Minggu 13
Minggu 13
PEKERJAAN : KONTRUKSI PEMBANGUNAN BALAI NIKAH DAN MANASIK HAJI MINGGU KE : 13 (TIGABELAS)
KUA KECAMATAN BANDAR NEGERI SEMUONG TANGGAMUS PERIODE KERJA : 29 AGUSTUS - 04 SEPTEMBER 2021
LOKASI : KEC. BANDAR NEGERI SEMUONG KAB. TANGGAMUS BOBOT REALISASI (%) : 79.063
NO. KONTRAK : B-0925/Kk.08.06/3/KS.01.7/05/2021
TGL KONTRAK : 31 MEI 2021
NILAI : Rp. 1.043.800.000,00
TAHUN : 2021
KONSULTAN : CV. PANDU CONSULTANT ENGINEERING
KONTRAKTOR : CV. ABDI PRIMA JAYA
REALISASI FISIK
HARGA SATUAN JUMLAH HARGA BOBOT
S/D MINGGU LALU MINGGU INI MINGGU INI
NO URAIAN PEKERJAAN ANALISA SAT VOLUME PROSENTASE
BOBOT BOBOT BOBOT
(Rp) (Rp) (%) VOLUME VOLUME VOLUME
(%) (%) (%)
1 2 3 4 5 6 7 6 7 8 9 10 11 12 13
A PEKERJAAN PERSIAPAN
1 Pembuatan Laporan, Dokumentasi (0%, 50% dan 100%) Ls Ls 1.00 1,000,000.00 1,000,000.00 0.11 0.66 0.07 - - 0.66 0.07 66.33
2 Pembuatan Papan Nama Proyek Ls Ls 1.00 250,000.00 250,000.00 0.03 1.00 0.03 - - 1.00 0.03 100.00
3 Air Dan Listrik Kerja Ls Ls 1.00 300,000.00 300,000.00 0.03 1.00 0.03 - - 1.00 0.03 100.00
4 Pengukuran Dan Pemasangan Bowplank Ls Ls 1.00 700,000.00 700,000.00 0.07 1.00 0.07 - - 1.00 0.07 100.00
5 Pembuatan Direksikeet / Gudang / Barak Kerja sementara uk. 4x6 m Ls Ls 1.00 900,000.00 900,000.00 0.09 1.00 0.09 - - 1.00 0.09 100.00
6 Mobilisasi Alat dan Pembersihan Sisa Material Ls Ls 1.00 700,000.00 700,000.00 0.07 0.50 0.04 - - 0.50 0.04 50.00
7 Job Mix Formula ( JMF ) Ls Ls 1.00 3,500,000.00 3,500,000.00 0.37 - - - - - - -
8 APK dan APD K3 (Kesehatan Keselamatan Kerja ) Ls Ls 1.00 1,500,000.00 1,500,000.00 0.16 1.00 0.16 - - 1.00 0.16 100.00
JUMLAH TOTAL PEKERJAAN PERSIAPAN 8,850,000.00 0.93 0.49 - 0.49
6 Pek. Kolom Praktis 12/12 Adk. 1:2:3 K-175 A.4.1.1.35 M1 137.60 91,593.70 12,603,293.12 1.33 137.60 1.33 - - 137.60 1.33 100.00
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding dalam (Ruangan) 3X Cat A.4.7.1.10 M2 696.03 29,942.00 20,840,659.01 2.20 141.14 0.45 205.94 0.65 347.08 1.10 49.87
2 Pek. Pengecatan Dinding Luar 3X cat A.4.7.1.10a M2 218.62 33,847.00 7,399,573.60 0.78 - - - - - - -
3 Pek. Pengecatan List Plank Grc Ls M2 14.77 40,000.00 590,880.00 0.06 14.77 0.06 - - 14.77 0.06 100.00
4 Pek. Pengecatan Finishing Kolom A.4.7.1.10a M2 30.91 33,847.00 1,046,278.46 0.11 - - - - - - -
SUB TOTAL IX 29,877,391.07 3.15 0.51 0.65 1.16
C PEKERJAAN PAGAR
I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Pondasi Batu Belah 0-1 m A.2.3.1.1 M3 19.25 69,025.00 1,328,731.25 0.14 19.25 0.14 - - 19.25 0.14 100.00
2 Pek. Urugan Tanah A.2.3.1.10 M3 20.66 244,277.00 5,046,274.27 0.53 20.66 0.53 - - 20.66 0.53 100.00
3 Pek. Urugan Pasir Dibawah Pondasi A.2.3.1.11 M3 2.69 257,290.00 692,110.10 0.07 2.69 0.07 - - 2.69 0.07 100.00
4 Pek. Pondasi Batu Belah 1:4 A.2.3.1.2 M3 46.48 901,637.00 41,903,579.58 4.42 46.48 4.42 - - 46.48 4.42 100.00
SUB TOTAL I 48,970,695.19 5.16 5.16 - 5.16
II PEKERJAAN BETON
1 Pek. Sloof 15/20
Beton A.4.1.1.5 M3 2.56 1,263,842.64 3,237,964.84 0.34 2.56 0.34 - - 2.56 0.34 100.00
Pembesian Polos A.4.1.1.17 Kg 495.27 17,307.40 8,571,758.46 0.90 495.27 0.90 - - 495.27 0.90 100.00
Bekisting A.4.1.1.21 M2 13.98 165,432.30 2,312,619.48 0.24 13.98 0.24 - - 13.98 0.24 100.00
2 Pek. Kolom 20/30
Beton A.4.1.1.5 M3 3.35 1,263,842.64 4,231,345.16 0.45 3.35 0.45 - - 3.35 0.45 100.00
Pembesian Polos A.4.1.1.17 Kg 431.07 17,307.40 7,460,756.86 0.79 431.07 0.79 - - 431.07 0.79 100.00
Bekisting A.4.1.1.22 M2 14.47 261,527.75 3,783,434.78 0.40 14.47 0.40 - - 14.47 0.40 100.00
SUB TOTAL II 29,597,879.58 3.12 3.12 - 3.12
III PEKERJAAN PASANGAN
1 Pas. Dinding Batu bata 1:4 A.4.4.1.9 M2 108.36 107,517.30 11,650,359.59 1.23 108.36 1.23 - - 108.36 1.23 100.00
2 Pek. Plesteran Dinding 1 : 4 A.4.4.1.19 M2 227.81 35,634.72 8,117,945.56 0.86 227.81 0.86 - - 227.81 0.86 100.00
3 Pek. Acian Dinding A.4.4.27 M2 172.78 34,457.50 5,953,697.90 0.63 90.98 0.33 - - 90.98 0.33 52.65
4 Pas. Dinding Granit Tile 60x60 cm (hitam) A.4.4.3.54.B M2 5.92 302,318.50 1,789,725.52 0.19 - - - - - - -
5 Pek. Profilan pilar pagar Ls Bh 31.00 95,000.00 2,945,000.00 0.31 31.00 0.31 - - 31.00 0.31 100.00
6 Pek. Profilan lis band pagar Ls M1 143.56 15,000.00 2,153,400.00 0.23 107.15 0.17 - - 107.15 0.17 74.64
7 Pas. Besi Hollow Bentuk Pagug diatas Pilar Ls Bh 7.00 125,000.00 875,000.00 0.09 - - - - - - -
8 Pas. Logo dan Tulisan Nama Acrylic Ls Ls 1.00 3,450,000.00 3,450,000.00 0.36 - - - - - - -
9 Pas. Pipa Galvanis dia. 1" (Sulingan) Ls M1 5.60 22,000.00 123,200.00 0.01 5.60 0.01 - - 5.60 0.01 100.00
10 Sigerr Beton Ls Ls 1.00 325,000.00 325,000.00 0.03 1.00 0.03 - - 1.00 0.03 100.00
11 Pek. Pasangan Pintu Gerbang Besi Hollow Ls M2 15.71 825,000.00 12,958,275.00 1.37 - - - - - - -
SUB TOTAL III 50,341,603.57 5.30 2.94 - 2.94
IV PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding A.4.7.1.10a M2 141.17 33,847.00 4,778,053.70 0.50 - - - - - - -
2 Pek. Pengecatan Batu Alam Vernis (Coating) Ls M2 4.30 40,000.00 172,000.00 0.02 - - - - - - -
3 Pek. Pengecatan Besi Pagar Ls Ls 1.00 800,000.00 800,000.00 0.08 - - - - - - -
SUB TOTAL IV 5,750,053.70 0.61
V PEKERJAAN LAIN-LAIN
1 Pasang Paving Block tebal 6 cm A.4.4.3.65 M2 172.35 194,383.20 33,501,944.52 3.53 - - - - - - -
2 Cor beton Plat lantai gorong-gorong, uk. 3,5 x 1,5 x 0,15 m Ls LS 1.00 2,400,000.00 2,400,000.00 0.25 - - - - - - -