PEMBESIAN
2. STEK KOLOM
D 16 417 0 ‐417 1.761,05 ada stok
SUB TOTAL 1.761,05
2. PEKERJAAN TIE BEAM BAWAH
Ø 8 779 742 ‐37 3.692,46 tidak ada stok
D 16 425 405 ‐20 8.047,80 ada stok
SUB TOTAL 11.740,26
3. PEKERJAAN TIE BEAM ATAS
Ø 8 742 0 ‐742 3.517,08 tidak ada stok
D 16 405 0 ‐405 7.669,08 ada stok
SUB TOTAL 11.186,16
4. PEDESTAL
Ø 10 65 0 ‐65 477,36 ada stok
D 16 70 0 ‐70 1.325,52 ada stok
SUB TOTAL 1.802,88
5. RETAINING WALL
Ø 10 262 0 ‐262 1.924,13 ada stok
D 13 350 0 ‐350 4.376,40 ada stok
SUB TOTAL 6.300,53
TOTAL 37.920,88
6
RESUME TABEL KEBUTUHAN PEMBESIAN
NO. MATERIAL QTY QTY Selisih STOK GG KURANG KET
Datang
1 Ø 8 1.521 742 (779) 1.521 BELI
2 Ø 10 442 115 (327) 8.982 ADA STOK
3 D 13 650 273 (377) 30.626 ADA STOK
4 D 16 1.410 498 (912) 19.081 ADA STOK
5 D 19 20 14 (6) 20 BELI