1 Pekerjaan Kolom K1 40 x 15 Cm
Beton K 150 5,04 M3 858.642,92 4.327.560,34
Tulangan Utama Besi 8 Ø 12 mm 646,29 Kg 12.627,00 8.160.694,74
Tulangan Utama Besi Ø 8 - 150 mm 240,40 Kg 12.627,00 3.035.499,44
Bekisting Kolom K1 46,20 M2 179.012,00 8.270.354,40
2 Pekerjaan Kolom K2 30 x 15 Cm
Beton K 150 0,28 M3 858.642,92 243.425,27
Tulangan Utama Besi 6 Ø 12 mm 36,22 Kg 12.627,00 457.357,62
Tulangan Utama Besi Ø 8 - 150 mm 14,19 Kg 12.627,00 179.223,07
Bekisting Kolom K2 2,84 M2 179.012,00 507.499,02
3 Pekerjaan Kolom KP (Kolom Praktis) 15 x 15 Cm
Beton K 150 5,24 M3 858.642,92 4.503.367,47
Tulangan Utama Besi 4 Ø 12 mm 893,44 Kg 12.627,00 11.281.487,89
Tulangan Utama Besi Ø 8 - 150 mm 317,86 Kg 12.627,00 4.013.653,54
Bekisting Kolom Praktis 34,97 M2 179.012,00 6.259.154,58
4 Pekerjaan Balok BL El. +5,95 (15 x 15 ) Cm
Beton K 150 0,45 M3 858.642,92 382.525,42
Tulangan Utama Besi 4 Ø 12 mm 70,31 Kg 12.627,00 887.811,85
Tulangan Utama Besi Ø 8 - 150 mm 26,14 Kg 12.627,00 330.014,91
Bekisting Balok 2,97 M2 189.332,00 562.316,04
5 Pekerjaan Balok BL El. +5,95 (15 x 15 ) Cm
Beton K 150 0,45 M3 858.642,92 382.525,42
Tulangan Utama Besi 4 Ø 12 mm 70,31 Kg 12.627,00 887.811,85
Tulangan Utama Besi Ø 8 - 150 mm 26,14 Kg 12.627,00 330.014,91
Bekisting Balok 2,97 M2 189.332,00 562.316,04
6 Pekerjaan Balok BL El. +6,1 (15 x 15 ) Cm
Beton K 150 1,13 M3 858.642,92 965.973,29
Tulangan Utama Besi 4 Ø 12 mm 177,55 Kg 12.627,00 2.241.949,10
Tulangan Utama Besi Ø 8 - 150 mm 60,86 Kg 12.627,00 768.506,94
Bekisting Balok 7,50 M2 189.332,00 1.419.990,00
7 Pekerjaan Balok B2 El. +6,25 (30 x 15 ) Cm
Beton K 150 0,86 M3 858.642,92 734.139,70
Tulangan Utama Besi 6 Ø 12 mm 101,20 Kg 12.627,00 1.277.910,99
Tulangan Utama Besi Ø 8 - 150 mm 41,58 Kg 12.627,00 525.047,87
Bekisting Balok 5,70 M2 189.332,00 1.079.192,40
8 Pekerjaan Balok B3 El. +6,25 (25 x 15 ) Cm
Beton K 150 1,13 M3 858.642,92 972.413,11
Tulangan Utama Besi 6 Ø 12 mm 160,86 Kg 12.627,00 2.031.205,89
Tulangan Utama Besi Ø 8 - 150 mm 55,03 Kg 12.627,00 694.904,58
Bekisting Balok 7,55 M2 189.332,00 1.429.456,60
9 Pekerjaan Balok B2 El. +6,35 (30 x 15 ) Cm
Beton K 150 4,84 M3 858.642,92 4.153.685,14
Tulangan Utama Besi 6 Ø 12 mm 572,61 Kg 12.627,00 7.230.285,86
Tulangan Utama Besi Ø 8 - 150 mm 216,40 Kg 12.627,00 2.732.520,78
Bekisting Balok 32,25 M2 189.332,00 6.105.957,00
10 Pekerjaan Balok B3 El. +6,45 (25 x 15 ) Cm
Beton K 150 3,47 M3 858.642,92 2.978.417,64
Tulangan Utama Besi 6 Ø 12 mm 492,71 Kg 12.627,00 6.221.408,76
Tulangan Utama Besi Ø 8 - 150 mm 164,23 Kg 12.627,00 2.073.753,10
Bekisting Balok 23,13 M2 189.332,00 4.378.302,50
11 Pekerjaan RB El. +6,45 (20 x 15 ) Cm
Beton K 150 4,41 M3 858.642,92 3.786.615,29
Tulangan Utama Besi 4 Ø 12 mm 783,00 Kg 12.627,00 9.886.995,55
Tulangan Utama Besi Ø 8 - 150 mm 222,72 Kg 12.627,00 2.812.300,96
Bekisting Balok 29,40 M2 189.332,00 5.566.360,80
PEKERJAAN TANGGA DAN PLAT LANTAI
JUMLAH Rp 1.556.926.578,50
DIBULATKAN Rp 1.556.900.000,00
TERBILANG :
SATU MILYAR LIMA RATUS LIMA PULUH ENAM JUTA SEMBILAN RATUS RIBU
RUPIAH
Luwuk, Januari 2021
Di Buat Oleh :
SYAMSUL LATIF
ANALISA HARGA SATUAN PEKERJAAN
A.4.1.1.2 Membuat Beton Mutu f'c = 9,8 MPa (K 125), Slump (12 ± 2) cm, W/C = 0,78
AHSP - A.4.7.1.10.a Pengecatan Tembok Baru (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup), Exterior
AHSP - A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 Daun Pintu dan Jendela Kaca, Kayu Kelas I
AHSP - A.4.5.1.5 Pemasangan 1 M2 Langit-langit Gypsum Ukuran (60 x 120) cm, Tebal 5 mm
Dihitung Oleh
SYAMSUL LATIF
DAFTAR HARGA SATUAN UPAH DAN BAHAN
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
I. UPAH KERJA
1 Mandor Hari
2 Kepala Tukang Hari
3 Tukang Kayu, Batu, Besi, Cat Hari 125.000,00
4 Pekerja Hari 100.000,00
SYAMSUL LATIF
-