LOKASI : TULUNGAGUNG
6
9
4
3
54
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN PEMBANGUNAN JEMBATAN KENDARAAN DAN PEDESTRIAN
:
PENGHUBUNG RSCM KENCANA - RSCM KIRANA
LOKASI : RSUPN Dr. CIPTO MANGUNKUSUMO
TAHUN ANGGARAN : 2022
JUMLAH 15,960,913,068.58
PPN 10% 1,596,091,306.86
TOTAL JUMLAH 17,557,004,375.43
PEMBULATAN 17,557,004,000.00
Terbilang : Tujuh Belas Milyar Lima Ratus Lima Puluh Tujuh Juta Empat Ribu Rupiah
PAIDI
Direktur Cabang
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN JEMBATAN KENDARAAN DAN PEDESTRIAN PENGHUBUNG RSCM KENCANA - RSCM KIRANA
LOKASI : RSUPN Dr. CIPTO MANGUNKUSUMO
TAHUN : 2022
I PEKERJAAN PERSIAPAN
1. Mobilisasi/Demobilisasi peralatan, material dan tenaga kerja 1.00 Ls 120,000,000.00 120,000,000.00
2. Site Management, Safety & Security 1.00 Ls 170,000,000.00 170,000,000.00
3. Site Office 1.00 Ls 30,000,000.00 30,000,000.00
4. Material Test 1.00 Ls 30,000,000.00 30,000,000.00
5. Pembersihan Lapangan Dan Perataan 344.50 m2 75,000.00 25,837,500.00
6. Pembongkaran bangunan eksisting 1.00 Ls 6,000,000.00 6,000,000.00
7. Pek. Pemasangan Bowplank 116.00 m' 135,000.00 15,660,000.00
8. Pembuangan Bongkaran Material 92.41 m3 125,000.00 11,551,250.00
9. Swab Antigen 30.00 Person 85,000.00 2,550,000.00
10. Total Station 1.00 Ls 35,000,000.00 35,000,000.00
JUMLAH I. PEKERJAAN PERSIAPAN 446,598,750.00
II PEKERJAAN TANAH
1. Pek. Galian Tanah untuk pondasi & pilecap 740.85 m3 71,500.00 52,970,775.00
2. Pek. Urugan (granular material) termasuk pemadatan 558.94 m3 238,000.00 133,027,125.00
pilecap & ramp
JUMLAH II. PEKERJAAN TANAH 185,997,900.00
2. Rangka Atap
a. Pipa Baja Ø 355.6 (Tebal 12mm) (ASTM A992) 57,944.78 kg 25,600.00 1,483,386,240.00
Kebutuhan = 95 Lonjor (Panjang 6 m)
b. Pipa Baja Ø 355.6 (Tebal 12mm) (ASTM A992) 9,149.18 kg 25,600.00 234,218,880.00
Kebutuhan = 15 Lonjor (Panjang 6 m)
c. Plat Tebal 15 mm (ASTM A992) 5,200.00 kg 25,600.00 133,120,000.00
d. Sambungan Pin Plat 30 mm (ASTM A992) 3,000.00 kg 25,600.00 76,800,000.00
e. Pin M100 48.00 pcs 1,800,000.00 86,400,000.00
f. Bolt M30 (Mutu A325 Grup A) termasuk ring 768.00 pcs 84,500.00 64,896,000.00
g. Painting struktur baja 75,293.95 kg 2,000.00 150,587,900.00
- SSPC SP 14
- Prime Coating : Inorganic Zinc 50 μm
- Intermediate Coating : Polyamide Epoxy Primer 75 μm
- Finish Coating : Apliphatic Polyurethane coat 25 μm
SUB JUMLAH III.C. PEKERJAAN STRUKTUR BAJA 7,209,500,620.00
D. PEKERJAAN LAINNYA
1. Expansion Joint 18.00 m 5,500,000.00 99,000,000.00
2. Mechanical Pot Bearing (1 Fix, 2 Guided Sliding, 1 Free Sliding) 4.00 buah 55,000,000.00 220,000,000.00
termasuk supply & install serta pekerjaan grouting
3. Pot Bearing Test 1.00 buah 35,000,000.00 35,000,000.00
4. Pagar Pengaman Jembatan Railing Lantai 1 termasuk cat 220.00 m 1,000,000.00 220,000,000.00
5. Pekerjaan Trotoar beton pada jembatan 50.40 m3 3,000,000.00 151,200,000.00
6. Pekerjaan Temporary Stage Pada saat Pemasangan Jembatan 1.00 LS 300,000,000.00 300,000,000.00
termasuk perijinan dsb
7. Perbaikan kerusakan akibat pelaksanaan 1.00 LS 75,000,000.00 75,000,000.00
8. Rambu 1.00 LS 18,000,000.00 18,000,000.00
9. Road Marking 1.00 LS 18,000,000.00 18,000,000.00
SUB JUMLAH III.D. PEKERJAAN LAINNYA 1,136,200,000.00
JUMLAH III. PEKERJAAN STRUKTUR 13,983,043,218.58
IV PEKERJAAN ELEKTRIKAL
Lantai 1
1. Pek. Pemasangan Panel Listrik 1.00 Bh 1,500,000.00 1,500,000.00
2. Pek. Instalasi Titik Lampu 39.00 Bh 850,000.00 33,150,000.00
3. Pek. Instalasi Titik Saklar 6.00 Bh 1,300,000.00 7,800,000.00
4. Pek. Instalasi Lampu LED Strip 3.00 Bh 3,800,000.00 11,400,000.00
5. Pek. Pemasangan Lampu Spotlight 10 Watt 24.00 Bh 440,000.00 10,560,000.00
6. Pek. Pemasangan Lampu LED 70 Watt 12.00 Bh 2,300,000.00 27,600,000.00
7. Pek. Pemasangan Lampu LED Strip (White) 222.00 m1 120,000.00 26,640,000.00
8. Pek. Pemasangan Lampu LED Strip (Magenta) 127.20 m1 120,000.00 15,264,000.00
9. Pek. Pemasangan Lampu LED Strip (Biru) 376.00 m1 120,000.00 45,120,000.00
179,034,000.00
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN VOL SAT
( Rp. ) ( Rp. )
a b c d e f=cxe
V PEKERJAAN PLUMBING
1. Pek. Pemasangan pipa ∅3" (Buangan air hujan) 221.00 m1 185,000.00 40,885,000.00
2. Pek. Floor Drain (Stainless Steel) 42.00 Bh 110,000.00 4,620,000.00
3. Pek. Pemasangan Klem pipa ∅3" 224.00 Bh 8,300.00 1,859,200.00
4. Lain-lain… 1.00 Ls 3,000,000.00 3,000,000.00
JUMLAH V. PEKERJAAN PLUMBING 50,364,200.00
April 2022 Mei 2022 Juni 2022 Juli 2022 Agustus 2022 September 2022 Oktober 2022 Nov-22
Bobot M1 M2 M3 M4 M5 M6 M7 M8 M9 M 10 M 11 M 12 M 13 M 14 M 15 M 16 M 17 M 18 M 19 M 20 M 21 M 22 M 23 M 24 M 25 M 26 M 27 M 28 M 29 M 30
No Uraian Sat. Volume Keterangan
(%) 13-Apr 20-Apr 27-Apr 4-May 11-May 18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov
19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May 7-Jun 14-Jun 21-Jun 28-Jun 5-Jul 12-Jul 19-Jul 26-Jul 2-Aug 9-Aug 16-Aug 23-Aug 30-Aug 6-Sep 13-Sep 20-Sep 27-Sep 4-Oct 11-Oct 18-Oct 25-Oct 1-Nov 8-Nov
I PEKERJAAN PERSIAPAN
1. Mobilisasi/Demobilisasi peralatan, material dan tenaga kerja Ls 1.00 0.75% 0.188% 0.188% 0.188% 0.188% 100.00%
2. Site Management, Safety & Security Ls 1.00 1.07% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036% 0.036%
3. Site Office Ls 1.00 0.19% 0.094% 0.094%
4. Material Test Ls 1.00 0.19% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
5. Pembersihan Lapangan Dan Perataan m2 344.50 0.16% 0.040% 0.040% 0.040% 0.040%
6. Pembongkaran bangunan eksisting Ls 1.00 0.04% 0.009% 0.009% 0.009% 0.009%
7. Pek. Pemasangan Bowplank m' 116.00 0.10% 0.049% 0.049%
8. Pembuangan Bongkaran Material m3 92.41 0.07% 0.036% 0.036%
9. Swab Antigen Person 30.00 0.02% 0.008% 0.008%
10. Total Station Ls 1.00 0.22% 0.110% 0.110%
II PEKERJAAN TANAH
1. Pek. Galian Tanah untuk pondasi & pilecap m3 740.85 0.33% 0.111% 0.111% 0.111%
2. Pek. Urugan (granular material) termasuk pemadatan m3 558.94 0.83% 0.417% 0.417%
c. Membuat Beton Mutu f'c = 25 Mpa (K300) m3 255.42 1.92% 0.640% 0.640% 0.640%
4. Pekerjaan Plat
Lantai 1
a. Pembesian kg 19,612.50 1.66% 0.829% 0.829%
b. Plat Bondex 1.2mm m2 523.00 0.93% 0.464% 0.464%
c. Membuat Beton Mutu f'c = 25 Mpa (K300) T=250mm m3 130.75 0.98% 0.492% 0.492%
5. Pekerjaan Ramp termasuk dinding dan pondasi
a. Pembesian kg 43,456.88 3.68% 1.838% 1.838%
b. Membuat Beton Mutu f'c = 25 Mpa (K300) T=250mm m3 289.71 2.18% 1.089% 1.089%
2. Rangka Atap
a. Pipa Baja Ø 355.6 (Tebal 12mm) (ASTM A992) kg 57,944.78 9.29% 2.323% 2.323% 2.323% 2.323%
Kebutuhan = 95 Lonjor (Panjang 6 m)
b. Pipa Baja Ø 355.6 (Tebal 12mm) (ASTM A992) kg 9,149.18 1.47% 0.367% 0.367% 0.367% 0.367%
Kebutuhan = 15 Lonjor (Panjang 6 m)
c. Plat Tebal 15 mm (ASTM A992) kg 5,200.00 0.83% 0.209% 0.209% 0.209% 0.209%
d. Sambungan Pin Plat 30 mm (ASTM A992) kg 3,000.00 0.48% 0.120% 0.120% 0.120% 0.120%
e. Pin M100 pcs 48.00 0.54% 0.135% 0.135% 0.135% 0.135%
f. Bolt M30 (Mutu A325 Grup A) termasuk ring pcs 768.00 0.41% 0.102% 0.102% 0.102% 0.102%
g. Painting struktur baja kg 75,293.95 0.94% 0.236% 0.236% 0.236% 0.236%
- SSPC SP 14
- Prime Coating : Inorganic Zinc 50 μm
- Intermediate Coating : Polyamide Epoxy Primer 75 μm
- Finish Coating : Apliphatic Polyurethane coat 25 μm
D. PEKERJAAN LAINNYA
1. Expansion Joint m 18.00 0.62% 0.310% 0.310%
2. Mechanical Pot Bearing (1 Fix, 2 Guided Sliding, 1 Free Sliding) buah 4.00 1.38% 0.689% 0.689%
termasuk supply & install serta pekerjaan grouting
3. Pot Bearing Test buah 1.00 0.22% 0.219%
4. Pagar Pengaman Jembatan Railing Lantai 1 termasuk cat m 220.00 1.38% 0.689% 0.689%
5. Pekerjaan Trotoar beton pada jembatan m3 50.40 0.95% 0.474% 0.474%
6. Pekerjaan Temporary Stage Pada saat Pemasangan Jembatan LS 1.00 1.88% 0.940% 0.940%
termasuk perijinan dsb
7. Perbaikan kerusakan akibat pelaksanaan LS 1.00 0.47% 0.157% 0.157% 0.157%
8. Rambu LS 1.00 0.11% 0.056% 0.056%
9. Road Marking LS 1.00 0.11% 0.056% 0.056%
IV PEKERJAAN ELEKTRIKAL
Lantai 1
1. Pek. Pemasangan Panel Listrik Bh 1.00 0.01% 0.002% 0.002% 0.002% 0.002%
2. Pek. Instalasi Titik Lampu Bh 39.00 0.21% 0.052% 0.052% 0.052% 0.052%
3. Pek. Instalasi Titik Saklar Bh 6.00 0.05% 0.012% 0.012% 0.012% 0.012%
4. Pek. Instalasi Lampu LED Strip Bh 3.00 0.07% 0.018% 0.018% 0.018% 0.018%
5. Pek. Pemasangan Lampu Spotlight 10 Watt Bh 24.00 0.07% 0.017% 0.017% 0.017% 0.017%
6. Pek. Pemasangan Lampu LED 70 Watt Bh 12.00 0.17% 0.043% 0.043% 0.043% 0.043%
7. Pek. Pemasangan Lampu LED Strip (White) m1 222.00 0.17% 0.042% 0.042% 0.042% 0.042%
8. Pek. Pemasangan Lampu LED Strip (Magenta) m1 127.20 0.10% 0.024% 0.024% 0.024% 0.024%
9. Pek. Pemasangan Lampu LED Strip (Biru) m1 376.00 0.28% 0.071% 0.071% 0.071% 0.071%
V PEKERJAAN PLUMBING
1. Pek. Pemasangan pipa ∅3" (Buangan air hujan) m1 221.00 0.26% 0.128% 0.128%
2. Pek. Floor Drain (Stainless Steel) Bh 42.00 0.03% 0.014% 0.014%
3. Pek. Pemasangan Klem pipa ∅3" Bh 224.00 0.01% 0.006% 0.006%
4. Lain-lain… Ls 1.00 0.02% 0.009% 0.009%
Total 100.00%
Rencana Progress 0.366% 0.366% 0.036% 0.036% 0.440% 5.041% 4.690% 4.735% 3.174% 3.164% 1.974% 2.681% 4.159% 12.498% 9.200% 7.843% 7.843% 3.535% 3.535% 5.320% 5.320% 1.749% 1.749% 2.832% 3.051% 0.797% 1.644% 1.440% 0.593% 0.192%
Komulatif Rencana Progress 0.366% 0.732% 0.767% 0.803% 1.242% 6.283% 10.973% 15.708% 18.882% 22.045% 24.019% 26.700% 30.859% 43.357% 52.557% 60.400% 68.244% 71.779% 75.314% 80.633% 85.953% 87.702% 89.451% 92.283% 95.334% 96.131% 97.775% 99.215% 99.808% 100.000%
Pelaksanaan
Kumulatif Pelaksanaan
Deviasi
PEKERJAAN : PEMBANGUNAN JEMBATAN KENDARAAN DAN PEDESTRIAN PENGHUBUNG RSCM KENCANA - RSCM KIRANA
LOKASI : RSUPN Dr. CIPTO MANGUNKUSUMO
TAHUN : 2022
Harga Jumlah
% Dari Nilai
No. Jenis Pekerjaan Satuan Volume Satuan Harga Ket.
Penawaran
(Rp.) (Rp.)
Nihil
Jumlah Rp - 0.000