PP U
PP PEKERJAAN PERSIAPAN U UPAH
C
PT
PT PEKERJAAN TANAH C CAT
BB
PPS
PPS PEKERJAAN PASANGAN PONDASI BB BETON DAN BARANG DARI BETON
PD
PD PASANGAN DINDING PP PIPA
PB
PB PEKERJAAN BETON B
B BUIS BETON / KERB
PPT
PPT PEKERJAAN PLESTERAN PS
PS PERALATAN SANITASI
PPL
PPL PEKERJAAN PASANG LANTAI CB
CB BATA HALAMAN / PAVING BLOCK
PCB
PCB PEKERJAAN CONE BLOCK / PAVING BLOCK AS
AS ASBES
PK
PK PEKERJAAN KAYU AT
AT ATAP
PA
PA PEKERJAAN ATAP ALT
K SEWA ALAT
KP
PC
PC PEKERJAAN PENGECATAN KAPUR & GIPS
PBK LT
PBK PEKERJAAN BONGKARAN LANTAI KERAMIK, TEGEL, TERASO, UBIN
SPL
AS ANALISA SUPLEMEN KY
KY KAYU
PS
PS PEKERJAAN SANITASI TNM
TNM BAHAN TUMBUHAN
PBS
PBS PEKERJAAN BESI DAN ALUMUNIUM LS
LS LISTRIK
PPG
PPG PEKERJAAN KUNCI DAN KACA LG
LG BAHAN LOGAM BESI/BAJA TULANGAN/BESI BETON
PLS PG
PLS ANALISA HARGA SATUAN PEKERJAAN LISTRIK PG PENGGANTUNG / PENGUNCI
KPUT ASP
KPUT ANALISA KPUT ASP ASPAL
ASP
ASP ANALISA ASPAL BT
BT BATU, AGREGAT, TANAH
ALT
ALT SEWA ALAT PC
PC BAHAN PEREKAT HIDROLIS & ORGANIK
PTMN
PTMN PEKERJAAN PEMBERSIHAN TAMAN, JALAN PK
PK PAKU, BAUT
BBM
BBM BAHAN PELARUT, PELUMAS
BK
BK BAHAN KIMIA PEMBANTU UNTUK BETON
KC
KC BAHAN KACA
KB
KB PERALATAN KEBERSIHAN
LL
LL LAIN-LAIN
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
U UPAH
U 1 Tukang kayu hari 80,000.00
U 2 Tukang batu hari 80,000.00
U 3 Tukang alumunium hari 80,000.00
U 4 Tukang besi hari 80,000.00
U 5 Tukang las hari 80,000.00
U 6 Tukang cat hari 80,000.00
U 7 Tukang plitur hari 80,000.00
U 8 Tukang bor hari 80,000.00
U 9 Tukang listrik hari 80,000.00
U 10 Tukang pipa ledeng hari 80,000.00
Tukang Pancang hari 80,000.00
U 11 Kepala tukang hari 90,000.00
U 12 Tukan gali/timbun hari 80,000.00
U 13 Pekerja hari 55,000.00
U 14 Mandor hari 80,000.00
U 15 Pengawas hari 100,000.00
U 16 Ahli ukur hari 100,000.00
U 17 Asisten ahli ukur hari 100,000.00
U 18 Sopir hari 100,000.00
U 19 Masinis hari 100,000.00
U 20 Kernet / pembantu sopir hari 80,000.00
U 21 Mekanik terlatih hari 100,000.00
U 22 Operator tak terlatih hari 80,000.00
U 23 Operator terlatih hari 100,000.00
U 24 Pembantu Operator hari 80,000.00
U 25 Operator semi terlatih hari 80,000.00
U 26 Penjaga hari 80,000.00
U 27 Penyelam hari 150,000.00
U 28 Tukang Grouting hari 80,000.00
U 29 Operator mesin sondir hari 100,000.00
U 30 Analis test sondir hari 100,000.00
AS ASBES
AS 1 Asbes plat ( 100 x 100 x 0,3 ) lbr 15,100.00
AS 2 Asbes gelombang besar ( 225 x 92 x 0,5 ) lbr
AS 3 Asbes gelombang besar ( 200 x 92 x 0,5 ) lbr
AS 4 Asbes gelombang besar ( 180 x 92 x 0,5 ) lbr 29,100.00
AS 5 Asbes gelombang besar ( 240 x 108 x 0,6 ) lbr 39,100.00
AS 6 Asbes gelombang besar ( 210 x 108 x 0,6 ) lbr 34,000.00
AS 7 Asbes gelombang besar ( 180 x 108 x 0,6 ) lbr
AS 8 Asbes gelombang kecil ( 210 x 105 x 0,4 ) lbr
AS 9 Asbes gelombang kecil ( 180 x 105 x 0,4 ) lbr
AS 10 Asbes gelombang kecil ( 150 x 105 x 0,4 ) lbr
AS 11 Asbes gelombang kecil ( 240 x 105 x 0,4 ) lbr
AS 12 Asbes nok gelombang besar lbr
AS 13 Asbes nok gelombang kecil lbr
AS 14 Nok paten (Rabung) lbr
AS 15 Nok stel rata lbr
ASP ASPAL
ASP 1 Aspal cair kg 9,400.00
ASP 2 Aspal curah kg
ASP 3 Aspal drum kg
ASP 4 Aspal modifer / asphalt joint kg
ASP 5 Drum aspal bekas bh
ASP 6 Rubber Filler m1
ASP 7 Filler kg
ASP 8 Karosene ltr
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
AT GENTENG
AT 1 Genteng beton besar natural 1m 9 biji bh
AT 2 Genteng beton besar warna 1m 9 biji bh
AT 3 Genteng beton kecil natural 1m 11 biji bh
AT 4 Genteng beton kecil warna 1m 11 biji bh
AT 5 Genteng beton kecil natural 1m 20 biji bh
AT 6 Genteng beton kecil warna 1m 20 biji bh
AT 7 Genteng metal m2 184,000.00
AT 8 Genteng bubungan beton bh
AT 9 Bubung stel gelombang lbr
AT 10 Genteng bubungan warna bh
AT SENG BJLS
AT 1 Seng BJLS 0,20 gelombang P = 180 cm lbr
AT 2 Seng BJLS 0,20 gelombang P = 240 cm lbr
AT 3 Seng plat 3" x 6" BJLS 28 lbr 1,288.13
AT 4 Seng gelombang 2" - 5" BJLS 24 lbr
AT 5 Alumunium gelombang tebal 0,55 m2
AT 6 Alumunium foil m2
AT 7 Rabung alumunium standar 40 cm 18 SWG 22 m1
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
BK 3 Flincoat ltr
C CAT
C 1 Cat dasar meni kg 35,300.00
C 2 Cat tembok melamin kg 24,000.00
C 3 Cat dasar meni kayu kg 51,800.00
C 4 Cat alkali resisting primer kg
C 5 Cat ICI Weathershield kg 88,200.00
C 6 Cat penutup kg
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
C 7 Cat kayu kg 59,200.00
C Cat Epoxy/Tar kg
C 8 Dempul kayu typa A (putih) Jago kg 22,700.00
C 9 Plamur Fuji kg
C 10 Kalkarium kg
C 11 Politur jadi ltr
C 12 Teak oil Fuji ltr
C 13 Pernis ltr
C 14 Minyak cat ltr 12,000.00
C 15 Thinner ltr 12,000.00
C 16 Kuas roll bh
C 17 Kuas ukuran 3,5" bh
C 18 Kuas ukuran 2,5" bh
C 19 Kuas ukuran kecil 1" bh
C 20 Soda api kg 39,400.00
C 21 Sabun deterjen kg
C 22 Amplas lbr 2,500.00
C 23 Perekat kg 25,200.00
KB PERALATAN KEBERSIHAN
KB 1 Sapu lidi bh
KB 2 Tangkai Sapu bh
KB 3 Seragam bh
KB 4 Sarung tangan bh
KB 5 Masker bh
KB 6 Gerobak (alat baru) bh
KB 7 Gerobak (sewa) bh
KB 8 Serok bh
KB 9 Gunting pangkas bh
KB 10 Mesin potong rumput bh
KB 11 Garpu tanah bh
KB 12 Arit bh
KB 13 Sepatu ps
KB 14 Ember bh
KB 15 Pacul bh
KB 16 Sewa kendaraan untuk membuang lumpur hr
KB 17 Gas oksigen 5 kg tb
KB 18 Pipa dia. 3/8" - 15 cm bh
KB 19 Nitobond EC kg
KB 20 Conbextra EP kg
KC BAHAN KACA
KC 1 Kaca polos m2 262,500.00
KC 2 Kaca patri m2
KC 3 Fiber glass lbr
KC 4 Profil kaca m' 304,500.00
KY KAYU
KY 1 Kayu Kelas III m3 5,937,500.00
KY 2 Damar Laut (Kelas I) m3 15,625,000.00
KY 3 Kayu meranti balok m2 9,200,000.00
KY 4 Kayu meranti papan m3 9,200,000.00
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
KY 5 Papan kayu damar laut m3
KY 6 Papan cetakan / bekesting m3 5,937,500.00
KY 7 Kayu dolken m3 48,000.00
KY 8 Kayu dolken Ø 8 - 10/400 cm btg 48,000.00
KY 9 Perancah kayu m3
KY
KY LIST KAYU PROFIL
KY 10 List kayu profil m1
KY 11 Kayu plepet eternit 1/5 cm m1
KY KAYU LAPIS
KY 12 Akustik soft board 60 x 120 lbr
KY 13 Akustik soft board 40 x 60 lbr
KY 14 Akustik soft board 30 x 60 lbr
KY 15 Melamin wood 90 x 120 cm lbr
KY 16 Melamin wood 120 x 240 cm lbr
KY 17 Formika 4" x 8" x 0,3 cm lbr
KY 18 Triplek lbr
KY 19 Teak wood ( 90 x 240 ) lbr
KY 20 Plywood 4 mm lbr 56,100.00
KY 21 Multiplek lbr 283,500.00
KY 21 Kalsiboart 8mm lbr 105,000.00
LG BESI BETON
LG 1 Besi beton polos kg 11,600.00
LG 2 Besi beton ulir kg 12,300.00
LG 3 Besi baja profil kg 12,100.00
LG 4 Besi tuang / cor kg
LG 5 Besi plat lembaran kg 12,500.00
LG 6 Besi scuare tube ml
LG 7 Besi lis kaca (1 x 1) cm ml
LG 8 Besi gording canal kg 12,100.00
LG 9 Baja profil IWF kg 12,100.00
LG 10 Besi strip kg 13,300.00
LG 11 Besi profil kg 12,100.00
LG 12 Besi siku rata-rata kg 12,100.00
LG 13 Besi angkur dia. 8mm kg
LG 14 Plat baja t = 3 mm Kg 12,500.00
LG 15 Formite/penjaga jarak bekisting/spacer bh
LG 16 Scafolding unit
LG 17 Profil alumunium m1
LG 18 Skrup fixer bh
LG 19 Sealent tube 7,500.00
LG 20 Alumunium strip ml
LG 21 Besi pelat/baja tulangan dia 19 mm kg
LG 22 Al. Composite Panel (Alucopan) m2 277,200.00
LG 23 Rangka furing m' 5,000.00
LG 24 kawat penggantung rangka furing m' 13,000.00
LG KAWAT
LG 1 Kawat beton / bindrat kg 20,000.00
LG 2 Kawat bronjong kg
LG 3 Kawat nyamuk m2 20,000.00
Kawat jaring m2
LG 4 Kawat las kg 31,800.00
LG 5 Kawat galvanis kg
LG 6 Kawat duri kg 20,000.00
LG 7 Besi jaring kawat baja kg
LG 8 Kawat harmonika m2
LG 9 Kawat penggantung rangka hollow m1
LG 10 Profil Alumunium "T" m1
LG 11 Baja ringan m2 80,000.00
LG 12 Pipa hollow 4 x 4 cm tebal 1.2 mm m1
7,875.00
LG 13 Kusen alumunium uk 2"x4" tebal 1.2 mm sekualitas YKK putih m1
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
LG 14 Jendela nako bh 300,000.00
LG 15 Pintu besi baja m2
LG 16 Jendela besi baja m2
LG 17 Jendela besi tahan api m2
LG 18 Pintu gulung besi m2
LG 19 Pintu lipat besi m2
LG 20 Sunscreen alumunium m2
LG 21 Roll door m2
LG 22 Pintu alumunium m' 105,800.00
LG 23 Vertikal blind m2
LG 24 Wall paper m2
LG Scafolding
LG 1 Main Frame (MF-1219/h = 190 cm) bh
LG 2 Ladder Frame (LF-1209/h =90) bh
LG 3 Join Pin (JP-42) bh
LG 4 Cross Brase (CB-1218/I = 220 cm)-MF bh
LG 5 Cross Brase (CB-0618/I = 193)-LF bh
LG 6 Head Jack (HJ-60) bh
LG 7 Base Jack (BJ-60) bh
LG 8 Balok 8/12 (10x pakai) m3
LG 9 Papan Alas 3/20 (3x pakai) m3
LG 10 Kawat Pengikat kg
LAIN-LAIN
LL 1 Tiang bendera
LL -Pondasi umpak buah
LL -Ompak ornamen buah
LL -Tiang galvanis 3" m'
LL -Bendera 120 x 180 buah
LL 2 Rambu lalu lintas (terpasang) buah
LL 3 Papan nama jalan (terpasang) buah
LL 4 Sumur peresapan 5 m buah
LL 5 Air minum, instalasi dalam dengan pipa pralon 1" medium, acesories dihitung sendiri m1
LL 6 Air minum, instalasi luar dengan pipa pralon 1" medium, acesoris dihitung sendiri m1
LL 7 Asbuton kg
LL 8 Tumpuan konstruksi m
LL 9 Geotextile Polyfelt. TS 70 m2
LL 10 Pelapisan kedap air lantai dengan coating ( terpasang ) m2
LL 11 Pelapisan kedap air lantai dengan membran ( terpasang ) m2
LS LISTRIK
LS 1 Pasang instalasi / titik titik
LS 2 Penyambungan beban ls
LS 3 Kabel Snoor 2 x 0,23 "Supreme" roll
LS 4 Kabel NYA 2,5 sqmm "Supreme" roll
LS 5 Kabel NYA 1,5 sqmm "Supreme" roll
LS 6 Kabel NYA 2,5 sqmm "Supreme" m'
LS 7 Kabel NYA 1,5 sqmm "Supreme" m'
LS 8 Kabel NYM 2 x 1,5 sqmm "Supreme" m1
LS 9 Kabel NYM 2 x 2,5 sqmm "Supreme" m1
LS 10 Kabel NYM 2 x 4 sqmm "Supreme" m1
LS 11 Kabel NYM 3 x 1,5 sqmm "Supreme" m1
LS 12 Kabel NYM 3 x 2,5 sqmm "Supreme" m1
LS 13 Kabel NYM 3 x 4 sqmm "Supreme" m1
LS 14 Kabel NYY 3 x 6 sqmm "Supreme" m1
LS 15 Kabel NYY 3 x 1,5 sqmm "Supreme" m1
LS 16 Kabel NYY 3 x 2,5 sqmm "Supreme" m1
LS 17 Kabel NYY 3 x 4 sqmm "Supreme" m1
LS 18 Kabel NYY 3 x 6 sqmm "Supreme" m1
LS 19 Kabel NYY 3 x 10 sqmm "Supreme" m1
LS 20 Kabel NYY 4 x 10 sqmm "Supreme" m1
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
LS 21 Kabel NYFGBY 3 x 10 sqmm "Supreme" m1
LS 22 Kabel DX 2 x 10 sqmm "Supreme" m1
LS 23 Kabel DX 2 x 16 sqmm "Supreme" m1
LS 24 Kabel DX 2 x 25 sqmm "Supreme" m1
LS 25 Kapasitor 12,5 uF buah
LS 26 MCB 10 Ampere + box "MG" buah
LS 27 MCB 6 Ampere "MG" buah
LS 28 Tutup panel 30x30 buah
LS 29 Pipa pralon 3" m'
LS 30 Pasang panel kontrol unit / ls
LS 31 Penyetelan dan penyalaan titik
LS 32 Alat bantu set 5,000.00
LS 33 Retur material existing unit
LS 34 Angkutan jam
LT TEGEL / KERAMIK
LT 1 Plint tegel abu-abu 15/20 bh
LT 2 Plint tegel abu-abu 10/20 bh
LT 3 Plint tegel abu-abu 10/30 bh
LT 4 Plint tegel abu-abu 10/40 bh
LT 5 Plint tegel warna 10/20 bh
LT 6 Plint tegel warna 10/30 bh
LT 7 Plint tegel warna 10/40 bh
LT 8 Plint ubin teraso 10/30 bh
LT 9 Plint ubin teraso 10/40 bh
LT 10 Plint ubin granit 10/30 bh
LT 11 Plint ubin granit 10/40 bh
LT 12 Plint ubin teralux marmer 10/60 bh
LT 13 Plint ubin teralux marmer 10/40 bh
LT 14 Plint ubin teralux marmer 10/30 bh
LT 15 Tegel keramik 5/20 berglasir bh
LT 16 Tegel keramik 10/20 berglasir bh
LT 17 Tegel keramik 10/30 berglasir bh
LT 18 Tegel keramik 20/20 berglasir bh 2,880.00
LT 19 Tegel keramik 20/25 berglasir bh 3,900.00
LT 19 Tegel keramik 30/30 berglasir bh
LT 20 Tegel keramik 40/40 berglasir bh 11,520.00
LT 20 Tegel keramik 60/60 berglasir bh 69,984.00
LT 20 Batu Alam. m2 157,500.00
LT 21 Tegel keramik mosaik m2
LT 22 Marmer bh
LT 23 Tegel porselin m2
LT 24 Stepnosing granito bh
LT 25 List keramik dinding motif 5/20 bh
LT 26 Plint keramik artistik bh
LT 27 Keramik dinding 20/25 m2
LT 28 Internal cove bh
LT 29 Bahan teraso cor m3
P PIPA
P 1 Pipa beton 20 x 30 Panjang 1 m m
P 2 Pipa beton 15 x 30 Panjang 1 m m
P 3 Pipa tanah dia. 15 cm bh
P 4 Pipa tanah dia. 20 cm bh
P 5 Pipa galvanis dia. 1/2" m1
P 6 Pipa galvanis dia. 3/4" m1
P 7 Pipa galvanis dia. 1" m1
P 8 Pipa galvanis dia. 1 1/2" m1
P 9 Pipa galvanis dia. 3" m1
P 10 Pipa galvanis dia. 4" m1
P BAHAN PLASTIK
P 11 Pipa PVC abu-abu dia. 1/2" Wavin btg
P 12 Pipa PVC abu-abu dia. 3/4" Wavin btg
P 13 Pipa PVC abu-abu dia. 1" Wavin btg
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
P 14 Pipa PVC abu-abu dia. 1 1/2" Wavin btg
P 15 Pipa PVC abu-abu dia. 2" Wavin btg
P 16 Pipa PVC abu-abu dia. 2 1/2" Wavin btg
P 17 Pipa PVC abu-abu dia. 3" Wavin btg
P 18 Pipa PVC abu-abu dia. 4" Wavin btg
PG PENGGANTUNG / PENGUNCI
PG 1 Engsel pintu bh
PG 2 Engsel jendela bh
PG 3 Grendel bh
PG 4 Hak angin bh
PG 5 Engsel angin bh
PG 6 Kait angin bh
PG 7 Door holder bh
PG 8 Door stop bh
PG 9 Penggantung + rel pintu dorong bh
PG 10 Kunci tanam bh 69,300.00
PG 11 Kunci tanam antik bh
PG 12 Kunci tanam biasa bh
PG 13 Kunci kamar mandi bh
PG 14 Kunci gembok bh
PG 15 Kunci selot bh
PG 16 Kunci silinder bh
PG 17 Kunci lemari bh
PG 18 Spring knip bh
PG 19 Door closer bh
PK 20 Ramset / dina bolt bh 2,000.00
PK PAKU
PK 1 Paku gording 125 x 5,1 mm kg 16,300.00
PK 2 Paku usuk 80 x 3,8 mm kg 16,300.00
PK 3 Paku reng 55 x 3,1 mm kg 16,300.00
PK 4 Paku eternit 20 x 1,5 mm kg 16,300.00
PK 5 Water mur kg
PK 6 Angkur / baut bh
PK 7 Paku biasa kg 16,300.00
PK 8 Paku asbes bh
PK 9 Paku sumbat bh
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
PK 10 Paku sekrup 3.5" bh
PK 11 Paku skrup kg 16,300.00
PK 12 Paku triplek kg 16,300.00
PK 13 Paku gypsum kg 16,300.00
PK 14 Paku hak panjang 15 cm kg 16,300.00
PK 15 Paku biasa 1/2" - 1" kg 16,300.00
PS BAK MANDI
PS 1 Bak mandi fiber glass 1,00 m3 bh
PS 2 Bak mandi fiber glass 0,30 m3 bh
PS KLOSET
PS 1 Kloset jongkok porselin type CE8 standar bh
PS 2 Kloset duduk standar / porselin ( dengan tangki KIA standart) "Toto" bh
PS 3 Kloset duduk putih dengan tangki "Toto" set 1,890,000.00
PS 4 Kloset jongkok teraso bh
PS WASTAFEL
PS 1 Wastafel putih (KIA) set 535,500.00
PS 2 Badkip bh
PS 3 Bak cuci teraso bh
PS 4 Bak cuci stainless steel bh
PS 5 Water drain + asesories set
PS 6 Shower dinding set
PS URINOIR
PS 1 Urinoir putih set 882,000.00
PS 2 Kran air diameter 3/4" atau 1/2" exs. Toto bh 31,500.00
PS 3 Seal tape bh 5,000.00
PS 4 Floordrain bh 78,100.00
PS 5 Kran air angsa bh
PS 6 Perlengkapan set
PS 7 Tempat sabun bh
HARGA SATUAN
KODE NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
ALT ALAT
ALT 1 Crane Kap. 35 ton hari 3,900,000.00
ALT 2 Hammer + Pile driver hari 1,850,000.00
ALT 3 Kotrek 2,5 ton bh 200,000.00
ALT 4 Kunci set 125,000.00
ALT 5 Perancah hari 350,000.00
ALT 6 Waterpass unit 400,000.00
ALT 7 Piling Barge Driving hari 1,500,000.00
ALT 8 Ponton Kap. 1000 ton hari 4,000,000.00
ALT 9 Work Boat hari 1,000,000.00
ALT 10 Generator 150 kVA hari 1,500,000.00
ALT 11 Theodolite unit 500,000.00
ALT 12 Crawler Crane Kap. 35 ton hari 3,900,000.00
ALT 13 Alat Pancang Pile Compactor hari 1,800,000.00
ALT 14 Crane Kap. 10-15 Ton hari 2,800,000.00
ALT 15 Genset hari 275,000.00
ALT 16 Bor beton hari 375,000.00
ALT 17 Sewa alat las hr 1,146,000.00
ALT 18 Sewa alat sondir hr
ALT 19 Sewa alat perakitan tulangan hr
ALT 20 Sewa Scaffolding unit
ALT 21 Biaya tes beton per benda uji bh
ALT 22 Vienetions dan vertikal blinds (tirai) m2
ALT 23 Karpet m2
ALT 24 Biaya analisis tes beton perbeda uji bh
ALT 25 Sewa Compressor untuk pekerjaan grouting hr
ALT 26 Sewa Mesin Grouting hr
ALT 27 Sewa mesin gerinda untuk pekerjaan grouting hr
ALT 28 Sewa mixer ubtuk pekerjaan grouting hr
ALT 29 Sewa alar bor hr
ALT 30 Sewa Alat Ukur hr
ALT 31 Sewa Motor Walls hr
ALT 32 Alat bantu pekerjaan grouting ls
ALT 33 Alat bantu pekerjaan pekerjaan marka ls
ALT 34 Alat bantu pekerjaan pekerjaan expantion joint ls
ALT 35 Waterstop lebar 230 mm - 320 mm m'
ALT 36 Waterstop lebar 200 mm m'
ALT 13 Alat bantu pekerjaan pancang unt 1,000,000.00
ALT 37 Waterstop lebar 150 mm m'
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PP 0 PEKERJAAN PERSIAPAN
PP1 1 M2 Pekerjaan Pengukuran Gedung 8,500 - 8,500
PP2 1 M1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran 14,800 175,126 189,926
PP3 1 M2 Membersihkan lapangan dan perataan 9,500 - 9,500
PP4 1 buah Membuat Papan Nama Proyek 80x120 cm 357,300 454,830 812,130
PP5 1 M2 Pembuatan jalan sementara, tebal 25 cm 63,000 11,859 74,859
PP6 1 M2 Pembuatan kantor sementara, dengan lantai plesteran 381,000 2,458,066 2,839,066
PP7 1 M1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter 41,400 352,293 393,693
PP8 1 M1 Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter 35,900 554,086 589,986
PP9 1 M2 Pembuatan gudang semen dan alat-alat 237,000 1,361,168 1,598,168
PP10 1 M2 Pembuatan rumah jaga/konstruksi kayu 192,500 1,794,160 1,986,660
PP11 1 M2 Pembuatan bedeng buruh 237,000 1,451,415 1,688,415
PP12 1 M2 Pasang pagar kawat jaring galvanis, tinggi 1,00 m 6,190 - 6,190
PP13 1 M1 Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm 33,225 102,028 135,253
PT PEKERJAAN TANAH
PT1 1 M3 Galian tanah biasa sedalam sampai 1 meter 43,250 - 43,250
PT2 1 M3 Galian tanah biasa sedalam 1 - 2 meter 53,100 - 53,100
PT3 1 M3 Galian tanah biasa sedalam 2 - 3 meter 63,110 - 63,110
PT4 1 M3 Galian tanah keras sedalam sampai 1 meter 57,560 - 57,560
PT5 1 M3 Galian tanah cadas sedalam sampai 1 meter 87,300 - 87,300
PT6 1 M3 Galian tanah lumpur sedalam 1 meter 69,600 - 69,600
PT7 1 M3 Stripping tebing setinggi 1 meter 3,150 - 3,150
PT8 1 M3 Pengangkutan tanah sejauh 15 meter 18,950 - 18,950
PT9 1 M3 Pemadatkan tanah per 20 cm 31,500 - 31,500
PT10 1 M3 Urug kembali bekas galian (dihitung 1/3 kali galian tanah) 14,414 - 14,414
PT11 1 M3 Urugan pasir 17,300 113,400 130,700
PT12 1 M3 Urugan sirtu padat untuk peninggian lantai bangunan 15,750 166,320 182,070
PT13 1 M3 Urug tanah mendatangkan 17,300 - 17,300
PT14 1 M2 Memasang Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi 86,000 12,400 98,400
PT15 1 M2 Gebalan rumput 29,500 - 29,500
PT16 1 M3 Pemasangan lapisan ijuk tebal 10cm untuk peresapan 9,450 - 9,450
PT17 1 M3 Pembuangan Tanah sampai dengan sejauh 150 meter 32,380 - 32,380
PD PASANGAN DINDING
PD1 1 M2 Pasangan dinding HB/CB 10, camp. 1pc : 4ps 26,600 63,239 89,839
PD2 1 M2 Pasangan dinding HB/CB 10, camp. 1pc : 3ps 26,600 64,525 91,125
PD3 1 M2 Pasangan dinding HB/CB 15, camp. 1pc : 4ps 29,560 94,865 124,425
PD4 1 M2 Pasangan dinding HB/CB 15, camp. 1pc : 3ps 29,560 97,268 126,828
PD5 1 M2 Pasangan dinding HB/CB 20, camp. 1pc : 4ps 34,000 125,998 159,998
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PD6 1 M2 Pasangan dinding HB/CB 20, camp. 1pc : 3ps 34,000 129,050 163,050
PD7 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2Ps 26,600 46,086 72,686
PD8 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps 26,600 45,094 71,694
PD9 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 26,600 54,938 81,538
PD10 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps 26,600 56,938 83,538
PD11 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps 26,600 59,320 85,920
PD12 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps 26,600 60,710 87,310
PD13 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 26,600 62,973 89,573
PD14 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps 26,600 66,559 93,159
PD15 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps 26,600 72,616 99,216
PD16 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps 53,200 110,335 163,535
PD17 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps 53,200 124,078 177,278
PD18 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps 53,200 126,765 179,965
PD19 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps 53,200 131,666 184,866
PD20 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps 53,200 140,226 193,426
PD21 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps 53,200 153,413 206,613
PD22 1 M2 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 4ps 26,600 19,325 45,925
PD23 1 M2 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 3ps 26,600 23,090 49,690
PD24 1 M2 Pasangan bata merah expose (5 x 11 x 24 cm), camp. 1 Pc : 3 Ps 31,050 23,090 54,140
PD25 1 M2 Pasangan dinding bataco 38,400 66,988 105,388
PD26 1 M2 Pasangan roster 25/25 cm - 21,988 21,988
PB PEKERJAAN BETON
PB1 1 M3 Membuat beton , 1 Pc : 2 Ps : 3 Kr 119,400 684,993 804,393
PB2 1 M3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr 119,400 532,061 651,461
PB3 1 M3 Beton mutu f’'c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 121,825 572,619 694,444
PB4 1 M3 Beton mutu f’ = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 121,825 611,042 732,867
PB5 1 M3 Beton mutu f’'c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 121,825 640,975 762,800
PB6 1 M3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87 88,600 555,744 644,344
PB7 1 M3 Beton mutu f’'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 121,825 676,661 798,486
PB8 1 M3 Beton mutu f’'c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 121,825 710,242 832,067
PB9 1 M3 Beton mutu f’'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 121,825 736,078 857,903
PB10 1 M3 Beton mutu f’'c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 121,825 752,169 873,994
PB11 1 M3 Beton mutu f’'c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 121,825 779,671 901,496
PB12 1 M3 Beton mutu f’'c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 121,825 788,245 910,070
PB13 1 M3 Beton mutu f’'c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49 155,050 820,672 975,722
PB14 1 M3 Beton mutu f’'c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48 155,050 831,838 986,888
PB15 1 M3 Membongkar cetakan 220,000 - 220,000
PB16 1 M3 Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken ) 1,141,000 33,600 1,174,600
PB17 1 M3 Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding ) 442,100 - 442,100
PB18 1 M1 PVC Waterstop lebar 150 mm 6,210 - 6,210
PB19 1 M1 PVC Waterstop lebar 200 mm 7,525 - 7,525
PB20 1 M1 PVC Waterstop lebar 230 mm - 320 mm 8,280 - 8,280
PB21 1 KG Pembesian dengan besi polos 1,036 12,480 13,516
PB22 1 KG Pembesian dengan besi ulir 1,036 13,215 14,251
PB23 1 KG Memasang kabel presstressed polos/strands 740 12,380 13,120
PB24 1 KG Memasang jaring kawat baja/wire mesh 573 11,932 12,505
PB25 1 M2 Cetakan beton / begisting memakai papan 56,300 383,720 440,020
PB26 1 M2 Cetakan beton / begisting memakai multiplek 56,300 261,295 317,595
PB27 1 M2 Begesting untuk pondasi 53,820 242,990 296,810
PB28 1 M2 Begesting untuk sloof 53,820 272,678 326,498
PB29 1 M2 Begesting untuk kolom 68,310 578,445 646,755
PB30 1 M2 Begesting untuk balok 68,310 606,045 674,355
PB31 1 M2 Begesting untuk lantai 68,310 770,445 838,755
PB32 1 M2 Begesting untuk dinding 68,310 613,070 681,380
PB33 1 M2 Begesting untuk tangga 68,310 518,770 587,080
PB34 1 M1 Jembatan untuk pengecoran beton 17,350 190,530 207,880
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PB35 1 M1 Kolom praktis beton bertulang (11 x 11) cm 15,960 63,986 79,946
PB36 1 M1 Ring balok beton bertulang (10 x 15) cm 26,355 72,754 99,109
PB37 1 M1 Pembuatan tiang pancang (40 x 40) cm, beton bertulang 118,630 965,289 1,083,919
PB38 1 M1 Pembuatan tiang pancang (35 x 35) cm, beton bertulang 91,700 770,358 862,058
PEKERJAAN KERAMIK
PPL17 1 M2 Pasang lantai keramik artistik uk. 10 x 20 cm 72,450 21,818 94,268
PPL18 1 M2 Pasang lantai keramik artistik uk. 10 x 10 cm atau 5 x 20 cm 72,450 22,661 95,111
PPL19 1 M2 Pasang ubin porselin uk. 11 x 11 cm 54,000 17,760 71,760
PPL20 1 M2 Pasang ubin porselin uk. 10 x 20 cm 93,150 20,104 113,254
PPL21 1 M2 Pasang ubin porselin uk. 20 x 20 cm 93,150 247,748 340,898
PPL22 1 M2 Pasang tegel keramik uk. 33/33 72,450 19,699 92,149
PPL23 1 M2 Pasang tegel keramik uk. 30/30 72,450 21,963 94,413
PPL24 1 M2 Pasang tegel keramik uk. 20/20 72,450 99,058 171,508
PPL25 1 M2 Pasang tegel keramik uk. 10 x 33 cm (variasi/border) 108,675 27,069 135,744
PPL26 1 M2 Pasang lantai mozaik uk. 30 x 30 cm, camp. 1pc : 3ps 72,450 27,886 100,336
PPL27 1 M1 Pasang plint keramik ukuran 10 x 30 cm 13,320 1,974 15,294
PPL28 1 M1 Pasang plint keramik ukuran 10 x 40 cm 13,320 2,021 15,341
PPL29 1 M1 Pasang plint keramik 5 x 20 cm 13,320 988 14,308
PPL30 1 M1 Pasang plint internal cove artistik 5 x 5 x 20 cm 111,000 2,115 113,115
PPL31 1 M2 Pasang lantai marmer uk. 100 x 100 cm 72,450 17,880 90,330
PPL32 1 M2 Pasang lantai karpet 25,160 - 25,160
PPL33 1 M2 Pasang keramik dinding artistik 10 x 20 cm 93,150 172,744 265,894
PPL34 1 M2 Pasang keramik dinding artistik 5 x 20 cm 93,150 20,104 113,254
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PPL35 1 M2 Pasang keramik dinding 10 x 20 cm 93,150 20,104 113,254
PPL36 1 M2 Pasang keramik dinding 20 x 20 cm 93,150 94,905 188,055
PPL37 1 M2 Pasang keramik dinding 20/25 76,730 95,760 172,490
PPL38 1 M2 Pasang keramik stepnosing granito 5/30 11,850 782 12,632
PPL39 1 M2 Pasang dinding marmer uk. 100 x 100 cm 134,550 70,273 204,823
PPL40 1 M2 Pasang lantai vinyl uk. 30 x 30 cm kls 1 22,200 - 22,200
PPL41 1 M2 Pasang wallpaper lebar 50 cm 34,920 - 34,920
PPL42 1 M2 Pasang floor hardener 17,760 - 17,760
PPL43 1 M1 Pasang plint vinyl karet uk. 15 x 30 cm dengan perekat 11,840 - 11,840
PPL44 1 M1 Pasang plint kayu klas II tebal 2cm, lebar 10cm 17,760 815 18,575
PPL45 1 M1 Pasang keramik dinding 60/60 76,730 212,160 288,890
PPL46 1 M1 Pasang keramik dinding 40/40 76,730 89,760 166,490
PK PEKERJAAN KAYU
PK1 1 M3 Pasang konstruksi kuda-kuda konvensional 1,304,000 ### 11,714,780
PK2 1 M3 Pasang gording Kayu meranti 782,400 ### 11,150,800
PK3 1 M2 Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar (laut) 14,800 189,125 203,925
PK4 1 M2 Pasang usuk 5/7 Kayu meranti, reng 3/4 Kayu damar (laut) 14,800 245,375 260,175
PK5 1 M2 Pasang rangka atap sirap 17,760 1,521,260 1,539,020
PK6 1 M2 Pasang rangka langit-langit (50 x 100) c 40,950 144,940 185,890
PK7 1 M' Pasang lisplank ukuran (3 x 20) cm 23,700 100,990 124,690
PK8 1 M' Pasang lisplank ukuran (3 x 30) cm, 23,700 102,015 125,715
PK9 1 M' Pasang lisplank ukuran (2 x 20) cm 14,800 45,138 59,938
PK10 1 M' Pasang lisplank ukuran (2 x 25) cm 14,800 56,178 70,978
PK11 1 M' Pasang lisplank ukuran 2 x (3 x 20) cm 31,100 134,378 165,478
PK12 1 M' Pasang lisplank ukuran 2 x (2 x 20) cm 14,800 80,098 94,898
PK13 1 M' Mengerjakan papan ruiter 2/20 8,772 37,126 45,898
PK14 1 M2 Pasang rangka dinding pemisah ukuran (60 x 120) cm 48,900 260,045 308,945
PK15 1 M2 Pasang dinding pemisah teakwood rangkap 48,900 262,845 311,745
PK16 1 M2 Pasang dinding pemisah plywood rangkap 65,200 53,491 118,691
PK17 1 M2 Pasang dinding lambiziring, dari Kayu jati papan 195,600 66,030 261,630
PK18 1 M2 Pasang dinding bilik bambu, rangka kayu klas III, IV 10,350 218,799 229,149
PK19 1 M2 Membuat dan memasang kusen pintu / jendela Kayu Meranti 2,282,000 ### 12,422,375
PK20 1 M2 Membuat dan memasang kusen pintu / jendela kayu Damar Laut 1,956,000 ### 19,163,875
PK21 1 M2 Membuat dan memasang pintu klamp standar 114,100 625,815 739,915
PK22 1 M2 Membuat dan memasang daun pintu panil 326,000 370,500 696,500
PK23 1 M2 Membuat dan memasang daun pintu dan jendela jalusi 326,000 591,300 917,300
PK24 1 M2 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu 228,200 289,089 517,289
PK25 1 M2 Membuat pintu plywood rangkap, rangka expose 260,800 294,609 555,409
PK26 1 M2 Memasang jalusi kusen 241,650 554,445 796,095
PK27 1 M2 Memasang teakwood rangkap, rangka expose 260,800 231,989 492,789
PK28 1 M2 Memasang teakwood rangkap lapis formika, rangka expose 277,100 234,489 511,589
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PBS15 1 M2 Pasang pintu lipat (folding door) bahan plastik/PVC 65,120 - 65,120
PBS16 1 M2 Pasang pintu Sunscreen alumunium 75,920 - 75,920
PBS17 1 M2 Pasang Rolling door alumunium 148,000 105,800 253,800
PBS18 1 M2 Pasang kusen pintu alumunium 6,360 450 6,810
PBS19 1 M2 Pasang pintu alumunium strip lebar 8 cm 12,576 - 12,576
PBS20 1 M2 Pasang pintu kaca rangka alumunium 12,685 802,495 815,180
PBS21 1 M2 Pasang vienetions dan vertikal blinds 51,800 - 51,800
PBS22 1 M2 Pasang terali besi strip (2 x 3) mm 247,120 82,154 329,274
PBS23 1 M2 Pasang kawat nyamuk 14,800 44,823 59,623
PBS24 1 M2 Pasang jendela nako & tralis 28,880 586,100 614,980
PBS25 1 M' Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm 46,050 176,397 222,447
PBS26 1 M' Pasang talang ½ lingkaran D - 15 cm, seng plat BJLS 30 lebar 45 cm 35,550 8,166 43,716
PA PEKERJAAN ATAP
PA1 1 M2 Langit-langit asbes semen tebal 4, 5 dan 6 mm 8,200 16,773 24,973
PA2 1 M2 Langit-langit asbes (1,00 x 1,00) m memakai plepet 8,000 16,773 24,773
PA3 1 M2 Langit-langit akustik ukuran (30 x 30) cm 17,760 815 18,575
PA4 1 M2 Langit-langit akustik ukuran (30 x 60) cm 14,800 815 15,615
PA5 1 M2 Langit-langit akustik ukuran (60 x 120) cm 14,800 815 15,615
PA6 1 M2 Langit-langit triplek ukuran (120 x 240) cm tebal 3mm, 4mm, dan 6 mm 14,800 489 15,289
PA7 1 M2 Langit-langit lambriziring Kayu jati tebal 9 mm 118,400 138,489 256,889
PA8 1 M2 Langit-langit gypsum board ukuran (1200 x 2400 x 9) mm 10,350 26,545 36,895
PA9 1 M' Pasang list plafond gypsum profil 8,880 8,048 16,928
PA10 1 M2 Langit-langit akustik ukuran 60 x 120 cm + rangka alumunium 74,000 5,100 79,100
PA11 1 M' List langit-langit kayu profil 7,440 163 7,603
PA12 1 M2 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu jati 31,100 112,030 143,130
PA13 1 M2 Pasang rangka langit-langit (60 x 120) cm, Kayu jati 34,060 121,556 155,616
PA14 1 M2 Langit-langit rangka hollow 36,740 36,090 72,830
PA15 1 M2 Pasang genteng beton besar Natural ( isi 9 / m2 ) 20,700 - 20,700
PA16 1 M2 Pasang genteng beton besar Natural ( isi 9 / m2 ) untuk rumah tingkat 26,600 - 26,600
PA17 1 M2 Pasang genteng beton besar Warna ( isi 9 / m2 ) 20,700 - 20,700
PA18 1 M2 Pasang genteng beton besar Warna ( isi 9 / m2 ) untuk rumah tingkat 26,600 - 26,600
PA19 1 M2 Pasang genteng keramik berglasir KIA, Kanmuri Natural 20,700 - 20,700
PA20 1 M2 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat 26,600 - 26,600
PA21 1 M1 Pasang bubungan genteng paris 41,400 4,680 46,080
PA22 1 M1 Pasang bubungan genteng beton Warna 41,400 4,680 46,080
PA23 1 M2 Pasang atap asbes gelombang (2,25 x 0,92 m) x 5 mm 15,060 1,956 17,016
PA24 1 M2 Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm 14,490 1,956 16,446
PA25 1 M2 Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm 14,490 23,781 38,271
PA26 1 M2 Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm 14,250 1,956 16,206
PA27 1 M2 Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm 14,250 19,296 33,546
PA28 1 M2 Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm 14,250 1,956 16,206
PA29 1 M2 Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm 14,250 19,942 34,192
PA30 1 M2 Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm 14,250 18,616 32,866
PA31 1 M2 Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm 14,250 1,956 16,206
PA32 1 M1 Pasang bubung stel gelombang 0,92 m 16,110 97,800 113,910
PA33 1 M1 Pasang nok stel rata 0,92 m 18,990 97,800 116,790
PA34 1 M1 Pasang nok stel rata 1,09 m 16,110 97,800 113,910
PA35 1 M1 Pasang nok atap seng 15,050 1,038 16,088
PA36 1 M1 Pasang atap genteng metal zinc alume type prima roof 19,980 187,680 207,660
PA37 1 M1 Pasang atap metal gelombang 19,980 - 19,980
PA38 1 M1 Pasang nok genteng metal U type prima roof 28,140 - 28,140
PA39 1 M1 Pasang atap alumunium 69,450 326 69,776
PA40 1 M1 Pasang nok alumunium 87,200 652 87,852
PA41 1 M2 Pasang alumunium foil / sisalation 13,340 - 13,340
PA42 1 M2 Pasang atap polikarbonat 72,200 352,150 424,350
PC PEKERJAAN PENGECATAN
PC1 1 M2 Mengecat kerb 3 kali TIAP 1 M2 ( 3 kali ) 38,500 15,687 54,187
Mengecat kerb 3 kali TIAP 1 M2 ( 2 kali ) 25,667 10,458 36,124
Mengecat kerb 3 kali TIAP 1 M2 ( 1 kali ) 12,833 5,229 18,062
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PC2 1 M2 Mengikis / mengerok permukaan cat tembok lama 8,450 1,970 10,420
PC3 1 M2 Mengerok karat cat lama permukaan baja dengan cara manual 8,450 - 8,450
PC4 1 M2 Mendempul dan menggosok kayu 5,960 2,056 8,016
PC5 1 M2 Pengecatan bidang kayu lama 10,725 8,806 19,531
PC6 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup 4,590 26,366 30,956
PC7 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup 12,810 20,424 33,234
PC8 1 M2 Pelaburan bidang kayu dengan teak oil 13,110 - 13,110
PC9 1 M2 Pelaburan bidang kayu dengan politur 6,440 5,000 11,440
PC10 1 M2 Pelaburan bidang kayu dengan cat residu atau ter 5,980 - 5,980
PC11 1 M2 Pelaburan bidang kayu dengan vernis 23,240 1,385 24,625
PC12 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 6,907 5,180 12,087
PC13 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 5,478 6,216 11,694
PC14 1 M2 Pengecatan tembok tidak terlindung dari panas dan hujan 6,907 31,752 38,659
PC15 1 M2 Melabur tembok dengan kalkarium 5,478 - 5,478
PC16 1 M2 Pengecatan bidang besi ( 3 x ) 12,810 7,695 20,505
PC17 1 M2 Melamin 19,490 4,800 24,290
PC18 1 M2 Pemasangan wall paper 17,480 5,040 22,520
PC19 1 M2 Pengecacatan permukaan baja dengan meni besi 19,700 3,530 23,230
PC20 1 M2 Pengecacatan permukaan baja dengan meni besi memakai perancah 33,000 3,530 36,530
PC21 1 M2 Pengetiran kayu ( 2 x ) 5,900 - 5,900
PC22 1 M2 Mengecat genteng 6,907 31,752 38,659
PS PEKERJAAN SANITASI
PS1 1 bh Memasang kloset duduk/monoblock 282,390 1,896,804 2,179,194
PS2 1 bh Memasang kloset jongkok porselen 322,800 9,450 332,250
PS3 1 bh Memasang kloset jongkok teraso 210,800 13,650 224,450
PS4 1 bh Memasang urinoir 152,000 970,830 1,122,830
PS5 1 bh Memasang wastafel 203,500 552,661 756,161
PS6 1 bh Memasang bak mandi fiberglass volume 0,30 m3 372,400 - 372,400
PS7 1 bh Memasang badkip porselen 93,500 - 93,500
PS8 1 bh Memasang bak fiberglass volume 1 m3 air 678,000 - 678,000
PS9 1 M1 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm 6,170 3,535 9,705
PS10 1 M1 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm 8,520 16,106 24,626
PS11 1 M1 Memasang pipa beton, diameter 15 cm - 20 cm 14,490 23,978 38,468
PS12 1 M1 Memasang pipa beton, diameter 30 cm - 100 cm 39,330 226,003 265,333
PS13 1 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm 258,615 160,531 419,146
PS14 1 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm 125,850 256,341 382,191
PS15 1 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm 190,880 389,135 580,015
PS16 1 M1 Memasang pipa galvanis diameter 1/2" 13,140 - 13,140
PS17 1 M1 Memasang pipa galvanis diameter 3/4" 13,140 - 13,140
PS18 1 M1 Memasang pipa galvanis diameter 1" 13,140 - 13,140
PS19 1 M1 Memasang pipa galvanis diameter 1 1/2" 22,392 - 22,392
PS20 1 M1 Memasang pipa galvanis diameter 3" 22,392 - 22,392
PS21 1 M1 Memasang pipa galvanis diameter 4" 27,994 - 27,994
PS22 1 M1 Memasang pipa PVC tipe AW diameter 1/2" 7,464 - 7,464
PS23 1 M1 Memasang pipa PVC tipe AW diameter 3/4" 7,464 - 7,464
PS24 1 M1 Memasang pipa PVC tipe AW diameter 1" 7,464 - 7,464
PS25 1 M1 Memasang pipa PVC tipe AW diameter 1 1/2" 7,464 - 7,464
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
PS26 1 M1 Memasang pipa PVC tipe AW diameter 2" 11,218 - 11,218
PS27 1 M1 Memasang pipa PVC tipe AW diameter 2 1/2" 7,464 - 7,464
PS28 1 M1 Memasang pipa PVC tipe AW diameter 3" 19,750 - 19,750
PS29 1 M1 Memasang pipa PVC tipe AW diameter 4" 19,750 - 19,750
PS30 1 bh Memasang bak cuci piring stainless steel 28,470 - 28,470
PS31 1 bh Memasang bak cuci piring teraso 47,450 33,500 80,950
PS32 1 bh Memasang kran diameter 3/4" atau 1/2" 9,850 31,625 41,475
PS33 1 bh Memasang floor drain 9,850 78,100 87,950
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
SPL26 1 M' Mengebor beton dermaga untuk lobang baut fender '(dihitung 120 menit). 388,000 - 388,000
SPL27 1 BH Memasang fender karet 1,271,000 - 1,271,000
SPL28 1 BH Memasang shower dinding 8,550 - 8,550
SPL29 1 BH Memasang kran air angsa 8,550 - 8,550
SPL30 1 BH Memasang tempat sabun 8,550 - 8,550
SPL31 1 M' Prime coat 3,150 9,400 12,550
SPL32 1 M' Tack coat 3,150 4,700 7,850
SPL33 1 M' Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m 54,450 - 54,450
SPL34 1 M' Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m 95,700 - 95,700
SPL35 1 bh Handling dan Transport tiang pancang dan penimbunan ke titik pancang 531,000 - 531,000
SPL36 1 M2 Pelapisan epoxy/tar tiang pancang 54,500 7,520 62,020
SPL37 1 bh Sambungan tiang pancang beton/spun pile dia 50 cm 1,067,613 - 1,067,613
SPL38 1 bh Sambungan tiang pancang baja dia 50 cm 1,067,613 - 1,067,613
SPL39 1 bh Memotong tiang pancang beton/ spun pile dia 50 cm 435,290 - 435,290
SPL40 1 M2 Membongkar Paving Block 6,300 - 6,300
SPL41 1 bh Membongkar dan melepas fender 337,000 - 337,000
SPL42 1 M2 Membongkar perkerasan lama (serifying) tebal 10 cm 1,362 - 1,362
SPL43 TTK Sambungan tiang pancang diameter 35 cm 747,329 - 747,329
SPL44 TTK Rangka plafon furing 36,740 88,152 124,892
SPL45 m2 Pasangan batu alam 25,875 194,563 220,438
SPL46 m2 Pasang dinding pemisah kalsiboart 65,200 92,745 157,945
SPL47 m2 Plesteran minimalis 74,100 65,554 139,654
SPL48 m' Kisi-kisi holow 17,160 9,708 26,868
HARGA SATUAN
KODE SATUAN MACAM PEKERJAAN
UPAH BAHAN TOTAL
KPUT9 1 M2 Lapisan Penetrasi 4 cm padat 98,928 2,410,171 2,509,099
KPUT10 1 M2 Pengaspalan sand sheet (latasir), tebal 1 cm jereng 1,250,595 104,380 1,354,975
KPUT11 1 M2 Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jereng 89,890 37,086 126,975
KPUT12 1 M2 Mengecat marka jalan dengan Rettar 220,058 236,758 456,816
KPUT13 1 M2 Mengecat marka jalan dengan Thermoplastic 446,992 1,624,644 2,071,636
KPUT14 1 M2 Pemotongan aspal dengan mesin potong (cutter), 2 sisi 2,807 13,333 16,139
KPUT15 1 M1 Pembongkaran aspal dengan Jack Hammer 173,394 972,576 1,145,970
KPUT16 1 M2 Expantion joint 2,750,720 ### 19,016,808
PEKERJAAN PERSIAPAN
PP2 1 M' Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
Kayu meranti balok 0.0120 m3 X Rp. 9,200,000.00 110,400.00
Paku reng 55 x 3,1 mm 0.0200 kg X Rp. 16,300.00 326.00
Kayu meranti papan 0.0070 m3 X Rp. 9,200,000.00 64,400.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 175,126.00 189,926.00
PP7 1 M' Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
Kayu dolken Ø 8 - 10/400 cm 1.2500 btg X Rp. 48,000.00 60,000.00
Portland Cement (PC) 2.5000 kg X Rp. 1,375.00 3,437.50
Seng gelombang 2" - 5" BJLS 24 1.2000 lbr X Rp. -
Pasir beton 0.0050 m3 X Rp. 120,000.00 600.00
Krikil beton 0.0090 m3 X Rp. 195,300.00 1,757.70
Kayu meranti balok 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Cat dasar meni 0.4000 kg X Rp. 35,300.00 14,120.00
Tukang kayu 0.2000 org X Rp. 80,000.00 16,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00 1,600.00
JUMLAH 41,400.00 352,293.20 393,693.20
PP8 1 M' Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter
Kayu dolken Ø 8 - 10/400 cm 1.0000 btg X Rp. 48,000.00 48,000.00
Portland Cement (PC) 2.0000 kg X Rp. 1,375.00 2,750.00
Kawat duri 25.0000 kg X Rp. 20,000.00 500,000.00
Pasir beton 0.0050 m3 X Rp. 120,000.00 600.00
Krikil beton 0.0090 m3 X Rp. 195,300.00 1,757.70
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 35,900.00 554,085.70 589,985.70
PEKERJAAN TANAH
PT10 1 m3 Urug kembali bekas galian (dihitung 1/3 kali galian tanah)
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
Mandor 0.0083 org X Rp. 80,000.00 664.00
JUMLAH 14,414.00 14,414.00
PEKERJAAN PASANGAN
Pasangan pondasi
PPS14 1 M3 Beton cyclope 60% beton camp. 1pc:2ps:3kr, 40% batu belah
Batu belah putih 0.4800 m3 X Rp. -
Portland Cement (PC) 194.0000 kg X Rp. 1,375.00 266,750.00
Pasir beton 0.3120 m3 X Rp. 120,000.00 37,440.00
Krikil beton 0.4680 m3 X Rp. 195,300.00 91,400.40
Besi beton polos 126.0000 kg X Rp. 11,600.00 1,461,600.00
Kawat beton / bindrat 1.8000 kg X Rp. 20,000.00 36,000.00
Tukang batu 0.8500 org X Rp. 80,000.00 68,000.00
Kepala Tukang 0.0850 org X Rp. 90,000.00 7,650.00
Pekerja 3.4000 org X Rp. 55,000.00 187,000.00
Mandor 0.1700 org X Rp. 80,000.00 13,600.00
JUMLAH 276,250.00 1,893,190.40 2,169,440.40
PASANGAN DINDING
PEKERJAAN BETON
PB3 1 M3 Beton mutu f’'c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Portland Cement (PC) 247.000 kg X Rp. 1,375.00 339,625.00
Pasir beton 0.621 m3 X Rp. 120,000.00 74,485.71
Split D 1 - 2 cm 0.740 m3 X Rp. 214,200.00 158,508.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 572,618.71 694,443.71
PB4 1 M3 Beton mutu f’ = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Portland Cement (PC) 276.000 kg X Rp. 1,375.00 379,500.00
Pasir beton 0.591 m3 X Rp. 120,000.00 70,971.43
Split D 1 - 2 cm 0.750 m3 X Rp. 214,200.00 160,570.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 611,042.10 732,867.10
PB5 1 M3 Beton mutu f’'c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Portland Cement (PC) 299.000 kg X Rp. 1,375.00 411,125.00
Pasir beton 0.571 m3 X Rp. 120,000.00 68,485.71
Split D 1 - 2 cm 0.753 m3 X Rp. 214,200.00 161,364.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 640,974.71 762,799.71
PB6 1 M3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87
Portland Cement (PC) 230.000 kg X Rp. 1,375.00 316,250.00
Pasir beton 0.638 m3 X Rp. 120,000.00 76,542.86
Split D 1 - 2 cm 0.761 m3 X Rp. 214,200.00 162,950.67
Pekerja 1.200 OH X Rp. 55,000.00 66,000.00
Tukang Batu 0.200 OH X Rp. 80,000.00 16,000.00
Kepala Tukang 0.020 OH X Rp. 90,000.00 1,800.00
Mandor 0.060 OH X Rp. 80,000.00 4,800.00
JUMLAH 88,600.00 555,743.52 644,343.52
PB7 1 M3 Beton mutu f’'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Portland Cement (PC) 326.000 kg X Rp. 1,375.00 448,250.00
Pasir beton 0.543 m3 X Rp. 120,000.00 65,142.86
Split D 1 - 2 cm 0.762 m3 X Rp. 214,200.00 163,268.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 676,660.86 798,485.86
PB8 1 M3 Beton mutu f’'c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Portland Cement (PC) 352.000 kg X Rp. 1,375.00 484,000.00
Pasir beton 0.522 m3 X Rp. 120,000.00 62,657.14
Split D 1 - 2 cm 0.764 m3 X Rp. 214,200.00 163,585.33
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 710,242.48 832,067.48
PB9 1 M3 Beton mutu f’'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Portland Cement (PC) 371.000 kg X Rp. 1,375.00 510,125.00
Pasir beton 0.499 m3 X Rp. 120,000.00 59,828.57
Split D 1 - 2 cm 0.776 m3 X Rp. 214,200.00 166,124.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 736,077.57 857,902.57
PB10 1 M3 Beton mutu f’'c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Portland Cement (PC) 384.000 kg X Rp. 1,375.00 528,000.00
Pasir beton 0.494 m3 X Rp. 120,000.00 59,314.29
Split D 1 - 2 cm 0.770 m3 X Rp. 214,200.00 164,854.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 752,168.95 873,993.95
PB11 1 M3 Beton mutu f’'c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Portland Cement (PC) 406.000 kg X Rp. 1,375.00 558,250.00
Pasir beton 0.489 m3 X Rp. 120,000.00 58,628.57
Split D 1 - 2 cm 0.760 m3 X Rp. 214,200.00 162,792.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 779,670.57 901,495.57
PB12 1 M3 Beton mutu f’'c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Portland Cement (PC) 413.000 kg X Rp. 1,375.00 567,875.00
Pasir beton 0.486 m3 X Rp. 120,000.00 58,371.43
Split D 1 - 2 cm 0.756 m3 X Rp. 214,200.00 161,998.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 788,245.10 910,070.10
PB13 1 M3 Beton mutu f’'c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Portland Cement (PC) 439.000 kg X Rp. 1,375.00 603,625.00
Pasir beton 0.479 m3 X Rp. 120,000.00 57,428.57
Split D 1 - 2 cm 0.745 m3 X Rp. 214,200.00 159,618.67
Pekerja 2.100 OH X Rp. 55,000.00 115,500.00
Tukang Batu 0.350 OH X Rp. 80,000.00 28,000.00
Kepala Tukang 0.035 OH X Rp. 90,000.00 3,150.00
Mandor 0.105 OH X Rp. 80,000.00 8,400.00
JUMLAH 155,050.00 820,672.24 975,722.24
PB14 1 M3 Beton mutu f’'c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Portland Cement (PC) 448.000 kg X Rp. 1,375.00 616,000.00
Pasir beton 0.476 m3 X Rp. 120,000.00 57,171.43
Split D 1 - 2 cm 0.741 m3 X Rp. 214,200.00 158,666.67
Pekerja 2.100 OH X Rp. 55,000.00 115,500.00
Tukang Batu 0.350 OH X Rp. 80,000.00 28,000.00
Kepala Tukang 0.035 OH X Rp. 90,000.00 3,150.00
PB37 1 m' Pembuatan tiang pancang (40 x 40) cm, beton bertulang
Pasir urug darat 0.0190 m3 X Rp. 94,500.00 1,795.50
Pasir beton 0.0940 m3 X Rp. 120,000.00 11,280.00
Batu pecah 2/3 ( split ) 0.1500 m3 X Rp. 214,200.00 32,130.00
Portland Cement (PC) 60.5000 kg X Rp. 1,375.00 83,187.50
Besi beton polos 45.0000 kg X Rp. 11,600.00 522,000.00
Kawat beton / bindrat 0.9000 kg X Rp. 20,000.00 18,000.00
Kayu meranti balok 0.0320 m3 X Rp. 9,200,000.00 294,400.00
Paku reng 55 x 3,1 mm 0.1200 kg X Rp. 16,300.00 1,956.00
Minyak bekisting 0.0900 ltr X Rp. 6,000.00 540.00
Plamur Fuji 0.2400 kg X Rp. -
Tukang batu 0.6700 org X Rp. 80,000.00 53,600.00
Kepala tukang 0.0670 org X Rp. 90,000.00 6,030.00
PB38 1 m' Pembuatan tiang pancang (35 x 35) cm, beton bertulang
Pasir urug darat 0.0160 m3 X Rp. 94,500.00 1,512.00
Pasir beton 0.0800 m3 X Rp. 120,000.00 9,600.00
Batu pecah 2/3 ( split ) 0.1250 m3 X Rp. 214,200.00 26,775.00
Portland Cement (PC) 49.0000 kg X Rp. 1,375.00 67,375.00
Besi beton polos 34.5000 kg X Rp. 11,600.00 400,200.00
Kawat beton / bindrat 0.7000 kg X Rp. 20,000.00 14,000.00
Kayu meranti balok 0.0270 m3 X Rp. 9,200,000.00 248,400.00
Paku reng 55 x 3,1 mm 0.1200 kg X Rp. 16,300.00 1,956.00
Minyak bekisting 0.0900 ltr X Rp. 6,000.00 540.00
Plamur Fuji 0.2000 kg X Rp. -
Tukang batu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0400 org X Rp. 80,000.00 3,200.00
JUMLAH 91,700.00 770,358.00 862,058.00
PEKERJAAN PELESTERAN
PPT16 1 m2 Acian
Portland Cement (PC) 3.2500 kg X Rp. 1,375.00 4,468.75
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 20,700.00 4,468.75 25,168.75
PEKERJAAN KERAMIK
PPL44 1 m' Pasang plint kayu klas II tebal 2cm, lebar 10cm
Papan kayu damar laut 0.0030 m3 X Rp. -
Paku skrup 0.0500 kg X Rp. 16,300.00 815.00
Tukang Kayu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 17,760.00 815.00 18,575.00
PPL45 1 m2 Pasang keramik dinding 60/60
Tegel keramik 60/60 berglasir 2.7778 bh X Rp. 69,984.00 194,400.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen putih 1.5000 kg X Rp. 1,875.00 2,812.50
Tukang batu 0.6500 org X Rp. 80,000.00 52,000.00
Kepala Tukang 0.0650 org X Rp. 90,000.00 5,850.00
Pekerja 0.3200 org X Rp. 55,000.00 17,600.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 76,730.00 212,160.00 288,890.00
PPL46 1 m2 Pasang keramik dinding 40/40
Tegel keramik 40/40 berglasir 6.2500 bh X Rp. 11,520.00 72,000.00
PCB1 1 m2 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400
Tipe segi empat, uni, segi 6 tebal = 8 cm K 400 1.0000 m2 X Rp. -
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00
PCB3 1 m2 Pasang conblock tipe segi-empat, uni, segi-enam warna 8 cm, K-400
Tipe segi empat, uni, segi 6 tebal = 8 cm K 400 1.0000 m2 X Rp. -
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00
PEKERJAAN KAYU
Pasang gording
PK3 1 m2 Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar laut
Kayu meranti balok 0.0140 m3 X Rp. 9,200,000.00 128,800.00
Damar Laut (Kelas I) 0.0036 m3 X Rp. 15,625,000.00 56,250.00
Paku biasa 1/2" - 1" 0.1500 kg X Rp. 16,300.00 2,445.00
Paku reng 55 x 3,1 mm 0.1000 kg X Rp. 16,300.00 1,630.00
Tukang Kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 189,125.00 203,925.00
PK4 1 m2 Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar laut
Kayu meranti balok 0.0140 m3 X Rp. 9,200,000.00 128,800.00
Damar Laut (Kelas I) 0.0072 m3 X Rp. 15,625,000.00 112,500.00
Paku usuk 80 x 3,8 mm 0.1500 kg X Rp. 16,300.00 2,445.00
Paku reng 55 x 3,1 mm 0.1000 kg X Rp. 16,300.00 1,630.00
Tukang Kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
Rangka langit-langit
Pasang Listplank
PK24 1 m2 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu
Kayu meranti papan 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 1/2" - 1" 0.0300 kg X Rp. 16,300.00 489.00
Lem kayu (putih) Fox 0.5000 kg X Rp. 5,000.00 2,500.00
Plywood 4 mm 1.0000 lbr X Rp. 56,100.00 56,100.00
Tukang kayu 2.1000 org X Rp. 80,000.00 168,000.00
Kepala tukang 0.2100 org X Rp. 90,000.00 18,900.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 228,200.00 289,089.00 517,289.00
PBS9 1 unit Grill dari besi beton Ǿ 16mm rangka baja 50.50.5 uk 1 x 1 m
Besi siku rata-rata 24.1280 kg X Rp. 12,100.00 291,948.80
Besi beton polos 31.6000 kg X Rp. 11,600.00 366,560.00
Besi angkur dia. 8mm 2.0000 bh X Rp. -
Cat dasar meni 1.8850 m2 X Rp. 35,300.00 66,540.50
Tukang Las 0.1000 oh X Rp. 80,000.00 8,000.00
Pekerja 1.0000 oh X Rp. 55,000.00 55,000.00
JUMLAH 63,000.00 725,049.30 788,049.30
PBS11 1 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Besi siku rata-rata 15.0000 kg X Rp. 12,100.00 181,500.00
Plat baja t = 3 mm 32.8000 kg X Rp. 12,500.00 410,000.00
Kawat las 0.0500 kg X Rp. 31,800.00 1,590.00
Tukang las 1.0500 org X Rp. 80,000.00 84,000.00
PBS25 1 m' Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu jati
Seng plat 3" x 6" BJLS 28 1.0500 m1 X Rp. 1,288.13 1,352.53
Paku biasa 1/2" - 1" 0.0150 kg X Rp. 16,300.00 244.50
Kayu meranti papan 0.0190 m3 X Rp. 9,200,000.00 174,800.00
Tukang kayu 0.4000 org X Rp. 80,000.00 32,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 46,050.00 176,397.03 222,447.03
PBS26 1 m' Pasang talang ½ lingkaran D - 15 cm, seng plat BJLS 30 lebar 45 cm
Seng plat 3" x 6" BJLS 28 1.0500 lbr X Rp. 1,288.13 1,352.53
Paku biasa 1/2" - 1" 0.0100 kg X Rp. 16,300.00 163.00
Besi strip 0.5000 kg X Rp. 13,300.00 6,650.00
Tukang kayu 0.3000 org X Rp. 80,000.00 24,000.00
Kepala tukang 0.0300 org X Rp. 90,000.00 2,700.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 35,550.00 8,165.53 43,715.53
PEKERJAAN ATAP
Asbes plat ( 100 x 100 x 0,3 ) 1.1000 lbr X Rp. 15,100.00 16,610.00
Kayu plepet eternit 1/5 cm 2.6000 m1 X Rp. -
Paku eternit 20 x 1,5 mm 0.0100 kg X Rp. 16,300.00 163.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.0300 org X Rp. 55,000.00 1,650.00
Mandor 0.0015 org X Rp. 80,000.00 120.00
JUMLAH 8,000.00 16,773.00 24,773.00
PA6 1 m2 Langit-langit triplek ukuran (120 x 240) cm tebal 3mm, 4mm, dan 6 mm
Triplek 0.3750 lbr X Rp. -
Paku triplek 0.0300 kg X Rp. 16,300.00 489.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 489.00 15,289.00
PA16 1 m2 Pasang genteng beton besar Natural ( isi 9 / m 2 ) untuk rumah tingkat
Genteng beton besar natural 1m 9 biji 9.0000 bh X Rp. -
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 - 26,600.00
PA18 1 m2 Pasang genteng beton besar Warna ( isi 9 / m 2 ) untuk rumah tingkat
Genteng beton besar warna 1m 9 biji 9.0000 bh X Rp. -
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 - 26,600.00
PA20 1 m2 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat
Genteng beton besar natural 1m 9 biji 14.5000 bh X Rp. -
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 - 26,600.00
PA36 1 m2 Pasang atap genteng metal zinc alume type prima roof
Genteng metal 1.0200 m2 X Rp. 184,000.00 187,680.00
Paku anti karat 0.2000 kg X Rp. -
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0010 org X Rp. 80,000.00 80.00
JUMLAH 19,980.00 187,680.00 207,660.00
PEKERJAAN PENGECATAN
PC3 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual
Sabun deterjen 0.0500 kg X Rp. -
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 8,450.00 - 8,450.00
PC6 1 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
Cat dasar meni kayu 0.2000 kg X Rp. 51,800.00 10,360.00
Plamur Fuji 0.1500 kg X Rp. -
Cat dasar meni kayu 0.1700 kg X Rp. 51,800.00 8,806.00
Cat penutup 0.2600 kg X Rp. -
Tukang cat 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 4,590.00 26,366.00 30,956.00
PC7 1 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
Cat dasar meni kayu 0.2000 kg X Rp. 51,800.00 10,360.00
Plamur Fuji 0.1500 kg X Rp. -
Cat kayu 0.1700 kg X Rp. 59,200.00 10,064.00
Cat penutup 0.3500 kg X Rp. -
Tukang cat 0.1050 org X Rp. 80,000.00 8,400.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 12,810.00 20,424.00 33,234.00
PC12 1 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Plamur Fuji 0.1000 kg X Rp. -
Cat dasar meni kayu 0.1000 kg X Rp. 51,800.00 5,180.00
Cat penutup 0.2600 kg X Rp. -
Tukang cat 0.0630 org X Rp. 80,000.00 5,040.00
Kepala tukang 0.0063 org X Rp. 90,000.00 567.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,907.00 5,180.00 12,087.00
PC13 1 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Cat dasar meni kayu 0.1200 kg X Rp. 51,800.00 6,216.00
Cat penutup 0.1800 kg X Rp. -
Tukang cat 0.0420 org X Rp. 80,000.00 3,360.00
Kepala tukang 0.0042 org X Rp. 90,000.00 378.00
Pekerja 0.0280 org X Rp. 55,000.00 1,540.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 5,478.00 6,216.00 11,694.00
PC17 1 m2 Melamin
Cat tembok melamin 0.2000 kg X Rp. 24,000.00 4,800.00
Kuas ukuran 3,5" 0.0150 bh X Rp. -
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Tukang cat 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0050 org X Rp. 90,000.00 450.00
Mandor 0.0005 org X Rp. 80,000.00 40.00
JUMLAH 19,490.00 4,800.00 24,290.00
PEKERJAAN BONGKARAN
PBK10 1 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
Tukang kayu 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 770,000.00 - 770,000.00
PBK11 1 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 71,000.00 - 71,000.00
PEKERJAAN SANITASI
PS9 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
Pipa tanah dia. 15 cm 1.6000 bh X Rp. -
Portland Cement (PC) 0.6800 kg X Rp. 1,375.00 935.00
Pasir pasang ( progo ) 0.0130 m3 X Rp. 120,000.00 1,560.00
Pasir urug darat 0.0110 m3 X Rp. 94,500.00 1,039.50
Tukang batu 0.0300 org X Rp. 80,000.00 2,400.00
Kepala tukang 0.0030 org X Rp. 90,000.00 270.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,170.00 3,534.50 9,704.50
PS10 1 m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
Pipa tanah dia. 20 cm 1.6000 bh X Rp. -
Portland Cement (PC) 0.8700 kg X Rp. 1,375.00 1,196.25
Pasir pasang ( progo ) 0.0140 m3 X Rp. 120,000.00 1,680.00
Pasir urug darat 0.1400 m3 X Rp. 94,500.00 13,230.00
Tukang batu 0.0400 org X Rp. 80,000.00 3,200.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0800 org X Rp. 55,000.00 4,400.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 8,520.00 16,106.25 24,626.25
PS13 1 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm
Batu merah ( 5x11x23 ) 87.0000 bh X Rp. 600.00 52,200.00
Portland Cement (PC) 44.0000 kg X Rp. 1,375.00 60,500.00
Pasir pasang ( progo ) 0.0700 m3 X Rp. 120,000.00 8,400.00
Krikil beton 0.0700 m3 X Rp. 195,300.00 13,671.00
Besi beton polos 1.6000 kg X Rp. 11,600.00 18,560.00
Pasir beton 0.0600 m3 X Rp. 120,000.00 7,200.00
Tukang batu 1.0150 org X Rp. 80,000.00 81,200.00
Kepala tukang 0.0015 org X Rp. 90,000.00 135.00
Pekerja 3.2000 org X Rp. 55,000.00 176,000.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 258,615.00 160,531.00 419,146.00
PS14 1 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm
Batu merah ( 5x11x23 ) 150.0000 bh X Rp. 600.00 90,000.00
Portland Cement (PC) 77.0000 kg X Rp. 1,375.00 105,875.00
Pasir pasang ( progo ) 0.1300 m3 X Rp. 120,000.00 15,600.00
Krikil beton 0.0200 m3 X Rp. 195,300.00 3,906.00
Besi beton polos 2.6000 kg X Rp. 11,600.00 30,160.00
Pasir beton 0.0900 m3 X Rp. 120,000.00 10,800.00
Tukang batu 0.4730 org X Rp. 80,000.00 37,840.00
Kepala tukang 0.0470 org X Rp. 90,000.00 4,230.00
Pekerja 1.4200 org X Rp. 55,000.00 78,100.00
Mandor 0.0710 org X Rp. 80,000.00 5,680.00
JUMLAH 125,850.00 256,341.00 382,191.00
PS15 1 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm
Batu merah ( 5x11x23 ) 222.0000 bh X Rp. 600.00 133,200.00
Portland Cement (PC) 114.0000 kg X Rp. 1,375.00 156,750.00
Pasir pasang ( progo ) 0.1840 m3 X Rp. 120,000.00 22,080.00
Krikil beton 0.0330 m3 X Rp. 195,300.00 6,444.90
Besi beton polos 4.8500 kg X Rp. 11,600.00 56,260.00
Pasir beton 0.1200 m3 X Rp. 120,000.00 14,400.00
Tukang batu 0.7200 org X Rp. 80,000.00 57,600.00
Kepala tukang 0.0720 org X Rp. 90,000.00 6,480.00
Pekerja 2.1600 org X Rp. 55,000.00 118,800.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 190,880.00 389,134.90 580,014.90
PPG28 1 m' Pekerjaan Grouting / Injeksi retakan beton dengan epoxy resin
Nitobond EC 0.050 kg X Rp. -
Conbextra EP 0.016 kg X Rp. -
Sewa Compressor untuk pekerjaan grouting 0.225 hr X Rp. -
Sewa Mesin Grouting 0.150 hr X Rp. -
Sewa mesin gerinda untuk pekerjaan grouting 0.075 hr X Rp. -
PPG29 1 m' Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100)
Pipa PVC abu-abu dia. 1/2" Wavin 3.000 bh X Rp. -
Nitobond EC 0.050 kg X Rp. -
Sewa Mesin Grouting 0.150 hr X Rp. -
Sewa mesin gerinda untuk pekerjaan grouting 0.075 hr X Rp. -
Alat bantu 1.000 ls X Rp. 5,000.00 5,000.00
Tukang grouting 0.3125 org X Rp. 80,000.00 25,000.00
Kepala Tukang 0.0312 org X Rp. 90,000.00 2,808.00
Pekerja 1.2500 org X Rp. 55,000.00 68,750.00
Mandor 0.1562 org X Rp. 80,000.00 12,496.00
JUMLAH 109,054.00 5,000.00 114,054.00
SPL9 1 M2 Mengerjakan lantai jembatan (papan yang dipakukan diatas gelagar kayu) :
Paku biasa 1/2" - 1" 0.075 kg X Rp. 16,300.00 1,222.50
Papan kayu damar laut 0.025 X Rp. -
Tukang kayu 0.500 org/hr X Rp. 80,000.00 40,000.00
Kepala tukang 0.050 org/hr X Rp. 90,000.00 4,500.00
Pekerja 0.200 org/hr X Rp. 55,000.00 11,000.00
Mandor 0.010 org/hr X Rp. 80,000.00 800.00
JUMLAH 56,300.00 1,222.50 57522.5
SPL14 1 M2 memasang lantai cone block t.10 cm dipadatkan denganVibratory Roller kapasitas 10-15 ton
Conblock t=10 cm 44.000 Bh X Rp. 4,400.00 193,600.00
Pasir pasang ( progo ) 0.050 M3 X Rp. 120,000.00 6,000.00
Pasir pasang ( krasak ) 0.015 M3 X Rp. 120,000.00 1,800.00
Tukang batu 0.100 org/hr X Rp. 80,000.00 8,000.00
Pekerja 0.400 org/hr X Rp. 55,000.00 22,000.00
Kepala tukang 0.010 org/hr X Rp. 90,000.00 900.00
Mandor 0.040 org/hr X Rp. 80,000.00 3,200.00
Mesin Gilas getar otomatis 5 - 8 T 0.002 hr X Rp. 433,290.05 866.58
JUMLAH 34,966.58 201,400.00 236366.580104322
SPL18 1 m2 Pasang Aluminium Composite Panel (Alucopan) : (Jumlah volume besi disesuaikan terhadap rencana design)
Al. Composite Panel (Alucopan) 1.05 m2 X Rp. 277,200.00 291,060.00
Besi Profil 30 Kg X Rp. 12,100.00 363,000.00
Ramset / dina bolt 8 Bh X Rp. 2,000.00 16,000.00
Sewa alat las 1 ls X Rp. 50,000.00 50,000.00
Tukang alumunium 0.5 org/hr X Rp. 80,000.00 40,000.00
Kepala Tukang 0.05 org/hr X Rp. 90,000.00 4,500.00
Pekerja 1 org/hr X Rp. 55,000.00 55,000.00
Mandor 0.05 org/hr X Rp. 80,000.00 4,000.00
JUMLAH 103,500.00 720,060.00 823,560.00
SPL26 1 Bh Mengebor beton dermaga untuk lobang baut fender '(dihitung 120 menit).
Tukang besi 0.250 org/hr X Rp. 80,000.00 20,000.00
Kepala tukang 0.025 org/hr X Rp. 90,000.00 2,250.00
Pekerja 0.250 org/hr X Rp. 55,000.00 13,750.00
Mandor 0.025 org/hr X Rp. 80,000.00 2,000.00
Mekanik terlatih 1.000 org/hr X Rp. 100,000.00 100,000.00
Genset 0.250 hr X Rp. 275,000.00 68,750.00
Bor beton 0.250 hr X Rp. 375,000.00 93,750.00
Perancah 0.250 hr X Rp. 350,000.00 87,500.00
JUMLAH 388,000.00 - 388,000.00
SPL35 1 bh Handling dan Transport tiang pancang dan penimbunan ke titik pancang
Pekerja 8.400 oh X Rp. 55,000.00 462000
Tukang Pancang 0.800 oh X Rp. 80,000.00 64000
Alat Bantu 1.000 ls X Rp. 5,000.00 5000
JUMLAH 531,000.00 - 531,000.00
PLS6 50 M' Pasang Kabel DX 2x10 sqmm + Accessories (antar tiang / gawang)
Kabel DX 2 x 10 sqmm "Supreme" 50.0000 m1 X Rp. -
Tukang Listrik 0.5000 org X Rp. 80000 40,000.00
Pekerja 0.5000 org X Rp. 55000 27,500.00
Mandor 0.2500 org X Rp. 80000 20,000.00
Penyambungan beban 1.0000 ls X Rp. -
JUMLAH 87,500.00 - 87,500.00
PLS7 50 M' Pasang Kabel DX 2x16 sqmm + Accessories (antar tiang / gawang)
Kabel DX 2 x 16 sqmm "Supreme" 50.0000 m1 X Rp. -
Tukang Listrik 0.5000 org X Rp. 80000 40,000.00
Pekerja 0.5000 org X Rp. 55000 27,500.00
Mandor 0.2500 org X Rp. 80000 20,000.00
Penyambungan beban 1.0000 ls X Rp. -
JUMLAH 87,500.00 - 87,500.00
PLS25 1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan
Pekerja 0.5000 org X Rp. 55000 27,500.00
Tukang Listrik 0.5000 org X Rp. 80000 40,000.00
Pengawas 1.2500 org X Rp. 100000 125,000.00
Mandor 0.5000 org X Rp. 80000 40,000.00
JUMLAH (A) 232,500.00 - 232,500.00
PLS26 1 Set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son
Pekerja 0.8750 org X Rp. 55000 48,125.00
Tukang Listrik 0.8750 org X Rp. 80000 70,000.00
Pengawas 1.8033 org X Rp. 100000 180,330.00
Mandor 0.7413 org X Rp. 80000 59,306.40
JUMLAH (C) 357,761.40 - 357,761.40
PLS27 1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son
Pekerja 0.5000 org X Rp. 55000 27,500.00
Tukang Listrik 0.5000 org X Rp. 80000 40,000.00
Pengawas 1.2500 org X Rp. 100000 125,000.00
Mandor 0.5000 org X Rp. 80000 40,000.00
JUMLAH (D) 232,500.00 - 232,500.00
PLS28 1 Set Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00 206,304.00
Pekerja 2.8500 org X Rp. 55000 156,750.00
Tukang Listrik 2.8500 org X Rp. 80000 228,000.00
Pengawas 2.0075 org X Rp. 100000 200,750.00
Mandor 1.0000 org X Rp. 80000 80,000.00
JUMLAH (E) 665,500.00 206,304.00 871,804.00
PLS29 1 Set Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00 206,304.00
Pekerja 3.1000 org X Rp. 55000 170,500.00
Tukang Listrik 3.1000 org X Rp. 80000 248,000.00
Pengawas 2.5000 org X Rp. 100000 250,000.00
Mandor 1.2100 org X Rp. 80000 96,800.00
JUMLAH (F) 765,300.00 206,304.00 971,604.00
PLS30 1 Set Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00 206,304.00
Pekerja 3.3000 org X Rp. 55000 181,500.00
Tukang Listrik 3.3000 org X Rp. 80000 264,000.00
Pengawas 2.5782 org X Rp. 100000 257,820.00
Mandor 1.2433 org X Rp. 80000 99,464.00
JUMLAH (G) 802,784.00 206,304.00 1,009,088.00
PLS31 1 Set Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00 206,304.00
Pekerja 3.8100 org X Rp. 55000 209,550.00
Tukang Listrik 3.8100 org X Rp. 80000 304,800.00
Pengawas 2.6626 org X Rp. 100000 266,260.00
Mandor 1.2650 org X Rp. 80000 101,200.00
JUMLAH (H) 881,810.00 206,304.00 1,088,114.00
PLS32 1 Set Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00 206,304.00
Pekerja 4.2500 org X Rp. 55000 233,750.00
Tukang Listrik 4.2500 org X Rp. 80000 340,000.00
Pengawas 2.9287 org X Rp. 100000 292,870.00
Mandor 1.2939 org X Rp. 80000 103,512.00
JUMLAH (I) 970,132.00 206,304.00 1,176,436.00
PLS33 1 Set Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return
Pekerja 0.9000 org X Rp. 55000 49,500.00
Tukang Listrik 0.9000 org X Rp. 80000 72,000.00
Pengawas 2.1044 org X Rp. 100000 210,440.00
Mandor 0.8418 org X Rp. 80000 67,344.00
Retur material existing 0.0500 unit X Rp. -
JUMLAH (J) 399,284.00 - 399,284.00
PLS34 1 Set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur
Pekerja 0.8750 org X Rp. 55000 48,125.00
Tukang Listrik 0.8750 org X Rp. 80000 70,000.00
Pengawas 1.6995 org X Rp. 100000 169,950.00
Mandor 0.6798 org X Rp. 80000 54,384.00
Retur material existing 0.0500 unit X Rp. -
JUMLAH (K) 342,459.00 - 342,459.00
PLS35 1 Set Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur
Pekerja 0.9000 org X Rp. 55000 49,500.00
Tukang Listrik 0.9000 org X Rp. 80000 72,000.00
Pengawas 2.1044 org X Rp. 100000 210,440.00
Mandor 0.8418 org X Rp. 80000 67,344.00
Retur material existing 0.0500 unit X Rp. -
JUMLAH (L) 399,284.00 - 399,284.00
PLS36 1 Set Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur
Pekerja 0.8500 org X Rp. 55000 46,750.00
Tukang Listrik 0.8500 org X Rp. 80000 68,000.00
Pengawas 1.9554 org X Rp. 100000 195,540.00
Mandor 0.7822 org X Rp. 80000 62,576.00
Retur material existing 0.0500 unit X Rp. -
JUMLAH (M) 372,866.00 - 372,866.00
KPUT4 100 m2 Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat
Pasair pasang 5.0000 m3 X Rp. 491,200.00 2,456,000.00
Batu belah 15/20 23.0000 m 3
X Rp. 491,200.00 11,297,600.00
Batu pecah 5/7 cm 3.0000 m3 X Rp. 491,200.00 1,473,600.00
Pasir urug 6.5000 m3 X Rp. 491,200.00 3,192,800.00
Isi batu berkerasan 26.0000 m 3
X Rp. 491,200.00 12,771,200.00
Menyawur pasir 6.5000 Tng X Rp. 491,200.00 3,192,800.00
JUMLAH 15,964,000.00 18,420,000.00 34,384,000.00
Tiap m2
1/100 x 15,964,000.00 + 18,420,000.00 159,640.00 184,200.00
Biaya menggilas
1/200 x 1,964,800.00 + 9,210,000.00 9,824.00 46,050.00
Sewa motor walls
1/200 x - -
JUMLAH 169,464.00 230,250.00 399,714.00
KPUT5 100 m2 Pembuatan lapis pondasi bawah (sub base) tebal 15 cm padat
Pasair urug 5.0000 m3 X Rp. 491,200.00 2,456,000.00
Batu belah 15/20 17.5000 m 3
X Rp. 491,200.00 8,596,000.00
Batu pecah 5/7 cm 3.0000 m3 X Rp. 491,200.00 1,473,600.00
Pasir urug (pengisi) 6.5000 m3 X Rp. 491,200.00 3,192,800.00
Isi batu berkerasan 20.5000 m 3
X Rp. 491,200.00 10,069,600.00
Menyawur pasir 5.0000 Tng X Rp. 491,200.00 2,456,000.00
JUMLAH ( BELUM TERMASUK PPN ) 12,525,600.00 15,718,400.00 28,244,000.00
Tiap m2
1/100 x 12,525,600.00 + 15,718,400.00 125,256.00 157,184.00
Biaya menggilas
1/200 x 1,964,800.00 + 9,210,000.00 9,824.00 46,050.00
Sewa motor walls
1/200 x - -
JUMLAH 135,080.00 203,234.00 338,314.00
Tiap m2
1/100 x 7,982,000.00 + 7,982,000.00 79,820.00 79,820.00
Biaya menggilas
1/150 x 1,964,800.00 + 9,210,000.00 13,098.67 61,400.00
Sewa motor walls
1/150 x - -
JUMLAH 92,918.67 141,220.00 234,138.67
Tiap m2
1/100 x 9,578,400.00 + 239,543,504.00 95,784.00 2,395,435.04
Biaya menggilas
4/12,5/200 x 1,964,800.00 + 9,210,000.00 3,143.68 14,736.00
Sewa motor walls
1/200 x - -
JUMLAH 98,927.68 2,410,171.04 2,509,098.72
Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat)
2/100 x 62,333,280.00 + 4,298,000.00 1,246,665.60 85,960.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00 3,929.60 18,420.00
Sewa motor walls
1/500 x - -
Aspal untuk lem 0,5 kg
0.5000 x - -
JUMLAH 1,250,595.20 104,380.00 1,354,975.20
Tiap m1
Aspal sand sheet 3 cm jereng (2 cm padat)
3/100 x 62,333,280.00 + 4,298,000.00 1,869,998.40 128,940.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00 3,929.60 18,420.00
Sewa motor walls
1/500 x - -
Aspal untuk lem 0,5 kg
0.5000 x - -
JUMLAH 1,873,928.00 147,360.00 2,021,288.00
KPUT11 100 m2 Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jereng
Aspal - kg X Rp. 491,200.00 -
Pasair pasang 1.0000 m3 X Rp. 491,200.00 491,200.00
Kayu bakar 0.9000 m3 X Rp. 491,200.00 442,080.00
Juru godog aspal 0.2500 org X Rp. 491,200.00 122,800.00
Pekerja 8.1000 org X Rp. 491,200.00 3,978,720.00
Mandor 0.4000 org X Rp. 491,200.00 196,480.00
JUMLAH 4,298,000.00 933,280.00 5,231,280.00
Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal
2/100 x 4,298,000.00 + 933,280.00 85,960.00 18,665.60
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00 3,929.60 18,420.00
Sewa motor walls
1/500 x - -
Aspal untuk lem 0,5 kg
0.5000 x - -
JUMLAH 89,889.60 37,085.60 126,975.20
Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal
2/100 x 4,298,000.00 + 933,280.00 85,960.00 18,665.60
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00 3,929.60 18,420.00
Sewa motor walls
1/500 x - -
Aspal untuk lem 0,5 kg
0.5000 x - -
JUMLAH 89,889.60 37,085.60 126,975.20
KPUT14 350 m' Pemotongan aspal dengan mesin potong (cutter), 2 sisi
Cutter 2.0000 bh X Rp. 491,200.00 982,400.00
Sewa mesin cutter 2.0000 hr X Rp. 491,200.00 982,400.00
Solar 15.0000 ltr X Rp. 491,200.00 7,368,000.00
Tk. Cutter / masinis 2.0000 org X Rp. 491,200.00 982,400.00
Pekerja 2.0000 org X Rp. 491,200.00 982,400.00
JUMLAH 1,964,800.00 9,332,800.00 11,297,600.00
Tiap m1
1/350 x 1,964,800.00 + 9,332,800.00 5,613.71 26,665.14 32,278.86
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT MIXING PLANT E01
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 50.00 Ton/jam
4 Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,500.00 Jam
c. Harga Alat B 7,500,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,500.00 Jam Alat Baru
c. Harga Alat B' 7,500,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT FINISHER E02
2 Tenaga Pw 47.00 HP
3 Kapasitas Cp 6.00 Ton
4 Alat Baru : a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 715,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 6.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 715,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT SPRAYER E03
2 Tenaga Pw 15.00 HP
3 Kapasitas Cp 800.00 Liter
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 145,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 145,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan BULLDOZER 100 -150 HP E04
2 Tenaga Pw 140.00 HP
3 Kapasitas Cp Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 700,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 700,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan COMPRESSOR 4000 - 6500 L/M E05
2 Tenaga Pw 80.00 HP
3 Kapasitas Cp Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 175,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 175,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WHEEL LOADER 1,0 - 1,6 M3 E15
2 Tenaga Pw 105.00 HP
3 Kapasitas Cp 1.50 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 840,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 840,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TANDEM ROLLER 6 - 8 T E17
2 Tenaga Pw 50.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c Harga Alat B 460,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 460,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan PNEUMATIC TYRE ROLLER 8 - 10 T E18
2 Tenaga Pw 60.00 HP
3 Kapasitas Cp 10.00 Ton
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 1,800.00 Jam
c Harga Alat B 510,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 1,800.00 Jam Alat Baru
c Harga Alat B' 510,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK E09
2 Tenaga Pw 125.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 145,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 145,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan GENERATOR SET E12
2 Tenaga Pw 175.00 HP
3 Kapasitas Cp 125.00 KVA
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 440,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 440,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan MOTOR GRADER > 100 HP E12
2 Tenaga Pw 125.00 HP
3 Kapasitas Cp - -
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c Harga Alat B 880,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 880,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan VIBRATORY ROLLER 5 - 8 T E19
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp 7.00 Ton
4 Alat Baru Umur Ekonomis A 4.00 Tahun
Jam Kerja dalam 1 Tahun W 2,000.00 Jam
Harga Alat B 500,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 4.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 500,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WATER TANK TRUCK 3000 - 4000 L E23
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 4,000.00 Liter
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 50,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 50,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan JACK HAMMER E26
2 Tenaga Pw 3.00 HP
3 Kapasitas Cp - Liter
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 3,500,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 3,500,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TAMPER E25
2 Tenaga Pw 5.00 HP
3 Kapasitas Cp 0.170 Ton
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 3,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 3,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan STONE CRUSHER E21
2 Tenaga Pw 220.00 HP
3 Kapasitas Cp 50.00 Ton/Jam
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 491,500,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 491,500,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan THREE WHEEL ROLLER 6 - 8 T E16
2 Tenaga Pw 55.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 125,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 125,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE VIBRATOR E20
2 Tenaga Pw 10.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 12,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 12,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE MIXER 0.3 - 0.6 M3 E06
2 Tenaga Pw 15.00 HP
3 Kapasitas Cp 500.00 Liter
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 45,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 45,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CRANE 10 - 15 TON E07
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 15.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 300,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 300,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK 3 - 4 M3 E08
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 6.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 100,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 100,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan EXCAVATOR 80 - 140 HP E10
2 Tenaga Pw 80.00 HP
3 Kapasitas Cp 0.50 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 250,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 250,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan FLAT BED TRUCK 3 - 4 M3 E11
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 4.00 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 250,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 250,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WATER PUMP 70 - 100 mm E22
2 Tenaga Pw 6.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 2.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 5,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 2.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 5,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan FULVI MIXER E27
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 100,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 100,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TRACK LOADER 75 - 100 HP E14
2 Tenaga Pw 90.00 HP
3 Kapasitas Cp 1.60 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 300,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 300,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 100,000.00 Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 80,000.00 Rp / Jam
4 Bahan bakar bensin Mb 5,400.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak Pelumas Mp 42,000.00 Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0113 6,875.00 77.93
2 Mandor ( L 03 ) Jam 0.0016 80,000.00 129.54
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0121 276,000.00 3,343.65
2 Agregat Halus ( M 04 ) M3 0.0232 288,000.00 6,682.37
3 Filler ( M 05 ) Kg 4.8004 - -
4 Aspal ( M 10 ) Kg 5.2962 9,400.00 49,784.60
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0011 548,210.53 608.85
2 AMP ( E 01 ) Jam 0.0016 6,937,602.41 11,233.90
3 Genset ( E 12 ) Jam 0.0016 588,272.18 952.58
4 Dump Truck ( E 09 ) Jam 0.0143 435,400.78 6,242.49
5 Aspal Finisher ( E 02 ) Jam 0.0020 406,519.57 822.83
6 Tandem Roller ( E 17 ) Jam 0.0017 368,176.60 633.69
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0013 408,950.16 525.56
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 81,537.99
JASA 10 % 8,153.80
JUMLAH ( BELUM TERMASUK PPN ) 89,691.79
DIBULATKAN 89,691.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
I ASUMSI
1 Menggunakan alat berat ( cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan padat t 0.03 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump Truck dan diangkut ke lokasi pekerjaan.
3 Campuran panas HRS dihampar dengan Finisher dan dipadatakan dengan Tandem
dan Peneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch HRS Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 30.00 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 24.00 menit
Ts2 85.00 menit
e Finisher ( E 02 )
Kapasitas produksi V 40.00 km / jam
Faktor efisiensi alat Fa 0.83 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50 km/jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 617.56 m2 / jam
Produksi HRS / hari = Tk x Q2 Qt 4,322.92 m2
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp 89,691.00 / M2
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0217 6,875.00 149.10
2 Mandor ( L 03 ) Jam 0.0022 80,000.00 173.49
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0336 276,000.00 9,282.57
2 Agregat Halus ( M 04 ) M3 0.0149 288,000.00 4,276.80
3 Filler ( M 05 ) Kg 4.8015 - -
4 Aspal ( M 10 ) Kg 6.6150 9,400.00 62,181.00
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0015 548,210.53 815.43
2 AMP ( E 01 ) Jam 0.0022 6,937,602.41 15,045.40
3 Genset ( E 12 ) Jam 0.0022 588,272.18 1,275.77
4 Dump Truck ( E 09 ) Jam 0.0348 435,400.78 15,144.04
5 Aspal Finisher ( E 02 ) Jam 0.0027 406,519.57 1,102.01
6 Tandem Roller ( E 17 ) Jam 0.0016 368,176.60 591.45
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0023 408,950.16 938.50
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 111,475.56
JASA 10 % 11,147.56
JUMLAH ( BELUM TERMASUK PPN ) 122,623.11
DIBULATKAN 122,623.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan ( AC ) padat t 0.04 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump Truck dan diangkut ke lapangan
3 Campuran panas AC dihampar dengan Finisher dan dipadatakan dengan Tandem dan
Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 4.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch AC Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 8.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 29.99 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 23.99 menit
Ts2 76.98 menit
e Finisher ( E 02 )
Kapasitas produksi V 40.00 ton / jam
Faktor efisiensi alat Fa 0.83 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 2.50 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 4.00 lintasan
Faktor efisiensi alat Fa 0.83 -
h Alat Bantu
Diperlukan :
- Rambu = 2 bh
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 461.11 m2 / jam
Produksi AC / hari = Tk x Q2 Qt 3,227.78 m2
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
Rp 122,623.00 / M2
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.3880 6,875.00 2,667.17
2 Mandor ( L 03 ) Jam 0.0554 80,000.00 4,433.73
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7028 276,000.00 193,966.67
2 Agregat Halus ( M 04 ) M3 0.5341 288,000.00 153,824.00
3 Filler ( M 05 ) Kg 139.2 - -
4 Aspal ( M 10 ) Kg 157.0 9,400.00 1,475,799.96
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0380 548,210.53 20,838.65
2 AMP ( E 01 ) Jam 0.0554 6,937,602.41 384,493.63
3 Genset ( E 12 ) Jam 0.0554 588,272.18 32,603.04
4 Dump Truck ( E 09 ) Jam 0.4906 435,400.78 213,622.82
5 Aspal Finisher ( E 02 ) Jam 0.0767 406,519.57 31,166.50
6 Tandem Roller ( E 17 ) Jam 0.0430 368,176.60 15,842.37
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0321 408,950.16 13,138.96
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 2,542,897.49
JASA 10 % 254,289.75
JUMLAH ( BELUM TERMASUK PPN ) 2,797,187.24
DIBULATKAN 2,797,187.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : M3 ASP 6
I ASUMSI
1 Menggunakan alat berat ( Cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan ( ATB ) padat t 0.04 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump truck dan diangkut ke lokasi pekerjaan
3 Campuran panas ATB dihampar dengan Finisher dan dipadatakan dengan Tandem
dan Pneumatic Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch ATB Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 29.99 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 23.99 menit
Ts2 84.99 menit
e Finisher
Kapasitas produksi V 40.00 ton/jam
Faktor efisiensi alat Fa 0.75 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 18.04 m3 / jam
Produksi ATB / hari = Tk x Q2 Qt 126.30 m3
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp 2,797,187.00 / M3
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301 6,875.00 207.08
2 Mandor ( L 03 ) Jam 0.0060 80,000.00 481.93
B BAHAN
1 Aspal ( M 10 ) ( M 10 ) Kg 0.6417 9,400.00 6,032.15
2 Karosene ( M 11 ) ( M 11 ) Liter 0.4889 - -
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030 237,950.78 716.72
2 Compresor ( E 05 ) Jam 0.0031 361,044.90 1,128.27
3 Dump Truck ( E 08 ) Jam 0.0030 435,400.78 1,311.45
JUMLAH 9,877.59
JASA 10 % 987.76
JUMLAH ( BELUM TERMASUK PPN ) 10,865.35
DIBULATKAN 10,865.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : L ASP 8
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km
4 Jam kerja efektif 1 hari Tk 7.00 Jam
5 Faktor kehilangan material Fh 1.10 -
6 Komposisi campuran AC ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 56 % 100 Bagian
- Minyak Flux / pencair K 44 % 80 Bagian
8 Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan
II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck
2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00 liter
Faktor efisiensi alat Fa 0.83 -
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 jam
b Air Compresor ( E 05 )
Kapasitas alat -----------> Diambil V 400.00 m2 / jam
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.80 liter / m2
c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 2,324.00 Liter
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
Rp 10,865.00 / LITER
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373 6,875.00 3,006.47
2 Mandor ( L 03 ) Jam 0.0625 80,000.00 4,997.77
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7680 276,000.00 211,968.00
2 Agregat Halus ( M 04 ) M3 0.4320 288,000.00 124,416.00
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625 548,210.53 34,247.87
2 Dump Truck ( E 09 ) Jam 0.1994 435,400.78 86,810.29
3 Motor Grader ( E 13 ) Jam 0.0117 433,290.05 5,075.35
4 Vibratory Roller ( E 19 ) Jam 0.0178 433,290.05 7,733.87
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 408,950.16 1,751.86
6 Water Tank Truck ( E 23 ) Jam 0.0211 370,198.54 7,805.39
7 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 488,312.87
JASA 10 % 48,831.29
JUMLAH ( BELUM TERMASUK PPN ) 537,144.16
DIBULATKAN 537,144.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : M3 ASP 10
I ASUMSI
1 Menggunakan alat berat Cara mekanik
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal Agregat padat t 0.15 m
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00 Jam
8 Proporsi campuran
- Agregat Kasar Ak 64.00 % Tabel; 5.1.2 (a)
- Agregat halus Ah 36.00 %
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base
camp
2
Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dg motor Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan
Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Mencampur T1 2.50 menit
- Memuat dan Lain lain T2 1.00 menit
Ts 1 3.50 menit
b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 45.00 km / jam
Kecepatan rata rata kosong v2 60.00 km / jam
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit
- lain lain termasuk menurunkan Agregat T3 3.00 menit
c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 4.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 3
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 0.75 menit
- Lain lain T2 1.00 menit
Ts 3 1.75 menit
d Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 3.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam
Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp 537,144.00 / M2
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373 6,875.00 3,006.47
2 Mandor ( L 03 ) Jam 0.0625 80,000.00 4,997.77
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7080 276,000.00 195,408.00
2 Agregat Halus ( M 04 ) M3 0.4920 288,000.00 141,696.00
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625 548,210.53 34,247.87
2 Dump Truck ( E 09 ) Jam 0.1994 435,400.78 86,810.29
3 Motor Grader ( E 13 ) Jam 0.0117 433,290.05 5,075.35
4 Vibratory Roller ( E 19 ) Jam 0.0178 433,290.05 7,733.87
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 408,950.16 1,751.86
6 Water Tank Truck ( E 23 ) Jam 0.0211 370,198.54 7,805.39
7 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 489,032.87
JASA 10 % 48,903.29
JUMLAH ( BELUM TERMASUK PPN ) 537,936.16
DIBULATKAN 537,936.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : M3 ASP 12
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal Agregat padat t 0.15 m
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00 Jam
8 Proporsi campuran
- Agregat Kasar Ak 59.00 % Tabel; 5.1.2 (a)
- Agregat halus Ah 41.00 %
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base
camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dengan motor
Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan
Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Mencampur T1 2.50 menit
- Memuat dan Lain lain T2 1.00 menit
Ts 1 3.50 menit
b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 45.00 km / jam
Kecepatan rata rata kosong v2 60.00 km / jam
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit
- lain lain termasuk menurunkan Agregat T3 3.00 menit
c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 4.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 3
- Perataan 1 Lintasan = ( Lh x 60 ) : ( v x 1000 ) T1 0.75 menit
- Lain lain T2 1.00 menit
Ts 3 1.75 menit
d Vibratory Roller ( E 17 )
Kecepatan rata rata alat v 3.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam
Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3 / jam
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp 537,936.00 / M2
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301 6,875.00 207.08
2 Mandor ( L 03 ) Jam 0.0060 80,000.00 481.93
B BAHAN
1 Aspal ( M 10 ) Kg 0.8880 9,400.00 8,346.86
2 Kerosene ( M 11 ) Liter 0.2530 - -
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030 237,950.78 716.72
2 Compresor ( E 05 ) Jam 0.0063 361,044.90 2,256.53
3 Dump Truck ( E 08 ) Jam 0.0030 435,400.78 1,311.45
JUMLAH 13,320.57
JASA 10 % 1,332.06
JUMLAH ( BELUM TERMASUK PPN ) 14,652.62
DIBULATKAN 14,652.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : M3 ASP 14
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km
4 Jam kerja efektif 1 hari Tk 7.00 Jam
5 Faktor kehilangan material Fh 1.10 -
6 Komposisi campuran ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 77 % 100 Bagian
- Minyak Flux / pencair K 23 % 30 Bagian
8
Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan
II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal
cair
2
Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan
dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck
2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00 Liter
Faktor efisiensi alat Fa 0.83 -
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 Jam
b Air Compresor ( E 05 )
Kapasitas alat . . . . . Diambil V 400.00 m2 / jam
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.40 Liter / m2
c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter
Produksi Lapis Perekat / hari = Tk x Q4 Qt 2,324.00 Liter
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
Rp 14,652.00 / Liter
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0161 6,875.00 110.44
2 Mandor ( L 02 ) Jam 0.0040 80,000.00 321.29
B BAHAN
C PERALATAN
1 Motor Grader ( E 13 ) Jam 0.0025 592,669.36 1,487.62
2 Vibratory Roller ( E 19 ) Jam 0.0040 433,290.05 1,740.12
3 Water Tank Truck ( E 23 ) Jam 0.0105 370,198.54 3,902.70
4 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH 8,062.17
JASA 10 % 806.22
JUMLAH ( BELUM TERMASUK PPN ) 8,868.38
DIBULATKAN 8,868.00
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak ) dan biaya biaya
lainnya
SATUAN : M2 ASP 16
I ASUMSI
1 Pekerjaan dilakukan pada hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi jalan : jelek / belum padat
5 Jam kerja efektif per hari Tk 7.00 Jam
II URUTAN KERJA
1 Motor Grader meratakan permukaan hasil galian
2 Vibro Roller memadatkan permukaan jalan yang telah diratakan oleh Motor grader
3 Sekelompok pekerja akan membanru meratakan badan jalan dengan alat bantu
permukaan dengan menggunakan alat bantu
2 ALAT
a Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 2.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 1
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 1.50 menit
- Lain lain T2 1.00 menit
Ts 1 2.50 menit
b Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 2.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : VIBRATORY ROLLER Q2 249.00 m3 / jam
Produksi Pekerjaan / hari = Tk x Q2 Qt 1,743.00 m3
Kebutuhan tenaga
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Rp 8,868.00 / M2