : PT JAYA ABADI
KONTRAKTOR : PT MEGA JAYA
MARET APRIL MEI JUNI
NO URAIAN PEKERJAAN TOTAL HARGA Rp. BOBOT PEK. 3/4/2019 3/11/2019 ### 3/25/2019 4/1/2019 4/8/2019 4/15/2019 4/22/2019 4/29/2019 5/6/2019 5/13/2019 5/20/2019 5/27/2019 6/3/2019 6/10/2019
%
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3

I PEKERJAAN PERSIAPAN 31,698,897.12 15.28 5.53 5.60 4.14


II PEKERJAAN TANAH 3,820,736.70 1.84 1.84
III PEKERJAAN PONDASI 16,492,836.73 7.95 2.00 5.95
IV PEKERJAAN KUSEN 4,430,948.50 2.14 2.14
V PEKERJAAN KUNCI DAN KACA 2,001,492.80 0.96 0.96

VI PEKERJAAN DINDING,PLESTERAN DAN ACIAN 27,540,512.64 13.27 2.88 7.55 2.85

VII PEKERJAAN BETON 3,245,282.26 1.56 1.22 0.28 0.06


VIII PEKERJAAN BESI DAN ALUMUNIUM 5,196,752.80 2.50 0.58 1.93
IX PEKERJAAN RANGKA ATAP 15,346,321.10 7.40 3.79 1.85 1.75
X PEKERJAAN PENUTUP ATAP 4,678,783.20 2.26 2.26
XII PEKERJAAN LANGIT-LANGIT 13,352,781.42 6.44 0.68 4.83 0.93
XII PEKERJAAN PENUTUP LANTAI&DINDING 51,701,867.53 24.92 5.69 6.63 6.68 5.04 0.88
XIII PEKERJAAN PENGECATAN 8,137,026.70 3.92 0.65 3.27
XIV PEKERJAAN INSTALASI LISTRIK 4,851,528.00 2.34 0.26
XV PEKERJAAN SANITASI 14,976,113.71 7.22 1.69 1.68 0.68 1.71
TOTAL 207,471,881.21 100.00

Kemajuan Pek.
Rencana
Mingguan %
5.53 5.60 5.83 6.74 6.82 7.91 8.23 6.71 6.50 6.58 6.62 6.63 6.68 5.69 4.41
Kemajuan Pek. 0.00
Kumulatif %
5.53 11.13 16.96 23.70 30.52 38.43 46.65 53.36 59.86 66.44 73.06 79.69 86.37 92.06 96.47
Kemajuan Pek.
Realisasi
Mingguan % 5.05 10.92 13.88 9.53 8.90 9.23 11.11 8.51 8.83 4.47 6.43 9.72 16.65 8.92 12.42
Kemajuan Pek.
0.00
Kumulatif % 5.53 11.13 16.96 23.70 30.52 38.43 46.65 53.36 59.86 66.44 73.06 79.69 86.37 92.06 96.47
Kumulatif Deviasi
-0.49 5.32 8.05 2.79 2.08 1.32 2.88 1.80 2.33 -2.11 -0.19 3.09 9.97 3.23 8.01
ASI TIME SCHEDULE

JUNI
6/17/2019
4

2.08
1.45

3.53

100.00

3.53

100.00

0.00
langkah kerja membuat kurva s
blok bobot komulatif
insert , chart, 2d line
hilangkan grid dan sumbu yang tidak di perlukan
pilih plot area, klik kanan format plot area - no fill
pilih chart area, klik kanan format chart area - no fill, border color - no line
tempatkan kurva s pada diagram batang

0 5.53 11.13 16.96 23.70 30.52 38.43 46.65 53.36 59.86


66.44 73.06 79.69 86.37 92.06 96.47 100.00