Pekerjaan Tambah Ceiling Plafond PPN
Pekerjaan Tambah Ceiling Plafond PPN
JUMLAH 135.370.885
PEMBULATAN 150.260.000
Effendi Juwono
BILL OF QUANTITY
PEKERJAAN RUMAH TINGGAL BAPAK. STANLEY LEEANSYAH
PERMATA BUANA - JAKARTA
CEILING
1 Lantai 1
Pekerjaan Expose dan Ceiling
1 Plafond Gypsum 12mm ex. Jayaboard, M² 12,00 208.000 2.496.000
Rangka Hollow 20x40;40x40 tebal 0,6mm Galv , Finish Kompound
2 List Alumunium M' 15,30 23.000 351.900
3 Expose Dak beton M² 310,19 175.000 54.283.075
Jumlah 1 57.130.975
2 Lantai 2
Pekerjaan Ceiling
1 Plafond Gypsum 12mm ex. Jayaboard, M² 141,01 175.000 24.676.050
Rangka Hollow 20x40;40x40 tebal 0,6mm Galv , Finish Kompound
2 Plafond Gypsum 13mm ex. Jayaboard, M² 25,60 208.000 5.323.968
Rangka Hollow 20x40;40x40 tebal 0,6mm Galv , Finish Kompound
3 Curtain Wall M' 20,86 150.000 3.129.300
4 List Alumunium M' 158,95 23.000 3.655.758
5 Cove + Drop Detail Potongan 1.1 M' 6,51 219.000 1.425.690
6 Cove + Drop Detail Potongan 2.2 M' 4,69 219.000 1.027.548
7 Cove + Drop Detail Potongan 3.3 M' 9,66 219.000 2.115.540
Jumlah 2 41.353.854
3 Lantai 3
Pekerjaan Ceiling
1 Plafond Gypsum 12mm ex. Jayaboard, M² 123,74 175.000 21.655.200
Rangka Hollow 20x40;40x40 tebal 0,6mm Galv , Finish Kompound
2 Plafond Gypsum 13mm ex. Jayaboard, M² 42,38 208.000 8.815.872
Rangka Hollow 20x40;40x40 tebal 0,6mm Galv , Finish Kompound
3 Curtain Wall M' 5,71 150.000 856.800
4 List Alumunium M' 187,27 23.000 4.307.256
5 Cove + Drop Detail Potongan 6.6 M' 5,71 219.000 1.250.928
Jumlah 3 36.886.056
Jumlah Total 135.370.885