Daerah Jakarta
1 STASIUN LENTENG AGUNG 384.00 - -
Daerah Bekasi
3 STASIUN BEKASI 672.00 - -
TERBILA
`
PEKERJAAN KANOPI MOTOR
STASIUN PORIS
RENCANA ANGGARAN BIAYA
6 1 Kg Besi Profil
Bahan An. SNI ( Revisi ) 6.1.1
1.10000 kg Besi profil @ Rp. 26,900.00 = Rp. 29,590.00
0.08000 ltr Meni besi @ Rp. 16,000.00 = Rp 1,280.00
Sub total : = Rp. 30,870.00
Upah An. SNI ( Revisi ) 6.1.2
0.00600 oh Pekerja @ Rp. 167,000.00 = Rp. 1,002.00
0.06000 oh Tukang @ Rp. 177,000.00 = Rp. 10,620.00
0.00600 oh Kepala Tukang @ Rp. 194,000.00 = Rp. 1,164.00
0.00030 oh Mandor @ Rp. 216,000.00 = Rp. 64.80
Sub total : = Rp. 12,850.80
7 1 bh Pasang Angkur dia. 16 mm
Bahan 1.00000 bh Angkur dia. 16 mm @ Rp. 101,650.00 = Rp 101,650.00
Sub total : = Rp 101,650.00
Upah
0.00600 Oh Pekerja @ Rp. 167,000.00 = Rp 1,002.00
0.06000 Oh Tukang @ Rp. 177,000.00 = Rp 10,620.00
0.00600 Oh Kepala tukang @ Rp. 194,000.00 = Rp 1,164.00
0.00030 Oh Mandor @ Rp. 216,000.00 = Rp 64.80
Sub total : = Rp 12,850.80
5 1m3 Urugan kembali
Upah An. SNI ( Revisi ) 6.9.2
0.25000 Oh Pekerja @ Rp. 167,000.00 = Rp 41,750.00
0.00800 Oh Mandor @ Rp. 216,000.00 = Rp 1,728.00
Sub total : = Rp 43,478.00
6 1 kg Pek. Pembesian
Bahan An. SNI ( Revisi ) 6.25.1
1.10000 Kg Besi beton @ Rp. 13,000.00 = Rp 14,300.00
0.00250 Kg Kawat bendrat @ Rp. 28,000.00 = Rp 70.00
Sub total : = Rp 14,370.00
Upah An. SNI ( Revisi ) 6.25.2
0.00700 Oh Pekerja @ Rp. 167,000.00 = Rp 1,169.00
0.00700 Oh Tukang @ Rp. 177,000.00 = Rp 1,239.00
0.00070 Oh Kepala Tukang @ Rp. 194,000.00 = Rp 135.80
0.00030 Oh Mandor @ Rp. 216,000.00 = Rp 64.80
Sub total : = Rp 2,608.60
7 1 m3 Membuat beton Bertulang, 1pc : 2ps : 3kr
Bahan An. SNI ( Revisi ) 6.35.1
232.00000 Kg Semen portland @ Rp. 1,440.00 = Rp 334,080.00
0.52000 m3 Pasir beton @ Rp. 288,800.00 = Rp 150,176.00
0.78000 m3 Koral beton @ Rp. 264,000.00 = Rp 205,920.00
Sub total : = Rp 690,176.00
Upah An. SNI ( Revisi ) 6.35.2
1.65000 Oh Pekerja @ Rp. 167,000.00 = Rp 275,550.00
0.25000 Oh Tukang @ Rp. 177,000.00 = Rp 44,250.00
ANALISA HARGA SATUAN
PENAMBAHAN KANOPI HALL, PENAMBAHAN LOKET DAN PEMASANGAN PARTISI TAMPIAS DI STASIUN RANGKASBITUNG
Bahan
1.10000 m Besi Hollow 100x100 @ Rp. 165,833.33 = @ Rp. 182,416.67
Sub Total = @ Rp. 182,416.67
An. SNI (Revisi) 6.12.1
Upah 0.10400 Oh Pekerja @ Rp. 167,000.00 = @ Rp. 17,368.00
0.10400 Oh Tukang besi @ Rp. 177,000.00 = @ Rp. 18,408.00
0.00100 Oh Kepala Tukang besi @ Rp. 194,000.00 = @ Rp. 194.00
0.00005 Oh Mandor @ Rp. 216,000.00 = @ Rp. 10.80
Sub Total = @ Rp. 35,980.80
Upah PUPR28-2016
0.02500 Oh Pekerja @ Rp. 167,000.00 = Rp 4,175.00
0.02500 Oh Tukang @ Rp. 177,000.00 = Rp 4,425.00
0.00200 Oh Kepala Tukang @ Rp. 194,000.00 = Rp 388.00
0.00100 Oh Mandor @ Rp. 216,000.00 = Rp 216.00
Sub total : = Rp 9,204.00
52 1 titik Pengelasan las listrik untuk tiap 10 Cm
Bahan (KAI 2012 no. 137 hal. 63 )
0.40000 kg Kawat las LB 52 2,6mm Kobe @ Rp. 35,000.00 = Rp 14,000.00
Sub total : = Rp 14,000.00
Upah
0.04000 oh Pekerja @ Rp. 167,000.00 = Rp 6,680.00
0.02000 oh Tukang @ Rp. 177,000.00 = Rp 3,540.00
0.00200 oh Mandor @ Rp. 216,000.00 = Rp 432.00
Sub total : = Rp 10,652.00